DATE DAY TEAM Planned / Executed Activities Completed NOTES Accept/Reject
No Delays
AM Scan Before PWHT of F22 CW-M253A-M255A-001-01-C1 yes
Team 1
01-Mar Mon
PM Calibration and working on set ups - Rodney yes
No Delays
AM Scan After PWHT of LTCS 12x53 CW-R363A-R364A-201-01R1 yes
Team 1
02-Mar Tues
PM Analysis and report of Before PWHT of F22 20x51.5 CW-M253A-M255A-001-01-C1 yes Accept
No Delays
AM Analysis & Report of LTCS 12x53 CW-R363A-R364A-201-01R1 yes Accept
Team 1
03-Mar Wed
PM Scan of Single Side Access CW-M253A-M253B-003-02 yes
No Delays
AM Analysis & Report of Single Side Access CW-M253A-M253B-003-02 yes Accept
Team 1
04-Mar Thu
PM Scan After PWHT of F22 CW-M253A-M255A-001-01-C1 yes
1 tream from today Delay in permit. Dealy in issue of permit. Not valid until 10.00 am
AM 3x16mm LTCS Scanning X2 YES
Team 1
05-Mar Fri Kenny
PM Data analysis and report for After PWHT of F22 CW-M253A-M255A-001-01-C1 YES Accept
Delay in permit again today. Not valid until 10;30. Scaffold tag was yellow therefore requiring issue of
AM 3x16mm LTCS Scanning X2 YES
Team 1 harness' and rescue plan. 2.5 hrs lost productivity.
06-Mar SAT Kenny
PM 3x16mm LTCS Scanning X7 YES
2 Regular Water Deliveries. Coffee Lady is getting Angry at the local guys for taking 2 Monitor running of heater in Calibration workshop.
water
3 3 We are experiencing delays in the issue of NDT requests. We are unable to proceed with reporting and sign off
until these have been receved. Requests should be issued based on the planned week schedule.
4 4 Better planning and execution of site weld preparation is needed. As can be seen from this week, failure to
prepare and heat the welds can have a significant impact on productivity.