COST EFFICIENT CONSTRUCTION 05/13/2021

TIM DIM SQUA DESCRIPTION

Concrete work for 15cm thick slab


4.78 slab between Axis 1& 2 , A & B
1 3.52
16.83 m2
4.8 slab between Axis 2& 3 , A & B
1 3.52
16.90 m
2

1 3.79 slab between Axis 3& 4 , A & B


3.52
13.34 m
2

1 3.84 slab between Axis 4 & 5 , A & B


2.65
10.18 m2
1 3.79 slab between Axis 5 & 6 , A & B
3.52
13.34 m2
4.8 slab between Axis 6 & 7 , A & B
1 3.52
16.90 m
2

4.78 slab between Axis 7 & 8 , A & B


1 3.52
16.83 m
2

4.78 slab between Axis 1& 2 , B & C


1 4.98
23.80 m
2

4.8 slab between Axis 2& 3 , B & C


1 4.98
23.90 m
2

1 3.79 slab between Axis 3& 4 , B & C


4.98
18.87 m
2

1 3.79 slab between Axis 5 & 6 , B & C


4.98
18.87 m
2

4.8 slab between Axis 6 & 7 , B & C


1 4.98
23.90 m
2

4.78 slab between Axis 7 & 8 , B & C


1 4.98
23.80 m
2

4.8 cantiliver slab between Axis 2 & 3, 6 & 7

INSTRUCTORS
EIABC Mr. EARMIAS & 1
Mr. ALEMAYEHU
COST EFFICIENT CONSTRUCTION 05/13/2021

1 4.98
23.90 m2
TIM DIM SQUA DESCRIPTION
4.78 slab between Axis 7 & 8 , B & C
1 4.98
23.80 m2
Total Area of slab concrete work
285.17 m2
4 but total story of the building is G+4 their fore total qty is
1140.70 m
2

Formwork for Slabs


4.78 Formwork between Axis 1& 2 , A & B
1 3.52
16.83 m2
4.8 Formwork between Axis 2& 3 , A & B
1 3.52
16.90 m2
1 3.79 Formwork between Axis 3& 4 , A & B
3.52
13.34 m2
1 3.84 Formwork between Axis 4 & 5 , A & B
2.65
10.18 m2
1 3.79 Formwork between Axis 5 & 6 , A & B
3.52
13.34 m2
4.8 Formwork between Axis 6 & 7 , A & B
1 3.52
16.90 m
2

4.78 Formwork between Axis 7 & 8 , A & B


1 3.52
16.83 m
2

4.78 Formwork between Axis 1& 2 , B & C


1 4.98
23.80 m2
4.8 Formwork between Axis 2& 3 , B & C
1 4.98
23.90 m2
1 3.79 Formwork between Axis 3& 4 , B & C
4.98
18.87 m
2

1 3.79 Formwork between Axis 5 & 6 , B & C


4.98
18.87 m
2

INSTRUCTORS
EIABC Mr. EARMIAS & 2
Mr. ALEMAYEHU
COST EFFICIENT CONSTRUCTION 05/13/2021

4.8 Formwork between Axis 6 & 7 , B & C


1 4.98
23.90 m2
TIM DIM SQUA DESCRIPTION

4.78 Formwork between Axis 7 & 8 , B & C


1 4.98
23.80 m2
4.8 cantiliver slab Formwork between Axis 2 & 3, 6 & 7
1 4.98
23.90 m2
4.78 Formwork between Axis 7 & 8 , B & C
1 4.98
23.80 m
2

Total Area of slab Formwork work


285.17 m2
4 but total story of the building is G+4 their fore total qty is
1140.70 m2
plastering work
4.78 plastering work Axis 1& 2 , A & B
1 3.52
16.83 m
2

