JHA NO. /2020 -JHA PTW NO WORK PERMIT TYPE COLD WORK
FACILITY Platform LOCATION Thai Binh, Block 102 & 106 SPECIFIC WORKSTATION Mezzanine Deck
EQUIPMENT NO. A-7710 WORK DESCRIPTION PPM ON THE GAS ENGINE GENERATOR
NOTE
1. JHA shall be applicable for all work activities which requires PTW.
2. Personnel carrying out the work shall be fully familiar with the written Work/Operating Procedures developed for the job. The Work/Operating Procedures shall describe, in step-by-step instructions, the correct method of executing the specified work.
3. Prior to commencement of work, the task-specific JHA shall be discussed amongst all personnel involved in the execution; and requirements contained therein shall be fully understood and agreed by all involved personnel.
JOB POTENTIAL
DESCRIPTION OF JOB STEP POTENTIAL HAZARD CONTROL BARRIERS ACTION PARTY RECOVERY BARRIERS ACTION PARTY
STEP CONSEQUENCE
1. Valid PTW
2. Tool Box Talk
Preparation: PIC Standard PPE
Noise 3. Joint work site check before obtain PIC
1 Worksite check for conflict activity Human E&I. Tech First aid kit
Slip/trip/fall authorization E&I. Tech
Hand tool and part preparation Mech. Tech ERP
Page 1
JHA APPROVAL DURING PTW APPLICATION
NAME NAME
DESIGNATION DESIGNATION
SIGNATURE SIGNATURE
DATE DATE
WORK TEAM (CONFIRMATION THAT JHA HAS BEEN COMMUNICATED TO WORK TEAM AS PART OF PRE-JOB/TOOLBOX MEETING)
Page 2