Sr. No.

Job Title Activities % Wt Last Wk

Cable pulling in basement upto TCC 4.30% 90.00%


Installation of Annunciator panels 2.15% 98.00%
Termination of cables in Genset
2.09% 25.00%
control panels
New annunciator
1
panel inside TCC Testing & Commissioning of cables in Genset
2.09% 0.00%
control panels
Interfacing annunciator panel with BMS 6.97% 0.00%
Configuration & programming BMS 4.18% 0.00%

Excavation for laying cable upto panel board 2.10% 99.00%


Form work in Abqaiq Yard 8.30% 100.00%
Replace Path lights Concrete Pouring for foundations in Abq. 9.00% 100.00%
2 in dark areas Ar- Road cutting & excavation along the road 2.75% 100.00%
Rabiyah Asphalting on road side 1.00% 100.00%
Excavation & installation of foundations 6.66% 99.00%
Installation of Gazeebo Lights 2.50% 0.00%

Replacing downlights with modified trims 30.00% 60%


Replacing troffer lights 30.00% 45%
Replace lights with Wall lights installation 2.30% 60%
3
LED at MAB New Trims fabrication completed in Riyadh

Approx. 1193 lights installed until now

Shop Drawings Approved 15.00% 100%


Final NMR-02 submittal 3.00% 100%

Replacement of Preparing IAP with SDEC 3.00% 100%


4 Obsolete Gen. at
DOHA 10.00% 100%
Ordering of major material from Saudi Diesel

As per rev. schedule provided by SDEC, 1st


delivery is on 30 Dec,2015
-

Laydown area 2.00% 100%


Upgrade Fire water Marking and layout 1.00% 100%
5 pump at North admin
Bldg 175 Excavation for footings 5.00% 0%
Overall Job
This Week Remarks/Material Status
%age

90% Annunciator panel arrived, installation completed


98% Honey well contacted already for configuration & programming of BMS
Sch:100.00%
25% Termination, programming balance, Caterpillar/Zahid Tractors to be contacted
to get verification for CIM

0% We are having problem with the termination of annunciator due


Act: 88% to compatibility issue(Non availability of dry contacts in existing genset)
0% Proposal for the connections have already been sent, Saudi Aramco is asking
0% for a solution other than VO

99% Lighting Poles delayed approx. 4 months due to SASO


100% Sch:97.09% Wall Mounted lights 2 shipments arrived already
100% concrete pouring and installation completed
100% Road side asphalting complete
100% Only Installation of lighting poles & gazebo lights balance
Act: 90.00%
99% Gazebo lights installation on-going
25%

72% 5 Shipments arrived. (1 air freight& 4 sea freight).


45% Sch: 78.83% All 6 shipments arrived
60% New trims fabrication completed
1798 lights received out of 2867 lights
45.60% Down-lights installation started again

100% Generators ordered. Expected ETA for 1st unit Sep 30. (could be delayed)
100% Sch: 25.28% Inspection level as per Saudi Aramco revision is Level-2
Third party has been contacted, PO released
100% Air Discharge attenuator issue to be discussed with SA.
Generator Buildings are not sound proof (4 generators)
100% Major material ordered already.
Act:26%
PIM conducted on 13th July.
Fabrication resumed after PIM,

100% Fire water pump submitted on 3rd June, approved on 12th July
Sch: 5.00%
100%
0% Act: 3.05 Dimensional discrepancy in the size of new fire pump rooms, already
highlighted to Saudi Aramco