4.8 plastering work between Axis 2& 3 , A & B


1 3.52
16.90 m
2

1 3.79 plastering work between Axis 3& 4 , A & B


3.52
13.34 m
2

1 3.84 plastering work between Axis 4 & 5 , A & B


2.65
10.18 m
2

1 3.79 plastering work between Axis 5 & 6 , A & B


3.52
13.34 m2
4.8 plastering work between Axis 6 & 7 , A & B
1 3.52
16.90 m
2

4.78 plastering work between Axis 7 & 8 , A & B


1 3.52
16.83 m
2

4.78 plastering work between Axis 1& 2 , B & C


1 4.98

INSTRUCTORS
EIABC Mr. EARMIAS & 3
Mr. ALEMAYEHU
COST EFFICIENT CONSTRUCTION 05/13/2021

23.80 m2
4.8 plastering work between Axis 2& 3 , B & C
1 4.98
23.90 m
2

TIM DIM SQUA DESCRIPTION


1 3.79 plastering work between Axis 3& 4 , B & C
4.98
18.87 m2
1 3.79 plastering work between Axis 5 & 6 , B & C
4.98
18.87 m
2

4.8 plastering work between Axis 6 & 7 , B & C


1 4.98
23.90 m
2

4.78 plastering work between Axis 7 & 8 , B & C


1 4.98
23.80 m
2

4.8 cantiliver slab plastering work between Axis 2 & 3, 6 & 7


1 4.98
23.90 m
2

4.78 plastering work between Axis 7 & 8 , B & C


1 4.98
23.80 m
2

Total Area of slab plastering work


285.17 m2
4 but total story of the building is G+4 their fore total qty is
1140.70 m
2

painting work
4.78 painting work Axis 1& 2 , A & B
1 3.52
16.83 m2
4.8 painting work between Axis 2& 3 , A & B
1 3.52
16.90 m
2

1 3.79 painting work between Axis 3& 4 , A & B


3.52
13.34 m2
1 3.84 painting work between Axis 4 & 5 , A & B
2.65
10.18 m2
1 3.79 painting work between Axis 5 & 6 , A & B

INSTRUCTORS
EIABC Mr. EARMIAS & 4
Mr. ALEMAYEHU
COST EFFICIENT CONSTRUCTION 05/13/2021

3.52
13.34 m2
4.8 painting work between Axis 6 & 7 , A & B
1 3.52
16.90 m2

TIM DIM SQUA DESCRIPTION

4.78 painting work between Axis 7 & 8 , A & B


1 3.52
16.83 m
2

4.78 painting work between Axis 1& 2 , B & C


1 4.98
23.80 m
2

4.8 painting work between Axis 2& 3 , B & C


1 4.98
23.90 m
2

1 3.79 painting work between Axis 3& 4 , B & C


4.98
18.87 m
2

1 3.79 painting work between Axis 5 & 6 , B & C


4.98
18.87 m
2

4.8 painting work between Axis 6 & 7 , B & C


1 4.98
23.90 m2
4.78 painting work between Axis 7 & 8 , B & C
1 4.98
23.80 m2
4.8 cantiliver slab painting work between Axis 2 & 3, 6 & 7
1 4.98
23.90 m2
4.78 painting work between Axis 7 & 8 , B & C
1 4.98
23.80 m
2

Total Area of slab painting work


285.17 m2
4 but total story of the building is G+4 their fore total qty is
1140.70 m2

INSTRUCTORS
EIABC Mr. EARMIAS & 5
Mr. ALEMAYEHU
Cost efficient project 05/13/2021

