You are on page 1of 19

Assistance required in Pkg-1 on RPJ-BTI Doubling

Description Remarks by PMC/RVNL


SN Location Infringement / Assistance Required Status of action taken
of Assistance/Constraints with Probable TDC

A Assistance / Constraints

1 Location plan for staff quarters (Type-II) at RPJ Station RPJ

B NS Items

Assistance required in pkg-1 on RPJ-BTI Doubling(DOC-KKRL)


Description Remarks by PMC/RVNL
SN Location Infringement / Assistance Required Status of action taken
of Assistance/Constraints with Probable TDC
A Civil & P-way

Br 93 - canal syphon
1 GADs - modification Letter submitted for revision of GAD. Follow up for early resolve
bridge

2 Minor Bridge design pending Br 43, 77 Request RVNL to provide PSC Slab Foundation drawing. Follow up for early resolve

PTA, DBN, NBA


3 Infringement/Hindrances due to trees Trees infringing yard works (p/f, loop line etc.)
Yard

Duty hut and S&T Room proposed; land issue needs to be


4 LC-20, LC-31 (Land Issue) LC 20, LC 31
resolved

Location plan for staff quarters (Type-II/Double Storey) at PTA


5 PTA
Station
BR NO. 43, 48,54,57, 60,
63, 75, 77, 80, 82, 88,
6 Approval and permissions for Minor bridges Approval and permissions for Minor bridges
97, 105, 106, 107 RHS,
108 RHS, 110, 113A, 119

7 Approval and permissions for dismantling PF shelters DBN &NBA. Approval and permissions for dismantling PF shelters

Arrangement of Rails to facilitate Track linking works for formation completed


8 Service Rails/Rail Panels
locations.

B Signaling & Telecommunication

1 SIP - 3 Nos PTA, DBN, NBA SIPs already submitted by Agency Request RVNL for early approval

Observations by RVNL being corrected. Agency to Re-submit


2 Track Circuit Plan PTA, DBN, NBA Request RVNL for early approval
within a week of receiving approved SIP.

Observations by RVNL being corrected. Agency to Re-submit


3 Cable Corage Plan PTA, DBN, NBA Request RVNL for early approval
within a week of receiving approved SIP.
Annexure-2
Manpower Deployement Details

Min. No. of Qualification & Experience in Similar


S. No. Position Employee Name
Personnel works (years)

A Key Personnel

Graduate/ Diploma in Civil


Engineering 10 years, out of which 3 Suraj Pal Singh
years in-charge of road/Railway
1 Project Manager Two
project (for Graduate) 16 years, out
of which 3 years in-charge of
road/Railway project (for Diploma) Varinder Bains

Sr. Engineers
Graduate/ Diploma in Civil
Engineering
i) For Earth work ONE Mohit Sharma
5 years (for Graduate) (10 years for
Diploma)
Graduate/ Diploma in Civil
Engineering
ONE 5 years (for Graduate) 10 years (for Siddharth
ii) For Bridges
Diploma)

Graduate/ Diploma in Civil


Engineering
iii) P Way ONE Neeraj Kumar
2 5 years (for Graduate) (10 years for
Diploma)
Degree/Diploma in Electronic/Telecom
Engineering
iv) S & T ONE Experience in Signaling - Brij Bihari
3 years (for Graduate) 7 years (for
Diploma)
Degree/Diploma in
Electrical/Mechanical/Electronics Eng.
Or a combination of basic stream of
v) OHE (for project with Electrical/Mechanical/
RE)/General Electrical works ONE Electronics Eng. Lovey Saxena
(GS) (for projects without RE)
Experience in OHE - 3
years (for Graduate) 7 years (for
Diploma)
Technicians/Supervisors
Suraj Kumar
a) Earthwork THREE Minimum Diploma in Civil Engineering Pravesh
Javed Akhtar

Minimum Diploma in Civil


b) Bridges ONE Engineering Harvinder Singh
3 5 years

Minimum Diploma in Civil Engineering Babalu Yadav


c) P Way TWO
5 years Jitender Kumar

Minimum Diploma in Civil Engineering


d) Buildings & Platform ONE Chander Mehta
5 years

Minimum Diploma in Ajay Kumar


Electrical/Electronics/Communication
Engineering OR a combination of basic
4 Technicians / Supervisor S&T THREE Dilip Tomar
stream of
Electrical/Electronics/Communication
Eng. 5 years Surendra Kumar

Minimum Diploma in
Electrical/Mechanical/Electronics Eng. Krishna Kumar Gupta
5 Technicians/ Supervisor OHE TWO Or a combination of basic stream of
Electrical/Mechanical/Electronics Rohit Vishwakarma
Engineering 5 years

Page 2 of 19
Annexure-2

Min. No. of Qualification & Experience in Similar


S. No. Position Employee Name
Personnel works (years)

Surveyor for setting out lines Minimum Diploma in Civil Engineering


6 ONE Pathikrit Das
and levels
5 years

Minimum Diploma in Civil


7 Material Testing Engineer ONE Neeraj Dubey
Engineering, 5 Years

Liaison Manager for Liaison Graduate. Preferably retired Govt.


