Date: 11/3/21 Time 11:00 AM Change Over plan From D-16mm CWR to Sq-12mm CWR

Timing Completion Progression


Job by CRANE - 1 (New Crane) Assigned Person Hazard Safety Measure
(In minute) Sequence (In Minute)
Follow Proper SOP, Follow of LOTO if there any,
Stand and By Pass Observe Human Movement, Dismantle all
LCS Operation 5 Arif
Movement Electrical, Mechanical, Hydraulic and Lubrication
1 5
connection

Lock all the hooks and slings properly, Follow


Rafiq, Kashem, Linkan, Casual Crane Movement, Falling
# 12 stand to stand 6 1 hazard
Human Movement underneath, Avoid walkway 2 11
for keeping stands and by pass
Lock all the hooks and slings properly, Follow
Rafiq, Kashem, Linkan, Casual Crane Movement, Falling
# 11 stand to stand 6 1 hazard
Human Movement underneath, Avoid walkway 3 17
for keeping stands and by pass
Lock all the hooks and slings properly, Follow
Rafiq, Kashem, Linkan, Casual Crane Movement, Falling
# 10 stand to stand 6 1 hazard
Human Movement underneath, Avoid walkway 4 23
for keeping stands and by pass
Lock all the hooks and slings properly, Follow
Rafiq, Kashem, Linkan, Casual Crane Movement, Falling
# 9 stand to stand 6 1 hazard
Human Movement underneath, Avoid walkway 5 29
for keeping stands and by pass
# Intermediate Mill all stand base frame greasing (Parallel Job) 10 Casual 1 Spillage Proper House Keeping
# Roughing Mill stock adjustment from beginning (Parallel Job) 10 Pannu Burn Hazard Use of Leather Hand gloves, Safety Goggles

# Intermediate Mill Sampling (motor needs to be given clearance after 15 minutes) 6 Rafiq, Delowar, Casual 1 Burn Hazard Use of Leather Hand gloves, Safety Goggles

Timing Completion Progression


Job by CRANE - 2
(In minute) Sequence (In Minute)

Follow Proper SOP, Follow of LOTO if there any,


Stand and By Pass Observe Human Movement, Dismantle all
LCS Operation 4 Raihan,
Movement Electrical, Mechanical, Hydraulic and Lubrication
1 4
connection

Lock all the hooks and slings properly, Follow


Rashed, Zahed, Casual 1 Crane Movement, Falling
# 19 stand to stand (Sampling to be done immediately after that) 5 hazard
Human Movement underneath, Avoid walkway 2 9
person, Kalam
for keeping stands and by pass
Lock all the hooks and slings properly, Follow
Amzad, Delowar, Casual 1, Crane Movement, Falling
# 15 stand to stand 5 hazard
Human Movement underneath, Avoid walkway 3 14
1 Person from WS
for keeping stands and by pass
Lock all the hooks and slings properly, Follow
Amzad, Delowar, Casual 1, Crane Movement, Falling
# 16 stand to stand 5 1 Person from WS hazard
Human Movement underneath, Avoid walkway 4 19
for keeping stands and by pass
Lock all the hooks and slings properly, Follow
Amzad, Delowar, Casual 1, Crane Movement, Falling
# 17 stand to stand 5 hazard
Human Movement underneath, Avoid walkway 5 24
1 Person from WS
for keeping stands and by pass
Lock all the hooks and slings properly, Follow
Rashed, Zahed, Casual 1 Crane Movement, Falling
# 18 stand to stand 5 hazard
Human Movement underneath, Avoid walkway 6 29
person, Kalam
for keeping stands and by pass
# F/mill All stand baseframe greasing (Parallel Job) 10 Casual 1 Spillage Proper House Keeping
Cutting Hazard, Burn
# Pass grinding of Finishing Mill and Roll Cross adjustment (Parallel Job) & 15,16 Sampling 25 Raihan, Kalam
Hazard
Use of Leather Hand gloves, Safety Goggles

Timing Completion Progression


Job by CRANE - 3
(In minute) Sequence (In Minute)
Follow Proper SOP, Follow of LOTO if there any,
Stand and By Pass Observe Human Movement, Dismantle all
LCS Operation (Parallel Job) 3 Ullash
Movement Electrical, Mechanical, Hydraulic and Lubrication
1 3
connection
Lock all the hooks and slings properly, Follow
# 3 slit QTB entry exit by pass funnel alignment, Cooler Replacement with QTB shifting and Zia, Masud, Casual 2 Crane Movement, Falling
20 person, Hashem 1 hazard
Human Movement underneath, Avoid walkway 2 23
position locking for keeping stands and by pass
Lock all the hooks and slings properly, Follow
Zia, Masud, Casual 2 Crane Movement, Falling
# 20 stand to stand 5 hazard
Human Movement underneath, Avoid walkway 3 28
person, Hashem 1
for keeping stands and by pass
Cutting Hazard, Burn
# F/Mill Checking, , Roll gap adjustment (1 min) Ghost Rolling (1min) 2 Amzad, Zahed, Hasan Use of Leather Hand gloves, Safety Goggles 4 30
Hazard
READY TO TAKE FIRST BILLET = 30