BAR SCHEDULE FOR Solid slab


TOTAL LENGTH OF BAR BASED ON DIAMETR(m)
structural element Location Type Ref Bar Dia Length No of bar No of member Total No of bar Dia Dia Dia Dia Dia Dia Dia
of bar No Shape (pcs) (pcs) (pcs) 6 8 10 12 14 16 20 Remark
SLABS First floor
First floor
BAR-1
Between axis A,B & 1-3, 6-8 First floor Main 10 3.5 144 1 144 504
Between axis A,B & 3-6 First floor Main 10 3.5 84 1 84 294
BAR-2 First floor
Between axis A,B & 1-3, 6-8 First floor Main 10 5.05 144 1 144 727.2
Between axis A,B & 3-4,5-6 First floor Main 10 5.05 56 1 56 282.8
BAR-3
Between axis A,B & 1-3, 6-8 First floor Negative 12 1.6 160 1 160 256
Between axis A,B & 3-4,5-6 First floor Negative 12 1.6 64 1 64 102.4
BAR-4
B/n Axis-A,B & 0N Axis 4&5 First floor Negative 10 0.9 54 1 54 48.6
BAR-5 First floor
B/n Axis A,B 0N Axis 2,3,6&7 First floor Negative 12 2 108 1 108 216
B/n Axis B,C 0N Axis 2,3,6&7 First floor Negative 12 2 152 1 152 304
BAR-6
B/n Axis A,B 0N Axis 1 & 8 First floor Negative 10 1.24 108 1 108 133.92
B/n Axis B,C 0N Axis 1 & 8 First floor Negative 10 1.24 152 1 152 188.48
BAR-7
0N Axis A B/n axis 1-3, 6-8 First floor Negative 10 1.24 152 1 152 188.48
0N Axis B B/n axis 1-3, 6-8 First floor Negative 10 1.24 152 1 152 188.48
0N Axis A B/n axis 3-4, 5-6 First floor Negative 10 1.24 60 1 60 74.4
0N Axis B B/n axis 3-4, 5-6 First floor Negative 10 1.24 60 1 60 74.4 74.4
TOTAL LENGTH OF BARS 0 0 2705 953 0 0 0
UNIT WEGHT (KG/M) 0.222 0.395 0.617 0.888 1.209 1.586 2.469
TOTAL WEGHT (KG) 0 0 1669 846 0 0 0
but total story of the building is G+4 their fore total qty is 4 0 0 6675.348 3384.346 0 0 0

INSTRUCTORS
EIABC Mr. Earmias 6
Mr. Alemayehu
Cost efficient project 05/13/2021

INSTRUCTORS
EIABC Mr. Earmias 7
Mr. Alemayehu
Cost efficient project 05/13/2021

TIM DIM SQUA DESCRIPTION


Ribbed beam
3.68 Ribbed beam between Axis A, B &1-4,5-8
38 1
139.84 m
5.14 Ribbed beam between Axis B, C &1-4,5-8
38 1
195.32 m
8 1.13 Ribbed beam at
1 cantiliver slab between Axis 2 & 3, 6 & 7
9.04 m
4.04 Ribbed beam between Axis A, B & 4,5
4 1
16.16 m
Total Ribbed beam
360.36
4 but total story of the building is G+4 their fore total qty is
1441.44 m
2. Ribbed block work for Ribbed slab
3.52 Ribbed block between Axis A, B &1-4,5-8
44 0.5
77.44 m2
4.98 Ribbed block between Axis B, C &1-4,5-8
44 0.5
109.56 m
2

16 1.13 Ribbed block at


0.5 cantiliver slab between Axis 2 & 3, 6 & 7
9.04 m
2

3.84 Ribbed block between Axis A, B & 4,5


4 0.5
7.68 m
2

T0tal Ribbed block


203.72 m2
4 but total story of the building is G+4 their fore total qty is
814.88 m2
Concrete work for 6cm thick concrete cover
4.78 concrete work between Axis 1& 2 , A & B
1 3.52
16.83 m2
4.8 concrete work between Axis 2& 3 , A & B
1 3.52
16.90 m2
1 3.79 concrete work between Axis 3& 4 , A & B
3.52
INSTRUCTORS
EIABC Mr. Earmias 8
Mr. Alemayehu
Cost efficient project 05/13/2021

13.34 m2
TIM DIM SQUA DESCRIPTION
1 3.84 concrete work between Axis 4 & 5 , A & B
2.65
10.18 m2
1 3.79 concrete work between Axis 5 & 6 , A & B
3.52
13.34 m2
4.8 concrete work between Axis 6 & 7 , A & B
1 3.52
16.90 m2
4.78 concrete work between Axis 7 & 8 , A & B
1 3.52
16.83 m2
4.78 concrete work between Axis 1& 2 , B & C
1 4.98
23.80 m
2

