Reported Weld
DATE DAY TEAM Planned / Exectued Activities Completed DELAYS Accept/Reject
Team 1 AM CW-R601A-R602A MUT Misalignmet Report KTR-FGP-0077 100% 01. No Site Delays today N/A
RA/Kairat PM CW-R366A-R351A-202-01 Original Report conversion to KTR 100% 02. R.Ates / Completed final 24 Inch reports in order to clear for After PWHT Inspection N/A
01-Feb Mon
Team 2 AM Scan After PWHT 047 / 00005-21 FW-07C1 TOFD 100% N/A
SB/Timur PM Scan After PWHT 047 / 00005-21 FW-07C1 PAUT 100% N/A
Team 1 AM Quarantine - Transport / Check In N/A 01. R.Ates taken to Quaranrine due to Close contact in Bus seating positive COVID Case N/A
RA PM Quarantine - Weekly meeting & Quarantine mitegation planning N/A 02. Cap removal still in progress for F22 weld Scheduled. Scanning Commenced after lunch and subsequently N/A
02-Feb Tues only 50% was completed
Team 2 AM Scan Before PWHT 047 / 00005-14 / FW-01 0% Accept
SKB PM Scan Before PWHT 047 / 00005-14 / FW-01 50% N/A
Team 1 AM Quarantine - Report and Analysis of 047 / 00005-21 FW-07C1 100% 01. No Data Issued from 02-02-2021 due to scanning delays on 02-02-2021 Accept
RA PM Quarantine - Meetings and planning for Quaranntine N/A 02. No Site Delays today N/A
03-Feb Wed
Team 2 AM Scan Before PWHT 047 / 00005-14 / FW-01 50% N/A
SKB PM Coupon LTCS 12x53 QWT-742 in Calibration Workshop 100% N/A
Team 1 AM Quarantine - Analysis & Report 00005-14-FW01 100% 01. Data Received for QWT-742 & 00005-14-FW01 in The morning Accept
RA PM Quarantine - Analysis & Report QWT-742 100% 02. No Site Delays today Reject
04-Feb Thu
Team 2 AM Scan Before PWHT Coupon QWT-733 TOFD 100% N/A
SKB PM Scan Before PWHT Coupon QWT-733 PAUT 100% N/A
AM Quarantine - Analysis & Report 00005-14-FW01 100% 01. No Site Delays today N/A
Team 1
RA
PM Quarantine - Begin SSA 18x58mm Validation Report ~50 pages 100% N/A
05-Feb Fri
Team 2
AM Scan After PWHT - 00093-12 CW-M253A-M251A-201-01 TOFD 100% N/A
SKB
PM Scan After PWHT - 00093-12 CW-M253A-M251A-201-01 PAUT 100% N/A
Team 1 AM Analyse and Report of Coupon QWT-733 TOFD 100% 01. No Site Delays today Accept
RA PM Analyse and Report of - 00093-12 CW-M253A-M251A-201-01 100% Accept
06-Feb SAT
Team 2 AM Scan Before PWHT - 00005-21 FW-04 (D1.1) TOFD 100% N/A
SKB PM Scan Before PWHT - 00005-21 FW-04 (D1.1) PAUT 100% N/A
Team 1 AM Analysis & Report - 00005-21 FW-04 (D1.1) 100% 01. Rodney: Analysis took time due to multiple Indications. Most are acceptable however 1 must be
confirmed by Manual UT in order to provide the most accurate result. Pending
RA PM Analysis & Report - 00005-21 FW-04 (D1.1) 100%
In the last 2 weeks the root / Hotpass welders are creating an error. Something has changed from previous.
07-Feb SUN AM KTR Sweep Olet report final conversions 100% N/A
02 Shaun: Complete final drafts of KTR Converted Weld-Olet & Trunion Reports to be finalised with Euvgeni
Team 2
SKB PM KTR Sweep Olet report final conversions 100% N/A
2 Regular Water Deliveries. Coffee Lady is getting Angry at the local guys for taking 2 Monitor running of heater in Calibration workshop.
water
3 3
4
Week 5 Results
Week 5 Completed Welds
Material & Before / After NDT Request Planned Scanning
Day Date Zone Iso No. Weld No. Construction ID. Analysis Result
Size PWHT No. PWHT Completed
1 Monday 01/02/2021 49A F22 16x52 047-2900-LLL-ISO-000-000-00005-21 FW-07C1 D1.2 After UT.113.Post P-021 Yes Accept
2 Tuesday 02/02/2021 49A F22 16x52 047-2900-LLL-ISO-000-000-00005-14 FW-01 C1.5 Before UT.115 No N/A
3 Wednesday 02/02/2021 49A F22 16x52 047-2900-LLL-ISO-000-000-00005-14 FW-01 C1.5 Before UT.115 Yes Accept
4 Wednesday 03/02/2021 Cal Shed LTCS 12x53 Coupon QWT-742 N/A N/A UT069 100% Reject
5 Thursday 04/02/2021 CAL Shed F22 20x51.5 Coupon QWT-733 NA N/A UT068 100% Accept
6 Friday 05/02/2021 Module F22 20x51.5 047-2900-LLL-ISO-000-000-00093-12 CW-M253A-M251A-201-01 P-021 After UT.112.Post 100% Accept
7 Saturday 06/02/2021 49A F22 16x52 047-2900-LLL-ISO-000-000-00005-21 FW-04 D1.1 Before UT.116 100% Pending MUT
Summary of Welds pending Examination
Active Production Scope Waiting For Inspection (NDT Request Issued) Febuary 2021
Module F22 16x52 047-2900-LLL-ISO-000-000-00065-03 CW-M253A-M252A-015-01 P-003 Before UT.117