March 2020
April 2020
We set the piers, foundation support, and the floor on the first weekend.
The second weekend we were able to raise the external walls.
The third weekend we were able to finish the roof.
The next weekend we did the sheeting on the sides.
May 2020
We worked only the first weekend and finished the interior walls.
We also finished the sheeting on the front.
June 2020
July 2020
We spent most of August and into September tiling the shower and the toilet area.
October 2020
Hallway Cabinets with lots of
Before we closed the cabin for the winter, we demolished
storage
the old bathroom and opened the wall to the cabin.
March 2021
We started our demo and pocket doors for the bedrooms.
April 2021
Flooring started.
May 2021
Cabinets started.
Finish work and trim is started.
Conclusion
This project has run without many delays. We were able complete things ahead of our planned completion date of fall of 2021. The
bathroom is usable now and everyone is very happy with what has been done.
Recommendation
We will be able to finish this in the next couple of weeks. Our biggest problem is finishing this while everyone is using the bathroom.