4.8 concrete work between Axis 2& 3 , B & C


1 4.98
23.90 m
2

1 3.79 concrete work between Axis 3& 4 , B & C


4.98
18.87 m2
1 3.79 concrete work between Axis 5 & 6 , B & C
4.98
18.87 m2
4.8 concrete work between Axis 6 & 7 , B & C
1 4.98
23.90 m2
4.78 concrete work between Axis 7 & 8 , B & C
1 4.98
23.80 m2
4.8 concrete work at cantiliver between Axis 2 & 3, 6 & 7
1 4.98
23.90 m2
4.78 concrete work between Axis 7 & 8 , B & C
1 4.98
23.80 m2
Total Area of concrete work Ribbed slab

285.17 m2
4 but total story of the building is G+4 their fore total qty is
1140.70 m2

INSTRUCTORS
EIABC Mr. Earmias 9
Mr. Alemayehu
Cost efficient project 05/13/2021

TIM DIM SQUA DESCRIPTION


plastering work
4.78 plastering work Axis 1& 2 , A & B
1 3.52
16.83 m
2

4.8 plastering work between Axis 2& 3 , A & B


1 3.52
16.90 m
2

1 3.79 plastering work between Axis 3& 4 , A & B


3.52
13.34 m
2

1 3.84 plastering work between Axis 4 & 5 , A & B


2.65
10.18 m
2

1 3.79 plastering work between Axis 5 & 6 , A & B


3.52
13.34 m
2

4.8 plastering work between Axis 6 & 7 , A & B


1 3.52
16.90 m
2

4.78 plastering work between Axis 7 & 8 , A & B


1 3.52
16.83 m
2

4.78 plastering work between Axis 1& 2 , B & C


1 4.98
23.80 m2
4.8 plastering work between Axis 2& 3 , B & C
1 4.98
23.90 m2
1 3.79 plastering work between Axis 3& 4 , B & C
4.98
18.87 m
2

1 3.79 plastering work between Axis 5 & 6 , B & C


4.98
18.87 m
2

4.8 plastering work between Axis 6 & 7 , B & C


1 4.98
23.90 m
2

4.78 plastering work between Axis 7 & 8 , B & C


1 4.98
INSTRUCTORS
EIABC Mr. Earmias 10
Mr. Alemayehu
Cost efficient project 05/13/2021

23.80 m
2

TIM DIM SQUA DESCRIPTION


4.8 cantiliver slab plastering work between Axis 2 & 3, 6 & 7
1 4.98
23.90 m
2

4.78 plastering work between Axis 7 & 8 , B & C


1 4.98
23.80 m
2

Total Area of slab plastering work


285.17 m2
4 but total story of the building is G+4 their fore total qty is
1140.70 m2
painting work
4.78 painting work Axis 1& 2 , A & B
1 3.52
16.83 m
2

4.8 painting work between Axis 2& 3 , A & B


1 3.52
16.90 m
2

1 3.79 painting work between Axis 3& 4 , A & B


3.52
13.34 m
2

1 3.84 painting work between Axis 4 & 5 , A & B


2.65
10.18 m
2

1 3.79 painting work between Axis 5 & 6 , A & B


3.52
13.34 m2
4.8 painting work between Axis 6 & 7 , A & B
1 3.52
16.90 m2
4.78 painting work between Axis 7 & 8 , A & B
1 3.52
16.83 m2
4.78 painting work between Axis 1& 2 , B & C
1 4.98
23.80 m2
4.8 painting work between Axis 2& 3 , B & C
1 4.98
23.90 m
2

INSTRUCTORS
EIABC Mr. Earmias 11
Mr. Alemayehu
Cost efficient project 05/13/2021

1 3.79 painting work between Axis 3& 4 , B & C


4.98
18.87 m
2

TIM DIM SQUA DESCRIPTION


1 3.79 painting work between Axis 5 & 6 , B & C
4.98
18.87 m2
4.8 painting work between Axis 6 & 7 , B & C
1 4.98
23.90 m2
4.78 painting work between Axis 7 & 8 , B & C
1 4.98
23.80 m
2

4.8 cantiliver slab painting work b/n Axis 2-3,6-7


1 4.98
23.90 m
2

4.78 painting work between Axis 7 & 8 , B & C


1 4.98
23.80 m
2

Total Area of slab painting work


285.17 m2
4 but total story of the building is G+4 their fore total qty is
1140.70 m2

