S.n Item No Lengt Breadth Height/Dept Total Gran


o (Nomenclature) . h h d
Total
1. Excavation in
foundation in soft soil
up to 5’ and up to one
chain dressing, levelling,
compacting, etc.
complete.
F1 11 4’-0” 4’-0” 4’-0” 704 c.ft 1270
F2 3 3’-0” 3’-0” 4’-0” 108 c.ft c.ft
Outer wall 1 138’-0” 1’-6” 2’-0” 414 c.ft
Steps 1 4’-0” 3’-0” 0’-9” 9 c.ft
R.C.C Staircase 1 3’-6” 2’-0” 5’-0” 35 c.ft

2. P/L (Providing and


Laying) 1:4:8 concrete
base in foundation
dressing, levelling,
curing and compacting,
etc. complete.
F1 11 4’-0” 4’-0” 0’-6” 88 c.ft 213
F2 3 3’-0” 3’-0” 0’-6” 14 c.ft c.ft
Outer wall 1 138’-0” 1’-6” 0’-6” 104 c.ft
Steps 1 4’-0” 3’-0” 0’-3” 3 c.ft
R.C.C Staircase 1 3’-6” 2’-0” 0.5’ 4 c.ft

3a. P/L (Providing and


Laying) R.C.C 1:2:4
concrete base in
foundation, dressing,
levelling, curing,
compacting, etc.
complete.
F1 11 4’-0” 4’-0” 1’-0” 176 c.ft 210
F2 3 3’-0” 3’-0” 1’-0” 27 c.ft c.ft
R.C.C Staircase 1 2’-0” 3’-6” 1’-0” 7 c.ft

3b. P/L (Providing and


Laying) R.C.C concrete
base up to plinth
dressing, levelling,
curing, compacting, etc.
complete.
C1 11 1’-6” 0’-6” 3’-0” 25 c.ft 32 c.ft
C2 3 1’-0” 0’-6” 3’-0” 7 c.ft

S.n Item (Nomenclature) No. Length Breadth Height/Depth Total Grand


o Total
4. P/L (Providing and
laying) R.C.C plinth
beam up to plinth
levelling, curing,
dressing, compacting,
etc. complete.
P.B running length 1 244’-0” 0’-6” 1’-6” 183 c.ft 192
R.C.C Staircase 1 3’-0” 0’-9” 4’-0” 9 c.ft c.ft

5. Providing + Laying Block


Masonry (BM) 1:3:6 in
foundation and plinth
with joining mortar 1:6
levelling, dressing, etc.
complete.
Step 1: BM 1 138’-0” 1’-0” 0’-6” 69 c.ft 173
Step 2: BM 1 138’-0” 0’-6” 1’-6” 104 c.ft c.ft

6. P/L (Providing and


Laying) Earth filling with
sweet earth above 11”
thick compacting,
levelling, including
curing, etc complete.
R1 + R2 (Bedrooms) 2 13’-0” 11’-0” 0.92’ 263 c.ft 727
R3 (Drawing Room) 1 14’-0” 11’-0” 0.92’ 142 c.ft c.ft
R4 + R5 (Bath) 2 4’-0” 7’-0” 0.92’ 51 c.ft
R6 (Staircase + Lobby) 1 14’-0” 11’-0” 0.92’ 142 c.ft
R7 (Kitchen) 1 8’-0” 11’-0” 0.92’ 81 c.ft
R8 (Powder Room) 1 4’-0” 5’-0” 0.92’ 18 c.ft
R9 (Open-to-sky) 1 4’-0” 8’-0” 0.92’ 30 c.ft

7. P/L (Providing and


Laying) Stone soiling 6”
thick under the floors
levelling, dressing,
compacting, etc.
complete.
R1 + R2 (Bedrooms) 2 13’-0” 11’-0” 0’-6” 143 c.ft 395
R3 (Drawing Room) 1 14’-0” 11’-0” 0’-6” 77 c.ft c.ft
R4 + R5 (Bath) 2 4’-0” 7’-0” 0’-6” 28 c.ft
R6 (Staircase + Lobby) 1 14’-0” 11’-0” 0’-6” 77 c.ft
R7 (Kitchen) 1 8’-0” 11’-0” 0’-6” 44 c.ft
R8 (Powder Room) 1 4’-0” 5’-0” 0’-6” 10 c.ft
R9 (Open-to-sky) 1 4’-0” 8’-0” 0’-6” 16 c.ft

S.n Item (Nomenclature) No. Length Breadth Height/Depth Total Grand


o Total
8. P/L (Providing and
Laying) 1:2:4 concrete
2” under floor
compacting, dressing,
etc. complete.
R1 + R2 (Bedrooms) 2 13’-0” 11’-0” 0.16’ 46 c.ft 127
R3 (Drawing Room) 1 14’-0” 11’-0” 0.16’ 25 c.ft c.ft
R4 + R5 (Bath) 2 4’-0” 7’-0” 0.16’ 9 c.ft
R6 (Staircase + Lobby) 1 14’-0” 11’-0” 0.16’ 25 c.ft
R7 (Kitchen) 1 8’-0” 11’-0” 0.16’ 14 c.ft
R8 (Powder Room) 1 4’-0” 5’-0” 0.16’ 3.2 c.ft
R9 (Open-to-sky) 1 4’-0” 8’-0” 0.16’ 5.12 c.ft

