→ listrik = watt x n x - x (J) (V)

tv 55 x 1 x 1.00 x 20 = 1100.00

kipas angin 60 x 1 x 1.00 x 20 = 1200.00

kulkas 128 x 1 x 1.00 x 20 = 2560.00

lampu 18 x 2 x 1.00 x 20 = 720.00

lampu 15 x 2 x 1.00 x 20 = 600.00

lampu 18 x 3 x 1.00 x 1 = 54.00

= 6234.00 watt

→ arus = Listrik : volt (V)

6234.00 : 220 = 28.34

400 : 1 = 0.00

= 28.34 Ampere

→ Keterangan, yang di sediakan PLN

220 VA = 1 A

450 VA = 2 A

900 VA = 4 A

1300 VA = 6 A

2200 VA = 10 A
3500 VA = 16 A

4400 VA = 20 A

5500 VA = 25 A

TYPE 45
→ listrik = watt x n x - x (J) (V)

tv 55 x 2 x 1.00 x 1 = 110.00

rice cooker 400 x 1 x 0.00 x 1 = 0.00

kipas angin 60 x 1 x 1.00 x 1 = 60.00

AC 400 x 1 x 1.00 x 2 = 800.00

kulkas 128 x 1 x 1.00 x 2 = 256.00

lampu 18 x 6 x 1.00 x 2 = 216.00

lampu 15 x 2 x 1.00 x 2 = 60.00

= 1502.00 watt

→ arus = Listrik : volt (V)

1502.00 : 220 = 6.83


400 : 1 = 0.00

= 6.83 Ampere

→ Keterangan, yang di sediakan PLN

220 VA = 1 A

450 VA = 2 A

900 VA = 4 A

1300 VA = 6 A

2200 VA = 10 A

3500 VA = 16 A

4400 VA = 20 A

5500 VA = 25 A
BQ PERSIAPAN
BOWPLANK
→ = P x - x - x p (V)

1 MESS I 99.8 x 1 x 1.00 x 1 = 99.80

1 TYPE 45 I 164.8 x 1 x 1.00 x 1 = 164.80

1 TYPE 70 I 46.4 x 1 x 1.00 x 1 = 46.40

= 311.00 m

PAGAR SENG
→ = P x - x - x p (V)

1 I 61 x 1 x 1.00 x 1 = 61.00

= 61.00 m2
BQ HALAMAN
Timbunan
→ stationing = A1 + A2 x 0.5 x p (V)

1 0-5 I 10.72 + 18.0741 x 0.50 x 5 = 71.99

2 5 - 10 II 18.07414 + 22.127 x 0.50 x 5 = 100.50

3 10 - 15 III 22.12697 + 24.8985 x 0.50 x 5 = 117.56

4 15 - 20 IV 24.89852 + 29.86 x 0.50 x 5 = 136.90

5 20 - 25 V 29.86005 + 36.0847 x 0.50 x 5 = 164.86

6 25 - 30 VI 36.08468 + 41.1916 x 0.50 x 5 = 193.19

7 30 - 35 VII 41.1916 + 45.0172 x 0.50 x 5 = 215.52

8 35 - 40 VIII 45.01725 + 46.7983 x 0.50 x 5 = 229.54

9 40 - 45 IX 46.79831 + 50.6785 x 0.50 x 5 = 243.69

10 45 - 50 X 50.67848 + 49.2245 x 0.50 x 5 = 249.76

= 1723.51 m3

Pemasangan Paving
→ = a x - x - x p (V)

1 I 316.4371 x 1 x 1.00 x 1 = 316.44

= 316.44 m2

pekerjaan drainase
→ dindinng = p x t x - x (J) (V)

172.37 x 0.35 x 1.00 x 2 = 120.66

= 120.66

→ plesteran = p x l x - x (J) (V)

172.37 x 0.3 x 1.00 x 2 = 103.42

= 103.42

→ rabat = p x l x t x (J) (V)

172.37 x 0.3 x 0.08 x 1 = 4.14

= 4.14
BQ MESS PEGAWAI
pekerjaan tanah
→ Gali tnh = p x l x t x (J) (V)

f1 1.4 x 1.4 x 1.50 x 24 = 70.56

f2 1.1 x 1.1 x 1.50 x 12 = 21.78

= 92.34

→ urug pasir bawah footplat = (P) x (L) x (T) x (J) (V)

f1 1.4 x 1.4 x 0.10 x 24 = 4.70


f2 1.1 x 1.1 x 0.10 x 12 = 1.45

= 6.16

→ urug pasir bawah lantai = p x l x t x (J) (V)

39.00 x 6.9 x 0.30 x 1 = 80.73

= 80.73

→ urugan tanah kembali = v x - x - x (J) (V)

galian 92.34 x 1 x 1 x 1 = 92.34

fp1 16.22 x 1 x 1 x -1 = -16.22

fp2 4.80 x 1 x 1 x -1 = -4.80

ur. pasir dibawah fondasi 6.16 x 1 x 1 x -1 = -6.16

p1 2.88 x 1 x 1 x -1 = -2.88

p2 1.20 x 1 x 1 x -1 = -1.20

= 62.28

pekerjaan Pancang
→ pancang = n x ttk x - x (J) (V)

3 x 4 x 1.00 x 24 = 288.00

3 x 2 x 1.00 x 12 = 72.00

= 360.00

→ Pemancangan = n x ttk x p x (J) (V)

3 x 4 x 4.00 x 24 = 1152.00

3 x 2 x 4.00 x 12 = 288.00

= 1440.00

→ sambung pancang = n x ttk x P x (J) (V)

2 x 4 x 0.80 x 24 = 153.60

2 x 2 x 0.80 x 12 = 38.40
= 192.00

→ potong pancang = n x ttk x - x (J) (V)

1 x 4 x 1.00 x 24 = 96.00

1 x 2 x 1.00 x 12 = 24.00
= 120.00
pekerjaan beton
lt 1

→ f1 = p x l x t x (J) (V)

1 I 1.3 x 1.3 x 0.40 x 24 = 16.22

= 16.22

→ f2 = p x l x t x (J) (V)

1 I 1 x 1 x 0.40 x 12 = 4.80

= 4.80

→ p1 = b x h x t x (J) (V)

1 I 0.25 x 0.4 x 1.2 x 24 = 2.88

= 2.88

→ p2 = b x h x t x (J) (V)

1 I 0.25 x 0.25 x 1.6 x 12 = 1.20

= 1.20

→ S1 = b x h x p x (J) (V)

1 25x40 I 0.25 x 0.4 x 62.40 x 1 = 6.24

= 6.24

→ S2 = b x h x p x (J) (V)

1 25x40 I 0.25 x 0.4 x 152.00 x 1 = 15.20

= 15.20

→ S3 = b x h x p x (J) (V)

1 15x20 I 0.15 x 0.2 x 24.00 x 1 = 0.72

= 0.72

→ lantai 1 = p x l x t x (J) (V)

1 t = 10 I 3.75 x 3.25 x 0.10 x 10 = 12.19


1 t = 10 I 3.25 x 1.45 x 0.10 x 10 = 4.71

1 t = 10 I 1 x 0.95 x 0.10 x 10 = 0.95

1 t = 10 I 1 x 1.65 x 0.10 x 10 = 1.65

1 t = 10 I 1 x 0.3 x 0.10 x 10 = 0.30

1 t = 10 I 3.75 x 3.85 x 0.10 x 1 = 1.44

1 t = 10 I 3.75 x 2.3 x 0.10 x 1 = 0.86

= 22.11

→ K1 = b x h x t x (J) (V)

1 25x40 I 0.25 x 0.4 x 3.60 x 24 = 8.64

= 8.64
→ K2 = b x h x t x (J) (V)

1 25x25 I 0.25 x 0.25 x 3.60 x 12 = 2.70


= 2.70

→ K3 = b x h x t x (J) (V)

1 12x15 I 0.1 x 0.15 x 3.40 x 62 = 3.16

= 3.16

→ B4 = b x h x p x (J) (V)

1 10x20 I 0.1 x 0.2 x 7.09 x 10 = 1.42


= 1.42

→ B3 = b x h x p x (J) (V)

1 15x25 I 0.15 x 0.25 x 4.27 x 10 = 1.60

1 15x25 I 0.15 x 0.25 x 3.75 x 1 = 0.14

= 1.74

→ plat kanopi = p x l x t x (J) (V)

1 I 4.675 x 0.675 x 0.08 x 10 = 2.52

1 I 3.55 x 0.52 x 0.08 x 2 = 0.30

1 I 3.75 x 0.65 x 0.08 x 1 = 0.20

= 3.01

→ B1 = b x h x p x (J) (V)

1 I 0.25 x 0.4 x 3.75 x 1 = 0.38


= 0.38

→ plat bordes = p x l x t x (J) (V)

1 I 3.75 x 1.04 x 0.12 x 1 = 0.47

= 0.47

→ anak tangga = p x l x - x (J) (V)


1 I 1.9078 x 1.6 x 1 x 1 = 3.05

= 3.05

lt 2

→ B1 = b x h x p x (J) (V)

1 25x40 I 0.25 x 0.4 x 62.40 x 1 = 6.24

= 6.24

→ B2 = b x h x p x (J) (V)

1 25x40 I 0.25 x 0.4 x 152.00 x 1 = 15.20

= 15.20
→ B3 = b x h x p x (J) (V)

1 15x25 I 0.15 x 0.25 x 24.00 x 1 = 0.90


= 0.90

→ lantai 2 = p x l x t x (J) (V)

1 t = 10 I 3.75 x 3.25 x 0.12 x 10 = 14.63

1 t = 10 I 3.25 x 1.45 x 0.12 x 10 = 5.66

1 t = 10 I 1 x 0.95 x 0.12 x 10 = 1.14

1 t = 10 I 1 x 1.65 x 0.12 x 10 = 1.98

1 t = 10 I 1 x 0.3 x 0.12 x 10 = 0.36


1 t = 10 I 3.75 x 1.45 x 0.12 x 1 = 0.65

= 24.41

→ K1 = b x h x t x (J) (V)

1 25x40 I 0.25 x 0.4 x 3.60 x 24 = 8.64

= 8.64

→ K2 = b x h x t x (J) (V)

1 20x20 I 0.25 x 0.25 x 3.60 x 12 = 2.70

= 2.70

→ K3 = b x h x t x (J) (V)

1 I 0.12 x 0.15 x 3.40 x 22 = 1.35

= 1.35

→ B4 = b x h x p x (J) (V)

1 10x20 I 0.1 x 0.2 x 7.09 x 10 = 1.42

= 1.42

→ B3 = b x h x p x (J) (V)

1 15x25 I 0.15 x 0.25 x 4.27 x 10 = 1.60

1 15x25 I 0.15 x 0.25 x 3.75 x 1 = 0.14


= 1.74

→ plat kanopi = p x l x t x (J) (V)

1 I 4.675 x 0.675 x 0.08 x 10 = 2.52

1 I 3.55 x 0.52 x 0.08 x 2 = 0.30

1 I 3.75 x 0.65 x 0.08 x 1 = 0.20

= 3.01

→ RB1 = b x h x p x (J) (V)

1 25x40 I 0.25 x 0.4 x 62.40 x 1 = 6.24

= 6.24
→ RB2 = b x h x p x (J) (V)

1 25x40 I 0.25 x 0.4 x 121.00 x 1 = 12.10


= 12.10

→ RB3 = b x h x p x (J) (V)

1 10x20 I 0.1 x 0.2 x 24.00 x 1 = 0.48

1 10x20 I 0.1 x 0.2 x 35.00 x 1 = 0.70

= 1.18

→ RB4 = b x h x p x (J) (V)


1 20x40 I 0.2 x 0.4 x 48.80 x 2 = 7.81

1 20x40 I 0.2 x 0.4 x 16.00 x 2 = 2.56

= 10.37

→ K4 = b x h x t x (J) (V)

1 25x25 I 0.25 x 0.25 x 0.20 x 26 = 0.33

= 0.33

→ Plat Kanopi = p x l x t x (J) (V)

1 I 19.1 x 0.8 x 0.10 x 4 = 6.11

1 I 6.9 x 0.8 x 0.10 x 4 = 2.21

= 8.32

→ Listplank Beton = p x l x t x (J) (V)

1 I 19.1 x 0.4 x 0.10 x 4 = 3.06


1 I 8.5 x 0.4 x 0.10 x 4 = 1.36

= 4.42

→ Dak atap = p x l x t x (J) (V)

1 I 6.15 x 3.75 x 0.15 x 1 = 3.46

= 3.46

pekerjaan pasangan
lt 1

→ dinding bata lt.1 = p x t x - x (J) (V)

1 horisontal I 101.25 x 3.60 x 1.00 x 1 = 364.50

1 vertikal I 58.35 x 3.60 x 1.00 x 1 = 210.06

1 vertikal I 25 x 3.8 x 1.00 x 1 = 95.00

1 tangga I 10.26 x 0.95 x 1.00 x 1 = 9.75

1 pagar I 1.29 x 1 x 1.00 x 10 = 12.85


0.45 x 2 x 1.00 x 10 = 9.00

1 saft I 1.2 x 3.60 x 1.00 x -4 = -17.28

1 lubang I 77.79 x 1 x 1.00 x -1 = -77.79

= 606.09
→ plesteran = p x s x - x (J) (V)

1 I 606.09 x 2 x 1.00 x 1 = 1212.17


= 1212.17

→ keramik 40x40 = p x l x - x (J) (V)

1 selasar I 38.90 x 1.775 x 1.00 x 1 = 69.05

1 selasar I 5.35 x 3.9 x 1.00 x 1 = 20.87

1 kamar I 3.88 x 3.4 x 1.00 x 10 = 131.75

1 kamar I 1.25 x 1.1 x 1.00 x 10 = 13.70

1 tangga I 4.00 x 1.6 x 1.00 x 1 = 6.40


1 tangga I 3.00 x 1.6 x 1.00 x 2 = 9.60

= 251.36

→ keramik lantai wc = p x l x - x (J) (V)

1 I 1.70 x 1.1 x 1.00 x 10 = 18.70

= 18.70

→ keramik dinding wc = p x t x - x (J) (V)

1 I 3.40 x 1.6 x 1.00 x 10 = 54.40

= 54.40

→ pagar hollow = p x t x - x (J) (V)

1 depan I 3.05 x 1 x 1.00 x 0 = 0.00

1 belakang I 1.08 x 1 x 1.00 x 10 = 10.75

= 10.75

→ Relling Tangga = p x t x - x (J) (V)

1 I x 1 x 1.00 x 1 = 0.00

1 I x 1 x 1.00 x 1 = 0.00

= 0.00

→ Pipa galvanis = p x n x - x (J) (V)


1 I 2.15 x 2 x 1.00 x 10 = 43.00

1 I 1.05 x 4 x 1.00 x 10 = 42.00

= 85.00
lt 2

→ dinding bata lt.1 = p x t x - x (J) (V)


1 horisontal I 101.25 x 3.60 x 1.00 x 1 = 364.50

1 vertikal I 58.35 x 3.60 x 1.00 x 1 = 210.06

1 vertikal I 25 x 3.80 x 1.00 x 1 = 95.00

1 pagar I 1.285 x 1 x 1.00 x 10 = 12.85

lemari 0.45 x 2 x 1.00 x 10 = 9.00

1 saft I 1.2 x 3.60 x 1.00 x -4 = -17.28

1 lubang I 81.4188 x 1 x 1.00 x -1 = -81.42

= 592.71

→ plesteran = p x s x - x (J) (V)

1 I 592.71 x 2 x 1.00 x 1 = 1185.42

= 1185.42

→ keramik 40x40 = p x l x - x (J) (V)

1 selasar I 38.90 x 1.775 x 1.00 x 1 = 69.05


1 kamar I 3.88 x 3.4 x 1.00 x 10 = 131.75

1 kamar I 1.25 x 1.1 x 1.00 x 10 = 13.70

= 214.49

→ keramik lantai wc = p x l x - x (J) (V)

1 I 1.70 x 1.1 x 1.00 x 10 = 18.70

= 18.70

→ keramik dinding wc = p x t x - x (J) (V)

1 I 3.40 x 1.6 x 1.00 x 10 = 54.40

= 54.40

→ pagar hollow = p x t x - x (J) (V)

1 depan I 3.05 x 1 x 1.00 x 0 = 0.00

1 depan I 3.05 x 2.5 x 1.00 x 0 = 0.00


1 depan I 3.55 x 2.5 x 1.00 x 1 = 8.88

1 belakang I 1.08 x 1 x 1.00 x 10 = 10.75

= 19.63

→ relling tangga = p x t x - x (J) (V)

1 I 10.26 x 1 x 1.00 x 1 = 10.26

= 10.26

→ Pipa galvanis = p x n x - x (J) (V)

1 I 2.15 x 2 x 1.00 x 10 = 43.00

1 I 1.03 x 4 x 1.00 x 10 = 41.20

= 84.20
pekerjaan kusen
→ kaca mati = a x - x - x (J) (V)
1 Pj I 0.41 x 1 x 1.00 x 20 = 8.25

1 j2 I 0.57 x 1 x 1.00 x 3 = 1.71

= 9.96

pekerjaan plafond
lt 1

→ rangka / plafond = p x l x t x (J) (V)

1 selasar I 38.90 x 1.775 x 1.00 x 1 = 69.05


1 kamar I 3.88 x 3.4 x 1.00 x 10 = 131.75

1 kamar I 1.25 x 1.1 x 1.00 x 10 = 13.70

1 kamar I 1.70 x 1.1 x 1.00 x 10 = 18.70

= 233.19

→ list = p x - x - x (J) (V)

1 selasar I 88.03 x 1 x 1.00 x 1 = 88.03


1 kamar I 13.96 x 1 x 1.00 x 10 = 139.60

1 kamar I 4.96 x 1 x 1.00 x 10 = 49.60

1 kamar I 3.76 x 1 x 1.00 x 10 = 37.60

= 314.83

lt 2

→ rangka / plafond = p x l x t x (J) (V)

1 selasar I 38.83 x 1.62 x 1.00 x 1 = 62.90


1 selasar I 5.35 x 3.75 x 1.00 x 1 = 20.06

1 kamar I 3.88 x 3.4 x 1.00 x 10 = 131.75

1 kamar I 1.25 x 1.1 x 1.00 x 10 = 13.70

1 kamar I 1.70 x 1.1 x 1.00 x 10 = 18.70

= 247.10

→ list = p x - x - x (J) (V)


1 selasar I 95.57 x 1 x 1.00 x 1 = 95.57

1 kamar I 13.96 x 1 x 1.00 x 10.00 = 139.60

1 kamar I 4.96 x 1 x 1.00 x 10.00 = 49.60

1 kamar I 3.76 x 1 x 1.00 x 10.00 = 37.60

= 322.37
pekerjaan atap
→ rangka atap / atap = p x s x - x (J) (V)
65.83 x 2 x 1.00 x 2 = 263.32

17.78 x 2 x 1.00 x 2 = 71.12

= 334.44

→ bubungan = p x - x - x (J) (V)

34.56 x 1 x 1.00 x 2 = 69.12

= 69.12

→ List plank kayu = p x - x - x (J) (V)

52.60 x 1 x 1.00 x 2 = 105.20

= 105.20

pekerjaan elektrikal
→ = n x - x - x (J) (V)

tunggal 2.00 x 1 x 1.00 x 20 = 40.00


ganda 1.00 x 1 x 1.00 x 20 = 20.00

sk 2.00 x 1 x 1.00 x 20 = 40.00

lampu 18 watt 2.00 x 1 x 1.00 x 20 = 40.00

lampu 15 watt 2.00 x 1 x 1.00 x 20 = 40.00

lampu 18 watt 4.00 x 1 x 1.00 x 1 = 4.00

→ listrik = watt x n x - x (J) (V)

tv 55 x 1 x 1.00 x 20 = 1100.00
kipas angin 60 x 1 x 1.00 x 20 = 1200.00

kulkas 128 x 1 x 1.00 x 20 = 2560.00

lampu 18 x 2 x 1.00 x 20 = 720.00

lampu 15 x 2 x 1.00 x 20 = 600.00

lampu 18 x 3 x 1.00 x 1 = 54.00

= 6234.00 watt

→ arus = Listrik : volt (V)

6234.00 : 220 = 28.34


400 : 1 = 0.00

= 28.34 A

pekerjaan sanitasi
→ closed = n x - x - x (J) (V)

lt 1 10.00 x 1 x 1.00 x 1 = 10.00

lt 2 10.00 x 1 x 1.00 x 1 = 10.00


= 20.00
→ Pipa 6" = p x - x - x (J) (V)

16.00 x 1 x 1.00 x 2 = 32.00


= 32.00

→ Pipa 4" = p x - x - x (J) (V)

lt. 1 12.00 x 1 x 1.00 x 2 = 24.00

lt. 2 24.00 x 1 x 1.00 x 2 = 48.00

= 72.00

→ Pipa 3" = p x - x - x (J) (V)


lt. 1 20.00 x 1 x 1.00 x 2 = 40.00

lt. 2 12.00 x 1 x 1.00 x 2 = 24.00

= 64.00

→ Pipa 2" = p x - x - x (J) (V)

lt. 1 12.00 x 1 x 1.00 x 2 = 24.00

lt. 2 12.00 x 1 x 1.00 x 2 = 24.00


roof 8.00 x 1 x 1.00 x 2 = 16.00

= 64.00

→ Pipa 3/4" = p x - x - x (J) (V)

lt. 1 5.00 x 1 x 1.00 x 2 = 10.00

lt. 2 5.00 x 1 x 1.00 x 2 = 10.00

= 20.00

pekerjaan lemari
→ dinding = p x t x - x (J) (V)

0.45 x 2 x 1.00 x 20 = 18.00

= 18.00

→ plesteran = p x t x - x (J) (V)

18.00 x 2 x 1.00 x 1 = 36.00


= 36.00

→ kp = b x h x t x (J) (V)

0.12 x 0.15 x 2.00 x 20 = 0.72

= 0.72

→ mutyplak = p x l x - x (J) (V)

0.60 x 1.3 x 1.00 x 20 = 15.60


= 15.60

pekerjaan Septictank
→ pasir = p x l x t x (J) (V)

1.60 x 4 x 0.10 x 1 = 0.64

= 0.64
→ lantai = p x l x t x (J) (V)

1.60 x 4 x 0.15 x 1 = 0.96


= 0.96

→ dinding = p x l x t x (J) (V)

4.00 x 1.5 x 0.15 x 2 = 1.80

1.30 x 1.5 x 0.15 x 2 = 0.59

= 2.39

→ atap = p x l x t x (J) (V)


4.00 x 1.6 x 0.10 x 1 = 0.64

= 0.64

→ bata = p x t x - x (J) (V)

5.60 x 1.3 x 1.00 x 2 = 14.56

= 14.56

pekerjaan kuxen
→ pintu dan jendela lt 1 = p x b x h x (J) (V)

p1 5.10 x 0.05 x 0.10 x 10 = 0.26

p2 4.90 x 0.05 x 0.10 x 10 = 0.25

p3 2.70 x 0.05 x 0.10 x 10 = 0.14

pj 6.69 x 0.05 x 0.10 x 10 = 0.33

j1 5.55 x 0.05 x 0.10 x 10 = 0.28

j2 4.40 x 0.05 x 0.10 x 3 = 0.07


= 1.31

→ pintu dan jendela lt 2 = p x b x h x (J) (V)

p1 5.10 x 0.05 x 0.10 x 10 = 0.26

p2 4.90 x 0.05 x 0.10 x 10 = 0.25

p3 2.70 x 0.05 x 0.10 x 10 = 0.14

pj 6.69 x 0.05 x 0.10 x 10 = 0.33


j1 5.55 x 0.05 x 0.10 x 10 = 0.28

= 1.25
BQ TYPE 45 B
pekerjaan tanah
→ Gali tnh = p x l x t x (J) (V)

H 23.9 x 0.8 x 0.95 x 1 = 18.16

V 21.4 x 0.8 x 0.95 x 1 = 16.26

45.3 = 34.43 m3

→ urug pasir bawah fondasi = (P) x (L) x (T) x (J) (V)

H 23.9 x 0.8 x 0.05 x 1 = 0.96

V 21.4 x 0.8 x 0.05 x 1 = 0.86

= 1.81 m3

→ urug pasir bawah lantai = p x l x t x (J) (V)

7.50 x 3 x 0.25 x 1 = 5.63

5.70 x 2.8 x 0.25 x 1 = 3.99

3.30 x 2 x 0.20 x 1 = 1.32

= 10.94 m3

→ urugan tanah kembali = p x l x t x (J) (V)

galian 34.43 x 1 x 1 x 1 = 34.43

fp2 17.21 x 1 x -1 x 1 = -17.21

lantai kerja 3.62 x 1 x -1 x 1 = -3.62

urug pasir bawah fondasi 1.81 x 1 x -1 x 1 = -1.81

= 11.78 m3

pekerjaan FONDASI
→ Batu gunung = p x l x t x (J) (V)

H 23.9 x 0.475 x 0.80 x 1 = 9.08

V 21.4 x 0.475 x 0.80 x 1 = 8.13

45.3 = 17.21 m3

pekerjaan beton
→ rabat = a x t x - x (J) (V)

1 I 15.44 x 0.1 x 1.00 x 1 = 1.54

= 1.54 m3

→ lantai kerja = p x l x t x (J) (V)

1 I 23.9 x 0.8 x 0.10 x 1 = 1.91

1 I 21.4 x 0.8 x 0.1 x 1 = 1.71


= 3.62 m3
→ sloof = b x h x p x (J) (V)

1 I 0.15 x 0.2 x 45.30 x 1 = 1.36

= 1.36 m3

→ lantai = p x l x t x (J) (V)

1 I 2.9 x 2.9 x 0.10 x 2 = 1.68

1 I 1.7 x 1.4 x 0.10 x 1 = 0.24

1 I 1.1 x 1.4 x 0.10 x 1 = 0.15

1 I 2.7 x 5.6 x 0.10 x 1 = 1.51

1 I 1.9 x 3.2 x 0.10 x 1 = 0.61

= 4.19 m3

→ K1 = b x h x t x (J) (V)

1 I 0.15 x 0.15 x 7.4 x 1 = 0.17

= 0.17 m3

→ K2 = b x h x t x (J) (V)

1 I 0.1 x 0.15 x 4 x 18 = 1.08

= 1.08 m3

→ balok latei = b x h x p x (J) (V)

1 I 0.1 x 0.15 x 22.85 x 1 = 0.34


= 0.34 m3

→ dak atap = p x l x t x (J) (V)

1 I 1.1 x 1.1 x 0.10 x 1 = 0.12

1 I 4.324 x 1 x 0.10 x 1 = 0.43

= 0.55 m3

→ kanopi = p x l x t x (J) (V)

1 I 6.62 x 0.4 x 0.08 x 1 = 0.21

1 I 1.1 x 1.4 x 0.08 x 1 = 0.12

= 0.34 m3

→ ringbalk = b x h x p x (J) (V)

1 I 0.1 x 0.15 x 23.30 x 1 = 0.35

1 I 0.1 x 0.15 x 21.40 x 1 = 0.32

= 0.67 m3
pekerjaan pasangan
→ dinding bata lt.1 = p x t x - x (J) (V)

1 horisontal I 23.9 x 4.00 x 1.00 x 1 = 95.60

1 vertikal I 20.5 x 4.00 x 1.00 x 1 = 82.00

1 vertikal I 0.2 x 2.17 x 1.00 x 1 = 0.43


1 selasar I 5.13 x 0.2 x 1.00 x 1 = 1.03

1 I x x x = 0.00

1 lubang I 21.58 x 1 x 1.00 x -1 = -21.58

= 157.48 m2

→ plesteran = p x s x - x (J) (V)

1 I 157.48 x 2 x 1.00 x 1 = 314.96

= 314.96 m2

→ keramik 40x40 = a x - x - x (J) (V)

1 dalam I 39.75 x 1 x 1.00 x 1 = 39.75

1 teras I 1.40 x 0.7 x 1.00 x 1 = 0.98

1 belakang I 1.20 x 1.2 x 1.00 x 1 = 1.44

= 42.17 m2

→ keramik lantai wc = a x l x - x (J) (V)

1 I 1.70 x 1.4 x 1.00 x 1 = 2.38

= 2.38 m2

→ keramik dinding wc = p x t x - x (J) (V)

1 I 5.40 x 1.6 x 1.00 x 1 = 8.64

= 8.64 m2

→ lubng angin = n x - x - x (J) (V)

1 I 14.00 x 1 x 1.00 x 1 = 14.00

= 14.00 m2

pekerjaan plafond
→ rangka / plafond = p x l x t x (J) (V)

1 I 42.13 x 1 x 1.00 x 1 = 42.13

1 I 24.42 x 1 x 1.00 x 1 = 24.42

= 66.55 m2

→ list = p x - x - x (J) (V)

1 selasar I 31.04 x 1 x 1.00 x 1 = 31.04

1 dalam I 55.40 x 1 x 1.00 x 1 = 55.40


= 86.44 m2

pekerjaan atap
→ rangka atap / atap = a x - x - x (J) (V)
24.02 x 1 x 1.00 x 1 = 24.02

19.81 x 1 x 1.00 x 1 = 19.81

22.52 x 1 x 1.00 x 1 = 22.52

20.46 x 1 x 1.00 x 1 = 20.46

= 86.82 m2

→ bubungan = p x - x - x (J) (V)

36.84 x 1 x 1 x 1 = 36.84

= 36.84 m2

→ List plank kayu = p x - x - x (J) (V)

36.40 x 1 x 1.00 x 1 = 36.40

= 36.40 m2

pekerjaan sanitasi
→ closed = n x - x - x (J) (V)

lt 1 1.00 x 1 x 1.00 x 1 = 1.00

= 1.00 bh

→ 4" = p x - x - x (J) (V)

lt.1 8.00 x 1 x 1.00 x 1 = 8.00

= 8.00 m

→ 3" = p x - x - x (J) (V)

lt.1 12.00 x 1 x 1.00 x 1 = 12.00

= 12.00 m

→ 3/4" = p x - x - x (J) (V)

lt.1 20.00 x 1 x 1.00 x 1 = 20.00

= 20.00 m

pekerjaan Kusen
→ kaca = p x t x - x (J) (V)

1.80 x 0.5 x 1.00 x 1 = 0.90

= 0.90 m2
pekerjaan elektrikal
→ listrik = watt x n x - x (J) (V)

tv 55 x 2 x 1.00 x 1 = 110.00

rice cooker 400 x 1 x 0.00 x 1 = 0.00

kipas angin 60 x 1 x 1.00 x 1 = 60.00


AC 820 x 1 x 1.00 x 1 = 820.00

kulkas 128 x 1 x 1.00 x 1 = 128.00

lampu 18 x 6 x 1.00 x 1 = 108.00

lampu 15 x 2 x 1.00 x 1 = 30.00

= 1256.00 watt

→ arus = Listrik : volt (V)

1256.00 : 220 = 5.71

400 : 1 = 0.00

= 5.71 A

pekerjaan teralis
→ = a x - x - x (J) (V)

j1 1.80 x 1 x 1.00 x 3 = 5.40

j2 0.75 x 1 x 1.00 x 3 = 2.25

j3 0.50 x 1 x 1.00 x 2 = 1.00

= 8.65

pekerjaan kusen
→ pintu dan jendela = p x b x h x (J) (V)

p1 4.92 x 0.06 x 0.12 x 4 = 0.14

p2 4.82 x 0.06 x 0.12 x 1 = 0.03

J1 7.26 x 0.06 x 0.12 x 3 = 0.16

J2 4.24 x 0.06 x 0.12 x 3 = 0.09


J3 3.24 x 0.06 x 0.12 x 2 = 0.05

J4 5.76 x 0.06 x 0.12 x 1 = 0.04

= 0.51
BQ TYPE 70
pekerjaan tanah
→ Gali tnh = p x l x t x (J) (V)

H 33 x 0.8 x 0.95 x 1 = 25.08

V 32.4 x 0.8 x 0.95 x 1 = 24.62

65.4 = 49.70 m3

→ urug pasir bawah fondasi = (P) x (L) x (T) x (J) (V)

H 33 x 0.8 x 0.05 x 1 = 1.32

V 32.4 x 0.8 x 0.05 x 1 = 1.30

= 2.62 m3

→ urug pasir bawah lantai = p x l x t x (J) (V)


8.00 x 3 x 0.25 x 1 = 6.00

5.50 x 2 x 0.25 x 1 = 2.75

7.00 x 3.5 x 0.25 x 1 = 6.13

4.30 x 1.5 x 0.25 x 1 = 1.61

1.50 x 3 x 0.25 x 1 = 1.13

= 17.61 m3

→ urugan tanah kembali = p x l x t x (J) (V)

galian 49.70 x 1 x 1 x 1 = 49.70

fp1 0.29 x 1 x -1 x 1 = -0.29

fp2 24.85 x 1 x -1 x 1 = -24.85

ur. pasir dibawah fondasi 5.23 x 1 x -1 x 1 = -5.23

= 19.33 m3

pekerjaan FONDASI
→ Batu gunung = p x l x t x (J) (V)

H 33 x 0.475 x 0.80 x 1 = 12.54

V 32.4 x 0.475 x 0.80 x 1 = 12.31

65.4 = 24.85 m3

pekerjaan beton
→ rabat = a x t x - x (J) (V)

1 I 22.63 x 0.1 x 1.00 x 1 = 2.26

= 2.26 m3
→ lantai kerja = p x l x t x (J) (V)

1 I 33 x 0.8 x 0.10 x 1 = 2.64

1 I 32.4 x 0.8 x 0.1 x 1 = 2.59

= 5.23 m3

→ sloof = b x h x p x (J) (V)

1 I 0.15 x 0.2 x 65.40 x 1 = 1.96

= 1.96 m3

→ footplate = p x l x t x (J) (V)

1 I 0.7 x 0.7 x 0.20 x 3 = 0.29

= 0.29 m3

→ lantai = p x l x t x (J) (V)

1 I 8.00 x 3.00 x 0.10 x 1 = 2.40

1 I 5.50 x 2.00 x 0.10 x 1 = 1.10

1 I 7.00 x 3.50 x 0.10 x 1 = 2.45

1 I 4.30 x 1.50 x 0.10 x 1 = 0.65

1 I 1.50 x 3.00 x 0.10 x 1 = 0.45

= 7.05 m3

→ K1 = b x h x t x (J) (V)

1 I 0.1 x 0.15 x 4 x 22 = 1.32

1 I 0.1 x 0.15 x 2.65 x 2 = 0.08

= 1.40 m3

→ balok latei = b x h x p x (J) (V)

1 I 0.1 x 0.15 x 13.20 x 1 = 0.20

1 I 0.1 x 0.15 x 18.70 x 1 = 0.28

1 I 0.1 x 0.15 x 16.75 x 1 = 0.25

= 0.73 m3

→ dak atap = p x l x t x (J) (V)

1 I 2.7 x 1 x 0.10 x 1 = 0.27

1 I 2.9 x 1.15 x 0.10 x 1 = 0.33

1 I 2.9 x 0.9 x 0.10 x 1 = 0.26

= 0.86 m3

→ kanopi = p x l x t x (J) (V)

1 I 0.62 x 0.4 x 0.08 x 4 = 0.08

1 I 1.38 x 0.4 x 0.08 x 2 = 0.09


= 0.17 m3

→ ringbalk = b x h x p x (J) (V)

1 I 0.1 x 0.15 x 31.30 x 1 = 0.47

1 I 0.1 x 0.15 x 30.00 x 1 = 0.45

= 0.92 m3

pekerjaan pasangan
→ dinding bata lt.1 = p x t x - x (J) (V)

1 horisontal I 29.3 x 4.00 x 1.00 x 1 = 117.20

1 vertikal I 30 x 4.00 x 1.00 x 1 = 120.00

1 vertikal I 0.46 x 2.5 x 1.00 x 1 = 1.15

1 selasar I 5.6 x 0.2 x 1.00 x 1 = 1.12

1 I x x x = 0.00

1 lubang I 31.7766 x 1 x 1.00 x -1 = -31.78


= 207.69 m2

→ plesteran = p x s x - x (J) (V)

1 I 207.69 x 2 x 1.00 x 1 = 415.39

= 415.39 m2

→ keramik 40x40 = a x - x - x (J) (V)

1 dalam I 61.63 x 1 x 1.00 x 1 = 61.63

1 teras I 3.10 x 1.2 x 1.00 x 1 = 3.72

1 belakang I 3.00 x 0.8 x 1.00 x 1 = 2.40

= 67.75 m2

→ keramik lantai wc = p x l x - x (J) (V)

1 I 1.80 x 2.3 x 1.00 x 1 = 4.14

= 4.14 m2

→ keramik dinding wc = p x t x - x (J) (V)

1 I 7.40 x 1.6 x 1.00 x 1 = 11.84

= 11.84 m2

→ kisi hollow = p x t x - x (J) (V)

1 depan I 2.50 x 0.4 x 1.00 x 1 = 1.00

1 belakang I 1.00 x 0.4 x 1.00 x 2 = 0.80

= 1.80 m2

→ lubang angin = n x - x - x (J) (V)


1 I 10.00 x 1 x 1.00 x 1 = 10.00

= 10.00 bh
pekerjaan plafond
→ rangka / plafond = p x l x t x (J) (V)

1 I 65.77 x 1 x 1.00 x 1 = 65.77

1 I 27.72 x 1 x 1.00 x 1 = 27.72

= 93.48 m2

→ list = p x - x - x (J) (V)

1 selasar I 40.00 x 1 x 1.00 x 1 = 40.00

1 DALAM I 75.76 x 1 x 1.00 x 1 = 75.76

= 115.76 m

pekerjaan atap
→ rangka atap / atap = a x - x - x (J) (V)

28.63 x 1 x 1.00 x 1 = 28.63

25.66 x 1 x 1.00 x 1 = 25.66


32.32 x 1 x 1.00 x 1 = 32.32

41.59 x 1 x 1.00 x 1 = 41.59

= 128.19 m2

→ bubungan = p x - x - x (J) (V)

3.72 x 1 x 1 x 2 = 7.44

16.05 x 1 x 1 x 1 = 16.05

3.72 x 1 x 1 x 2 = 7.44

= 30.93 m

→ List plank kayu = p x - x - x (J) (V)

45.40 x 1 x 1.00 x 1 = 45.40

= 45.40 m

pekerjaan sanitasi
→ closed = n x - x - x (J) (V)

lt 1 1.00 x 1 x 1.00 x 1 = 1.00

= 1.00 bh

→ 4" = p x - x - x (J) (V)

lt.1 4.00 x 1 x 1.00 x 1 = 4.00

= 4.00 m

→ 3" = p x - x - x (J) (V)

lt.1 12.00 x 1 x 1.00 x 1 = 12.00

= 12.00 m
→ 3/4" = p x - x - x (J) (V)

lt.1 16.00 x 1 x 1.00 x 1 = 16.00

= 16.00 m

pekerjaan Kusen
→ kaca = p x t x - x (J) (V)

1.80 x 0.5 x 1.00 x 1 = 0.90

= 0.90 m2

pekerjaan elektrikal
→ listrik = watt x n x - x (J) (V)

tv 55 x 2 x 1.00 x 1 = 110.00

rice cooker 400 x 1 x 0.00 x 1 = 0.00

kipas angin 60 x 1 x 1.00 x 1 = 60.00

AC 820 x 1 x 1.00 x 1 = 820.00


kulkas 128 x 1 x 1.00 x 1 = 128.00

lampu 18 x 6 x 1.00 x 1 = 108.00

lampu 15 x 2 x 1.00 x 1 = 30.00

= 1256.00 watt

→ arus = Listrik : volt (V)

1256.00 : 220 = 5.71

400 : 1 = 0.00

= 5.71 A

pekerjaan teralis
→ = a x - x - x (J) (V)

j1 1.80 x 1 x 1.00 x 2 = 3.60

j2 0.75 x 1 x 1.00 x 4 = 3.00

j3 0.50 x 1 x 1.00 x 1 = 0.50

j3 0.72 x 2 x 1.00 x 1 = 1.44

= 8.54
pekerjaan kusen
→ pintu dan jendela = p x b x h x (J) (V)

pj 11.56 x 0.06 x 0.12 x 1 = 0.08

p1 4.92 x 0.06 x 0.12 x 5 = 0.18

p2 4.82 x 0.06 x 0.12 x 2 = 0.07

J1 7.26 x 0.06 x 0.12 x 2 = 0.10

J2 4.24 x 0.06 x 0.12 x 4 = 0.12

J3 3.24 x 0.06 x 0.12 x 1 = 0.02

J4 5.76 x 0.06 x 0.12 x 1 = 0.04

= 0.62
CV. BLUE Print Consultant
Planning, Supervision & Engineering Consultant
Office: Jl. Yos Sudarso RT. 002 Sebengkok Tarakan
e-mail : blueprintconsultant@yahoo.com

REKAPITULASI
ESTIMATE ENGINEERING (EE)
KEGIATAN : PEMBANGUNAN GEDUNG KANTOR
PEKERJAAN : PEMBANGUNAN GEDUNG KANTOR BPBD PROVINSI KALIMANTAN UTARA
LOKASI : TANJUNG SELOR
TAHUN : 2015

JUMLAH BIAYA
No. URAIAN PEKERJAAN
( Rp. )

I PEKERJAAN PERSIAPAN Rp. 94,204,470.09

II ### Rp. #NAME?

III ### Rp. #NAME?

IV ### Rp. #NAME?

V ### Rp. #NAME?

VI ### Rp. #NAME?

VII ### Rp. #NAME?

VIII ### Rp. #NAME?

IX ### Rp. #NAME?

X ### Rp. #NAME?

XI ### Rp. #NAME?

XII ### Rp. #NAME?

XIII ### Rp. #NAME?

JUM LAH Rp. #NAME?

PPn 10% Rp. #NAME?

JUMLAH Rp. #NAME?

BIAYA PERENCANAAN Rp. 240,000,000.00

BIAYA PENGAWASAN Rp. 168,000,000.00

TOTAL KESELURUHAN Rp. #NAME?

DIBULATKAN Rp. #NAME?


Terbilang :

#NAME?

Konsultan Perencana,
CV. BLUE Print Consultant

MUHAMMAD RAMLI, ST
Direktur
CV. BLUE Print Consultant
Planning, Supervision & Engineering Consultant
Office: Jl. Yos Sudarso RT. 002 Sebengkok Tarakan
e-mail : blueprintconsultant@yahoo.com

REKAPITULASI
ESTIMATE ENGINEERING (EE)
PAKET KEGIATAN : USULAN PEMBANGUNAN RUMAH DINAS
LOKASI : TARAKAN
TAHUN : 2020

JUMLAH BIAYA
No. URAIAN PEKERJAAN
( Rp. )
I PEKERJAAN PERSIAPAN Rp. 94,204,470.09
II PEKERJAAN HALAMAN Rp. 622,251,392.65
III RUMAH DINAS TYPE 45 A (8 UNIT) Rp. 2,727,165,369.82
IV PEKERJAAN PAGAR Rp. 285,473,575.83

JUM LAH Rp. 3,729,094,808.39

PPn 10% Rp. 372,909,480.84

TOTAL KESELURUHAN Rp. 4,102,004,289.23

DIBULATKAN Rp. 4,102,004,000.00


Terbilang :

Tiga Milyar Sembilan Ratus Empat Puluh Tujuh Juta Tujuh Ratus Lima Puluh Tujuh Ribu Rupiah

Tarakan, 18 Februari 2020


Di Periksa Kepala Kantor Pelayanan
Kepala Bidang Cipta Karya Kekayaan Negara dan Lelang
Dinas Pekerjaan Umum dan Tata Ruang Tarakan
Kota Tarakan

FANDARIANSYAH, S.T., M.T. GUNTUR SUMITRO


NIP. 19710508 199803 1 009 NIP. 19700403 199603 1 002
CV. BLUE Print Consultant
Planning, Supervision & Engineering Consultant
Office: Jl. Yos Sudarso RT. 002 Sebengkok Tarakan
e-mail : blueprintconsultant@yahoo.com

ESTIMATE ENGINEERING (EE)


PAKET KEGIATAN : USULAN PEMBANGUNAN RUMAH DINAS
LOKASI : TARAKAN
TAHUN : 2020

HARGA SATUAN JUMLAH


No. URAIAN PEKERJAAN VOLUME SATUAN
( Rp.) ( Rp.)

A PEKERJAAN PERSIAPAN
1 Pemasangan Bowplank 134.00 m 94,823.14 12,706,300.09
2 Plank Nama Proyek 1.00 ls 500,000.00 500,000.00
3 Dokumentasi 1.00 ls 3,000,000.00 3,000,000.00
4 K3 1.00 ls 77,998,170.00 77,998,170.00

Total A 94,204,470.09

B PEKERJAAN HALAMAN
1 Urugan Tanah 563.00 m3 158,505.54 89,238,616.21
2 Pemasangan Paving 559.52 m2 270,336.77 151,258,828.15
3 Pembuatan Saluran Drainase
- Pemasangan dinding 1/2 bata, 965.27 m2 280,752.49 271,002,517.53
- Plesteran dinding saluran, 827.38 m2 86,563.43 71,620,506.53
- Cor rabat lantai saluran 33.10 m3 1,182,380.33 39,130,924.24
Total B 622,251,392.65

C RUMAH DINAS TYPE 45 A (8 UNIT)

I PEKERJAAN TANAH
1 Galian Tanah 268.64 m3 100,943.84 27,117,148.73
2 Urugan Pasir Dibawah Fondasi, T = 10 Cm 14.57 m3 158,505.54 2,309,742.66
3 Urugan pasir Dibawah Lantai 94.42 m3 158,505.54 14,965,458.59
4 Urugan Tanah Kembali 105.47 m3 73,432.68 7,744,797.37
Sub Total I 52,137,147.35

II PEKERJAAN FONDASI
1 Fondasi Batu Gunung 132.85 m3 1,440,493.16 191,366,635.65
Sub Total II 191,366,635.65

III PEKERJAAN BETON


1 Cor Beton Rabat
- Cor Beton K-175 14.14 m3 1,182,380.33 16,714,128.31
2 Cor Beton Bertulang Lantai Kerja, t = 10 cm
- Cor Beton K-225 27.97 m3 1,249,836.78 34,955,435.19
- Pembesian polos 1,000.22 kg 21,764.26 21,769,039.68
3 Cor Beton Bertulang Foot Plate Foot plat 70x70x20
- Cor Beton K-225 2.35 m3 1,249,836.78 2,939,616.12
- Pembesian polos 268.23 kg 21,764.26 5,837,801.50
- Begesting 13.44 m2 241,170.85 3,241,336.18
HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN VOLUME SATUAN
( Rp.) ( Rp.)

4 Cor Beton Bertulang Sloof 15x20


- Cor Beton K-225 11.62 m3 1,249,836.78 14,518,104.09
- Pembesian polos 2,067.65 kg 21,764.26 45,000,829.90
- Pembesian polos 513.12 kg 21,764.26 11,167,587.97
- Begesting 154.88 m2 255,672.35 39,598,533.10
5 Cor Beton Bertulang Lantai t = 10 cm
- Cor Beton K-225 32.33 m3 1,249,836.78 40,404,723.57
- Pembesian polos 1,410.24 kg 21,764.26 30,692,925.41
6 Cor Beton Bertulang Kolom Kolom 10x15
- Cor Beton K-225 9.89 m3 1,249,836.78 12,358,386.12
- Pembesian polos 2,343.46 kg 21,764.26 51,003,587.09
- Pembesian polos 355.97 kg 21,764.26 7,747,380.32
- Begesting 82.40 m2 467,486.26 38,520,867.70
7 Cor Beton Bertulang Balok Latei 10x15
- Cor Beton K-225 4.39 m3 1,249,836.78 5,489,283.16
- Pembesian polos 935.50 kg 21,764.26 20,360,378.73
- Begesting 58.56 m2 477,860.41 27,983,505.52
8 Cor Beton Bertulang Dak atap t = 10 cm
- Cor Beton K-225 3.08 m3 1,249,836.78 3,849,497.30
- Pembesian polos 134.36 kg 21,764.26 2,924,220.81
- Begesting 30.80 m2 634,009.36 19,527,488.40
9 Cor Beton Bertulang Plat Kanopi
- Cor Beton K-225 2.68 m3 1,249,836.78 3,349,962.53
- Pembesian polos 119.56 kg 21,764.26 2,602,070.00
- Begesting 16.75 m2 634,009.36 10,620,924.86
10 Cor Beton Ringbalk
- Cor Beton K-225 5.40 m3 1,249,836.78 6,749,118.64
- Pembesian polos 896.40 kg 21,764.26 19,509,483.20
- Pembesian polos 253.80 kg 21,764.26 5,523,769.34
- Begesting 36.00 m2 477,860.41 17,202,974.71
Sub Total III 522,162,959.46

IV PEKERJAAN ATAP
1 Pasangan Rangka Atap Baja Ringan 693.29 m2 269,598.41 186,909,773.83
2 Pasangan Atap Multy Colour 693.29 m2 154,921.66 107,405,578.12
3 Pasangan Bubungan Atap Multy Colour 273.90 m 128,339.74 35,152,766.91
4 Pasangan Listplank kayu 291.20 m 81,968.38 23,869,191.53
Sub Total IV 353,337,310.39

V PEKERJAAN PASANGAN
1 Pasangan Dinding 1/2 Bata, Camp. 1:4 1,238.88 m2 280,752.49 347,818,644.81
2 Plesteran Dinding , Camp. 1:4 2,477.76 m2 86,563.43 214,483,410.51
3 Pemasangan Lantai Keramik 60x60 340.10 m2 489,849.62 166,599,032.19
4 Pemasangan Lantai WC Keramik 20x20 19.04 m2 285,369.43 5,433,433.94
5 Pemasangan Dinding WC Keramik 20x25 69.12 m2 322,532.92 22,293,475.53
6 Pemasangan Kisi Holow 7.78 m2 650,000.00 5,054,400.00
7 Pemasangan Lubang Angin Kayu 120.00 bh 150,000.00 18,000,000.00
Sub Total V 779,682,396.99

VI PEKERJAAN KUSEN
1 Pemasangan Kusen Pintu dan Jendela Kayu Kelas II 3.92 m3 8,095,101.85 31,706,894.93
2 Pemasangan daun pintu panel kayu kelas II 40.00 bh 1,900,000.00 76,000,000.00
3 Pemasangan daun jendela kayu kelas II + kaca polos t = 5 mm 80.00 bh 600,000.00 48,000,000.00
4 Pemasangan kaca polos t = 5 mm 7.20 bh 254,535.46 1,832,655.31
5 Pemasangan Bovent (Bv) 8.00 bh 150,000.00 1,200,000.00
6 Pemasangan Teralis besi jendela 43.20 m2 350,000.00 15,120,000.00
Sub Total VI 173,859,550.23
HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN VOLUME SATUAN
( Rp.) ( Rp.)

VII PEKERJAAN PENGANTUNG & PENGUNCI


1 Pemasangan Kunci Tanam 2 x Putar, Yale 40.00 unit 284,957.87 11,398,314.70
2 Engsel Pintu Ukuran 4", Ex Hona 60.00 psg 53,906.45 3,234,386.87
3 Engsel Jendela Ukuran 3", Ex Hona 80.00 psg 44,633.16 3,570,652.94
4 Grendel 80.00 psg 55,231.99 4,418,559.44
5 Handle 80.00 psg 55,231.99 4,418,559.44
6 Kait angin 80.00 psg 55,231.99 4,418,559.44
Sub Total VII 31,459,032.83

VIII PEKERJAAN PLAFOND


1 Pemasangan rangka plafond 542.90 m2 345,491.07 187,566,827.14
2 Pemasangan plafond 542.90 m2 59,622.04 32,368,756.46
3 Pemasangan List Plafond 754.24 m 54,242.59 40,911,931.46
Sub Total VIII 260,847,515.06

IX PEKERJAAN PENGECATAN
1 Pengecatan Dinding dan Struktur Expose 2,477.76 m2 49,001.89 121,414,931.14
2 Pengecatan Plafond 542.90 m2 49,001.89 26,603,088.67
3 Pengecatan List Plafond 75.42 m2 49,001.89 3,695,918.80
4 Pengecatan Listplank kayu 87.36 m2 48,624.69 4,247,853.01
Sub Total IX 155,961,791.62

X PEKERJAAN SANITASI
1 Pemasangan Kloset Duduk 8.00 unit 2,715,206.12 21,721,648.96
2 Pemasangan Bak Cuci Piring 1 Lubang 8.00 bh 278,421.38 2,227,371.06
3 Pemasangan Pipa Air Bersih PVC 3/4" 160.00 m 25,275.27 4,044,043.52
4 Pemasangan Pipa Air Kotor PVC 3" 96.00 m 88,430.38 8,489,316.00
5 Pemasangan Pipa Air Kotor PVC 4" 64.00 m 122,743.50 7,855,584.00
6 Pemasangan Floor Drain 8.00 bh 85,021.63 680,173.02
7 Kran Air 16.00 bh 121,738.05 1,947,808.82
8 Pemasangan shower 8.00 bh 256,371.63 2,050,973.02
9 Pemasangan Septic Tank Dan Peresapan
Cor Beton Bertulang Lantai
- Cor Beton K-225 1.20 m3 1,249,836.78 1,499,804.14
- Pembesian polos 82.58 kg 25,327.50 2,091,646.26
Cor Beton Bertulang Dinding
- Cor Beton K-225 5.52 m3 1,249,836.78 6,899,099.05
- Pembesian polos 379.89 kg 25,327.50 9,621,572.80
- Begesting 13.80 m2 434,054.50 5,989,952.10
Cor Beton Bertulang Dak Penutup
- Cor Beton K-225 1.20 m3 1,249,836.78 1,499,804.14
- Pembesian polos 82.58 kg 25,327.50 2,091,646.26
- Begesting 12.00 m2 434,054.50 5,208,654.00
Urugan pasir Dibawah Lantai 1.20 m3 158,505.54 190,206.64
Pasangan dinding bata 52.00 m2 280,752.49 14,599,129.48
Plesteran dinding 104.00 m2 86,563.43 9,002,596.98
Sub Total X 107,711,030.25
HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN VOLUME SATUAN
( Rp.) ( Rp.)

XI PEKERJAAN MEKANIKAL ELECTRICAL


1 Penyambungan Listrik 10 A 8.00 ls 5,000,000.00 40,000,000.00
2 Pemasangan Titik Lampu dan Stop Kontak 112.00 ttk 350,000.00 39,200,000.00
3 Pemasangan Lampu SL 18 Watt 72.00 bh 55,000.00 3,960,000.00
5 Pemasangan Saklar Ganda 16.00 bh 49,500.00 792,000.00
6 Pemasangan Saklar Tunggal 40.00 bh 49,500.00 1,980,000.00
7 Pemasangan Stop Kontak 40.00 bh 27,700.00 1,108,000.00
8 Pemasangan Titik AC 16.00 bh 350,000.00 5,600,000.00
9 Pemasangan Box MCB 8.00 bh 350,000.00 2,800,000.00
10 Pemasangan MCB 32.00 bh 100,000.00 3,200,000.00
Sub Total XI 98,640,000.00

Total C 2,727,165,369.82

D PEKERJAAN PAGAR

I PEKERJAAN PAGAR (PG1)


1 Galian Tanah 24.44 m3 100,943.84 2,466,562.67
2 Fondasi Batu Gunung 24.44 m3 1,440,493.16 35,198,450.43
3 Cor Beton Bertulang Sloof 15x30
- Cor Beton K-225 4.07 m3 1,249,836.78 5,089,960.30
- Pembesian polos 714.90 kg 21,764.26 15,559,333.89
- Begesting 13.58 m2 255,672.35 3,470,752.11
4 Cor Beton Bertulang Kolom Kolom 15x15
- Cor Beton K-225 1.40 m3 1,249,836.78 1,743,522.31
- Pembesian polos 192.51 kg 21,764.26 4,189,837.81
- Begesting 9.30 m2 467,486.26 4,347,622.20
5 Cor Beton Bertulang Balok Latei 15x20
- Cor Beton K-225 2.72 m3 1,249,836.78 3,393,306.87
- Pembesian polos 317.66 kg 21,764.26 6,913,526.20
- Begesting 12.44 m2 477,860.41 5,946,375.46
6 Pasangan Dinding 1/2 Bata, Camp. 1:4 181.00 m2 280,752.49 50,816,200.69
7 Plesteran Dinding, Kolom & Sloof, Camp. 1:4 362.00 m2 86,563.43 31,335,962.57
8 Pengecatan Dinding dan Struktur Expose 362.00 m2 49,001.89 17,738,685.37
Sub Total I 188,210,098.89

II PEKERJAAN PAGAR (PG2)


1 Galian Tanah 3.53 m3 100,943.84 356,493.26
2 Fondasi Batu Gunung 3.53 m3 1,440,493.16 5,087,245.65
3 Cor Beton Bertulang Sloof 15x30
- Cor Beton K-225 0.59 m3 1,249,836.78 735,653.93
- Pembesian polos 103.33 kg 21,764.26 2,248,796.54
- Begesting 3.92 m2 255,672.35 1,003,258.29
4 Cor Beton Bertulang Kolom Kolom 15x15
- Cor Beton K-225 0.11 m3 1,249,836.78 140,606.64
- Pembesian polos 15.53 kg 21,764.26 337,890.15
- Begesting 0.75 m2 467,486.26 350,614.69
5 Cor Beton Bertulang Balok Latei 15x20
- Cor Beton K-225 0.39 m3 1,249,836.78 490,435.95
- Pembesian polos 45.91 kg 21,764.26 999,214.62
- Begesting 1.80 m2 477,860.41 859,431.94
6 Pasangan Dinding 1/2 Bata, Camp. 1:4 26.16 m2 280,752.49 7,344,485.14
7 Plesteran Dinding, Kolom & Sloof, Camp. 1:4 26.16 m2 86,563.43 2,264,499.39
8 Pengecatan Dinding dan Struktur Expose 26.16 m2 49,001.89 1,281,889.53
Sub Total II 23,500,515.73
HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN VOLUME SATUAN
( Rp.) ( Rp.)