8 with Govt. Dept. and local ONE Official of local area Bhuvanesh Pareek
bodies
5 Years

Preferably Graduate in any discipline


Bust must have completed Diploma in
9 Safety Officer ONE industrial safety management OR Jagdish Prasad
construction management
5 Years

Graduate/Diploma in Civil Engineering

10 Quality Officer ONE 5 Years (for Graduate) / 8 Years (for Tarun Kumar
Diploma) experience as a Quality

Control Engineer

Graduate/Diploma in Engineering 5
Years (for Graduate) / 8 Years (for
11 Material Manager ONE Diploma) experience of material Satish Kumar
handling and accounting of material
for Project of this size

Draftsman with knowledge of Auto Cad

Minimum Diploma in Civil Engineering


(a) Civil ONE Shanawaz Ahmed
3 years

Minimum Diploma in
Electrical/Electronics/Communication
Engineering OR a combination of basic
(b) S&T ONE stream of Arun Kumar
12 Electrical/Electronics/Communication
Engineering
3 years

Minimum Diploma in
Electrical/Mechanical/Electronics
Engg. Or a combination of basic
(c) OHE ONE stream of RAM BILAS GUPTA
Electrical/Mechanical/Electronics
Engineering
3 years

Page 3 of 19
Annexure: 3
P&M Mobilization Status

SL No. Category Model Nos

1 Excavator Tata Hitachi EX130 2


2 Dumper TATA Hyva 3118 15
3 Roller Escorts 3
JCB 3DX / Tata
4 Backhoe Loader 4
Hitachi
Caterpillar K2 &
5 Grader 3
Mahindra Grader
Schwing Stetter
6 Batching Plant 2
CP30
Schwing Stetter
7 Transit Mixer 12
(7M3)
8 Concrete Pump Schwing Stetter 1
9 Tractor Various Make 5
10 Concrete Mixer machine 0.20 M3 Capacity 1
11 Vibrator Various Make 6
12 Total Station Topcon B40A 2
13 Auto Level Topcon 4
14 Cable Locator Stanley 4
Grand Total 64
Status of activities in complete section of RPJ-KKRL of pkg-1 on RPJ-BTI Doubling

Dhablan
Rajpura

Patiala

Patiala

Nabha
Kalan

Cantt
Daun
Kauli
SN Items/Section

i Length (km) 0.20 8.90 1.34 5.78 1.48 4.45 1.93 3.42 0.94 7.12 1.49 11.34 2.03 5.18

Target of Commissioning/
ii Apr-21 2021-22
Completion

A Civil Engineering

1 Earthwork in filling (Cum) 5500/5500 107956/107956 4200/4200 79316/79316 2800/2800 34000/34000 0/0 0/0 0/0 75000/75000 0/0 28500/28500 0/4100 21400/21400

2 Earthwork in cutting (Cum) 1500/1500 15000/15000 6400/6400 5000/5000 3000/3000 7500/7500 7800/7800 8347/10000 4000/4000 20000/20000 2500/3000 21000/21000 1900/5000 19900/19900

3 Blanketing (Cum):(WIP/total) 4000/4000 62000/62000 7000/7000 48037/48037 10500/10500 28700/29500 0/7000 18207/19000 4820/5000 38300/40000 0/3500 63500/63500 0/3000 27500/29000

Completed Completed Completed


H/o of Formation for linking
4 Completed Completed Completed Completed Completed Except LC'S & Nov'21 Except LC'S & Except LC'S & Nov'21 Nov'21 Completed Nov'21 Nov'21
(Km)
Br.'s Br.'s Br.'s

5 Ballast Supply (Cum) 2073/2073 29700/29700 13000/13000 17500/17500 7027/7027 11971/11971 0/5711 7900/9202 1500/2790 17800/19142 3500/4409 30505/30505 4566/6007 13934/13934

6 Ballast Spreading (km) Completed Completed Completed Completed Completed 1.8/4.45 0/1.93 1.9/3.421 0/0.943 0/7.116 0/1.49 0/11.34 0.9/2.03 0.4/5.18

7 Minor Bridges (WIP/total) 2/2 14/14 1/1 3/ 3 0/0 2/2 1/2 2/ 4 1/1 9 / 11 1/3 17 / 22 2/6 5/8

8 Major Bridges (WIP/total) 0/0 1/1 0/0 1/1 0/0 3 0/0 0 0/0 3 0/0 2 0/0 1

9 Stn./S&T Buildings (WIP/total) 0/0 0/0 1/1 0/0 1/1 0/0 1/1 0 1/1 0 1/1 0 1/1 0/1

10 Relay Huts (WIP/total) 1/1 0/0 2/2 0/0 0/0 0/0 1/1 0/1 0/0 0 1/1 0 2/2 0

11 New Gumti/Duty Huts(WIP/total) 1/1 2/2 0/0 0/0 1/1 0/0 0/0 0/1 0/0 2/2 0/0 1/1 2/2 0

12 Extension of existing LHS (No.) 0/0 2/2 0 0 0 0 0 0 0 0 0 0 0 0

13 New LHSs (Nos.) 0/0 2/2 2/2 0 2/2 0 0/1 0 0 0 0/1 0 0 0

14 FOBs: 0/0 0/0 1/1 0/0 1/1 - 0/2 - - - 0/1 - 0/1 -

T. refuges on other side of prop.


15 25/32 24/30 0/25 - 0/15 - 0/50 - 0/65 - 0/30
track (Nos.)
T. refuges on proposed track
16 46/48 25/27 0/33 0/10 0/35 7/40 5/20
side(Nos.)

17 Retaining walls (mtr.) 0/0 0/0 1350/1350 0/0 600/600 0/300 0 0 0 1250/2000 0 0 0 0

Commissioning of new Gumtis in


18 alignment (LC-2,3,8,9,12, 3/3 1/1 2/2 0/0 1/1 0/0 0/1 0/0 0/1 0/2 0/0 1/1 0/2 0/0
20,28,30,37,41 & 42)

Shifting of Lifting Barrier (Nos.)


