New Rice Mill Project PT - Padi Flour Nusantara Mojokerto - Indonesia
New Rice Mill Project PT - Padi Flour Nusantara Mojokerto - Indonesia
12
WEEKLY REPORT
MAIN CONTRACT WORKS
NO. 013
27th May –02nd June 2019
CONTENTS
1|PT. SINAR GUNUNG SEJATI
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.12
1. Executive Summary
( Completed and on-going Major Critical Works )
A. Production Building
1) Completed Work :
Excavation Wet Process area in
Installation Rebar Boiler, F3, F5, F7, and F8
Casting Concrete F3, F5, F7, and F8
Erection Main Frame ( Rafter R1, Rafter R2, Steel Column SC1, Steel Column
SC2A) at Zone C as grid J1-B1 in
Connecting Steel Beam (SB1) to Steel Column (SC1) Zone A without 100% of
torque at Zone B as grid P-J1 in
Excavation F5 at grid Q1-P
2) On-going :
Casting Slab Pit Bottom Slab Daily Bin 22nd Mei 2019
3) On- Schedule :
Back Filling with imported Material at Zone C as grid 32A-39A;B1-D1 30th
May 2019
Disposal Pile Concrete to elevation ground Slab in 09th June 2019
Back Filling with imported material at Zone A as grid 37A-39A;Q1-S1 09th
June 2019
Casting Slab Pit Bottom Slab Daily Bin 22nd Mei 2019
Install form work PC and F3 wet process area at Zone B 15 th June 2019
Fabrication and installation rebar
2) On-going
Installation Anchor Bolt
Re-install rear canopy
3) On-schedule
Casting Concrete Footplate and Foundation 27th May 2019
Un-install Roof at Grid F1 – F14 depend of FAMSUN tools
Installation Anchor Bolt 26th May 2019
Re-install rear canopy 26th May 2019
Chiping Slab Grid F13-F23 10TH June 2019
C. Intake Building
1) Completed Work :
2) On-going
Casting lean concrete at Pit area
Fabrication Rebar Pit and Foundation
Install Form work side of Wall Pit
Disposal existing rigid concrete
3) On-Schedule
Casting Slab 1 Bottom of Pit Intake 28th May 2019
Excavation Foundation Grid 28A - 31 A 28th May 2019
Excavation Dock Area 29th May 2019
D. Silo
1) Completed work :
2) On- going :
Sundries Construction Join Inc. Filler
E. Office Building
1) Completed work :
Rebar fabrication
Installing bottom rebar Continues Footing and Footplate at grid 37A - 38 A
Installing Tie Beam rebar at grid 37A – 38 A
2) On- going :
Casting Concrete Continues Footing
Casting Tiebeam Concrete
Fabrication and Installation Column Rebar and Balk at Ground Flour
Casting Column Rebar Ground Flour
3) On-Schedule :
Installation Form work and Support Column and Balk
Casting Concrete Column 1st Floor
Casting Balk concrete 1st Floor
Installation Rebar column 1st Floor
Install Deck Slab GF
F. WWTP
1) Completed work :
Excavation at Zone 1
Excavation at Zone 3
Excavation at Zone 2
Anti-termite Zone 1
2) On- going :
Anti-termite Zone 3
Anti-termite Zone 2
Back Filling to Elevation of Bottom Slab with imported material at Grid W1-
W3 ; WB-WG
Compacted and CBR 80% at Zone 1-3 , Grid W1-W3 ; WB-WG
Casting LC at Zone 1-3 Grid W1-W3 ; WB-WG
Fabrication Bottom Rebar and Retaining Wall Zone 1&3
3) On-Schedule :
Installation Rebar of Retaining Wall and Ground Slab
Casting Slab Concrete ( Bottom of Pit ) at Zone 1&3
Installation Retaining wall form work at Zone 1
5. Bill 06 Silo :
1) Perubahan elevasi pada embedded plate akibat tingginya slab existing pada saat setelah
pengecoran, gambar permohonan elevasi embedded plate pada Shop drawing ( SGS – STR –
CL-1024-E, SGS – STR – CL-1024-F, SGS – STR – CL-1024-G, SGS – STR – CL-1024-H)
,perubahan berdasarkan Reverensi Shop Drawing ( SGS – STR – CL-1024) dan RFI no. RFI-
SGS-013
2) Adjustable elevasi pada pedestal diarea Production Building, berkaitan dengan posisi frame
Clading agar sejajar dengan frame lainnya (SGS – STR – BP – 1008 ,1003,1004,1005)
3) SI additional work ( WWTP, Office, Car Park, Motorcycle Park, PLN Substation, Pump Room,
Weight Bridge, Waste Storage ) berdasarkan S.I No : 3637/SGS/003
*lampiran 01
4) Permit Excavation Warehouse, Excavation WWTP, Excavation Intake Building, Excavation
Office area, Installation Rebar Office Still not Ready.
a. Production Building
COMPLETE
ON-GOING
ON-SCHEDULE
b. Warehouse
COMPLETE
ON-GOING
ON-SCHEDULE
c. Silo
COMPLETE
ON-GOING
d. Intake
COMPLETE
ON-GOING
ON-SCHEDULE
10 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10
e. WWTP
COMPLETE
ON-GOING
ON-SCHEDULE
f. Office
COMPLETE
ON-GOING
ON-SCHEDULE
11 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10
COMPLETE
ON-GOING
ON-SCHEDULE
12 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10
COMPLETE
ON-GOING
ON-SCHEDULE
13 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10
COMPLETE
ON-GOING
ON-SCHEDULE
14 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10
COMPLETE
ON-SCHEDULE
UJ
15 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10
COMPLETE
ON-GOING
ON-SCHEDULE
3.3 SILO
EEE3
ZONA A
COMPLETED
SLAB ZONE A COMPLETE
ON-GOING
SLAB ZONE B
ZONA C1
FINNISH SLAB
ZONE C1
ZONA C2
FINNISH SLAB
ZONE C2
16 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10
ON-GOING
17 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10
3.4 OFFICE
COMPLETE
ON-GOING
B. Excavation and LC ( Office Building )
ON-SCHEDULE
18 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10
3.5 WWTP
A. Excavation WWTP
COMPLETE
ON-GOING
ON-SCHEDULE
COMPLETE
ON-GOING
ON-SCHEDULE
19 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO
4. PROGRESS PERFORMANCE
3.6 INTAKE BUILDING
20 | P T . S I N A R G U N U N G S E J A T I
D0P3A2neviati.69rgslctu
o%
WEEKLY PROGRESS REPORT NO.10
COMPLETE
ON-GOING
ON-SCHEDULE
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10
21 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10
Warehouse Area :
Office Area :
22 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10
WWTP area :
Filling with imported material on the top ground with 500mm layer, compacted CBR
min 80% at Zone 2
Start Casting concrete LC with fc 15 Mpa
Preparation Casting concrete for Backwall with fc 30 Mpa’ (incl. Integral)
Fabrication rebar for foundation and Water Wall
Fabrication formwork pit area, footplate, and pedestal column
23 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10
6. Progress Photo
24 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10
6.3 WWTP
25 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10
26 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10
6.5 FG Warehouse
27 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10
7. 3D PROGRESS VIEW
COMPLETE
ON-GOING
ON-SCHEDULE
COMPLETE
ON-GOING
ON-SCHEDULE
28 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10
29 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10
30 | P T . S I N A R G U N U N G S E J A T I
DDDV NEW RICE FLOUR MILL PROJECT – MOJOKERTO WEEKLY PROGRESS REPORT NO.10
31 | P T . S I N A R G U N U N G S E J A T I