III PEKERJAAN PAGAR (PG3)


1 Galian Tanah 10.80 m3 100,943.84 1,090,193.45
2 Fondasi Batu Gunung 10.80 m3 1,440,493.16 15,557,326.16
3 Cor Beton Bertulang Sloof 15x30
- Cor Beton K-225 1.20 m3 1,249,836.78 1,499,804.14
- Pembesian polos 210.65 kg 21,764.26 4,584,702.44
- Begesting 4.00 m2 255,672.35 1,022,689.39
4 Cor Beton Bertulang Kolom Kolom 15x15
- Cor Beton K-225 0.41 m3 1,249,836.78 511,808.16
- Pembesian polos 56.51 kg 21,764.26 1,229,920.13
- Begesting 2.73 m2 467,486.26 1,276,237.49
6 Pasangan Pagar Hollow + Aksesoris 65.84 m2 650,000.00 42,798,600.00
7 Plesteran Kolom & Sloof, Camp. 1:4 30.92 m2 86,563.43 2,676,541.33
8 Pengecatan Dinding dan Struktur Expose 30.92 m2 49,001.89 1,515,138.54
Sub Total III 73,762,961.22

Total D 285,473,575.83
DAFTAR ISI ANALISA
CLICK HERE A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN

CLICK HERE A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

CLICK HERE A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI

CLICK HERE A.4.1.1. HARGA SATUAN PEKERJAAN BETON

CLICK HERE A.4.2.1. HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM

CLICK HERE A.4.4.1. HARGA SATUAN PEKERJAAN PASANGAN DINDING

CLICK HERE A.4.4.2. HARGA SATUAN PEKERJAAN PLESTERAN

HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN


CLICK HERE A.4.4.3.
DINDING
HARGA SATUAN PEKERJAAN LANGIT-LANGIT
CLICK HERE A.4.5.1.
(PLAFOND)
CLICK HERE A.4.5.2. HARGA SATUAN PEKERJAAN PENUTUP ATAP

CLICK HERE A.4.6.1. HARGA SATUAN PEKERJAAN KAYU

CLICK HERE A.4.6.2. HARGA SATUAN PEKERJAAN KUNCI DAN KACA

CLICK HERE A.4.7.1. HARGA SATUAN PEKERJAAN PENGECATAN

HARGA SATUAN PEKERJAAN SANITASI DALAM


CLICK HERE A.5.1.1.
GEDUNG

CV. MITRA UTAMA KONSULTAN 38


CV. MITRA UTAMA KONSULTAN 39
NO URAIAN PEKERJAAN

BACK A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN


CLICK HERE A.2.2.1.9 Pembersihan 1 m² lapangan dan perataan
CLICK HERE A.2.2.1.11 Pembuatan 1 buah kotak adukan ukuran 40 cm x 50 cm x 25 cm
CLICK HERE A.2.2.1.13 Pembongkaran 1 m³ beton bertulang
CLICK HERE A.2.2.1.13 1 M2 Pagar Sementara dari seng gelombang tinggi 2 M

CLICK HERE A.2.2.1.13 1 M' Pengukuran dan pemasangan bowplank


CLICK HERE A.2.2.1.14 Pembongkaran 1 m³ dinding tembok batu bata
CLICK HERE A.2.2.1.15 Pemasangan 1 m² pagar kawat jaring galvanis panjang 240 cm

BACK A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


CLICK HERE A.2.3.1.1 Penggalian 1 m³ tanah biasa sedalam 1 m
CLICK HERE A.2.3.1.2 Penggalian 1 m³ tanah biasa sedalam 2 m
CLICK HERE A.2.3.1.3 Menggali 1 m³ tanah biasa sedalam 3 m
CLICK HERE A.2.3.1.4 Menggali 1 m³ tanah keras sedalam 1 m
CLICK HERE A.2.3.1.5 Menggali 1 m³ tanah cadas sedalam 1 m
CLICK HERE A.2.3.1.6 Menggali 1 m³ tanah lumpur sedalam 1 m
CLICK HERE A.2.3.1.8 Pembuangan 1 m³ tanah sejauh 30 m
CLICK HERE A.2.3.1.9 Pengurukan kembali 1 m³ galian tanah
CLICK HERE A.2.3.1.10 Pemadatan tanah 1 m³ tanah ( per 20 cm )
CLICK HERE A.2.3.1.11 Pengurugan 1 m³ dengan pasir urug
CLICK HERE A.2.3.1.14 Pengurugan 1 m³ sirtu padat

BACK A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI


CLICK HERE A.3.2.1.1 Pemasangan 1 m³ pondasi batu belah campuran 1 SP : 3 PP
CLICK HERE A.3.2.1.2 Pemasangan 1 m³ pondasi batu belah campuran 1 SP : 4 PP
CLICK HERE A.3.2.1.3 Pemasangan 1 m³ pondasi batu belah campuran 1 SP : 5 PP
CLICK HERE A.3.2.1.4 Pemasangan 1 m³ pondasi batu belah campuran 1 SP : 6 PP
CLICK HERE A.3.2.1.5 Pemasangan 1 m³ pondasi batu belah campuran 1 SP : 8 PP
CLICK HERE A.3.2.1.9 Pemasangan 1 m³ batu kosong ( anstamping )
CLICK HERE A.3.2.1.10 Pemasangan 1 m³ pondasi siklop, 60% beton campuran 1 SP : 2 PB : 3 Kr dan 40% batu belah
CLICK HERE A.3.2.1.11 Pemasangan 1 m³ pondasi, sumuran, diameter 100 cm

BACK A.4.1.1. HARGA SATUAN PEKERJAAN BETON


CLICK HERE A.4.1.1.1. Membuat 1 m³ beton mutu f 'c = 7,4 Mpa ( K - 100 ), Slump (12 ± 2 ) cm, w/c = 0.87
CLICK HERE A.4.1.1.2. Membuat 1 m³ beton mutu f 'c = 9,8 Mpa ( K - 125 ), Slump (12 ± 2 ) cm, w/c = 0.78
CLICK HERE A.4.1.1.3. Membuat 1 m³ beton mutu f 'c = 12,2 Mpa ( K - 150 ), Slump (12 ± 2 ) cm, w/c = 0.72
CLICK HERE CATATAN :

CV. MITRA UTAMA KONSULTAN 40


Bobot isi pasir = 1.400 Kg/m³, bobot isi kerikil = 1.350 Kg/m³, buckling factor pasir = 20%

CLICK HERE A.4.1.1.4. Membuat 1 m³ lantai kerja beton mutu f 'c = 7,4 Mpa ( K - 100 ), Slump ( 3 - 6 ) cm, w/c = 0.87
CLICK HERE A.4.1.1.5. Membuat 1 m³ beton mutu f 'c = 14,5 Mpa ( K - 175 ), Slump ( 12 ± 2 ) cm, w/c = 0.66
CLICK HERE A.4.1.1.6. Membuat 1 m³ beton mutu f 'c = 16,9 Mpa ( K - 200 ), Slump ( 12 ± 2 ) cm, w/c = 0.61
CLICK HERE A.4.1.1.7. Membuat 1 m³ beton mutu f 'c = 19,3 Mpa ( K - 225 ), Slump ( 12 ± 2 ) cm, w/c = 0.58
CLICK HERE A.4.1.1.8. Membuat 1 m³ beton mutu f 'c = 21,7 Mpa ( K - 250 ), Slump ( 12 ± 2 ) cm, w/c = 0.56
CLICK HERE A.4.1.1.9. Membuat 1 m³ beton mutu f 'c = 24,0 Mpa ( K - 275 ), Slump ( 12 ± 2 ) cm, w/c = 0.53
CLICK HERE A.4.1.1.10. Membuat 1 m³ beton mutu f 'c = 26,4 Mpa ( K - 300 ), Slump ( 12 ± 2 ) cm, w/c = 0.52
CLICK HERE A.4.1.1.11. Membuat 1 m³ beton mutu f 'c = 28,8 Mpa ( K - 325 ), Slump ( 12 ± 2 ) cm, w/c = 0.49
CLICK HERE A.4.1.1.12. Membuat 1 m³ beton mutu f 'c = 31,2 Mpa ( K - 350 ), Slump ( 12 ± 2 ) cm, w/c = 0.48
CLICK HERE A.4.1.1.17. Pembesian 10 Kg dengan besi ulir
CLICK HERE A.4.1.1.17. Pembesian 10 Kg dengan besi Polos
CLICK HERE A.4.1.1.18. Pemasangan 10 Kg kabel presstressed polos / strands
CLICK HERE A.4.1.1.19. Pemasangan 10 Kg jaring kawat baja ( wiremesh )
CLICK HERE A.4.1.1.20. Pemasangan 1 m² bekisting untuk pondasi
CLICK HERE A.4.1.1.21. Pemasangan 1 m² bekisting untuk sloof
CLICK HERE A.4.1.1.22. Pemasangan 1 m² bekisting untuk kolom
CLICK HERE A.4.1.1.23. Pemasangan 1 m² bekisting untuk balok
CLICK HERE A.4.1.1.24. Pemasangan 1 m² bekisting untuk lantai
CLICK HERE A.4.1.1.25. Pemasangan 1 m² bekisting untuk dinding
CLICK HERE A.4.1.1.26. Pemasangan 1 m² bekisting untuk tangga
CLICK HERE A.4.1.1.27. Pemasangan 1 m² jembatan untuk pengecoran beton
CLICK HERE A.4.1.1.28. Membuat 1 m³ pondasi beton bertulang ( 150 Kg besi + Bekisting )
CLICK HERE A.4.1.1.29. Membuat 1 m³ sloof beton bertulang ( 200 Kg besi + Bekisting )
CLICK HERE A.4.1.1.30. Membuat 1 m³ kolom beton bertulang ( 300 Kg besi + Bekisting )
CLICK HERE A.4.1.1.31. Membuat 1 m³ Balok beton bertulang ( 200 Kg besi + Bekisting )
CLICK HERE A.4.1.1.32. Membuat 1 m³ kolom beton bertulang ( 150 Kg besi + Bekisting )
CLICK HERE A.4.1.1.33. Membuat 1 m³ dinding beton bertulang ( 150 Kg besi + Bekisting )
CLICK HERE A.4.1.1.34. Membuat 1 m³ dinding beton bertulang ( 200 Kg besi + Bekisting )
CLICK HERE A.4.1.1.35. Membuat 1 m' kolom praktis beton bertulang ( 11 x 11 ) cm
CLICK HERE A.4.1.1.36. Membuat 1 m' ring balok beton bertulang ( 10 x 15 ) cm

BACK A.4.2.1. HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM


CLICK HERE A.4.2.1.1. Pemasangan 1 Kg besi profil
CLICK HERE A.4.2.1.2. Pemasangan 1 Kg rangka kuda-kuda baja I WF
CLICK HERE A.4.2.1.3. Pengerjaan 100 Kg pekerjaan perakitan
CLICK HERE A.4.2.1.5. Pengerjaan 10 cm pengelasan dengan las listrik
CLICK HERE A.4.2.1.9. Pemasangan 1 m² sunscreen alluminium
CLICK HERE A.4.2.1.10. Pemasangan 1 m² rolling door alluminium
CLICK HERE A.4.2.1.11. Pemasangan 1 m kusen pintu alluminium
CLICK HERE A.4.2.1.12. Pemasangan 1 m² pintu alluminium strip lebar 8 cm
CLICK HERE A.4.2.1.13. Pemasangan 1 m² pintu pntu kaca rangka alluminium
CLICK HERE A.4.2.1.14. Pemasangan 1 m² venetions blinds dan vertical blinds(Tirai)

CV. MITRA UTAMA KONSULTAN 41


CLICK HERE A.4.2.1.16. Pemasangan 1 m² kawat nyamuk
CLICK HERE A.4.2.1.18. Pemasangan 1 m¹ talang dasar / jurai seng bjls 28 lebar 90 cm
CLICK HERE A.4.2.1.19. Pemasangan 1 m¹ talang ½ lingkaran Ø15 cm, seng plat bjls 30 lebar 45 cm
CLICK HERE A.4.2.1.20. Pemasangan 1 m² rangka besi holow 1 x 40 x 40 x 2 mm, modul 60 x 120 cm, dinding partisi
CLICK HERE A.4.2.1.21. Pemasangan 1 m² rangka besi holow 1 x 40 x 40 x 2 mm, modul 60 x 60 cm, plafond

BACK A.4.4.1. HARGA SATUAN PEKERJAAN PASANGAN DINDING


CLICK HERE A.4.4.1.1. Pemasangan 1 m² dinding bata merah ( 9 x 9 x 18 ) cm tebal 1 batu campuran 1 SP : 2 PP
CLICK HERE A.4.4.1.2. Pemasangan 1 m² dinding bata merah ( 9 x 9 x 18 ) cm tebal 1 batu campuran 1 SP : 4 PP
CLICK HERE A.4.4.1.7. Pemasangan 1 m² dinding bata merah ( 9 x 9 x 18 ) cm tebal ½ batu campuran 1 SP : 2 PP
CLICK HERE A.4.4.1.8. Pemasangan 1 m² dinding bata merah ( 9 x 9 x 18 ) cm tebal ½ batu campuran 1 SP : 4 PP
CLICK HERE A.4.4.1.22. Pemasangan 1 m² dinding terawang ( rooster ) 12 x 11 x 24 campuran 1 SP : 3 PP

BACK A.4.4.2. HARGA SATUAN PEKERJAAN PLESTERAN


CLICK HERE A.4.4.2.1. Pemasangan 1 m² plesteran 1 SP : 1 PP tebal 15 mm
CLICK HERE A.4.4.2.2. Pemasangan 1 m² plesteran 1 SP : 2 PP tebal 15 mm
CLICK HERE A.4.4.2.3. Pemasangan 1 m² plesteran 1 SP : 3 PP tebal 15 mm
CLICK HERE A.4.4.2.4. Pemasangan 1 m² plesteran 1 SP : 4 PP tebal 15 mm
CLICK HERE A.4.4.2.5. Pemasangan 1 m² plesteran 1 SP : 5 PP tebal 15 mm
CLICK HERE A.4.4.2.6. Pemasangan 1 m² plesteran 1 SP : 6 PP tebal 15 mm
CLICK HERE A.4.4.2.7. Pemasangan 1 m² plesteran 1 SP : 7 PP tebal 15 mm
CLICK HERE A.4.4.2.8. Pemasangan 1 m² plesteran 1 SP : 8 PP tebal 15 mm

CLICK HERE A.4.4.2.13. Pemasangan 1 m² plesteran 1 SP : 1 PP tebal 20 mm


CLICK HERE A.4.4.2.14. Pemasangan 1 m² plesteran 1 SP : 3 PP tebal 20 mm
CLICK HERE A.4.4.2.15. Pemasangan 1 m² plesteran 1 SP : 4 PP tebal 20 mm
CLICK HERE A.4.4.2.16. Pemasangan 1 m² plesteran 1 SP : 5 PP tebal 20 mm
CLICK HERE A.4.4.2.17. Pemasangan 1 m² plesteran 1 SP : 6 PP tebal 20 mm
CLICK HERE A.4.4.2.23. Pemasangan 1 m² plesteran ciprat 1 SP : 2 PP
CLICK HERE A.4.4.2.24. Pemasangan 1 m² fhinishingsiar pasangan bata merah
CLICK HERE A.4.4.2.26. Pemasangan 1 m² fhinishingsiar pasangan batu kali, campuran 1 SP : 2 PP
CLICK HERE A.4.4.2.27. Pemasangan 1 m² acian

HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN


BACK A.4.4.3.
DINDING
CLICK HERE A.4.4.3.35. Pemasangan 1 m² lantai keramik ukuran 30 cm x 30 cm
CLICK HERE A.4.4.3.35. Pemasangan 1 m² lantai keramik ukuran 40 cm x 40 cm
CLICK HERE A.4.4.3.36. Pemasangan 1 m² lantai keramik ukuran 20 cm x 20 cm
CLICK HERE A.4.4.3.37. Pemasangan 1 m² lantai keramik ukuran 10 cm x 33 cm atau untuk variasi / border

CLICK HERE A.4.4.3.46. Pemasangan 1 m² parquet kayu

CLICK HERE A.4.4.3.53. Pemasangan 1 m² dinding keramik 10 cm x 20 cm


CLICK HERE A.4.4.3.54. Pemasangan 1 m² dinding keramik 20 cm x 20 cm
CLICK HERE A.4.4.3.58. Pemasangan 1 m² dinding batu tempel hitam

CV. MITRA UTAMA KONSULTAN 42


CLICK HERE A.4.4.3.60. Pemasangan 1 m² wallpaper lebar 50 cm
CLICK HERE A.4.4.3.60. Pemasangan 1 m² HPL

HARGA SATUAN PEKERJAAN LANGIT-LANGIT


BACK A.4.5.1.
(PLAFOND)
CLICK HERE A.4.5.1.5. Pemasangan 1 m² langit-langit tripleks ukuran ( 120 x 240 ) cm, tebal 3 mm, 4 mm & 6 mm
CLICK HERE A.4.5.1.6. Pemasangan 1 m² langit-langit lambrisering kayu, tebal 9 mm
CLICK HERE A.4.5.1.7. Pemasangan 1 m² langit-langit gypsum board ukuran ( 120 x 240 x 9 ) mm, tebal 9 mm
CLICK HERE A.4.5.1.8. Pemasangan 1 m² langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm
CLICK HERE A.4.5.1.9. Pemasangan Panel ACP

BACK A.4.5.2. HARGA SATUAN PEKERJAAN PENUTUP ATAP

CLICK HERE A.4.5.2.38. Pemasangan 1 m² atap seng gelombang


CLICK HERE A.4.5.2.39. Pemasangan 1 m¹ nok atap seng
CLICK HERE A.4.5.2.40. Pemasangan 1 m² atap Zincalum deck 4 mm
CLICK HERE A.4.5.2.40. Pemasangan 1 m² atap Sapndeck 4 mm
CLICK HERE A.4.5.2.41. Pemasangan 1 m¹ nok atap metal roof

A.4.5.2.41. Pemasangan 1 m2 Rangka Space frame (Annodize) Ball Joint

A.4.5.2.41. Pemasangan 1 m2 Rangka Atap Baja Ringan

BACK A.4.6.1. HARGA SATUAN PEKERJAAN KAYU


CLICK HERE A.4.6.1.2. Pembuatan dan pemasangan 1 m³ kusen pintu dan kusen jendela, kayu kelas II & III
CLICK HERE A.4.6.1.5. Pembuatan dan pemasangan 1 m² daun pintu panel, kayu kelas I atau II
CLICK HERE A.4.6.1.6. Pembuatan dan pemasangan 1 m² pintu dan jendela kaca, kayu kelas I atau II
CLICK HERE A.4.6.1.7. Pembuatan dan pemasangan 1 m² pintu dan jendela jalusi, kayu kelas I atau II
CLICK HERE A.4.6.1.8. Pembuatan 1 m² daun pintu plywood rangkap, rangka kayu kelas II tertutup ( lebar sampai 90 cm )
CLICK HERE A.4.6.1.9. Pembuatan 1 m² pintu plywood rangkap, rangka expose kayu kelas I atau II
CLICK HERE A.4.6.1.10. Pemasangan 1 m² jalusi kusen, kayu kelas I atau II
CLICK HERE A.4.6.1.13. Pemasangan 1 m³ konstruksi kuda-kuda konvensional, kayu kelas I, II dan III
CLICK HERE A.4.6.1.14. Pemasangan 1 m³ konstruksi kuda-kuda expose, kayu kelas I
CLICK HERE A.4.6.1.15. Pemasangan 1 m³ konstruksi gording, kayu kelas II
CLICK HERE A.4.6.1.19. Pemasangan 1 m² rangka langit-langit ( 50 x 100 ) cm, kayu kelas II atau III
CLICK HERE A.4.6.1.20. Pemasangan 1 m² rangka langit-langit ( 60 x 60 ) cm, kayu kelas II atau III
CLICK HERE A.4.6.1.21. Pemasangan 1 m¹ listplank ukuran ( 3 x 20 ) cm, kayu kelas I atau kelas II
CLICK HERE A.4.6.1.22. Pemasangan 1 m¹ listplank ukuran ( 3 x 30 ) cm, kayu kelas I atau kelas II
CLICK HERE A.4.6.1.23. Pemasangan 1 m² rangka dinding pemisah ( 60 x 120 ) cm, kayu kelas II atau III
CLICK HERE A.4.6.1.24. Pemasangan 1 m² dinding pemisah rangkap, rangka kayu kelas II
CLICK HERE A.4.6.1.25. Pemasangan 1 m² dinding pemisah plywood rangkap, rangka kayu kelas II

BACK A.4.6.2. HARGA SATUAN PEKERJAAN KUNCI DAN KACA


CLICK HERE A.4.6.2.2. Pemasangan 1 buah kunci tanam biasa

CV. MITRA UTAMA KONSULTAN 43


CLICK HERE A.4.6.2.5. Pemasangan 1 buah engsel pintu
CLICK HERE A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu
CLICK HERE A.4.6.2.9. Pemasangan 1 buah kait angin
CLICK HERE A.4.6.2.17. Pemasangan 1 m² kaca tebal 5 mm
CLICK HERE A.4.6.2.18. Pemasangan 1 m² kaca tebal 8 mm

BACK A.4.7.1. HARGA SATUAN PEKERJAAN PENGECATAN


CLICK HERE A.4.7.1.1. 1 m² pengikisan / pengerokan permukaan cat lama
CLICK HERE A.4.7.1.2. 1 m² pencucian bidang permukaan tembok yang pernah dicat
CLICK HERE A.4.7.1.3. 1 m² pengerokan karat pada permukaan baja cara manual
CLICK HERE A.4.7.1.4. 1 m² pengecatan bidang kayu baru ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )
CLICK HERE A.4.7.1.5. 1 m² pengecatan bidang kayu baru ( 1 lapis plamir, 1 lapis cat dasar, 3 lapis cat penutup )
CLICK HERE A.4.7.1.10. Pengecataan 1 m² tembok baru ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )
CLICK HERE A.4.7.1.11. Pengecataan 1 m² tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup )
CLICK HERE A.4.7.1.16. Pengecatan 1 m² permukaan baja dengan menie besi

HARGA SATUAN PEKERJAAN SANITASI DALAM


BACK A.5.1.1.
GEDUNG
CLICK HERE A.5.1.1.1. Pemasangan 1 buah closet duduk / monoblock
CLICK HERE A.5.1.1.2. Pemasangan 1 buah closet jongkok porslen
CLICK HERE A.5.1.1.4. Pemasangan 1 buah urinoir
CKLICK HERE A.5.1.1.5. Pemasangan 1 buah washtafel
CLICK HERE A.5.1.1.8. Pemasangan 1 buah bak mandi batu bata vol 0,30 m³
CLICK HERE A.5.1.1.12. Pemasangan 1 buah bak cuci piring stainlessteel
CLICK HERE A.5.1.1.14. Pemasangan 1 buah floor drain
CLICK HERE A.5.1.1.15. Pemasangan 1 buah bak kontrol pasangan bata 30 x 30 tinggi 35 cm
CLICK HERE A.5.1.1.16. Pemasangan 1 buah bak kontrol pasangan bata 45 x 45 tinggi 50 cm
CLICK HERE A.5.1.1.17. Pemasangan 1 buah bak kontrol pasangan bata 60 x 60 tinggi 65 cm
CLICK HERE A.5.1.1.18. Pemasangan 1 m¹ pipa galvanis ؽ"
CLICK HERE A.5.1.1.19. Pemasangan 1 buah kran air ؽ" atau ؾ"
CLICK HERE A.5.1.1.20. Pemasangan 1 m¹ pipa galvanis ؾ"
CLICK HERE A.5.1.1.21. Pemasangan 1 m¹ pipa galvanis Ø1"
CLICK HERE A.5.1.1.22. Pemasangan 1 m¹ pipa galvanis Ø1½"
CLICK HERE A.5.1.1.23. Pemasangan 1 m¹ pipa galvanis Ø2"
CLICK HERE A.5.1.1.23. Pemasangan 1 m¹ pipa galvanis Ø3"
CLICK HERE A.5.1.1.24. Pemasangan 1 m¹ pipa galvanis Ø4"
CLICK HERE A.5.1.1.25. Pemasangan 1 m¹ PVC type AW ؽ"
CLICK HERE A.5.1.1.26. Pemasangan 1 m¹ PVC type AW ؾ"
CLICK HERE A.5.1.1.27. Pemasangan 1 m¹ PVC type AW Ø1"
CLICK HERE A.5.1.1.29. Pemasangan 1 m¹ PVC type AW Ø2"

CV. MITRA UTAMA KONSULTAN 44


CV. MITRA UTAMA KONSULTAN 45
HARGA SATUAN
(Rp)

22,050.68

157,926.28

1,836,716.45
184,782.00

94,823.14

917,715.95

Err:509

100,943.84

123,894.16

147,212.68

134,346.31

203,728.71

162,430.66

44,231.19

73,432.68

73,432.68

158,505.54

Err:509

1,522,630.19

1,440,493.16

1,445,679.20

1,343,552.65

1,288,722.60

834,894.10

3,863,800.94

1,351,029.33

1,427,513.69

1,494,590.52

1,545,848.60

CV. MITRA UTAMA KONSULTAN 46


1,545,848.60

1,642,815.95

1,699,676.65

1,746,737.85

1,694,878.62

1,815,086.04

1,828,337.77

1,953,960.63

1,971,323.73

23,092.51

21,764.26

Err:509

241,170.85

255,672.35

467,486.26

477,860.41

634,009.36

501,546.61

443,379.61

141,465.78

6,131,102.50

7,516,725.38

12,217,604.30

9,460,152.76

8,791,078.06

8,374,890.50

8,878,308.13

147,815.83

158,745.63

Err:509

Err:509

Err:509

Err:509
Err:509

Err:509

Err:509

Err:509

Err:509

Err:509

CV. MITRA UTAMA KONSULTAN 47


Err:509
Err:509

Err:509

174,632.87

345,491.07

281,216.92

280,752.49
143,546.73

130,932.42

Err:509

106,141.95

94,862.29

89,880.15

86,563.43

84,566.80

83,016.49

82,128.57

81,240.66

126,923.29

100,639.80

115,786.12

113,195.97

111,056.86

69,682.12

40,834.07

84,200.41

52,158.60

Err:509

265,381.73

285,369.43

356,179.17

Err:509

415,729.08

322,532.92

Err:509

CV. MITRA UTAMA KONSULTAN 48


Err:509
Err:509

Err:509

291,102.72

59,622.04

Err:509

Err:509

Err:509

Err:509

Err:509

Err:509

128,339.74

2,475,000.00

225,000.00

8,095,101.85

#REF!

#REF!

#REF!

#REF!

#REF!

702,117.72

6,556,938.90

8,276,707.55

8,250,921.73

134,347.31

132,701.61

81,968.38

81,260.44

182,995.50

Err:509

Err:509

284,957.87

CV. MITRA UTAMA KONSULTAN 49


53,906.45

44,633.16
55,231.99
254,535.46

Err:509

Err:509

Err:509

Err:509

48,624.69

68,574.02
49,001.89

39,987.71

41,317.23

2,715,206.12

Err:509

Err:509

2,640,310.28

Err:509

278,421.38

85,021.63

Err:509

Err:509

Err:509

Err:509

121,738.05

Err:509

Err:509

Err:509

Err:509

Err:509

Err:509

23,399.77

25,275.27

Err:509

53,428.41

CV. MITRA UTAMA KONSULTAN 50


CV. BLUE Print Consultant
Planning, Supervision & Engineering Consultant
Office: Jl. Yos Sudarso RT. 002 Sebengkok Tarakan
e-mail : blueprintconsultant@yahoo.com

DAFTAR HARGA SATUAN


PAKET KEGIATAN :
USULAN PEMBANGUNAN RUMAH DINAS

LOKASI : TARAKAN
TAHUN : 2020

No. URAIAN BAHAN SATUAN HARGA SATUAN KETERANGAN

(1) (2) (3) (4) (5)

I UPAH (standar harga kota Tarakan)

1 Pekerja Hari Rp. 111,700.00

2 Tukang Hari Rp. 135,070.00

3 Mandor Hari Rp. 160,090.00

4 Kepala Tukang Hari Rp. 140,740.00

II BAHAN

1 Agregat Kasar/batu pecah M3 Rp. 573,600 424.89 Kg


2 Kawat Las Dos Rp. 176,500 17,650.00 Kg
3 Semen (50kg) Zak Rp. 100,000 2,000.00 / kg setara tonasa
4 Semen Putih / Zak Rp. 114,700 2,294.00 / kg
5 Besi beton polos Kg Rp. 15,900
6 Besi beton ulir Kg Rp. 17,000
7 Kawat Ikat / Kg Rp. 22,700
8 Plywood 4 mm / Lbr Rp. 83,000
9 Gypsum Board / Lbr Rp. 80,900
10 Plywood 9 mm / Lbr Rp. 159,900
11 List Gypsum M' Rp. 31,100
12 Tepung Gypsum kg Rp. 6,600
13 Multi Colour / Lbr Rp. 91,000 multiroof
14 Paku Multi Colour / Bh Rp. 400
15 Bubungan Multi Colour / Lbr Rp. 52,700
16 Paku Biasa / Kg Rp. 22,400
17 Paku Seng / Kg Rp. 31,300
18 Paku Skrup / Kg Rp. 400
19 Tegel keramik ( 60 x 60 ) / M2 Rp. 337,000 112,333.33 /Bh setara roman
20 Tegel keramik ( 40 x 40 ) / M2 Rp. 74,700 10,671.43 /Bh setara roman
21 Tegel keramik ( 30 x 30 ) / M2 Rp. 67,500 6,136.36 /Bh setara roman
22 Tegel Keramik ( 20 x 20 ) / M2 Rp. 74,700 2,988.00 /Bh setara roman
23 Cat Kilap / Kg Rp. 51,800 setara avian
24 Cat Tembok / Kg Rp. 83,000 setara vinilex
25 Cat Tembok Dasar / Kg Rp. 83,000 setara vinilex
26 Tear Oil / Kg Rp. 35,300
27 Minyak Cat A / Kg Rp. 25,800
28 Meni / Kg Rp. 33,600
29 Dempul / plamir / Kg Rp. 6,200
30 Kuas Bh Rp. 10,500
31 Amplas / Lbr Rp. 5,600
32 Plitur / Kg Rp. 56,000
33 Minyak Begesting Ltr Rp. 10,900
34 Batu Pecah / M3 Rp. 573,600 395.59 /kg
35 Batu Gunung / M3 Rp. 447,900
36 Kerikil / M3 Rp. 256,800 155.64 /kg
37 Pasir Pasangan / M3 Rp. 187,900 117.44 /kg
38 Tanah Urug / Pasir urug / M3 Rp. 85,600
39 Batu Bata / Bh Rp. 900
40 Paving Bujur sangkar ( t = 10 cm ) / Bh Rp. 3,300
41 Air Bersih Ltr Rp. 53
42 Kayu Perancah / M3 Rp. 2,522,000
43 Kayu Meranti / M3 Rp. 2,522,000
44 Kayu Kapur / Bengkirai / Lembasung / M3 Rp. 3,007,000
45 Kayu Bulat/Dolken Dia. 10 cm Btg Rp. 35,000
46 Kaca Polos T. 5 mm / M2 Rp. 179,600
47 Kunci Tanam / Bh Rp. 171,300
48 Kunci Tanam Biasa / Bh Rp. 51,800
49 Handle Pintu 35 cm / Psg Rp. 20,000
50 Engsel Kupu-kupu 4" / Psg Rp. 22,700 setara solid
51 Engsel Kupu-kupu 3" / Psg Rp. 22,700 setara solid
52 Hak Angin / Bh Rp. 22,700
53 Grendel / Bh Rp. 22,700 setara solid
54 Sealant Tube Rp. 30,000
55 Closed Duduk + aksesoris / Bh Rp. 1,714,000 toto
56 Wastafel Porslint lengkap / Bh Rp. 1,428,400 toto
57 Bak Cuci alumunium satu lubang / Bh Rp. 212,900
58 Floor drain / Bh Rp. 57,100
59 Profil 1100 Lt / Bh Rp. 1,055,800
60 Profil 2200 Lt / Bh Rp. 3,519,600
61 Pipa PVC 1/2 " AW / Btg Rp. 20,600
62 Pipa PVC 3/4 " AW / Btg Rp. 25,000
63 Pipa PVC 2 " AW / Btg Rp. 73,900
64 Pipa PVC 3 " AW / Btg Rp. 130,500
65 Pipa PVC 4 " AW / Btg Rp. 211,000
66 Pipa PVC 6 " AW / Btg Rp. 555,000
67 Kran Air / Bh Rp. 43,900 Onda / Setara
68 Hollow Galvalum 2 x 4,t = 0,3 p = 4 m / Btg Rp. 165,000 41,250.00 /M'
69 Hollow Galvalum 4 x 4,t = 0,3 p = 4 m / Btg Rp. 0.00 /M'
70 Hollow Besi 2 x 4, t = 1.7 mm p = 6 m / Btg Rp. 39,900
71 Hollow Besi 4 x 4, t = 1.7 mm p = 6 m / Btg Rp. 165,600
72 C-75, 0.8 / Btg Rp.
73 C-75, 0.55 / Btg Rp.
74 Reng 32, 0.45 / Btg Rp.
75 Baut ( screw driver ) / Kg Rp. 23,000 575.00 /Buah
76 Dynabolt / Buah Rp. 4,000
77 Talang jurai / Lbr Rp. 150,000 50,000.00 /M'
78 Besi baja C- 75. 0,8 / Btg Rp. 110,000 18,333.33 /M'
79 Besi baja C- 75. 0,8 / Btg Rp. 110,000 18,333.33 /M'
80 Reng 32, 0.45 / Btg Rp. 75,000 12,500.00 /M'
81 Lampu SL / Roll Rp. 55,000 Philips
82 Kabel listrik NYY 4 x 35 / Roll Rp. 140,000
83 Kabel listrik NYM 3 x 4 / Roll Rp. 140,000
84 MCB / bh Rp. 49,800 Eterna / setara
85 Box Panel / bh Rp. 1,007,300
86 Box MCB / bh Rp. 35,000
87 Saklar / bh Rp. 49,500 Broko / setara
88 Stop Kontak / bh Rp. 27,700 Broko / setara
89 Shower / bh Rp. 206,100
90 Plat besi / lbr Rp. 0.00 /Kg

III PERALATAN ( sdh termasuk bahan bakar)

1 PILE DRIVER + HAMMER JE Rp.


2 MESIN LAS JE Rp.
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK : USULAN PEMBANGUNAN RUMAH DINAS


No. PAKET KONTRAK :
NAMA PAKET : USULAN PEMBANGUNAN RUMAH DINAS
PROP / KAB / KODYA : Kalimanta Utara / Kota Tarakan
JENIS PEKERJAAN Penyelenggaraan Sistem Manajemen Keselamatan Konstruksi (SMKK)
SATUAN PEMBAYARAN : Ls

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp.)
1 2 3 4 5 6 7
A PENYIAPAN RKK
1 Dokumen RKK
2 Prosedur dan Instruksi Kerja Set 1.00 5,000,000.00 5,000,000.00
3 Penyiapan Formulir
Jumlah A 5,000,000.00
B SOSIALISASI
1 Spanduk K3 Lb 3.00 150,000.00 450,000.00
2 Pengarahan K3 (Safety Briefing) Org 3.00 15,000.00 45,000.00
Jumlah B 495,000.00
C APD Dan APK
1 Helm Pelindung (Safety Helmet) Buah 30.00 81,439.00 2,443,170.00
2 Sarung Tangan (Safety Gloves) Psg 90.00 20,000.00 1,800,000.00
3 Pelindung Pernapasan dan Mulut (Masker) Box 10.00 50,000.00 500,000.00
4 Sepatu Keselamatan (Rubber Safety Shoes) Psg 30.00 100,000.00 3,000,000.00
5 Rompi Keselamatan (Safety Vest) Buah 30.00 25,000.00 750,000.00
Jumlah C 8,493,170.00
D ASURANSI
1 Asuransi Ls 1.00 4,000,000.00 4,000,000.00
Jumlah D 4,000,000.00
E PERSONIL K3 KONSTRUKSI
1 Ahli K3 Konstruksi OB 1.00 10,000,000.00 10,000,000.00
2 Petugas K3 Konstruksi OB 13.00 3,500,000.00 45,500,000.00
Petugas Tangkap Darurat
Petugas P3K
Petugas Pengatur Lalu Lintas
Jumlah E 55,500,000.00
F PERALATAN P3K
1 Tandu, Obat Luka, Perban dll Ls 1.00 750,000.00 750,000.00
Jumlah F 750,000.00
G RAMBU-RAMBU
1 Rambu Peringatan Buah 3.00 75,000.00 225,000.00
2 Rambu Informasi Buah 3.00 75,000.00 225,000.00
Jumlah G 450,000.00
Lain-lain Terkait Pengendalian Risiko
H Keselamatan Konstruksi
1 Bendera K3 Buah 1.00 150,000.00 150,000.00
2 Lampu Darurat (Emergency Lamp) Buah 3.00 150,000.00 450,000.00
3 Program Inspeksi Ls 1.00 2,000,000.00 2,000,000.00
4 Pelaporan dan Penyelidikan Insiden Ls 1.00 500,000.00 500,000.00
5 Pembuatan Kartu Identitas Pekerja (KIP) Lb 30.00 7,000.00 210,000.00
Jumlah G 3,310,000.00
Jumlah A s/d H 77,998,170.00
Balok 15 x 20 cm

0.15 x 0.2 m

beton cover atas-bawah = 5 cm = 0.05 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang di daerah tumpuan = 20 cm = 0.2 m

jarak sengkang di daerah lapangan 20 cm 0.2 m

Overlap sambungan besi sengkang = 20 cm = 0.2 m

Panjang BALOK dalam 1 m3 = 33.33 m

Jumlah tulangan Pokok = 4 bh

Jumlah tulangan Tengah = - bh

P R O C E S S I N G

Pembesian

Tulangan Pokok

1. D10 ----> 0.62 kg/m' L= 33.33 m x 4 bh = 133.33 m

Wtul. Pokok = 83.00 kg

2. D10 ----> 0.62 kg/m' L= 33.33 m x - bh = - m

Wtul. Pokok = - kg

Tulangan Sengkang

3. D8 ----> 0.393 kg/m' L= 0.50 m x 85 bh = 42.50 m

Wtul. Sengkang = 17.00 kg

4. D8 ----> 0.393 kg/m' L= 0.50 m x 85 bh = 42.50 m

Wtul. Sengkang = 17.00 kg

Begesting

Luasan begesting
Sisi Samping = 6.67 m2 x 2 sisi = 13.33 m2

Sisi Bawah balok = 5.00 m2 x 1 sisi = 5.00 m2

Jadi utk Vol 1 m3 beton diperlukan luasan begesting L total = 18.33 m2 / per 1 m3 beton
KOLOM 15 x 15 cm

0.15 x 0.15 m

beton cover atas-bawah = 5 cm = 0.05 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang di daerah tumpuan = 20 cm = 0.2 m

jarak sengkang di daerah lapangan 20 cm = 0.20 m

Overlap sambungan besi sengkang = 10 cm = 0.10 m

Panjang KOLOM 1 M3 = 44.44 m

Jumlah tulangan Pokok = 4 bh

Volume beton dalam 1 buah kolom = 1.00 m3

P R O C E S S I N G

Pembesian

Tulangan Pokok

1. D10 ----> 0.62 kg/m' L= 44.34 m x 4 bh = 177.38 m

Wtul. Pokok = 110.00 kg

Tulangan Sengkang

3. D8 ----> 0.393 kg/m' L= 0.30 m x 112 bh = 33.60 m

Wtul. Sengkang = 14.00 kg

4. D8 ----> 0.393 kg/m' L= 0.30 m x 112 bh = 33.60 m

Wtul. Sengkang = 14.00 kg

Begesting

Luasan begesting
= 13.33 m2 x 2 sisi = 26.67 m2

= = - m2

L total = 26.67 m2 / per 1 bh kolom

Jadi utk Vol 1 m3 beton diperlukan luasan begesting L total = 26.67 m2 / per 1 m3 beton
SLOOF 15 x 30 cm

0.15 x 0.3 m

beton cover atas-bawah = 5 cm = 0.05 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang di daerah tumpuan = 15 cm = 0.15 m

jarak sengkang di daerah lapangan 15 cm = 0.15 m

Overlap sambungan besi = 10 cm = 0.1 m

Panjang sloof dalam 1 m3 = = 22.22 m

Jumlah tulangan Pokok = 6 bh

Jumlah tulangan Puntir = - bh

P R O C E S S I N G

Pembesian

Tulangan Pokok

D12 ------> 0.887 kg/m' L= 22.22 m x 6 bh = 133.33 m

Wtul. Pokok = 119.00 kg

D12 ------> 0.887 kg/m' L= 22.22 m x - bh = - m

Wtul. Pokok = - kg
Tulangan Sengkang

D10 ------> 0.62 kg/m' L= 0.60 m x 76 bh = 45.60 m

Wtul. Sengkang = 28.27 kg

D10 ------> 0.62 kg/m' L= 0.60 m x 76 bh = 45.60 m

Wtul. Sengkang = 28.27 kg

Begesting

Luasan begesting
Samping = 6.67 m2 x 2 sisi = 13.33 m2

Bawah = = - m2

L total = 13.33 m2
Jadi utk Vol 1 m3 beton diperlukan luasan begesting = 13.33 m2
BQ PAGAR
pekerjaan tanah
→ Gali tnh = p x l x t x (J) (V)

PG1 90.5 x 0.45 x 0.60 x 1 = 24.44

PG2 13.08 x 0.45 x 0.60 x 1 = 3.53

PG3 40 x 0.45 x 0.60 x 1 = 10.80

= 24.44

pekerjaan FONDASI
→ Batu gunung = p x l x t x (J) (V)

PG1 90.5 x 0.45 x 0.60 x 1 = 24.44

PG2 13.08 x 0.45 x 0.60 x 1 = 3.53

PG3 40 x 0.45 x 0.60 x 1 = 10.80

143.58 = 27.97

→ sloof = b x h x p x (J) (V)

1 PG1 I 0.15 x 0.3 x 90.50 x 1 = 4.07

1 PG2 I 0.15 x 0.3 x 13.08 x 1 = 0.59

1 PG3 I 0.15 x 0.2 x 40.00 x 1 = 1.20

= 4.66

→ K1 = b x h x t x (J) (V)

1 PG1 I 0.15 x 0.15 x 2 x 31 = 1.40

1 PG2 I 0.15 x 0.15 x 1 x 5 = 0.11

1 PG3 I 0.15 x 0.15 x 1.3 x 14 = 0.41

= 1.92

→ balok = b x h x p x (J) (V)

1 PG1 I 0.2 x 0.15 x 90.50 x 1 = 2.72

1 PG2 I 0.2 x 0.15 x 13.08 x 1 = 0.39

= 3.11

pekerjaan pasangan
→ dinding bata lt.1 = p x t x - x (J) (V)

1 PG1 I 90.50 x 2.00 x x 1 = 181.00

1 PG2 I 13.08 x 1.00 x x 1 = 13.08

= 194.08
→ plesteran = p x s x t x (J) (V)

1 PG1 I 90.50 x 2 x 2.00 x 1 = 362.00

1 PG2 I 13.08 x 2 x 1.00 x 1 = 26.16

= 388.16

→ Pagar Hollow = l x t x - x (J) (V)

1 PG3 I 2.90 x 1.3 x x 9 = 33.93

1 I 3.90 x 1.3 x x 3 = 15.21

1 P1 I 10.44 x 1.6 x x 1 = 16.70

= 65.84
BQ TYPE 45 A
pekerjaan tanah
→ Gali tnh = p x l x t x (J) (V)

H 19.7 x 0.8 x 0.95 x 1 = 14.97

V 24 x 0.8 x 0.95 x 1 = 18.24

V 0.7 x 0.7 x 0.25 x 3 = 0.37

43.7 = 33.58

→ urug pasir bawah fondasi = (P) x (L) x (T) x (J) (V)

H 19.7 x 0.8 x 0.05 x 1 = 0.79

V 24 x 0.8 x 0.05 x 1 = 0.96

V 0.7 x 0.7 x 0.05 x 3 = 0.07

= 1.82

→ urug pasir bawah lantai = p x l x t x (J) (V)

7.50 x 3 x 0.25 x 1 = 5.63

7.50 x 3 x 0.25 x 1 = 5.63

1.20 x 1.5 x 0.20 x 1 = 0.36

2.40 x 0.8 x 0.10 x 1 = 0.19

= 11.80

→ urugan tanah kembali = p x l x t x (J) (V)

galian 33.58 x 1 x 1 x 1 = 33.58

fp1 0.29 x 1 x -1 x 1 = -0.29

fp2 16.61 x 1 x -1 x 1 = -16.61

ur. pasir dibawah fondasi 3.50 x 1 x -1 x 1 = -3.50

= 13.18

pekerjaan FONDASI
→ Batu gunung = p x l x t x (J) (V)

H 19.7 x 0.475 x 0.80 x 1 = 7.49

V 24 x 0.475 x 0.80 x 1 = 9.12

43.7 = 16.61

pekerjaan beton
→ cor rabat = a x t x - x (J) (V)

1 I 17.67 x 0.1 x 1.00 x 1 = 1.77

= 1.77
→ lantai kerja = p x l x t x (J) (V)

1 I 19.7 x 0.8 x 0.10 x 1 = 1.58

1 I 24 x 0.8 x 0.1 x 1 = 1.92

= 3.50

→ sloof = b x h x p x (J) (V)

1 I 0.15 x 0.2 x 43.70 x 1 = 1.31

1 I 0.15 x 0.2 x 4.70 x 1 = 0.14

= 1.45

→ footplate = p x l x t x (J) (V)

1 I 0.7 x 0.7 x 0.20 x 3 = 0.29

= 0.29

→ lantai = p x l x t x (J) (V)

1 I 2.85 x 4.85 x 0.10 x 1 = 1.38

1 I 2.85 x 2.35 x 0.10 x 1 = 0.67

1 I 2.85 x 2.85 x 0.10 x 1 = 0.81

1 I 2.85 x 2.85 x 0.10 x 1 = 0.81

1 I 1.05 x 1.35 x 0.10 x 1 = 0.14

1 I 1.65 x 1.35 x 0.10 x 1 = 0.22

= 4.04

→ K1 = b x h x t x (J) (V)

1 I 0.1 x 0.15 x 4 x 18 = 1.08

1 I 0.1 x 0.15 x 2.5 x 1 = 0.04

1 I 0.1 x 0.15 x 2.25 x 2 = 0.07

1 I 0.1 x 0.15 x 3.4 x 1 = 0.05

= 1.24

→ balok latei = b x h x p x (J) (V)

1 I 0.1 x 0.15 x 10.20 x 1 = 0.15

1 I 0.1 x 0.15 x 11.00 x 1 = 0.17


1 I 0.1 x 0.15 x 15.40 x 1 = 0.23

= 0.55

→ dak atap = p x l x t x (J) (V)

1 I 1.1 x 2.1 x 0.10 x 1 = 0.23

1 I 1.1 x 1.4 x 0.10 x 1 = 0.15

= 0.39
→ kanopi = p x l x t x (J) (V)

1 I 6.62 x 0.4 x 0.08 x 1 = 0.21

1 I 1.1 x 1.4 x 0.08 x 1 = 0.12

= 0.34

→ ringbalk = b x h x p x (J) (V)

1 I 0.1 x 0.15 x 21.00 x 1 = 0.32

1 I 0.1 x 0.15 x 24.00 x 1 = 0.36

= 0.68

pekerjaan pasangan
→ dinding bata lt.1 = p x t x - x (J) (V)

1 horisontal I 19.7 x 4.00 x 1.00 x 1 = 78.80

1 vertikal I 24 x 4.00 x 1.00 x 1 = 96.00

1 vertikal I 0.46 x 2.5 x 1.00 x 1 = 1.15


1 I x x x = 0.00

1 I x x x = 0.00

1 lubang I 21.09 x 1 x 1.00 x -1 = -21.09

= 154.86

→ plesteran = p x s x - x (J) (V)

1 I 154.86 x 2 x 1.00 x 1 = 309.72

= 309.72

→ keramik 40x40 = a x - x - x (J) (V)

1 dalam I 39.74 x 1 x 1.00 x 1 = 39.74

1 teras I 1.50 x 1.2 x 1.00 x 1 = 1.80

1 belakang I 1.22 x 0.8 x 1.00 x 1 = 0.98

= 42.51

→ keramik lantai wc = p x l x - x (J) (V)

1 I 1.70 x 1.4 x 1.00 x 1 = 2.38

= 2.38

→ keramik dinding wc = p x t x - x (J) (V)

1 I 5.40 x 1.6 x 1.00 x 1 = 8.64

= 8.64

→ kisi hollow = p x t x - x (J) (V)

1 depan I 1.38 x 0.4 x 1.00 x 1 = 0.55

1 belakang I 1.05 x 0.4 x 1.00 x 1 = 0.42


= 0.97
→ lubang angin = n x - x - x (J) (V)

1 I 15.00 x 1 x 1.00 x 1 = 15.00

= 15.00

pekerjaan plafond
→ rangka / plafond = p x l x t x (J) (V)

1 I 42.12 x 1 x 1.00 x 1 = 42.12

1 I 25.75 x 1 x 1.00 x 1 = 25.75

= 67.86

→ list = p x - x - x (J) (V)

1 selasar I 30.48 x 1 x 1.00 x 1 = 30.48

1 kamar I 63.80 x 1 x 1.00 x 1 = 63.80

= 94.28

pekerjaan atap
→ rangka atap / atap = a x - x - x (J) (V)

6.47 x 1 x 1.00 x 2 = 12.93

21.69 x 1 x 1.00 x 2 = 43.38

15.17 x 1 x 1.00 x 2 = 30.35

= 86.66

→ bubungan = p x - x - x (J) (V)

14.48 x 1 x 1 x 1 = 14.48

12.04 x 1 x 1 x 1 = 12.04

4.72 x 1 x 1 x 1 = 4.72

3.00 x 1 x 1 x 1 = 3.00

= 34.24

→ List plank kayu = p x - x - x (J) (V)

36.40 x 1 x 1.00 x 1 = 36.40

= 36.40

pekerjaan sanitasi
→ closed = n x - x - x (J) (V)

lt 1 1.00 x 1 x 1.00 x 1 = 1.00

= 1.00

→ 4" = p x - x - x (J) (V)

lt.1 8.00 x 1 x 1.00 x 1 = 8.00

= 8.00
→ 3" = p x - x - x (J) (V)

lt.1 12.00 x 1 x 1.00 x 1 = 12.00

= 12.00

→ 3/4" = p x - x - x (J) (V)

lt.1 20.00 x 1 x 1.00 x 1 = 20.00

= 20.00

pekerjaan Kusen
→ kaca = p x t x - x (J) (V)

1.80 x 0.5 x 1.00 x 1 = 0.90

= 0.90

pekerjaan elektrikal
→ listrik = watt x n x - x (J) (V)

tv 55 x 2 x 1.00 x 1 = 110.00

rice cooker 400 x 1 x 0.00 x 1 = 0.00

kipas angin 60 x 1 x 1.00 x 1 = 60.00

AC 820 x 1 x 1.00 x 1 = 820.00

kulkas 128 x 1 x 1.00 x 1 = 128.00

lampu 18 x 6 x 1.00 x 1 = 108.00

lampu 15 x 2 x 1.00 x 1 = 30.00

= 1256.00 watt

→ arus = Listrik : volt (V)

1256.00 : 220 = 5.71

400 : 1 = 0.00

= 5.71 A

pekerjaan teralis
→ = a x - x - x (J) (V)

j1 1.80 x 1 x 1.00 x 3 = 5.40

j2 0.75 x 1 x 1.00 x 3 = 2.25

j3 0.50 x 1 x 1.00 x 1 = 0.50

= 5.40

pekerjaan Septictank
→ pasir = p x l x t x (J) (V)

1.00 x 1.5 x 0.10 x 1 = 0.15

= 0.15
→ lantai = p x l x t x (J) (V)

1.00 x 1.5 x 0.10 x 1 = 0.15

= 0.15

→ dinding = p x l x t x (J) (V)

1.50 x 1.5 x 0.10 x 2 = 0.45

0.80 x 1.5 x 0.10 x 2 = 0.24

= 0.69

→ atap = p x l x t x (J) (V)

1.50 x 1.00 x 0.10 x 1 = 0.15

= 0.15

→ bata = p x t x - x (J) (V)

2.50 x 1.3 x 1.00 x 2 = 6.50

= 6.50

pekerjaan kusen
→ pintu dan jendela = p x b x h x (J) (V)

p1 4.92 x 0.06 x 0.12 x 4 = 0.14

p2 4.82 x 0.06 x 0.12 x 1 = 0.03

J1 7.26 x 0.06 x 0.12 x 3 = 0.16

J2 4.24 x 0.06 x 0.12 x 3 = 0.09

J3 3.24 x 0.06 x 0.12 x 1 = 0.02

J4 5.76 x 0.06 x 0.12 x 1 = 0.04

= 0.49
CV. BLUE Print Consultant
Planning, Supervision & Engineering Consultant
Office: Jl. Yos Sudarso RT. 002 Sebengkok Tarakan
e-mail : blueprintconsultant@yahoo.com

REKAPITULASI
ESTIMATE ENGINEERING (EE)
PAKET KEGIATAN : PENGEMBANGAN RTH SAMPING TAMAN BERTUAH
LOKASI : TARAKAN
TAHUN : 2020

JUMLAH BIAYA
No. URAIAN PEKERJAAN
( Rp. )
I PEKERJAAN PERSIAPAN Rp. 3,597,195.00
II PEKERJAAN AREA TAMAN Rp. 641,848,723.41

JUM LAH Rp. 645,445,918.41

PPn 10% Rp. 64,544,591.84

TOTAL KESELURUHAN Rp. 709,990,510.25

DIBULATKAN Rp. 709,990,000.00


Terbilang :

Tujuh Ratus Sembilaan Juta Sembilan Ratus Sembilan Puluh Ribu Rupiah

Tarakan, 18 Maret 2020


Di Periksa Konsultan Perencana
Pejabat Pembuat Komitmen CV. BLUE Print Consultant
Dinas Pekerjaan Umum dan Tata Ruang
Kota Tarakan

Drs. BROTO SUBAGYO MUHAMMAD RAMLI, ST


NIP. 19620314 199003 1 001 Direktur
CV. BLUE Print Consultant
Planning, Supervision & Engineering Consultant
Office: Jl. Yos Sudarso RT. 002 Sebengkok Tarakan
e-mail : blueprintconsultant@yahoo.com

ESTIMATE ENGINEERING (EE)


PAKET KEGIATAN : PENGEMBANGAN RTH SAMPING TAMAN BERTUAH
LOKASI : TARAKAN
TAHUN : 2020

HARGA SATUAN JUMLAH


No. URAIAN PEKERJAAN VOLUME SATUAN
( Rp.) ( Rp.)