19 (LC-2,3,5,7,8,9,12, 20,28,30,37,41 5/6 1/1 0/0 0/0 0/1 0/0 0/2 0/0 0/1 0/2 0/0
& 42)

Shifting of Height Gauges (Nos.)


20 (LC-2,3,5,7,8,9,12, 20,28,30,37,41 6/6 1/1 0/0 0/0 0/1 0/0 0/2 0/0 0/1 0/2 0/0
& 42)

21 Passenger Platform(Nos.) 0/0 0/0 1/2 0/0 2/2 0 0/2 0 0/2 0 0/2 0 0/2 0/2
Dhablan
Rajpura

Patiala

Patiala

Nabha
Kalan

Cantt
Daun
Kauli
SN Items/Section

22 Goods Platform (Nos.) 0/0 0/0 WIP 0/0 0/0 0 0/1 0 0 0 0 0 0/1 0

B Electrical

1 Foundation (WIP/Total) 232/232 138/138 86/86 119/119 72/95 50/70 98/150 0/240 0/95

2 Mast erection (WIP/Total) 194/194 109/109 73/73 101/101 47/75 0/60 0/120 0/190 0/80

3 Grouting (Nos.) 224/224 161/161 82/82 152/152 47/75 0/60 0/120 0/190 0/80

4 Bond (Nos.) 193/193 90/146 73/73 79/90 0/75 0/60 0/120 0/190 0/80

5 Catenary Wire (per shorts) 10/10 8/8 04/04 6/6 0/3 0/3 0/6 0/8 0/3

6 Contact Wire (per shorts) 10/10 8/8 04/04 6/6 0/3 0/3 0/6 0/8 0/3

7 ATD Erection (Nos.) 18/18 16/18 8/8 10/10 0/6 0/6 0/12 0/14 0/6

8 Droppering & Clipping (Span) 209/209 180/180 82/82 95/95 0/90 0/67 0/147 0/245 0/96

Bracket Adjustment and


9 224/224 161/161 82/82 152/152 0/77 0/62 0/122 0/192 0/82
checking(Nos.)

ATD Adjustment and checking


10 18/18 16/18 8/8 10/10 0/6 0/6 0/12 0/14 0/6
(Nos.)

11 Tower Wagon Checking (TKM) 10.266/10.670 0/7.660 5.016/5.016 1.740/7.238 0/4.45 0/3.421 0/7.116 0/11.34 0/4.621

C S&T

1 SIP - 0/0 1/1 0/0 1/1 1/1 NA 1/1 1/1

2 TOC/ST - 0/0 1/1 0/0 1/1 0/1 NA 0/1 0/1

3 Circuit approval - 0/0 1/1 0/0 1/1 0/1 NA 0/1 0/1

4 Logic - 0/0 1/1 0/0 1/1 0/1 NA 0/1 0/1

5 SWRD - 0/0 1/1 0/0 1/1 0/1 NA 0/1 0/1

6 Condonation - 0/0 1/1 0/0 1/1 0/1 NA 0/1 0/1

7 FAT - 0/0 1/1 0/0 1/1 0/1 NA 0/1 0/1

8 SAT - 0/0 0/1 0/0 1/1 0/1 NA 0/1 0/1

9 Cable Laying (Km) 13/13 40/40 100/100 0/0 110/110 22/95 NA 12/75 10/75

Signal Foundation (No.)


10 2/2 4/4 18/18 0/0 13/13 0/18 NA 0/14 0/16
(Main+Shunt)

11 Signal Erection (No.) 0/2 0/4 19/19 0/0 13/13 0/18 NA 0/14 0/16

12 Location Wring (No.) 4/4 13/13 70/70 0/0 65/65 0/85 NA 0/75 0/80

13 Relays Rack (No.) 1/1 1/1 5/5 0/0 3/3 0/54 NA 0/35 0/65

14 EI 0/0 0/0 3/3 0/0 1/1 0/1 NA 0/1 0/1


WEEKLY PROGRESS REPORT - PKG 1 (FROM RAJPURA TO KAKRALA HALT)
Block Section ===> All Sections Combined Rajpura Yard Rajpura to Kauli Kauli Yard KLI-DOC
(Lenght in Km) (upto ( 57.5 km) (0.600-1.700 km) (1.700-10.780 km) (10.780-12.440 km) (12.440-17.960 km)
20/2/2
2)
SN Work Item Unit Overall Total Cummu. Balance Total Weekly Cummu. Balance Total Qty. Weekly Cummu. Balance Total Weekly Cummu. Balance Total Qty. Weekly Cummu. Balance
Total scope Weekly Prog. Qty. Prog. Prog. Prog. Prog. Qty. Prog. Prog. Prog. Prog.
Prog.
1 CUTTING Cum 247,570 1,651 215,673 31,897 6,060 0 5,818 242 53,981 0 53,981 0 16,607 0 16,607 0 15,825 0 15,825 0

2 EARTHWORK Cum 419,889 678 410,208 9,681 10,119 0 10,119 0 109,583 0 109,583 0 7,803 0 7,803 0 68,500 0 68,500 0
3 BLANKETING Cum 309,118 487 274,447 34,671 6,018 0 5,818 200 56,458 0 56,458 0 6,239 0 6,239 0 34,352 0 34,352 0
4 MAJOR BRIDGES Nos. 11 0 11 0 0 0 0 0 1 0 1 0 0 0 0 0 1 0 1 0
5 MINOR BRIDGE Nos. 79 0 58 21 0 0 0 0 16 0 16 0 1 0 1 0 3 0 3 0