INSTRUCTORS
EIABC Mr. Earmias 12
Mr. Alemayehu
Cost efficient project 05/13/2021

BAR SCHEDULE FOR RIBBED SLAB


TOTAL LENGTH OF BAR BASED ON DIAMETR(m)
structural element Location Type Ref Bar Dia Length No of bar No of member Total No of bar Dia Dia Dia Dia Dia Dia Dia
of bar No Shape (pcs) (pcs) (pcs) 6 8 10 12 14 16 20.00 Total weght

BAR-e
On Axis-A, b/n 1-2 & 7-8 1/FF-4/FF Negative 12 20.25 14 1 14 283.5
BAR-e
On Axis-A, b/n 3-4 & 5-6 1/FF-4/FF Negative 12 20.25 10 1 10 202.5
BAR-a
ON Axis-A, b/n 2-3 & 6-7 1/FF-4/FF Negative 12 34.55 14 2 28 967.4
BAR-d
On Axis-B, b/n 1-4 & 5-8 1/FF-4/FF Negative 12 26.9 38 2 76 2044.4
BAR-b
On Axis-C, b/n 1-4 & 5-8 1/FF-4/FF Negative 12 23.15 38 1 38 879.7
BAR-c
On Axis-4& 5 b/n A & B 1/FF-4/FF Negative 12 13.25 8 1 8 106
TOTAL LENGTH OF BARS 0 0 0 4484 0 0 0
UNIT WEGHT (KG/M) 0.222 0.395 0.617 0.888 1.209 1.586 2.469
TOTAL WEGHT (KG) 0 0 0 3981 0 0 0 3981
but total story of the building is G+4 their fore total qty is 4 0 0 0 15925.392 0 0 0 3981.348

INSTRUCTORS
EIABC Mr. Earmias 13
Mr. Alemayehu
Cost efficient project 05/13/2021

INSTRUCTORS
EIABC Mr. Earmias 14
Mr. Alemayehu
Cost efficient project 05/13/2021

TIM DIM SQUA DESCRIPTION


22cm thick Rc. Precast Slab Pannels
5.08 slab between Axis 1& 2 , A & B
1 3.82
19.41 m
2

5.1 slab between Axis 2& 3 , A & B


1 3.82
19.48 m
2

1 4.09 slab between Axis 3& 4 , A & B


3.82
15.62 m
2

1 4.14 slab between Axis 4 & 5 , A & B


2.95
12.21 m
2

1 4.09 slab between Axis 5 & 6 , A & B


3.82
15.62 m
2

5.1 slab between Axis 6 & 7 , A & B


1 3.82
19.48 m
2

5.08 slab between Axis 7 & 8 , A & B


1 3.82
19.41 m2
5.08 slab between Axis 1& 2 , B & C
1 5.28
26.82 m2
5.1 slab between Axis 2& 3 , B & C
1 5.28
26.93 m
2

1 4.09 slab between Axis 3& 4 , B & C


5.28
21.60 m
2

1 4.09 slab between Axis 5 & 6 , B & C


5.28
21.60 m
2

5.1 slab between Axis 6 & 7 , B & C


1 5.28
26.93 m
2

5.08 slab between Axis 7 & 8 , B & C


1 5.28
26.82 m
2

5.1 cantiliver slab between Axis 2 & 3, 6 & 7

INSTRUCTORS
EIABC Mr. Earmias 15
Mr. Alemayehu
Cost efficient project 05/13/2021

1 5.28
26.93 m2
TIM DIM SQUA DESCRIPTION
5.08 slab between Axis 7 & 8 , B & C
1 5.28
26.82 m
2

Total Area of Rc. Precast T-slab


325.68 m2
4 but total story of the building is G+4 their fore total qty is
1302.71 m2
painting work
4.78 painting work Axis 1& 2 , A & B
1 3.52
16.83 m
2

4.8 painting work between Axis 2& 3 , A & B


1 3.52
16.90 m2
1 3.79 painting work between Axis 3& 4 , A & B
3.52
13.34 m2
1 3.84 painting work between Axis 4 & 5 , A & B
2.65
10.18 m
2