I PEKERJAAN PERSIAPAN
1 Plank Nama Proyek 1.00 ls 500,000.00 500,000.00
2 Dokumentasi 1.00 ls 750,000.00 750,000.00
3 K3 1.00 ls 2,347,195.00 2,347,195.00

Total I 3,597,195.00

II PEKERJAAN AREA TAMAN


1 Urugan Pasir 202.93 m3 158,533.14 32,171,129.09
2 Tanah Urug 72.90 m3 158,533.14 11,557,065.54
3 Pemasangan Paving Press 1,344.94 m2 255,175.17 343,195,800.13
4 Pembuatan Pengunci Paving
- Cor Beton K-175 27.94 m3 1,455,517.75 40,671,386.87
- Bekisting 39.03 m2 255,720.19 9,980,065.79
5 Pembuatan Jembatan Beton
- Cor Beton K-225 3.50 m3 1,533,564.65 5,361,342.03
- Pembesian 326.10 kg 21,764.90 7,097,448.33
- Bekisting 17.48 m2 255,720.19 4,469,988.87
6 Pemasangan Pipa Galvanis 2" 15.00 m' 101,566.67 1,523,500.00
7 Pembuatan Kolom 15x15
- Cor Beton K-175 0.09 m3 1,455,517.75 130,996.60
- Pembesian 14.83 kg 21,764.90 322,860.59
- Bekisting 1.20 m2 255,720.19 306,864.22
8 Pohon Palem Ekor Tupai 30.00 Pohon 525,000.00 15,750,000.00
9 Rumput Gajah Mini 153.00 m2 61,500.00 9,409,500.00
10 Pohon Pucuk Merah 90.00 Pohon 112,200.00 10,098,000.00
11 Tenda Kerucut Ukuran 2x2 Meter 15.00 Unit 1,300,000.00 19,500,000.00
12 Pekerjaan Pagar BRC
- Cor Beton Sloof Tiang K-175 2.56 m3 1,455,517.75 3,720,303.36
- Bekisting 17.04 m2 255,720.19 4,357,471.99
- Tiang BRC 2" 142.00 Btg 200,000.00 28,400,000.00
- Pagar BRC 175x240 139.00 Lbr 675,000.00 93,825,000.00
Total II 641,848,723.41
A.2.3.1 HARGA SATUAN PEKERJAAN TANAH
A.2.3.1.1 Penggalian 1 m³ tanah biasa sedalam 1 m
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.750 111,780.00 83,835.00
2 Mandor L.04 OH 0.025 160,090.00 4,002.25
Jumlah Tenaga Kerja 87,837.25
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 87,837.25
E Overhead + Profit ( Contoh 15% ) 15% x D 13,175.59
F Harga Satuan Pekerjaan ( D + E ) 101,012.84

A.2.3.1.9 Pengurukan kembali 1 m³ galian tanah


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 111,780.00 55,890.00
2 Mandor L.04 OH 0.050 160,090.00 8,004.50
Jumlah Tenaga Kerja 63,894.50
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 63,894.50
E Overhead + Profit ( Contoh 15% ) 15% x D 9,584.18
F Harga Satuan Pekerjaan ( D + E ) 73,478.68

71
A.2.3.1.11 Pengurugan 1 m³ dengan pasir urug
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7

A Tenaga
1 Pekerja L.01 OH 0.300 111,780.00 33,534.00
2 Mandor L.04 OH 0.010 160,090.00 1,600.90
Jumlah Tenaga Kerja 35,134.90
B Bahan
1 Pasir Urug m³ 1.200 85,600.00 102,720.00
Jumlah Harga Bahan 102,720.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 137,854.90
E Overhead + Profit ( Contoh 15% ) 15% x D 20,678.24
F Harga Satuan Pekerjaan ( D + E ) 158,533.14

A.3.2.1.1 Pemasangan 1 m2 Paving blok


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.200 111,780.00 22,356.00
2 Tukang Batu L.02 OH 0.300 135,070.00 40,521.00
3 Kepala Tukang L.03 OH 0.030 140,740.00 4,222.20
4 Mandor L.04 OH 0.025 160,090.00 4,002.25
Jumlah Tenaga Kerja 71,101.45
B Bahan
1 Paving m2 1.000 132,000.00 132,000.00
2 Pasir Pasang m³ 0.100 187,900.00 18,790.00
Jumlah Harga Bahan 150,790.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 221,891.45
E Overhead + Profit ( Contoh 15% ) 15% x D 33,283.72
F Harga Satuan Pekerjaan ( D + E ) 255,175.17

72
A.3.2.1.2 Pemasangan 1 m' Kanstin uk. 15/20 30x50
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 111,780.00 55,890.00
2 Tukang Batu L.02 OH 0.050 135,070.00 6,753.50
3 Kepala Tukang L.03 OH 0.010 140,740.00 1,407.40
4 Mandor L.04 OH 0.001 160,090.00 160.09
Jumlah Tenaga Kerja 64,210.99
B Bahan
1 Semen (PC) zak 0.360 75,000.00 27,000.00
2 Pasir Pasang m2 0.001 187,900.00 187.90
3 Kanstin uk. 15/20 30x50 bh 2.000 41,800.00 83,600.00
Jumlah Harga Bahan 110,787.90
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 174,998.89
E Overhead + Profit ( Contoh 15% ) 15% x D 26,249.83
F Harga Satuan Pekerjaan ( D + E ) 201,248.72

73
A.4.1.1. HARGA SATUAN PEKERJAAN BETON
A.4.1.1.5. Membuat 1 m³ beton mutu f 'c = 14,5 Mpa ( K - 175 ), Slump ( 12 ± 2 ) cm, w/c = 0.66
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.650 111,780.00 184,437.00
2 Tukang Batu L.02 OH 0.275 135,070.00 37,144.25
3 Kepala Tukang L.03 OH 0.028 140,740.00 3,940.72
4 Mandor L.04 OH 0.083 160,090.00 13,287.47
Jumlah Tenaga Kerja 238,809.44
B Bahan
1 Semen Portland Kg 326.000 1,500.00 489,000.00
2 Pasir Beton Kg 760.000 117.44 89,252.50
3 Kerikil ( Maks 30mm ) Kg 1,029.000 424.89 437,210.67
4 Air Liter 215.000 53.00 11,395.00
Jumlah Harga Bahan 1,026,858.17
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,265,667.61
E Overhead + Profit ( Contoh 15% ) 15% x D 189,850.14
F Harga Satuan Pekerjaan ( D + E ) 1,455,517.75

A.4.1.1.7. Membuat 1 m³ beton mutu f 'c = 19,3 Mpa ( K - 225 ), Slump ( 12 ± 2 ) cm, w/c = 0.58
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.650 111,780.00 184,437.00
2 Tukang Batu L.02 OH 0.275 135,070.00 37,144.25
3 Kepala Tukang L.03 OH 0.028 140,740.00 3,940.72
4 Mandor L.04 OH 0.083 160,090.00 13,287.47
Jumlah Tenaga Kerja 238,809.44
B Bahan
1 Semen Portland Kg 371.000 1,500.00 556,500.00
2 Pasir Beton Kg 698.000 117.44 81,971.38
3 Kerikil ( Maks 30mm ) Kg 1,047.000 424.89 444,858.67
4 Air Liter 215.000 53.00 11,395.00
Jumlah Harga Bahan 1,094,725.04
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,333,534.48
E Overhead + Profit ( Contoh 15% ) 15% x D 200,030.17
F Harga Satuan Pekerjaan ( D + E ) 1,533,564.65

74
A.4.1.1.17. Pembesian 10 Kg dengan besi polos
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.070 111,780.00 7,824.60
2 Tukang Besi L.02 OH 0.070 135,070.00 9,454.90
3 Kepala Tukang L.03 OH 0.007 140,740.00 985.18
4 Mandor L.04 OH 0.004 160,090.00 640.36
Jumlah Tenaga Kerja 18,905.04
B Bahan
1 Besi Beton Polos Kg 10.500 15,900.00 166,950.00
2 Kawat Beton Kg 0.150 22,700.00 3,405.00
Jumlah Harga Bahan 170,355.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 189,260.04
E Overhead + Profit ( Contoh 15% ) 15% x D 28,389.01
F Harga Satuan Pekerjaan ( D + E ) 217,649.05
Harga Satuan Pekerjaan /1 kg besi F/10 21,764.90

A.4.1.1.21. Pemasangan 1 m² bekisting untuk sloof


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.520 111,780.00 58,125.60
2 Tukang Kayu L.02 OH 0.260 135,070.00 35,118.20
3 Kepala Tukang L.03 OH 0.026 140,740.00 3,659.24
4 Mandor L.04 OH 0.026 160,090.00 4,162.34
Jumlah Tenaga Kerja 101,065.38
B Bahan
1 Kayu Kelas III m³ 0.045 2,522,000.00 113,490.00
2 Paku 5 - 10 cm Kg 0.300 22,400.00 6,720.00
3 Minyak Bekisting Liter 0.100 10,900.00 1,090.00
Jumlah Harga Bahan 121,300.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 222,365.38
E Overhead + Profit ( Contoh 15% ) 15% x D 33,354.81
F Harga Satuan Pekerjaan ( D + E ) 255,720.19

75
A.4.4.1. HARGA SATUAN PEKERJAAN PASANGAN DINDING
A.4.4.1.3. Pemasangan 1 m² dinding bata merah ( 9 x 9 x 18 ) cm tebal 1 batu campuran 1 SP : 4 PP
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 111,780.00 55,890.00
2 Tukang Batu L.02 OH 0.200 135,070.00 27,014.00
3 Kepala Tukang L.03 OH 0.020 140,740.00 2,814.80
4 Mandor L.04 OH 0.025 160,090.00 4,002.25
Jumlah Tenaga Kerja 89,721.05
B Bahan
1 Bata Merah m2 55.000 900.00 49,500.00
2 Semen Portland Kg 20.861 1,500.00 31,291.07
3 Pasir Pasang m³ 0.073 187,900.00 13,730.12
Jumlah Harga Bahan 94,521.19
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 184,242.24
E Overhead + Profit ( Contoh 15% ) 15% x D 27,636.34
F Harga Satuan Pekerjaan ( D + E ) 211,878.58

A.4.4.2. HARGA SATUAN PEKERJAAN PLESTERAN


A.4.4.2.4. Pemasangan 1 m² plesteran 1 SP : 4 PP tebal 15 mm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 111,780.00 33,534.00
2 Tukang Batu L.02 OH 0.150 135,070.00 20,260.50
3 Kepala Tukang L.03 OH 0.015 140,740.00 2,111.10
4 Mandor L.04 OH 0.015 160,090.00 2,401.35
Jumlah Tenaga Kerja 58,306.95
B Bahan
1 Semen Portland Kg 6.240 1,500.00 9,360.00
2 Pasir Pasang m³ 0.024 187,900.00 4,509.60
Jumlah Harga Bahan 13,869.60
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 72,176.55
E Overhead + Profit ( Contoh 15% ) 15% x D 10,826.48
F Harga Satuan Pekerjaan ( D + E ) 83,003.03

76
CV. BLUE Print Consultant
Planning, Supervision & Engineering Consultant
Office: Jl. Yos Sudarso RT. 002 Sebengkok Tarakan
e-mail : blueprintconsultant@yahoo.com

DAFTAR HARGA SATUAN


PAKET KEGIATAN :
PENGEMBANGAN RTH SAMPING TAMAN BERTUAH

LOKASI : TARAKAN
TAHUN : 2020

No. URAIAN BAHAN SATUAN HARGA SATUAN KETERANGAN

(1) (2) (3) (4) (5)

I UPAH (standar harga kota Tarakan)

1 Pekerja Hari Rp. 111,780.00


2 Tukang Hari Rp. 135,070.00
3 Mandor Hari Rp. 160,090.00
4 Kepala Tukang Hari Rp. 140,740.00

II BAHAN

1 Agregat Kasar/batu pecah M3 Rp. 573,600 424.89 Kg


2 Semen (50kg) Zak Rp. 75,000 1,500.00 / kg setara tonasa
3 Besi beton polos Kg Rp. 15,900
4 Kawat Ikat / Kg Rp. 22,700
5 Plywood 4 mm / Lbr Rp. 83,000
6 Pipa Galvanis 2" / Btg Rp. 609,400
7 Paku Biasa / Kg Rp. 22,400
8 Tear Oil / Kg Rp. 35,300
9 Minyak Begesting Ltr Rp. 10,900
10 Batu Pecah / M3 Rp. 573,600 395.59 /kg
11 Pasir Pasangan / M3 Rp. 187,900 117.44 /kg
12 Tanah Urug / Pasir urug / M3 Rp. 85,600
13 Batu Bata / Bh Rp. 900
14 Paving Blok ( t = 8 cm ) / Bh Rp. 3,000
15 Air Bersih Ltr Rp. 53
16 Kayu Perancah / M3 Rp. 2,522,000
17 Kayu Meranti / M3 Rp. 2,522,000
18 Kayu Kapur / Bengkirai / Lembasung / M3 Rp. 3,007,000
19 Kanstin / bh Rp. 41,800
20 Pohon Palem Ekor Tupai / Pokok Rp. 525,000
21 Rumput Gajah Mini / M2 Rp. 77,100
22 Pohon Pucuk Merah / Pokok Rp. 178,000
23 BRC 175x240 / Lbr Rp. 675,000
24 Tiang BRC Galvanis / Btg Rp. 200,000
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : PENGEMBANGAN RTH SAMPING TAMAN BERTUAH
PROP / KAB / KODYA : Kalimanta Utara / Kota Tarakan
JENIS PEKERJAAN Penyelenggaraan Sistem Manajemen Keselamatan Konstruksi (SMKK)
SATUAN PEMBAYARAN : Ls

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp.)
1 2 3 4 5 6 7
A SOSIALISASI
1 Spanduk K3 Lb 1.00 150,000.00 150,000.00
2 Pengarahan K3 (Safety Briefing) Org 1.00 15,000.00 15,000.00
Jumlah B 165,000.00
B APD Dan APK
1 Helm Pelindung (Safety Helmet) Buah 5.00 81,439.00 407,195.00
2 Sarung Tangan (Safety Gloves) Psg 15.00 20,000.00 300,000.00
4 Sepatu Keselamatan (Rubber Safety Shoes) Psg 5.00 100,000.00 500,000.00
5 Rompi Keselamatan (Safety Vest) Buah 5.00 25,000.00 125,000.00
Jumlah C 1,332,195.00
C ASURANSI
1 Asuransi Ls 1.00 700,000.00 700,000.00
Jumlah D 700,000.00
D RAMBU-RAMBU
1 Rambu Peringatan Buah 1.00 75,000.00 75,000.00
2 Rambu Informasi Buah 1.00 75,000.00 75,000.00
Jumlah G 150,000.00
Jumlah A s/d H 2,347,195.00
CV. BLUE Print Consultant
Planning, Supervision & Engineering Consultant
Office: Jl. Yos Sudarso RT. 002 Sebengkok Tarakan
e-mail : blueprintconsultant@yahoo.com

REKAPITULASI
ESTIMATE ENGINEERING (EE)
PAKET KEGIATAN : PEMBUATAN TAMAN JUATA KERIKIL
LOKASI : TARAKAN
TAHUN : 2020

JUMLAH BIAYA
No. URAIAN PEKERJAAN
( Rp. )
I PEKERJAAN PERSIAPAN Rp. 3,087,195.00
II PEKERJAAN AREA TAMAN Rp. 169,640,917.59

JUM LAH Rp. 172,728,112.59

PPn 10% Rp. 17,272,811.26

TOTAL KESELURUHAN Rp. 190,000,923.85

DIBULATKAN Rp. 190,000,000.00


Terbilang :

Seratus Sembilan Puluh Juta Rupiah

Tarakan, 18 Maret 2020


Di Periksa Konsultan Perencana
Pejabat Pembuat Komitmen CV. BLUE Print Consultant
Dinas Pekerjaan Umum dan Tata Ruang
Kota Tarakan

Drs. BROTO SUBAGYO MUHAMMAD RAMLI, ST


NIP. 19620314 199003 1 001 Direktur
CV. BLUE Print Consultant
Planning, Supervision & Engineering Consultant
Office: Jl. Yos Sudarso RT. 002 Sebengkok Tarakan
e-mail : blueprintconsultant@yahoo.com

ESTIMATE ENGINEERING (EE)


PAKET KEGIATAN : PEMBUATAN TAMAN JUATA KERIKIL
LOKASI : TARAKAN
TAHUN : 2020

HARGA SATUAN JUMLAH


No. URAIAN PEKERJAAN VOLUME SATUAN
( Rp.) ( Rp.)

I PEKERJAAN PERSIAPAN
1 Plank Nama Proyek 1.00 ls 500,000.00 500,000.00
2 Dokumentasi 1.00 ls 750,000.00 750,000.00
3 K3 1.00 ls 1,837,195.00 1,837,195.00

Total I 3,087,195.00

II PEKERJAAN AREA TAMAN


1 Galian Tanah 0.20 m3 101,012.84 20,202.57
2 Pasir Urug 38.12 m3 158,533.14 6,042,648.97
3 Pemasangan Paving Press 128.82 m2 255,175.17 32,871,665.08
4 Pembuatan Pengunci Paving
- Cor Beton K-175 7.81 m3 1,455,517.75 11,371,377.96
- Bekisting 18.54 m2 255,720.19 4,741,563.71
5 Pohon Palem Ekor Tupai 7.00 Pohon 525,000.00 3,675,000.00
6 Rumput Gajah Mini 56.00 m2 61,500.00 3,444,000.00
7 Pohon Pucuk Merah 36.00 Pohon 112,200.00 4,039,200.00
8 Aksessories Taman Bermain
- Jongkang-jongket 1.00 Unit 1,700,000.00 1,700,000.00
- Gelongsor 1.00 Unit 5,700,000.00 5,700,000.00
- Palang Besi 1.00 Unit 2,800,000.00 2,800,000.00
- Besi Berayun 1.00 Unit 3,200,000.00 3,200,000.00
- Kursi Taman 5.00 Unit 1,100,000.00 5,500,000.00
9 Pekerjaan Gazebo
Foot Plat 50x50x20
- Cor Beton K-175 0.20 m3 1,455,517.75 291,103.55
- Pembesian 23.81 kg 21,764.90 518,178.85
- Bekisting 0.80 m2 255,720.19 204,576.15
Pas Bata Rolag 3.24 m2 268,803.58 870,923.60
Urugan Pasir 1.88 m3 158,533.14 298,676.43
Cor Dinding Lantai 1.79 m3 1,455,517.75 2,605,085.66
Cor Lantai Rabat 1.88 m3 1,455,517.75 2,742,195.44
Kolom 15x15
- Cor Beton K-175 0.18 m3 1,455,517.75 261,993.19
- Pembesian 29.43 kg 21,764.90 640,628.20
- Bekisting 1.87 m2 255,720.19 478,094.46
Balok 10x15
- Cor Beton K-175 0.18 m3 1,455,517.75 261,993.19
- Pembesian 41.66 kg 21,764.90 906,617.10
- Bekisting 1.35 m2 255,720.19 345,222.25
Kuda - kuda kayu 5/10 0.11 m3 6,557,306.90 752,778.83
Usuk 5/5 0.12 m3 6,557,306.90 793,434.13
Pas Atap MultiRoof 10.72 m2 154,940.06 1,660,957.48
Pas Nok MultiRoof 9.20 m' 115,682.84 1,064,282.09
ListPlank 2.40 m2 87,404.89 209,771.73
Pas Keramik 40x40 9.00 m2 743,839.31 6,694,553.75
10 Pembuatan Pergola
Pembuatan Pergola Dengan Rangka Hollow 79.20 m2 405,419.11 32,109,193.22
13 Pekerjaan Pagar BRC
- Tiang BRC 2" 36.00 Btg 200,000.00 7,200,000.00
- Pagar BRC 175x240 35.00 Lbr 675,000.00 23,625,000.00
HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN VOLUME SATUAN
( Rp.) ( Rp.)

Total II 169,640,917.59
A.2.3.1 HARGA SATUAN PEKERJAAN TANAH
A.2.3.1.1 Penggalian 1 m³ tanah biasa sedalam 1 m
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.750 111,780.00 83,835.00
2 Mandor L.04 OH 0.025 160,090.00 4,002.25
Jumlah Tenaga Kerja 87,837.25
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 87,837.25
E Overhead + Profit ( Contoh 15% ) 15% x D 13,175.59
F Harga Satuan Pekerjaan ( D + E ) 101,012.84

A.2.3.1.9 Pengurukan kembali 1 m³ galian tanah


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 111,780.00 55,890.00
2 Mandor L.04 OH 0.050 160,090.00 8,004.50
Jumlah Tenaga Kerja 63,894.50
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 63,894.50
E Overhead + Profit ( Contoh 15% ) 15% x D 9,584.18
F Harga Satuan Pekerjaan ( D + E ) 73,478.68

82
A.2.3.1.11 Pengurugan 1 m³ dengan pasir urug
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7

A Tenaga
1 Pekerja L.01 OH 0.300 111,780.00 33,534.00
2 Mandor L.04 OH 0.010 160,090.00 1,600.90
Jumlah Tenaga Kerja 35,134.90
B Bahan
1 Pasir Urug m³ 1.200 85,600.00 102,720.00
Jumlah Harga Bahan 102,720.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 137,854.90
E Overhead + Profit ( Contoh 15% ) 15% x D 20,678.24
F Harga Satuan Pekerjaan ( D + E ) 158,533.14

A.3.2.1.1 Pemasangan 1 m2 Paving blok


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.200 111,780.00 22,356.00
2 Tukang Batu L.02 OH 0.300 135,070.00 40,521.00
3 Kepala Tukang L.03 OH 0.030 140,740.00 4,222.20
4 Mandor L.04 OH 0.025 160,090.00 4,002.25
Jumlah Tenaga Kerja 71,101.45
B Bahan
1 Paving m2 1.000 132,000.00 132,000.00
2 Pasir Pasang m³ 0.100 187,900.00 18,790.00
Jumlah Harga Bahan 150,790.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 221,891.45
E Overhead + Profit ( Contoh 15% ) 15% x D 33,283.72
F Harga Satuan Pekerjaan ( D + E ) 255,175.17

83
A.3.2.1.2 Pemasangan 1 m' Kanstin uk. 15/20 30x50
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 111,780.00 55,890.00
2 Tukang Batu L.02 OH 0.050 135,070.00 6,753.50
3 Kepala Tukang L.03 OH 0.010 140,740.00 1,407.40
4 Mandor L.04 OH 0.001 160,090.00 160.09
Jumlah Tenaga Kerja 64,210.99
B Bahan
1 Semen (PC) zak 0.360 75,000.00 27,000.00
2 Pasir Pasang m2 0.001 187,900.00 187.90
3 Kanstin uk. 15/20 30x50 bh 2.000 51,666.67 103,333.33
Jumlah Harga Bahan 130,521.23
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 194,732.22
E Overhead + Profit ( Contoh 15% ) 15% x D 29,209.83
F Harga Satuan Pekerjaan ( D + E ) 223,942.06

A.4.1.1. HARGA SATUAN PEKERJAAN BETON


A.4.1.1.5. Membuat 1 m³ beton mutu f 'c = 14,5 Mpa ( K - 175 ), Slump ( 12 ± 2 ) cm, w/c = 0.66
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.650 111,780.00 184,437.00
2 Tukang Batu L.02 OH 0.275 135,070.00 37,144.25
3 Kepala Tukang L.03 OH 0.028 140,740.00 3,940.72
4 Mandor L.04 OH 0.083 160,090.00 13,287.47
Jumlah Tenaga Kerja 238,809.44
B Bahan
1 Semen Portland Kg 326.000 1,500.00 489,000.00
2 Pasir Beton Kg 760.000 117.44 89,252.50
3 Kerikil ( Maks 30mm ) Kg 1,029.000 424.89 437,210.67
4 Air Liter 215.000 53.00 11,395.00
Jumlah Harga Bahan 1,026,858.17
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,265,667.61
E Overhead + Profit ( Contoh 15% ) 15% x D 189,850.14
F Harga Satuan Pekerjaan ( D + E ) 1,455,517.75

84
A.4.1.1.7. Membuat 1 m³ beton mutu f 'c = 19,3 Mpa ( K - 225 ), Slump ( 12 ± 2 ) cm, w/c = 0.58
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.650 111,780.00 184,437.00
2 Tukang Batu L.02 OH 0.275 135,070.00 37,144.25
3 Kepala Tukang L.03 OH 0.028 140,740.00 3,940.72
4 Mandor L.04 OH 0.083 160,090.00 13,287.47
Jumlah Tenaga Kerja 238,809.44
B Bahan
1 Semen Portland Kg 371.000 1,500.00 556,500.00
2 Pasir Beton Kg 698.000 117.44 81,971.38
3 Kerikil ( Maks 30mm ) Kg 1,047.000 424.89 444,858.67
4 Air Liter 215.000 53.00 11,395.00
Jumlah Harga Bahan 1,094,725.04
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,333,534.48
E Overhead + Profit ( Contoh 15% ) 15% x D 200,030.17
F Harga Satuan Pekerjaan ( D + E ) 1,533,564.65

A.4.1.1.17. Pembesian 10 Kg dengan besi polos


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.070 111,780.00 7,824.60
2 Tukang Besi L.02 OH 0.070 135,070.00 9,454.90
3 Kepala Tukang L.03 OH 0.007 140,740.00 985.18
4 Mandor L.04 OH 0.004 160,090.00 640.36
Jumlah Tenaga Kerja 18,905.04
B Bahan
1 Besi Beton Polos Kg 10.500 15,900.00 166,950.00
2 Kawat Beton Kg 0.150 22,700.00 3,405.00
Jumlah Harga Bahan 170,355.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 189,260.04
E Overhead + Profit ( Contoh 15% ) 15% x D 28,389.01
F Harga Satuan Pekerjaan ( D + E ) 217,649.05
Harga Satuan Pekerjaan /1 kg besi F/10 21,764.90

85
A.4.1.1.21. Pemasangan 1 m² bekisting untuk sloof
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.520 111,780.00 58,125.60
2 Tukang Kayu L.02 OH 0.260 135,070.00 35,118.20
3 Kepala Tukang L.03 OH 0.026 140,740.00 3,659.24
4 Mandor L.04 OH 0.026 160,090.00 4,162.34
Jumlah Tenaga Kerja 101,065.38
B Bahan
1 Kayu Kelas III m³ 0.045 2,522,000.00 113,490.00
2 Paku 5 - 10 cm Kg 0.300 22,400.00 6,720.00
3 Minyak Bekisting Liter 0.100 10,900.00 1,090.00
Jumlah Harga Bahan 121,300.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 222,365.38
E Overhead + Profit ( Contoh 15% ) 15% x D 33,354.81
F Harga Satuan Pekerjaan ( D + E ) 255,720.19

A.4.2.1. HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM


A.4.2.1.21. Pemasangan 1 m² rangka besi holow 1 x 50 x 50 x 2 mm,
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.350 111,780.00 39,123.00
2 Tukang Besi L.02 OH 0.350 135,070.00 47,274.50
3 Kepala Tukang L.03 OH 0.0350 140,740.00 4,925.90
4 Mandor L.04 OH 0.0180 160,090.00 2,881.62
Jumlah Tenaga Kerja 94,205.02
B Bahan
1 Rangka Metal Hollow 50.50.2
m¹ 4.000 51,666.67 206,666.67
mm
2 Assesoris ( Perkuatan, Las dll 100% x
Ls 51,666.67 51,666.67
) Rangka
Jumlah Harga Bahan 258,333.33
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 352,538.35
E Overhead + Profit ( Contoh 15% ) 15% x D 52,880.75
F Harga Satuan Pekerjaan ( D + E ) 405,419.11

86
A.4.4.1. HARGA SATUAN PEKERJAAN PASANGAN DINDING
A.4.4.1.3. Pemasangan 1 m² dinding bata merah ( 9 x 9 x 18 ) cm tebal 1 batu campuran 1 SP : 4 PP
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 111,780.00 55,890.00
2 Tukang Batu L.02 OH 0.200 135,070.00 27,014.00
3 Kepala Tukang L.03 OH 0.020 140,740.00 2,814.80
4 Mandor L.04 OH 0.025 160,090.00 4,002.25
Jumlah Tenaga Kerja 89,721.05
B Bahan
1 Bata Merah m2 110.000 900.00 99,000.00
2 Semen Portland Kg 20.861 1,500.00 31,291.07
3 Pasir Pasang m³ 0.073 187,900.00 13,730.12
Jumlah Harga Bahan 144,021.19
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 233,742.24
E Overhead + Profit ( Contoh 15% ) 15% x D 35,061.34
F Harga Satuan Pekerjaan ( D + E ) 268,803.58

A.4.4.1.3. Pemasangan 1 m² dinding bata merah ( 9 x 9 x 18 ) cm tebal 1 batu campuran 1 SP : 4 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 111,780.00 55,890.00
2 Tukang Batu L.02 OH 0.200 135,070.00 27,014.00
3 Kepala Tukang L.03 OH 0.020 140,740.00 2,814.80
4 Mandor L.04 OH 0.025 160,090.00 4,002.25
Jumlah Tenaga Kerja 89,721.05
B Bahan
1 Bata Merah m2 55.000 900.00 49,500.00
2 Semen Portland Kg 20.861 1,500.00 31,291.07
3 Pasir Pasang m³ 0.073 187,900.00 13,730.12
Jumlah Harga Bahan 94,521.19
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 184,242.24
E Overhead + Profit ( Contoh 15% ) 15% x D 27,636.34
F Harga Satuan Pekerjaan ( D + E ) 211,878.58

87
A.4.4.2. HARGA SATUAN PEKERJAAN PLESTERAN
A.4.4.2.4. Pemasangan 1 m² plesteran 1 SP : 4 PP tebal 15 mm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 111,780.00 33,534.00
2 Tukang Batu L.02 OH 0.150 135,070.00 20,260.50
3 Kepala Tukang L.03 OH 0.015 140,740.00 2,111.10
4 Mandor L.04 OH 0.015 160,090.00 2,401.35
Jumlah Tenaga Kerja 58,306.95
B Bahan
1 Semen Portland Kg 6.240 1,500.00 9,360.00
2 Pasir Pasang m³ 0.024 187,900.00 4,509.60
Jumlah Harga Bahan 13,869.60
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 72,176.55
E Overhead + Profit ( Contoh 15% ) 15% x D 10,826.48
F Harga Satuan Pekerjaan ( D + E ) 83,003.03

HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN


A.4.4.3.
DINDING
A.4.4.3.35. Pemasangan 1 m² lantai keramik ukuran 40c m x 40 cm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.700 111,780.00 78,246.00
2 Tukang Batu L.02 OH 0.350 135,070.00 47,274.50
3 Kepala Tukang L.03 OH 0.035 140,740.00 4,925.90
4 Mandor L.04 OH 0.035 160,090.00 5,603.15
Jumlah Tenaga Kerja 136,049.55
B Bahan
1 Ubin Keramik Bh 6.875 74,700.00 513,562.50
2 Semen Portland Kg 10.000 1,500.00 15,000.00
3 Pasir Pasang m³ 0.045 187,900.00 8,455.50
4 Semen Warna Kg 1.500 2,100.00 3,150.00
Jumlah Harga Bahan 540,168.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 676,217.55
E Overhead + Profit ( Contoh 10% ) 10% x D 67,621.76
F Harga Satuan Pekerjaan ( D + E ) 743,839.31

88
A.4.5.2. HARGA SATUAN PEKERJAAN PENUTUP ATAP
A.4.5.2.40. Pemasangan 1 m² atap metalroof
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.200 111,780.00 22,356.00
2 Tukang Kayu L.02 OH 0.100 135,070.00 13,507.00
3 Kepala Tukang L.03 OH 0.0100 140,740.00 1,407.40
4 Mandor L.04 OH 0.001 160,090.00 160.09
Jumlah Tenaga Kerja 37,430.49
B Bahan
1 Genteng Metal Lembar 1.020 91,000.00 92,820.00
2 Paku Biasa 2" - 5" Kg 0.200 22,400.00 4,480.00
Jumlah Harga Bahan 97,300.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 134,730.49
E Overhead + Profit ( Contoh 15% ) 15% x D 20,209.57
F Harga Satuan Pekerjaan ( D + E ) 154,940.06

A.4.5.2.41. Pemasangan 1 m¹ nok atap Metal roof


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.250 111,780.00 27,945.00
2 Tukang Kayu L.02 OH 0.150 135,070.00 20,260.50
3 Kepala Tukang L.03 OH 0.0150 140,740.00 2,111.10
4 Mandor L.04 OH 0.013 160,090.00 2,081.17
Jumlah Tenaga Kerja 52,397.77
B Bahan
1 Nok Buah 1.100 43,000.00 47,300.00
2 Paku Hak Panjang 15 cm Kg 0.040 22,400.00 896.00
Jumlah Harga Bahan 48,196.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 100,593.77
E Overhead + Profit ( Contoh 15% ) 15% x D 15,089.07
F Harga Satuan Pekerjaan ( D + E ) 115,682.84

89
A.4.6.1. HARGA SATUAN PEKERJAAN KAYU
A.4.6.1.13. Pemasangan 1 m³ konstruksi kuda-kuda konvensional, kayu kelas I, II dan III
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 4.000 111,780.00 447,120.00
2 Tukang Kayu L.02 OH 12.000 135,070.00 1,620,840.00
3 Kepala Tukang L.03 OH 1.2000 140,740.00 168,888.00
4 Mandor L.04 OH 0.200 160,090.00 32,018.00
Jumlah Tenaga Kerja 2,268,866.00
B Bahan
1 Balok Kayu m³ 1.1000 3,007,000.00 3,307,700.00
2 Besi Strip Tebal 5 mm Kg 15.000 -
3 Paku 12 cm Kg 5.600 22,400.00 125,440.00
Jumlah Harga Bahan 3,433,140.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 5,702,006.00
E Overhead + Profit ( Contoh 15% ) 15% x D 855,300.90
F Harga Satuan Pekerjaan ( D + E ) 6,557,306.90

A.4.6.1.19. Pemasangan 1 m² rangka langit-langit ( 50 x 100 ) cm, kayu kelas II atau III
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.150 111,780.00 16,767.00
2 Tukang Kayu L.02 OH 0.300 135,070.00 40,521.00
3 Kepala Tukang L.03 OH 0.0300 140,740.00 4,222.20
4 Mandor L.04 OH 0.075 160,090.00 12,006.75
Jumlah Tenaga Kerja 73,516.95
B Bahan
1 Kaso-kaso 5 x 7 cm m³ 0.0154 3,007,000.00 46,307.80
2 Paku 7 cm - 10 cm Kg 0.200 22,400.00 4,480.00
Jumlah Harga Bahan 50,787.80
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 124,304.75
E Overhead + Profit ( Contoh 15% ) 15% x D 18,645.71
F Harga Satuan Pekerjaan ( D + E ) 142,950.46

90
A.4.6.1.22. Pemasangan 1 m¹ listplank ukuran ( 3 x 30 ) cm, kayu kelas I atau kelas II
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.100 111,780.00 11,178.00
2 Tukang Kayu L.02 OH 0.200 135,070.00 27,014.00
3 Kepala Tukang L.03 OH 0.0200 140,740.00 2,814.80
4 Mandor L.04 OH 0.005 160,090.00 800.45
Jumlah Tenaga Kerja 41,807.25
B Bahan
1 Papan Kayu m³ 0.0110 3,007,000.00 33,077.00
2 Paku 5 cm dan 7 cm Kg 0.050 22,400.00 1,120.00
Jumlah Harga Bahan 34,197.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 76,004.25
E Overhead + Profit ( Contoh 15% ) 15% x D 11,400.64
F Harga Satuan Pekerjaan ( D + E ) 87,404.89

91
CV. BLUE Print Consultant
Planning, Supervision & Engineering Consultant
Office: Jl. Yos Sudarso RT. 002 Sebengkok Tarakan
e-mail : blueprintconsultant@yahoo.com

DAFTAR HARGA SATUAN


PAKET KEGIATAN :
PEMBUATAN TAMAN JUATA KERIKIL

LOKASI : TARAKAN
TAHUN : 2020

No. URAIAN BAHAN SATUAN HARGA SATUAN KETERANGAN

(1) (2) (3) (4) (5)

I UPAH (standar harga kota Tarakan)

1 Pekerja Hari Rp. 111,780.00


2 Tukang Hari Rp. 135,070.00
3 Mandor Hari Rp. 160,090.00
4 Kepala Tukang Hari Rp. 140,740.00

II BAHAN

1 Agregat Kasar/batu pecah M3 Rp. 573,600 424.89 Kg


2 Semen (50kg) Zak Rp. 75,000 1,500.00 / kg setara tonasa
3 Semen Warna Kg Rp. 2,100 / kg
3 Besi beton polos Kg Rp. 15,900
4 Kawat Ikat / Kg Rp. 22,700
5 Plywood 4 mm / Lbr Rp. 83,000
6 Keramik 40x40 / Kotak Rp. 74,700
7 Paku Biasa / Kg Rp. 22,400
8 Tear Oil / Kg Rp. 35,300
9 Minyak Begesting Ltr Rp. 10,900
10 Batu Pecah / M3 Rp. 573,600 395.59 /kg
11 Pasir Pasangan / M3 Rp. 187,900 117.44 /kg
12 Tanah Urug / Pasir urug / M3 Rp. 85,600
13 Batu Bata / Bh Rp. 900
14 Paving Blok ( t = 8 cm ) / Bh Rp. 3,000
15 Air Bersih Ltr Rp. 53
16 Kayu Perancah / M3 Rp. 2,522,000
17 Kayu Meranti / M3 Rp. 2,522,000
18 Kayu Kapur / Bengkirai / Lembasung / M3 Rp. 3,007,000
19 Hollow 50x50x2 /m Rp. 51,667
20 Atap Multi Roof / Lbr Rp. 91,000
21 Nok Multi Roof /m Rp. 43,000
20 Pohon Palem Ekor Tupai / Pokok Rp. 525,000
21 Rumput Gajah Mini / M2 Rp. 77,100
22 Pohon Pucuk Merah / Pokok Rp. 178,000
23 BRC 175x240 / Lbr Rp. 675,000
24 Tiang BRC Galvanis / Btg Rp. 200,000
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : PEMBUATAN TAMAN JUATA KERIKIL
PROP / KAB / KODYA : Kalimanta Utara / Kota Tarakan
JENIS PEKERJAAN Penyelenggaraan Sistem Manajemen Keselamatan Konstruksi (SMKK)
SATUAN PEMBAYARAN : Ls

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp.)
1 2 3 4 5 6 7
A SOSIALISASI
1 Spanduk K3 Lb 1.00 150,000.00 150,000.00
2 Pengarahan K3 (Safety Briefing) Org 1.00 15,000.00 15,000.00
Jumlah B 165,000.00
B APD Dan APK
1 Helm Pelindung (Safety Helmet) Buah 5.00 81,439.00 407,195.00
2 Sarung Tangan (Safety Gloves) Psg 15.00 20,000.00 300,000.00
4 Sepatu Keselamatan (Rubber Safety Shoes) Psg 5.00 100,000.00 500,000.00
5 Rompi Keselamatan (Safety Vest) Buah 5.00 25,000.00 125,000.00
Jumlah C 1,332,195.00
C ASURANSI
1 Asuransi Ls 1.00 190,000.00 190,000.00
Jumlah D 190,000.00
D RAMBU-RAMBU
1 Rambu Peringatan Buah 1.00 75,000.00 75,000.00
2 Rambu Informasi Buah 1.00 75,000.00 75,000.00
Jumlah G 150,000.00
Jumlah A s/d H 1,837,195.00
CV. BLUE Print Consultant
Planning, Supervision & Engineering Consultant
Office: Jl. Yos Sudarso RT. 002 Sebengkok Tarakan
e-mail : blueprintconsultant@yahoo.com

###

REKAPITULASI
ESTIMATE ENGINEERING (EE)
PAKET KEGIATAN : PEMBUATAN TAMAN KELURAHAN JUATA PERMAI
LOKASI : TARAKAN
TAHUN : 2020

JUMLAH BIAYA
No. URAIAN PEKERJAAN
( Rp. )
I PEKERJAAN PERSIAPAN Rp. 3,051,385.00 ###
II PEKERJAAN AREA TAMAN Rp. 137,122,104.38 ###

JUM LAH Rp. 140,173,489.38

PPn 10% Rp. 14,017,348.94

TOTAL KESELURUHAN Rp. 154,190,838.32 ###

DIBULATKAN Rp. 154,190,000.00 ###


Terbilang :

Seratus Lima Puluh Empat Juta Seratus Sembilan Puluh Ribu Rupiah

Tarakan, 18 Maret 2020


Di Periksa Konsultan Perencana
Pejabat Pembuat Komitmen CV. BLUE Print Consultant
Dinas Pekerjaan Umum dan Tata Ruang
Kota Tarakan

Drs. BROTO SUBAGYO MUHAMMAD RAMLI, ST


NIP. 19620314 199003 1 001 Direktur
CV. BLUE Print Consultant
Planning, Supervision & Engineering Consultant
Office: Jl. Yos Sudarso RT. 002 Sebengkok Tarakan
e-mail : blueprintconsultant@yahoo.com

ESTIMATE ENGINEERING (EE)


PAKET KEGIATAN : PEMBUATAN TAMAN KELURAHAN JUATA PERMAI
LOKASI : TARAKAN
TAHUN : 2020

HARGA SATUAN JUMLAH


No. URAIAN PEKERJAAN VOLUME SATUAN
( Rp.) ( Rp.)

I PEKERJAAN PERSIAPAN
1 Plank Nama Proyek 1.00 ls 500,000.00 500,000.00
2 Dokumentasi 1.00 ls 750,000.00 750,000.00
3 K3 1.00 ls 1,801,385.00 1,801,385.00

Total I 3,051,385.00

II PEKERJAAN AREA TAMAN


1 Galian Tanah 1.50 m3 99,331.25 148,798.21
2 Pasir Urug 14.03 m3 205,332.50 2,881,081.91
3 Tanah Urug 49.06 m2 157,860.50 7,743,846.83
3 Pemasangan Paving Press 140.31 m2 251,016.25 35,220,843.09
4 Pembuatan Pengunci Paving
- Cor Beton K-175 4.91 m3 1,353,533.39 6,640,434.81
- Bekisting 4.46 m2 254,161.50 1,133,560.29
7 Rumput Gajah Mini 63.00 m2 61,500.00 3,874,500.00
8 Pohon Pucuk Merah 20.00 Pohon 112,200.00 2,244,000.00
9 Aksessories Taman Bermain
- Jongkang-jongket 1.00 Unit 5,000,000.00 5,000,000.00
- Ayunan Difabel 1.00 Unit 5,000,000.00 5,000,000.00
- Mangkok Putar Difabel 1.00 Unit 4,200,000.00 4,200,000.00
- Besi Berayun 1.00 Unit 3,200,000.00 3,200,000.00
- Kursi Taman 2.00 Unit 1,100,000.00 2,200,000.00
10 Pekerjaan Gazebo
Foot Plat 50x50x20
- Cor Beton K-175 0.20 m3 1,353,533.39 270,706.68
- Pembesian 23.81 kg 21,739.03 517,562.71
- Bekisting 0.53 m2 254,161.50 135,552.80
Urugan Pasir 3.06 m3 205,332.50 628,317.45
Sloof 15x30
- Cor Beton K-175 0.54 m3 1,353,533.39 730,908.03
- Pembesian 51.17 kg 21,739.03 1,112,407.65
- Bekisting 1.59 m2 254,161.50 403,075.51
Kolom 15x15
- Cor Beton K-175 0.18 m3 1,353,533.39 243,636.01
- Pembesian 29.43 kg 21,739.03 639,866.46
- Bekisting 0.80 m2 254,161.50 203,329.20
Balok 10x15
- Cor Beton K-175 0.18 m3 1,353,533.39 243,636.01
- Pembesian 41.66 kg 21,739.03 905,539.09
- Bekisting 1.41 m2 254,161.50 358,367.72
Kuda - kuda kayu 5/10 0.11 m3 6,532,161.00 749,892.08
Usuk 5/5 0.12 m3 6,532,161.00 790,391.48
Pas Atap MultiRoof 10.72 m2 154,393.25 1,655,095.64
Pas Nok MultiRoof 9.20 m' 114,897.65 1,057,058.38
ListPlank 2.40 m2 86,907.80 208,578.72
Pas Keramik 40x40 9.00 m2 725,395.00 6,528,555.00
Pengecatan Listplank & Konstruksi Kuda-kuda Kayu 9.29 m2 46,734.85 434,073.29
Pengecatan Kolom, Sloof & Balok 16.80 m2 49,161.35 825,910.68
12 Pekerjaan Pagar BRC
- Cor Beton Sloof Tiang K-175 0.53 m3 1,353,533.39 714,665.63
- Bekisting 0.70 m2 254,161.50 177,913.05
- Tiang BRC 2" 33.00 Btg 200,000.00 6,600,000.00
- Pagar BRC 175x240 32.00 Lbr 750,000.00 24,000,000.00
- Pintu Pagar Hollow 5.00 m' 1,500,000.00 7,500,000.00
Total II 137,122,104.38
A.2.3.1 HARGA SATUAN PEKERJAAN TANAH
A.2.3.1.1 Penggalian 1 m³ tanah biasa sedalam 1 m
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.750 110,000.00 82,500.00
2 Mandor L.04 OH 0.025 155,000.00 3,875.00
Jumlah Tenaga Kerja 86,375.00
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 86,375.00
E Overhead + Profit ( Contoh 15% ) 15% x D 12,956.25
F Harga Satuan Pekerjaan ( D + E ) 99,331.25

A.2.3.1.9 Pengurukan kembali 1 m³ galian tanah


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 110,000.00 55,000.00
2 Mandor L.04 OH 0.050 155,000.00 7,750.00
Jumlah Tenaga Kerja 62,750.00
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 62,750.00
E Overhead + Profit ( Contoh 15% ) 15% x D 9,412.50
F Harga Satuan Pekerjaan ( D + E ) 72,162.50

96
A.2.3.1.11 Pengurugan 1 m³ dengan tanah urug
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7

A Tenaga
1 Pekerja L.01 OH 0.300 110,000.00 33,000.00
2 Mandor L.04 OH 0.010 155,000.00 1,550.00
Jumlah Tenaga Kerja 34,550.00
B Bahan
1 Tanah Urug m³ 1.200 85,600.00 102,720.00
Jumlah Harga Bahan 102,720.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 137,270.00
E Overhead + Profit ( Contoh 15% ) 15% x D 20,590.50
F Harga Satuan Pekerjaan ( D + E ) 157,860.50

A.2.3.1.12 Pengurugan 1 m³ dengan pasir urug


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7

A Tenaga
1 Pekerja L.01 OH 0.300 110,000.00 33,000.00
2 Mandor L.04 OH 0.010 155,000.00 1,550.00
Jumlah Tenaga Kerja 34,550.00
B Bahan
1 Pasir Urug m³ 1.200 120,000.00 144,000.00
Jumlah Harga Bahan 144,000.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 178,550.00
E Overhead + Profit ( Contoh 15% ) 15% x D 26,782.50
F Harga Satuan Pekerjaan ( D + E ) 205,332.50

A.3.2.1.1 Pemasangan 1 m2 Paving blok


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.200 110,000.00 22,000.00
2 Tukang Batu L.02 OH 0.300 134,000.00 40,200.00
3 Kepala Tukang L.03 OH 0.030 140,000.00 4,200.00
4 Mandor L.04 OH 0.025 155,000.00 3,875.00
Jumlah Tenaga Kerja 70,275.00
B Bahan
1 Paving m2 1.000 132,000.00 132,000.00
2 Pasir Pasang m³ 0.100 160,000.00 16,000.00
Jumlah Harga Bahan 148,000.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 218,275.00
E Overhead + Profit ( Contoh 15% ) 15% x D 32,741.25

97
F Harga Satuan Pekerjaan ( D + E ) 251,016.25

98
A.3.2.1.2 Pemasangan 1 m' Kanstin uk. 15/20 30x50
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 110,000.00 55,000.00
2 Tukang Batu L.02 OH 0.050 134,000.00 6,700.00
3 Kepala Tukang L.03 OH 0.010 140,000.00 1,400.00
4 Mandor L.04 OH 0.001 155,000.00 155.00
Jumlah Tenaga Kerja 63,255.00
B Bahan
1 Semen (PC) zak 0.360 65,000.00 23,400.00
2 Pasir Pasang m2 0.001 160,000.00 160.00
3 Kanstin uk. 15/20 30x50 bh 2.000 51,666.67 103,333.33
Jumlah Harga Bahan 126,893.33
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 190,148.33
E Overhead + Profit ( Contoh 15% ) 15% x D 28,522.25
F Harga Satuan Pekerjaan ( D + E ) 218,670.58

A.3.2.1.8 Pemasangan 1 m³ pondasi batu belah campuran ¼ SP : 1 KP : 4 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.500 110,000.00 165,000.00
2 Tukang Batu L.02 OH 0.750 134,000.00 100,500.00
3 Kepala Tukang L.03 OH 0.075 140,000.00 10,500.00
4 Mandor L.04 OH 0.075 155,000.00 11,625.00
Jumlah Tenaga Kerja 265,500.00
B Bahan
1 Batu Belah m³ 1.200 447,900.00 537,480.00
1 Kapur m³ 0.131 - -
2 Semen Portland Kg 41.000 1,300.00 53,300.00
3 Pasir Pasang m³ 0.523 160,000.00 83,680.00
Jumlah Harga Bahan 674,460.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 939,960.00
E Overhead + Profit ( Contoh 15% ) 15% x D 140,994.00
F Harga Satuan Pekerjaan ( D + E ) 1,080,954.00

99
A.4.1.1. HARGA SATUAN PEKERJAAN BETON
A.4.1.1.5. Membuat 1 m³ beton mutu f 'c = 14,5 Mpa ( K - 175 ), Slump ( 12 ± 2 ) cm, w/c = 0.66
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.650 110,000.00 181,500.00
2 Tukang Batu L.02 OH 0.275 134,000.00 36,850.00
3 Kepala Tukang L.03 OH 0.028 140,000.00 3,920.00
4 Mandor L.04 OH 0.083 155,000.00 12,865.00
Jumlah Tenaga Kerja 235,135.00
B Bahan
1 Semen Portland Kg 326.000 1,300.00 423,800.00
2 Pasir Beton Kg 760.000 100.00 76,000.00
3 Kerikil ( Maks 30mm ) Kg 1,029.000 418.52 430,655.56
4 Air Liter 215.000 53.00 11,395.00
Jumlah Harga Bahan 941,850.56
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,176,985.56
E Overhead + Profit ( Contoh 15% ) 15% x D 176,547.83
F Harga Satuan Pekerjaan ( D + E ) 1,353,533.39

A.4.1.1.7. Membuat 1 m³ beton mutu f 'c = 19,3 Mpa ( K - 225 ), Slump ( 12 ± 2 ) cm, w/c = 0.58
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.650 110,000.00 181,500.00
2 Tukang Batu L.02 OH 0.275 134,000.00 36,850.00
3 Kepala Tukang L.03 OH 0.028 140,000.00 3,920.00
4 Mandor L.04 OH 0.083 155,000.00 12,865.00
Jumlah Tenaga Kerja 235,135.00
B Bahan
1 Semen Portland Kg 371.000 1,300.00 482,300.00
2 Pasir Beton Kg 698.000 100.00 69,800.00
3 Kerikil ( Maks 30mm ) Kg 1,047.000 418.52 438,188.89
4 Air Liter 215.000 53.00 11,395.00
Jumlah Harga Bahan 1,001,683.89
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,236,818.89
E Overhead + Profit ( Contoh 15% ) 15% x D 185,522.83
F Harga Satuan Pekerjaan ( D + E ) 1,422,341.72

100
A.4.1.1.17. Pembesian 10 Kg dengan besi polos
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.070 110,000.00 7,700.00
2 Tukang Besi L.02 OH 0.070 134,000.00 9,380.00
3 Kepala Tukang L.03 OH 0.007 140,000.00 980.00
4 Mandor L.04 OH 0.004 155,000.00 620.00
Jumlah Tenaga Kerja 18,680.00
B Bahan
1 Besi Beton Polos Kg 10.500 15,900.00 166,950.00
2 Kawat Beton Kg 0.150 22,700.00 3,405.00
Jumlah Harga Bahan 170,355.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 189,035.00
E Overhead + Profit ( Contoh 15% ) 15% x D 28,355.25
F Harga Satuan Pekerjaan ( D + E ) 217,390.25
Harga Satuan Pekerjaan /1 kg besi F/10 21,739.03

A.4.1.1.21. Pemasangan 1 m² bekisting untuk sloof


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.520 110,000.00 57,200.00
2 Tukang Kayu L.02 OH 0.260 134,000.00 34,840.00
3 Kepala Tukang L.03 OH 0.026 140,000.00 3,640.00
4 Mandor L.04 OH 0.026 155,000.00 4,030.00
Jumlah Tenaga Kerja 99,710.00
B Bahan
1 Kayu Kelas III m³ 0.045 2,522,000.00 113,490.00
2 Paku 5 - 10 cm Kg 0.300 22,400.00 6,720.00
3 Minyak Bekisting Liter 0.100 10,900.00 1,090.00
Jumlah Harga Bahan 121,300.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 221,010.00
E Overhead + Profit ( Contoh 15% ) 15% x D 33,151.50
F Harga Satuan Pekerjaan ( D + E ) 254,161.50

101
A.4.2.1. HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM
A.4.2.1.21. Pemasangan 1 m² rangka besi holow 1 x 50 x 50 x 2 mm,
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.350 110,000.00 38,500.00
2 Tukang Besi L.02 OH 0.350 134,000.00 46,900.00
3 Kepala Tukang L.03 OH 0.0350 140,000.00 4,900.00
4 Mandor L.04 OH 0.0180 155,000.00 2,790.00
Jumlah Tenaga Kerja 93,090.00
B Bahan
1 Rangka Metal Hollow 50.50.2
m¹ 4.000 51,666.67 206,666.67
mm
2 Assesoris ( Perkuatan, Las dll 100% x
Ls 51,666.67 51,666.67
) Rangka
Jumlah Harga Bahan 258,333.33
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 351,423.33
E Overhead + Profit ( Contoh 15% ) 15% x D 52,713.50
F Harga Satuan Pekerjaan ( D + E ) 404,136.83

A.4.4.1. HARGA SATUAN PEKERJAAN PASANGAN DINDING


A.4.4.1.3. Pemasangan 1 m² dinding bata merah ( 9 x 9 x 18 ) cm tebal 1 batu campuran 1 SP : 4 PP
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 110,000.00 55,000.00
2 Tukang Batu L.02 OH 0.200 134,000.00 26,800.00
3 Kepala Tukang L.03 OH 0.020 140,000.00 2,800.00
4 Mandor L.04 OH 0.025 155,000.00 3,875.00
Jumlah Tenaga Kerja 88,475.00
B Bahan
1 Bata Merah m2 110.000 120,000.00 13,200,000.00
2 Semen Portland Kg 20.861 1,300.00 27,118.93
3 Pasir Pasang m³ 0.073 160,000.00 11,691.43
Jumlah Harga Bahan 13,238,810.36
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 13,327,285.36
E Overhead + Profit ( Contoh 15% ) 15% x D 1,999,092.80
F Harga Satuan Pekerjaan ( D + E ) 15,326,378.16

102
A.4.4.1.3. Pemasangan 1 m² dinding bata merah ( 9 x 9 x 18 ) cm tebal 1 batu campuran 1 SP : 4 PP
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 110,000.00 55,000.00
2 Tukang Batu L.02 OH 0.200 134,000.00 26,800.00
3 Kepala Tukang L.03 OH 0.020 140,000.00 2,800.00
4 Mandor L.04 OH 0.025 155,000.00 3,875.00
Jumlah Tenaga Kerja 88,475.00
B Bahan
1 Bata Merah m2 55.000 120,000.00 6,600,000.00
2 Semen Portland Kg 20.861 1,300.00 27,118.93
3 Pasir Pasang m³ 0.073 160,000.00 11,691.43
Jumlah Harga Bahan 6,638,810.36
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 6,727,285.36
E Overhead + Profit ( Contoh 15% ) 15% x D 1,009,092.80
F Harga Satuan Pekerjaan ( D + E ) 7,736,378.16

A.4.4.2. HARGA SATUAN PEKERJAAN PLESTERAN


A.4.4.2.4. Pemasangan 1 m² plesteran 1 SP : 4 PP tebal 15 mm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 110,000.00 33,000.00
2 Tukang Batu L.02 OH 0.150 134,000.00 20,100.00
3 Kepala Tukang L.03 OH 0.015 140,000.00 2,100.00
4 Mandor L.04 OH 0.015 155,000.00 2,325.00
Jumlah Tenaga Kerja 57,525.00
B Bahan
1 Semen Portland Kg 6.240 1,300.00 8,112.00
2 Pasir Pasang m³ 0.024 160,000.00 3,840.00
Jumlah Harga Bahan 11,952.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 69,477.00
E Overhead + Profit ( Contoh 15% ) 15% x D 10,421.55
F Harga Satuan Pekerjaan ( D + E ) 79,898.55

103
HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN
A.4.4.3.
DINDING
A.4.4.3.35. Pemasangan 1 m² lantai keramik ukuran 40c m x 40 cm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.700 110,000.00 77,000.00
2 Tukang Batu L.02 OH 0.350 134,000.00 46,900.00
3 Kepala Tukang L.03 OH 0.035 140,000.00 4,900.00
4 Mandor L.04 OH 0.035 155,000.00 5,425.00
Jumlah Tenaga Kerja 134,225.00
B Bahan
1 Ubin Keramik Bh 6.875 73,000.00 501,875.00
2 Semen Portland Kg 10.000 1,300.00 13,000.00
3 Pasir Pasang m³ 0.045 160,000.00 7,200.00
4 Semen Warna Kg 1.500 2,100.00 3,150.00
Jumlah Harga Bahan 525,225.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 659,450.00
E Overhead + Profit ( Contoh 10% ) 10% x D 65,945.00
F Harga Satuan Pekerjaan ( D + E ) 725,395.00

A.4.5.2. HARGA SATUAN PEKERJAAN PENUTUP ATAP


A.4.5.2.40. Pemasangan 1 m² atap metalroof
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.200 110,000.00 22,000.00
2 Tukang Kayu L.02 OH 0.100 134,000.00 13,400.00
3 Kepala Tukang L.03 OH 0.0100 140,000.00 1,400.00
4 Mandor L.04 OH 0.001 155,000.00 155.00
Jumlah Tenaga Kerja 36,955.00
B Bahan
1 Genteng Metal Lembar 1.020 91,000.00 92,820.00
2 Paku Biasa 2" - 5" Kg 0.200 22,400.00 4,480.00
Jumlah Harga Bahan 97,300.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 134,255.00
E Overhead + Profit ( Contoh 15% ) 15% x D 20,138.25
F Harga Satuan Pekerjaan ( D + E ) 154,393.25

104
A.4.5.2.41. Pemasangan 1 m¹ nok atap Metal roof
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.250 110,000.00 27,500.00
2 Tukang Kayu L.02 OH 0.150 134,000.00 20,100.00
3 Kepala Tukang L.03 OH 0.0150 140,000.00 2,100.00
4 Mandor L.04 OH 0.013 155,000.00 2,015.00
Jumlah Tenaga Kerja 51,715.00
B Bahan
1 Nok Buah 1.100 43,000.00 47,300.00
2 Paku Hak Panjang 15 cm Kg 0.040 22,400.00 896.00
Jumlah Harga Bahan 48,196.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 99,911.00
E Overhead + Profit ( Contoh 15% ) 15% x D 14,986.65
F Harga Satuan Pekerjaan ( D + E ) 114,897.65

A.4.6.1. HARGA SATUAN PEKERJAAN KAYU


A.4.6.1.13. Pemasangan 1 m³ konstruksi kuda-kuda konvensional, kayu kelas I, II dan III
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 4.000 110,000.00 440,000.00
2 Tukang Kayu L.02 OH 12.000 134,000.00 1,608,000.00
3 Kepala Tukang L.03 OH 1.2000 140,000.00 168,000.00
4 Mandor L.04 OH 0.200 155,000.00 31,000.00
Jumlah Tenaga Kerja 2,247,000.00
B Bahan
1 Balok Kayu m³ 1.1000 3,007,000.00 3,307,700.00
2 Besi Strip Tebal 5 mm Kg 15.000 -
3 Paku 12 cm Kg 5.600 22,400.00 125,440.00
Jumlah Harga Bahan 3,433,140.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 5,680,140.00
E Overhead + Profit ( Contoh 15% ) 15% x D 852,021.00
F Harga Satuan Pekerjaan ( D + E ) 6,532,161.00

105
A.4.6.1.19. Pemasangan 1 m² rangka langit-langit ( 50 x 100 ) cm, kayu kelas II atau III
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.150 110,000.00 16,500.00
2 Tukang Kayu L.02 OH 0.300 134,000.00 40,200.00
3 Kepala Tukang L.03 OH 0.0300 140,000.00 4,200.00
4 Mandor L.04 OH 0.075 155,000.00 11,625.00
Jumlah Tenaga Kerja 72,525.00
B Bahan
1 Kaso-kaso 5 x 7 cm m³ 0.0154 3,007,000.00 46,307.80
2 Paku 7 cm - 10 cm Kg 0.200 22,400.00 4,480.00
Jumlah Harga Bahan 50,787.80
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 123,312.80
E Overhead + Profit ( Contoh 15% ) 15% x D 18,496.92
F Harga Satuan Pekerjaan ( D + E ) 141,809.72

A.4.6.1.22. Pemasangan 1 m¹ listplank ukuran ( 3 x 30 ) cm, kayu kelas I atau kelas II


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.100 110,000.00 11,000.00
2 Tukang Kayu L.02 OH 0.200 134,000.00 26,800.00
3 Kepala Tukang L.03 OH 0.0200 140,000.00 2,800.00
4 Mandor L.04 OH 0.005 155,000.00 775.00
Jumlah Tenaga Kerja 41,375.00
B Bahan
1 Papan Kayu m³ 0.0110 3,007,000.00 33,077.00
2 Paku 5 cm dan 7 cm Kg 0.050 22,400.00 1,120.00
Jumlah Harga Bahan 34,197.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 75,572.00
E Overhead + Profit ( Contoh 15% ) 15% x D 11,335.80
F Harga Satuan Pekerjaan ( D + E ) 86,907.80

A.4.7.1. HARGA SATUAN PEKERJAAN PENGECATAN


A.4.7.1.4. 1 m² pengecatan bidang kayu baru ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.070 110,000.00 7,700.00
2 Tukang Cat L.02 OH 0.009 134,000.00 1,206.00
3 Kepala Tukang L.03 OH 0.006 140,000.00 840.00
4 Mandor L.04 OH 0.003 155,000.00 465.00
Jumlah Tenaga Kerja 10,211.00

106
B Bahan
1 Cat Menie Kg 0.200 31,000.00 6,200.00
2 Plamir Kg 0.150 -
3 Cat Dasar Kg 0.170 51,800.00 8,806.00
4 Cat Penutup Kg 0.260 51,800.00 13,468.00
5 Kuas Buah 0.010 18,000.00 180.00
6 Pengencer Kg 0.030 25,800.00 774.00
7 Ampelas Lembar 0.200 5,000.00 1,000.00
Jumlah Harga Bahan 30,428.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 40,639.00
E Overhead + Profit ( Contoh 15% ) 15% x D 6,095.85
F Harga Satuan Pekerjaan ( D + E ) 46,734.85

A.4.7.1.10. Pengecataan 1 m² tembok baru ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.020 110,000.00 2,200.00
2 Tukang Cat L.02 OH 0.063 134,000.00 8,442.00
3 Kepala Tukang L.03 OH 0.0063 140,000.00 882.00
4 Mandor L.04 OH 0.003 155,000.00 465.00
Jumlah Tenaga Kerja 11,989.00
B Bahan
1 Plamir Kg 0.100 8,800.00 880.00
2 Cat Dasar Kg 0.100 83,000.00 8,300.00
3 Cat Penutup Kg 0.260 83,000.00 21,580.00
Jumlah Harga Bahan 30,760.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 42,749.00
E Overhead + Profit ( Contoh 15% ) 15% x D 6,412.35
F Harga Satuan Pekerjaan ( D + E ) 49,161.35

107
CV. BLUE Print Consultant
Planning, Supervision & Engineering Consultant
Office: Jl. Yos Sudarso RT. 002 Sebengkok Tarakan
e-mail : blueprintconsultant@yahoo.com

DAFTAR HARGA SATUAN


PAKET KEGIATAN :
PEMBUATAN TAMAN KELURAHAN JUATA PERMAI

LOKASI : TARAKAN
TAHUN : 2020

No. URAIAN BAHAN SATUAN HARGA SATUAN KETERANGAN

(1) (2) (3) (4) (5)

I UPAH (standar harga kota Tarakan)

1 Pekerja Hari Rp. 110,000.00


2 Tukang Hari Rp. 134,000.00
3 Mandor Hari Rp. 155,000.00
4 Kepala Tukang Hari Rp. 140,000.00

II BAHAN
1 Agregat Kasar/batu pecah M3 Rp. 565,000 418.52 Kg
2 Semen (50kg) Zak Rp. 65,000 1,300.00 / kg setara tonasa
3 Semen Warna Kg Rp. 2,100 / kg
4 Besi beton polos Kg Rp. 15,900
5 Kawat Ikat / Kg Rp. 22,700
6 Plywood 4 mm / Lbr Rp. 83,000
7 Keramik 40x40 / Kotak Rp. 73,000
8 Paku Biasa / Kg Rp. 22,400
9 Tear Oil / Kg Rp. 35,300
10 Minyak Begesting Ltr Rp. 10,900
11 Batu Gunung / M3 Rp. 447,900 308.90 /kg
12 Pasir Pasangan / M3 Rp. 160,000 100.00 /kg
13 Tanah Urug / M3 Rp. 85,600
14 Pasir Urug / M3 Rp. 120,000
15 Paving Blok ( t = 8 cm ) / Bh Rp. 3,000
16 Air Bersih Ltr Rp. 53
17 Kayu Perancah / M3 Rp. 2,522,000
18 Kayu Meranti / M3 Rp. 2,522,000
19 Kayu Kapur / Bengkirai / Lembasung / M3 Rp. 3,007,000
20 Hollow 50x50x2 /m Rp. 51,667
21 Atap Multi Roof / Lbr Rp. 91,000
22 Nok Multi Roof /m Rp. 43,000
23 BRC 120x240 / Lbr Rp. 750,000
24 Tiang BRC Galvanis / Btg Rp. 200,000
25 Pohon Palem Ekor Tupai / Pokok Rp. 525,000
26 Rumput Gajah Mini / M2 Rp. 61,500
27 Pohon Pucuk Merah / Pokok Rp. 112,200
28 Cat Menie / Kg Rp. 31,000
29 Plamir / Kg Rp. 8,800
30 Cat Minyak / Kg Rp. 51,800
31 Cat Air / Kg Rp. 83,000
32 Kuas / Bh Rp. 18,000
33 Pengencer / Kg Rp. 25,800
34 Ampelas / Lbr Rp. 5,000
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : PEMBUATAN TAMAN KELURAHAN KP.4
PROP / KAB / KODYA : Kalimanta Utara / Kota Tarakan
JENIS PEKERJAAN Penyelenggaraan Sistem Manajemen Keselamatan Konstruksi (SMKK)
SATUAN PEMBAYARAN : Ls

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp.)
1 2 3 4 5 6 7
A SOSIALISASI
1 Spanduk K3 Lb 1.00 150,000.00 150,000.00
2 Pengarahan K3 (Safety Briefing) Org 1.00 15,000.00 15,000.00
Jumlah B 165,000.00
B APD Dan APK
1 Helm Pelindung (Safety Helmet) Buah 5.00 81,439.00 407,195.00
2 Sarung Tangan (Safety Gloves) Psg 15.00 20,000.00 300,000.00
4 Sepatu Keselamatan (Rubber Safety Shoes) Psg 5.00 100,000.00 500,000.00
5 Rompi Keselamatan (Safety Vest) Buah 5.00 25,000.00 125,000.00
Jumlah C 1,332,195.00
C ASURANSI
1 Asuransi Ls 1.00 154,190.00 154,190.00
Jumlah D 154,190.00
D RAMBU-RAMBU
1 Rambu Peringatan Buah 1.00 75,000.00 75,000.00
2 Rambu Informasi Buah 1.00 75,000.00 75,000.00
Jumlah G 150,000.00
Jumlah A s/d H 1,801,385.00
CV. BLUE Print Consultant
Planning, Supervision & Engineering Consultant
Office: Jl. Yos Sudarso RT. 002 Sebengkok Tarakan
e-mail : blueprintconsultant@yahoo.com

REKAPITULASI
ESTIMATE ENGINEERING (EE)
PAKET KEGIATAN : PEMBUATAN TAMAN KELURAHAN KARANG ANYAR
LOKASI : TARAKAN
TAHUN : 2020

JUMLAH BIAYA
No. URAIAN PEKERJAAN
( Rp. )
I PEKERJAAN PERSIAPAN Rp. 6,087,195.00
II PEKERJAAN AREA TAMAN Rp. 166,640,609.95

JUM LAH Rp. 172,727,804.95

PPn 10% Rp. 17,272,780.49

TOTAL KESELURUHAN Rp. 190,000,585.44

DIBULATKAN Rp. 190,000,000.00


Terbilang :

Seratus Sembilan Puluh Juta Rupiah

Tarakan, 18 Maret 2020


Di Periksa Konsultan Perencana
Pejabat Pembuat Komitmen CV. BLUE Print Consultant
Dinas Pekerjaan Umum dan Tata Ruang
Kota Tarakan

Drs. BROTO SUBAGYO MUHAMMAD RAMLI, ST


NIP. 19620314 199003 1 001 Direktur
CV. BLUE Print Consultant
Planning, Supervision & Engineering Consultant
Office: Jl. Yos Sudarso RT. 002 Sebengkok Tarakan
e-mail : blueprintconsultant@yahoo.com

ESTIMATE ENGINEERING (EE)


PAKET KEGIATAN : PEMBUATAN TAMAN KELURAHAN KARANG ANYAR
LOKASI : TARAKAN
TAHUN : 2020

HARGA SATUAN JUMLAH


No. URAIAN PEKERJAAN VOLUME SATUAN
( Rp.) ( Rp.)