6 LHS Nos. 5 0 2 3 0 0 0 0 0 0 0 0 2 0 0 2 1 0 1 0
7 LC GATE LODGE Nos. 12 0 8 4 1 0 1 0 2 0 2 0 1 0 1 0 1 0 1 0
8 BALLAST Cum 218,076 0 161,135 56,941 3,180 0 1,200 1,980 29,522 0 29,522 0 16,267 0 16,267 0 16,010 0 16,010 0
9 FORMATION Kms 56.90 0.00 48.65 8.25 1.10 0.00 0.97 0.13 9.08 0.00 9.08 0.00 1.66 0.00 1.66 0.00 5.52 0.00 5.52 0.00
HANDOVER

10 TRACK LINKING Tkm 72.14 0.00 30.04 42.11 1.10 0.00 0.97 0.13 9.08 0.00 9.08 0.00 5.84 0.00 5.84 0.00 5.52 0.00 5.52 0.00
11 Commiitted TDCs Minor Bridge - 30.06.2022 Minor Bridge - NA Minor Bridge - Complete Minor Bridge - NA Minor Bridge - Complete
Major Bridge - Br. 62 - 30.01.2022 Major Bridge - NA Major Bridge - Complete Major Bridge - NA Major Bridge - Complete
Blanketing - 30.06.2021 Earthwork - Complete Earthwork - Complete Earthwork - Complete Earthwork - Complete
Formation hand Over - 30.06.2021 Blanketing - Complete Blanketing - Complete Blanketing - Complete Blanketing - Complete
Ballast - 15.07.2022 Formation hand Over - 15.02.2022 Formation hand Over - Complete Formation hand Over - Complete Formation hand Over - Complete
Track Linking - 31.07.2022 Ballast - 28.02.2021 Ballast - Complete Ballast - Complete Ballast - Complete
LC Gate shifting - 30.05.2022 Track Linking - 15.03.2022 Track Linking - Complete Track Linking - Complete Track Linking - Complete
LC Lodge Gate - Complete LC Lodge Gate - Complete LC Lodge Gate - Complete LC Lodge Gate - Complete
LHS - At LC No.9 in progress .
TDC-28.2.22

12 Issues Minor Bridge - App GAD of 23


Nos.minor bridge required.
Site plan approval of Duty hut at LC
No.20 &31

Page 7 of 19
WEEKLY PROGRESS REPORT - PKG 1 (FROM RAJPURA TO KAKRALA HALT)
Block Section ===> DOC-Yard DOC-PTA PTA Yard PTA-DBN DBN Yard
(Lenght in Km) (upto (17.960-19.300 km) (19.300-23.800 km) (23.800-25.600 km) (25.600-37.100 km) (37.100-38.220 km)
20/2/2
2)
SN Work Item Unit Total Qty. Weekly Cummu. Balance Total Qty. Weekly Cummu. Balance Total Qty. Weekly Cummu. Balance Total Qty. Weekly Cummu. Balance Total Qty. Weekly Cummu. Balance
Prog. Prog. Prog. Prog. Prog. Prog. Prog. Prog. Prog. Prog.

1 CUTTING Cum 3,570 0 3,570 0 10,979 0 10,659 320 12,000 0 2,085 9,915 29,059 1,078 27,020 2,039 3,132 0 0 3,132

2 EARTHWORK Cum 11,993 0 11,993 0 50,146 0 49,906 240 1,995 0 1,780 215 86,742 678 83,310 3,432 1,742 0 0 1,742
3 BLANKETING Cum 11,736 0 11,736 0 24,881 0 24,622 259 7,000 0 864 6,136 57,771 487 49,483 8,288 3,636 0 0 3,636
4 MAJOR BRIDGES Nos. 0 0 0 0 3 0 3 0 0 0 0 0 3 0 3 0 0 0 0 0
5 MINOR BRIDGE Nos. 0 0 0 0 2 0 2 0 2 0 1 1 16 0 12 4 3 0 1 2

6 LHS Nos. 1 0 1 0 0 0 0 0 1 0 0 1 0 0 0 0 0 0 0 0
7 LC GATE LODGE Nos. 0 0 0 0 0 0 0 0 0 0 0 0 3 0 0 3 1 0 0 1
8 BALLAST Cum 8,617 0 8,617 0 14,822 0 14,048 774 26,010 0 0 26,010 34,500 0 29,082 5,418 5,597 0 3,003 2,594
9 FORMATION Kms 1.34 0.00 1.34 0.00 4.50 0.00 4.40 0.10 1.80 0.00 0.00 1.80 11.50 0.00 9.16 2.34 1.12 0.00 0.00 1.12
HANDOVER

10 TRACK LINKING Tkm 3.00 0.00 3.00 0.00 4.50 0.00 3.40 1.10 8.67 0.00 0.00 8.67 11.50 0.00 0.00 11.50 2.12 0.00 0.00 2.12
11 Commiitted TDCs Minor Bridge - NA Minor Bridge - Complete Minor Bridge - 30.06.2022 (Br. 43) 4 Minor Bridge (48, 54, 60, 63) - Minor Bridge (75 & 77) -
Major Bridge - NA Major Bridge - Complete Major Bridge - NA 31.03.2022 30.05.2022
Earthwork - Complete Earthwork - 05.03.22 Earthwork - 15.06.2022 1 Minor Br. Closed ( 57) Major Bridge - NA
Blanketing - Complete Blanketing - 05.03.2022 Blanketing - 20.06.2022 Major Bridge (62A) - Completed Earthwork - 30.05.2022
Formation hand Over - Complete Formation handover - 05.03.2022 Formation hand Over - 30.06.2022 Earthwork - 30.05.2022 Blanketing - 15.06.2022
Ballast - Complete Ballast - 03.03.2022 Ballast - 30.06.2022 Blanketing - 30.06.2022 Formation hand Over - 30.06.2022
Track Linking - Complete Track Linking - 05.03.22 (only LC Track Linking - 31.07.2022 Formation hand Over - 30.06.2022 Ballast - 15.07.2022
LC Lodge Gate - Complete No. 15 & 16 to be made through) LC Gate - NA (LHS 17 will be Ballast - 15.07.2022 Track Linking - 31.07.2022
constructed) Track Linking - 31.07.2022 LC No.31 duty hut const. -
LC Gate shifting- 30.05.2022 30.05.2022

