Professional Documents
Culture Documents
KTR Summary of Activities 3gi Week 06 2021
KTR Summary of Activities 3gi Week 06 2021
Reported Weld
DATE DAY TEAM Planned / Exectued Activities Completed NOTES Accept/Reject
Team 1 AM Report template for 18x58mm SSA Validation (Start) 100% 01. No Site Delays today N/A
RA/Kairat PM Report template for 18x58mm SSA Validation 100% N/A
08-Feb Mon
Team 2 AM Scan Before PWHT of 047-2900-LLL-ISO-000-000-00065-03 (P-003) 100% N/A
SB/Timur PM MUT Follow UP scan of Defect 00005-21-FW-04 (D1.1) 100% N/A
Team 1 AM Analysis & Report of 00065-03|CW-M253A-M252A-015-01 (P-003) N/A 01. Delay after Calibrations. Lifting operations & scaffolding barriers blocking area. After negotioting Accept
RA PM Analysis & Report of 00005-21-FW-04 (D1.1) N/A access and hauling equipment up the scaffold team discovered there was no heating. Weather was -9 Reject
09-Feb Tues degC Team 2 Carried on with part of the validation preperation of the 18"x 58mm SSA Project Block.
Team 2 AM Scan After PWHT of 00005-14 FW-01 (C1.5) DELAYED 0% N/A
SKB PM Validation preperation of Sequence 1 SSA Scan Plan 00083 N/A N/A
Team 1 AM Report template for 18x58mm SSA Validation 01. Report Template for SSA 18x58mm template complete until Validation data is available. N/A
100% 62 Pages of report. Analysis and screen shots will be included after Validation.
RA PM Report template for 18x58mm SSA Validation - (Completeed) N/A
10-Feb Wed
Team 2 AM Scan After PWHT of 00005-14 FW-01 TOFD (C1.5) 100% N/A
SKB PM Scan After PWHT of 00005-14 FW-01 PAUT (C1.5) 100% N/A
Team 1 AM Analysis & Report of 00005-14 FW-01 (C1.5) 100% 01. No Site Delays today Accept
RA PM Validation Report Template for LTCS 3"x16mm Validation 100% 02. 3"x 16mm Validation report has been complete until witnessed validation data is collected N/A
11-Feb Thu
Team 2 AM Scan After PWHT of CW-M252B-M253B-901-01 (P-018) TOFD 100% N/A
SKB PM Scan After PWHT of CW-M252B-M253B-901-01 (P-018) PAUT 100% N/A
AM Analysis & Report of CW-M252B-M253B-901-01 (P-018) 100% 01. No Site Delays today Accept
Team 1
02. 12"x 17.4mm Validation report has been complete until witnessed validation data is collected
RA
PM Validation Report Template for LTCS 12"x17.48mm Validation 100% 03. Delay as Scheduled weld not prepared by VLS Construction. AUT Team continued with Validation N/A
12-Feb Fri prepweration
Team 2
AM Delay - No Field weld ready for inspection. 100% N/A
SKB
PM Validation preperation for Single Bevel LTCS 100% N/A
Team 1 AM Validation Report Template for LTCS 8"x18.26mm Validation 100% 01. No Site Delays today N/A
RA PM Validation Report Template for LTCS 8"x18.26mm Validation 100% 02. 12"x 17.4mm Validation report has been complete until witnessed validation data is collected N/A
13-Feb SAT 03. Mark up repair prior to repair works.
Team 2 AM Mark UP Repair/Re-Scan of 00055-02/CW-M253A-M253B-003-01 PAUT (P-058) 100% N/A
SKB PM Mark UP Repair of 00055-02/CW-M253A-M253B-003-01 MUT (P-058) 100% N/A
Team 1 AM Validation Report Template for LTCS 8"x18.26mm Validation Delayed 01. Delay of Validation report template as no Project Qualification Block is on record. N/A
RA PM Mark UP Repair REPORT of 00055-02/CW-M253A-M253B-003-01 PAUT (P-058) 100% N/A
14-Feb SUN 100%
Team 2 AM Scan After PWHT of 047-2900-LLL-ISO-000-000-00065-03 (P-003) Pending
SKB PM Scan After PWHT of 047-2900-LLL-ISO-000-000-00065-03 (P-003) 100% Pending
2 Regular Water Deliveries. Coffee Lady is getting Angry at the local guys for taking 2 Monitor running of heater in Calibration workshop.
water
3 3
4
Week 6 Results
Week 6 Completed Welds
Material & Construction Before / After NDT Request Planned Scanning
Day Date Zone Iso No. Weld No. Analysis Result
Size ID. PWHT No. PWHT Completed
1 Monday 08/02/2021 49A F22 16x52 047-2900-LLL-ISO-000-000-00005-21 FW-04 D1.1 Before UT.116 100% Reject
2 Monday 08/02/2021 Module F22 16x52 047-2900-LLL-ISO-000-000-00065-03 CW-M253A-M252A-015-01 P-003 Before UT.117 100% Accept
3 Wednesday 10/02/2021 Module F22 16x52 047-2900-LLL-ISO-000-000-00005-14 FW-01 C1.5 After UT.115.Post 100% Accept
4 Thursday 11/02/2021 Module F22 18x58 047-2900-LLL-ISO-000-000-00055-03 CW-M252B-M253B-901-01 P-018 After UT.99.Post 100% Accept
7 Sunday 14/02/2021 Module F22 16x52 047-2900-LLL-ISO-000-000-00065-03 CW-M253A-M252A-015-01 P-003 After UT.117.Post Pending
Summary of Welds pending Examination
Active Production Scope Waiting For Inspection (NDT Request Issued) Febuary 2021