I PEKERJAAN PERSIAPAN
1 Plank Nama Proyek 1.00 ls 500,000.00 500,000.00
2 Dokumentasi 1.00 ls 750,000.00 750,000.00
3 K3 1.00 ls 1,837,195.00 1,837,195.00
4 Pembongkaran Lantai Beton 1.00 ls 3,000,000.00 3,000,000.00

Total I 6,087,195.00

II PEKERJAAN AREA TAMAN


1 Galian Tanah 0.90 m3 99,331.25 89,795.45
2 Pasir Urug 13.40 m3 205,332.50 2,751,455.50
3 Pemasangan Paving Press 134.00 m2 251,016.25 33,636,177.50
4 Pembuatan Pengunci Paving
- Cor Beton K-175 5.75 m3 1,353,533.39 7,788,129.60
- Bekisting 6.42 m2 254,161.50 1,632,778.86
5 Rumput Gajah Mini 110.00 m2 61,500.00 6,765,000.00
6 Pohon Pucuk Merah 34.00 Pohon 112,200.00 3,814,800.00
7 Aksessories Taman Bermain
- Jongkang-jongket 1.00 Unit 5,000,000.00 5,000,000.00
- Ayunan Difabel 1.00 Unit 5,000,000.00 5,000,000.00
- Mangkok Putar Difabel 1.00 Unit 4,200,000.00 4,200,000.00
- Besi Berayun 1.00 Unit 3,200,000.00 3,200,000.00
- Kursi Taman 4.00 Unit 1,100,000.00 4,400,000.00
8 Pekerjaan Gazebo
Cor Beton Tangga K-175 1.44 m3 1,353,533.39 1,949,088.08
Foot Plat 50x50x20
- Cor Beton K-175 0.20 m3 1,353,533.39 270,706.68
- Pembesian 23.81 kg 21,739.03 517,562.71
- Bekisting 0.64 m2 254,161.50 162,663.36
Urugan Pasir 3.06 m3 205,332.50 628,317.45
Cor Lantai Rabat 0.90 m3 21,739.03 19,565.12
Sloof 15x30
- Cor Beton K-175 0.54 m3 1,353,533.39 730,908.03
- Pembesian 51.17 kg 21,739.03 1,112,407.65
- Bekisting 2.31 m2 254,161.50 586,320.08
Kolom 15x15
- Cor Beton K-175 0.18 m3 1,353,533.39 243,636.01
- Pembesian 29.43 kg 21,739.03 639,866.46
- Bekisting 1.20 m2 254,161.50 304,993.80
Balok 10x15
- Cor Beton K-175 0.18 m3 1,353,533.39 243,636.01
- Pembesian 41.66 kg 21,739.03 905,539.09
- Bekisting 1.35 m2 254,161.50 343,118.03
Kuda - kuda kayu 5/10 0.11 m3 6,532,161.00 749,892.08
Usuk 5/5 0.12 m3 6,532,161.00 790,391.48
Pas Atap MultiRoof 10.72 m2 154,393.25 1,655,095.64
Pas Nok MultiRoof 9.20 m' 114,897.65 1,057,058.38
ListPlank 2.40 m2 86,907.80 208,578.72
Pas Keramik 40x40 9.00 m2 725,395.00 6,528,555.00
Pengecatan Listplank & Konstruksi Kuda-kuda Kayu 9.29 m2 46,734.85 434,073.29
Pengecatan Kolom, Sloof & Balok 16.80 m2 49,161.35 825,910.68
9 Pembuatan Pergola
- Rangka Kayu 5/10 0.67 m3 6,532,161.00 4,376,547.87
- Cor Beton Pondasi K-175 0.26 m3 1,353,533.39 346,504.55
- Pengecatan Rangka Kayu Pergola 10.05 m2 46,734.85 469,685.24
10 Pekerjaan Pagar BRC
Foot Plat 40x40x20
- Cor Beton K-175 1.12 m3 1,353,533.39 1,515,957.40
- Pembesian 173.60 kg 21,739.03 3,773,894.74
- Bekisting 1.87 m2 254,161.50 474,434.80
- Cor Beton Sloof Tiang K-175 3.65 m3 1,353,533.39 4,940,329.19
- Pembesian 402.31 kg 21,739.03 8,745,731.50
- Bekisting 8.11 m2 254,161.50 2,061,503.93
- Tiang BRC 2" 35.00 Btg 200,000.00 7,000,000.00
- Pagar BRC 120x240 34.00 Lbr 750,000.00 25,500,000.00
- Pintu Pagar Hollow 5.50 m' 1,500,000.00 8,250,000.00
Total II 166,640,609.95
A.2.3.1 HARGA SATUAN PEKERJAAN TANAH
A.2.3.1.1 Penggalian 1 m³ tanah biasa sedalam 1 m
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.750 110,000.00 82,500.00
2 Mandor L.04 OH 0.025 155,000.00 3,875.00
Jumlah Tenaga Kerja 86,375.00
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 86,375.00
E Overhead + Profit ( Contoh 15% ) 15% x D 12,956.25
F Harga Satuan Pekerjaan ( D + E ) 99,331.25

A.2.3.1.9 Pengurukan kembali 1 m³ galian tanah


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 110,000.00 55,000.00
2 Mandor L.04 OH 0.050 155,000.00 7,750.00
Jumlah Tenaga Kerja 62,750.00
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 62,750.00
E Overhead + Profit ( Contoh 15% ) 15% x D 9,412.50
F Harga Satuan Pekerjaan ( D + E ) 72,162.50

112
A.2.3.1.11 Pengurugan 1 m³ dengan tanah urug
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7

A Tenaga
1 Pekerja L.01 OH 0.300 110,000.00 33,000.00
2 Mandor L.04 OH 0.010 155,000.00 1,550.00
Jumlah Tenaga Kerja 34,550.00
B Bahan
1 Tanah Urug m³ 1.200 85,600.00 102,720.00
Jumlah Harga Bahan 102,720.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 137,270.00
E Overhead + Profit ( Contoh 15% ) 15% x D 20,590.50
F Harga Satuan Pekerjaan ( D + E ) 157,860.50

A.2.3.1.12 Pengurugan 1 m³ dengan pasir urug


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7

A Tenaga
1 Pekerja L.01 OH 0.300 110,000.00 33,000.00
2 Mandor L.04 OH 0.010 155,000.00 1,550.00
Jumlah Tenaga Kerja 34,550.00
B Bahan
1 Pasir Urug m³ 1.200 120,000.00 144,000.00
Jumlah Harga Bahan 144,000.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 178,550.00
E Overhead + Profit ( Contoh 15% ) 15% x D 26,782.50
F Harga Satuan Pekerjaan ( D + E ) 205,332.50

A.3.2.1.1 Pemasangan 1 m2 Paving blok


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.200 110,000.00 22,000.00
2 Tukang Batu L.02 OH 0.300 134,000.00 40,200.00
3 Kepala Tukang L.03 OH 0.030 140,000.00 4,200.00
4 Mandor L.04 OH 0.025 155,000.00 3,875.00
Jumlah Tenaga Kerja 70,275.00
B Bahan
1 Paving m2 1.000 132,000.00 132,000.00
2 Pasir Pasang m³ 0.100 160,000.00 16,000.00
Jumlah Harga Bahan 148,000.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 218,275.00
E Overhead + Profit ( Contoh 15% ) 15% x D 32,741.25

113
F Harga Satuan Pekerjaan ( D + E ) 251,016.25

114
A.3.2.1.2 Pemasangan 1 m' Kanstin uk. 15/20 30x50
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 110,000.00 55,000.00
2 Tukang Batu L.02 OH 0.050 134,000.00 6,700.00
3 Kepala Tukang L.03 OH 0.010 140,000.00 1,400.00
4 Mandor L.04 OH 0.001 155,000.00 155.00
Jumlah Tenaga Kerja 63,255.00
B Bahan
1 Semen (PC) zak 0.360 65,000.00 23,400.00
2 Pasir Pasang m2 0.001 160,000.00 160.00
3 Kanstin uk. 15/20 30x50 bh 2.000 51,666.67 103,333.33
Jumlah Harga Bahan 126,893.33
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 190,148.33
E Overhead + Profit ( Contoh 15% ) 15% x D 28,522.25
F Harga Satuan Pekerjaan ( D + E ) 218,670.58

A.4.1.1. HARGA SATUAN PEKERJAAN BETON


A.4.1.1.5. Membuat 1 m³ beton mutu f 'c = 14,5 Mpa ( K - 175 ), Slump ( 12 ± 2 ) cm, w/c = 0.66
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.650 110,000.00 181,500.00
2 Tukang Batu L.02 OH 0.275 134,000.00 36,850.00
3 Kepala Tukang L.03 OH 0.028 140,000.00 3,920.00
4 Mandor L.04 OH 0.083 155,000.00 12,865.00
Jumlah Tenaga Kerja 235,135.00
B Bahan
1 Semen Portland Kg 326.000 1,300.00 423,800.00
2 Pasir Beton Kg 760.000 100.00 76,000.00
3 Kerikil ( Maks 30mm ) Kg 1,029.000 418.52 430,655.56
4 Air Liter 215.000 53.00 11,395.00
Jumlah Harga Bahan 941,850.56
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,176,985.56
E Overhead + Profit ( Contoh 15% ) 15% x D 176,547.83
F Harga Satuan Pekerjaan ( D + E ) 1,353,533.39

115
A.4.1.1.7. Membuat 1 m³ beton mutu f 'c = 19,3 Mpa ( K - 225 ), Slump ( 12 ± 2 ) cm, w/c = 0.58
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.650 110,000.00 181,500.00
2 Tukang Batu L.02 OH 0.275 134,000.00 36,850.00
3 Kepala Tukang L.03 OH 0.028 140,000.00 3,920.00
4 Mandor L.04 OH 0.083 155,000.00 12,865.00
Jumlah Tenaga Kerja 235,135.00
B Bahan
1 Semen Portland Kg 371.000 1,300.00 482,300.00
2 Pasir Beton Kg 698.000 100.00 69,800.00
3 Kerikil ( Maks 30mm ) Kg 1,047.000 418.52 438,188.89
4 Air Liter 215.000 53.00 11,395.00
Jumlah Harga Bahan 1,001,683.89
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,236,818.89
E Overhead + Profit ( Contoh 15% ) 15% x D 185,522.83
F Harga Satuan Pekerjaan ( D + E ) 1,422,341.72

A.4.1.1.17. Pembesian 10 Kg dengan besi polos


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.070 110,000.00 7,700.00
2 Tukang Besi L.02 OH 0.070 134,000.00 9,380.00
3 Kepala Tukang L.03 OH 0.007 140,000.00 980.00
4 Mandor L.04 OH 0.004 155,000.00 620.00
Jumlah Tenaga Kerja 18,680.00
B Bahan
1 Besi Beton Polos Kg 10.500 15,900.00 166,950.00
2 Kawat Beton Kg 0.150 22,700.00 3,405.00
Jumlah Harga Bahan 170,355.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 189,035.00
E Overhead + Profit ( Contoh 15% ) 15% x D 28,355.25
F Harga Satuan Pekerjaan ( D + E ) 217,390.25
Harga Satuan Pekerjaan /1 kg besi F/10 21,739.03

116
A.4.1.1.21. Pemasangan 1 m² bekisting untuk sloof
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.520 110,000.00 57,200.00
2 Tukang Kayu L.02 OH 0.260 134,000.00 34,840.00
3 Kepala Tukang L.03 OH 0.026 140,000.00 3,640.00
4 Mandor L.04 OH 0.026 155,000.00 4,030.00
Jumlah Tenaga Kerja 99,710.00
B Bahan
1 Kayu Kelas III m³ 0.045 2,522,000.00 113,490.00
2 Paku 5 - 10 cm Kg 0.300 22,400.00 6,720.00
3 Minyak Bekisting Liter 0.100 10,900.00 1,090.00
Jumlah Harga Bahan 121,300.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 221,010.00
E Overhead + Profit ( Contoh 15% ) 15% x D 33,151.50
F Harga Satuan Pekerjaan ( D + E ) 254,161.50

A.4.2.1. HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM


A.4.2.1.21. Pemasangan 1 m² rangka besi holow 1 x 50 x 50 x 2 mm,
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.350 110,000.00 38,500.00
2 Tukang Besi L.02 OH 0.350 134,000.00 46,900.00
3 Kepala Tukang L.03 OH 0.0350 140,000.00 4,900.00
4 Mandor L.04 OH 0.0180 155,000.00 2,790.00
Jumlah Tenaga Kerja 93,090.00
B Bahan
1 Rangka Metal Hollow 50.50.2
m¹ 4.000 51,666.67 206,666.67
mm
2 Assesoris ( Perkuatan, Las dll 100% x
Ls 51,666.67 51,666.67
) Rangka
Jumlah Harga Bahan 258,333.33
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 351,423.33
E Overhead + Profit ( Contoh 15% ) 15% x D 52,713.50
F Harga Satuan Pekerjaan ( D + E ) 404,136.83

117
A.4.4.1. HARGA SATUAN PEKERJAAN PASANGAN DINDING
A.4.4.1.3. Pemasangan 1 m² dinding bata merah ( 9 x 9 x 18 ) cm tebal 1 batu campuran 1 SP : 4 PP
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 110,000.00 55,000.00
2 Tukang Batu L.02 OH 0.200 134,000.00 26,800.00
3 Kepala Tukang L.03 OH 0.020 140,000.00 2,800.00
4 Mandor L.04 OH 0.025 155,000.00 3,875.00
Jumlah Tenaga Kerja 88,475.00
B Bahan
1 Bata Merah m2 110.000 120,000.00 13,200,000.00
2 Semen Portland Kg 20.861 1,300.00 27,118.93
3 Pasir Pasang m³ 0.073 160,000.00 11,691.43
Jumlah Harga Bahan 13,238,810.36
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 13,327,285.36
E Overhead + Profit ( Contoh 15% ) 15% x D 1,999,092.80
F Harga Satuan Pekerjaan ( D + E ) 15,326,378.16

A.4.4.1.3. Pemasangan 1 m² dinding bata merah ( 9 x 9 x 18 ) cm tebal 1 batu campuran 1 SP : 4 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 110,000.00 55,000.00
2 Tukang Batu L.02 OH 0.200 134,000.00 26,800.00
3 Kepala Tukang L.03 OH 0.020 140,000.00 2,800.00
4 Mandor L.04 OH 0.025 155,000.00 3,875.00
Jumlah Tenaga Kerja 88,475.00
B Bahan
1 Bata Merah m2 55.000 120,000.00 6,600,000.00
2 Semen Portland Kg 20.861 1,300.00 27,118.93
3 Pasir Pasang m³ 0.073 160,000.00 11,691.43
Jumlah Harga Bahan 6,638,810.36
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 6,727,285.36
E Overhead + Profit ( Contoh 15% ) 15% x D 1,009,092.80
F Harga Satuan Pekerjaan ( D + E ) 7,736,378.16

118
A.4.4.2. HARGA SATUAN PEKERJAAN PLESTERAN
A.4.4.2.4. Pemasangan 1 m² plesteran 1 SP : 4 PP tebal 15 mm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 110,000.00 33,000.00
2 Tukang Batu L.02 OH 0.150 134,000.00 20,100.00
3 Kepala Tukang L.03 OH 0.015 140,000.00 2,100.00
4 Mandor L.04 OH 0.015 155,000.00 2,325.00
Jumlah Tenaga Kerja 57,525.00
B Bahan
1 Semen Portland Kg 6.240 1,300.00 8,112.00
2 Pasir Pasang m³ 0.024 160,000.00 3,840.00
Jumlah Harga Bahan 11,952.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 69,477.00
E Overhead + Profit ( Contoh 15% ) 15% x D 10,421.55
F Harga Satuan Pekerjaan ( D + E ) 79,898.55

HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN


A.4.4.3.
DINDING
A.4.4.3.35. Pemasangan 1 m² lantai keramik ukuran 40c m x 40 cm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.700 110,000.00 77,000.00
2 Tukang Batu L.02 OH 0.350 134,000.00 46,900.00
3 Kepala Tukang L.03 OH 0.035 140,000.00 4,900.00
4 Mandor L.04 OH 0.035 155,000.00 5,425.00
Jumlah Tenaga Kerja 134,225.00
B Bahan
1 Ubin Keramik Bh 6.875 73,000.00 501,875.00
2 Semen Portland Kg 10.000 1,300.00 13,000.00
3 Pasir Pasang m³ 0.045 160,000.00 7,200.00
4 Semen Warna Kg 1.500 2,100.00 3,150.00
Jumlah Harga Bahan 525,225.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 659,450.00
E Overhead + Profit ( Contoh 10% ) 10% x D 65,945.00
F Harga Satuan Pekerjaan ( D + E ) 725,395.00

119
A.4.5.2. HARGA SATUAN PEKERJAAN PENUTUP ATAP
A.4.5.2.40. Pemasangan 1 m² atap metalroof
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.200 110,000.00 22,000.00
2 Tukang Kayu L.02 OH 0.100 134,000.00 13,400.00
3 Kepala Tukang L.03 OH 0.0100 140,000.00 1,400.00
4 Mandor L.04 OH 0.001 155,000.00 155.00
Jumlah Tenaga Kerja 36,955.00
B Bahan
1 Genteng Metal Lembar 1.020 91,000.00 92,820.00
2 Paku Biasa 2" - 5" Kg 0.200 22,400.00 4,480.00
Jumlah Harga Bahan 97,300.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 134,255.00
E Overhead + Profit ( Contoh 15% ) 15% x D 20,138.25
F Harga Satuan Pekerjaan ( D + E ) 154,393.25

A.4.5.2.41. Pemasangan 1 m¹ nok atap Metal roof


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.250 110,000.00 27,500.00
2 Tukang Kayu L.02 OH 0.150 134,000.00 20,100.00
3 Kepala Tukang L.03 OH 0.0150 140,000.00 2,100.00
4 Mandor L.04 OH 0.013 155,000.00 2,015.00
Jumlah Tenaga Kerja 51,715.00
B Bahan
1 Nok Buah 1.100 43,000.00 47,300.00
2 Paku Hak Panjang 15 cm Kg 0.040 22,400.00 896.00
Jumlah Harga Bahan 48,196.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 99,911.00
E Overhead + Profit ( Contoh 15% ) 15% x D 14,986.65
F Harga Satuan Pekerjaan ( D + E ) 114,897.65

120
A.4.6.1. HARGA SATUAN PEKERJAAN KAYU
A.4.6.1.13. Pemasangan 1 m³ konstruksi kuda-kuda konvensional, kayu kelas I, II dan III
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 4.000 110,000.00 440,000.00
2 Tukang Kayu L.02 OH 12.000 134,000.00 1,608,000.00
3 Kepala Tukang L.03 OH 1.2000 140,000.00 168,000.00
4 Mandor L.04 OH 0.200 155,000.00 31,000.00
Jumlah Tenaga Kerja 2,247,000.00
B Bahan
1 Balok Kayu m³ 1.1000 3,007,000.00 3,307,700.00
2 Besi Strip Tebal 5 mm Kg 15.000 -
3 Paku 12 cm Kg 5.600 22,400.00 125,440.00
Jumlah Harga Bahan 3,433,140.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 5,680,140.00
E Overhead + Profit ( Contoh 15% ) 15% x D 852,021.00
F Harga Satuan Pekerjaan ( D + E ) 6,532,161.00

A.4.6.1.22. Pemasangan 1 m¹ listplank ukuran ( 3 x 30 ) cm, kayu kelas I atau kelas II


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.100 110,000.00 11,000.00
2 Tukang Kayu L.02 OH 0.200 134,000.00 26,800.00
3 Kepala Tukang L.03 OH 0.0200 140,000.00 2,800.00
4 Mandor L.04 OH 0.005 155,000.00 775.00
Jumlah Tenaga Kerja 41,375.00
B Bahan
1 Papan Kayu m³ 0.0110 3,007,000.00 33,077.00
2 Paku 5 cm dan 7 cm Kg 0.050 22,400.00 1,120.00
Jumlah Harga Bahan 34,197.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 75,572.00
E Overhead + Profit ( Contoh 15% ) 15% x D 11,335.80
F Harga Satuan Pekerjaan ( D + E ) 86,907.80

A.4.7.1. HARGA SATUAN PEKERJAAN PENGECATAN


A.4.7.1.4. 1 m² pengecatan bidang kayu baru ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga

121
1 Pekerja L.01 OH 0.070 110,000.00 7,700.00
2 Tukang Cat L.02 OH 0.009 134,000.00 1,206.00
3 Kepala Tukang L.03 OH 0.006 140,000.00 840.00
4 Mandor L.04 OH 0.003 155,000.00 465.00
Jumlah Tenaga Kerja 10,211.00
B Bahan
1 Cat Menie Kg 0.200 31,000.00 6,200.00
2 Plamir Kg 0.150 -
3 Cat Dasar Kg 0.170 51,800.00 8,806.00
4 Cat Penutup Kg 0.260 51,800.00 13,468.00
5 Kuas Buah 0.010 18,000.00 180.00
6 Pengencer Kg 0.030 25,800.00 774.00
7 Ampelas Lembar 0.200 5,000.00 1,000.00
Jumlah Harga Bahan 30,428.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 40,639.00
E Overhead + Profit ( Contoh 15% ) 15% x D 6,095.85
F Harga Satuan Pekerjaan ( D + E ) 46,734.85

A.4.7.1.10. Pengecataan 1 m² tembok baru ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.020 110,000.00 2,200.00
2 Tukang Cat L.02 OH 0.063 134,000.00 8,442.00
3 Kepala Tukang L.03 OH 0.0063 140,000.00 882.00
4 Mandor L.04 OH 0.003 155,000.00 465.00
Jumlah Tenaga Kerja 11,989.00
B Bahan
1 Plamir Kg 0.100 8,800.00 880.00
2 Cat Dasar Kg 0.100 83,000.00 8,300.00
3 Cat Penutup Kg 0.260 83,000.00 21,580.00
Jumlah Harga Bahan 30,760.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 42,749.00
E Overhead + Profit ( Contoh 15% ) 15% x D 6,412.35
F Harga Satuan Pekerjaan ( D + E ) 49,161.35

122
CV. BLUE Print Consultant
Planning, Supervision & Engineering Consultant
Office: Jl. Yos Sudarso RT. 002 Sebengkok Tarakan
e-mail : blueprintconsultant@yahoo.com

DAFTAR HARGA SATUAN


PAKET KEGIATAN :
PEMBUATAN TAMAN KELURAHAN KARANG ANYAR

LOKASI : TARAKAN
TAHUN : 2020

No. URAIAN BAHAN SATUAN HARGA SATUAN KETERANGAN

(1) (2) (3) (4) (5)

I UPAH (standar harga kota Tarakan)

1 Pekerja Hari Rp. 110,000.00


2 Tukang Hari Rp. 134,000.00
3 Mandor Hari Rp. 155,000.00
4 Kepala Tukang Hari Rp. 140,000.00

II BAHAN
1 Agregat Kasar/batu pecah M3 Rp. 565,000 418.52 Kg
2 Semen (50kg) Zak Rp. 65,000 1,300.00 / kg setara tonasa
3 Semen Warna Kg Rp. 2,100 / kg
4 Besi beton polos Kg Rp. 15,900
5 Kawat Ikat / Kg Rp. 22,700
6 Plywood 4 mm / Lbr Rp. 83,000
7 Keramik 40x40 / Kotak Rp. 73,000
8 Paku Biasa / Kg Rp. 22,400
9 Tear Oil / Kg Rp. 35,300
10 Minyak Begesting Ltr Rp. 10,900
11 Batu Pecah / M3 Rp. 565,000 389.66 /kg
12 Pasir Pasangan / M3 Rp. 160,000 100.00 /kg
13 Tanah Urug / M3 Rp. 85,600
14 Pasir Urug / M3 Rp. 120,000
15 Paving Blok ( t = 8 cm ) / Bh Rp. 3,000
16 Air Bersih Ltr Rp. 53
17 Kayu Perancah / M3 Rp. 2,522,000
18 Kayu Meranti / M3 Rp. 2,522,000
19 Kayu Kapur / Bengkirai / Lembasung / M3 Rp. 3,007,000
20 Hollow 50x50x2 /m Rp. 51,667
21 Atap Multi Roof / Lbr Rp. 91,000
22 Nok Multi Roof /m Rp. 43,000
23 BRC 120x240 / Lbr Rp. 750,000
24 Tiang BRC Galvanis / Btg Rp. 200,000
25 Pohon Palem Ekor Tupai / Pokok Rp. 525,000
26 Rumput Gajah Mini / M2 Rp. 61,500
27 Pohon Pucuk Merah / Pokok Rp. 112,200
28 Cat Menie / Kg Rp. 31,000
29 Plamir / Kg Rp. 8,800
30 Cat Minyak / Kg Rp. 51,800
31 Cat Air / Kg Rp. 83,000
32 Kuas / Bh Rp. 18,000
33 Pengencer / Kg Rp. 25,800
34 Ampelas / Lbr Rp. 5,000
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : PEMBUATAN TAMAN DEPAN 613
PROP / KAB / KODYA : Kalimanta Utara / Kota Tarakan
JENIS PEKERJAAN Penyelenggaraan Sistem Manajemen Keselamatan Konstruksi (SMKK)
SATUAN PEMBAYARAN : Ls

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp.)
1 2 3 4 5 6 7
A SOSIALISASI
1 Spanduk K3 Lb 1.00 150,000.00 150,000.00
2 Pengarahan K3 (Safety Briefing) Org 1.00 15,000.00 15,000.00
Jumlah B 165,000.00
B APD Dan APK
1 Helm Pelindung (Safety Helmet) Buah 5.00 81,439.00 407,195.00
2 Sarung Tangan (Safety Gloves) Psg 15.00 20,000.00 300,000.00
4 Sepatu Keselamatan (Rubber Safety Shoes) Psg 5.00 100,000.00 500,000.00
5 Rompi Keselamatan (Safety Vest) Buah 5.00 25,000.00 125,000.00
Jumlah C 1,332,195.00
C ASURANSI
1 Asuransi Ls 1.00 190,000.00 190,000.00
Jumlah D 190,000.00
D RAMBU-RAMBU
1 Rambu Peringatan Buah 1.00 75,000.00 75,000.00
2 Rambu Informasi Buah 1.00 75,000.00 75,000.00
Jumlah G 150,000.00
Jumlah A s/d H 1,837,195.00
CV. BLUE Print Consultant
Planning, Supervision & Engineering Consultant
Office: Jl. Yos Sudarso RT. 002 Sebengkok Tarakan
e-mail : blueprintconsultant@yahoo.com

REKAPITULASI
ESTIMATE ENGINEERING (EE)
PAKET KEGIATAN : TAMAN BELAKANG BRI
LOKASI : TARAKAN
TAHUN : 2020

JUMLAH BIAYA
No. URAIAN PEKERJAAN
( Rp. )
I PEKERJAAN PERSIAPAN Rp. 3,087,195.00
II PEKERJAAN BETON Rp. 1,053,399,430.19
III PEKERJAAN PASANGAN Rp. 102,657,158.52
IV PEKERJAAN ATAP Rp. 23,416,209.27
V PEKERJAAN KUSEN Rp. 12,289,382.47
VI PEKERJAAN PENGANTUNG & PENGUNCI Rp. 2,314,987.83
VII PEKERJAAN PLAFOND Rp. 17,164,947.96
VIII PEKERJAAN PENGECATAN Rp. 19,040,106.28
IX PEKERJAAN SANITASI Rp. 2,310,295.61
X PEKERJAAN MEKANIKAL ELECTRIKAL Rp. 2,645,206.00
XI PEKERJAAN PAGAR & TAMAN Rp. 30,141,178.10

JUM LAH Rp. 1,056,486,625.19

PPn 10% Rp. 105,648,662.52

TOTAL KESELURUHAN Rp. 1,162,135,287.71

DIBULATKAN Rp. 1,162,135,000.00


Terbilang :

Satu Milyar Tiga Ratus Delapan Puluh Delapan Juta Lima Puluh Tiga Ribu Rupiah

Tarakan, 18 Maret 2020


Di Periksa Konsultan Perencana
Pejabat Pembuat Komitmen CV. BLUE Print Consultant
Dinas Pekerjaan Umum dan Tata Ruang
Kota Tarakan

Drs. BROTO SUBAGYO MUHAMMAD RAMLI, ST


NIP. 19620314 199003 1 001 Direktur
CV. BLUE Print Consultant
Planning, Supervision & Engineering Consultant
Office: Jl. Yos Sudarso RT. 002 Sebengkok Tarakan
e-mail : blueprintconsultant@yahoo.com

ESTIMATE ENGINEERING (EE)


PAKET KEGIATAN : TAMAN BELAKANG BRI
LOKASI : TARAKAN
TAHUN : 2020

HARGA SATUAN JUMLAH


No. URAIAN PEKERJAAN VOLUME SATUAN
( Rp.) ( Rp.)

I PEKERJAAN PERSIAPAN
1 Plank Nama Proyek 1.00 ls 500,000.00 500,000.00
2 Dokumentasi 1.00 ls 750,000.00 750,000.00
3 K3 1.00 ls 1,837,195.00 1,837,195.00

Total I 3,087,195.00

II PEKERJAAN BETON
1 Pancang Beton 10/10, 400 820.00 Btg 404,400.00 331,608,000.00
2 Cor Beton Bertulang Foot Plat
- Cor Beton K-225 20.99 M3 1,780,721.06 37,380,896.42
- Pembesian 4,775.68 Kg 22,360.00 106,784,198.52
- Bekisting 104.96 M2 261,412.69 27,437,875.63
3 Cor Beton Bertulang Kolom K1
- Cor Beton K-225 4.61 M3 1,780,721.06 8,213,575.87
- Pembesian 2,425.89 Kg 22,360.00 54,242,852.49
- Bekisting 142.68 M2 261,412.69 37,298,362.18
4 Cor Beton Bertulang Balok B1
- Cor Beton K-225 3.68 M3 1,780,721.06 6,544,149.88
- Pembesian 834.48 Kg 22,360.00 18,658,971.70
- Bekisting 63.70 M2 261,412.69 16,651,988.16
5 Cor Beton Bertulang Kolom K2
- Cor Beton K-225 0.74 M3 1,780,721.06 1,324,856.47
- Pembesian 206.18 Kg 22,360.00 4,610,095.09
- Bekisting 12.32 M2 261,412.69 3,220,604.30
6 Cor Beton Bertulang Ring Balk
- Cor Beton K-225 0.90 M3 1,780,721.06 1,607,991.11
- Pembesian 208.19 Kg 22,360.00 4,655,038.69
- Bekisting 24.08 M2 261,412.69 6,294,817.50
7 Cor Beton Bertulang Plat Lantai T:12 cm
- Cor Beton K-225 61.70 M3 1,780,721.06 109,877,612.08
- Pembesian 6,376.08 Kg 22,360.00 142,569,140.42
- Bekisting 514.20 M2 261,412.69 134,418,403.66
Total II 1,053,399,430.19

III PEKERJAAN PASANGAN


1 Pasangan Dinding 1/2 Bata, Camp 1:4 208.18 M2 226,399.88 47,131,926.13
2 Plesteran Dinding, Camp 1:4 416.36 M2 87,617.75 36,480,527.43
3 Pemasangan Lantai Keramik 40x40 54.00 M2 300,475.14 16,225,657.47
4 Pemasangan Lantai Wc keramik 20x20 2.40 M2 216,849.81 520,439.54
5 Pemasangan Dinding Wc Keramik 20x25 10.60 M2 216,849.81 2,298,607.96
Total III 102,657,158.52

IV PEKERJAAN ATAP
1 Rangka Atap kayu 5/10 1.28 M3 6,696,456.90 8,590,214.91
2 Pas Atap Seng Gelombang 117.00 M2 85,984.10 10,060,139.35
3 Pemasangan Bubungan 13.50 M' 40,594.56 548,026.60
4 Pasangan Listplank Kayu 2x20 47.50 M 88,796.39 4,217,828.41
Total IV 23,416,209.27

V PEKERJAAN KUSEN
1 Pemasangan Kusen Pintu (PJ1) 2.00 Bh 1,100,000.00 2,200,000.00
2 Pemasangan Kusen Pintu (P1) 1.00 Bh 450,000.00 450,000.00
3 Pemasangan Kusen (J2) 2.00 Bh 700,000.00 1,400,000.00
4 Pemasangan Daun Pintu (P1) 3.00 Bh 1,500,000.00 4,500,000.00
5 Pemasangan Daun Jendela (J2) 8.00 Bh 400,000.00 3,200,000.00
6 Kaca Polos t=3mm 3.06 m2 176,268.78 539,382.47
Total V 12,289,382.47

VI PEKERJAAN PENGANTUNG & PENGUNCI


1 Pemasangan Kunci Tanam 2x putar 3.00 Unit 228,148.79 684,446.36
2 Engsel Pintu Ukuran 4" 3.00 Psg 53,907.83 161,723.48
3 Engsel Jendela Ukuran 3" 8.00 Psg 44,634.08 357,072.65
4 Handle 3.00 Bh 110,963.79 332,891.36
5 Grandel 8.00 Bh 55,233.37 441,866.98
6 Kait Angin 8.00 Bh 42,123.37 336,986.98
Total VI 2,314,987.83

VII PEKERJAAN PLAFOND


HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN VOLUME SATUAN
( Rp.) ( Rp.)

1 Pemasangan rangka Plafond 74.40 M2 134,781.96 10,027,777.45


2 Pemasangan plafond Gypsum 74.40 M2 41,099.22 3,057,781.78
3 Pemasangan List Plafond Gypsum 75.20 M 54,247.19 4,079,388.73
Total VII 17,164,947.96
HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN VOLUME SATUAN
( Rp.) ( Rp.)

VIII PEKERJAAN PENGECATAN


1 pengecatan Dinding dan Struktur Expose 416.36 M2 36,385.93 15,149,647.19
2 Pengecatan Plafond 74.40 M2 36,385.93 2,707,113.44
3 Pengecatan list Plafond 7.52 M2 36,385.93 273,622.22
4 Pengecatan List Plank Kayu 19.00 M2 47,880.18 909,723.44
Total VIII 19,040,106.28

IX PEKERJAAN SANITASI
1 Pemasangan Kloset Jongkok 1.00 Bh 717,150.81 717,150.81
2 Pemasangan Kran Air 1.00 Bh 105,570.98 105,570.98
3 Pemasangan Pipa air Bersih PVC 3/4" 20.00 M 25,278.44 505,568.80
4 pemasangan Pipa Air Kotor 4" 8.00 M 122,750.63 982,005.02
Total IX 2,310,295.61

X PEKERJAAN MEKANIKAL ELECTRIKAL


1 Pemasangan Titik Lampu dan Stop Kontak 7.00 Ttk 304,458.00 2,131,206.00
2 Pemasangan lampu SL 18 Watt = downlight 5.00 Bh 55,000.00 275,000.00
3 Pemasangan Saklar tunggal 5.00 Bh 31,000.00 155,000.00
4 Pemasangan Stop kontak 2.00 Bh 42,000.00 84,000.00
Total X 2,645,206.00

XI PEKERJAAN PAGAR & TAMAN


1 Cor Beton Bertulang Kolom Pagar
- Cor Beton K-225 0.72 M3 1,780,721.06 1,282,119.16
- Pembesian 76.46 Kg 22,360.00 1,709,734.94
- Bekisting 7.20 M2 261,412.69 1,882,171.35
1 Pasangan Dinding 1/2 Bata, Camp 1:4 22.71 M2 226,399.88 5,141,541.18
2 Plesteran Dinding, Camp 1:4 45.42 M2 87,617.75 3,979,598.32
3 Pemasangan Pagar Hollow 23.80 M2 405,419.11 9,648,974.73
4 Tanah Urug 7.92 M3 310,333.14 2,457,838.43
4 Pohon Pucuk Merah 36.00 Btg 112,200.00 4,039,200.00
Total XI 30,141,178.10
A.2.3.1 HARGA SATUAN PEKERJAAN TANAH
A.2.3.1.1 Penggalian 1 m³ tanah biasa sedalam 1 m
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.750 111,780.00 83,835.00
2 Mandor L.04 OH 0.025 160,090.00 4,002.25
Jumlah Tenaga Kerja 87,837.25
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 87,837.25
E Overhead + Profit ( Contoh 15% ) 15% x D 13,175.59
F Harga Satuan Pekerjaan ( D + E ) 101,012.84

A.2.3.1.9 Pengurukan kembali 1 m³ galian tanah


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 111,780.00 55,890.00
2 Mandor L.04 OH 0.050 160,090.00 8,004.50
Jumlah Tenaga Kerja 63,894.50
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 63,894.50
E Overhead + Profit ( Contoh 15% ) 15% x D 9,584.18
F Harga Satuan Pekerjaan ( D + E ) 73,478.68

129
A.2.3.1.11 Pengurugan 1 m³ dengan pasir urug
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7

A Tenaga
1 Pekerja L.01 OH 0.300 111,780.00 33,534.00
2 Mandor L.04 OH 0.010 160,090.00 1,600.90
Jumlah Tenaga Kerja 35,134.90
B Bahan
1 Pasir Urug m³ 1.200 195,600.00 234,720.00
Jumlah Harga Bahan 234,720.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 269,854.90
E Overhead + Profit ( Contoh 15% ) 15% x D 40,478.24
F Harga Satuan Pekerjaan ( D + E ) 310,333.14

A.3.2.1.1 Pemasangan 1 m2 Paving blok


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.200 111,780.00 22,356.00
2 Tukang Batu L.02 OH 0.300 135,070.00 40,521.00
3 Kepala Tukang L.03 OH 0.030 140,740.00 4,222.20
4 Mandor L.04 OH 0.025 160,090.00 4,002.25
Jumlah Tenaga Kerja 71,101.45
B Bahan
1 Paving m2 1.000 132,000.00 132,000.00
2 Pasir Pasang m³ 0.100 297,900.00 29,790.00
Jumlah Harga Bahan 161,790.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 232,891.45
E Overhead + Profit ( Contoh 15% ) 15% x D 34,933.72
F Harga Satuan Pekerjaan ( D + E ) 267,825.17

130
A.3.2.1.2 Pemasangan 1 m' Kanstin uk. 15/20 30x50
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 111,780.00 55,890.00
2 Tukang Batu L.02 OH 0.050 135,070.00 6,753.50
3 Kepala Tukang L.03 OH 0.010 140,740.00 1,407.40
4 Mandor L.04 OH 0.001 160,090.00 160.09
Jumlah Tenaga Kerja 64,210.99
B Bahan
1 Semen (PC) zak 0.360 86,000.00 30,960.00
2 Pasir Pasang m2 0.001 297,900.00 297.90
3 Kanstin uk. 15/20 30x50 bh 2.000 51,666.67 103,333.33
Jumlah Harga Bahan 134,591.23
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 198,802.22
E Overhead + Profit ( Contoh 15% ) 15% x D 29,820.33
F Harga Satuan Pekerjaan ( D + E ) 228,622.56

A.4.1.1. HARGA SATUAN PEKERJAAN BETON


A.4.1.1.5. Membuat 1 m³ beton mutu f 'c = 14,5 Mpa ( K - 175 ), Slump ( 12 ± 2 ) cm, w/c = 0.66
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.650 111,780.00 184,437.00
2 Tukang Batu L.02 OH 0.275 135,070.00 37,144.25
3 Kepala Tukang L.03 OH 0.028 140,740.00 3,940.72
4 Mandor L.04 OH 0.083 160,090.00 13,287.47
Jumlah Tenaga Kerja 238,809.44
B Bahan
1 Semen Portland Kg 326.000 1,720.00 560,720.00
2 Pasir Beton Kg 760.000 186.19 141,502.50
3 Kerikil ( Maks 30mm ) Kg 1,029.000 506.37 521,055.11
4 Air Liter 215.000 53.00 11,395.00
Jumlah Harga Bahan 1,234,672.61
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,473,482.05
E Overhead + Profit ( Contoh 15% ) 15% x D 221,022.31
F Harga Satuan Pekerjaan ( D + E ) 1,694,504.36

131
A.4.1.1.7. Membuat 1 m³ beton mutu f 'c = 19,3 Mpa ( K - 225 ), Slump ( 12 ± 2 ) cm, w/c = 0.58
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.650 111,780.00 184,437.00
2 Tukang Batu L.02 OH 0.275 135,070.00 37,144.25
3 Kepala Tukang L.03 OH 0.028 140,740.00 3,940.72
4 Mandor L.04 OH 0.083 160,090.00 13,287.47
Jumlah Tenaga Kerja 238,809.44
B Bahan
1 Semen Portland Kg 371.000 1,720.00 638,120.00
2 Pasir Beton Kg 698.000 186.19 129,958.88
3 Kerikil ( Maks 30mm ) Kg 1,047.000 506.37 530,169.78
4 Air Liter 215.000 53.00 11,395.00
Jumlah Harga Bahan 1,309,643.65
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,548,453.09
E Overhead + Profit ( Contoh 15% ) 15% x D 232,267.96
F Harga Satuan Pekerjaan ( D + E ) 1,780,721.06

A.4.1.1.17. Pembesian 10 Kg dengan besi polos


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.070 111,780.00 7,824.60
2 Tukang Besi L.02 OH 0.070 135,070.00 9,454.90
3 Kepala Tukang L.03 OH 0.007 140,740.00 985.18
4 Mandor L.04 OH 0.004 160,090.00 640.36
Jumlah Tenaga Kerja 18,905.04
B Bahan
1 Besi Beton Polos Kg 10.500 16,392.83 172,124.73
2 Kawat Beton Kg 0.150 22,700.00 3,405.00
Jumlah Harga Bahan 175,529.73
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 194,434.77
E Overhead + Profit ( Contoh 15% ) 15% x D 29,165.22
F Harga Satuan Pekerjaan ( D + E ) 223,599.99
Harga Satuan Pekerjaan /1 kg besi F/10 22,360.00

132
A.4.1.1.21. Pemasangan 1 m² bekisting untuk sloof
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.520 111,780.00 58,125.60
2 Tukang Kayu L.02 OH 0.260 135,070.00 35,118.20
3 Kepala Tukang L.03 OH 0.026 140,740.00 3,659.24
4 Mandor L.04 OH 0.026 160,090.00 4,162.34
Jumlah Tenaga Kerja 101,065.38
B Bahan
1 Kayu Kelas III m³ 0.045 2,632,000.00 118,440.00
2 Paku 5 - 10 cm Kg 0.300 22,400.00 6,720.00
3 Minyak Bekisting Liter 0.100 10,900.00 1,090.00
Jumlah Harga Bahan 126,250.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 227,315.38
E Overhead + Profit ( Contoh 15% ) 15% x D 34,097.31
F Harga Satuan Pekerjaan ( D + E ) 261,412.69

A.4.2.1. HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM


A.4.2.1.21. Pemasangan 1 m² rangka besi holow 1 x 50 x 50 x 2 mm,
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.350 111,780.00 39,123.00
2 Tukang Besi L.02 OH 0.350 135,070.00 47,274.50
3 Kepala Tukang L.03 OH 0.0350 140,740.00 4,925.90
4 Mandor L.04 OH 0.0180 160,090.00 2,881.62
Jumlah Tenaga Kerja 94,205.02
B Bahan
1 Rangka Metal Hollow 50.50.2
m¹ 4.000 51,666.67 206,666.67
mm
2 Assesoris ( Perkuatan, Las dll 100% x
Ls 51,666.67 51,666.67
) Rangka
Jumlah Harga Bahan 258,333.33
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 352,538.35
E Overhead + Profit ( Contoh 15% ) 15% x D 52,880.75
F Harga Satuan Pekerjaan ( D + E ) 405,419.11

133
A.4.4.1. HARGA SATUAN PEKERJAAN PASANGAN DINDING
A.4.4.1.3. Pemasangan 1 m² dinding bata merah ( 9 x 9 x 18 ) cm tebal 1 batu campuran 1 SP : 4 PP
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 111,780.00 55,890.00
2 Tukang Batu L.02 OH 0.200 135,070.00 27,014.00
3 Kepala Tukang L.03 OH 0.020 140,740.00 2,814.80
4 Mandor L.04 OH 0.025 160,090.00 4,002.25
Jumlah Tenaga Kerja 89,721.05
B Bahan
1 Bata Merah m2 110.000 900.00 99,000.00
2 Semen Portland Kg 20.861 1,720.00 35,880.43
3 Pasir Pasang m³ 0.073 297,900.00 21,767.98
Jumlah Harga Bahan 156,648.41
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 246,369.46
E Overhead + Profit ( Contoh 15% ) 15% x D 36,955.42
F Harga Satuan Pekerjaan ( D + E ) 283,324.88

A.4.4.1.3. Pemasangan 1 m² dinding bata merah ( 9 x 9 x 18 ) cm tebal 1 batu campuran 1 SP : 4 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 111,780.00 55,890.00
2 Tukang Batu L.02 OH 0.200 135,070.00 27,014.00
3 Kepala Tukang L.03 OH 0.020 140,740.00 2,814.80
4 Mandor L.04 OH 0.025 160,090.00 4,002.25
Jumlah Tenaga Kerja 89,721.05
B Bahan
1 Bata Merah m2 55.000 900.00 49,500.00
2 Semen Portland Kg 20.861 1,720.00 35,880.43
3 Pasir Pasang m³ 0.073 297,900.00 21,767.98
Jumlah Harga Bahan 107,148.41
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 196,869.46
E Overhead + Profit ( Contoh 15% ) 15% x D 29,530.42
F Harga Satuan Pekerjaan ( D + E ) 226,399.88

134
A.4.4.2. HARGA SATUAN PEKERJAAN PLESTERAN
A.4.4.2.4. Pemasangan 1 m² plesteran 1 SP : 4 PP tebal 15 mm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 111,780.00 33,534.00
2 Tukang Batu L.02 OH 0.150 135,070.00 20,260.50
3 Kepala Tukang L.03 OH 0.015 140,740.00 2,111.10
4 Mandor L.04 OH 0.015 160,090.00 2,401.35
Jumlah Tenaga Kerja 58,306.95
B Bahan
1 Semen Portland Kg 6.240 1,720.00 10,732.80
2 Pasir Pasang m³ 0.024 297,900.00 7,149.60
Jumlah Harga Bahan 17,882.40
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 76,189.35
E Overhead + Profit ( Contoh 15% ) 15% x D 11,428.40
F Harga Satuan Pekerjaan ( D + E ) 87,617.75

HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN


A.4.4.3.
DINDING
A.4.4.3.35. Pemasangan 1 m² lantai keramik ukuran 40c m x 40 cm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.700 111,780.00 78,246.00
2 Tukang Batu L.02 OH 0.350 135,070.00 47,274.50
3 Kepala Tukang L.03 OH 0.035 140,740.00 4,925.90
4 Mandor L.04 OH 0.035 160,090.00 5,603.15
Jumlah Tenaga Kerja 136,049.55
B Bahan
1 Ubin Keramik Bh 6.875 12,633.33 86,854.17
2 Semen Portland Kg 10.000 1,720.00 17,200.00
3 Pasir Pasang m³ 0.045 297,900.00 13,405.50
4 Semen Warna Kg 1.500 13,100.00 19,650.00
Jumlah Harga Bahan 137,109.67
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 273,159.22
E Overhead + Profit ( Contoh 10% ) 10% x D 27,315.92
F Harga Satuan Pekerjaan ( D + E ) 300,475.14

135
A.4.4.3.36. Pemasangan 1 m² lantai keramik ukuran 20 cm x 20 cm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.700 111,780.00 78,246.00
2 Tukang Batu L.02 OH 0.350 135,070.00 47,274.50
3 Kepala Tukang L.03 OH 0.035 140,740.00 4,925.90
4 Mandor L.04 OH 0.035 160,090.00 5,603.15
Jumlah Tenaga Kerja 136,049.55
B Bahan
1 Ubin Keramik Bh 26.500 -
2 Semen Portland Kg 10.400 1,720.00 17,888.00
3 Pasir Pasang m³ 0.045 297,900.00 13,405.50
4 Semen Warna Kg 1.620 13,100.00 21,222.00
Jumlah Harga Bahan 52,515.50
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 188,565.05
E Overhead + Profit ( Contoh 15% ) 15% x D 28,284.76
F Harga Satuan Pekerjaan ( D + E ) 216,849.81

HARGA SATUAN PEKERJAAN LANGIT-LANGIT


A.4.5.1.
(PLAFOND)
A.4.5.1.7. Pemasangan 1 m² langit-langit gypsum board ukuran ( 120 x 240 x 9 ) mm, tebal 9 mm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.100 111,780.00 11,178.00
2 Tukang Kayu L.02 OH 0.050 135,070.00 6,753.50
3 Kepala Tukang L.03 OH 0.005 140,740.00 703.70
4 Mandor L.04 OH 0.005 160,090.00 800.45
Jumlah Tenaga Kerja 19,435.65
B Bahan
1 Gypsum Board Lembar 0.364 32,700.00 11,902.80
2 Paku Skrup Kg 0.110 40,000.00 4,400.00
Jumlah Harga Bahan 16,302.80
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 35,738.45
E Overhead + Profit ( Contoh 15% ) 15% x D 5,360.77
F Harga Satuan Pekerjaan ( D + E ) 41,099.22

136
A.4.5.1.9. Pemasangan 1 m¹ list langit-langit gypsum
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.050 111,780.00 5,589.00
2 Tukang Kayu L.02 OH 0.050 135,070.00 6,753.50
3 Kepala Tukang L.03 OH 0.005 140,740.00 703.70
4 Mandor L.04 OH 0.003 160,090.00 480.27
Jumlah Tenaga Kerja 13,526.47
B Bahan
1 List Gypsum m 1.050 31,100.00 32,655.00
2 Tepung gypsum Kg 0.150 6,600.00 990.00
Jumlah Harga Bahan 33,645.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 47,171.47
E Overhead + Profit ( Contoh 15% ) 15% x D 7,075.72
F Harga Satuan Pekerjaan ( D + E ) 54,247.19

A.4.5.2. HARGA SATUAN PEKERJAAN PENUTUP ATAP


A.4.5.2.38. Pemasangan 1 m² atap seng gelombang
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.120 111,780.00 13,413.60
2 Tukang Kayu L.02 OH 0.060 135,070.00 8,104.20
3 Kepala Tukang L.03 OH 0.0060 140,740.00 844.44
4 Mandor L.04 OH 0.006 160,090.00 960.54
Jumlah Tenaga Kerja 23,322.78
B Bahan
1 Seng Gelombang 3" x 6" Lembar 0.700 72,600.00 50,820.00
2 Paku Seng Kg 0.020 31,300.00 626.00
Jumlah Harga Bahan 51,446.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 74,768.78
E Overhead + Profit ( Contoh 15% ) 15% x D 11,215.32
F Harga Satuan Pekerjaan ( D + E ) 85,984.10

137
A.4.5.2.39. Pemasangan 1 m¹ nok atap seng
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.150 111,780.00 16,767.00
2 Tukang Kayu L.02 OH 0.070 135,070.00 9,454.90
3 Kepala Tukang L.03 OH 0.0070 140,740.00 985.18
4 Mandor L.04 OH 0.006 160,090.00 960.54
Jumlah Tenaga Kerja 28,167.62
B Bahan
1 Seng Plat 3" x 6" BJLS 28 Lembar 0.300 19,600.00 5,880.00
2 Paku Seng Kg 0.040 31,300.00 1,252.00
Jumlah Harga Bahan 7,132.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 35,299.62
E Overhead + Profit ( Contoh 15% ) 15% x D 5,294.94
F Harga Satuan Pekerjaan ( D + E ) 40,594.56

A.4.6.1. HARGA SATUAN PEKERJAAN KAYU


A.4.6.1.13. Pemasangan 1 m³ konstruksi kuda-kuda konvensional, kayu kelas I, II dan III
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 4.000 111,780.00 447,120.00
2 Tukang Kayu L.02 OH 12.000 135,070.00 1,620,840.00
3 Kepala Tukang L.03 OH 1.2000 140,740.00 168,888.00
4 Mandor L.04 OH 0.200 160,090.00 32,018.00
Jumlah Tenaga Kerja 2,268,866.00
B Bahan
1 Balok Kayu m³ 1.1000 3,117,000.00 3,428,700.00
2 Besi Strip Tebal 5 mm Kg 15.000 -
3 Paku 12 cm Kg 5.600 22,400.00 125,440.00
Jumlah Harga Bahan 3,554,140.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 5,823,006.00
E Overhead + Profit ( Contoh 15% ) 15% x D 873,450.90
F Harga Satuan Pekerjaan ( D + E ) 6,696,456.90

138
A.4.6.1.20. Pemasangan 1 m² rangka langit-langit ( 60 x 60 ) cm, kayu kelas II atau III
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.200 111,780.00 22,356.00
2 Tukang Kayu L.02 OH 0.300 135,070.00 40,521.00
3 Kepala Tukang L.03 OH 0.0300 140,740.00 4,222.20
4 Mandor L.04 OH 0.010 160,090.00 1,600.90
Jumlah Tenaga Kerja 68,700.10
B Bahan
1 Kaso-kaso m³ 0.0163 2,632,000.00 42,901.60
2 Paku 7 cm - 10 cm Kg 0.250 22,400.00 5,600.00
Jumlah Harga Bahan 48,501.60
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 117,201.70
E Overhead + Profit ( Contoh 15% ) 15% x D 17,580.26
F Harga Satuan Pekerjaan ( D + E ) 134,781.96

A.4.6.1.22. Pemasangan 1 m¹ listplank ukuran ( 3 x 30 ) cm, kayu kelas I atau kelas II


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.100 111,780.00 11,178.00
2 Tukang Kayu L.02 OH 0.200 135,070.00 27,014.00
3 Kepala Tukang L.03 OH 0.0200 140,740.00 2,814.80
4 Mandor L.04 OH 0.005 160,090.00 800.45
Jumlah Tenaga Kerja 41,807.25
B Bahan
1 Papan Kayu m³ 0.0110 3,117,000.00 34,287.00
2 Paku 5 cm dan 7 cm Kg 0.050 22,400.00 1,120.00
Jumlah Harga Bahan 35,407.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 77,214.25
E Overhead + Profit ( Contoh 15% ) 15% x D 11,582.14
F Harga Satuan Pekerjaan ( D + E ) 88,796.39

139
A.4.6.2. HARGA SATUAN PEKERJAAN KUNCI DAN KACA
A.4.6.2.2. Pemasangan 1 buah kunci tanam
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.010 111,780.00 1,117.80
2 Tukang Kayu L.02 OH 0.500 135,070.00 67,535.00
3 Kepala Tukang L.03 OH 0.0500 140,740.00 7,037.00
4 Mandor L.04 OH 0.005 160,090.00 800.45
Jumlah Tenaga Kerja 76,490.25
B Bahan
1 Kunci Tanam Biasa Buah 1.000 121,900.00 121,900.00
Jumlah Harga Bahan 121,900.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 198,390.25
E Overhead + Profit ( Contoh 15% ) 15% x D 29,758.54
F Harga Satuan Pekerjaan ( D + E ) 228,148.79

A.4.6.2.2. Pemasangan 1 pasang handle pintu


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.010 111,780.00 1,117.80
2 Tukang Kayu L.02 OH 0.500 135,070.00 67,535.00
3 Kepala Tukang L.03 OH 0.0500 140,740.00 7,037.00
4 Mandor L.04 OH 0.005 160,090.00 800.45
Jumlah Tenaga Kerja 76,490.25
B Bahan
1 Handle pintu Buah 1.000 20,000.00 20,000.00
Jumlah Harga Bahan 20,000.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 96,490.25
E Overhead + Profit ( Contoh 15% ) 15% x D 14,473.54
F Harga Satuan Pekerjaan ( D + E ) 110,963.79