12 Issues LC No. 15 & 16 to be made Revised GAD of Br No. 43 LC-20 - Forest land issue: 1 m less LC-31 - Private Land will be taken.
through. TDC: 05.03.2022 submitted to Divn on 2.2.22 after width. Revised site plan sent to Divn for Agency instructed for the same.
marking of stabling Yard lines on approval. ESP is in the Division.
ground. Observations are being removed of GAD of Br. No. 77 will be
GAD of br.63. submitted to Hq after checking of
GAD of Br No. 54 was not readable as
LHS in lieu of LC No. 17 is to be per HQ. Autocad copy received and will fitness of existing br for 32.5 T
consturcted: Traffic Diversion & be sent to Divn on monday. Loading.
utility shifting to be done. Marking Proposal for closure of Br. 57 sent to Due to revision in ESP of DBN the
on ground done . jointly site Division on 31.1.22. GAD of Br No. 75 will be revised.
inspection is being arranged in next GAD of minor Br 48 & 60 submitted to Detail sent to FLS team for
week. HQ on 7.2.22. revision.
Land adjacent to track is not available, Cut & connections on both sides.
hence ballast spreading will be done
after bridge constrction.

Page 8 of 19
WEEKLY PROGRESS REPORT - PKG 1 (FROM RAJPURA TO KAKRALA HALT)
Block Section ===> DBN-NBA NBA Yard NBA-KKR Remarks
(Lenght in Km) (upto (38.220-49.980 km) (49.980-53.700 km) (53.700-57.500 km)
20/2/2
2)
SN Work Item Unit Total Qty. Weekly Cummu. Balance Total Qty. Weekly Cummu. Balance Total Qty. Weekly Cummu. Balance
Prog. Prog. Prog. Prog. Prog. Prog.

1 CUTTING Cum 47,122 573 43,373 3,749 21,000 0 11,500 9,500 28,235 0 25,235 3,000

2 EARTHWORK Cum 39,752 0 39,307 445 19,061 0 16,000 3,061 12,453 0 11,907 546
3 BLANKETING Cum 60,484 0 56,274 4,210 20,672 0 10,604 10,068 19,871 0 17,997 1,874
4 MAJOR BRIDGES Nos. 2 0 2 0 0 0 0 0 1 0 1 0
5 MINOR BRIDGE Nos. 22 0 14 8 5 0 2 3 9 0 6 3 Box Completed & closed Bridges also taken in completed
Bridge. The work of minor Br Ni. 118 has been started.

6 LHS Nos. 0 0 0 0 0 0 0 0 0 0 0 0 LC No. 17 in PTA yard to be constructed. LCNo. 31&32


in DBN yard, LC No.40 & 41 in NBA yard to be
7 LC GATE LODGE Nos. 1 0 1 0 2 0 2 0 0 0 0 0 extended. LC No.42 will be closed in 1st phase.

8 BALLAST Cum 35,280 0 28,152 7,128 16,871 0 11,641 5,230 11,400 0 3,593 7,807
9 FORMATION Kms 11.76 0.00 10.52 1.24 3.72 0.00 2.60 1.12 3.80 0.00 3.40 0.40 At cut and connection location at km 53.0-54.0 km bet
HANDOVER NBA-KKRL formation completed. Now balance
formaton is 400 m at Minor br and LC locations.
10 TRACK LINKING Tkm 11.76 0.00 0.00 11.76 5.26 0.00 1.00 4.26 3.80 0.00 1.23 2.57 14.5 Tkm SH rail available. (Used for 4 km DOC-PTA)
(Planned 3.8 km NBA-KKR)
11 Commiitted TDCs Minor Bridge - 30.05.2022 Minor Bridge - 15.03.2022 Minor Bridge (113A, 118 & 119) -
Major Bridge - Completed Minor Br. Closed (Br No.110) 28.02.2022
Earthwork - 30.05.2022 Major Bridge - NA Major Bridge - Completed
Blanketing - 15.06.2022 Earthwork - 31.03.2022 Earthwork - 28.02.2022 (Br.
Formation hand Over - 30.06.2022 Blanketing - 10.04.2022 Approach)
Ballast - 10.07.2022 Formation hand Over - 15.04.2022 Blanketing - 10.03.2022
Track Linking - 31.07.2022 Ballast - 30.04.2022 Formation hand Over - 15.03.2022
LC Gate shifting - 30.05.2022 Track Linking - 31.05.2022 Ballast - 31.03.2022
LC Gate shifting- 20.03.2022 Track Linking - 31.03.2022
LC Gate Shifting - 15.02.2022

12 Issues GAD of Minor Br. GADs of 2 Minor Br. (107, 108 ) Approval of GAD of Br. 119 reqd.
No. 81: CRS sd received on 31.01.22 will be revised. Data sent to FLS Fitness of existing Br No.119 for
No. 88: Approved by HQ only for team for revision. 25T is req by HQ.
existing Br. On Tuesday R-1 of the Br No.109: CRS sanction received After correction GAD of Br
same for Doubling br will be on 31.1.2011 no.113A submitted to HQ on
submitted to Division. Proposal for closure of Minor Br 7.2.22.
GAD of Br No. 80,82, 93, 97, 105 & 110 sent to Division on 31.1.2022. Br No. 118 - CRS sanction received
106 resubmitted to HQ on 7.2.22. Cut & connections on both ends on 31.1.2022.
& will be done during PNI & NI.

