METHOD STATEMENT
ENTER SHORT DETAILS OF JOB OR TASK
Project/Contract
Contractor
Site Address
Project Start Date
Expected Duration
Projected Completion Date
Authorised by
(for Client)
Mobile
The following method statement has been developed to provide a safe system of work and
must be adhered to at all times, any significant deviation from this system must first be
authorised by your manager or safety representative. Please read the entire sheet
before beginning the procedure, if you have any questions please contact your
manager or safety representative.
This method statement describes the work process for the replacement of broken glass
panels at various heights.
1) Start of works. Site foreman will ensure site is safe to commence work, barriers
erected to prevent unauthorised access
2) Staff and contractors will put on Personal Protective Equipment
3) Erect ladders and secure in place to access upper balconies
4) Carry required hand tools to location
5) Connect fall arrest cable to balcony hand rail
6) Remove beading, hack out existing broken glass, while operative on ground floor
makes sure that general public are directed away from the area of works
7) When all broken glass and putty has been removed from the window frame,
operatives on the ground floor and at window location will sweep up all broken glass
and old putty and dispose of in cullet bin on vehicle.
8) Carry new pre-cut pane of glass to location
9) Fit new glass and replace beading
10) Check for quality of finish
11) Leave site clean and tidy
Series: Series & Number Number system Issue Date: Enter date here
Revision Number Revision Date Page 2 of 2