140
A.4.6.2.5. Pemasangan 1 buah engsel pintu
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.015 111,780.00 1,676.70
2 Tukang Kayu L.02 OH 0.150 135,070.00 20,260.50
3 Kepala Tukang L.03 OH 0.0150 140,740.00 2,111.10
4 Mandor L.04 OH 0.0008 160,090.00 128.07
Jumlah Tenaga Kerja 24,176.37
B Bahan
1 Engsel Pintu Buah 1.000 22,700.00 22,700.00
Jumlah Harga Bahan 22,700.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 46,876.37
E Overhead + Profit ( Contoh 15% ) 15% x D 7,031.46
F Harga Satuan Pekerjaan ( D + E ) 53,907.83

A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.010 111,780.00 1,117.80
2 Tukang Kayu L.02 OH 0.100 135,070.00 13,507.00
3 Kepala Tukang L.03 OH 0.0100 140,740.00 1,407.40
4 Mandor L.04 OH 0.0005 160,090.00 80.05
Jumlah Tenaga Kerja 16,112.25
B Bahan
1 Engsel Kupu-kupu Buah 1.000 22,700.00 22,700.00
Jumlah Harga Bahan 22,700.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 38,812.25
E Overhead + Profit ( Contoh 15% ) 15% x D 5,821.84
F Harga Satuan Pekerjaan ( D + E ) 44,634.08

141
A.4.6.2.9. Pemasangan 1 buah kait angin
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.015 111,780.00 1,676.70
2 Tukang Kayu L.02 OH 0.150 135,070.00 20,260.50
3 Kepala Tukang L.03 OH 0.0150 140,740.00 2,111.10
4 Mandor L.04 OH 0.0080 160,090.00 1,280.72
Jumlah Tenaga Kerja 25,329.02
B Bahan
1 Kait Angin Buah 1.000 11,300.00 11,300.00
Jumlah Harga Bahan 11,300.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 36,629.02
E Overhead + Profit ( Contoh 15% ) 15% x D 5,494.35
F Harga Satuan Pekerjaan ( D + E ) 42,123.37

A.4.6.2.9. Pemasangan 1 buah handle / grendle


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.015 111,780.00 1,676.70
2 Tukang Kayu L.02 OH 0.150 135,070.00 20,260.50
3 Kepala Tukang L.03 OH 0.0150 140,740.00 2,111.10
4 Mandor L.04 OH 0.0080 160,090.00 1,280.72
Jumlah Tenaga Kerja 25,329.02
B Bahan
1 handle Buah 1.000 22,700.00 22,700.00
Jumlah Harga Bahan 22,700.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 48,029.02
E Overhead + Profit ( Contoh 15% ) 15% x D 7,204.35
F Harga Satuan Pekerjaan ( D + E ) 55,233.37

142
A.4.6.2.16. Pemasangan 1 m² kaca tebal 3 mm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.015 111,780.00 1,676.70
2 Tukang Kayu L.02 OH 0.150 135,070.00 20,260.50
3 Kepala Tukang L.03 OH 0.0015 140,740.00 211.11
4 Mandor L.04 OH 0.0008 160,090.00 128.07
Jumlah Tenaga Kerja 21,937.20
B Bahan
1 Kaca Tebal 3 mm m² 1.100 119,400.00 131,340.00
2 Sealant Kg 0.050 31,100.00 1,555.00
Jumlah Harga Bahan 131,340.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 153,277.20
E Overhead + Profit ( Contoh 15% ) 15% x D 22,991.58
F Harga Satuan Pekerjaan ( D + E ) 176,268.78

A.4.7.1. HARGA SATUAN PEKERJAAN PENGECATAN


A.4.7.1.4. 1 m² pengecatan bidang kayu baru ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.070 111,780.00 7,824.60
2 Tukang Cat L.02 OH 0.009 135,070.00 1,215.63
3 Kepala Tukang L.03 OH 0.006 140,740.00 844.44
4 Mandor L.04 OH 0.003 160,090.00 480.27
Jumlah Tenaga Kerja 10,364.94
B Bahan
1 Cat Menie Kg 0.200 28,000.00 5,600.00
2 Plamir Kg 0.150 8,800.00 1,320.00
3 Cat Dasar Kg 0.170 51,800.00 8,806.00
4 Cat Penutup Kg 0.260 51,800.00 13,468.00
5 Kuas Buah 0.010 18,200.00 182.00
6 Pengencer Kg 0.030 25,800.00 774.00
7 Ampelas Lembar 0.200 5,600.00 1,120.00
Jumlah Harga Bahan 31,270.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 41,634.94
E Overhead + Profit ( Contoh 15% ) 15% x D 6,245.24
F Harga Satuan Pekerjaan ( D + E ) 47,880.18

143
A.4.7.1.10. Pengecataan 1 m² tembok baru ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.020 111,780.00 2,235.60
2 Tukang Cat L.02 OH 0.063 135,070.00 8,509.41
3 Kepala Tukang L.03 OH 0.0063 140,740.00 886.66
4 Mandor L.04 OH 0.003 160,090.00 480.27
Jumlah Tenaga Kerja 12,111.94
B Bahan
1 Plamir Kg 0.100 8,800.00 880.00
2 Cat Dasar Kg 0.100 51,800.00 5,180.00
3 Cat Penutup Kg 0.260 51,800.00 13,468.00
Jumlah Harga Bahan 19,528.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 31,639.94
E Overhead + Profit ( Contoh 15% ) 15% x D 4,745.99
F Harga Satuan Pekerjaan ( D + E ) 36,385.93

A.5.1.1. HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG


A.5.1.1.2. Pemasangan 1 buah closet jongkok porslen
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.000 111,780.00 111,780.00
2 Tukang Batu L.02 OH 1.500 135,070.00 202,605.00
3 Kepala Tukang L.03 OH 0.150 140,740.00 21,111.00
4 Mandor L.04 OH 0.160 160,090.00 25,614.40
Jumlah Tenaga Kerja 361,110.40
B Bahan
1 Closet Jongkok Unit 1.000 249,200.00 249,200.00
2 Semen Portland Kg 6.000 1,720.00 10,320.00
3 Pasir Pasang m³ 0.010 297,900.00 2,979.00
Jumlah Harga Bahan 262,499.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 623,609.40
E Overhead + Profit ( Contoh 15% ) 15% x D 93,541.41
F Harga Satuan Pekerjaan ( D + E ) 717,150.81

144
A.5.1.1.19. Pemasangan 1 buah kran air ؽ" atau ؾ"
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.010 111,780.00 1,117.80
2 Tukang Batu L.02 OH 0.400 135,070.00 54,028.00
3 Kepala Tukang L.03 OH 0.040 140,740.00 5,629.60
4 Mandor L.04 OH 0.005 160,090.00 800.45
Jumlah Tenaga Kerja 61,575.85
B Bahan
1 Kran Air ؽ" atau ؾ m¹ 1.000 30,100.00 30,100.00
2 Sealtape Buah 0.025 5,000.00 125.00
Jumlah Harga Bahan 30,225.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 91,800.85
E Overhead + Profit ( Contoh 15% ) 15% x D 13,770.13
F Harga Satuan Pekerjaan ( D + E ) 105,570.98

A.5.1.1.26. Pemasangan 1 m¹ PVC type AW ؾ"


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.036 111,780.00 4,024.08
2 Tukang Batu L.02 OH 0.060 135,070.00 8,104.20
3 Kepala Tukang L.03 OH 0.006 140,740.00 844.44
4 Mandor L.04 OH 0.002 160,090.00 320.18
Jumlah Tenaga Kerja 13,292.90
B Bahan
1 Pipa PVC ؾ" m¹ 1.200 6,250.00 7,500.00
2 Perlengkapan % 35.000 2,187.50 2,187.50
Jumlah Harga Bahan 9,687.50
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 22,980.40
E Overhead + Profit ( Contoh 10% ) 10% x D 2,298.04
F Harga Satuan Pekerjaan ( D + E ) 25,278.44

145
A.5.1.1.32. Pemasangan 1 m¹ PVC type AW Ø4"
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.081 111,780.00 9,054.18
2 Tukang Batu L.02 OH 0.135 135,070.00 18,234.45
3 Kepala Tukang L.03 OH 0.0135 140,740.00 1,899.99
4 Mandor L.04 OH 0.004 160,090.00 640.36
Jumlah Tenaga Kerja 29,828.98
B Bahan
1 Pipa PVC Ø4" m¹ 1.200 52,750.00 63,300.00
2 Perlengkapan % 35.000 18,462.50 18,462.50
Jumlah Harga Bahan 81,762.50
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 111,591.48
E Overhead + Profit ( Contoh 10% ) 10% x D 11,159.15
F Harga Satuan Pekerjaan ( D + E ) 122,750.63

(K3) Pemasangan 1 Buah Titik Lampu


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Upah L.01 % 100.000 111,780.00 111,780.00
Jumlah Tenaga Kerja 111,780.00
B Bahan
1 Pipa listrik dia 5/8" btg 3.000 15,000.00 45,000.00
2 Kabel m¹ 24.000 5,000.00 120,000.00
3 T dus bh 3.000 2,000.00 6,000.00
4 L bow bh 4.000 2,000.00 8,000.00
5 Las Dop bh 3.000 2,000.00 6,000.00
6 Klem bh 24.000 2,000.00 48,000.00
7 Mangkok bh 1.000 2,000.00 2,000.00
8 Saklar bh 1.000 15,000.00 15,000.00
9 Fitting bh 1.000 2,000.00 2,000.00
Jumlah Harga Bahan 165,000.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 276,780.00
E Overhead + Profit ( Contoh 10% ) 10% x D 27,678.00
F Harga Satuan Pekerjaan ( D + E ) 304,458.00

146
CV. BLUE Print Consultant
Planning, Supervision & Engineering Consultant
Office: Jl. Yos Sudarso RT. 002 Sebengkok Tarakan
e-mail : blueprintconsultant@yahoo.com

DAFTAR HARGA SATUAN


PAKET KEGIATAN :
TAMAN BELAKANG BRI

LOKASI : TARAKAN
TAHUN : 2020

No. URAIAN BAHAN SATUAN HARGA SATUAN KETERANGAN

(1) (2) (3) (4) (5)

I UPAH (standar harga kota Tarakan)

1 Pekerja Hari Rp. 111,780.00


2 Tukang Hari Rp. 135,070.00
3 Mandor Hari Rp. 160,090.00
4 Kepala Tukang Hari Rp. 140,740.00

II BAHAN
1 Agregat Kasar/batu pecah M3 Rp. 683,600 506.37 Kg + Ongkos Angkut
2 Semen (50kg) Zak Rp. 86,000 1,720.00 / kg + Ongkos Angkut
3 Semen Warna Kg Rp. 13,100 / kg + Ongkos Angkut
4 Besi beton polos Kg Rp. 16,393 + Ongkos Angkut
5 Kawat Ikat / Kg Rp. 22,700
6 Plywood 4 mm / Lbr Rp. 85,200 + Ongkos Angkut
7 Keramik 40x40 / Kotak Rp. 12,633 75,800.00 + Ongkos Angkut
8 Keramik 20x20 / Kotak Rp. 3,032 75,800.00 + Ongkos Angkut
9 Paku Biasa / Kg Rp. 22,400
10 Paku Seng / Kg Rp. 31,300
11 Paku Sekrup / Kg Rp. 40,000
12 Tear Oil / Kg Rp. 35,300
13 Minyak Begesting Ltr Rp. 10,900
14 Batu Pecah / M3 Rp. 683,600 471.45 /kg + Ongkos Angkut
15 Pasir Pasangan / M3 Rp. 297,900 186.19 /kg + Ongkos Angkut
16 Tanah Urug / Pasir urug / M3 Rp. 195,600 + Ongkos Angkut
17 Batu Bata / Bh Rp. 900 + Ongkos Angkut
18 Paving Blok ( t = 8 cm ) / Bh Rp. 3,000
19 Air Bersih Ltr Rp. 53
20 Kayu Perancah / M3 Rp. 2,742,000 + Ongkos Angkut
21 Kayu Meranti / M3 Rp. 2,632,000 + Ongkos Angkut
22 Kayu Kapur / Bengkirai / Lembasung / M3 Rp. 3,117,000 + Ongkos Angkut
23 Hollow 50x50x2 /m Rp. 51,667
24 Seng Plat 3" x 6" BJLS 28 /m Rp. 19,600
25 Seng Gelombang 3" x 6" / Lbr Rp. 72,600
26 BRC 175x240 / Lbr Rp. 675,000
27 Pohon Palem Ekor Tupai / Pokok Rp. 525,000
28 Rumput Gajah Mini / M2 Rp. 77,100
29 Pohon Pucuk Merah / Pokok Rp. 178,000
30 Kran Air / Bh Rp. 30,100
31 Pipa PVC 3/4" /M Rp. 6,250 25,000.00
32 Pipa PVC 4" /M Rp. 52,750 211,000.00
33 Kloset Jongkok / Bh Rp. 249,200
34 Plamir / Kg Rp. 8,800
35 Cat Air / Kg Rp. 51,800
36 Cat Minyak / Kg Rp. 56,000
37 Menie / Kg Rp. 28,000
38 Kuas / Bh Rp. 18,200
39 Ampelas / Lembar Rp. 5,600
40 Thiner / Ltr Rp. 25,800
41 Kaca 3mm / M2 Rp. 119,400
42 Sealent / Tube Rp. 31,100
43 Heandle / Bh Rp. 20,000
44 Grendle / Bh Rp. 22,700
45 Kait Angin / Bh Rp. 11,300
46 Engsel 4" / Bh Rp. 22,700
47 Engsel 3" / Bh Rp. 22,700
48 Kunci Tanam / Bh Rp. 121,900
49 Gypsum Board / Lbr Rp. 32,700 + Ongkos Angkut
50 List Gypsum /M Rp. 31,100 + Ongkos Angkut
51 Tepung Gypsum / Kg Rp. 6,600 + Ongkos Angkut
52 Pancang Beton 10/10 400 / Btg Rp. 404,400 + Ongkos Angkut
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : TAMAN BELAKANG BRI
PROP / KAB / KODYA : Kalimanta Utara / Kota Tarakan
JENIS PEKERJAAN Penyelenggaraan Sistem Manajemen Keselamatan Konstruksi (SMKK)
SATUAN PEMBAYARAN : Ls

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp.)
1 2 3 4 5 6 7
A SOSIALISASI
1 Spanduk K3 Lb 1.00 150,000.00 150,000.00
2 Pengarahan K3 (Safety Briefing) Org 1.00 15,000.00 15,000.00
Jumlah B 165,000.00
B APD Dan APK
1 Helm Pelindung (Safety Helmet) Buah 5.00 81,439.00 407,195.00
2 Sarung Tangan (Safety Gloves) Psg 15.00 20,000.00 300,000.00
4 Sepatu Keselamatan (Rubber Safety Shoes) Psg 5.00 100,000.00 500,000.00
5 Rompi Keselamatan (Safety Vest) Buah 5.00 25,000.00 125,000.00
Jumlah C 1,332,195.00
C ASURANSI
1 Asuransi Ls 1.00 190,000.00 190,000.00
Jumlah D 190,000.00
D RAMBU-RAMBU
1 Rambu Peringatan Buah 1.00 75,000.00 75,000.00
2 Rambu Informasi Buah 1.00 75,000.00 75,000.00
Jumlah G 150,000.00
Jumlah A s/d H 1,837,195.00
CV. BLUE Print Consultant
Planning, Supervision & Engineering Consultant
Office: Jl. Yos Sudarso RT. 002 Sebengkok Tarakan
e-mail : blueprintconsultant@yahoo.com

REKAPITULASI
ESTIMATE ENGINEERING (EE)
PAKET KEGIATAN : TAMAN BELAKANG BRI
LOKASI : TARAKAN
TAHUN : 2020

JUMLAH BIAYA
No. URAIAN PEKERJAAN
( Rp. )
I PEKERJAAN PERSIAPAN Rp. 3,087,195.00
II PEKERJAAN BETON Rp. 167,156,544.06
III PEKERJAAN PAGAR & TAMAN Rp. 11,575,000.00

JUM LAH Rp. 181,818,739.06

PPn 10% Rp. 18,181,873.91

TOTAL KESELURUHAN Rp. 200,000,612.97

DIBULATKAN Rp. 200,000,000.00


Terbilang :

Dua Ratus Juta Rupiah

Tarakan, 18 Maret 2020


Di Periksa Konsultan Perencana
Pejabat Pembuat Komitmen CV. BLUE Print Consultant
Dinas Pekerjaan Umum dan Tata Ruang
Kota Tarakan

Drs. BROTO SUBAGYO MUHAMMAD RAMLI, ST


NIP. 19620314 199003 1 001 Direktur
CV. BLUE Print Consultant
Planning, Supervision & Engineering Consultant
Office: Jl. Yos Sudarso RT. 002 Sebengkok Tarakan
e-mail : blueprintconsultant@yahoo.com

ESTIMATE ENGINEERING (EE)


PAKET KEGIATAN : TAMAN BELAKANG BRI
LOKASI : TARAKAN
TAHUN : 2020

HARGA SATUAN JUMLAH


No. URAIAN PEKERJAAN VOLUME SATUAN
( Rp.) ( Rp.)

I PEKERJAAN PERSIAPAN
1 Plank Nama Proyek 1.00 ls 500,000.00 500,000.00
2 Dokumentasi 1.00 ls 750,000.00 750,000.00
3 K3 1.00 ls 1,837,195.00 1,837,195.00

Total I 3,087,195.00

II PEKERJAAN BETON
1 Pancang Beton 10/10, 400 125.00 Btg 404,400.00 50,550,000.00
2 Cor Beton Bertulang Foot Plat
- Cor Beton K-225 3.20 M3 1,780,721.06 5,698,307.38
- Pembesian 728.00 Kg 22,360.00 16,278,079.04
- Bekisting 16.00 M2 261,412.69 4,182,602.99
3 Cor Beton Bertulang Kolom K1
- Cor Beton K-225 0.70 M3 1,780,721.06 1,252,069.49
- Pembesian 369.80 Kg 22,360.00 8,268,727.51
- Bekisting 18.45 M2 261,412.69 4,823,201.32
4 Cor Beton Bertulang Balok B1
- Cor Beton K-225 3.68 M3 1,780,721.06 6,544,149.88
- Pembesian 834.48 Kg 22,360.00 18,658,971.70
- Bekisting 31.85 M2 261,412.69 8,325,994.08
5 Cor Beton Bertulang Plat Lantai T:12 cm
- Cor Beton K-225 7.68 M3 1,780,721.06 13,675,937.72
- Pembesian 793.60 Kg 22,360.00 17,744,894.96
- Bekisting 42.67 M2 261,412.69 11,153,607.98
Total II 167,156,544.06

III PEKERJAAN PAGAR & TAMAN


1 Pekerjaan Pagar BRC
- Tiang BRC 2" 14.00 Btg 200,000.00 2,800,000.00
- Pagar BRC 175x240 13.00 Lbr 675,000.00 8,775,000.00
Total III 11,575,000.00
A.4.1.1. HARGA SATUAN PEKERJAAN BETON
A.4.1.1.5. Membuat 1 m³ beton mutu f 'c = 14,5 Mpa ( K - 175 ), Slump ( 12 ± 2 ) cm, w/c = 0.66
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.650 111,780.00 184,437.00
2 Tukang Batu L.02 OH 0.275 135,070.00 37,144.25
3 Kepala Tukang L.03 OH 0.028 140,740.00 3,940.72
4 Mandor L.04 OH 0.083 160,090.00 13,287.47
Jumlah Tenaga Kerja 238,809.44
B Bahan
1 Semen Portland Kg 326.000 1,720.00 560,720.00
2 Pasir Beton Kg 760.000 186.19 141,502.50
3 Kerikil ( Maks 30mm ) Kg 1,029.000 506.37 521,055.11
4 Air Liter 215.000 53.00 11,395.00
Jumlah Harga Bahan 1,234,672.61
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,473,482.05
E Overhead + Profit ( Contoh 15% ) 15% x D 221,022.31
F Harga Satuan Pekerjaan ( D + E ) 1,694,504.36

A.4.1.1.7. Membuat 1 m³ beton mutu f 'c = 19,3 Mpa ( K - 225 ), Slump ( 12 ± 2 ) cm, w/c = 0.58
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.650 111,780.00 184,437.00
2 Tukang Batu L.02 OH 0.275 135,070.00 37,144.25
3 Kepala Tukang L.03 OH 0.028 140,740.00 3,940.72
4 Mandor L.04 OH 0.083 160,090.00 13,287.47
Jumlah Tenaga Kerja 238,809.44
B Bahan
1 Semen Portland Kg 371.000 1,720.00 638,120.00
2 Pasir Beton Kg 698.000 186.19 129,958.88
3 Kerikil ( Maks 30mm ) Kg 1,047.000 506.37 530,169.78
4 Air Liter 215.000 53.00 11,395.00
Jumlah Harga Bahan 1,309,643.65
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,548,453.09
E Overhead + Profit ( Contoh 15% ) 15% x D 232,267.96
F Harga Satuan Pekerjaan ( D + E ) 1,780,721.06

152
A.4.1.1.17. Pembesian 10 Kg dengan besi polos
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.070 111,780.00 7,824.60
2 Tukang Besi L.02 OH 0.070 135,070.00 9,454.90
3 Kepala Tukang L.03 OH 0.007 140,740.00 985.18
4 Mandor L.04 OH 0.004 160,090.00 640.36
Jumlah Tenaga Kerja 18,905.04
B Bahan
1 Besi Beton Polos Kg 10.500 16,392.83 172,124.73
2 Kawat Beton Kg 0.150 22,700.00 3,405.00
Jumlah Harga Bahan 175,529.73
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 194,434.77
E Overhead + Profit ( Contoh 15% ) 15% x D 29,165.22
F Harga Satuan Pekerjaan ( D + E ) 223,599.99
Harga Satuan Pekerjaan /1 kg besi F/10 22,360.00

A.4.1.1.21. Pemasangan 1 m² bekisting untuk sloof


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.520 111,780.00 58,125.60
2 Tukang Kayu L.02 OH 0.260 135,070.00 35,118.20
3 Kepala Tukang L.03 OH 0.026 140,740.00 3,659.24
4 Mandor L.04 OH 0.026 160,090.00 4,162.34
Jumlah Tenaga Kerja 101,065.38
B Bahan
1 Kayu Kelas III m³ 0.045 2,632,000.00 118,440.00
2 Paku 5 - 10 cm Kg 0.300 22,400.00 6,720.00
3 Minyak Bekisting Liter 0.100 10,900.00 1,090.00
Jumlah Harga Bahan 126,250.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 227,315.38
E Overhead + Profit ( Contoh 15% ) 15% x D 34,097.31
F Harga Satuan Pekerjaan ( D + E ) 261,412.69

153
CV. BLUE Print Consultant
Planning, Supervision & Engineering Consultant
Office: Jl. Yos Sudarso RT. 002 Sebengkok Tarakan
e-mail : blueprintconsultant@yahoo.com

DAFTAR HARGA SATUAN


PAKET KEGIATAN :
TAMAN BELAKANG BRI

LOKASI : TARAKAN
TAHUN : 2020

No. URAIAN BAHAN SATUAN HARGA SATUAN KETERANGAN

(1) (2) (3) (4) (5)

I UPAH (standar harga kota Tarakan)

1 Pekerja Hari Rp. 111,780.00


2 Tukang Hari Rp. 135,070.00
3 Mandor Hari Rp. 160,090.00
4 Kepala Tukang Hari Rp. 140,740.00

II BAHAN
1 Agregat Kasar/batu pecah M3 Rp. 683,600 506.37 Kg + Ongkos Angkut
2 Semen (50kg) Zak Rp. 86,000 1,720.00 / kg + Ongkos Angkut
3 Semen Warna Kg Rp. 13,100 / kg + Ongkos Angkut
4 Besi beton polos Kg Rp. 16,393 + Ongkos Angkut
5 Kawat Ikat / Kg Rp. 22,700
6 Plywood 4 mm / Lbr Rp. 85,200 + Ongkos Angkut
7 Keramik 40x40 / Kotak Rp. 12,633 75,800.00 + Ongkos Angkut
8 Keramik 20x20 / Kotak Rp. 3,032 75,800.00 + Ongkos Angkut
9 Paku Biasa / Kg Rp. 22,400
10 Paku Seng / Kg Rp. 31,300
11 Paku Sekrup / Kg Rp. 40,000
12 Tear Oil / Kg Rp. 35,300
13 Minyak Begesting Ltr Rp. 10,900
14 Batu Pecah / M3 Rp. 683,600 471.45 /kg + Ongkos Angkut
15 Pasir Pasangan / M3 Rp. 297,900 186.19 /kg + Ongkos Angkut
16 Tanah Urug / Pasir urug / M3 Rp. 195,600 + Ongkos Angkut
17 Batu Bata / Bh Rp. 900 + Ongkos Angkut
18 Paving Blok ( t = 8 cm ) / Bh Rp. 3,000
19 Air Bersih Ltr Rp. 53
20 Kayu Perancah / M3 Rp. 2,742,000 + Ongkos Angkut
21 Kayu Meranti / M3 Rp. 2,632,000 + Ongkos Angkut
22 Kayu Kapur / Bengkirai / Lembasung / M3 Rp. 3,117,000 + Ongkos Angkut
23 Hollow 50x50x2 /m Rp. 51,667
24 Seng Plat 3" x 6" BJLS 28 /m Rp. 19,600
25 Seng Gelombang 3" x 6" / Lbr Rp. 72,600
26 BRC 175x240 / Lbr Rp. 675,000
27 Pohon Palem Ekor Tupai / Pokok Rp. 525,000
28 Rumput Gajah Mini / M2 Rp. 77,100
29 Pohon Pucuk Merah / Pokok Rp. 178,000
30 Kran Air / Bh Rp. 30,100
31 Pipa PVC 3/4" /M Rp. 6,250 25,000.00
32 Pipa PVC 4" /M Rp. 52,750 211,000.00
33 Kloset Jongkok / Bh Rp. 249,200
34 Plamir / Kg Rp. 8,800
35 Cat Air / Kg Rp. 51,800
36 Cat Minyak / Kg Rp. 56,000
37 Menie / Kg Rp. 28,000
38 Kuas / Bh Rp. 18,200
39 Ampelas / Lembar Rp. 5,600
40 Thiner / Ltr Rp. 25,800
41 Kaca 3mm / M2 Rp. 119,400
42 Sealent / Tube Rp. 31,100
43 Heandle / Bh Rp. 20,000
44 Grendle / Bh Rp. 22,700
45 Kait Angin / Bh Rp. 11,300
46 Engsel 4" / Bh Rp. 22,700
47 Engsel 3" / Bh Rp. 22,700
48 Kunci Tanam / Bh Rp. 121,900
49 Gypsum Board / Lbr Rp. 32,700 + Ongkos Angkut
50 List Gypsum /M Rp. 31,100 + Ongkos Angkut
51 Tepung Gypsum / Kg Rp. 6,600 + Ongkos Angkut
52 Pancang Beton 10/10 400 / Btg Rp. 404,400 + Ongkos Angkut
53 BRC 175x240 / Lbr Rp. 675,000
54 Tiang BRC Galvanis / Btg Rp. 200,000
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : TAMAN BELAKANG BRI
PROP / KAB / KODYA : Kalimanta Utara / Kota Tarakan
JENIS PEKERJAAN Penyelenggaraan Sistem Manajemen Keselamatan Konstruksi (SMKK)
SATUAN PEMBAYARAN : Ls

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp.)
1 2 3 4 5 6 7
A SOSIALISASI
1 Spanduk K3 Lb 1.00 150,000.00 150,000.00
2 Pengarahan K3 (Safety Briefing) Org 1.00 15,000.00 15,000.00
Jumlah B 165,000.00
B APD Dan APK
1 Helm Pelindung (Safety Helmet) Buah 5.00 81,439.00 407,195.00
2 Sarung Tangan (Safety Gloves) Psg 15.00 20,000.00 300,000.00
4 Sepatu Keselamatan (Rubber Safety Shoes) Psg 5.00 100,000.00 500,000.00
5 Rompi Keselamatan (Safety Vest) Buah 5.00 25,000.00 125,000.00
Jumlah C 1,332,195.00
C ASURANSI
1 Asuransi Ls 1.00 190,000.00 190,000.00
Jumlah D 190,000.00
D RAMBU-RAMBU
1 Rambu Peringatan Buah 1.00 75,000.00 75,000.00
2 Rambu Informasi Buah 1.00 75,000.00 75,000.00
Jumlah G 150,000.00
Jumlah A s/d H 1,837,195.00
CV. BLUE Print Consultant
Planning, Supervision & Engineering Consultant
Office: Jl. Yos Sudarso RT. 002 Sebengkok Tarakan
e-mail : blueprintconsultant@yahoo.com

###

REKAPITULASI
ESTIMATE ENGINEERING (EE)
PAKET KEGIATAN : PEMBUATAN TAMAN KELURAHAN PAMUSIAN
LOKASI : TARAKAN
TAHUN : 2020

JUMLAH BIAYA
No. URAIAN PEKERJAAN
( Rp. )
I PEKERJAAN PERSIAPAN Rp. 3,087,195.00 ###
II PEKERJAAN AREA TAMAN Rp. 178,730,996.60 ###

JUM LAH Rp. 181,818,191.60

PPn 10% Rp. 18,181,819.16

TOTAL KESELURUHAN Rp. 200,000,010.76 ###

DIBULATKAN Rp. 200,000,000.00 ###


Terbilang :

Dua Ratus Juta

Tarakan, 18 Maret 2020


Di Periksa Konsultan Perencana
Pejabat Pembuat Komitmen CV. BLUE Print Consultant
Dinas Pekerjaan Umum dan Tata Ruang
Kota Tarakan

Drs. BROTO SUBAGYO MUHAMMAD RAMLI, ST


NIP. 19620314 199003 1 001 Direktur
CV. BLUE Print Consultant
Planning, Supervision & Engineering Consultant
Office: Jl. Yos Sudarso RT. 002 Sebengkok Tarakan
e-mail : blueprintconsultant@yahoo.com

ESTIMATE ENGINEERING (EE)


PAKET KEGIATAN : PEMBUATAN TAMAN KELURAHAN PAMUSIAN
LOKASI : TARAKAN
TAHUN : 2020

HARGA SATUAN JUMLAH


No. URAIAN PEKERJAAN VOLUME SATUAN
( Rp.) ( Rp.)

I PEKERJAAN PERSIAPAN
1 Plank Nama Proyek 1.00 ls 500,000.00 500,000.00
2 Dokumentasi 1.00 ls 750,000.00 750,000.00
3 K3 1.00 ls 1,837,195.00 1,837,195.00

Total I 3,087,195.00

II PEKERJAAN AREA TAMAN


1 Galian Tanah 1.55 m3 99,331.25 153,764.78
2 Urugan Tanah 88.26 m3 157,860.50 13,933,083.45
2 Pasir Urug 17.62 m3 205,332.50 3,617,198.92
3 Pemasangan Paving Press 147.87 m2 251,016.25 37,117,772.89
4 Pembuatan Pengunci Paving
- Cor Beton K-175 6.10 m3 1,353,533.39 8,250,733.48
- Bekisting 6.10 m2 254,161.50 1,549,292.26
6 Rumput Gajah Mini 80.00 m2 61,500.00 4,920,000.00
7 Pohon Pucuk Merah 29.00 Pohon 112,200.00 3,253,800.00
8 Aksessories Taman Bermain
- Jongkang-jongket 1.00 Unit 5,000,000.00 5,000,000.00
- Ayunan Difabel 1.00 Unit 5,000,000.00 5,000,000.00
- Mangkok Putar Difabel 1.00 Unit 4,200,000.00 4,200,000.00
- Besi Berayun 1.00 Unit 3,200,000.00 3,200,000.00
- Kursi Taman 4.00 Unit 1,100,000.00 4,400,000.00
9 Pekerjaan Gazebo
Foot Plat 50x50x25
- Cor Beton K-175 0.30 m3 1,353,533.39 406,060.02
- Pembesian 23.81 kg 21,376.78 508,938.26
- Bekisting 0.80 m2 254,161.50 203,329.20
Urugan Pasir 0.90 m3 205,332.50 184,799.25
Cor Lantai Rabat 0.90 m3 1,353,533.39 1,218,180.05
Sloof 15x30
- Cor Beton K-175 0.54 m3 1,353,533.39 730,908.03
- Pembesian 51.17 kg 21,376.78 1,093,870.95
- Bekisting 1.80 m2 254,161.50 457,490.70
Kolom 15x15
- Cor Beton K-175 0.22 m3 1,353,533.39 294,799.57
- Pembesian 35.94 kg 21,376.78 768,289.84
- Bekisting 1.72 m2 254,161.50 437,056.12
Balok 10x15
- Cor Beton K-175 0.18 m3 254,161.50 45,749.07
- Pembesian 41.66 kg 21,376.78 890,449.56
- Bekisting 3.60 m2 254,161.50 914,981.40
Kuda - kuda kayu 5/10 0.11 m3 6,532,161.00 749,892.08
Usuk 5/5 0.12 m3 6,532,161.00 790,391.48
Pas Atap MultiRoof 10.72 m2 154,393.25 1,655,095.64
Pas Nok MultiRoof 9.20 m' 114,897.65 1,057,058.38
ListPlank 2.40 m2 86,907.80 208,578.72
Pas Keramik 40x40 9.00 m2 725,395.00 6,528,555.00
Pengecatan Listplank & Konstruksi Kuda-kuda Kayu 9.29 m2 46,734.85 434,073.29
Pengecatan Kolom, Sloof & Balok 16.80 m2 49,161.35 825,910.68
13 Pekerjaan Pagar BRC
Foot Plat 40x40x20
- Cor Beton K-175 1.25 m3 1,353,533.39 1,689,209.67
- Pembesian 193.44 kg 21,376.78 4,135,123.36
- Bekisting 2.08 m2 254,161.50 528,655.92
Sloof 15x30
- Cor Beton K-175 4.02 m3 1,353,533.39 5,439,783.01
- Pembesian 333.26 kg 21,376.78 7,124,017.20
- Bekisting 3.99 m2 254,161.50 1,014,104.39
- Tiang BRC 2" 39.00 Btg 200,000.00 7,800,000.00
- Pagar BRC 120x240 38.00 Lbr 750,000.00 28,500,000.00
- Pintu Pagar Hollow 5.00 m' 1,500,000.00 7,500,000.00
HARGA SATUAN JUMLAH
No. URAIAN PEKERJAAN VOLUME SATUAN
( Rp.) ( Rp.)

Total II 178,730,996.60
A.2.3.1 HARGA SATUAN PEKERJAAN TANAH
A.2.3.1.1 Penggalian 1 m³ tanah biasa sedalam 1 m
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.750 110,000.00 82,500.00
2 Mandor L.04 OH 0.025 155,000.00 3,875.00
Jumlah Tenaga Kerja 86,375.00
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 86,375.00
E Overhead + Profit ( Contoh 15% ) 15% x D 12,956.25
F Harga Satuan Pekerjaan ( D + E ) 99,331.25

A.2.3.1.9 Pengurukan kembali 1 m³ galian tanah


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 110,000.00 55,000.00
2 Mandor L.04 OH 0.050 155,000.00 7,750.00
Jumlah Tenaga Kerja 62,750.00
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 62,750.00
E Overhead + Profit ( Contoh 15% ) 15% x D 9,412.50
F Harga Satuan Pekerjaan ( D + E ) 72,162.50

160
A.2.3.1.11 Pengurugan 1 m³ dengan tanah urug
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7

A Tenaga
1 Pekerja L.01 OH 0.300 110,000.00 33,000.00
2 Mandor L.04 OH 0.010 155,000.00 1,550.00
Jumlah Tenaga Kerja 34,550.00
B Bahan
1 Tanah Urug m³ 1.200 85,600.00 102,720.00
Jumlah Harga Bahan 102,720.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 137,270.00
E Overhead + Profit ( Contoh 15% ) 15% x D 20,590.50
F Harga Satuan Pekerjaan ( D + E ) 157,860.50

A.2.3.1.12 Pengurugan 1 m³ dengan pasir urug


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7

A Tenaga
1 Pekerja L.01 OH 0.300 110,000.00 33,000.00
2 Mandor L.04 OH 0.010 155,000.00 1,550.00
Jumlah Tenaga Kerja 34,550.00
B Bahan
1 Pasir Urug m³ 1.200 120,000.00 144,000.00
Jumlah Harga Bahan 144,000.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 178,550.00
E Overhead + Profit ( Contoh 15% ) 15% x D 26,782.50
F Harga Satuan Pekerjaan ( D + E ) 205,332.50

A.3.2.1.1 Pemasangan 1 m2 Paving blok


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.200 110,000.00 22,000.00
2 Tukang Batu L.02 OH 0.300 134,000.00 40,200.00
3 Kepala Tukang L.03 OH 0.030 140,000.00 4,200.00
4 Mandor L.04 OH 0.025 155,000.00 3,875.00
Jumlah Tenaga Kerja 70,275.00
B Bahan
1 Paving m2 1.000 132,000.00 132,000.00
2 Pasir Pasang m³ 0.100 160,000.00 16,000.00
Jumlah Harga Bahan 148,000.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 218,275.00
E Overhead + Profit ( Contoh 15% ) 15% x D 32,741.25

161
F Harga Satuan Pekerjaan ( D + E ) 251,016.25

162
A.3.2.1.2 Pemasangan 1 m' Kanstin uk. 15/20 30x50
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 110,000.00 55,000.00
2 Tukang Batu L.02 OH 0.050 134,000.00 6,700.00
3 Kepala Tukang L.03 OH 0.010 140,000.00 1,400.00
4 Mandor L.04 OH 0.001 155,000.00 155.00
Jumlah Tenaga Kerja 63,255.00
B Bahan
1 Semen (PC) zak 0.360 65,000.00 23,400.00
2 Pasir Pasang m2 0.001 160,000.00 160.00
3 Kanstin uk. 15/20 30x50 bh 2.000 51,666.67 103,333.33
Jumlah Harga Bahan 126,893.33
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 190,148.33
E Overhead + Profit ( Contoh 15% ) 15% x D 28,522.25
F Harga Satuan Pekerjaan ( D + E ) 218,670.58

A.4.1.1. HARGA SATUAN PEKERJAAN BETON


A.4.1.1.5. Membuat 1 m³ beton mutu f 'c = 14,5 Mpa ( K - 175 ), Slump ( 12 ± 2 ) cm, w/c = 0.66
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.650 110,000.00 181,500.00
2 Tukang Batu L.02 OH 0.275 134,000.00 36,850.00
3 Kepala Tukang L.03 OH 0.028 140,000.00 3,920.00
4 Mandor L.04 OH 0.083 155,000.00 12,865.00
Jumlah Tenaga Kerja 235,135.00
B Bahan
1 Semen Portland Kg 326.000 1,300.00 423,800.00
2 Pasir Beton Kg 760.000 100.00 76,000.00
3 Kerikil ( Maks 30mm ) Kg 1,029.000 418.52 430,655.56
4 Air Liter 215.000 53.00 11,395.00
Jumlah Harga Bahan 941,850.56
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,176,985.56
E Overhead + Profit ( Contoh 15% ) 15% x D 176,547.83
F Harga Satuan Pekerjaan ( D + E ) 1,353,533.39

163
A.4.1.1.7. Membuat 1 m³ beton mutu f 'c = 19,3 Mpa ( K - 225 ), Slump ( 12 ± 2 ) cm, w/c = 0.58
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.650 110,000.00 181,500.00
2 Tukang Batu L.02 OH 0.275 134,000.00 36,850.00
3 Kepala Tukang L.03 OH 0.028 140,000.00 3,920.00
4 Mandor L.04 OH 0.083 155,000.00 12,865.00
Jumlah Tenaga Kerja 235,135.00
B Bahan
1 Semen Portland Kg 371.000 1,300.00 482,300.00
2 Pasir Beton Kg 698.000 100.00 69,800.00
3 Kerikil ( Maks 30mm ) Kg 1,047.000 418.52 438,188.89
4 Air Liter 215.000 53.00 11,395.00
Jumlah Harga Bahan 1,001,683.89
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,236,818.89
E Overhead + Profit ( Contoh 15% ) 15% x D 185,522.83
F Harga Satuan Pekerjaan ( D + E ) 1,422,341.72

A.4.1.1.17. Pembesian 10 Kg dengan besi polos


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.070 110,000.00 7,700.00
2 Tukang Besi L.02 OH 0.070 134,000.00 9,380.00
3 Kepala Tukang L.03 OH 0.007 140,000.00 980.00
4 Mandor L.04 OH 0.004 155,000.00 620.00
Jumlah Tenaga Kerja 18,680.00
B Bahan
1 Besi Beton Polos Kg 10.500 15,600.00 163,800.00
2 Kawat Beton Kg 0.150 22,700.00 3,405.00
Jumlah Harga Bahan 167,205.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 185,885.00
E Overhead + Profit ( Contoh 15% ) 15% x D 27,882.75
F Harga Satuan Pekerjaan ( D + E ) 213,767.75
Harga Satuan Pekerjaan /1 kg besi F/10 21,376.78

164
A.4.1.1.21. Pemasangan 1 m² bekisting untuk sloof
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.520 110,000.00 57,200.00
2 Tukang Kayu L.02 OH 0.260 134,000.00 34,840.00
3 Kepala Tukang L.03 OH 0.026 140,000.00 3,640.00
4 Mandor L.04 OH 0.026 155,000.00 4,030.00
Jumlah Tenaga Kerja 99,710.00
B Bahan
1 Kayu Kelas III m³ 0.045 2,522,000.00 113,490.00
2 Paku 5 - 10 cm Kg 0.300 22,400.00 6,720.00
3 Minyak Bekisting Liter 0.100 10,900.00 1,090.00
Jumlah Harga Bahan 121,300.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 221,010.00
E Overhead + Profit ( Contoh 15% ) 15% x D 33,151.50
F Harga Satuan Pekerjaan ( D + E ) 254,161.50

A.4.2.1. HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM


A.4.2.1.21. Pemasangan 1 m² rangka besi holow 1 x 50 x 50 x 2 mm,
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.350 110,000.00 38,500.00
2 Tukang Besi L.02 OH 0.350 134,000.00 46,900.00
3 Kepala Tukang L.03 OH 0.0350 140,000.00 4,900.00
4 Mandor L.04 OH 0.0180 155,000.00 2,790.00
Jumlah Tenaga Kerja 93,090.00
B Bahan
1 Rangka Metal Hollow 50.50.2
m¹ 4.000 51,666.67 206,666.67
mm
2 Assesoris ( Perkuatan, Las dll 100% x
Ls 51,666.67 51,666.67
) Rangka
Jumlah Harga Bahan 258,333.33
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 351,423.33
E Overhead + Profit ( Contoh 15% ) 15% x D 52,713.50
F Harga Satuan Pekerjaan ( D + E ) 404,136.83

165
A.4.4.1. HARGA SATUAN PEKERJAAN PASANGAN DINDING
A.4.4.1.3. Pemasangan 1 m² dinding bata merah ( 9 x 9 x 18 ) cm tebal 1 batu campuran 1 SP : 4 PP
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 110,000.00 55,000.00
2 Tukang Batu L.02 OH 0.200 134,000.00 26,800.00
3 Kepala Tukang L.03 OH 0.020 140,000.00 2,800.00
4 Mandor L.04 OH 0.025 155,000.00 3,875.00
Jumlah Tenaga Kerja 88,475.00
B Bahan
1 Bata Merah m2 110.000 120,000.00 13,200,000.00
2 Semen Portland Kg 20.861 1,300.00 27,118.93
3 Pasir Pasang m³ 0.073 160,000.00 11,691.43
Jumlah Harga Bahan 13,238,810.36
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 13,327,285.36
E Overhead + Profit ( Contoh 15% ) 15% x D 1,999,092.80
F Harga Satuan Pekerjaan ( D + E ) 15,326,378.16

A.4.4.1.3. Pemasangan 1 m² dinding bata merah ( 9 x 9 x 18 ) cm tebal 1 batu campuran 1 SP : 4 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 110,000.00 55,000.00
2 Tukang Batu L.02 OH 0.200 134,000.00 26,800.00
3 Kepala Tukang L.03 OH 0.020 140,000.00 2,800.00
4 Mandor L.04 OH 0.025 155,000.00 3,875.00
Jumlah Tenaga Kerja 88,475.00
B Bahan
1 Bata Merah m2 55.000 120,000.00 6,600,000.00
2 Semen Portland Kg 20.861 1,300.00 27,118.93
3 Pasir Pasang m³ 0.073 160,000.00 11,691.43
Jumlah Harga Bahan 6,638,810.36
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 6,727,285.36
E Overhead + Profit ( Contoh 15% ) 15% x D 1,009,092.80
F Harga Satuan Pekerjaan ( D + E ) 7,736,378.16

166
A.4.4.2. HARGA SATUAN PEKERJAAN PLESTERAN
A.4.4.2.4. Pemasangan 1 m² plesteran 1 SP : 4 PP tebal 15 mm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 110,000.00 33,000.00
2 Tukang Batu L.02 OH 0.150 134,000.00 20,100.00
3 Kepala Tukang L.03 OH 0.015 140,000.00 2,100.00
4 Mandor L.04 OH 0.015 155,000.00 2,325.00
Jumlah Tenaga Kerja 57,525.00
B Bahan
1 Semen Portland Kg 6.240 1,300.00 8,112.00
2 Pasir Pasang m³ 0.024 160,000.00 3,840.00
Jumlah Harga Bahan 11,952.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 69,477.00
E Overhead + Profit ( Contoh 15% ) 15% x D 10,421.55
F Harga Satuan Pekerjaan ( D + E ) 79,898.55

HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN


A.4.4.3.
DINDING
A.4.4.3.35. Pemasangan 1 m² lantai keramik ukuran 40c m x 40 cm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.700 110,000.00 77,000.00
2 Tukang Batu L.02 OH 0.350 134,000.00 46,900.00
3 Kepala Tukang L.03 OH 0.035 140,000.00 4,900.00
4 Mandor L.04 OH 0.035 155,000.00 5,425.00
Jumlah Tenaga Kerja 134,225.00
B Bahan
1 Ubin Keramik Bh 6.875 73,000.00 501,875.00
2 Semen Portland Kg 10.000 1,300.00 13,000.00
3 Pasir Pasang m³ 0.045 160,000.00 7,200.00
4 Semen Warna Kg 1.500 2,100.00 3,150.00
Jumlah Harga Bahan 525,225.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 659,450.00
E Overhead + Profit ( Contoh 10% ) 10% x D 65,945.00
F Harga Satuan Pekerjaan ( D + E ) 725,395.00

167
A.4.5.2. HARGA SATUAN PEKERJAAN PENUTUP ATAP
A.4.5.2.40. Pemasangan 1 m² atap metalroof
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.200 110,000.00 22,000.00
2 Tukang Kayu L.02 OH 0.100 134,000.00 13,400.00
3 Kepala Tukang L.03 OH 0.0100 140,000.00 1,400.00
4 Mandor L.04 OH 0.001 155,000.00 155.00
Jumlah Tenaga Kerja 36,955.00
B Bahan
1 Genteng Metal Lembar 1.020 91,000.00 92,820.00
2 Paku Biasa 2" - 5" Kg 0.200 22,400.00 4,480.00
Jumlah Harga Bahan 97,300.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 134,255.00
E Overhead + Profit ( Contoh 15% ) 15% x D 20,138.25
F Harga Satuan Pekerjaan ( D + E ) 154,393.25

A.4.5.2.41. Pemasangan 1 m¹ nok atap Metal roof


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.250 110,000.00 27,500.00
2 Tukang Kayu L.02 OH 0.150 134,000.00 20,100.00
3 Kepala Tukang L.03 OH 0.0150 140,000.00 2,100.00
4 Mandor L.04 OH 0.013 155,000.00 2,015.00
Jumlah Tenaga Kerja 51,715.00
B Bahan
1 Nok Buah 1.100 43,000.00 47,300.00
2 Paku Hak Panjang 15 cm Kg 0.040 22,400.00 896.00
Jumlah Harga Bahan 48,196.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 99,911.00
E Overhead + Profit ( Contoh 15% ) 15% x D 14,986.65
F Harga Satuan Pekerjaan ( D + E ) 114,897.65

168
A.4.6.1. HARGA SATUAN PEKERJAAN KAYU
A.4.6.1.13. Pemasangan 1 m³ konstruksi kuda-kuda konvensional, kayu kelas I, II dan III
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 4.000 110,000.00 440,000.00
2 Tukang Kayu L.02 OH 12.000 134,000.00 1,608,000.00
3 Kepala Tukang L.03 OH 1.2000 140,000.00 168,000.00
4 Mandor L.04 OH 0.200 155,000.00 31,000.00
Jumlah Tenaga Kerja 2,247,000.00
B Bahan
1 Balok Kayu m³ 1.1000 3,007,000.00 3,307,700.00
2 Besi Strip Tebal 5 mm Kg 15.000 -
3 Paku 12 cm Kg 5.600 22,400.00 125,440.00
Jumlah Harga Bahan 3,433,140.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 5,680,140.00
E Overhead + Profit ( Contoh 15% ) 15% x D 852,021.00
F Harga Satuan Pekerjaan ( D + E ) 6,532,161.00

A.4.6.1.19. Pemasangan 1 m² rangka langit-langit ( 50 x 100 ) cm, kayu kelas II atau III
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.150 110,000.00 16,500.00
2 Tukang Kayu L.02 OH 0.300 134,000.00 40,200.00
3 Kepala Tukang L.03 OH 0.0300 140,000.00 4,200.00
4 Mandor L.04 OH 0.075 155,000.00 11,625.00
Jumlah Tenaga Kerja 72,525.00
B Bahan
1 Kaso-kaso 5 x 7 cm m³ 0.0154 3,007,000.00 46,307.80
2 Paku 7 cm - 10 cm Kg 0.200 22,400.00 4,480.00
Jumlah Harga Bahan 50,787.80
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 123,312.80
E Overhead + Profit ( Contoh 15% ) 15% x D 18,496.92
F Harga Satuan Pekerjaan ( D + E ) 141,809.72

169
A.4.6.1.22. Pemasangan 1 m¹ listplank ukuran ( 3 x 30 ) cm, kayu kelas I atau kelas II
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.100 110,000.00 11,000.00
2 Tukang Kayu L.02 OH 0.200 134,000.00 26,800.00
3 Kepala Tukang L.03 OH 0.0200 140,000.00 2,800.00
4 Mandor L.04 OH 0.005 155,000.00 775.00
Jumlah Tenaga Kerja 41,375.00
B Bahan
1 Papan Kayu m³ 0.0110 3,007,000.00 33,077.00
2 Paku 5 cm dan 7 cm Kg 0.050 22,400.00 1,120.00
Jumlah Harga Bahan 34,197.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 75,572.00
E Overhead + Profit ( Contoh 15% ) 15% x D 11,335.80
F Harga Satuan Pekerjaan ( D + E ) 86,907.80

A.4.7.1. HARGA SATUAN PEKERJAAN PENGECATAN


A.4.7.1.4. 1 m² pengecatan bidang kayu baru ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.070 110,000.00 7,700.00
2 Tukang Cat L.02 OH 0.009 134,000.00 1,206.00
3 Kepala Tukang L.03 OH 0.006 140,000.00 840.00
4 Mandor L.04 OH 0.003 155,000.00 465.00
Jumlah Tenaga Kerja 10,211.00
B Bahan
1 Cat Menie Kg 0.200 31,000.00 6,200.00
2 Plamir Kg 0.150 -
3 Cat Dasar Kg 0.170 51,800.00 8,806.00
4 Cat Penutup Kg 0.260 51,800.00 13,468.00
5 Kuas Buah 0.010 18,000.00 180.00
6 Pengencer Kg 0.030 25,800.00 774.00
7 Ampelas Lembar 0.200 5,000.00 1,000.00
Jumlah Harga Bahan 30,428.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 40,639.00
E Overhead + Profit ( Contoh 15% ) 15% x D 6,095.85
F Harga Satuan Pekerjaan ( D + E ) 46,734.85

A.4.7.1.10. Pengecataan 1 m² tembok baru ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga

170
1 Pekerja L.01 OH 0.020 110,000.00 2,200.00
2 Tukang Cat L.02 OH 0.063 134,000.00 8,442.00
3 Kepala Tukang L.03 OH 0.0063 140,000.00 882.00
4 Mandor L.04 OH 0.003 155,000.00 465.00
Jumlah Tenaga Kerja 11,989.00
B Bahan
1 Plamir Kg 0.100 8,800.00 880.00
2 Cat Dasar Kg 0.100 83,000.00 8,300.00
3 Cat Penutup Kg 0.260 83,000.00 21,580.00
Jumlah Harga Bahan 30,760.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 42,749.00
E Overhead + Profit ( Contoh 15% ) 15% x D 6,412.35
F Harga Satuan Pekerjaan ( D + E ) 49,161.35

171
CV. BLUE Print Consultant
Planning, Supervision & Engineering Consultant
Office: Jl. Yos Sudarso RT. 002 Sebengkok Tarakan
e-mail : blueprintconsultant@yahoo.com

DAFTAR HARGA SATUAN


PAKET KEGIATAN :
PEMBUATAN TAMAN KELURAHAN PAMUSIAN

LOKASI : TARAKAN
TAHUN : 2020

No. URAIAN BAHAN SATUAN HARGA SATUAN KETERANGAN

(1) (2) (3) (4) (5)

I UPAH (standar harga kota Tarakan)

1 Pekerja Hari Rp. 110,000.00


2 Tukang Hari Rp. 134,000.00
3 Mandor Hari Rp. 155,000.00
4 Kepala Tukang Hari Rp. 140,000.00

II BAHAN

1 Agregat Kasar/batu pecah M3 Rp. 565,000 418.52 Kg


2 Semen (50kg) Zak Rp. 65,000 1,300.00 / kg setara tonasa
3 Semen Warna Kg Rp. 2,100 / kg
4 Besi beton polos Kg Rp. 15,600
5 Kawat Ikat / Kg Rp. 22,700
6 Plywood 4 mm / Lbr Rp. 83,000
7 Keramik 40x40 / Kotak Rp. 73,000
8 Paku Biasa / Kg Rp. 22,400
9 Tear Oil / Kg Rp. 35,300
10 Minyak Begesting Ltr Rp. 10,900
11 Batu Pecah / M3 Rp. 565,000 389.66 /kg
12 Pasir Pasangan / M3 Rp. 160,000 100.00 /kg
13 Tanah Urug / M3 Rp. 85,600
14 Pasir Urug / M3 Rp. 120,000
15 Paving Blok ( t = 8 cm ) / Bh Rp. 3,000
16 Air Bersih Ltr Rp. 53
17 Kayu Perancah / M3 Rp. 2,522,000
18 Kayu Meranti / M3 Rp. 2,522,000
19 Kayu Kapur / Bengkirai / Lembasung / M3 Rp. 3,007,000
20 Hollow 50x50x2 /m Rp. 51,667
21 Atap Multi Roof / Lbr Rp. 91,000
22 Nok Multi Roof /m Rp. 43,000
23 Pohon Palem Ekor Tupai / Pokok Rp. 525,000
24 Rumput Gajah Mini / M2 Rp. 61,500
25 Pohon Pucuk Merah / Pokok Rp. 112,200
26 BRC 120x240 / Lbr Rp. 750,000
27 Tiang BRC Galvanis / Btg Rp. 200,000
28 Cat Menie / Kg Rp. 31,000
29 Plamir / Kg Rp. 8,800
30 Cat Minyak / Kg Rp. 51,800
31 Cat Air / Kg Rp. 83,000
32 Kuas / Bh Rp. 18,000
33 Pengencer / Kg Rp. 25,800
34 Ampelas / Lbr Rp. 5,000
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : PEMBUATAN TAMAN JUATA KERIKIL
PROP / KAB / KODYA : Kalimanta Utara / Kota Tarakan
JENIS PEKERJAAN Penyelenggaraan Sistem Manajemen Keselamatan Konstruksi (SMKK)
SATUAN PEMBAYARAN : Ls

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp.)
1 2 3 4 5 6 7
A SOSIALISASI
1 Spanduk K3 Lb 1.00 150,000.00 150,000.00
2 Pengarahan K3 (Safety Briefing) Org 1.00 15,000.00 15,000.00
Jumlah B 165,000.00
B APD Dan APK
1 Helm Pelindung (Safety Helmet) Buah 5.00 81,439.00 407,195.00
2 Sarung Tangan (Safety Gloves) Psg 15.00 20,000.00 300,000.00
4 Sepatu Keselamatan (Rubber Safety Shoes) Psg 5.00 100,000.00 500,000.00
5 Rompi Keselamatan (Safety Vest) Buah 5.00 25,000.00 125,000.00
Jumlah C 1,332,195.00
C ASURANSI
1 Asuransi Ls 1.00 190,000.00 190,000.00
Jumlah D 190,000.00
D RAMBU-RAMBU
1 Rambu Peringatan Buah 1.00 75,000.00 75,000.00
2 Rambu Informasi Buah 1.00 75,000.00 75,000.00
Jumlah G 150,000.00
Jumlah A s/d H 1,837,195.00
A.2.3.1 HARGA SATUAN PEKERJAAN TANAH
A.2.3.1.1 Penggalian 1 m³ tanah biasa sedalam 1 m
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.750 #REF! #REF!
2 Mandor L.04 OH 0.025 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.2.3.1.9 Pengurukan kembali 1 m³ galian tanah


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 #REF! #REF!
2 Mandor L.04 OH 0.050 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

175
A.2.3.1.11 Pengurugan 1 m³ dengan pasir urug
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7

A Tenaga
1 Pekerja L.01 OH 0.300 #REF! #REF!
2 Mandor L.04 OH 0.010 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Pasir Urug m³ 1.200 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.3.2.1.1 Pemasangan 1 m2 Paving blok


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.200 #REF! #REF!
2 Tukang Batu L.02 OH 0.300 #REF! #REF!
3 Kepala Tukang L.03 OH 0.030 #REF! #REF!
4 Mandor L.04 OH 0.025 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Paving m2 1.000 #REF! #REF!
2 Pasir Pasang m³ 0.100 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

176
A.3.2.1.2 Pemasangan 1 m' Kanstin uk. 15/20 30x50
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 #REF! #REF!
2 Tukang Batu L.02 OH 0.050 #REF! #REF!
3 Kepala Tukang L.03 OH 0.010 #REF! #REF!
4 Mandor L.04 OH 0.001 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Semen (PC) zak 0.360 100,000.00 36,000.00
2 Pasir Pasang m2 0.001 #REF! #REF!
3 Kanstin uk. 15/20 30x50 bh 2.000 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.4.1.1. HARGA SATUAN PEKERJAAN BETON


A.4.1.1.5. Membuat 1 m³ beton mutu f 'c = 14,5 Mpa ( K - 175 ), Slump ( 12 ± 2 ) cm, w/c = 0.66
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.650 #REF! #REF!
2 Tukang Batu L.02 OH 0.275 #REF! #REF!
3 Kepala Tukang L.03 OH 0.028 #REF! #REF!
4 Mandor L.04 OH 0.083 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Semen Portland Kg 326.000 #REF! #REF!
2 Pasir Beton Kg 760.000 #REF! #REF!
3 Kerikil ( Maks 30mm ) Kg 1,029.000 #REF! #REF!
4 Air Liter 215.000 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

177
A.4.1.1.7. Membuat 1 m³ beton mutu f 'c = 19,3 Mpa ( K - 225 ), Slump ( 12 ± 2 ) cm, w/c = 0.58
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.650 #REF! #REF!
2 Tukang Batu L.02 OH 0.275 #REF! #REF!
3 Kepala Tukang L.03 OH 0.028 #REF! #REF!
4 Mandor L.04 OH 0.083 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Semen Portland Kg 371.000 #REF! #REF!
2 Pasir Beton Kg 698.000 #REF! #REF!
3 Kerikil ( Maks 30mm ) Kg 1,047.000 #REF! #REF!
4 Air Liter 215.000 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.4.1.1.17. Pembesian 10 Kg dengan besi polos


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.070 #REF! #REF!
2 Tukang Besi L.02 OH 0.070 #REF! #REF!
3 Kepala Tukang L.03 OH 0.007 #REF! #REF!
4 Mandor L.04 OH 0.004 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Besi Beton Polos Kg 10.500 #REF! #REF!
2 Kawat Beton Kg 0.150 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!
Harga Satuan Pekerjaan /1 kg besi F/10 #REF!