Page 9 of 19
Annexure:-5

Pre-Cast Counterfort walls for H.L P/Forms in pkg-1 on RPJ-BTI Doubling

Counterfort Walls Required


(Nos.)
Total
SN Station Length 600/540 m P/F 375 m P/F Remarks
(m) Total
Nos. PF - 2/3
PF - 1 PF - 2 PF - 1 PF - 2
(Island)
1 RPJ 0 0 0 0 0 0 0
Casting complete
2 KLI 1140 1267 667 600 0 0 0

Casting complete
3 DOC 1080 1200 600 600 0 0 0

Casting complete
4 PTA 1140 1534 200 1334 0 0

Rail Level PF
5 PTE 0 0 0 0 0 0 0

Casting complete
6 DBN 1140 1267 667 600 0 0 0

Casting complete
7 NBA 540 1934 600 1334 0 0

Rail Level PF
8 KKRL 0 0 0 0 0 0 0

TOTAL 5,040 7,202 2,734 1,800 2,668 0 0

Note: Pre-Cast segments are as per RDSO Drg. No. MA-10870


Annexure: 6 (Revenue Tracker of Key Execution Activities)

Bill Work Done Under Different BOQ Total Amount (as per (A) Accrued Amount of (B) Revenue Generated
Difference (A-B)
Number Heads LOA) Work Done (Amount)

Bill No. 1: Earthwork in


1 INR 964,053,899.74 INR 890,208,580.00 INR 886,959,772.86 INR 3,248,807.14
Formation

2 Bill No. 2: Bridge work INR 175,128,704.00 INR 222,641,637.45 INR 160,131,131.21 INR 62,510,506.24

3 Bill No. 3 Ballast INR 297,183,169.00 INR 287,182,665.00 INR 278,821,018.43 INR 8,361,646.57

6 Bill No. 6: Buildings INR 139,610,093.03 INR 137,880,021.00 INR 134,042,205.35 INR 3,837,815.65
Bill No. 7A: PF, Passenger
7 INR 207,113,320.00 INR 114,920,911.91 INR 109,599,327.75 INR 5,321,584.16
Amenities & Miscellanious works

Total Revised value of Contract INR 480.82


Total Vaule of work done INR 320.08
Total Billed INR 297.90
INR 1,000,000,000.00

INR 900,000,000.00

INR 800,000,000.00

INR 700,000,000.00

INR 600,000,000.00

INR 500,000,000.00

INR 400,000,000.00

INR 300,000,000.00

INR 200,000,000.00

INR 100,000,000.00

INR -
Bill No. 1: Earthwork in Formation Bill No. 2: Bridge work Bill No. 3 Ballast Bill No. 6: Buildings Bill No. 7A: PF, Passenger Amenities &
Miscellanious works
1 2 3 6 7
(A) Accrued Amount of Work Done (B) Revenue Generated (Amount)
QUALITY CONTROL REPORT FOR FEBRUARY - 2022