9. P/L (Providing and


Laying) Porcelain tiles
flooring A grade matte
finish color and shade
approved by architect
compacting, dressing,
etc. complete.
R1 + R2 (Bedrooms) 2 13’-0” 11’-0” - 286 sq.ft 762
R3 (Drawing Room) 1 14’-0” 11’-0” - 154 sq.ft sq.ft
R4 + R5 (Bath) 2 4’-0” 7’-0” - 28 sq.ft
R6 (Staircase + Lobby) 1 14’-0” 11’-0” - 154 sq.ft
R7 (Kitchen) 1 8’-0” 11’-0” - 88 sq.ft
R8 (Powder Room) 1 4’-0” 5’-0” - 20 sq.ft
R9 (Open-to-sky) 1 4’-0” 8’-0” - 32 sq.ft

10. P/L (Providing and 1 224.5’ 0.5’ 7’-0” 785.75 786


Laying) C.C 1:3:6 (6” c.ft c.ft
BM) is s/s
(Superstructure)
including mortar 1:6 for
joining levelling,
dressing and curing, etc.
complete.
Deduction:
Door 1 7 3’-6” 0.5’ 7’-0” 86 c.ft 145
Door 2 3 2’-6” 0.5’ 7’-0” 26.25 c.ft c.ft
Windows 2 6’-0” 0.5” 4’-0” 24 c.ft
Ventilators 3 3’-0” 0.5’ 2’-0” 9 c.ft
786 c.ft – 145 c.ft = 641 c.ft
Total Block Masonry = 641 c.ft

S.n Item (Nomenclature) No. Length Breadth Height/Depth Total Grand


o Total
11. P/L (Providing and
Laying) R.C.C 1:2:4
column in
superstructure including
scaffolding, levelling,
curing, etc. complete.
C1 11 1’-6” 0.5’ 7’-0” 58 c.ft 69 c.ft
C2 3 1’-0” 0.5’ 7-0” 11 c.ft

12. P/L (Providing and 1 244’-0” 0.5’ 3’-0” 366 c.ft


Laying) R.C.C 1:2:4
beam, including
scaffolding, levelling,
curing, vibrating, etc.
complete.

13. P/L (Providing and 1 933 sq.ft 0.5’ 468 c.ft


Laying) slab including
scaffolding, levelling,
vibrating, dressing, etc.
complete.

14. P/L (Providing and 1 21’-0” 3’-0” 0.5’ 32 c.ft


Laying) R.C.C slab under
staircase 1:2:4 as per
plan including
scaffolding, levelling,
curing, compacting, etc.
complete.

15. P/A (Providing and


Applying) half inch thick
(1/4”) internal plaster
levelling over Block
Masonry and R.C.C
work, levelling,
dressing, curing, etc.
complete.
R1 (Bedroom) 1 48 r.ft (running feet) 10’-0” 480 sq.ft 3040
R2 (Bedroom) 1 48 r.ft (running feet) 10’-0” 480 sq.ft c.ft
R3 (Drawing Room) 1 50 r.ft (running feet) 10’-0” 500 sq.ft
R4 (Bath) 1 22 r.ft (running feet) 10’-0” 220 sq.ft
R5 (Bath) 1 22 r.ft (running feet) 10’-0” 220 sq.ft
R6 (Staircase + Lobby) 1 30 r.ft (running feet) 10’-0” 300 sq.ft
R7 (Kitchen) 1 42 r.ft (running feet) 10’-0” 420 sq.ft
R8 (Powder Room) 1 18 r.ft (running feet) 10’-0” 180 sq.ft
R9 (Open-to-sky) 1 24 r.ft (running feet) 10’-0” 240 sq.ft

S.n Item (Nomenclature) No. Length Breadth Height/Depth Total Grand


o Total
16. Providing and Fixing
ceramic glazed tiles up
to 7’ height in bathroom
dressing, laying, etc.
complete.

17. P/L (Providing and


Laying) ceramic glazed
tiles on bathroom floor
in dressing, laying,
compacting, etc.
complete.

18. P/A (Providing and


Applying) 3/8” thick 1:4
cement plaster over
ceiling, levelling,
dressing, curing, etc.
complete.
19. Proving and fixing
deodar wooden frames
including holdfast for
door and windows size
2”x7” dressing,
levelling, etc. complete.

20. Providing and Fixing


3”x1.5” wooden runner
shutters including fixing
of glass and fly-proofing
etc. complete.

S.n Item (Nomenclature) No. Length Breadth Height/Depth Total Grand


o Total

21. Providing and Fixing


solid core flush door
laminated with teak
veneer in position
during screwing in
proper position, etc.
complete.

22. P/A (Providing and


Applying) 3 course wax
polishing over
woodwork including
proper shade approved
by the architect, etc.
complete.
23. P/A (Providing and
Applying) 3 course
distemper paint over
ceiling with proper
base, etc. complete.

24. P/A (Providing and


Applying) 3 course
distemper paint over
internal walls with
proper base, etc.
complete.

S.n Item (Nomenclature) No. Length Breadth Height/Depth Total Grand


o Total
25. P/A (Providing and
Applying) 5/8” thick 1:4
cement plaster over
exterior walls, levelling,
dressing, etc. complete.

26. P/A (Providing and


Applying) distemper
paint over exterior
walls, levelling,
dressing, etc. complete.

27. Providing and Fixing


steel gate as per given
design by the architect
including fixing in
proper position,
painting, etc. complete.

28. P/L (Providing and


Laying) Under Ground
Water Tank as per given
size and location by the
architect of R.C.C wall
during complete
plastering inside and
outside including top,
etc. complete.

29. P/L (Providing and


Laying) Over Head
Water Tank as per given
size and location by the
architect of R.C.C wall
during complete
plastering inside and
outside including top,
etc. complete.