178
A.4.1.1.21. Pemasangan 1 m² bekisting untuk sloof
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.520 #REF! #REF!
2 Tukang Kayu L.02 OH 0.260 #REF! #REF!
3 Kepala Tukang L.03 OH 0.026 #REF! #REF!
4 Mandor L.04 OH 0.026 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Kayu Kelas III m³ 0.045 #REF! #REF!
2 Paku 5 - 10 cm Kg 0.300 #REF! #REF!
3 Minyak Bekisting Liter 0.100 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.4.2.1. HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM


A.4.2.1.21. Pemasangan 1 m² rangka besi holow 1 x 50 x 50 x 2 mm,
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.350 #REF! #REF!
2 Tukang Besi L.02 OH 0.350 #REF! #REF!
3 Kepala Tukang L.03 OH 0.0350 #REF! #REF!
4 Mandor L.04 OH 0.0180 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Rangka Metal Hollow 50.50.2
m¹ 4.000 #REF! #REF!
mm
2 Assesoris ( Perkuatan, Las dll 100% x
Ls #REF! #REF!
) Rangka
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

179
A.4.4.1. HARGA SATUAN PEKERJAAN PASANGAN DINDING
A.4.4.1.3. Pemasangan 1 m² dinding bata merah ( 9 x 9 x 18 ) cm tebal 1 batu campuran 1 SP : 4 PP
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 #REF! #REF!
2 Tukang Batu L.02 OH 0.200 #REF! #REF!
3 Kepala Tukang L.03 OH 0.020 #REF! #REF!
4 Mandor L.04 OH 0.025 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Bata Merah m2 110.000 #REF! #REF!
2 Semen Portland Kg 20.861 #REF! #REF!
3 Pasir Pasang m³ 0.073 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.4.4.1.3. Pemasangan 1 m² dinding bata merah ( 9 x 9 x 18 ) cm tebal 1 batu campuran 1 SP : 4 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 #REF! #REF!
2 Tukang Batu L.02 OH 0.200 #REF! #REF!
3 Kepala Tukang L.03 OH 0.020 #REF! #REF!
4 Mandor L.04 OH 0.025 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Bata Merah m2 55.000 #REF! #REF!
2 Semen Portland Kg 20.861 #REF! #REF!
3 Pasir Pasang m³ 0.073 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

180
A.4.4.2. HARGA SATUAN PEKERJAAN PLESTERAN
A.4.4.2.4. Pemasangan 1 m² plesteran 1 SP : 4 PP tebal 15 mm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 #REF! #REF!
2 Tukang Batu L.02 OH 0.150 #REF! #REF!
3 Kepala Tukang L.03 OH 0.015 #REF! #REF!
4 Mandor L.04 OH 0.015 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Semen Portland Kg 6.240 #REF! #REF!
2 Pasir Pasang m³ 0.024 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN


A.4.4.3.
DINDING
A.4.4.3.35. Pemasangan 1 m² lantai keramik ukuran 40c m x 40 cm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.700 #REF! #REF!
2 Tukang Batu L.02 OH 0.350 #REF! #REF!
3 Kepala Tukang L.03 OH 0.035 #REF! #REF!
4 Mandor L.04 OH 0.035 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Ubin Keramik Bh 6.875 #REF! #REF!
2 Semen Portland Kg 10.000 #REF! #REF!
3 Pasir Pasang m³ 0.045 #REF! #REF!
4 Semen Warna Kg 1.500 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 10% ) 10% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.4.4.3.36. Pemasangan 1 m² lantai keramik ukuran 20 cm x 20 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )

181
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.700 #REF! #REF!
2 Tukang Batu L.02 OH 0.350 #REF! #REF!
3 Kepala Tukang L.03 OH 0.035 #REF! #REF!
4 Mandor L.04 OH 0.035 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Ubin Keramik Bh 26.500 -
2 Semen Portland Kg 10.400 #REF! #REF!
3 Pasir Pasang m³ 0.045 #REF! #REF!
4 Semen Warna Kg 1.620 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

HARGA SATUAN PEKERJAAN LANGIT-LANGIT


A.4.5.1.
(PLAFOND)
A.4.5.1.7. Pemasangan 1 m² langit-langit gypsum board ukuran ( 120 x 240 x 9 ) mm, tebal 9 mm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.100 #REF! #REF!
2 Tukang Kayu L.02 OH 0.050 #REF! #REF!
3 Kepala Tukang L.03 OH 0.005 #REF! #REF!
4 Mandor L.04 OH 0.005 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Gypsum Board Lembar 0.364 #REF! #REF!
2 Paku Skrup Kg 0.110 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.4.5.1.9. Pemasangan 1 m¹ list langit-langit gypsum


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.050 #REF! #REF!
2 Tukang Kayu L.02 OH 0.050 #REF! #REF!
3 Kepala Tukang L.03 OH 0.005 #REF! #REF!
4 Mandor L.04 OH 0.003 #REF! #REF!

182
Jumlah Tenaga Kerja #REF!
B Bahan
1 List Gypsum m 1.050 #REF! #REF!
2 Tepung gypsum Kg 0.150 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

183
A.4.5.2. HARGA SATUAN PEKERJAAN PENUTUP ATAP
A.4.5.2.38. Pemasangan 1 m² atap seng gelombang
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.120 #REF! #REF!
2 Tukang Kayu L.02 OH 0.060 #REF! #REF!
3 Kepala Tukang L.03 OH 0.0060 #REF! #REF!
4 Mandor L.04 OH 0.006 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Seng Gelombang 3" x 6" Lembar 0.700 #REF! #REF!
2 Paku Seng Kg 0.020 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.4.5.2.39. Pemasangan 1 m¹ nok atap seng


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.150 #REF! #REF!
2 Tukang Kayu L.02 OH 0.070 #REF! #REF!
3 Kepala Tukang L.03 OH 0.0070 #REF! #REF!
4 Mandor L.04 OH 0.006 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Seng Plat 3" x 6" BJLS 28 Lembar 0.300 #REF! #REF!
2 Paku Seng Kg 0.040 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

184
A.4.6.1. HARGA SATUAN PEKERJAAN KAYU
A.4.6.1.13. Pemasangan 1 m³ konstruksi kuda-kuda konvensional, kayu kelas I, II dan III
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 4.000 #REF! #REF!
2 Tukang Kayu L.02 OH 12.000 #REF! #REF!
3 Kepala Tukang L.03 OH 1.2000 #REF! #REF!
4 Mandor L.04 OH 0.200 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Balok Kayu m³ 1.1000 #REF! #REF!
2 Besi Strip Tebal 5 mm Kg 15.000 -
3 Paku 12 cm Kg 5.600 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.4.6.1.20. Pemasangan 1 m² rangka langit-langit ( 60 x 60 ) cm, kayu kelas II atau III


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.200 #REF! #REF!
2 Tukang Kayu L.02 OH 0.300 #REF! #REF!
3 Kepala Tukang L.03 OH 0.0300 #REF! #REF!
4 Mandor L.04 OH 0.010 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Kaso-kaso m³ 0.0163 #REF! #REF!
2 Paku 7 cm - 10 cm Kg 0.250 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.4.6.1.22. Pemasangan 1 m¹ listplank ukuran ( 3 x 30 ) cm, kayu kelas I atau kelas II


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.100 #REF! #REF!
2 Tukang Kayu L.02 OH 0.200 #REF! #REF!
3 Kepala Tukang L.03 OH 0.0200 #REF! #REF!

185
4 Mandor L.04 OH 0.005 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Papan Kayu m³ 0.0110 #REF! #REF!
2 Paku 5 cm dan 7 cm Kg 0.050 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.4.6.2. HARGA SATUAN PEKERJAAN KUNCI DAN KACA


A.4.6.2.2. Pemasangan 1 buah kunci tanam
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.010 #REF! #REF!
2 Tukang Kayu L.02 OH 0.500 #REF! #REF!
3 Kepala Tukang L.03 OH 0.0500 #REF! #REF!
4 Mandor L.04 OH 0.005 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Kunci Tanam Biasa Buah 1.000 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.4.6.2.2. Pemasangan 1 pasang handle pintu


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.010 #REF! #REF!
2 Tukang Kayu L.02 OH 0.500 #REF! #REF!
3 Kepala Tukang L.03 OH 0.0500 #REF! #REF!
4 Mandor L.04 OH 0.005 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Handle pintu Buah 1.000 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

186
A.4.6.2.5. Pemasangan 1 buah engsel pintu
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.015 #REF! #REF!
2 Tukang Kayu L.02 OH 0.150 #REF! #REF!
3 Kepala Tukang L.03 OH 0.0150 #REF! #REF!
4 Mandor L.04 OH 0.0008 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Engsel Pintu Buah 1.000 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.010 #REF! #REF!
2 Tukang Kayu L.02 OH 0.100 #REF! #REF!
3 Kepala Tukang L.03 OH 0.0100 #REF! #REF!
4 Mandor L.04 OH 0.0005 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Engsel Kupu-kupu Buah 1.000 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.4.6.2.9. Pemasangan 1 buah kait angin


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.015 #REF! #REF!
2 Tukang Kayu L.02 OH 0.150 #REF! #REF!
3 Kepala Tukang L.03 OH 0.0150 #REF! #REF!
4 Mandor L.04 OH 0.0080 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Kait Angin Buah 1.000 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan

187
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.4.6.2.9. Pemasangan 1 buah handle / grendle


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.015 #REF! #REF!
2 Tukang Kayu L.02 OH 0.150 #REF! #REF!
3 Kepala Tukang L.03 OH 0.0150 #REF! #REF!
4 Mandor L.04 OH 0.0080 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 handle Buah 1.000 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.4.6.2.16. Pemasangan 1 m² kaca tebal 3 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.015 #REF! #REF!
2 Tukang Kayu L.02 OH 0.150 #REF! #REF!
3 Kepala Tukang L.03 OH 0.0015 #REF! #REF!
4 Mandor L.04 OH 0.0008 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Kaca Tebal 3 mm m² 1.100 #REF! #REF!
2 Sealant Kg 0.050 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.4.7.1. HARGA SATUAN PEKERJAAN PENGECATAN


A.4.7.1.4. 1 m² pengecatan bidang kayu baru ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga

188
1 Pekerja L.01 OH 0.070 #REF! #REF!
2 Tukang Cat L.02 OH 0.009 #REF! #REF!
3 Kepala Tukang L.03 OH 0.006 #REF! #REF!
4 Mandor L.04 OH 0.003 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Cat Menie Kg 0.200 #REF! #REF!
2 Plamir Kg 0.150 #REF! #REF!
3 Cat Dasar Kg 0.170 #REF! #REF!
4 Cat Penutup Kg 0.260 #REF! #REF!
5 Kuas Buah 0.010 #REF! #REF!
6 Pengencer Kg 0.030 #REF! #REF!
7 Ampelas Lembar 0.200 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.4.7.1.10. Pengecataan 1 m² tembok baru ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.020 #REF! #REF!
2 Tukang Cat L.02 OH 0.063 #REF! #REF!
3 Kepala Tukang L.03 OH 0.0063 #REF! #REF!
4 Mandor L.04 OH 0.003 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Plamir Kg 0.100 #REF! #REF!
2 Cat Dasar Kg 0.100 #REF! #REF!
3 Cat Penutup Kg 0.260 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.5.1.1. HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG


A.5.1.1.2. Pemasangan 1 buah closet jongkok porslen
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.000 #REF! #REF!
2 Tukang Batu L.02 OH 1.500 #REF! #REF!
3 Kepala Tukang L.03 OH 0.150 #REF! #REF!

189
4 Mandor L.04 OH 0.160 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Closet Jongkok Unit 1.000 #REF! #REF!
2 Semen Portland Kg 6.000 #REF! #REF!
3 Pasir Pasang m³ 0.010 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.5.1.1.19. Pemasangan 1 buah kran air ؽ" atau ؾ"


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.010 #REF! #REF!
2 Tukang Batu L.02 OH 0.400 #REF! #REF!
3 Kepala Tukang L.03 OH 0.040 #REF! #REF!
4 Mandor L.04 OH 0.005 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Kran Air ؽ" atau ؾ m¹ 1.000 #REF! #REF!
2 Sealtape Buah 0.025 5,000.00 125.00
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.5.1.1.26. Pemasangan 1 m¹ PVC type AW ؾ"


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.036 #REF! #REF!
2 Tukang Batu L.02 OH 0.060 #REF! #REF!
3 Kepala Tukang L.03 OH 0.006 #REF! #REF!
4 Mandor L.04 OH 0.002 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Pipa PVC ؾ" m¹ 1.200 #REF! #REF!
2 Perlengkapan % 35.000 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 10% ) 10% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

190
A.5.1.1.32. Pemasangan 1 m¹ PVC type AW Ø4"
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.081 #REF! #REF!
2 Tukang Batu L.02 OH 0.135 #REF! #REF!
3 Kepala Tukang L.03 OH 0.0135 #REF! #REF!
4 Mandor L.04 OH 0.004 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Pipa PVC Ø4" m¹ 1.200 #REF! #REF!
2 Perlengkapan % 35.000 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 10% ) 10% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

(K3) Pemasangan 1 Buah Titik Lampu


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Upah L.01 % 100.000 #REF! #REF!
Jumlah Tenaga Kerja #REF!
B Bahan
1 Pipa listrik dia 5/8" btg 3.000 15,000.00 45,000.00
2 Kabel m¹ 24.000 5,000.00 120,000.00
3 T dus bh 3.000 2,000.00 6,000.00
4 L bow bh 4.000 2,000.00 8,000.00
5 Las Dop bh 3.000 2,000.00 6,000.00
6 Klem bh 24.000 2,000.00 48,000.00
7 Mangkok bh 1.000 2,000.00 2,000.00
8 Saklar bh 1.000 15,000.00 15,000.00
9 Fitting bh 1.000 2,000.00 2,000.00
Jumlah Harga Bahan 165,000.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 10% ) 10% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

191
A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN
A.2.2.1.9 Pembersihan 1 m² lapangan dan perataan
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.100 111,700.00 11,170.00
2 Mandor L.04 OH 0.050 160,090.00 8,004.50
Jumlah Tenaga Kerja 19,174.50
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 19,174.50
E Overhead + Profit ( Contoh 15% ) 15% x D 2,876.18
F Harga Satuan Pekerjaan ( D + E ) 22,050.68
A.2.2.1.9 1 M2 Pagar Sementara dari seng gelombang tinggi 2 M
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.200 111,700.00 22,340.00
2 Tukang OH 0.400 135,070.00 54,028.00
3 Kepala tukang OH 0.020 140,740.00 2,814.80
2 Mandor L.04 OH 0.020 160,090.00 3,201.80
Jumlah Tenaga Kerja 82,384.60
B Bahan
Dolken dia 10 cm Batang - 35,000.00 -
Kayu Balok 5/7 Kelas III m³ 0.072 2,522,000.00 181,584.00
Semen Kg - 2,000.00 -
Seng Gelombang Lbr 1.200 -
Pasir beton M3 - 187,900.00 -
Koral Beton M3 - 573,600.00 -
Meni besi Liter - 33,600.00 -
Paku Biasa Kg 0.020 159,900.00 3,198.00
Jumlah Harga Bahan 184,782.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 267,166.60
E Overhead + Profit ( Contoh 15% ) 15% x D 40,074.99
F Harga Satuan Pekerjaan ( D + E ) 307,241.59

192
A.2.2.1.9 1 M' Pengukuran dan pemasangan bowplank
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.100 111,700.00 11,170.00
2 Tukang OH 0.100 135,070.00 13,507.00
3 Kepala tukang OH 0.010 140,740.00 1,407.40
2 Mandor L.04 OH 0.050 160,090.00 8,004.50
Jumlah Tenaga Kerja 34,088.90
B Bahan
Kayu papan kelas III m³ 0.007 2,522,000.00 17,654.00
Kayu Balok 5/7 Kelas III m³ 0.012 2,522,000.00 30,264.00
Paku Biasa Kg 0.020 22,400.00 448.00
Jumlah Harga Bahan 48,366.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 82,454.90
E Overhead + Profit ( Contoh 15% ) 15% x D 12,368.24
F Harga Satuan Pekerjaan ( D + E ) 94,823.14

A.2.2.1.11 Pembuatan 1 buah kotak adukan ukuran 40 cm x 50 cm x 25 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Tukang Kayu L.02 OH 0.300 135,070.00 40,521.00
2 Kepala Tukang L.03 OH 0.030 140,740.00 4,222.20
Jumlah Tenaga Kerja 44,743.20
B Bahan
Kayu papan kelas III m³ 0.036 2,522,000.00 90,792.00
Kayu Balok 5/7 Kelas III m³ - -
Paku Biasa Kg 0.080 22,400.00 1,792.00
Jumlah Harga Bahan 92,584.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 137,327.20
E Overhead + Profit ( Contoh 15% ) 15% x D 20,599.08
F Harga Satuan Pekerjaan ( D + E ) 157,926.28

A.2.2.1.13 Pembongkaran 1 m³ beton bertulang


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 13.344 111,700.00 1,490,524.80
2 Mandor L.04 OH 0.666 160,090.00 106,619.94
Jumlah Tenaga Kerja 1,597,144.74
B Bahan
Jumlah Harga Bahan -
C Peralatan

193
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,597,144.74
E Overhead + Profit ( Contoh 15% ) 15% x D 239,571.71
F Harga Satuan Pekerjaan ( D + E ) 1,836,716.45

A.2.2.1.14 Pembongkaran 1 m³ dinding tembok batu bata


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 6.667 111,700.00 744,703.90
2 Mandor L.04 OH 0.333 160,090.00 53,309.97
Jumlah Tenaga Kerja 798,013.87
B Bahan
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 798,013.87
E Overhead + Profit ( Contoh 15% ) 15% x D 119,702.08
F Harga Satuan Pekerjaan ( D + E ) 917,715.95

A.2.2.1.15 Pemasangan 1 m² pagar kawat jaring galvanis panjang 240 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.042 111,700.00 4,691.40
2 Tukang L.02 OH 0.004 135,070.00 540.28
3 Kepala Tukang L.03 OH 0.002 140,740.00 281.48
4 Mandor L.04 OH 0.042 160,090.00 6,723.78
Jumlah Tenaga Kerja 12,236.94
B Bahan
1 Kawat Jaring Lbr 0.143 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.2.2.1.16 Pemasangan 1 m² panel beton pracetak 5 x 50 x 213 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.375 - -
2 Tukang L.02 OH 0.125 - -
3 Kepala Tukang L.03 OH 0.012 - -
4 Mandor L.04 OH 0.019 - -
Jumlah Tenaga Kerja -
B Bahan

194
1 Panel Beton Pracetak Lbr 0.969 - -
2 Kolom Beton Pracetak Btg 0.525 - -
3 Semen PC Kg 45.000 - -
4 Pasir Beton m³ 0.074 - -
5 Koral m³ 0.146 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.2.2.1.17 Pemasangan 1 m² panel beton pracetak 5 x 50 x 213 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.375 - -
2 Tukang L.02 OH 0.125 - -
3 Kepala Tukang L.03 OH 0.012 - -
4 Mandor L.04 OH 0.019 - -
Jumlah Tenaga Kerja -
B Bahan
1 Panel Beton Pracetak Lbr 0.969 - -
2 Kolom Beton Pracetak Btg 0.525 - -
3 Semen PC Kg 45.000 - -
4 Pasir Beton m³ 0.074 - -
5 Koral m³ 0.146 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


A.2.3.1.1 Penggalian 1 m³ tanah biasa sedalam 1 m
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.750 111,700.00 83,775.00
2 Mandor L.04 OH 0.025 160,090.00 4,002.25
Jumlah Tenaga Kerja 87,777.25
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 87,777.25

195
E Overhead + Profit ( Contoh 15% ) 15% x D 13,166.59
F Harga Satuan Pekerjaan ( D + E ) 100,943.84

196
A.2.3.1.2 Penggalian 1 m³ tanah biasa sedalam 2 m
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.900 111,700.00 100,530.00
2 Mandor L.04 OH 0.045 160,090.00 7,204.05
Jumlah Tenaga Kerja 107,734.05
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 107,734.05
E Overhead + Profit ( Contoh 15% ) 15% x D 16,160.11
F Harga Satuan Pekerjaan ( D + E ) 123,894.16

A.2.3.1.3 Menggali 1 m³ tanah biasa sedalam 3 m


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.050 111,700.00 117,285.00
2 Mandor L.04 OH 0.067 160,090.00 10,726.03
Jumlah Tenaga Kerja 128,011.03
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 128,011.03
E Overhead + Profit ( Contoh 15% ) 15% x D 19,201.65
F Harga Satuan Pekerjaan ( D + E ) 147,212.68

A.2.3.1.4 Menggali 1 m³ tanah keras sedalam 1 m


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.000 111,700.00 111,700.00
2 Mandor L.04 OH 0.032 160,090.00 5,122.88
Jumlah Tenaga Kerja 116,822.88
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 116,822.88
E Overhead + Profit ( Contoh 15% ) 15% x D 17,523.43
F Harga Satuan Pekerjaan ( D + E ) 134,346.31

A.2.3.1.5 Menggali 1 m³ tanah cadas sedalam 1 m


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian

197
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.500 111,700.00 167,550.00
2 Mandor L.04 OH 0.060 160,090.00 9,605.40
Jumlah Tenaga Kerja 177,155.40
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 177,155.40
E Overhead + Profit ( Contoh 15% ) 15% x D 26,573.31
F Harga Satuan Pekerjaan ( D + E ) 203,728.71

A.2.3.1.6 Menggali 1 m³ tanah lumpur sedalam 1 m


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.200 111,700.00 134,040.00
2 Mandor L.04 OH 0.045 160,090.00 7,204.05
Jumlah Tenaga Kerja 141,244.05
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 141,244.05
E Overhead + Profit ( Contoh 15% ) 15% x D 21,186.61
F Harga Satuan Pekerjaan ( D + E ) 162,430.66

A.2.3.1.8 Pembuangan 1 m³ tanah sejauh 30 m


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7

A Tenaga
1 Pekerja L.01 OH 0.330 111,700.00 36,861.00
2 Mandor L.04 OH 0.010 160,090.00 1,600.90
Jumlah Tenaga Kerja 38,461.90
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 38,461.90
E Overhead + Profit ( Contoh 15% ) 15% x D 5,769.29
F Harga Satuan Pekerjaan ( D + E ) 44,231.19

A.2.3.1.9 Pengurukan kembali 1 m³ galian tanah


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7

198
A Tenaga
1 Pekerja L.01 OH 0.500 111,700.00 55,850.00
2 Mandor L.04 OH 0.050 160,090.00 8,004.50
Jumlah Tenaga Kerja 63,854.50
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 63,854.50
E Overhead + Profit ( Contoh 15% ) 15% x D 9,578.18
F Harga Satuan Pekerjaan ( D + E ) 73,432.68

A.2.3.1.10 Pemadatan tanah 1 m³ tanah ( per 20 cm )


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 111,700.00 55,850.00
2 Mandor L.04 OH 0.050 160,090.00 8,004.50
Jumlah Tenaga Kerja 63,854.50
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 63,854.50
E Overhead + Profit ( Contoh 15% ) 15% x D 9,578.18
F Harga Satuan Pekerjaan ( D + E ) 73,432.68

A.2.3.1.11 Pengurugan 1 m³ dengan pasir urug


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7

A Tenaga
1 Pekerja L.01 OH 0.300 111,700.00 33,510.00
2 Mandor L.04 OH 0.010 160,090.00 1,600.90
Jumlah Tenaga Kerja 35,110.90
B Bahan
1 Pasir Urug m³ 1.200 85,600.00 102,720.00
Jumlah Harga Bahan 102,720.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 137,830.90
E Overhead + Profit ( Contoh 15% ) 15% x D 20,674.64
F Harga Satuan Pekerjaan ( D + E ) 158,505.54

199
A.2.3.1.14 Pengurugan 1 m³ sirtu padat
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7

A Tenaga
1 Pekerja L.01 OH 0.250 111,700.00 27,925.00
2 Mandor L.04 OH 0.025 160,090.00 4,002.25
Jumlah Tenaga Kerja 31,927.25
B Bahan
1 Sirrtu m³ 1.200 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.3.2.1.1 Pemasangan 1 m2 Paving blok


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.200 111,700.00 22,340.00
2 Tukang Batu L.02 OH 0.300 135,070.00 40,521.00
3 Kepala Tukang L.03 OH 0.030 140,740.00 4,222.20
4 Mandor L.04 OH 0.025 160,090.00 4,002.25
Jumlah Tenaga Kerja 71,085.45
B Bahan
1 Paving m2 1.000 145,200.00 145,200.00
2 Pasir Pasang m³ 0.100 187,900.00 18,790.00
Jumlah Harga Bahan 163,990.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 235,075.45
E Overhead + Profit ( Contoh 15% ) 15% x D 35,261.32
F Harga Satuan Pekerjaan ( D + E ) 270,336.77

A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI


A.3.2.1.1 Pemasangan 1 m³ pondasi batu belah campuran 1 SP : 3 PP
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.500 111,700.00 167,550.00
2 Tukang Batu L.02 OH 0.750 135,070.00 101,302.50
3 Kepala Tukang L.03 OH 0.075 140,740.00 10,555.50
4 Mandor L.04 OH 0.075 160,090.00 12,006.75
Jumlah Tenaga Kerja 291,414.75

200
B Bahan
1 Batu Belah m³ 1.200 447,900.00 537,480.00
2 Semen Portland Kg 202.000 2,000.00 404,000.00
3 Pasir Pasang m³ 0.485 187,900.00 91,131.50
Jumlah Harga Bahan 1,032,611.50
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,324,026.25
E Overhead + Profit ( Contoh 15% ) 15% x D 198,603.94
F Harga Satuan Pekerjaan ( D + E ) 1,522,630.19

A.3.2.1.2 Pemasangan 1 m³ pondasi batu belah campuran 1 SP : 4 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.500 111,700.00 167,550.00
2 Tukang Batu L.02 OH 0.750 135,070.00 101,302.50
3 Kepala Tukang L.03 OH 0.075 140,740.00 10,555.50
4 Mandor L.04 OH 0.075 160,090.00 12,006.75
Jumlah Tenaga Kerja 291,414.75
B Bahan
1 Batu Belah m³ 1.200 447,900.00 537,480.00
2 Semen Portland Kg 163.000 2,000.00 326,000.00
3 Pasir Pasang m³ 0.520 187,900.00 97,708.00
Jumlah Harga Bahan 961,188.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,252,602.75
E Overhead + Profit ( Contoh 15% ) 15% x D 187,890.41
F Harga Satuan Pekerjaan ( D + E ) 1,440,493.16

A.3.2.1.3 Pemasangan 1 m³ pondasi batu belah campuran 1 SP : 5 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.500 111,700.00 167,550.00
2 Tukang Batu L.02 OH 0.750 135,070.00 101,302.50
3 Kepala Tukang L.03 OH 0.075 140,740.00 10,555.50
4 Mandor L.04 OH 0.075 160,090.00 12,006.75
Jumlah Tenaga Kerja 291,414.75
B Bahan
1 Batu Belah m³ 1.200 447,900.00 537,480.00
2 Semen Portland Kg 163.000 2,000.00 326,000.00
3 Pasir Pasang m³ 0.544 187,900.00 102,217.60
Jumlah Harga Bahan 965,697.60
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,257,112.35
E Overhead + Profit ( Contoh 15% ) 15% x D 188,566.85

201
F Harga Satuan Pekerjaan ( D + E ) 1,445,679.20

A.3.2.1.4 Pemasangan 1 m³ pondasi batu belah campuran 1 SP : 6 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.500 111,700.00 167,550.00
2 Tukang Batu L.02 OH 0.750 135,070.00 101,302.50
3 Kepala Tukang L.03 OH 0.075 140,740.00 10,555.50
4 Mandor L.04 OH 0.075 160,090.00 12,006.75
Jumlah Tenaga Kerja 291,414.75
B Bahan
1 Batu Belah m³ 1.200 447,900.00 537,480.00
2 Semen Portland Kg 117.000 2,000.00 234,000.00
3 Pasir Pasang m³ 0.561 187,900.00 105,411.90
Jumlah Harga Bahan 876,891.90
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,168,306.65
E Overhead + Profit ( Contoh 15% ) 15% x D 175,246.00
F Harga Satuan Pekerjaan ( D + E ) 1,343,552.65

A.3.2.1.5 Pemasangan 1 m³ pondasi batu belah campuran 1 SP : 8 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7

A Tenaga
1 Pekerja L.01 OH 1.500 111,700.00 167,550.00
2 Tukang Batu L.02 OH 0.750 135,070.00 101,302.50
3 Kepala Tukang L.03 OH 0.075 140,740.00 10,555.50
4 Mandor L.04 OH 0.075 160,090.00 12,006.75
Jumlah Tenaga Kerja 291,414.75
B Bahan
1 Batu Belah m³ 1.200 447,900.00 537,480.00
2 Semen Portland Kg 91.000 2,000.00 182,000.00
3 Pasir Pasang m³ 0.584 187,900.00 109,733.60
Jumlah Harga Bahan 829,213.60
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,120,628.35
E Overhead + Profit ( Contoh 15% ) 15% x D 168,094.25
F Harga Satuan Pekerjaan ( D + E ) 1,288,722.60

A.3.2.1.6 Pemasangan 1 m³ pondasi batu belah campuran 1 SP : 1 KP : 2 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.500 - -
2 Tukang Batu L.02 OH 0.750 - -

202
3 Kepala Tukang L.03 OH 0.075 - -
4 Mandor L.04 OH 0.075 - -
Jumlah Tenaga Kerja -
B Bahan
1 Batu Belah m³ 1.200 - -
1 Kapur m³ 0.170 - -
2 Semen Portland Kg 0.170 - -
3 Pasir Pasang m³ 0.340 - -
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.3.2.1.7 Pemasangan 1 m³ pondasi batu belah campuran 1 SP : 3 KP : 10 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.500 - -
2 Tukang Batu L.02 OH 0.750 - -
3 Kepala Tukang L.03 OH 0.075 - -
4 Mandor L.04 OH 0.075 - -
Jumlah Tenaga Kerja -
B Bahan
1 Batu Belah m³ 1.200 - -
1 Kapur m³ 0.147 - -
2 Semen Portland Kg 61.000 - -
3 Pasir Pasang m³ 0.492 - -
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.3.2.1.8 Pemasangan 1 m³ pondasi batu belah campuran ¼ SP : 1 KP : 4 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.500 - -
2 Tukang Batu L.02 OH 0.750 - -
3 Kepala Tukang L.03 OH 0.075 - -
4 Mandor L.04 OH 0.075 - -
Jumlah Tenaga Kerja -
B Bahan
1 Batu Belah m³ 1.200 - -
1 Kapur m³ 0.131 - -
2 Semen Portland Kg 41.000 - -

203
3 Pasir Pasang m³ 0.523 - -
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.3.2.1.9 Pemasangan 1 m³ batu kosong ( anstamping )


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7

A Tenaga
1 Pekerja L.01 OH 0.780 111,700.00 87,126.00
2 Tukang Batu L.02 OH 0.390 135,070.00 52,677.30
3 Kepala Tukang L.03 OH 0.039 140,740.00 5,488.86
4 Mandor L.04 OH 0.039 160,090.00 6,243.51
Jumlah Tenaga Kerja 151,535.67
B Bahan
1 Batu Belah m³ 1.200 447,900.00 537,480.00
2 Pasir Urug m³ 0.432 85,600.00 36,979.20
Jumlah Harga Bahan 574,459.20
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 725,994.87
E Overhead + Profit ( Contoh 15% ) 15% x D 108,899.23
F Harga Satuan Pekerjaan ( D + E ) 834,894.10

A.3.2.1.10 Pemasangan 1 m³ pondasi siklop, 60% beton campuran 1 SP : 2 PB : 3 Kr dan 40% batu belah
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 3.400 111,700.00 379,780.00
2 Tukang Batu L.02 OH 0.850 135,070.00 114,809.50
3 Kepala Tukang L.03 OH 0.085 140,740.00 11,962.90
4 Mandor L.04 OH 0.170 160,090.00 27,215.30
Jumlah Tenaga Kerja 533,767.70
B Bahan
1 Batu Belah m³ 0.480 447,900.00 214,992.00
2 Semen Portland Kg 194.000 2,000.00 388,000.00
3 Pasir Beton m³ 0.312 187,900.00 58,624.80
4 Kerikil m³ 0.468 256,800.00 120,182.40
5 Besi Beton Kg 126.000 15,900.00 2,003,400.00
6 Kawat Beton Kg 1.800 22,700.00 40,860.00
Jumlah Harga Bahan 2,826,059.20
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 3,359,826.90
E Overhead + Profit ( Contoh 15% ) 15% x D 503,974.04
F Harga Satuan Pekerjaan ( D + E ) 3,863,800.94

204
A.3.2.1.11 Pemasangan 1 m³ pondasi, sumuran, diameter 100 cm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 2.400 111,700.00 268,080.00
2 Tukang Batu L.02 OH 0.800 135,070.00 108,056.00
3 Kepala Tukang L.03 OH 0.080 140,740.00 11,259.20
4 Mandor L.04 OH 0.119 160,090.00 19,050.71
Jumlah Tenaga Kerja 406,445.91
B Bahan
1 Batu Belah m³ 0.450 447,900.00 201,555.00
2 Semen Portland Kg 194.000 2,000.00 388,000.00
3 Pasir Beton m³ 0.312 187,900.00 58,624.80
4 Kerikil m³ 0.468 256,800.00 120,182.40
Jumlah Harga Bahan 768,362.20
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,174,808.11
E Overhead + Profit ( Contoh 15% ) 15% x D 176,221.22
F Harga Satuan Pekerjaan ( D + E ) 1,351,029.33

205
A.4.1.1. HARGA SATUAN PEKERJAAN BETON
A.4.1.1.1. Membuat 1 m³ beton mutu f 'c = 7,4 Mpa ( K - 100 ), Slump (12 ± 2 ) cm, w/c = 0.87
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.650 111,700.00 184,305.00
2 Tukang Batu L.02 OH 0.275 135,070.00 37,144.25
3 Kepala Tukang L.03 OH 0.028 140,740.00 3,940.72
4 Mandor L.04 OH 0.083 160,090.00 13,287.47
Jumlah Tenaga Kerja 238,677.44
B Bahan
1 Semen Portland Kg 247.000 2,000.00 494,000.00
2 Pasir Beton Kg 869.000 117.44 102,053.19
3 Kerikil ( Maks 30mm ) Kg 999.000 395.59 395,190.62
4 Air Liter 215.000 53.00 11,395.00
Jumlah Harga Bahan 1,002,638.81
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,241,316.25
E Overhead + Profit ( Contoh 15% ) 15% x D 186,197.44
F Harga Satuan Pekerjaan ( D + E ) 1,427,513.69

A.4.1.1.2. Membuat 1 m³ beton mutu f 'c = 9,8 Mpa ( K - 125 ), Slump (12 ± 2 ) cm, w/c = 0.78
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.650 111,700.00 184,305.00
2 Tukang Batu L.02 OH 0.275 135,070.00 37,144.25
3 Kepala Tukang L.03 OH 0.028 140,740.00 3,940.72
4 Mandor L.04 OH 0.083 160,090.00 13,287.47
Jumlah Tenaga Kerja 238,677.44
B Bahan
1 Semen Portland Kg 276.000 2,000.00 552,000.00
2 Pasir Beton Kg 828.000 117.44 97,238.25
3 Kerikil ( Maks 30mm ) Kg 1,012.000 395.59 400,333.24
4 Air Liter 215.000 53.00 11,395.00
Jumlah Harga Bahan 1,060,966.49
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,299,643.93
E Overhead + Profit ( Contoh 15% ) 15% x D 194,946.59
F Harga Satuan Pekerjaan ( D + E ) 1,494,590.52

A.4.1.1.3. Membuat 1 m³ beton mutu f 'c = 12,2 Mpa ( K - 150 ), Slump (12 ± 2 ) cm, w/c = 0.72
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7

206
A Tenaga
1 Pekerja L.01 OH 1.650 111,700.00 184,305.00
2 Tukang Batu L.02 OH 0.275 135,070.00 37,144.25
3 Kepala Tukang L.03 OH 0.028 140,740.00 3,940.72
4 Mandor L.04 OH 0.083 160,090.00 13,287.47
Jumlah Tenaga Kerja 238,677.44
B Bahan
1 Semen Portland Kg 299.000 2,000.00 598,000.00
2 Pasir Beton Kg 799.000 117.44 93,832.56
3 Kerikil ( Maks 30mm ) Kg 1,017.000 395.59 402,311.17
4 Air Liter 215.000 53.00 11,395.00
Jumlah Harga Bahan 1,105,538.73
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,344,216.17
E Overhead + Profit ( Contoh 15% ) 15% x D 201,632.43
F Harga Satuan Pekerjaan ( D + E ) 1,545,848.60

CATATAN :
Bobot isi pasir = 1.400 Kg/m³, bobot isi kerikil = 1.350 Kg/m³, buckling factor pasir = 20%

A.4.1.1.4. Membuat 1 m³ lantai kerja beton mutu f 'c = 7,4 Mpa ( K - 100 ), Slump ( 3 - 6 ) cm, w/c = 0.87
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.650 111,700.00 184,305.00
2 Tukang Batu L.02 OH 0.275 135,070.00 37,144.25
3 Kepala Tukang L.03 OH 0.028 140,740.00 3,940.72
4 Mandor L.04 OH 0.083 160,090.00 13,287.47
Jumlah Tenaga Kerja 238,677.44
B Bahan
1 Semen Portland Kg 299.000 2,000.00 598,000.00
2 Pasir Beton Kg 799.000 117.44 93,832.56
3 Kerikil ( Maks 30mm ) Kg 1,017.000 395.59 402,311.17
4 Air Liter 215.000 53.00 11,395.00
Jumlah Harga Bahan 1,105,538.73
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,344,216.17
E Overhead + Profit ( Contoh 15% ) 15% x D 201,632.43
F Harga Satuan Pekerjaan ( D + E ) 1,545,848.60

A.4.1.1.5. Membuat 1 m³ beton mutu f 'c = 14,5 Mpa ( K - 175 ), Slump ( 12 ± 2 ) cm, w/c = 0.66
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.650 111,700.00 184,305.00
2 Tukang Batu L.02 OH 0.275 135,070.00 37,144.25

207
3 Kepala Tukang L.03 OH 0.028 140,740.00 3,940.72
4 Mandor L.04 OH 0.083 160,090.00 13,287.47
Jumlah Tenaga Kerja 238,677.44
B Bahan
1 Semen Portland Kg 326.000 2,000.00 652,000.00
2 Pasir Beton Kg 760.000 117.44 89,252.50
3 Kerikil ( Maks 30mm ) Kg 1,029.000 424.89 437,210.67
4 Air Liter 215.000 53.00 11,395.00
Jumlah Harga Bahan 1,189,858.17
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,428,535.61
E Overhead + Profit ( Contoh 15% ) 15% x D 214,280.34
F Harga Satuan Pekerjaan ( D + E ) 1,642,815.95

A.4.1.1.6. Membuat 1 m³ beton mutu f 'c = 16,9 Mpa ( K - 200 ), Slump ( 12 ± 2 ) cm, w/c = 0.61
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.650 111,700.00 184,305.00
2 Tukang Batu L.02 OH 0.275 135,070.00 37,144.25
3 Kepala Tukang L.03 OH 0.028 140,740.00 3,940.72
4 Mandor L.04 OH 0.083 160,090.00 13,287.47
Jumlah Tenaga Kerja 238,677.44
B Bahan
1 Semen Portland Kg 352.000 2,000.00 704,000.00
2 Pasir Beton Kg 731.000 117.44 85,846.81
3 Kerikil ( Maks 30mm ) Kg 1,031.000 424.89 438,060.44
4 Air Liter 215.000 53.00 11,395.00
Jumlah Harga Bahan 1,239,302.26
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,477,979.70
E Overhead + Profit ( Contoh 15% ) 15% x D 221,696.95
F Harga Satuan Pekerjaan ( D + E ) 1,699,676.65

A.4.1.1.7. Membuat 1 m³ beton mutu f 'c = 19,3 Mpa ( K - 225 ), Slump ( 12 ± 2 ) cm, w/c = 0.58
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.650 111,700.00 184,305.00
2 Tukang Batu L.02 OH 0.275 135,070.00 37,144.25
3 Kepala Tukang L.03 OH 0.028 140,740.00 3,940.72
4 Mandor L.04 OH 0.083 160,090.00 13,287.47
Jumlah Tenaga Kerja 238,677.44
B Bahan
1 Semen Portland Kg 371.000 2,000.00 742,000.00
2 Pasir Beton Kg 698.000 117.44 81,971.38
3 Kerikil ( Maks 30mm ) Kg 1,047.000 424.89 444,858.67

208
4 Air Liter 215.000 53.00 11,395.00
Jumlah Harga Bahan 1,280,225.04
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,518,902.48
E Overhead + Profit ( Contoh 15% ) 15% x D 227,835.37
F Harga Satuan Pekerjaan ( D + E ) 1,746,737.85

A.4.1.1.8. Membuat 1 m³ beton mutu f 'c = 21,7 Mpa ( K - 250 ), Slump ( 12 ± 2 ) cm, w/c = 0.56
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.650 111,700.00 184,305.00
2 Tukang Batu L.02 OH 0.275 135,070.00 37,144.25
3 Kepala Tukang L.03 OH 0.028 140,740.00 3,940.72
4 Mandor L.04 OH 0.083 160,090.00 13,287.47
Jumlah Tenaga Kerja 238,677.44
B Bahan
1 Semen Portland Kg 384.000 2,000.00 768,000.00
2 Pasir Beton Kg 692.000 117.44 81,266.75
3 Kerikil ( Maks 30mm ) Kg 1,039.000 424.89 441,459.56
4 Air Liter 215.000 53.00 11,395.00
Jumlah Harga Bahan 1,302,121.31
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,540,798.75
E Overhead + Profit ( Contoh 10% ) 10% x D 154,079.87
F Harga Satuan Pekerjaan ( D + E ) 1,694,878.62

A.4.1.1.9. Membuat 1 m³ beton mutu f 'c = 24,0 Mpa ( K - 275 ), Slump ( 12 ± 2 ) cm, w/c = 0.53
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.650 111,700.00 184,305.00
2 Tukang Batu L.02 OH 0.275 135,070.00 37,144.25
3 Kepala Tukang L.03 OH 0.028 140,740.00 3,940.72
4 Mandor L.04 OH 0.083 160,090.00 13,287.47
Jumlah Tenaga Kerja 238,677.44
B Bahan
1 Semen Portland Kg 406.000 2,000.00 812,000.00
2 Pasir Beton Kg 684.000 117.44 80,327.25
3 Kerikil ( Maks 30mm ) Kg 1,026.000 424.89 435,936.00
4 Air Liter 215.000 53.00 11,395.00
Jumlah Harga Bahan 1,339,658.25
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,578,335.69
E Overhead + Profit ( Contoh 15% ) 15% x D 236,750.35
F Harga Satuan Pekerjaan ( D + E ) 1,815,086.04

209
A.4.1.1.10. Membuat 1 m³ beton mutu f 'c = 26,4 Mpa ( K - 300 ), Slump ( 12 ± 2 ) cm, w/c = 0.52
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.650 111,700.00 184,305.00
2 Tukang Batu L.02 OH 0.275 135,070.00 37,144.25
3 Kepala Tukang L.03 OH 0.028 140,740.00 3,940.72
4 Mandor L.04 OH 0.083 160,090.00 13,287.47
Jumlah Tenaga Kerja 238,677.44
B Bahan
1 Semen Portland Kg 413.000 2,000.00 826,000.00
2 Pasir Beton Kg 681.000 117.44 79,974.94
3 Kerikil ( Maks 30mm ) Kg 1,021.000 424.89 433,811.56
4 Air Liter 215.000 53.00 11,395.00
Jumlah Harga Bahan 1,351,181.49
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,589,858.93
E Overhead + Profit ( Contoh 15% ) 15% x D 238,478.84
F Harga Satuan Pekerjaan ( D + E ) 1,828,337.77

A.4.1.1.11. Membuat 1 m³ beton mutu f 'c = 28,8 Mpa ( K - 325 ), Slump ( 12 ± 2 ) cm, w/c = 0.49
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 2.100 111,700.00 234,570.00
2 Tukang Batu L.02 OH 0.350 135,070.00 47,274.50
3 Kepala Tukang L.03 OH 0.035 140,740.00 4,925.90
4 Mandor L.04 OH 0.105 160,090.00 16,809.45
Jumlah Tenaga Kerja 303,579.85
B Bahan
1 Semen Portland Kg 439.000 2,000.00 878,000.00
2 Pasir Beton Kg 670.000 117.44 78,683.13
3 Kerikil ( Maks 30mm ) Kg 1,006.000 424.89 427,438.22
4 Air Liter 215.000 53.00 11,395.00
Jumlah Harga Bahan 1,395,516.35
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,699,096.20
E Overhead + Profit ( Contoh 15% ) 15% x D 254,864.43
F Harga Satuan Pekerjaan ( D + E ) 1,953,960.63

A.4.1.1.12. Membuat 1 m³ beton mutu f 'c = 31,2 Mpa ( K - 350 ), Slump ( 12 ± 2 ) cm, w/c = 0.48
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 2.100 111,700.00 234,570.00

210
2 Tukang Batu L.02 OH 0.350 135,070.00 47,274.50
3 Kepala Tukang L.03 OH 0.035 140,740.00 4,925.90
4 Mandor L.04 OH 0.105 160,090.00 16,809.45
Jumlah Tenaga Kerja 303,579.85
B Bahan
1 Semen Portland Kg 448.000 2,000.00 896,000.00
2 Pasir Beton Kg 667.000 117.44 78,330.81
3 Kerikil ( Maks 30mm ) Kg 1,000.000 424.89 424,888.89
4 Air Liter 215.000 53.00 11,395.00
Jumlah Harga Bahan 1,410,614.70
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 1,714,194.55
E Overhead + Profit ( Contoh 15% ) 15% x D 257,129.18
F Harga Satuan Pekerjaan ( D + E ) 1,971,323.73

A.4.1.1.14. Pemasangan 1 m' PVC Waterstop lebar 150 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.060 - -
2 Tukang Batu / Pipa L.02 OH 0.030 - -
3 Kepala Tukang L.03 OH 0.003 - -
4 Mandor L.04 OH 0.003 - -
Jumlah Tenaga Kerja -
B Bahan
1 Waterstp lebar 150 mm m' 1.050 - -
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.1.1.15. Pemasangan 1 m' PVC Waterstop lebar 200 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.070 - -
2 Tukang Batu / Pipa L.02 OH 0.035 - -
3 Kepala Tukang L.03 OH 0.004 - -
4 Mandor L.04 OH 0.007 - -
Jumlah Tenaga Kerja -
B Bahan
1 Waterstp lebar 200 mm m' 1.050 - -
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -

211
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.1.1.16. Pemasangan 1 m' PVC Waterstop lebar 230 mm - 320 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.080 - -
2 Tukang Batu / Pipa L.02 OH 0.040 - -
3 Kepala Tukang L.03 OH 0.004 - -
4 Mandor L.04 OH 0.004 - -
Jumlah Tenaga Kerja -
B Bahan
1 Waterstp lebar 230 mm - 320 mm m' 1.050 - -
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

212
A.4.1.1.17. Pembesian 10 Kg dengan besi ulir
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.070 111,700.00 7,819.00
2 Tukang Besi L.02 OH 0.070 135,070.00 9,454.90
3 Kepala Tukang L.03 OH 0.007 140,740.00 985.18
4 Mandor L.04 OH 0.004 160,090.00 640.36
Jumlah Tenaga Kerja 18,899.44
B Bahan
1 Besi Beton Ulir Kg 10.500 17,000.00 178,500.00
2 Kawat Beton Kg 0.150 22,700.00 3,405.00
Jumlah Harga Bahan 181,905.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 200,804.44
E Overhead + Profit ( Contoh 15% ) 15% x D 30,120.67
F Harga Satuan Pekerjaan ( D + E ) 230,925.11
Harga Satuan Pekerjaan /1 kg besi F/10 23,092.51

A.4.1.1.17. Pembesian 10 Kg dengan besi polos


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.070 111,700.00 7,819.00
2 Tukang Besi L.02 OH 0.070 135,070.00 9,454.90
3 Kepala Tukang L.03 OH 0.007 140,740.00 985.18
4 Mandor L.04 OH 0.004 160,090.00 640.36
Jumlah Tenaga Kerja 18,899.44
B Bahan
1 Besi Beton Polos Kg 10.500 15,900.00 166,950.00
2 Kawat Beton Kg 0.150 22,700.00 3,405.00
Jumlah Harga Bahan 170,355.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 189,254.44
E Overhead + Profit ( Contoh 15% ) 15% x D 28,388.17
F Harga Satuan Pekerjaan ( D + E ) 217,642.61
Harga Satuan Pekerjaan /1 kg besi F/10 21,764.26

A.4.1.1.18. Pemasangan 10 Kg kabel presstressed polos / strands


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.050 - -
2 Tukang Besi L.02 OH 0.050 - -

213
3 Kepala Tukang L.03 OH 0.005 - -
4 Mandor L.04 OH 0.003 - -
Jumlah Tenaga Kerja -
B Bahan
1 Besi Beton ( Polos / Ulir ) Kg 10.500 - -
2 Kawat Beton Kg 0.100 - -
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.1.1.19. Pemasangan 10 Kg jaring kawat baja ( wiremesh )


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.025 111,700.00 2,792.50
2 Tukang Besi L.02 OH 0.025 135,070.00 3,376.75
3 Kepala Tukang L.03 OH 0.025 140,740.00 3,518.50
4 Mandor L.04 OH 0.001 160,090.00 160.09
Jumlah Tenaga Kerja 9,847.84
B Bahan
1 Jaring kawat baja di las Kg 10.200 Err:509 Err:509
2 Kawat Beton Kg 0.050 22,700.00 1,135.00
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509
Harga Satuan Pekerjaan /1 kg WM F/10 Err:509

214
A.4.1.1.20. Pemasangan 1 m² bekisting untuk pondasi
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.520 111,700.00 58,084.00
2 Tukang Kayu L.02 OH 0.260 135,070.00 35,118.20
3 Kepala Tukang L.03 OH 0.026 140,740.00 3,659.24
4 Mandor L.04 OH 0.026 160,090.00 4,162.34
Jumlah Tenaga Kerja 101,023.78
B Bahan
1 Kayu Kelas III m³ 0.040 2,522,000.00 100,880.00
2 Paku 5 - 10 cm Kg 0.300 22,400.00 6,720.00
3 Minyak Bekisting Liter 0.100 10,900.00 1,090.00
Jumlah Harga Bahan 108,690.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 209,713.78
E Overhead + Profit ( Contoh 15% ) 15% x D 31,457.07
F Harga Satuan Pekerjaan ( D + E ) 241,170.85

A.4.1.1.21. Pemasangan 1 m² bekisting untuk sloof


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.520 111,700.00 58,084.00
2 Tukang Kayu L.02 OH 0.260 135,070.00 35,118.20
3 Kepala Tukang L.03 OH 0.026 140,740.00 3,659.24
4 Mandor L.04 OH 0.026 160,090.00 4,162.34
Jumlah Tenaga Kerja 101,023.78
B Bahan
1 Kayu Kelas III m³ 0.045 2,522,000.00 113,490.00
2 Paku 5 - 10 cm Kg 0.300 22,400.00 6,720.00
3 Minyak Bekisting Liter 0.100 10,900.00 1,090.00
Jumlah Harga Bahan 121,300.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 222,323.78
E Overhead + Profit ( Contoh 15% ) 15% x D 33,348.57
F Harga Satuan Pekerjaan ( D + E ) 255,672.35

215
A.4.1.1.22. Pemasangan 1 m² bekisting untuk kolom
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.660 111,700.00 73,722.00
2 Tukang Kayu L.02 OH 0.330 135,070.00 44,573.10
3 Kepala Tukang L.03 OH 0.033 140,740.00 4,644.42
4 Mandor L.04 OH 0.003 160,090.00 480.27
Jumlah Tenaga Kerja 123,419.79
B Bahan
1 Kayu Kelas III m³ 0.040 2,522,000.00 100,880.00
2 Paku 5 - 12 cm Kg 0.400 22,400.00 8,960.00
3 Minyak Bekisting Liter 0.200 10,900.00 2,180.00
4 Balok Kayu Kelas II m³ 0.015 3,007,000.00 45,105.00
5 Plywood Tebal 9 mm Lembar 0.350 159,900.00 55,965.00
6 Dolken Kayu Ø 8 - 10 cm -
Batang 2.000 35,000.00 70,000.00
Panjang 4 m
Jumlah Harga Bahan 283,090.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 406,509.79
E Overhead + Profit ( Contoh 15% ) 15% x D 60,976.47
F Harga Satuan Pekerjaan ( D + E ) 467,486.26

A.4.1.1.23. Pemasangan 1 m² bekisting untuk balok


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.660 111,700.00 73,722.00
2 Tukang Kayu L.02 OH 0.330 135,070.00 44,573.10
3 Kepala Tukang L.03 OH 0.033 140,740.00 4,644.42
4 Mandor L.04 OH 0.003 160,090.00 480.27
Jumlah Tenaga Kerja 123,419.79
B Bahan
1 Kayu Kelas III m³ 0.040 2,522,000.00 100,880.00
2 Paku 5 - 12 cm Kg 0.400 22,400.00 8,960.00
3 Minyak Bekisting Liter 0.200 10,900.00 2,180.00
4 Balok Kayu Kelas II m³ 0.018 3,007,000.00 54,126.00
5 Plywood Tebal 9 mm Lembar 0.350 159,900.00 55,965.00
6 Dolken Kayu Ø 8 - 10 cm -
Batang 2.000 35,000.00 70,000.00
Panjang 4 m
Jumlah Harga Bahan 292,111.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 415,530.79
E Overhead + Profit ( Contoh 15% ) 15% x D 62,329.62
F Harga Satuan Pekerjaan ( D + E ) 477,860.41

A.4.1.1.24. Pemasangan 1 m² bekisting untuk lantai

216
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.660 111,700.00 73,722.00
2 Tukang Kayu L.02 OH 0.330 135,070.00 44,573.10
3 Kepala Tukang L.03 OH 0.033 140,740.00 4,644.42
4 Mandor L.04 OH 0.033 160,090.00 5,282.97
Jumlah Tenaga Kerja 128,222.49
B Bahan
1 Kayu Kelas III m³ 0.040 2,522,000.00 100,880.00
2 Paku 5 - 12 cm Kg 0.400 22,400.00 8,960.00
3 Minyak Bekisting Liter 0.200 10,900.00 2,180.00
4 Balok Kayu Kelas II m³ 0.015 3,007,000.00 45,105.00
5 Plywood Tebal 9 mm Lembar 0.350 159,900.00 55,965.00
6 Dolken Kayu Galam Ø 8 - 10
Batang 6.000 35,000.00 210,000.00
cm - Panjang 4 m
Jumlah Harga Bahan 423,090.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 551,312.49
E Overhead + Profit ( Contoh 15% ) 15% x D 82,696.87
F Harga Satuan Pekerjaan ( D + E ) 634,009.36

217
A.4.1.1.25. Pemasangan 1 m² bekisting untuk dinding
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.660 111,700.00 73,722.00
2 Tukang Kayu L.02 OH 0.330 135,070.00 44,573.10
3 Kepala Tukang L.03 OH 0.033 140,740.00 4,644.42
4 Mandor L.04 OH 0.033 160,090.00 5,282.97
Jumlah Tenaga Kerja 128,222.49
B Bahan
1 Kayu Kelas III m³ 0.030 2,522,000.00 75,660.00
2 Paku 5 - 12 cm Kg 0.400 22,400.00 8,960.00
3 Minyak Bekisting Liter 0.200 10,900.00 2,180.00
4 Balok Kayu Kelas II m³ 0.020 3,007,000.00 60,140.00
5 Plywood Tebal 9 mm Lembar 0.350 159,900.00 55,965.00
6 Dolken Kayu Ø 8 - 10 cm -
Batang 3.000 35,000.00 105,000.00
Panjang 4 m
7 Panjang Jarak Bekisting /
Buah 4.000 - -
Spacer
Jumlah Harga Bahan 307,905.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 436,127.49
E Overhead + Profit ( Contoh 15% ) 15% x D 65,419.12
F Harga Satuan Pekerjaan ( D + E ) 501,546.61

A.4.1.1.26. Pemasangan 1 m² bekisting untuk tangga


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.660 111,700.00 73,722.00
2 Tukang Kayu L.02 OH 0.330 135,070.00 44,573.10
3 Kepala Tukang L.03 OH 0.033 140,740.00 4,644.42
4 Mandor L.04 OH 0.033 160,090.00 5,282.97
Jumlah Tenaga Kerja 128,222.49
B Bahan
1 Kayu Kelas III m³ 0.030 2,522,000.00 75,660.00
2 Paku 5 - 12 cm Kg 0.400 22,400.00 8,960.00
3 Minyak Bekisting Liter 0.150 10,900.00 1,635.00
4 Balok Kayu Kelas II m³ 0.015 3,007,000.00 45,105.00
5 Plywood Tebal 9 mm Lembar 0.350 159,900.00 55,965.00
6 Dolken Kayu Ø 8 - 10 cm -
Batang 2.000 35,000.00 70,000.00
Panjang 4 m
Jumlah Harga Bahan 257,325.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 385,547.49
E Overhead + Profit ( Contoh 15% ) 15% x D 57,832.12
F Harga Satuan Pekerjaan ( D + E ) 443,379.61

218
A.4.1.1.27. Pemasangan 1 m² jembatan untuk pengecoran beton
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.150 111,700.00 16,755.00
2 Tukang Kayu L.02 OH 0.050 135,070.00 6,753.50
3 Kepala Tukang L.03 OH 0.005 140,740.00 703.70
4 Mandor L.04 OH 0.008 160,090.00 1,280.72
Jumlah Tenaga Kerja 25,492.92
B Bahan
1 Kayu Kelas III ( Papan ) m³ 0.026 2,522,000.00 66,580.80
2 Paku 5 - 12 cm Kg 0.600 22,400.00 13,440.00
3 Dolken Kayu Ø 8 - 10 cm -
Batang 0.500 35,000.00 17,500.00
Panjang 4 m
Jumlah Harga Bahan 97,520.80
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 123,013.72
E Overhead + Profit ( Contoh 15% ) 15% x D 18,452.06
F Harga Satuan Pekerjaan ( D + E ) 141,465.78

A.4.1.1.28. Membuat 1 m³ pondasi beton bertulang ( 150 Kg besi + Bekisting )