IN HOUSE REPORT:
Number of Tests Conducted
Sl. Cumulative upto Total Tests Done
Name of Test Testing Method Frequency of Test Test done in this month Remarks
No Previous Month Upto Date
Passed Failed Total Passed Failed Total Passed Failed Total
OGL
MDD/OMC IS:2720 Part-8 1 Test /500 m 0 0 0 0 0 0 0 0 0
1
Ll/PI IS: 2720 Part-5 1 Test /500 m 0 0 0 0 0 0 0 0 0
GSA IS: 2720: Part-4 1 Test /500 m 0 0 0 0 0 0 0 0 0
Cutting Soil Test
MDD/OMC IS:2720 Part-8 1 Test /500 m 0 0 0 0 0 0 0 0 0
2 Ll/PI IS: 2720 Part-5 1 Test /500 m 0 0 0 0 0 0 0 0 0
GSA IS: 2720: Part-4 1 Test /500 m 0 0 0 0 0 0 0 0 0
CBR IS: 2720 Part-16 As Required 0 0 0 0 0 0 0 0 0
Borrow Area approval for Emb. & Subgrade (RDSO/2007/GE:0014 & Guidelines for Earthwork in Railway Project Guideline no.GENo.GE: G-1
MDD/OMC IS:2720 Part-8 1 test per Emb/Sub.5000/2000 m3 106 0 106 0 0 0 106 0 106
3 Ll/PI IS: 2720 Part-5 1 test per Emb/Sub.5000/2000 m3 106 0 106 0 0 0 106 0 106
GSA IS: 2720: Part-41 test per Emb/Sub.5000/2000 m3 106 0 106 0 0 0 106 0 106
CBR IS: 2720 Part-161 test per Emb/Sub.5000/2000 m3 106 0 106 0 0 0 106 0 106
Control test for Ballast material
Grading IRS-GE-1 June-2004 1 test per 100 m3 1889 0 1889 0 0 0 1889 0 1889
4 Water Absorption (%)
IRS-GE-1 June-2004 1 test per 2000 m3 0 0 0 0 0 0 0 0 0
AIV IRS-GE-1 June-2004 1 test per 2000 m3 0 0 0 0 0 0 0 0 0
Los Angales IRS-GE-1 June-2004 1 test per 2000 m3 0 0 0 0 0 0 0 0 0
Control test for Blanketing material
Grading RDSO/GE:014-2007 1 test per 500 m3 717 0 717 0 0 0 717 0 717
MDD/OMC RDSO/GE:014-2007 1 test per 500 m3 717 0 717 0 0 0 717 0 717
5
Cu & Cc RDSO/GE:014-2007 1 test per 500 m3 717 0 717 0 0 0 717 0 717
Los Angales RDSO/GE:014-2007 1 test per 500 m3 717 0 717 0 0 0 717 0 717
CBR RDSO/GE:014-2007 1 test per 500 m3 717 0 717 0 0 0 717 0 717
Coarse Aggregate for concrete
Grading 40mm
IS: 2386 Part-1 1 Test per stock 97 0 97 4 0 4 101 0 101
Aggregate
Grading 20mm
IS: 2386 Part-1 1 Test per stock 236 0 236 8 0 8 244 0 244
6 Aggregate
Grading 10mm
IS: 2386 Part-1 1 Test per stock 247 0 237 8 0 8 255 0 255
Aggregate
AIV IS: 2386 Part-4 1 Test per Month 182 0 182 8 0 8 190 0 190
Fiakiness IS: 2386 Part-1 1 Test per Month 202 0 202 8 0 8 210 0 210
Fine Aggregate for concrete
Grading IS: 2386 Part-1 1 Test per stock 240 0 230 8 0 8 248 0 248
7
Fineness IS: 2386 Part-1 1 Test per stock 237 0 227 8 0 8 245 0 245
Silt Content IS: 2386 Part-1 1 Test per stock 103 0 99 4 0 4 107 0 107
Cement OPC 53 Grade
Consistency IS:4031 Part-4 54 0 54 0 0 0 54 0 54
8 Setting Times IS:4031 Part-5 54 0 54 0 0 0 54 0 54
1 Test per Lot
Fineness IS:4031 Part-3 54 0 54 0 0 0 54 0 54
Compressive Strength IS:516 54 0 54 0 0 0 54 0 54
Cement PPC
Consistency IS:4031 Part-4 44 0 44 0 0 0 44 0 44
9 Setting Times IS:4031 Part-5 44 0 44 0 0 0 44 0 44
1 Test per Lot
Fineness IS:4031 Part-3 44 0 44 0 0 0 44 0 44
Compressive Strength IS:516 44 0 44 0 0 0 44 0 44
BRICKS
Dimension IS:1077/3496 88 0 88 3 0 3 91 0 91
10
Water Absorption (%) IS:1077/3495 1 Test per Lot 88 0 88 3 0 3 91 0 91
Compressive Strength IS:1077/3497 88 0 88 3 0 3 91 0 91
Concrete Cube Compressive Strength
7 Days 77 0 77 1 0 1 78 0 78
M-10 OHE
28 Days 66 0 66 2 0 2 68 0 68
7 Days 183 0 183 0 0 0 183 0 183
M-15
28 Days 414 0 414 0 0 0 414 0 414
7 Days 155 0 155 0 0 0 155 0 155
M-20 1 Sample for 1-5 Cum. 2
28 Days Sample for 6-15 Cum, 3 184 0 184 1 0 1 185 0 185
11 7 Days Sample for 16-30 Cum, 4 720 0 720 15 0 15 735 0 735
M-25
28 Days Sample for 31-50 Cum, 4+1 / 1373 0 1373 15 0 15 1388 0 1388
7 Days Additional 50Cum. Or part for 1297 0 1297 7 0 7 1304 0 1304
M-30 > 51 Cum.
28 Days 2410 0 2410 7 0 7 2417 0 2417
7 Days 82 0 82 4 0 4 86 0 86
M-35
28 Days 295 0 295 0 0 0 295 0 295
7 Days 8 0 8 0 0 0 8 0 8
M-40
28 Days 13 0 13 0 0 0 13 0 13
QUALITY CONTROL REPORT FOR THIRD PARTY
Number of Tests Conducted
Sl. Cumulative upto Previous Total Tests Done Upto
Name of Test Testing Method Frequency of Test Test done in this month Remarks
No Month Date
Passed Failed Total Passed Failed Total Passed Failed Total
OGL
MDD/OMC IS:2720 Part-8 1 Test /500 m 194 0 194 0 0 0 194 0 194
1 Ll/PI IS: 2720 Part-5 1 Test /500 m 194 0 194 0 0 0 194 0 194
GSA IS: 2720: Part-4 1 Test /500 m 194 0 194 0 0 0 194 0 194
CBR IS: 2720 Part-16 As Required 194 0 194 0 0 0 194 0 194
Cutting Soil Test
MDD/OMC IS:2720 Part-8 1 Test /500 m 0 0 0 0 0 0 0 0 0
2 Ll/PI IS: 2720 Part-5 1 Test /500 m 0 0 0 0 0 0 0 0 0
GSA IS: 2720: Part-4 1 Test /500 m 0 0 0 0 0 0 0 0 0
CBR IS: 2720 Part-16 As Required 0 0 0 0 0 0 0 0 0
Borrow Area approval for Emb. & Subgrade (RDSO/2007/GE:0014 & Guidelines for Earthwork in Railway Project Guideline no.GENo.GE: G-1
MDD/OMC IS:2720 Part-8 1 test per Emb/Sub.5000/2000 m 3 10 0 10 0 0 0 10 0 10
3 Ll/PI IS: 2720 Part-5 1 test per Emb/Sub.5000/2000 m 3
10 0 10 0 0 0 10 0 10
GSA IS: 2720: Part-4 1 test per Emb/Sub.5000/2000 m 3 10 0 10 0 0 0 10 0 10
CBR IS: 2720 Part-16 1 test per Emb/Sub.5000/2000 m 3 10 0 10 0 0 0 10 0 10
Control test for Ballast material
Grading IRS-GE-1 June-2004 1 test per 100 m3 0 0 0 0 0 0 0 0 0
4 Water Absorption (%)
IRS-GE-1 June-2004 1 test per 2000 m3 100 0 100 0 0 0 100 0 100
AIV IRS-GE-1 June-2004 1 test per 2000 m3 100 0 100 0 0 0 100 0 100
Los Angales IRS-GE-1 June-2004 1 test per 2000 m3 100 0 100 0 0 0 100 0 100
Control test for Blanketing material
Grading RDSO/GE:014-2007 1 test per 500 m3 2 0 2 0 0 0 2 0 2
MDD/OMC RDSO/GE:014-2007 1 test per 500 m3 2 0 2 0 0 0 2 0 2
5
Cu & Cc RDSO/GE:014-2007 1 test per 500 m3 2 0 2 0 0 0 2 0 2
Los Angales RDSO/GE:014-2007 1 test per 500 m3 2 0 2 0 0 0 2 0 2
CBR RDSO/GE:014-2007 1 test per 500 m3 2 0 2 0 0 0 2 0 2
Cement OPC 53 Grade
Consistency IS:4031 Part-4 2 0 2 0 0 0 2 0 2
6 Setting Times IS:4031 Part-5 2 0 2 0 0 0 2 0 2
1 Test per Lot
Fineness IS:4031 Part-3 2 0 2 0 0 0 2 0 2
6
1 Test per Lot