1 3.79 painting work between Axis 5 & 6 , A & B


3.52
13.34 m
2

4.8 painting work between Axis 6 & 7 , A & B


1 3.52
16.90 m
2

4.78 painting work between Axis 7 & 8 , A & B


1 3.52
16.83 m
2

4.78 painting work between Axis 1& 2 , B & C


1 4.98
23.80 m
2

4.8 painting work between Axis 2& 3 , B & C


1 4.98
23.90 m
2

1 3.79 painting work between Axis 3& 4 , B & C


4.98
18.87 m2
1 3.79 painting work between Axis 5 & 6 , B & C
4.98
INSTRUCTORS
EIABC Mr. Earmias 16
Mr. Alemayehu
Cost efficient project 05/13/2021

18.87 m
2

4.8 painting work between Axis 6 & 7 , B & C


1 4.98
23.90 m2
TIM DIM SQUA DESCRIPTION
4.78 painting work between Axis 7 & 8 , B & C
1 4.98
23.80 m
2

4.8 cantiliver slab painting work b/n Axis 2-3, 6-7


1 4.98
23.90 m
2

4.78 painting work between Axis 7 & 8 , B & C


1 4.98
23.80 m
2

Total Area of slab painting work


285.17 m
2

4 but total story of the building is G+4 their fore total qty is
1140.70 m2

INSTRUCTORS
EIABC Mr. Earmias 17
Mr. Alemayehu
Cost efficient project 05/13/2021

INSTRUCTORS
EIABC Mr. Earmias 18
Mr. Alemayehu
Cost efficient project 05/13/2021

INSTRUCTORS
EIABC Mr. Earmias 19
Mr. Alemayehu
Cost efficient project 05/13/2021

INSTRUCTORS
EIABC Mr. Earmias 20
Mr. Alemayehu
Cost efficient project 05/13/2021

INSTRUCTORS
EIABC Mr. Earmias 21
Mr. Alemayehu
Cost efficient project 05/13/2021

ProjectFLOOR SLAB
Date -11/20/2020
Client:GROUP MEMBERS
BILL OF QUANTITIES(BOQ)
ITEM DESCRIPTION UNIT QTY RATE(ETB) AMOUNT
SOLID SLAB
1 Concrete work cast in situ
1.1 total concrete for rc slab of the m2 1140.70 690.00 ETB 787,081.34
the whole story Blg C-25
1.2 Formwork 2cm thick timber
1.2.1 The rate of the formwork is including
whole the formwork and escafolding m2 1140.70 1600.00 ETB 1,825,116.16
1.3 Reinforcement work
1.3.1 total dia 12mm bar kg 6675.35 55.00 ETB 367,144.12
1.3.2 ditu but dia 10mm bar kg 3384.35 59.00 ETB 199,676.39
1.4 Finishing work
1.4.1 Plastering, Two Coats m2 1140.70 216 ETB 246,390.68
Cement/Sand Mortar (1:4)
1.4.2 Final Coat quartz paint m2 1140.70 105.31 ETB 120,131.14
Total cost for Solid slab ETB 3,545,539.84
2 RIBBED SLAB
2.1 Precast beam for Ribbed slab m 1441.44 414.00 ETB 596,756.16
2.2 Ribbed block with 24 cm thick m 2
814.88 302.00 ETB 246,093.76
2.3 C-25 concrete for topping after m2 1140.70 432 ETB 492,781.36
the ribbed block with 6cm thick
for the whole 4 story BLG
2.4 Reinforcement work
2.4.1 total dia 12mm bar kg 15925 55.000 ETB 875,896.56
2.5 Finishing work
2.5.1 Plastering, Two Coats m2 1140.70 201.00 ETB 229,280.22
Cement/Sand Mortar (1:4)
2.5.2 Final Coat quartz paint m2 1140.70 105.31 ETB 120,131.14
Total cost for ribbed slab ETB 2,560,939.20
3 PRECAST PANNEL
3.1 Precast panel m2 1302.71 1924.00 ETB 2,506,413.27
3.2 Finishing work
3.3.1 Final Coat quartz paint m2 1140.70 105.31 ETB 120,131.14
total cost for precast slab ETB 2,626,544.41