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 5.300 111,700.00 592,010.00
2 Tukang Batu L.02 OH 0.275 135,070.00 37,144.25
3 Tukang Kayu L.02 OH 1.300 135,070.00 175,591.00
4 Tukang Besi L.02 OH 1.050 135,070.00 141,823.50
5 Kepala Tukang L.03 OH 0.262 140,740.00 36,873.88
6 Mandor L.04 OH 0.265 160,090.00 42,423.85
Jumlah Tenaga Kerja 1,025,866.48
B Bahan
1 Kayu Kelas III ( Papan ) m³ 0.200 2,522,000.00 504,400.00
2 Paku 5 - 12 cm Kg 0.150 22,400.00 3,360.00
3 Minyak Bekisting Liter 0.400 10,900.00 4,360.00
4 Besi Beton Polos Kg 157.500 15,900.00 2,504,250.00
5 Kawat Beton Kg 2.250 22,700.00 51,075.00
6 Semen Portland Kg 336.000 2,000.00 672,000.00
7 Pasir Beton m³ 0.540 187,900.00 101,466.00
8 Kerikil m³ 0.810 573,600.00 464,616.00
Jumlah Harga Bahan 4,305,527.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 5,331,393.48
E Overhead + Profit ( Contoh 15% ) 15% x D 799,709.02
F Harga Satuan Pekerjaan ( D + E ) 6,131,102.50

219
A.4.1.1.29. Membuat 1 m³ sloof beton bertulang ( 200 Kg besi + Bekisting )
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 5.650 111,700.00 631,105.00
2 Tukang Batu L.02 OH 0.275 135,070.00 37,144.25
3 Tukang Kayu L.02 OH 1.560 135,070.00 210,709.20
4 Tukang Besi L.02 OH 1.400 135,070.00 189,098.00
5 Kepala Tukang L.03 OH 0.323 140,740.00 45,459.02
6 Mandor L.04 OH 0.283 160,090.00 45,305.47
Jumlah Tenaga Kerja 1,158,820.94
B Bahan
1 Kayu Kelas III m³ 0.270 2,522,000.00 680,940.00
2 Paku 5 - 12 cm Kg 2.000 22,400.00 44,800.00
3 Minyak Bekisting Liter 0.600 10,900.00 6,540.00
4 Besi Beton Polos Kg 210.000 15,900.00 3,339,000.00
5 Kawat Beton Kg 3.000 22,700.00 68,100.00
6 Semen Portland Kg 336.000 2,000.00 672,000.00
7 Pasir Beton m³ 0.540 187,900.00 101,466.00
8 Kerikil m³ 0.810 573,600.00 464,616.00
Jumlah Harga Bahan 5,377,462.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 6,536,282.94
E Overhead + Profit ( Contoh 15% ) 15% x D 980,442.44
F Harga Satuan Pekerjaan ( D + E ) 7,516,725.38

A.4.1.1.30. Membuat 1 m³ kolom beton bertulang ( 300 Kg besi + Bekisting )


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 7.050 111,700.00 787,485.00
2 Tukang Batu L.02 OH 0.275 135,070.00 37,144.25
3 Tukang Kayu L.02 OH 1.650 135,070.00 222,865.50
4 Tukang Besi L.02 OH 2.100 135,070.00 283,647.00
5 Kepala Tukang L.03 OH 0.403 140,740.00 56,718.22
6 Mandor L.04 OH 0.353 160,090.00 56,511.77
Jumlah Tenaga Kerja 1,444,371.74
B Bahan
1 Kayu Kelas III m³ 0.400 2,522,000.00 1,008,800.00
2 Paku 5 - 12 cm Kg 4.000 22,400.00 89,600.00
3 Minyak Bekisting Liter 2.000 10,900.00 21,800.00
4 Besi Beton Polos Kg 315.000 15,900.00 5,008,500.00
5 Kawat Beton Kg 4.500 22,700.00 102,150.00
6 Semen Portland Kg 336.000 2,000.00 672,000.00
7 Pasir Beton m³ 0.540 187,900.00 101,466.00
8 Kerikil m³ 0.810 573,600.00 464,616.00
9 Kayu Kelas II ( Balok ) m³ 0.150 3,007,000.00 451,050.00
10 Plywood 9 mm Lembar 3.500 159,900.00 559,650.00

220
11 Dolken Kayu Ø (8 - 10) cm, 35,000.00 700,000.00
Batang 20.000
Panjang 4m
Jumlah Harga Bahan 9,179,632.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 10,624,003.74
E Overhead + Profit ( Contoh 15% ) 15% x D 1,593,600.56
F Harga Satuan Pekerjaan ( D + E ) 12,217,604.30

A.4.1.1.31. Membuat 1 m³ Balok beton bertulang ( 200 Kg besi + Bekisting )


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 6.350 111,700.00 709,295.00
2 Tukang Batu L.02 OH 0.275 135,070.00 37,144.25
3 Tukang Kayu L.02 OH 1.650 135,070.00 222,865.50
4 Tukang Besi L.02 OH 1.400 135,070.00 189,098.00
5 Kepala Tukang L.03 OH 0.333 140,740.00 46,866.42
6 Mandor L.04 OH 0.318 160,090.00 50,908.62
Jumlah Tenaga Kerja 1,256,177.79
B Bahan
1 Kayu Kelas III m³ 0.320 2,522,000.00 807,040.00
2 Paku 5 - 12 cm Kg 3.200 22,400.00 71,680.00
3 Minyak Bekisting Liter 1.600 10,900.00 17,440.00
4 Besi Beton Polos Kg 210.000 15,900.00 3,339,000.00
5 Kawat Beton Kg 3.000 22,700.00 68,100.00
6 Semen Portland Kg 336.000 2,000.00 672,000.00
7 Pasir Beton m³ 0.540 187,900.00 101,466.00
8 Kerikil m³ 0.810 573,600.00 464,616.00
9 Kayu Kelas II ( Balok ) m³ 0.140 3,007,000.00 420,980.00
10 Plywood 9 mm Lembar 2.800 159,900.00 447,720.00
11 Dolken Kayu Ø (8 - 10) cm, 35,000.00 560,000.00
Batang 16.000
Panjang 4m
Jumlah Harga Bahan 6,970,042.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 8,226,219.79
E Overhead + Profit ( Contoh 15% ) 15% x D 1,233,932.97
F Harga Satuan Pekerjaan ( D + E ) 9,460,152.76

A.4.1.1.32. Membuat 1 m³ kolom beton bertulang ( 150 Kg besi + Bekisting )


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 5.300 111,700.00 592,010.00
2 Tukang Batu L.02 OH 0.275 135,070.00 37,144.25
3 Tukang Kayu L.02 OH 1.300 135,070.00 175,591.00
4 Tukang Besi L.02 OH 1.050 135,070.00 141,823.50
5 Kepala Tukang L.03 OH 0.265 140,740.00 37,296.10

221
6 Mandor L.04 OH 0.265 160,090.00 42,423.85
Jumlah Tenaga Kerja 1,026,288.70
B Bahan
1 Kayu Kelas III m³ 0.320 2,522,000.00 807,040.00
2 Paku 5 - 12 cm Kg 3.200 22,400.00 71,680.00
3 Minyak Bekisting Liter 1.600 10,900.00 17,440.00
4 Besi Beton Polos Kg 157.500 15,900.00 2,504,250.00
5 Kawat Beton Kg 2.250 22,700.00 51,075.00
6 Semen Portland Kg 336.000 2,000.00 672,000.00
7 Pasir Beton m³ 0.540 187,900.00 101,466.00
8 Kerikil m³ 0.810 573,600.00 464,616.00
9 Kayu Kelas II ( Balok ) m³ 0.120 3,007,000.00 360,840.00
10 Plywood 9 mm Lembar 2.800 159,900.00 447,720.00
11 Dolken Kayu Ø (8 - 10) cm, 35,000.00 1,120,000.00
Batang 32.000
Panjang 4m - -
Jumlah Harga Bahan 6,618,127.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 7,644,415.70
E Overhead + Profit ( Contoh 15% ) 15% x D 1,146,662.36
F Harga Satuan Pekerjaan ( D + E ) 8,791,078.06

A.4.1.1.33. Membuat 1 m³ dinding beton bertulang ( 150 Kg besi + Bekisting )


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 5.300 111,700.00 592,010.00
2 Tukang Batu L.02 OH 0.275 135,070.00 37,144.25
3 Tukang Kayu L.02 OH 1.300 135,070.00 175,591.00
4 Tukang Besi L.02 OH 1.050 135,070.00 141,823.50
5 Kepala Tukang L.03 OH 0.262 140,740.00 36,873.88
6 Mandor L.04 OH 0.265 160,090.00 42,423.85
Jumlah Tenaga Kerja 1,025,866.48
B Bahan
1 Kayu Kelas III m³ 0.240 2,522,000.00 605,280.00
2 Paku 5 - 12 cm Kg 3.200 22,400.00 71,680.00
3 Minyak Bekisting Liter 1.600 10,900.00 17,440.00
4 Besi Beton Polos Kg 157.500 15,900.00 2,504,250.00
5 Kawat Beton Kg 2.250 22,700.00 51,075.00
6 Semen Portland Kg 336.000 2,000.00 672,000.00
7 Pasir Beton m³ 0.540 187,900.00 101,466.00
8 Kerikil m³ 0.810 573,600.00 464,616.00
9 Kayu Kelas II ( Balok ) m³ 0.160 3,007,000.00 481,120.00
10 Plywood 9 mm Lembar 2.800 159,900.00 447,720.00
11 Dolken Kayu Ø (8 - 10) cm, 35,000.00 840,000.00
Batang 24.000
Panjang 4m - -
Jumlah Harga Bahan 6,256,647.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 7,282,513.48
E Overhead + Profit ( Contoh 15% ) 15% x D 1,092,377.02

222
F Harga Satuan Pekerjaan ( D + E ) 8,374,890.50

A.4.1.1.34. Membuat 1 m³ dinding beton bertulang ( 200 Kg besi + Bekisting )


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 5.650 111,700.00 631,105.00
2 Tukang Batu L.02 OH 0.275 135,070.00 37,144.25
3 Tukang Kayu L.02 OH 1.560 135,070.00 210,709.20
4 Tukang Besi L.02 OH 1.400 135,070.00 189,098.00
5 Kepala Tukang L.03 OH 0.323 140,740.00 45,459.02
6 Mandor L.04 OH 0.283 160,090.00 45,305.47
Jumlah Tenaga Kerja 1,158,820.94
B Bahan
1 Kayu Kelas III m³ 0.250 2,522,000.00 630,500.00
2 Paku 5 - 12 cm Kg 3.000 22,400.00 67,200.00
3 Minyak Bekisting Liter 1.200 10,900.00 13,080.00
4 Besi Beton Polos Kg 210.000 15,900.00 3,339,000.00
5 Kawat Beton Kg 3.000 22,700.00 68,100.00
6 Semen Portland Kg 336.000 2,000.00 672,000.00
7 Pasir Beton m³ 0.540 187,900.00 101,466.00
8 Kerikil m³ 0.810 573,600.00 464,616.00
9 Kayu Kelas II ( Balok ) m³ 0.105 3,007,000.00 315,735.00
10 Plywood 9 mm Lembar 2.500 159,900.00 399,750.00
11 Dolken Kayu Ø (8 - 10) cm, 35,000.00 490,000.00
Batang 14.000
Panjang 4m - -
Jumlah Harga Bahan 6,561,447.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 7,720,267.94
E Overhead + Profit ( Contoh 15% ) 15% x D 1,158,040.19
F Harga Satuan Pekerjaan ( D + E ) 8,878,308.13

A.4.1.1.35. Membuat 1 m' kolom praktis beton bertulang ( 11 x 11 ) cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.180 111,700.00 20,106.00
2 Tukang Batu L.02 OH 0.020 135,070.00 2,701.40
3 Tukang Kayu L.02 OH 0.020 135,070.00 2,701.40
4 Tukang Besi L.02 OH 0.020 135,070.00 2,701.40
5 Kepala Tukang L.03 OH 0.060 140,740.00 8,444.40
6 Mandor L.04 OH 0.090 160,090.00 14,408.10
Jumlah Tenaga Kerja 51,062.70
B Bahan
1 Kayu Kelas III m³ 0.002 2,522,000.00 5,044.00
2 Paku 5 - 12 cm Kg 0.010 22,400.00 224.00
3 Minyak Bekisting Liter - 10,900.00 -
4 Besi Beton Polos Kg 3.000 15,900.00 47,700.00

223
5 Kawat Beton Kg 0.450 22,700.00 10,215.00
6 Semen Portland Kg 4.000 2,000.00 8,000.00
7 Pasir Beton m³ 0.006 187,900.00 1,127.40
8 Kerikil m³ 0.009 573,600.00 5,162.40
Jumlah Harga Bahan 77,472.80
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 128,535.50
E Overhead + Profit ( Contoh 15% ) 15% x D 19,280.33
F Harga Satuan Pekerjaan ( D + E ) 147,815.83

A.4.1.1.36. Membuat 1 m' ring balok beton bertulang ( 10 x 15 ) cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.297 111,700.00 33,174.90
2 Tukang Batu L.02 OH 0.033 135,070.00 4,457.31
3 Tukang Kayu L.02 OH 0.033 135,070.00 4,457.31
4 Tukang Besi L.02 OH 0.033 135,070.00 4,457.31
5 Kepala Tukang L.03 OH 0.010 140,740.00 1,407.40
6 Mandor L.04 OH 0.015 160,090.00 2,401.35
Jumlah Tenaga Kerja 50,355.58
B Bahan
1 Kayu Kelas III m³ 0.003 2,522,000.00 7,566.00
2 Paku 5 - 12 cm Kg 0.020 22,400.00 448.00
3 Minyak Bekisting Liter - 10,900.00 -
4 Besi Beton Polos Kg 3.600 15,900.00 57,240.00
5 Kawat Beton Kg 0.050 22,700.00 1,135.00
6 Semen Portland Kg 5.500 2,000.00 11,000.00
7 Pasir Beton m³ 0.009 187,900.00 1,691.10
8 Kerikil m³ 0.015 573,600.00 8,604.00
Jumlah Harga Bahan 87,684.10
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 138,039.68
E Overhead + Profit ( Contoh 15% ) 15% x D 20,705.95
F Harga Satuan Pekerjaan ( D + E ) 158,745.63

A.4.1.2. HARGA SATUAN PEKERJAAN BETON PRACETAK


A.4.1.2.1. Pembuatan 1 m² lahan produksi tebal 8 cm beton f'c 14,5 Mpa ( K - 175 ) slump ( 12 ± 2 ) cm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.132 111,700.00 14,744.40
2 Tukang Batu L.02 OH 0.022 135,070.00 2,971.54
3 Kepala Tukang L.03 OH 0.002 140,740.00 281.48
4 Mandor L.04 OH 0.007 160,090.00 1,120.63

224
Jumlah Tenaga Kerja 19,118.05
B Bahan
1 Semen Portland Kg 26.080 2,000.00 52,160.00
2 Pasir Beton Kg 60.800 187,900.00 11,424,320.00
3 Kerikil ( Maks 30mm ) Kg 82.320 573,600.00 47,218,752.00
4 Air Liter 17.200 53.00 911.60
Jumlah Harga Bahan 58,696,143.60
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 58,715,261.65
E Overhead + Profit ( Contoh 15% ) 15% x D 8,807,289.25
F Harga Satuan Pekerjaan ( D + E ) 67,522,550.90

A.4.1.2.2. Pembuatan 1 m² lahan produksi tebal 10 cm beton f'c 14,5 Mpa ( K - 175 ) slump ( 12 ± 2 ) cm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.165 111,700.00 18,430.50
2 Tukang Batu L.02 OH 0.028 135,070.00 3,781.96
3 Kepala Tukang L.03 OH 0.003 140,740.00 422.22
4 Mandor L.04 OH 0.008 160,090.00 1,280.72
Jumlah Tenaga Kerja 23,915.40
B Bahan
1 Semen Portland Kg 32.600 2,000.00 65,200.00
2 Pasir Beton Kg 76.000 187,900.00 14,280,400.00
3 Kerikil ( Maks 30mm ) Kg 102.900 573,600.00 59,023,440.00
4 Air Liter 21.500 53.00 1,139.50
Jumlah Harga Bahan 73,370,179.50
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 73,394,094.90
E Overhead + Profit ( Contoh 15% ) 15% x D 11,009,114.24
F Harga Satuan Pekerjaan ( D + E ) 84,403,209.14

A.4.1.2.3. Pembuatan 1 m² lahan produksi tebal 12 cm beton f'c 14,5 Mpa ( K - 175 ) slump ( 12 ± 2 ) cm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.198 111,700.00 22,116.60
2 Tukang Batu L.02 OH 0.033 135,070.00 4,457.31
3 Kepala Tukang L.03 OH 0.003 140,740.00 422.22
4 Mandor L.04 OH 0.010 160,090.00 1,600.90
Jumlah Tenaga Kerja 28,597.03
B Bahan
1 Semen Portland Kg 32.120 2,000.00 64,240.00
2 Pasir Beton Kg 91.200 187,900.00 17,136,480.00
3 Kerikil ( Maks 30mm ) Kg 123.480 573,600.00 70,828,128.00
4 Air Liter 25.800 53.00 1,367.40
Jumlah Harga Bahan 88,030,215.40

225
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 88,058,812.43
E Overhead + Profit ( Contoh 15% ) 15% x D 13,208,821.86
F Harga Satuan Pekerjaan ( D + E ) 101,267,634.29

A.4.1.2.4. Pembuatan 1 m² lahan produksi tebal 15 cm beton f'c 14,5 Mpa ( K - 175 ) slump ( 12 ± 2 ) cm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.248 111,700.00 27,701.60
2 Tukang Batu L.02 OH 0.041 135,070.00 5,537.87
3 Kepala Tukang L.03 OH 0.004 140,740.00 562.96
4 Mandor L.04 OH 0.013 160,090.00 2,081.17
Jumlah Tenaga Kerja 35,883.60
B Bahan
1 Semen Portland Kg 48.900 2,000.00 97,800.00
2 Pasir Beton Kg 114.000 187,900.00 21,420,600.00
3 Kerikil ( Maks 30mm ) Kg 154.350 573,600.00 88,535,160.00
4 Air Liter 32.250 53.00 1,709.25
Jumlah Harga Bahan 110,055,269.25
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 110,091,152.85
E Overhead + Profit ( Contoh 15% ) 15% x D 16,513,672.93
F Harga Satuan Pekerjaan ( D + E ) 126,604,825.78

A.4.1.2.5. Pebuatan 1 m² bekisting untuk plat beton pracetak ( 5 kali pakai )


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.007 -
2 Tukang Batu L.02 OH 0.076 -
3 Kepala Tukang L.03 OH 0.008 -
4 Mandor L.04 OH 0.001 -
Jumlah Tenaga Kerja -
B Bahan
1 Lantai kerja tebal 10 cm m³ 0.080 - -
2 Besi hollow 50.50.3 Kg 9.394 - -
3 Kayu kaso 5/7 m³ 0.005 - -
4 Phenol film 12 mm Lembar 0.080 - -
5 Minyak bekisting Liter 0.200 - -
6 Dinabolt Ø12 mm (10 - 15 - -
Buah 3.882
7 cm ) - -
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -

226
F Harga Satuan Pekerjaan ( D + E ) -

A.4.1.2.6. Pebuatan 1 m² bekisting untuk balok beton pracetak ( 10 - 12 kali pakai )


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.004 - -
2 Tukang Batu L.02 OH 0.038 - -
3 Kepala Tukang L.03 OH 0.004 - -
4 Mandor L.04 OH 0.001 - -
Jumlah Tenaga Kerja -
B Bahan
1 Kayu kaso 5/7 m³ 0.005 - -
2 Phenol film 12 mm Lembar 0.043 - -
3 Minyak bekisting Liter 0.200 - -
4 Dinabolt Ø12 mm (10 - 15 - -
Buah 0.693
cm ) - -
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.1.2.7. Pebuatan 1 m² bekisting untuk kolom beton pracetak ( 10 - 12 kali pakai )


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.004 - -
2 Tukang Batu L.02 OH 0.038 - -
3 Kepala Tukang L.03 OH 0.004 - -
4 Mandor L.04 OH 0.001 - -
Jumlah Tenaga Kerja -
B Bahan
1 Kayu kaso 5/7 m³ 0.004 - -
2 Phenol film 12 mm Lembar 0.048 - -
3 Minyak bekisting Liter 0.200 - -
4 Dinabolt Ø12 mm (10 - 15 - -
Buah 0.693
cm ) - -
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.1.2.8. Pemasangan dan membuka bekisting 1 buah komponen plat beton pracetak
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )

227
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.053 - -
2 TukangKayu L.02 OH 0.018 - -
4 Mandor L.04 OH 0.005 - -
Jumlah Tenaga Kerja -
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.1.2.9. Pemasangan dan membuka bekisting 1 buah komponen balok beton pracetak
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.089 - -
2 TukangKayu L.02 OH 0.030 - -
4 Mandor L.04 OH 0.005 - -
Jumlah Tenaga Kerja -
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.1.2.10. Pemasangan dan membuka bekisting 1 buah komponen kolom beton pracetak
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.071 - -
2 TukangKayu L.02 OH 0.024 - -
4 Mandor L.04 OH 0.005 - -
Jumlah Tenaga Kerja -
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.1.2.11. Penuangan / menebar beton untuk 1 buah komponen plat pracetak


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )

228
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.064 - -
2 Tukang Batu L.02 OH 0.244 - -
3 Tukang Vibrator L.02 OH 0.128 - -
4 Kepala Tukang L.03 OH 0.034 - -
5 Mandor L.04 OH 0.073 - -
Jumlah Tenaga Kerja -
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.1.2.12. Penuangan / menebar beton untuk 1 buah komponen balok pracetak


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.069 - -
2 Tukang Batu L.02 OH 0.242 - -
3 Tukang Vibrator L.02 OH 0.138 - -
4 Kepala Tukang L.03 OH 0.037 - -
5 Mandor L.04 OH 0.073 - -
Jumlah Tenaga Kerja -
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.1.2.13. Penuangan / menebar beton untuk 1 buah komponen kolom pracetak


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.061 - -
2 Tukang Batu L.02 OH 0.213 - -
3 Tukang Vibrator L.02 OH 0.122 - -
4 Kepala Tukang L.03 OH 0.033 - -
5 Mandor L.04 OH 0.073 - -
Jumlah Tenaga Kerja -
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -

229
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.1.2.14. Mendirikan 1 buah komponen plat pracetak


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.067 - -
2 Tukang Batu L.02 OH 0.067 - -
3 Tukang Erection L.02 OH 0.134 - -
4 Kepala Tukang L.03 OH 0.067 - -
5 Mandor L.04 OH 0.067 - -
Jumlah Tenaga Kerja -
B Bahan
1 Solar Liter 6.676 - -
Jumlah Harga Bahan -
C Peralatan
1 Sewa Crane UH 0.067 - -
2 Sewa Pipe Support UH 1.100 - -
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.1.2.15. Mendirikan 1 buah komponen balok pracetak


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.061 - -
2 Tukang Batu L.02 OH 0.061 - -
3 Operator Crane L.02 OH 0.122 - -
4 Tukang Erection L.02 OH 0.061 - -
5 Pembantu operator crane L.02 OH 0.061 - -
6 Kepala Tukang L.03 OH 0.061 - -
7 Mandor L.04 OH 0.061 - -
Jumlah Tenaga Kerja -
B Bahan
1 Solar Liter 6.110 - -
Jumlah Harga Bahan -
C Peralatan
1 Sewa Crane UH 0.061 - -
2 Sewa Chaffolding UH 1.100 - -
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.1.2.16. Mendirikan 1 buah komponen kolom pracetak


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian

230
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.083 - -
2 Tukang Batu L.02 OH 0.083 - -
3 Operator Crane L.02 OH 0.166 - -
4 Tukang Erection L.02 OH 0.083 - -
5 Pembantu operator crane L.02 OH 0.083 - -
6 Kepala Tukang L.03 OH 0.083 - -
7 Mandor L.04 OH 0.083 - -
Jumlah Tenaga Kerja -
B Bahan
1 Solar Liter 8.277 - -
Jumlah Harga Bahan -
C Peralatan
1 Sewa Crane UH 0.083 - -
2 Sewa Pipe Support UH 2.200 - -
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.1.2.17. Melangsir 1 buah komponen plat pracetak ( ± 20 m )


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.019 - -
2 Tukang Batu L.02 OH 0.038 - -
3 Operator Crane L.02 OH 0.019 - -
4 Pembantu operator crane L.02 OH 0.019 - -
Jumlah Tenaga Kerja -
B Bahan
1 Solar Liter 1.897 - -
Jumlah Harga Bahan -
C Peralatan
1 Sewa Crane UH 0.019 - -
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.1.2.18. Melangsir 1 buah komponen balok pracetak ( ± 20 m )


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.019 - -
2 Tukang Batu L.02 OH 0.038 - -
3 Operator Crane L.02 OH 0.019 - -
4 Pembantu operator crane L.02 OH 0.019 - -

231
Jumlah Tenaga Kerja -
B Bahan
1 Solar Liter 1.897 - -
Jumlah Harga Bahan -
C Peralatan
1 Sewa Crane UH 0.019 - -
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.1.2.19. Melangsir 1 buah komponen kolom pracetak ( ± 20 m )


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.019 - -
2 Tukang Batu L.02 OH 0.038 - -
3 Operator Crane L.02 OH 0.019 - -
4 Pembantu operator crane L.02 OH 0.019 - -
Jumlah Tenaga Kerja -
B Bahan
1 Solar Liter 1.897 - -
Jumlah Harga Bahan -
C Peralatan
1 Sewa Crane UH 0.019 - -
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.2.1. HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM


A.4.2.1.1. Pemasangan 1 Kg besi profil
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.060 111,700.00 6,702.00
2 Tukang Las Konstruksi L.02 OH 0.060 135,070.00 8,104.20
3 Kepala Tukang L.03 OH 0.006 140,740.00 844.44
4 Mandor L.04 OH 0.003 160,090.00 480.27
Jumlah Tenaga Kerja 16,130.91
B Bahan
1 Besi Profil Kg 1.150 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509

232
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.2.1.2. Pemasangan 1 Kg rangka kuda-kuda baja IWF


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.060 111,700.00 6,702.00
2 Tukang Las Konstruksi L.02 OH 0.060 135,070.00 8,104.20
3 Kepala Tukang L.03 OH 0.006 140,740.00 844.44
4 Mandor L.04 OH 0.003 160,090.00 480.27
Jumlah Tenaga Kerja 16,130.91
B Bahan
1 Besi Baja Iwf Kg 1.150 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.2.1.3. Pengerjaan 100 Kg pekerjaan perakitan


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.100 111,700.00 11,170.00
2 Tukang Besi Konstruksi L.02 OH 0.100 135,070.00 13,507.00
3 Kepala Tukang L.03 OH 0.001 140,740.00 140.74
4 Mandor L.04 OH 0.005 160,090.00 800.45
Jumlah Tenaga Kerja 25,618.19
B Bahan
1 Solar Liter 1.000 Err:509 Err:509
2 Minyak Pelumas Liter 0.100 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
1 Sewa Alat Jam 0.800 - -
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.2.1.4. Pembuatan 1 m² pintu besi plat baja tebal 2 mm rangkap, rangka baja siku
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.050 - -
2 Tukang Las Biasa L.02 OH 1.050 - -
3 Kepala Tukang L.03 OH 0.105 - -
4 Mandor L.04 OH 0.052 - -

233
Jumlah Tenaga Kerja -
B Bahan
1 Besi Siku L 30.30.3 Kg 15.000 - -
2 Besi Plat Baja Kg 32.800 - -
3 Kawat Las KG 0.050 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.2.1.5. Pengerjaan 10 cm pengelasan dengan las listrik


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.040 111,700.00 4,468.00
2 Tukang Besi Konstruksi L.02 OH 0.020 135,070.00 2,701.40
3 Kepala Tukang L.03 OH 0.002 140,740.00 281.48
4 Mandor L.04 OH 0.002 160,090.00 320.18
Jumlah Tenaga Kerja 7,771.06
B Bahan
1 Kawat Las Listrik Kg 0.400 17,650.00 7,060.00
2 Solar Liter 0.300 Err:509 Err:509
3 Minyak Pelumas Liter 0.040 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
1 Sewa Alat Jam 0.170 - -
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.2.1.6. Pembuatan 1 m² rangka jendela besi scuare tube ( 25 x 5 ) cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.650 - -
2 Tukang Las Biasa L.02 OH 0.650 - -
3 Kepala Tukang L.03 OH 0.065 - -
4 Mandor L.04 OH 0.032 - -
Jumlah Tenaga Kerja -
B Bahan
1 Besi Scuare Tube m 4.760 - -
2 Besi Lis Kaca (1 x 1) cm m 4.522 - -
3 Pengelasan cm 20.000 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0

234
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.2.1.7. Pemasangan 1 m² pintu rolling door besi


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.200 111,700.00 134,040.00
2 Tukang Las Biasa L.02 OH 1.200 135,070.00 162,084.00
3 Kepala Tukang L.03 OH 0.120 140,740.00 16,888.80
4 Mandor L.04 OH 0.006 160,090.00 960.54
Jumlah Tenaga Kerja 313,973.34
B Bahan
1 Pintu Gulung Besi m 1.000 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.2.1.8. Pemasangan 1 m² pintu lipat ( folding door ) bahan plastik/PVC


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.440 - -
2 Tukang L.02 OH 0.440 - -
3 Kepala Tukang L.03 OH 0.044 - -
4 Mandor L.04 OH 0.022 - -
Jumlah Tenaga Kerja -
B Bahan
1 Pintu Lipat m² 1.000 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.2.1.9. Pemasangan 1 m² sunscreen alluminium


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.080 111,700.00 8,936.00
2 Tukang L.02 OH 0.800 135,070.00 108,056.00
3 Kepala Tukang L.03 OH 0.080 140,740.00 11,259.20
4 Mandor L.04 OH 0.004 160,090.00 640.36

235
Jumlah Tenaga Kerja 128,891.56
B Bahan
1 Sunscreen Alluminium m² 1.000 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.2.1.10. Pemasangan 1 m² rolling door alluminium


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.000 111,700.00 111,700.00
2 Tukang Khusus Alluinium L.02 OH 1.000 135,070.00 135,070.00
3 Kepala Tukang L.03 OH 0.100 140,740.00 14,074.00
4 Mandor L.04 OH 0.050 160,090.00 8,004.50
Jumlah Tenaga Kerja 268,848.50
B Bahan
1 Rolling Door Alluminium m² 1.000 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.2.1.11. Pemasangan 1 m kusen pintu alluminium


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.043 111,700.00 4,803.10
2 Tukang Khusus Alluinium L.02 OH 0.043 135,070.00 5,808.01
3 Kepala Tukang L.03 OH 0.0043 140,740.00 605.18
4 Mandor L.04 OH 0.0021 160,090.00 336.19
Jumlah Tenaga Kerja 11,552.48
B Bahan
1 Profil Alluminium m 1.100 Err:509 Err:509
2 Skrup Fixer Buah 2.000 Err:509 Err:509
3 Sealant Tube 0.060 30,000.00 1,800.00
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.2.1.12. Pemasangan 1 m² pintu alluminium strip lebar 8 cm

236
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.085 111,700.00 9,494.50
2 Tukang Khusus Alluinium L.02 OH 0.085 135,070.00 11,480.95
3 Kepala Tukang L.03 OH 0.0085 140,740.00 1,196.29
4 Mandor L.04 OH 0.0042 160,090.00 672.38
Jumlah Tenaga Kerja 22,844.12
B Bahan
1 Profil Alluminium m 4.400 Err:509 Err:509
2 Alluminium Strip m 14.600 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.2.1.13. Pemasangan 1 m² pintu pntu kaca rangka alluminium


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.085 111,700.00 9,494.50
2 Tukang Alluinium / Kaca L.02 OH 0.085 135,070.00 11,480.95
3 Kepala Tukang L.03 OH 0.0090 140,740.00 1,266.66
4 Mandor L.04 OH 0.0050 160,090.00 800.45
Jumlah Tenaga Kerja 23,042.56
B Bahan
1 Pintu Alluminium m 4.400 Err:509 Err:509
2 Profil Kaca m 4.500 179,600.00 808,200.00
3 Sealant Tube 0.270 30,000.00 8,100.00
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.2.1.14. Pemasangan 1 m² venetions blinds dan vertical blinds(Tirai)


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.350 111,700.00 39,095.00
2 Tukang L.02 OH 0.350 135,070.00 47,274.50
3 Kepala Tukang L.03 OH 0.0350 140,740.00 4,925.90
4 Mandor L.04 OH 0.0180 160,090.00 2,881.62
Jumlah Tenaga Kerja 94,177.02
B Bahan

237
1 venetions blinds dan vertical
m 4.400 Err:509 Err:509
blinds(Tirai)
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.2.1.15. Pemasangan 1 m² terali besi strip ( 2 x 3 ) mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.670 -
2 Tukang Las L.02 OH 1.670 -
3 Kepala Tukang L.03 OH 0.1670 -
4 Mandor L.04 OH 0.0830 -
Jumlah Tenaga Kerja -
B Bahan
1 venetions blinds dan vertical
m 4.400 - -
blinds(Tirai)
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.2.1.16. Pemasangan 1 m² kawat nyamuk


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.100 111,700.00 11,170.00
2 Tukang L.02 OH 0.100 135,070.00 13,507.00
3 Kepala Tukang L.03 OH 0.0100 140,740.00 1,407.40
4 Mandor L.04 OH 0.0050 160,090.00 800.45
Jumlah Tenaga Kerja 26,884.85
B Bahan
1 Kawat Nyamuk m² 1.100 Err:509 Err:509
2 Pengelasan cm 11.110 Err:509 Err:509
3 Baja Strip ( 0.2 x 2 ) cm Kg 1.716 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.2.1.17. Pemasangan 1 m² jendela naco & tralis

238
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.200 - -
2 Tukang L.02 OH 0.200 - -
3 Kepala Tukang L.03 OH 0.0200 - -
4 Mandor L.04 OH 0.0010 - -
Jumlah Tenaga Kerja -
B Bahan
1 Jendela Naco ( Rangka +
m² 1.100 - -
Kaca 5 mm )
2 Paku Skrup 1 cm - 2.5 cm Buah 10.000
3 Besi Strip m 7.000
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.2.1.18. Pemasangan 1 m¹ talang dasar / jurai seng bjls 28 lebar 90 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.200 111,700.00 22,340.00
2 Tukang L.02 OH 0.200 135,070.00 27,014.00
3 Kepala Tukang L.03 OH 0.0200 140,740.00 2,814.80
4 Mandor L.04 OH 0.0010 160,090.00 160.09
Jumlah Tenaga Kerja 52,328.89
B Bahan
1 Seng Plat m³ 1.050 Err:509 Err:509
2 Paku 1 cm - 2,5 cm Kg 0.015 22,400.00 336.00
3 Papan Kayu Kelas II / III m³ 0.019 3,007,000.00 57,133.00
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.2.1.19. Pemasangan 1 m¹ talang ½ lingkaran Ø15 cm, seng plat bjls 30 lebar 45 cm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.150 111,700.00 16,755.00
2 Tukang L.02 OH 0.300 135,070.00 40,521.00
3 Kepala Tukang L.03 OH 0.0300 140,740.00 4,222.20
4 Mandor L.04 OH 0.0080 160,090.00 1,280.72

239
Jumlah Tenaga Kerja 62,778.92
B Bahan
1 Seng Plat m³ 1.050 Err:509 Err:509
2 Paku 1 cm - 2,5 cm Kg 0.010 22,400.00 224.00
3 Besi Strip Kg 0.500 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.2.1.20. Pemasangan 1 m² rangka besi holow 1 x 40 x 40 x 2 mm, modul 60 x 120 cm, dinding partisi
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.250 111,700.00 27,925.00
2 Tukang Besi L.02 OH 0.250 135,070.00 33,767.50
3 Kepala Tukang L.03 OH 0.0250 140,740.00 3,518.50
4 Mandor L.04 OH 0.0130 160,090.00 2,081.17
Jumlah Tenaga Kerja 67,292.17
B Bahan
1 Rangka Metal Hollow 40.40.2
m¹ 1.050 41,250.00 43,312.50
mm
2 Assesoris ( Perkuatan, Las dll 100% x
Ls 41,250.00 41,250.00
) Rangka
Jumlah Harga Bahan 84,562.50
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 151,854.67
E Overhead + Profit ( Contoh 15% ) 15% x D 22,778.20
F Harga Satuan Pekerjaan ( D + E ) 174,632.87

A.4.2.1.21. Pemasangan 1 m² rangka besi holow 1 x 40 x 40 x 2 mm, modul 60 x 60 cm, plafond


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.350 111,700.00 39,095.00
2 Tukang Besi L.02 OH 0.350 135,070.00 47,274.50
3 Kepala Tukang L.03 OH 0.0350 140,740.00 4,925.90
4 Mandor L.04 OH 0.0180 160,090.00 2,881.62
Jumlah Tenaga Kerja 94,177.02
B Bahan
1 Rangka Metal Hollow 40.40.2
m¹ 4.000 41,250.00 165,000.00
mm
2 Assesoris ( Perkuatan, Las dll 100% x
Ls 41,250.00 41,250.00
) Rangka
Jumlah Harga Bahan 206,250.00
C Peralatan

240
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 300,427.02
E Overhead + Profit ( Contoh 15% ) 15% x D 45,064.05
F Harga Satuan Pekerjaan ( D + E ) 345,491.07

A.4.2.1.21. Pemasangan 1 m2 kuda-kuda baja ringan + reng untuk atap genteng metal
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.200 111,700.00 22,340.00
2 Tukang Besi L.02 OH 0.450 135,070.00 60,781.50
3 Kepala Tukang L.03 OH 0.0100 140,740.00 1,407.40
4 Mandor L.04 OH 0.0500 160,090.00 8,004.50
Jumlah Tenaga Kerja 92,533.40
B Bahan
1 C-75. 0,8 m2 1.488 18,333.33 27,280.00
2 C-75. 0,6 m2 2.232 18,333.33 40,920.00
3 Baut bh 28.000 575.00 16,100.00
4 Dynabolt bh 1.600 4,000.00 6,400.00
5 Reng m' 3.600 12,500.00 45,000.00
6 Talang jurai m' 0.124 50,000.00 6,200.00
Jumlah Harga Bahan 141,900.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 234,433.40
E Overhead + Profit ( Contoh 15% ) 15% x D 35,165.01
F Harga Satuan Pekerjaan ( D + E ) 269,598.41

A.4.4.1. HARGA SATUAN PEKERJAAN PASANGAN DINDING


A.4.4.1.1. Pemasangan 1 m² dinding bata merah ( 5 x 11 x 22 ) cm tebal 1 batu campuran 1 SP : 2 PP
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.600 - -
2 Tukang Batu L.02 OH 0.200 - -
3 Kepala Tukang L.03 OH 0.020 - -
4 Mandor L.04 OH 0.030 - -
Jumlah Tenaga Kerja -
B Bahan
1 Bata Merah m³ 140.000 - -
2 Semen Portland Kg 43.500 - -
3 Pasir Pasang m³ 0.080 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -

241
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.1.1. Pemasangan 1 m² dinding bata merah (9 x 9 x 18 ) cm tebal 1 batu campuran 1 SP : 2 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 111,700.00 55,850.00
2 Tukang Batu L.02 OH 0.020 135,070.00 2,701.40
3 Kepala Tukang L.03 OH 0.020 140,740.00 2,814.80
4 Mandor L.04 OH 0.025 160,090.00 4,002.25
Jumlah Tenaga Kerja 65,368.45
B Bahan
1 Bata Merah m³ 110.000 900.00 99,000.00
2 Semen Portland Kg 34.179 2,000.00 68,357.14
3 Pasir Pasang m³ 0.063 187,900.00 11,810.86
Jumlah Harga Bahan 179,168.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 244,536.45
E Overhead + Profit ( Contoh 15% ) 15% x D 36,680.47
F Harga Satuan Pekerjaan ( D + E ) 281,216.92

A.4.4.1.2. Pemasangan 1 m² dinding bata merah ( 5 x 11 x 22 ) cm tebal 1 batu campuran 1 SP : 3 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.600 - -
2 Tukang Batu L.02 OH 0.200 - -
3 Kepala Tukang L.03 OH 0.020 - -
4 Mandor L.04 OH 0.030 - -
Jumlah Tenaga Kerja -
B Bahan
1 Bata Merah m³ 140.000 - -
2 Semen Portland Kg 32.950 - -
3 Pasir Pasang m³ 0.091 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.1.3. Pemasangan 1 m² dinding bata merah ( 5 x 11 x 22 ) cm tebal 1 batu campuran 1 SP : 4 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.600 - -

242
2 Tukang Batu L.02 OH 0.200 - -
3 Kepala Tukang L.03 OH 0.020 - -
4 Mandor L.04 OH 0.030 - -
Jumlah Tenaga Kerja -
B Bahan
1 Bata Merah m³ 140.000 - -
2 Semen Portland Kg 26.550 - -
3 Pasir Pasang m³ 0.093 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.1.3. Pemasangan 1 m² dinding bata merah ( 9 x 9 x 18 ) cm tebal 1 batu campuran 1 SP : 4 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 111,700.00 55,850.00
2 Tukang Batu L.02 OH 0.200 135,070.00 27,014.00
3 Kepala Tukang L.03 OH 0.020 140,740.00 2,814.80
4 Mandor L.04 OH 0.025 160,090.00 4,002.25
Jumlah Tenaga Kerja 89,681.05
B Bahan
1 Bata Merah m2 110.000 900.00 99,000.00
2 Semen Portland Kg 20.861 2,000.00 41,721.43
3 Pasir Pasang m³ 0.073 187,900.00 13,730.12
Jumlah Harga Bahan 154,451.55
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 244,132.60
E Overhead + Profit ( Contoh 15% ) 15% x D 36,619.89
F Harga Satuan Pekerjaan ( D + E ) 280,752.49

A.4.4.1.4. Pemasangan 1 m² dinding bata merah ( 5 x 11 x 22 ) cm tebal 1 batu campuran 1 SP : 5 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.600 - -
2 Tukang Batu L.02 OH 0.200 - -
3 Kepala Tukang L.03 OH 0.020 - -
4 Mandor L.04 OH 0.030 - -
Jumlah Tenaga Kerja -
B Bahan
1 Bata Merah m³ 140.000 - -
2 Semen Portland Kg 22.200 - -
3 Pasir Pasang m³ 0.102 - -
Jumlah Harga Bahan -

243
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.1.5. Pemasangan 1 m² dinding bata merah ( 5 x 11 x 22 ) cm tebal 1 batu campuran 1 SP : 6 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.600 - -
2 Tukang Batu L.02 OH 0.200 - -
3 Kepala Tukang L.03 OH 0.020 - -
4 Mandor L.04 OH 0.030 - -
Jumlah Tenaga Kerja -
B Bahan
1 Bata Merah m³ 140.000 - -
2 Semen Portland Kg 18.500 - -
3 Pasir Pasang m³ 0.122 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.1.6. Pemasangan 1 m² dinding bata merah ( 5 x 11 x 22 ) cm tebal 1 batu campuran 1 SP : 3 KP : 10 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.600 - -
2 Tukang Batu L.02 OH 0.200 - -
3 Kepala Tukang L.03 OH 0.020 - -
4 Mandor L.04 OH 0.030 - -
Jumlah Tenaga Kerja -
B Bahan
1 Bata Merah m³ 140.000 - -
2 Semen Portland Kg 10.080 - -
3 Kapur Padam m³ 0.0275 - -
4 Pasir Pasang m³ 0.0925 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.1.7. Pemasangan 1 m² dinding bata merah ( 5 x 11 x 22 ) cm tebal ½ batu campuran 1 SP : 2 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian

244
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 - -
2 Tukang Batu L.02 OH 0.100 - -
3 Kepala Tukang L.03 OH 0.010 - -
4 Mandor L.04 OH 0.015 - -
Jumlah Tenaga Kerja -
B Bahan
1 Bata Merah m³ 70.000 - -
2 Semen Portland Kg 18.950 - -
3 Pasir Pasang m³ 0.0380 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.1.7. Pemasangan 1 m² dinding bata merah ( 9 x 9 x 18 ) cm tebal ½ batu campuran 1 SP : 2 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.236 111,700.00 26,329.29
2 Tukang Batu L.02 OH 0.079 135,070.00 10,612.64
3 Kepala Tukang L.03 OH 0.008 140,740.00 1,105.81
4 Mandor L.04 OH 0.012 160,090.00 1,886.78
Jumlah Tenaga Kerja 39,934.52
B Bahan
1 Bata Merah m³ 55.000 900.00 49,500.00
2 Semen Portland Kg 14.889 2,000.00 29,778.57
3 Pasir Pasang m³ 0.0299 187,900.00 5,610.16
Jumlah Harga Bahan 84,888.73
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 124,823.25
E Overhead + Profit ( Contoh 15% ) 15% x D 18,723.49
F Harga Satuan Pekerjaan ( D + E ) 143,546.73

A.4.4.1.8. Pemasangan 1 m² dinding bata merah ( 5 x 11 x 22 ) cm tebal ½ batu campuran 1 SP : 3 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 - -
2 Tukang Batu L.02 OH 0.100 - -
3 Kepala Tukang L.03 OH 0.010 - -
4 Mandor L.04 OH 0.015 - -
Jumlah Tenaga Kerja -
B Bahan

245
1 Bata Merah m³ 70.000 - -
2 Semen Portland Kg 14.370 - -
3 Pasir Pasang m³ 0.0400 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.1.9. Pemasangan 1 m² dinding bata merah ( 5 x 11 x 22 ) cm tebal ½ batu campuran 1 SP : 4 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 - -
2 Tukang Batu L.02 OH 0.100 - -
3 Kepala Tukang L.03 OH 0.010 - -
4 Mandor L.04 OH 0.015 - -
Jumlah Tenaga Kerja -
B Bahan
1 Bata Merah m³ 70.000 - -
2 Semen Portland Kg 11.500 - -
3 Pasir Pasang m³ 0.0430 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.1.9. Pemasangan 1 m² dinding bata merah ( 5 x 11 x 22 ) cm tebal ½ batu campuran 1 SP : 4 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.236 111,700.00 26,329.29
2 Tukang Batu L.02 OH 0.079 135,070.00 10,612.64
3 Kepala Tukang L.03 OH 0.008 140,740.00 1,105.81
4 Mandor L.04 OH 0.012 160,090.00 1,886.78
Jumlah Tenaga Kerja 39,934.52
B Bahan
1 Bata Merah m³ 55.000 900.00 49,500.00
2 Semen Portland Kg 9.036 2,000.00 18,071.43
3 Pasir Pasang m³ 0.0338 187,900.00 6,348.34
Jumlah Harga Bahan 73,919.76
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 113,854.28
E Overhead + Profit ( Contoh 15% ) 15% x D 17,078.14
F Harga Satuan Pekerjaan ( D + E ) 130,932.42

246
A.4.4.1.10. Pemasangan 1 m² dinding bata merah ( 5 x 11 x 22 ) cm tebal ½ batu campuran 1 SP : 5 PP
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 - -
2 Tukang Batu L.02 OH 0.100 - -
3 Kepala Tukang L.03 OH 0.010 - -
4 Mandor L.04 OH 0.015 - -
Jumlah Tenaga Kerja -
B Bahan
1 Bata Merah m³ 70.000 - -
2 Semen Portland Kg 9.680 - -
3 Pasir Pasang m³ 0.0450 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.1.11. Pemasangan 1 m² dinding bata merah ( 5 x 11 x 22 ) cm tebal ½ batu campuran 1 SP : 6 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 - -
2 Tukang Batu L.02 OH 0.100 - -
3 Kepala Tukang L.03 OH 0.010 - -
4 Mandor L.04 OH 0.015 - -
Jumlah Tenaga Kerja -
B Bahan
1 Bata Merah m³ 70.000 - -
2 Semen Portland Kg 8.320 - -
3 Pasir Pasang m³ 0.0490 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.1.12. Pemasangan 1 m² dinding bata merah ( 5 x 11 x 22 ) cm tebal ½ batu campuran 1 SP : 8 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 - -
2 Tukang Batu L.02 OH 0.100 - -
3 Kepala Tukang L.03 OH 0.010 - -
4 Mandor L.04 OH 0.015 - -

247
Jumlah Tenaga Kerja -
B Bahan
1 Bata Merah m³ 70.000 - -
2 Semen Portland Kg 6.500 - -
3 Pasir Pasang m³ 0.0500 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.1.13. Pemasangan 1 m² dinding bata merah ( 5 x 11 x 22 ) cm tebal ½ batu campuran 1 SP : 3 KP : 10 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 - -
2 Tukang Batu L.02 OH 0.100 - -
3 Kepala Tukang L.03 OH 0.010 - -
4 Mandor L.04 OH 0.015 - -
Jumlah Tenaga Kerja -
B Bahan
1 Bata Merah m³ 70.000 - -
2 Semen Portland Kg 4.500 - -
3 Kapur Padam m³ 0.0150 - -
4 Pasir Pasang m³ 0.0500 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.1.22. Pemasangan 1 m² dinding terawang ( rooster ) 12 x 11 x 24 campuran 1 SP : 3 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 - -
2 Tukang Batu L.02 OH 0.100 - -
3 Kepala Tukang L.03 OH 0.010 - -
4 Mandor L.04 OH 0.015 - -
Jumlah Tenaga Kerja -
B Bahan
1 Bata Rooster m³ 30.000 - -
2 Semen Portland Kg 11.000 - -
3 Pasir Pasang m³ 0.0350 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0

248
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.1.23. Pemasangan 1 m² dinding terawang ( rooster ) 12 x 11 x 24 campuran 1 SP : 4 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 111,700.00 33,510.00
2 Tukang Batu L.02 OH 0.100 135,070.00 13,507.00
3 Kepala Tukang L.03 OH 0.010 140,740.00 1,407.40
4 Mandor L.04 OH 0.015 160,090.00 2,401.35
Jumlah Tenaga Kerja 50,825.75
B Bahan
1 Bata Rooster m³ 30.000 Err:509 Err:509
2 Semen Portland Kg 11.000 2,000.00 22,000.00
3 Pasir Pasang m³ 0.0350 187,900.00 6,576.50
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.4.1.24. Pemasangan 1 m² dinding bata berongga ekspose 12 x 11 x 24 campuran 1 SP : 3 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 - -
2 Tukang Batu L.02 OH 0.150 - -
3 Kepala Tukang L.03 OH 0.015 - -
4 Mandor L.04 OH 0.015 - -
Jumlah Tenaga Kerja -
B Bahan
1 Bata Rooster m³ 70.000 - -
2 Semen Portland Kg 14.000 - -
3 Pasir Pasang m³ 0.0320 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.2. HARGA SATUAN PEKERJAAN PLESTERAN


A.4.4.2.1. Pemasangan 1 m² plesteran 1 SP : 1 PP tebal 15 mm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian

249
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 111,700.00 33,510.00
2 Tukang Batu L.02 OH 0.150 135,070.00 20,260.50
3 Kepala Tukang L.03 OH 0.015 140,740.00 2,111.10
4 Mandor L.04 OH 0.015 160,090.00 2,401.35
Jumlah Tenaga Kerja 58,282.95
B Bahan
1 Semen Portland Kg 15.504 2,000.00 31,008.00
2 Pasir Pasang m³ 0.016 187,900.00 3,006.40
Jumlah Harga Bahan 34,014.40
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 92,297.35
E Overhead + Profit ( Contoh 15% ) 15% x D 13,844.60
F Harga Satuan Pekerjaan ( D + E ) 106,141.95
`
A.4.4.2.2. Pemasangan 1 m² plesteran 1 SP : 2 PP tebal 15 mm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 111,700.00 33,510.00
2 Tukang Batu L.02 OH 0.150 135,070.00 20,260.50
3 Kepala Tukang L.03 OH 0.015 140,740.00 2,111.10
4 Mandor L.04 OH 0.015 160,090.00 2,401.35
Jumlah Tenaga Kerja 58,282.95
B Bahan
1 Semen Portland Kg 10.224 2,000.00 20,448.00
2 Pasir Pasang m³ 0.020 187,900.00 3,758.00
Jumlah Harga Bahan 24,206.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 82,488.95
E Overhead + Profit ( Contoh 15% ) 15% x D 12,373.34
F Harga Satuan Pekerjaan ( D + E ) 94,862.29

A.4.4.2.3. Pemasangan 1 m² plesteran 1 SP : 3 PP tebal 15 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 111,700.00 33,510.00
2 Tukang Batu L.02 OH 0.150 135,070.00 20,260.50
3 Kepala Tukang L.03 OH 0.015 140,740.00 2,111.10
4 Mandor L.04 OH 0.015 160,090.00 2,401.35
Jumlah Tenaga Kerja 58,282.95
B Bahan
1 Semen Portland Kg 7.776 2,000.00 15,552.00
2 Pasir Pasang m³ 0.023 187,900.00 4,321.70

250
Jumlah Harga Bahan 19,873.70
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 78,156.65
E Overhead + Profit ( Contoh 15% ) 15% x D 11,723.50
F Harga Satuan Pekerjaan ( D + E ) 89,880.15

A.4.4.2.4. Pemasangan 1 m² plesteran 1 SP : 4 PP tebal 15 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 111,700.00 33,510.00
2 Tukang Batu L.02 OH 0.150 135,070.00 20,260.50
3 Kepala Tukang L.03 OH 0.015 140,740.00 2,111.10
4 Mandor L.04 OH 0.015 160,090.00 2,401.35
Jumlah Tenaga Kerja 58,282.95
B Bahan
1 Semen Portland Kg 6.240 2,000.00 12,480.00
2 Pasir Pasang m³ 0.024 187,900.00 4,509.60
Jumlah Harga Bahan 16,989.60
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 75,272.55
E Overhead + Profit ( Contoh 15% ) 15% x D 11,290.88
F Harga Satuan Pekerjaan ( D + E ) 86,563.43

A.4.4.2.5. Pemasangan 1 m² plesteran 1 SP : 5 PP tebal 15 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 111,700.00 33,510.00
2 Tukang Batu L.02 OH 0.150 135,070.00 20,260.50
3 Kepala Tukang L.03 OH 0.015 140,740.00 2,111.10
4 Mandor L.04 OH 0.015 160,090.00 2,401.35
Jumlah Tenaga Kerja 58,282.95
B Bahan
1 Semen Portland Kg 5.184 2,000.00 10,368.00
2 Pasir Pasang m³ 0.026 187,900.00 4,885.40
Jumlah Harga Bahan 15,253.40
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 73,536.35
E Overhead + Profit ( Contoh 15% ) 15% x D 11,030.45
F Harga Satuan Pekerjaan ( D + E ) 84,566.80

A.4.4.2.6. Pemasangan 1 m² plesteran 1 SP : 6 PP tebal 15 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7

251
A Tenaga
1 Pekerja L.01 OH 0.300 111,700.00 33,510.00
2 Tukang Batu L.02 OH 0.150 135,070.00 20,260.50
3 Kepala Tukang L.03 OH 0.015 140,740.00 2,111.10
4 Mandor L.04 OH 0.015 160,090.00 2,401.35
Jumlah Tenaga Kerja 58,282.95
B Bahan
1 Semen Portland Kg 4.416 2,000.00 8,832.00
2 Pasir Pasang m³ 0.027 187,900.00 5,073.30
Jumlah Harga Bahan 13,905.30
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 72,188.25
E Overhead + Profit ( Contoh 15% ) 15% x D 10,828.24
F Harga Satuan Pekerjaan ( D + E ) 83,016.49

A.4.4.2.7. Pemasangan 1 m² plesteran 1 SP : 7 PP tebal 15 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 111,700.00 33,510.00
2 Tukang Batu L.02 OH 0.150 135,070.00 20,260.50
3 Kepala Tukang L.03 OH 0.015 140,740.00 2,111.10
4 Mandor L.04 OH 0.015 160,090.00 2,401.35
Jumlah Tenaga Kerja 58,282.95
B Bahan
1 Semen Portland Kg 3.936 2,000.00 7,872.00
2 Pasir Pasang m³ 0.028 187,900.00 5,261.20
Jumlah Harga Bahan 13,133.20
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 71,416.15
E Overhead + Profit ( Contoh 15% ) 15% x D 10,712.42
F Harga Satuan Pekerjaan ( D + E ) 82,128.57

A.4.4.2.8. Pemasangan 1 m² plesteran 1 SP : 8 PP tebal 15 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 111,700.00 33,510.00
2 Tukang Batu L.02 OH 0.150 135,070.00 20,260.50
3 Kepala Tukang L.03 OH 0.015 140,740.00 2,111.10
4 Mandor L.04 OH 0.015 160,090.00 2,401.35
Jumlah Tenaga Kerja 58,282.95
B Bahan
1 Semen Portland Kg 3.456 2,000.00 6,912.00
2 Pasir Pasang m³ 0.029 187,900.00 5,449.10
Jumlah Harga Bahan 12,361.10
C Peralatan

252
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 70,644.05
E Overhead + Profit ( Contoh 15% ) 15% x D 10,596.61
F Harga Satuan Pekerjaan ( D + E ) 81,240.66

A.4.4.2.9. Pemasangan 1 m² plesteran 1 SP : ½ KP : 3 PP tebal 15 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.360 - -
2 Tukang Batu L.02 OH 0.120 - -
3 Kepala Tukang L.03 OH 0.012 - -
4 Mandor L.04 OH 0.018 - -
Jumlah Tenaga Kerja -
B Bahan
1 Semen Portland Kg 5.760 - -
2 Kapur Padam m³ 0.003 - -
2 Pasir Pasang m³ 0.013 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.2.10. Pemasangan 1 m² plesteran 1 SP : 2 KP : 8 PP tebal 15 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.360 - -
2 Tukang Batu L.02 OH 0.120 - -
3 Kepala Tukang L.03 OH 0.012 - -
4 Mandor L.04 OH 0.018 - -
Jumlah Tenaga Kerja -
B Bahan
1 Semen Portland Kg 3.000 - -
2 Kapur Padam m³ 0.005 - -
2 Pasir Pasang m³ 0.020 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.2.13. Pemasangan 1 m² plesteran 1 SP : 1 PP tebal 20 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7

253
A Tenaga
1 Pekerja L.01 OH 0.400 111,700.00 44,680.00
2 Tukang Batu L.02 OH 0.200 135,070.00 27,014.00
3 Kepala Tukang L.03 OH 0.020 140,740.00 2,814.80
4 Mandor L.04 OH 0.022 160,090.00 3,521.98
Jumlah Tenaga Kerja 78,030.78
B Bahan
1 Semen Portland Kg 13.632 2,000.00 27,264.00
2 Pasir Pasang m³ 0.027 187,900.00 5,073.30
Jumlah Harga Bahan 32,337.30
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 110,368.08
E Overhead + Profit ( Contoh 15% ) 15% x D 16,555.21
F Harga Satuan Pekerjaan ( D + E ) 126,923.29

A.4.4.2.14. Pemasangan 1 m² plesteran 1 SP : 3 PP tebal 20 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.260 111,700.00 29,042.00
2 Tukang Batu L.02 OH 0.200 135,070.00 27,014.00
3 Kepala Tukang L.03 OH 0.020 140,740.00 2,814.80
4 Mandor L.04 OH 0.013 160,090.00 2,081.17
Jumlah Tenaga Kerja 60,951.97
B Bahan
1 Semen Portland Kg 10.368 2,000.00 20,736.00
2 Pasir Pasang m³ 0.031 187,900.00 5,824.90
Jumlah Harga Bahan 26,560.90
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 87,512.87
E Overhead + Profit ( Contoh 15% ) 15% x D 13,126.93
F Harga Satuan Pekerjaan ( D + E ) 100,639.80

A.4.4.2.15. Pemasangan 1 m² plesteran 1 SP : 4 PP tebal 20 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.400 111,700.00 44,680.00
2 Tukang Batu L.02 OH 0.200 135,070.00 27,014.00
3 Kepala Tukang L.03 OH 0.020 140,740.00 2,814.80
4 Mandor L.04 OH 0.022 160,090.00 3,521.98
Jumlah Tenaga Kerja 78,030.78
B Bahan
1 Semen Portland Kg 8.320 2,000.00 16,640.00
2 Pasir Pasang m³ 0.032 187,900.00 6,012.80
Jumlah Harga Bahan 22,652.80
C Peralatan

