could only be achieved with the support from competent Engineering, Procurement,
and Construction (EPC) companies behind it. Therefore, we shape Bina Rekayasa
Anugrah into a one stop solution provider for every development requirements to
maximize benefits for our partners and the general public alike.
We analyze, design, calculate, and organize every single project with analytical
planning and keen situational observation, to make a detailed and accurate list of
material and equipment procurements, before finally executing projects with the
Page 1
Foreword from CEO
Bina Bina Rekayasa Anugrah was established as a solution provider
quality material and equipments that are right for the job, also
Page 2
Vision
To become an outstanding company in Engineering,
Mission
Presenting the best working result in planning,
Page 3
Vision & Mission
Company
History
Bina Rekayasa Anugrah was established based on
AHU-0053442.AH.01.01.TAHUN 2017, as a
Construction.
Page 4
Company History
Master Planning is a critical aspect of many design and construction projects,
especially those that will have a significant long-term impact on the institution
or facility where the work is being done. Master Planning from Bina Rekayasa
Anugrah creates a unified and consistent vision for your projects and sets the
tiveness and high in efficiency. First, we discuss your ideas, vision, and needs.
and floor plans, and a detailed scope of work that outlines construction
methods and materials. Then we determine the budget needed to make the
Page 7
Development
Management
Bina Rekayasa Anugrah provides the management of the design development
and the documentation required to deliver the masterplan and final costings
for each project, the concept design through the engagement of specialist
master planning and design consultants to deliver the project scope, initial
financial feasibility to ensure that the concept can be delivered within the
desired project allocated budgets, and approval through the required authori-
deliver the required design packages and authority approvals in the required
time frames to ensure that the prefabrication and construction divisions can
Page 10
Recent Projects
Portfolio of recent projects below are the credibility and quality work generated by Bina Rekayasa Anugrah.
Year Project Name Customer Project Value
2015 Construction Management for General Houses, West Java Region Kementerian PUPR IDR 1,088,373,000
Gas Distribution Network Installations (Kp. Melayu) 4 Km – Chartering PT. GPE (KSO
2016 PT. Rekayasa Industri IDR. 5,600,000,000
Individual)
2016 Task Force - Auger-Boring, Reaming, Cleaning and Pull Back with Casing 12in PT. Rekayasa Industri IDR. 1,695,000,000
2017 Construction Management for PSU Public Residential Region 1 (Sumatera Jawa Bali) Kementerian PUPR IDR. 1,998,647,700
Gas Distribution Network Installation/Development (West Java and Southern Sumatera
2017 PT.PGN IDR 1,600,000,000
Area)
Gas Distribution Network Installation (HDD, Auger, Zinker, and Branch Line) Depok,
2018 PT. PGN IDR 3,003,575,800
Sentul, and Tajur Area
East Connection Taxiway Phase I, Soekarno-Hatta Airport and Perimeter BRC Beva
2018 PT. Hutama Karya IDR 15,700,000,000
Mesh Fences
2018 Construction of Public Residential, Pondok Pesantren YASTI Sukabumi PT. Wijaya Karya IDR 4,369,444,200
PT. Jakarta International
2018 Management Construction for Warehouse Fire Prevention System IDR 275,000,000
Container Terminal
2018 Revitalization of POLRI Public Residential Area, Lebak, Pandeglang, and Serang Kementerian PUPR IDR 558,660,000
2018 Bridge and Emergency Stairs Construction, Teluk Naga PT. PLN (Persero) IDR 167,197,222
2018 Construction of Micro Hydro Power Plant, Gunung Wugul PT. Hutama Karya IDR 4,269,074,630
2019 IML and Reinstallation of Electric Panel Rusun Polres Probolinggo Kementerian PUPR IDR 170,000,000
2019 Repaint Public Housing Building, Rusun LIPI Cibinong - Jawa Barat Kementerian PUPR IDR 197,000,000
2019 Infiltration Wells and Revitalization of Public Housing, BMKG Tangerang Kementerian PUPR IDR 175,000,000
Design Furniture dan Ruang Arsip . Kejaksaan Agung Republik Indonesia - Bulungan
2019 Kejagung RI IDR 85,000,000
Jakarta Selatan
2019 Manual & Auger Boring Crossing Pipa Avlure to DPPU Soetta MCE IDR 687,500,000
Year Project Name Customer Project Value
East Connection Taxiway Phase I, Soekarno-Hatta Airport and Perimeter BRC Beva
2019 PT. Hutama Karya IDR 5,315,000,000
Mesh Fences
2019 Construction of Residential House, Aldena Residence Type 45 Aldena Residence IDR 4,095,000,000
PT. Jakarta International
2019 Installation and Design of Warehouse Fire Prevention System IDR 3,294,883,680
Container Terminal
2019 BRC Beva Mesh Fences Installation, Terminal 3 VVIP, Soekarno-Hatta Airport PT. Wijaya Karya IDR 1,478,000,000
2019 Construction of Athlete Residential Building, Jawa Timur Kementerian PUPR IDR 1,078,396,000
2019 Construction of Residential Building, YPPI Area II Malang, Jawa Timur Kementerian PUPR IDR 10,862,013,000
2019 Civil Works and Finishing, Steam Gas Power Plant (PLTGU) 275 MW, Riau PT. Hutama Karya IDR 5,508,384,700
Construction of Rest Area Building Type A, 2 Sides – Bakauheni – Terbanggi Besar Toll
2019 PT. PP (Persero) IDR 39,869,374,000
Road
TOTAL PROJECT VALUE IDR 113, 067,792,000
Ongoing Project
Portfolio of recent projects below are the credibility and quality work generated by Bina Rekayasa Anugrah.
Year Project Name Customer Project Value
2020 Earthworks, Junction Tebingtinggi Toll Road Project PT. Hutama Karya IDR 51,453,243,243
2020 Earthworks, Jakarta-Cikampek II Selatan Package III Toll Road Construction PT. Waskita Karya IDR 30,348,890,000
Earthworks and Civil Works, Shipper & Launcher Terminal Building Area, Cepu, Jawa
2020 PT. PGN Solution IDR 6,600,000,000
Tengah
TOTAL PROJECT VALUE IDR 88,402,133,243