Compressive Strength IS:516 2 0 2 0 0 0 2 0 2


Cement PPC
Consistency IS:4031 Part-4 3 0 3 0 0 0 3 0 3
7 Setting Times IS:4031 Part-5 3 0 3 0 0 0 3 0 3
1 Test per Lot
Fineness IS:4031 Part-3 3 0 3 0 0 0 3 0 3
Compressive Strength IS:516 3 0 3 0 0 0 3 0 3
BRICKS
Dimension IS:1077/3496 1 0 1 0 0 0 1 0 1
8
Water Absorption (%) IS:1077/3495 1 Test per Lot 1 0 1 0 0 0 1 0 1
Compressive Strength IS:1077/3497 1 0 1 0 0 0 1 0 1
Steel Test
8mm 10 0 10 0 0 0 10 0 10
1 Test per 25MT
10mm 20 0 20 0 0 0 20 0 20
IS:1786, Table-3
12mm & RVNL Spec. 10 0 10 0 0 0 10 0 10
9
16mm Vol-1, Part A- 9 0 9 0 0 0 9 0 9
20mm Bridge, Sec-C 1 Test per 40MT 6 0 6 0 0 0 6 0 6
Cl.2
25mm 4 0 4 0 0 0 4 0 4
32mm 2 0 2 0 0 0 2 0 2
Water Test
10 RVNL Spec
Water Test Cl:3.0 & IS 1 Test per Source 3 0 3 0 0 0 3 0 3
456:2000 clL5.4
Package No.1 (RBD-1) - “Construction of Roadbed, minor bridges, supply of ballast, Installation of track
(excluding supply of rails, PSC sleepers & Thick web switches), Electrical (Railway Electrification and General
Electrification), Signaling and Telecommunication works for Doubling of track between Rajpura and Kakrala Halt
(Including) from km 0.00 to 57.5 in Ambala Division of Northern Railway, Punjab, India.”

CLIENT: RAIL VIKAS NIGAM LIMITED(RVNL)


JMC-KPTL-EESPL PMC: AARVEE ASSOCIATES ARCHITECTS ENGINEERS & CONSULTANTS PVT
(JV) LTD
CONTRACTOR: JMC-KPTL-EESPL(JV)

WEATHER REPORTS MONTH OF FEBRUARY - 2022


SR.NO DATE WEATHER TEMPERATURE RAIN IN FALL SIGNATURE SIGNATURE REMARKS
1 1/Feb/2022 Gogg 21.20 - Contractors PMC/RVNL
2 2/Feb/2022 Fogg/ Rainy 20.90 13.5mm
3 3/Feb/2022 Cloudy / Rainy 22.00 20mm
4 4/Feb/2022 Cloudy 19.20 -
5 5/Feb/2022 Sunny 18.20 -
6 6/Feb/2022 Sunny 17.90 -
7 7/Feb/2022 Sunny 16.70 -
8 8/Feb/2022 Sunny 17.20 -
9 9/Feb/2022 Sunny 16.50 -
10 10/Feb/2022 Sunny 16.80 -
11 11/Feb/2022 Sunny 15.10 -
12 12/Feb/2022 Sunny 16.30 -
13 13/Feb/2022 Sunny 17.00 -
14 14/Feb/2022 Sunny 16.60 -
15 15/Feb/2022 Sunny 15.30 -
16 16/Feb/2022 Sunny 15.60 -
17 17/Feb/2022 Sunny 14.10 -
18 18/Feb/2022 Sunny 14.30 -
19 19/Feb/2022 Sunny 13.90 -
20 20/Feb/2022 Sunny 15.60 -
21 21/Feb/2022 Sunny 17.20 -
22 22/Feb/2022 Sunny 16.50 -
23 23/Feb/2022 Sunny 16.30 -
24 24/Feb/2022 Sunny 17.20 -
25 25/Feb/2022 Sunny 16.50 -
26 26/Feb/2022 Cloudy 17.00 -
27 27/Feb/2022 Sunny 18.30 -
28 28/Feb/2022 Sunny 19.20 -

You might also like