### June-2021
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
Project Lead: David A. Ferreira, S.T. W22 W23 W24
Project Budget: Estimated: $0.00 | Baseline: $0.00 | Task Costs: Estimated: $52.00 | Baseline: $0.00 | Actual: $0.00 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
WBS Task Name Priority Resource Start Finish Duration Done Percent
M T W T F S S M T W T F S S M T W T
Complete
u 1 PEKERJAAN ARCHITECTURE NORMAL Fri 04-Jun-21 Fri 11-Jun-21 12 0% PEKERJAAN ARCHITECTU
u 1.1 Pasang Keramik Lantai NORMAL Siku, Jony Fri 04-Jun-21 Thu 10-Jun-21 5 0% Pasang Keramik Lanta
u 1.2 Pasang Batako Tebal 30 cm (PR5) NORMAL Jony, Siku Wed 09-Jun-21 Thu 10-Jun-21 2 0% Pasang Batako Tebal
Pemasangan Atap Reservoir (Steel Frame with Fiber Pemasangan Atap Rese
u 1.3
Sheet)
NORMAL July, Aldo Sat 05-Jun-21 Wed 09-Jun-21 3 0%
u 1.4 Pembersihan dan Pengecatan Bak Reservoir NORMAL Aldo, July Thu 10-Jun-21 Fri 11-Jun-21 2 0% Pembersihan dan Peng
u 2 PEKERJAAN MECHANICAL FACILITIES NORMAL Fri 04-Jun-21 Mon 07-Jun-21 2 0% PEKERJAAN MECHANICAL
u 3 PEKERJAAN RAINWATER NETWORK NORMAL Mon 07-Jun-21 Fri 11-Jun-21 6 0% PEKERJAAN RAINWATER
u 3.1 Instal Pipa Drainase Dia. 20cm to Pipe Culvert NORMAL Jony, Siku, Quibe Mon 07-Jun-21 Wed 09-Jun-21 3 0% Instal Pipa Drainase
u 3.2 Lanjutan Pasang Batako Bak Kontrol (Sumidourus) NORMAL Jony, Anuku Wed 09-Jun-21 Thu 10-Jun-21 2 0% Lanjutan Pasang Bata
u 3.3 Urugan dan Pemadatan Kembali Tanah NORMAL Felis, Stanis, Nando Fri 11-Jun-21 Fri 11-Jun-21 1 0% Please upgrade to the Pro version.
Exported from Gantt Excel on 06-Jun-21 10:28:20