EARTHWORKS

General Preliminaries
Excavation 13.00 cu.m. 100.00
CONCRETING & MASONRY
40 kgs. Bag Cement 200.00 bags 240.00
White Sand 15.00 cu.m. 1,000.00
Gravel 3/4 20.00 cu.m. 1,200.00
CHB 6" 750.00 pcs. 19.00
16 mm x 6 m Deformed Bar 20.00 pcs. 520.00
12 mm x 6 m Deformed Bar 40.00 pcs. 435.00
10 mm x 6 m Deformed Bar 60.00 pcs. 167.00
Tie Wire #16 2.00 rolls 1,800.00
Subtotal
CARPENTRY, WOODWORKS, & CEILING FRAME
2x2x12 R.O. 10 pcs. 200.00
2x4x12 R.O. 5 pcs. 280.00
1/4 thk. Ordinary Plywood 6 pcs. 400.00
Hardware 1.00 lot lumpsum
Subtotal
DOORS AND WINDOWS
Single Wooden Door - 0.8x1.9m 2.00 set 2,500.00
Subtotal
STEELWORKS
2x2x1.5mm thk Angle bar 10.00
1,300.00 2x3x1.2mm C-Purlin 9.00
10mm Square Bar 10.00
48,000.00 Welding rod 3.00
15,000.00 Disc 5.00
24,000.00
14,250.00 TINSMITHRY
10,400.00 GA 26 G.I.Box Gutter 3.00
17,400.00 GA 26 G.I. Center Capping Flashi 3.00
10,020.00 GA 26 Ribtype Roofing 15.00
3,600.00 Hardwares 1.00
142,670.00
Sanitary & Storm Line
2,000.00 3"Ø PVC Pipe - 4.00
1,400.00
2,400.00 PLUMBING WORKS
3,000.00 3" 45deg Elbow 4.00
8,800.00 Solvent Cement 200cc 3.00

5,000.00 Conduits, Pipes & Accessories


5,000.00 3/4" ∅ RSC 1.00
1/2" ∅ Flexible Hose 100m 1.00
Utility Box 2"x4" 2.00
Junction Box 4"x4" 3.00
Electrical Tape 2.00

HOUSE MATERIAL C
CONTINGENCY
SUBTOTAL
LABOR
GRAND TOTAL
pcs. 1,700.00 17,000.00
pcs. 650.00 5,850.00
pcs. 250.00 2,500.00
kg 120.00 360.00
pcs. 125.00 625.00
Subtotal 26,335.00

pcs. 800.00 2,400.00


pcs. 1,500.00 4,500.00
l.m. 500.00 7,500.00
lot lumpsum 1,500.00
Subtotal 15,900.00

pcs. 562.00 2,248.00


2,248.00

pcs. 52.45 209.80


can 114.45 343.35
553.00

pc 350.00 350.00
rolls 612.00 612.00
set 25.00 50.00
set 17.00 51.00
pc 20.00 40.00
1,103.00
OUSE MATERIAL COST 205,000.00
ONTINGENCY 25% 51,250.00
BTOTAL 256,250.00
45% 115,312.50
RAND TOTAL 371,562.50