254
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 100,683.58
E Overhead + Profit ( Contoh 15% ) 15% x D 15,102.54
F Harga Satuan Pekerjaan ( D + E ) 115,786.12

A.4.4.2.16. Pemasangan 1 m² plesteran 1 SP : 5 PP tebal 20 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.400 111,700.00 44,680.00
2 Tukang Batu L.02 OH 0.200 135,070.00 27,014.00
3 Kepala Tukang L.03 OH 0.020 140,740.00 2,814.80
4 Mandor L.04 OH 0.022 160,090.00 3,521.98
Jumlah Tenaga Kerja 78,030.78
B Bahan
1 Semen Portland Kg 6.912 2,000.00 13,824.00
2 Pasir Pasang m³ 0.035 187,900.00 6,576.50
Jumlah Harga Bahan 20,400.50
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 98,431.28
E Overhead + Profit ( Contoh 15% ) 15% x D 14,764.69
F Harga Satuan Pekerjaan ( D + E ) 113,195.97

A.4.4.2.17. Pemasangan 1 m² plesteran 1 SP : 6 PP tebal 20 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.400 111,700.00 44,680.00
2 Tukang Batu L.02 OH 0.200 135,070.00 27,014.00
3 Kepala Tukang L.03 OH 0.020 140,740.00 2,814.80
4 Mandor L.04 OH 0.022 160,090.00 3,521.98
Jumlah Tenaga Kerja 78,030.78
B Bahan
1 Semen Portland Kg 5.888 2,000.00 11,776.00
2 Pasir Pasang m³ 0.036 187,900.00 6,764.40
Jumlah Harga Bahan 18,540.40
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 96,571.18
E Overhead + Profit ( Contoh 15% ) 15% x D 14,485.68
F Harga Satuan Pekerjaan ( D + E ) 111,056.86

A.4.4.2.23. Pemasangan 1 m² plesteran ciprat 1 SP : 2 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 111,700.00 33,510.00

255
2 Tukang Batu L.02 OH 0.100 135,070.00 13,507.00
3 Kepala Tukang L.03 OH 0.010 140,740.00 1,407.40
4 Mandor L.04 OH 0.015 160,090.00 2,401.35
Jumlah Tenaga Kerja 50,825.75
B Bahan
1 Semen Portland Kg 4.320 2,000.00 8,640.00
2 Pasir Pasang m³ 0.006 187,900.00 1,127.40
Jumlah Harga Bahan 9,767.40
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 60,593.15
E Overhead + Profit ( Contoh 15% ) 15% x D 9,088.97
F Harga Satuan Pekerjaan ( D + E ) 69,682.12

A.4.4.2.24. Pemasangan 1 m² fhinishingsiar pasangan bata merah


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.150 111,700.00 16,755.00
2 Tukang Batu L.02 OH 0.075 135,070.00 10,130.25
3 Kepala Tukang L.03 OH 0.008 140,740.00 1,125.92
4 Mandor L.04 OH 0.008 160,090.00 1,280.72
Jumlah Tenaga Kerja 29,291.89
B Bahan
1 Semen Portland Kg 3.108 2,000.00 6,216.00
Jumlah Harga Bahan 6,216.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 35,507.89
E Overhead + Profit ( Contoh 15% ) 15% x D 5,326.18
F Harga Satuan Pekerjaan ( D + E ) 40,834.07

A.4.4.2.26. Pemasangan 1 m² fhinishingsiar pasangan batu kali, campuran 1 SP : 2 PP


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 111,700.00 33,510.00
2 Tukang Batu L.02 OH 0.150 135,070.00 20,260.50
3 Kepala Tukang L.03 OH 0.015 140,740.00 2,111.10
4 Mandor L.04 OH 0.015 160,090.00 2,401.35
Jumlah Tenaga Kerja 58,282.95
B Bahan
1 Semen Portland Kg 6.340 2,000.00 12,680.00
2 Pasir Pasang m³ 0.012 187,900.00 2,254.80
Jumlah Harga Bahan 14,934.80
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 73,217.75
E Overhead + Profit ( Contoh 15% ) 15% x D 10,982.66

256
F Harga Satuan Pekerjaan ( D + E ) 84,200.41

A.4.4.2.27. Pemasangan 1 m² acian


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.200 111,700.00 22,340.00
2 Tukang Batu L.02 OH 0.100 135,070.00 13,507.00
3 Kepala Tukang L.03 OH 0.010 140,740.00 1,407.40
4 Mandor L.04 OH 0.010 160,090.00 1,600.90
Jumlah Tenaga Kerja 38,855.30
B Bahan
1 Semen Portland Kg 3.250 2,000.00 6,500.00
Jumlah Harga Bahan 6,500.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 45,355.30
E Overhead + Profit ( Contoh 15% ) 15% x D 6,803.30
F Harga Satuan Pekerjaan ( D + E ) 52,158.60

HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN


A.4.4.3.
DINDING
A.4.4.3.1. Pemasangan 1 m² lantai ubin PC abu-abu ukuran 40 cm x 40 cm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.250 - -
2 Tukang Batu L.02 OH 0.125 - -
3 Kepala Tukang L.03 OH 0.013 - -
4 Mandor L.04 OH 0.013 - -
Jumlah Tenaga Kerja -
B Bahan
1 Ubin abu-abu Bh 6.630 - -
2 Semen Portland Kg 9.800 - -
3 Pasir Pasang m³ 0.045 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.3.2. Pemasangan 1 m² lantai ubin PC abu-abu ukuran 30 cm x 30 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga

257
1 Pekerja L.01 OH 0.250 - -
2 Tukang Batu L.02 OH 0.125 - -
3 Kepala Tukang L.03 OH 0.013 - -
4 Mandor L.04 OH 0.013 - -
Jumlah Tenaga Kerja -
B Bahan
1 Ubin abu-abu Bh 11.870 - -
2 Semen Portland Kg 10.000 - -
3 Pasir Pasang m³ 0.045 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.3.3. Pemasangan 1 m² lantai ubin PC abu-abu ukuran 20 cm x 20 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.270 - -
2 Tukang Batu L.02 OH 0.135 - -
3 Kepala Tukang L.03 OH 0.014 - -
4 Mandor L.04 OH 0.014 - -
Jumlah Tenaga Kerja -
B Bahan
1 Ubin abu-abu Bh 26.500 - -
2 Semen Portland Kg 10.400 - -
3 Pasir Pasang m³ 0.045 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.3.4. Pemasangan 1 m² lantai ubin PC warna ukuran 40 cm x 40 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.250 - -
2 Tukang Batu L.02 OH 0.125 - -
3 Kepala Tukang L.03 OH 0.013 - -
4 Mandor L.04 OH 0.013 - -
Jumlah Tenaga Kerja -
B Bahan
1 Ubin Warna Bh 6.630 - -
2 Semen Portland Kg 9.800 - -
3 Semen Warna Kg 1.300 - -

258
4 Pasir Pasang m³ 0.045 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.3.5. Pemasangan 1 m² lantai ubin PC warna ukuran 30 cm x 30 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.260 - -
2 Tukang Batu L.02 OH 0.130 - -
3 Kepala Tukang L.03 OH 0.013 - -
4 Mandor L.04 OH 0.013 - -
Jumlah Tenaga Kerja -
B Bahan
1 Ubin Warna Bh 11.870 - -
2 Semen Portland Kg 10.000 - -
3 Semen Warna Kg 1.500 - -
4 Pasir Pasang m³ 0.045 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.3.6. Pemasangan 1 m² lantai ubin PC warna ukuran 20 cm x 20 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.270 - -
2 Tukang Batu L.02 OH 0.135 - -
3 Kepala Tukang L.03 OH 0.014 - -
4 Mandor L.04 OH 0.014 - -
Jumlah Tenaga Kerja -
B Bahan
1 Ubin Warna Bh 26.500 - -
2 Semen Portland Kg 10.400 - -
3 Semen Warna Kg 1.620 - -
4 Pasir Pasang m³ 0.045 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

259
A.4.4.3.7. Pemasangan 1 m² lantai ubin PC warna ukuran 20 cm x 20 cm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.270 - -
2 Tukang Batu L.02 OH 0.135 - -
3 Kepala Tukang L.03 OH 0.014 - -
4 Mandor L.04 OH 0.014 - -
Jumlah Tenaga Kerja -
B Bahan
1 Ubin Warna Bh 26.500 - -
2 Semen Portland Kg 10.400 - -
3 Semen Warna Kg 1.620 - -
4 Pasir Pasang m³ 0.045 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.3.32. Pemasangan 1 m² lantai keramik artistik ukuran 10 cm x 20 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.700 - -
2 Tukang Batu L.02 OH 0.350 - -
3 Kepala Tukang L.03 OH 0.035 - -
4 Mandor L.04 OH 0.035 - -
Jumlah Tenaga Kerja -
B Bahan
1 Ubin Keramik Bh 53.000 - -
2 Semen Portland Kg 8.190 - -
3 Pasir Pasang m³ 0.045 - -
4 Semen Warna Kg 2.750 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.3.33. Pemasangan 1 m² lantai keramik artistik ukuran 10 cm x 10 cm atau 5 cm x 20 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.700 - -

260
2 Tukang Batu L.02 OH 0.350 - -
3 Kepala Tukang L.03 OH 0.035 - -
4 Mandor L.04 OH 0.035 - -
Jumlah Tenaga Kerja -
B Bahan
1 Ubin Keramik Bh 106.000 - -
2 Semen Portland Kg 8.190 - -
3 Pasir Pasang m³ 0.045 - -
4 Semen Warna Kg 3.200 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.3.34. Pemasangan 1 m² lantai keramik ukuran 33 cm x 33 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.700 - -
2 Tukang Batu L.02 OH 0.350 - -
3 Kepala Tukang L.03 OH 0.035 - -
4 Mandor L.04 OH 0.035 - -
Jumlah Tenaga Kerja -
B Bahan
1 Ubin Keramik Bh 10.000 - -
2 Semen Portland Kg 8.190 - -
3 Pasir Pasang m³ 0.045 - -
4 Semen Warna Kg 1.620 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.3.35. Pemasangan 1 m² lantai keramik ukuran 30 cm x 30 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.700 111,700.00 78,190.00
2 Tukang Batu L.02 OH 0.350 135,070.00 47,274.50
3 Kepala Tukang L.03 OH 0.035 140,740.00 4,925.90
4 Mandor L.04 OH 0.035 160,090.00 5,603.15
Jumlah Tenaga Kerja 135,993.55
B Bahan
1 Ubin Keramik Bh 11.870 6,136.36 72,838.64
2 Semen Portland Kg 10.000 2,000.00 20,000.00

261
3 Pasir Pasang m³ 0.045 Err:509 Err:509
4 Semen Warna Kg 1.500 2,294.00 3,441.00
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.4.3.35. Pemasangan 1 m² lantai keramik ukuran 40c m x 40 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.700 111,700.00 78,190.00
2 Tukang Batu L.02 OH 0.350 135,070.00 47,274.50
3 Kepala Tukang L.03 OH 0.035 140,740.00 4,925.90
4 Mandor L.04 OH 0.035 160,090.00 5,603.15
Jumlah Tenaga Kerja 135,993.55
B Bahan
1 Ubin Keramik Bh 6.875 10,671.43 73,366.07
2 Semen Portland Kg 10.000 2,000.00 20,000.00
3 Pasir Pasang m³ 0.045 187,900.00 8,455.50
4 Semen Warna Kg 1.500 2,294.00 3,441.00
Jumlah Harga Bahan 105,262.57
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 241,256.12
E Overhead + Profit ( Contoh 10% ) 10% x D 24,125.61
F Harga Satuan Pekerjaan ( D + E ) 265,381.73

A.4.4.3.35. Pemasangan 1 m² lantai keramik ukuran 60 cm x 60 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.240 111,700.00 26,808.00
2 Tukang Batu L.02 OH 0.120 135,070.00 16,208.40
3 Kepala Tukang L.03 OH 0.012 140,740.00 1,688.88
4 Mandor L.04 OH 0.012 160,090.00 1,921.08
Jumlah Tenaga Kerja 46,626.36
B Bahan
1 Ubin Keramik Bh 3.100 112,333.33 348,233.33
2 Semen Portland Kg 9.600 2,000.00 19,200.00
3 Pasir Pasang m³ 0.045 187,900.00 8,455.50
4 Semen Warna Kg 1.500 2,294.00 3,441.00
Jumlah Harga Bahan 379,329.83
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 425,956.19
E Overhead + Profit ( Contoh 15% ) 15% x D 63,893.43

262
F Harga Satuan Pekerjaan ( D + E ) 489,849.62

A.4.4.3.36. Pemasangan 1 m² lantai keramik ukuran 20 cm x 20 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.700 111,700.00 78,190.00
2 Tukang Batu L.02 OH 0.350 135,070.00 47,274.50
3 Kepala Tukang L.03 OH 0.035 140,740.00 4,925.90
4 Mandor L.04 OH 0.035 160,090.00 5,603.15
Jumlah Tenaga Kerja 135,993.55
B Bahan
1 Ubin Keramik Bh 26.500 2,988.00 79,182.00
2 Semen Portland Kg 10.400 2,000.00 20,800.00
3 Pasir Pasang m³ 0.045 187,900.00 8,455.50
4 Semen Warna Kg 1.620 2,294.00 3,716.28
Jumlah Harga Bahan 112,153.78
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 248,147.33
E Overhead + Profit ( Contoh 15% ) 15% x D 37,222.10
F Harga Satuan Pekerjaan ( D + E ) 285,369.43

A.4.4.3.37. Pemasangan 1 m² lantai keramik ukuran 10 cm x 33 cm atau untuk variasi / border


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.050 111,700.00 117,285.00
2 Tukang Batu L.02 OH 0.525 135,070.00 70,911.75
3 Kepala Tukang L.03 OH 0.053 140,740.00 7,459.22
4 Mandor L.04 OH 0.053 160,090.00 8,484.77
Jumlah Tenaga Kerja 204,140.74
B Bahan
1 Ubin Keramik Bh 33.000 2,045.45 67,500.00
2 Semen Portland Kg 9.800 2,000.00 19,600.00
3 Pasir Pasang m³ 0.045 187,900.00 8,455.50
4 Semen Warna Kg 4.370 2,294.00 10,024.78
Jumlah Harga Bahan 105,580.28
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 309,721.02
E Overhead + Profit ( Contoh 15% ) 15% x D 46,458.15
F Harga Satuan Pekerjaan ( D + E ) 356,179.17

A.4.4.3.38. Pemasangan 1 m² lantai keramik mozaik ukuran 30 cm x 30 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga

263
1 Pekerja L.01 OH 0.700 - -
2 Tukang Batu L.02 OH 0.350 - -
3 Kepala Tukang L.03 OH 0.035 - -
4 Mandor L.04 OH 0.035 - -
Jumlah Tenaga Kerja -
B Bahan
1 Ubin Keramik Bh 11.870 - -
2 Semen Portland Kg 14.150 - -
3 Pasir Pasang m³ 0.039 - -
4 Semen Warna Kg 2.000 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.3.43. Pemasangan 1 m² lantai marmer ukuran 100 cm x 100 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.700 - -
2 Tukang Batu L.02 OH 0.350 - -
3 Kepala Tukang L.03 OH 0.035 - -
4 Mandor L.04 OH 0.035 - -
Jumlah Tenaga Kerja -
B Bahan
1 Marmer Bh 1.060 - -
2 Semen Portland Kg 8.190 - -
3 Pasir Pasang m³ 0.045 - -
4 Semen Warna Kg 0.650 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.3.44. Pemasangan 1 m² lantai karpet


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.170 - -
2 Tukang Batu L.02 OH 0.170 - -
3 Kepala Tukang L.03 OH 0.017 - -
4 Mandor L.04 OH 0.009 - -
Jumlah Tenaga Kerja -
B Bahan
1 Karpet m² 1.050 - -

264
2 Lem Kg 0.350 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.3.45. Pemasangan 1 m² underlayer ( pelapis bawah karpet )


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.120 - -
2 Tukang Batu L.02 OH 0.120 - -
3 Kepala Tukang L.03 OH 0.012 - -
4 Mandor L.04 OH 0.006 - -
Jumlah Tenaga Kerja -
B Bahan
1 Underlayer m² 1.050 - -
2 Lem Kg 0.350 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.3.46. Pemasangan 1 m² parquet kayu


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.700 111,700.00 78,190.00
2 Tukang Batu L.02 OH 0.350 135,070.00 47,274.50
3 Kepala Tukang L.03 OH 0.035 140,740.00 4,925.90
4 Mandor L.04 OH 0.035 160,090.00 5,603.15
Jumlah Tenaga Kerja 135,993.55
B Bahan
1 Parquet Kayu m² 1.050 Err:509 Err:509
2 Lem Kg 0.600 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.4.3.47. Pemasangan 1 m² lantai kayu gymfloor


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )

265
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.700 - -
2 Tukang Batu L.02 OH 0.350 - -
3 Kepala Tukang L.03 OH 0.035 - -
4 Mandor L.04 OH 0.035 - -
Jumlah Tenaga Kerja -
B Bahan
1 Parquet m² 1.050 - -
2 Lem Kg 0.600 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.3.48. Pemasangan 1 m² dinding porslen 11 cm x 11 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.000 - -
2 Tukang Batu L.02 OH 0.500 - -
3 Kepala Tukang L.03 OH 0.050 - -
4 Mandor L.04 OH 0.050 - -
Jumlah Tenaga Kerja -
B Bahan
1 Porslen Bh 86.000 - -
2 Semen Portland Kg 9.300 - -
3 Pasir Pasang m³ 0.018 - -
4 Semen Warna Kg 1.500 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.3.49. Pemasangan 1 m² dinding porslen 10 cm x 20 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.900 - -
2 Tukang Batu L.02 OH 0.450 - -
3 Kepala Tukang L.03 OH 0.045 - -
4 Mandor L.04 OH 0.045 - -
Jumlah Tenaga Kerja -
B Bahan
1 Porslen Bh 53.000 - -

266
2 Semen Portland Kg 9.300 - -
3 Pasir Pasang m³ 0.018 - -
4 Semen Warna Kg 2.750 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.3.50. Pemasangan 1 m² dinding porslen 20 cm x 20 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.900 - -
2 Tukang Batu L.02 OH 0.450 - -
3 Kepala Tukang L.03 OH 0.045 - -
4 Mandor L.04 OH 0.045 - -
Jumlah Tenaga Kerja -
B Bahan
1 Porslen Bh 26.000 - -
2 Semen Portland Kg 9.300 - -
3 Pasir Pasang m³ 0.018 - -
4 Semen Warna Kg 1.940 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.3.51. Pemasangan 1 m² dinding keramik artistik 10 cm x 20 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.900 111,700.00 100,530.00
2 Tukang Batu L.02 OH 0.450 135,070.00 60,781.50
3 Kepala Tukang L.03 OH 0.045 140,740.00 6,333.30
4 Mandor L.04 OH 0.045 160,090.00 7,204.05
Jumlah Tenaga Kerja 174,848.85
B Bahan
1 Keramik Artistik Bh 53.000 2,988.00 158,364.00
2 Semen Portland Kg 9.300 2,000.00 18,600.00
3 Pasir Pasang m³ 0.018 187,900.00 3,382.20
4 Semen Warna Kg 2.750 2,294.00 6,308.50
Jumlah Harga Bahan 186,654.70
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 361,503.55

267
E Overhead + Profit ( Contoh 15% ) 15% x D 54,225.53
F Harga Satuan Pekerjaan ( D + E ) 415,729.08

A.4.4.3.52. Pemasangan 1 m² dinding keramik artistik 5 cm x 20 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.900 - -
2 Tukang Batu L.02 OH 0.450 - -
3 Kepala Tukang L.03 OH 0.045 - -
4 Mandor L.04 OH 0.045 - -
Jumlah Tenaga Kerja -
B Bahan
1 Keramik Artistik Bh 106.000 - -
2 Semen Portland Kg 9.300 - -
3 Pasir Pasang m³ 0.018 - -
4 Semen Warna Kg 2.900 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.3.53. Pemasangan 1 m² dinding keramik 10 cm x 20 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.900 - -
2 Tukang Batu L.02 OH 0.450 - -
3 Kepala Tukang L.03 OH 0.045 - -
4 Mandor L.04 OH 0.045 - -
Jumlah Tenaga Kerja -
B Bahan
1 Keramik Bh 53.000 - -
2 Semen Portland Kg 9.300 - -
3 Pasir Pasang m³ 0.018 - -
4 Semen Warna Kg 2.750 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

268
A.4.4.3.54. Pemasangan 1 m² dinding keramik 20 cm x 20 cm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.900 111,700.00 100,530.00
2 Tukang Batu L.02 OH 0.450 135,070.00 60,781.50
3 Kepala Tukang L.03 OH 0.045 140,740.00 6,333.30
4 Mandor L.04 OH 0.045 160,090.00 7,204.05
Jumlah Tenaga Kerja 174,848.85
B Bahan
1 Keramik Bh 26.500 2,988.00 79,182.00
2 Semen Portland Kg 9.300 2,000.00 18,600.00
3 Pasir Pasang m³ 0.018 187,900.00 3,382.20
4 Semen Warna Kg 1.940 2,294.00 4,450.36
Jumlah Harga Bahan 105,614.56
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 280,463.41
E Overhead + Profit ( Contoh 15% ) 15% x D 42,069.51
F Harga Satuan Pekerjaan ( D + E ) 322,532.92

A.4.4.3.55. Pemasangan 1 m² dinding marmer 100 cm x 100 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.300 - -
2 Tukang Batu L.02 OH 0.650 - -
3 Kepala Tukang L.03 OH 0.065 - -
4 Mandor L.04 OH 0.065 - -
Jumlah Tenaga Kerja -
B Bahan
1 Marmer Bh 1.060 - -
2 Semen Portland Kg 12.440 - -
3 Pasir Pasang m³ 0.025 - -
4 Semen Warna Kg 0.650 - -
5 Paku 12 cm Bh 3.030 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.3.56. Pemasangan 1 m² dinding bata pelapis 3 cm x 7 cm x 24 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.000 - -

269
2 Tukang Batu L.02 OH 0.500 - -
3 Kepala Tukang L.03 OH 0.050 - -
4 Mandor L.04 OH 0.050 - -
Jumlah Tenaga Kerja -
B Bahan
1 Bata Pelapis Bh 63.000 - -
2 Semen Portland Kg 12.440 - -
3 Pasir Pasang m³ 0.025 - -
4 Semen Warna Kg 0.050 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.3.57. Pemasangan 1 m² dinding batu paras


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.700 - -
2 Tukang Batu L.02 OH 0.350 - -
3 Kepala Tukang L.03 OH 0.035 - -
4 Mandor L.04 OH 0.035 - -
Jumlah Tenaga Kerja -
B Bahan
1 Batu Paras Bh 1.100 - -
2 Semen Portland Kg 11.750 - -
3 Pasir Pasang m³ 0.035 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.3.58. Pemasangan 1 m² dinding batu tempel hitam


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.700 111,700.00 78,190.00
2 Tukang Batu L.02 OH 0.350 135,070.00 47,274.50
3 Kepala Tukang L.03 OH 0.035 140,740.00 4,925.90
4 Mandor L.04 OH 0.035 160,090.00 5,603.15
Jumlah Tenaga Kerja 135,993.55
B Bahan
1 Batu Tempel Hitam Bh 1.100 Err:509 Err:509
2 Semen Portland Kg 11.750 2,000.00 23,500.00
3 Pasir Pasang m³ 0.035 187,900.00 6,576.50
Jumlah Harga Bahan Err:509

270
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.4.3.59. Pemasangan 1 m² lantai vynil ukuran 30 cm x 30 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.150 - -
2 Tukang Batu L.02 OH 0.150 - -
3 Kepala Tukang L.03 OH 0.015 - -
4 Mandor L.04 OH 0.008 - -
Jumlah Tenaga Kerja -
B Bahan
1 Vynil Bh 11.870 - -
2 Lem Kg 0.350 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.3.60. Pemasangan 1 m² wallpaper lebar 50 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.350 111,700.00 39,095.00
2 Tukang Batu L.02 OH 0.175 135,070.00 23,637.25
3 Kepala Tukang L.03 OH 0.017 140,740.00 2,392.58
4 Mandor L.04 OH 0.002 160,090.00 320.18
Jumlah Tenaga Kerja 65,445.01
B Bahan
1 Wallpaper m 2.200 Err:509 Err:509
2 Lem Kg 0.250 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.4.3.60. Pemasangan 1 m² HPL


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga

271
1 Pekerja L.01 OH 0.350 111,700.00 39,095.00
2 Tukang Batu L.02 OH 0.175 135,070.00 23,637.25
3 Kepala Tukang L.03 OH 0.017 140,740.00 2,392.58
4 Mandor L.04 OH 0.002 160,090.00 320.18
Jumlah Tenaga Kerja 65,445.01
B Bahan
1 HPL Lbr 0.367 Err:509 Err:509
2 Lem Kg 0.250 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.4.3.61. Pemasangan 1 m² floor harderner


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.120 - -
2 Tukang Batu L.02 OH 0.120 - -
3 Kepala Tukang L.03 OH 0.012 - -
4 Mandor L.04 OH 0.006 - -
Jumlah Tenaga Kerja -
B Bahan
1 Floor Harderner Kg 5.000 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.3.62. Pemasangan 1 m² plint vynil 15 cm x 30 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.080 - -
2 Tukang Batu L.02 OH 0.080 - -
3 Kepala Tukang L.03 OH 0.008 - -
4 Mandor L.04 OH 0.004 - -
Jumlah Tenaga Kerja -
B Bahan
1 Floor Harderner BH 1.760 - -
2 Lem Kg 0.080 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -

272
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.4.3.63. Pemasangan 1 m² plint kayu tebal 2 cm lebar 10 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.120 - -
2 Tukang Batu L.02 OH 0.120 - -
3 Kepala Tukang L.03 OH 0.012 - -
4 Mandor L.04 OH 0.006 - -
Jumlah Tenaga Kerja -
B Bahan
1 Papan Kayu Kelas I m³ 0.003 - -
2 Paku / Skrup cm Kg 0.050 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

HARGA SATUAN PEKERJAAN LANGIT-LANGIT


A.4.5.1.
(PLAFOND)
A.4.5.1.1. Pemasangan 1 m² langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.030 - -
2 Tukang Kayu L.02 OH 0.070 - -
3 Kepala Tukang L.03 OH 0.007 - -
4 Mandor L.04 OH 0.004 - -
Jumlah Tenaga Kerja -
B Bahan
1 Asbes Semen m² 1.100 - -
2 Paku Tripleks Kg 0.010 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.5.1.2. Pemasangan 1 m² langit-langit akustik ukuran ( 30 x 30 ) cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga

273
1 Pekerja L.01 OH 0.120 - -
2 Tukang Kayu L.02 OH 0.120 - -
3 Kepala Tukang L.03 OH 0.012 - -
4 Mandor L.04 OH 0.006 - -
Jumlah Tenaga Kerja -
B Bahan
1 Akustik Lembar 12.000 - -
2 Paku Tripleks Kg 0.050 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.5.1.3. Pemasangan 1 m² langit-langit akustik ukuran ( 30 x 60 ) cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.120 - -
2 Tukang Kayu L.02 OH 0.120 - -
3 Kepala Tukang L.03 OH 0.012 - -
4 Mandor L.04 OH 0.006 - -
Jumlah Tenaga Kerja -
B Bahan
1 Akustik Lembar 5.800 - -
2 Paku Tripleks Kg 0.050 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.5.1.4. Pemasangan 1 m² langit-langit akustik ukuran ( 60 x 120 ) cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.100 - -
2 Tukang Kayu L.02 OH 0.100 - -
3 Kepala Tukang L.03 OH 0.010 - -
4 Mandor L.04 OH 0.005 - -
Jumlah Tenaga Kerja -
B Bahan
1 Akustik Lembar 1.500 - -
2 Paku Tripleks Kg 0.050 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0

274
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.5.1.5. Pemasangan 1 m² langit-langit tripleks ukuran ( 120 x 240 ) cm, tebal 3 mm, 4 mm & 6 mm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.100 111,700.00 11,170.00
2 Tukang Kayu L.02 OH 0.100 135,070.00 13,507.00
3 Kepala Tukang L.03 OH 0.010 140,740.00 1,407.40
4 Mandor L.04 OH 0.005 160,090.00 800.45
Jumlah Tenaga Kerja 26,884.85
B Bahan
1 Tripleks Lembar 0.375 Err:509 Err:509
2 Paku Tripleks Kg 0.030 22,400.00 672.00
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.5.1.6. Pemasangan 1 m² langit-langit lambrisering kayu, tebal 9 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.800 111,700.00 89,360.00
2 Tukang Kayu L.02 OH 0.800 135,070.00 108,056.00
3 Kepala Tukang L.03 OH 0.080 140,740.00 11,259.20
4 Mandor L.04 OH 0.040 160,090.00 6,403.60
Jumlah Tenaga Kerja 215,078.80
B Bahan
1 Kayu Papan m³ 0.015 2,522,000.00 37,830.00
2 Paku Tripleks Kg 0.010 22,400.00 224.00
Jumlah Harga Bahan 38,054.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 253,132.80
E Overhead + Profit ( Contoh 15% ) 15% x D 37,969.92
F Harga Satuan Pekerjaan ( D + E ) 291,102.72

A.4.5.1.7. Pemasangan 1 m² langit-langit gypsum board ukuran ( 120 x 240 x 9 ) mm, tebal 9 mm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.100 111,700.00 11,170.00
2 Tukang Kayu L.02 OH 0.050 135,070.00 6,753.50

275
3 Kepala Tukang L.03 OH 0.005 140,740.00 703.70
4 Mandor L.04 OH 0.005 160,090.00 800.45
Jumlah Tenaga Kerja 19,427.65
B Bahan
1 Gypsum Board Lembar 0.364 80,900.00 29,447.60
2 Paku Skrup Kg 0.110 27,000.00 2,970.00
Jumlah Harga Bahan 32,417.60
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 51,845.25
E Overhead + Profit ( Contoh 15% ) 15% x D 7,776.79
F Harga Satuan Pekerjaan ( D + E ) 59,622.04

A.4.5.1.7. Pemasangan 1 m² langit-langit Semen Asbes board ukuran ( 120 x 240 x 4 ) mm, tebal 4 mm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.100 111,700.00 11,170.00
2 Tukang Kayu L.02 OH 0.050 135,070.00 6,753.50
3 Kepala Tukang L.03 OH 0.005 140,740.00 703.70
4 Mandor L.04 OH 0.005 160,090.00 800.45
Jumlah Tenaga Kerja 19,427.65
B Bahan
1 Semen Asbes Lembar 0.364 Err:509 Err:509
2 Paku Skrup Kg 0.110 27,000.00 2,970.00
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.5.1.7. Pemasangan 1 m² Panel Aluminium Composte Panel( ACP) , tebal 4 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 111,700.00 55,850.00
2 Tukang Kayu L.02 OH 0.250 135,070.00 33,767.50
3 Kepala Tukang L.03 OH 0.025 140,740.00 3,518.50
4 Mandor L.04 OH 0.025 160,090.00 4,002.25
Jumlah Tenaga Kerja 97,138.25
B Bahan
1 ACP Lembar 0.364 Err:509 Err:509
2 Silent ACP Tube 0.270 Err:509 Err:509
3 Paku Skrup Kg 0.110 27,000.00 2,970.00
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509

276
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.5.1.8. Pemasangan 1 m² langit-langit akustik ukuran ( 60 x 120 ) cm, berikut rangka alluminium
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.500 - -
2 Tukang Besi L.02 OH 0.500 - -
3 Kepala Tukang L.03 OH 0.050 - -
4 Mandor L.04 OH 0.025 - -
Jumlah Tenaga Kerja -
B Bahan
1 Profil Alluminium "T" m 3.600 - -
2 Kawat Ø4 mm Kg 0.150 - -
3 Ramset Buah 1.050 - -
4 Akustik 60 x 120 Lembar 1.500 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.5.1.9. Pemasangan 1 m¹ list langit-langit kayu profil


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.050 111,700.00 5,585.00
2 Tukang Kayu L.02 OH 0.050 135,070.00 6,753.50
3 Kepala Tukang L.03 OH 0.005 140,740.00 703.70
4 Mandor L.04 OH 0.003 160,090.00 480.27
Jumlah Tenaga Kerja 13,522.47
B Bahan
1 List Kayu Profil m 1.050 Err:509 Err:509
2 Paku Kg 0.010 22,400.00 224.00
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

277
A.4.5.1.9. Pemasangan 1 m¹ list langit-langit gypsum
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.050 111,700.00 5,585.00
2 Tukang Kayu L.02 OH 0.050 135,070.00 6,753.50
3 Kepala Tukang L.03 OH 0.005 140,740.00 703.70
4 Mandor L.04 OH 0.003 160,090.00 480.27
Jumlah Tenaga Kerja 13,522.47
B Bahan
1 List Gypsum m 1.050 31,100.00 32,655.00
2 Tepung gypsum Kg 0.150 6,600.00 990.00
Jumlah Harga Bahan 33,645.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 47,167.47
E Overhead + Profit ( Contoh 15% ) 15% x D 7,075.12
F Harga Satuan Pekerjaan ( D + E ) 54,242.59

A.4.5.1.10. Pemasangan 1 m² rangka langi-langit besi hollow 40 x 40


Lihat pada kelompok pekerjaan besi dan alluminium ( A.9.21 )

A.4.5.2. HARGA SATUAN PEKERJAAN PENUTUP ATAP


A.4.5.2.1. Pemasangan 1 m² atap genteng palentong kecil
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.150 - -
2 Tukang Kayu L.02 OH 0.075 - -
3 Kepala Tukang L.03 OH 0.0075 - -
4 Mandor L.04 OH 0.008 - -
Jumlah Tenaga Kerja -
B Bahan
1 Genteng Palentong Bh 25.000 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.5.2.2. Pemasangan 1 m² atap genteng kodok glazuur


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga

278
1 Pekerja L.01 OH 0.150 - -
2 Tukang Kayu L.02 OH 0.075 - -
3 Kepala Tukang L.03 OH 0.0080 - -
4 Mandor L.04 OH 0.008 - -
Jumlah Tenaga Kerja -
B Bahan
1 Genteng Kodok Bh 25.000 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.5.2.3. Pemasangan 1 m² atap palentong besar / super


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.150 - -
2 Tukang Kayu L.02 OH 0.075 - -
3 Kepala Tukang L.03 OH 0.0080 - -
4 Mandor L.04 OH 0.008 - -
Jumlah Tenaga Kerja -
B Bahan
1 Genteng Kodok Bh 12.000 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.5.2.4. Pemasangan 1 m¹ bubung genteng palentong


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.400 - -
2 Tukang Kayu L.02 OH 0.200 - -
3 Kepala Tukang L.03 OH 0.0200 - -
4 Mandor L.04 OH 0.002 - -
Jumlah Tenaga Kerja -
B Bahan
1 Genteng Bubung Bh 5.000 - -
2 Semen Portland Kg 8.000 - -
3 Pasir Pasang m³ 0.032 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -

279
F Harga Satuan Pekerjaan ( D + E ) -

A.4.5.2.5. Pemasangan 1 m¹ bubung genteng kodok glazuur


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.400 - -
2 Tukang Kayu L.02 OH 0.200 - -
3 Kepala Tukang L.03 OH 0.0200 - -
4 Mandor L.04 OH 0.002 - -
Jumlah Tenaga Kerja -
B Bahan
1 Genteng Bubung Bh 5.000 - -
2 Semen Portland Kg 8.000 - -
3 Pasir Pasang m³ 0.032 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.5.2.6. Pemasangan 1 m¹ bubung genteng palentong besar


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.400 - -
2 Tukang Kayu L.02 OH 0.200 - -
3 Kepala Tukang L.03 OH 0.0200 - -
4 Mandor L.04 OH 0.002 - -
Jumlah Tenaga Kerja -
B Bahan
1 Genteng Bubung Bh 4.000 - -
2 Semen Portland Kg 8.000 - -
3 Pasir Pasang m³ 0.032 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.5.2.8. Pemasangan 1 m² atap asbes gelombang 0.92 m x 2,5 m x 5 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.140 - -
2 Tukang Kayu L.02 OH 0.075 - -

280
3 Kepala Tukang L.03 OH 0.0080 - -
4 Mandor L.04 OH 0.008 - -
Jumlah Tenaga Kerja -
B Bahan
1 Asbes Gel 92 x 250 Lembar 0.500 - -
2 Paku Pancing 6 x 23 Kg 0.120 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.5.2.9. Pemasangan 1 m² atap asbes gelombang 0.92 m x 2,25 m x 5 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.140 - -
2 Tukang Kayu L.02 OH 0.075 - -
3 Kepala Tukang L.03 OH 0.0080 - -
4 Mandor L.04 OH 0.008 - -
Jumlah Tenaga Kerja -
B Bahan
1 Asbes Gel 92 x 225 Lembar 0.600 - -
2 Paku Pancing 6 x 23 Kg 0.120 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.5.2.10. Pemasangan 1 m² atap asbes gelombang 0.92 m x 2 m x 5 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.140 - -
2 Tukang Kayu L.02 OH 0.070 - -
3 Kepala Tukang L.03 OH 0.0070 - -
4 Mandor L.04 OH 0.007 - -
Jumlah Tenaga Kerja -
B Bahan
1 Asbes Gel 92 x 200 Lembar 0.600 - -
2 Paku Pancing 6 x 23 Kg 0.120 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -

281
F Harga Satuan Pekerjaan ( D + E ) -

A.4.5.2.11. Pemasangan 1 m² atap asbes gelombang 0.92 m x 1,80 m x 5 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.140 - -
2 Tukang Kayu L.02 OH 0.070 - -
3 Kepala Tukang L.03 OH 0.0070 - -
4 Mandor L.04 OH 0.007 - -
Jumlah Tenaga Kerja -
B Bahan
1 Asbes Gel 92 x 180 Lembar 0.750 - -
2 Paku Pancing 6 x 23 Kg 0.120 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.5.2.12. Pemasangan 1 m² atap asbes gelombang 1,05 m x 2,40 m x 4 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.140 - -
2 Tukang Kayu L.02 OH 0.070 - -
3 Kepala Tukang L.03 OH 0.0070 - -
4 Mandor L.04 OH 0.007 - -
Jumlah Tenaga Kerja -
B Bahan
1 Asbes Gel 105 x 300 Lembar 0.350 - -
2 Paku Pancing 6 x 23 Kg 0.120 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.5.2.13. Pemasangan 1 m² atap asbes gelombang 1,05 m x 2,70 m x 4 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.140 - -
2 Tukang Kayu L.02 OH 0.070 - -
3 Kepala Tukang L.03 OH 0.0070 - -
4 Mandor L.04 OH 0.007 - -

282
Jumlah Tenaga Kerja -
B Bahan
1 Asbes Gel 105 x 270 Lembar 0.420 - -
2 Paku Pancing 6 x 23 Kg 0.120 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.5.2.14. Pemasangan 1 m² atap asbes gelombang 1,05 m x 2,40 m x 4 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.140 - -
2 Tukang Kayu L.02 OH 0.070 - -
3 Kepala Tukang L.03 OH 0.0070 - -
4 Mandor L.04 OH 0.007 - -
Jumlah Tenaga Kerja -
B Bahan
1 Asbes Gel 105 x 240 Lembar 0.440 - -
2 Paku Pancing 6 x 23 Kg 0.120 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.5.2.15. Pemasangan 1 m² atap asbes gelombang 1,05 m x 2,10 m x 4 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.140 - -
2 Tukang Kayu L.02 OH 0.070 - -
3 Kepala Tukang L.03 OH 0.0070 - -
4 Mandor L.04 OH 0.007 - -
Jumlah Tenaga Kerja -
B Bahan
1 Asbes Gel 105 x 210 Lembar 0.510 - -
2 Paku Pancing 6 x 23 Kg 0.120 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

283
A.4.5.2.16. Pemasangan 1 m² atap asbes gelombang 1,05 m x 1,50 m x 4 mm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.140 - -
2 Tukang Kayu L.02 OH 0.070 - -
3 Kepala Tukang L.03 OH 0.0070 - -
4 Mandor L.04 OH 0.007 - -
Jumlah Tenaga Kerja -
B Bahan
1 Asbes Gel 105 x 150 Lembar 0.800 - -
2 Paku Pancing 6 x 23 Kg 0.120 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.5.2.17. Pemasangan 1 m² atap asbes gelombang 1,08 m x 3,00 m x 6 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
1
A Tenaga
1 Pekerja L.01 OH 0.140 - -
2 Tukang Kayu L.02 OH 0.070 - -
3 Kepala Tukang L.03 OH 0.0070 - -
4 Mandor L.04 OH 0.007 - -
Jumlah Tenaga Kerja -
B Bahan
1 Asbes Gel 108 x 300 Lembar 0.370 - -
2 Paku Pancing 6 x 23 Kg 0.120 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.5.2.18. Pemasangan 1 m² atap asbes gelombang 1,08 m x 2,70 m x 6 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.140 - -
2 Tukang Kayu L.02 OH 0.070 - -
3 Kepala Tukang L.03 OH 0.0070 - -
4 Mandor L.04 OH 0.007 - -
Jumlah Tenaga Kerja -

284
B Bahan
1 Asbes Gel 108 x 270 Lembar 0.380 - -
2 Paku Pancing 6 x 23 Kg 0.120 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.5.2.19. Pemasangan 1 m² atap asbes gelombang 1,08 m x 2,40 m x 6 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.140 - -
2 Tukang Kayu L.02 OH 0.070 - -
3 Kepala Tukang L.03 OH 0.0070 - -
4 Mandor L.04 OH 0.007 - -
Jumlah Tenaga Kerja -
B Bahan
1 Asbes Gel 108 x 240 Lembar 0.460 - -
2 Paku Pancing 6 x 23 Kg 0.120 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.5.2.20. Pemasangan 1 m² atap asbes gelombang 1,08 m x 2,10 m x 6 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.140 - -
2 Tukang Kayu L.02 OH 0.070 - -
3 Kepala Tukang L.03 OH 0.0070 - -
4 Mandor L.04 OH 0.007 - -
Jumlah Tenaga Kerja -
B Bahan
1 Asbes Gel 108 x 210 Lembar 0.490 - -
2 Paku Pancing 6 x 23 Kg 0.120 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.5.2.21. Pemasangan 1 m² atap asbes gelombang 1,08 m x 1,80 m x 6 mm

285
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.140 - -
2 Tukang Kayu L.02 OH 0.070 - -
3 Kepala Tukang L.03 OH 0.0070 - -
4 Mandor L.04 OH 0.007 - -
Jumlah Tenaga Kerja -
B Bahan
1 Asbes Gel 108 x 180 Lembar 0.570 - -
2 Paku Pancing 6 x 23 Kg 0.120 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.5.2.38. Pemasangan 1 m² atap seng gelombang


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.120 111,700.00 13,404.00
2 Tukang Kayu L.02 OH 0.060 135,070.00 8,104.20
3 Kepala Tukang L.03 OH 0.0060 140,740.00 844.44
4 Mandor L.04 OH 0.006 160,090.00 960.54
Jumlah Tenaga Kerja 23,313.18
B Bahan
1 Seng Gelombang 3" x 6" Lembar 0.700 Err:509 Err:509
2 Paku Seng Kg 0.020 31,300.00 626.00
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.5.2.39. Pemasangan 1 m¹ nok atap seng


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.150 111,700.00 16,755.00
2 Tukang Kayu L.02 OH 0.070 135,070.00 9,454.90
3 Kepala Tukang L.03 OH 0.0070 140,740.00 985.18
4 Mandor L.04 OH 0.006 160,090.00 960.54
Jumlah Tenaga Kerja 28,155.62
B Bahan
1 Seng Plat 3" x 6" BJLS 28 Lembar 0.300 Err:509 Err:509

286
2 Paku Seng Kg 0.040 31,300.00 1,252.00
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.5.2.40. Pemasangan 1 m² atap alluminium


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.150 - -
2 Tukang Kayu L.02 OH 0.750 - -
3 Kepala Tukang L.03 OH 0.0800 - -
4 Mandor L.04 OH 0.006 - -
Jumlah Tenaga Kerja -
B Bahan
1 alluminium gelombang tebal 0,55 Lembar 1.050 - -
2 Paku Hak Panjang 15 cm Kg 0.020 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.5.2.41. Pemasangan 1 m¹ nok atap alluminium


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.100 - -
2 Tukang Kayu L.02 OH 1.000 - -
3 Kepala Tukang L.03 OH 0.1000 - -
4 Mandor L.04 OH 0.050 - -
Jumlah Tenaga Kerja -
B Bahan
1 Nok Standar 40 x 18 Buah 1.200 - -
2 Paku Hak Panjang 15 cm Kg 0.040 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.5.2.40. Pemasangan 1 m² atap zincalum gelombang 4 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )

287
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.120 111,700.00 13,404.00
2 Tukang Kayu L.02 OH 0.060 135,070.00 8,104.20
3 Kepala Tukang L.03 OH 0.0060 140,740.00 844.44
4 Mandor L.04 OH 0.006 160,090.00 960.54
Jumlah Tenaga Kerja 23,313.18
B Bahan
1 Zincalum gelombang 4 mm Lembar 0.700 Err:509 Err:509
2 Paku Hak Panjang 15 cm Kg 0.020 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.5.2.40. Pemasangan 1 m² atap metalroof


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.200 111,700.00 22,340.00
2 Tukang Kayu L.02 OH 0.100 135,070.00 13,507.00
3 Kepala Tukang L.03 OH 0.0100 140,740.00 1,407.40
4 Mandor L.04 OH 0.001 160,090.00 160.09
Jumlah Tenaga Kerja 37,414.49
B Bahan
1 Genteng Metal Lembar 1.020 91,000.00 92,820.00
2 Paku Biasa 2" - 5" Kg 0.200 22,400.00 4,480.00
Jumlah Harga Bahan 97,300.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 134,714.49
E Overhead + Profit ( Contoh 15% ) 15% x D 20,207.17
F Harga Satuan Pekerjaan ( D + E ) 154,921.66

A.4.5.2.40. Pemasangan 1 m² atap spandeck


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.120 111,700.00 13,404.00
2 Tukang Kayu L.02 OH 0.060 135,070.00 8,104.20
3 Kepala Tukang L.03 OH 0.0060 140,740.00 844.44
4 Mandor L.04 OH 0.006 160,090.00 960.54
Jumlah Tenaga Kerja 23,313.18
B Bahan
1 Spandeck 4 mm Lembar 1.050 Err:509 Err:509
2 Paku Hak Panjang 15 cm Kg 0.020 - -
Jumlah Harga Bahan Err:509

288
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

289
A.4.5.2.41. Pemasangan 1 m¹ nok atap Metal roof
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.250 111,700.00 27,925.00
2 Tukang Kayu L.02 OH 0.150 135,070.00 20,260.50
3 Kepala Tukang L.03 OH 0.0150 140,740.00 2,111.10
4 Mandor L.04 OH 0.013 160,090.00 2,081.17
Jumlah Tenaga Kerja 52,377.77
B Bahan
1 Nok Buah 1.100 52,700.00 57,970.00
2 Paku Hak Panjang 15 cm Kg 0.040 31,300.00 1,252.00
Jumlah Harga Bahan 59,222.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 111,599.77
E Overhead + Profit ( Contoh 15% ) 15% x D 16,739.97
F Harga Satuan Pekerjaan ( D + E ) 128,339.74

A.4.6.1. HARGA SATUAN PEKERJAAN KAYU


A.4.6.1.1. Pembuatan dan pemasangan 1 m³ kusen pintu dan kusen jendela, kayu kelas I
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 7.000 - -
2 Tukang Kayu L.02 OH 21.000 - -
3 Kepala Tukang L.03 OH 2.1000 - -
4 Mandor L.04 OH 0.350 - -
Jumlah Tenaga Kerja -
B Bahan
1 Balok Kayu m³ 1.100 - -
2 Paku 10 cm Kg 1.250 - -
3 Lem Kayu Kg 1.000 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.6.1.2. Pembuatan dan pemasangan 1 m³ kusen pintu dan kusen jendela, kayu kelas II & III
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 6.000 111,700.00 670,200.00
2 Tukang Kayu L.02 OH 18.000 135,070.00 2,431,260.00

290
3 Kepala Tukang L.03 OH 1.8000 140,740.00 253,332.00
4 Mandor L.04 OH 0.300 160,090.00 48,027.00
Jumlah Tenaga Kerja 3,402,819.00
B Bahan
1 Balok Kayu m³ 1.200 3,007,000.00 3,608,400.00
2 Paku 10 cm Kg 1.250 22,400.00 28,000.00
Jumlah Harga Bahan 3,636,400.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 7,039,219.00
E Overhead + Profit ( Contoh 15% ) 15% x D 1,055,882.85
F Harga Satuan Pekerjaan ( D + E ) 8,095,101.85

A.4.6.1.3. Pembuatan dan pemasangan 1 m² kusen pintu klamp standar, kayu kelas II
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.350 - -
2 Tukang Kayu L.02 OH 1.050 - -
3 Kepala Tukang L.03 OH 0.1050 - -
4 Mandor L.04 OH 0.018 - -
Jumlah Tenaga Kerja -
B Bahan
1 Papan Kayu m³ 0.040 - -
2 Paku 5 - 7 cm Kg 0.050 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.6.1.4. Pembuatan dan pemasangan 1 m² kusen pintu klamp sederhana, kayu kelas III
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7

291
A Tenaga
1 Pekerja L.01 OH 0.350 - -
2 Tukang Kayu L.02 OH 1.050 - -
3 Kepala Tukang L.03 OH 0.1050 - -
4 Mandor L.04 OH 0.018 - -
Jumlah Tenaga Kerja -
B Bahan
1 Papan Kayu m³ 0.040 - -
2 Paku 5 - 7 cm Kg 0.050 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.6.1.5. Pembuatan dan pemasangan 1 m² daun pintu panel, kayu kelas I atau II
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.000 111,700.00 111,700.00
2 Tukang Kayu L.02 OH 3.000 135,070.00 405,210.00
3 Kepala Tukang L.03 OH 0.3000 140,740.00 42,222.00
4 Mandor L.04 OH 0.050 160,090.00 8,004.50
Jumlah Tenaga Kerja 567,136.50
B Bahan
1 Papan Kayu m³ 0.040 3,007,000.00 120,280.00
2 Lem Kayu Kg 0.500 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 10% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.4.6.1.6. Pembuatan dan pemasangan 1 m² pintu dan jendela kaca, kayu kelas I atau II
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.800 111,700.00 89,360.00
2 Tukang Kayu L.02 OH 2.400 135,070.00 324,168.00
3 Kepala Tukang L.03 OH 0.2400 140,740.00 33,777.60
4 Mandor L.04 OH 0.040 160,090.00 6,403.60
Jumlah Tenaga Kerja 453,709.20
B Bahan
1 Papan Kayu m³ 0.024 3,007,000.00 72,168.00
2 Lem Kayu Kg 0.300 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan

292
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.4.6.1.7. Pembuatan dan pemasangan 1 m² pintu dan jendela jalusi, kayu kelas I atau II
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.000 111,700.00 111,700.00
2 Tukang Kayu L.02 OH 3.000 135,070.00 405,210.00
3 Kepala Tukang L.03 OH 0.3000 140,740.00 42,222.00
4 Mandor L.04 OH 0.050 160,090.00 8,004.50
Jumlah Tenaga Kerja 567,136.50
B Bahan
1 Papan Kayu m³ 0.064 3,007,000.00 192,448.00
2 Lem Kayu Kg 0.500 #REF! #REF!
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.4.6.1.8. Pembuatan 1 m² daun pintu plywood rangkap, rangka kayu kelas II tertutup ( lebar sampai 90 cm )
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.700 111,700.00 78,190.00
2 Tukang Kayu L.02 OH 2.100 135,070.00 283,647.00
3 Kepala Tukang L.03 OH 0.2100 140,740.00 29,555.40
4 Mandor L.04 OH 0.035 160,090.00 5,603.15
Jumlah Tenaga Kerja 396,995.55
B Bahan
1 Papan Kayu m³ 0.025 3,007,000.00 75,175.00
2 Paku 1 cm - 2,5 cm Kg 0.030 22,400.00 672.00
3 Lem Kayu Kg 0.500 #REF! #REF!
4 Plywood tebal 4 mm ukuran
Lembar 0.035 83,000.00 2,905.00
( 90 x 220 ) cm
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.4.6.1.9. Pembuatan 1 m² pintu plywood rangkap, rangka expose kayu kelas I atau II
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )

293
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.800 111,700.00 89,360.00
2 Tukang Kayu L.02 OH 2.400 135,070.00 324,168.00
3 Kepala Tukang L.03 OH 0.2400 140,740.00 33,777.60
4 Mandor L.04 OH 0.040 160,090.00 6,403.60
Jumlah Tenaga Kerja 453,709.20
B Bahan
1 Papan Kayu m³ 0.0256 3,007,000.00 76,979.20
2 Paku 1 cm - 2,5 cm Kg 0.030 22,400.00 672.00
3 Lem Kayu Kg 0.500 #REF! #REF!
4 Plywood tebal 4 mm ukuran
Lembar 1.000 83,000.00 83,000.00
( 90 x 220 ) cm
Jumlah Harga Bahan #REF!
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) #REF!
E Overhead + Profit ( Contoh 15% ) 15% x D #REF!
F Harga Satuan Pekerjaan ( D + E ) #REF!

A.4.6.1.10. Pemasangan 1 m² jalusi kusen, kayu kelas I atau II


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.670 111,700.00 74,839.00
2 Tukang Kayu L.02 OH 2.000 135,070.00 270,140.00
3 Kepala Tukang L.03 OH 0.2000 140,740.00 28,148.00
4 Mandor L.04 OH 0.335 160,090.00 53,630.15
Jumlah Tenaga Kerja 426,757.15
B Bahan
1 Papan Kayu m³ 0.0600 3,007,000.00 180,420.00
2 Paku 1 cm - 2,5 cm Kg 0.150 22,400.00 3,360.00
Jumlah Harga Bahan 183,780.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 610,537.15
E Overhead + Profit ( Contoh 15% ) 15% x D 91,580.57
F Harga Satuan Pekerjaan ( D + E ) 702,117.72

A.4.6.1.11. Pemasangan 1 m² teakwood rangkap, rangka expose kayu kelas I


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.800 - -
2 Tukang Kayu L.02 OH 2.400 - -
3 Kepala Tukang L.03 OH 0.2400 - -
4 Mandor L.04 OH 0.040 - -
Jumlah Tenaga Kerja -
B Bahan

294
1 Papan Kayu m³ 0.0250 - -
2 Paku 1 cm - 2,5 cm Kg 0.030 - -
3 Lem Kayu Kg 0.300 - -
4 Teakwood tebal 4 mm ukuran
Lembar 1.000 - -
( 90 x 220 ) cm
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.6.1.12. Pemasangan 1 m² teakwood rangkap lapis formika, rangka expose kayu kelas II
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.850 - -
2 Tukang Kayu L.02 OH 2.550 - -
3 Kepala Tukang L.03 OH 0.2550 - -
4 Mandor L.04 OH 0.043 - -
Jumlah Tenaga Kerja -
B Bahan
1 Papan Kayu m³ 0.0250 - -
2 Paku 1 cm - 2,5 cm Kg 0.030 - -
3 Lem Kayu Kg 0.800 - -
4 Teakwood tebal 4 mm ukuran
Lembar 1.000 - -
( 90 x 220 ) cm
5 Formika Lembar 0.500 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.6.1.13. Pemasangan 1 m³ konstruksi kuda-kuda konvensional, kayu kelas I, II dan III


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 4.000 111,700.00 446,800.00
2 Tukang Kayu L.02 OH 12.000 135,070.00 1,620,840.00
3 Kepala Tukang L.03 OH 1.2000 140,740.00 168,888.00
4 Mandor L.04 OH 0.200 160,090.00 32,018.00
Jumlah Tenaga Kerja 2,268,546.00
B Bahan
1 Balok Kayu m³ 1.1000 3,007,000.00 3,307,700.00
2 Besi Strip Tebal 5 mm Kg 15.000 -
3 Paku 12 cm Kg 5.600 22,400.00 125,440.00
Jumlah Harga Bahan 3,433,140.00
C Peralatan

295
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 5,701,686.00
E Overhead + Profit ( Contoh 15% ) 15% x D 855,252.90
F Harga Satuan Pekerjaan ( D + E ) 6,556,938.90

A.4.6.1.14. Pemasangan 1 m³ konstruksi kuda-kuda expose, kayu kelas I


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 6.700 111,700.00 748,390.00
2 Tukang Kayu L.02 OH 20.100 135,070.00 2,714,907.00
3 Kepala Tukang L.03 OH 2.0100 140,740.00 282,887.40
4 Mandor L.04 OH 0.335 160,090.00 53,630.15
Jumlah Tenaga Kerja 3,463,297.00
B Bahan
1 Balok Kayu m³ 1.2000 3,007,000.00 3,608,400.00
2 Besi Strip Tebal 5 mm Kg 15.000 - -
3 Paku 12 cm Kg 5.600 22,400.00 125,440.00
Jumlah Harga Bahan 3,733,840.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 7,197,137.00
E Overhead + Profit ( Contoh 15% ) 15% x D 1,079,570.55
F Harga Satuan Pekerjaan ( D + E ) 8,276,707.55

A.4.6.1.15. Pemasangan 1 m³ konstruksi gording, kayu kelas II


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 6.700 111,700.00 748,390.00
2 Tukang Kayu L.02 OH 20.100 135,070.00 2,714,907.00
3 Kepala Tukang L.03 OH 2.0100 140,740.00 282,887.40
4 Mandor L.04 OH 0.335 160,090.00 53,630.15
Jumlah Tenaga Kerja 3,799,814.55
B Bahan
1 Balok Kayu m³ 1.1000 3,007,000.00 3,307,700.00
2 Besi Strip Tebal 5 mm Kg 15.000 - -
3 Paku 12 cm Kg 3.000 22,400.00 67,200.00
Jumlah Harga Bahan 3,374,900.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 7,174,714.55
E Overhead + Profit ( Contoh 15% ) 15% x D 1,076,207.18
F Harga Satuan Pekerjaan ( D + E ) 8,250,921.73

A.4.6.1.17. Pemasangan 1 m² rangka atap genteng beton, kayu kelas II


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7

296
A Tenaga
1 Pekerja L.01 OH 0.100 - -
2 Tukang Kayu L.02 OH 0.100 - -
3 Kepala Tukang L.03 OH 0.0100 - -
4 Mandor L.04 OH 0.005 - -
Jumlah Tenaga Kerja -
B Bahan
1 Kaso-kaso 5 x 7 cm m³ 0.0140 - -
2 Reng ( 3 x 4 ) cm m³ 0.057 - -
3 Paku 5 dan 10 cm Kg 0.250 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.6.1.18. Pemasangan 1 m² rangka atap sirap, kayu kelas II


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.120 - -
2 Tukang Kayu L.02 OH 0.120 - -
3 Kepala Tukang L.03 OH 0.0120 - -
4 Mandor L.04 OH 0.006 - -
Jumlah Tenaga Kerja -
B Bahan
1 Kayu Kelas II m³ 0.0140 - -
2 Paku 5 dan 10 cm Kg 0.057 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.6.1.19. Pemasangan 1 m² rangka langit-langit ( 50 x 100 ) cm, kayu kelas II atau III
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.150 111,700.00 16,755.00
2 Tukang Kayu L.02 OH 0.300 135,070.00 40,521.00
3 Kepala Tukang L.03 OH 0.0300 140,740.00 4,222.20
4 Mandor L.04 OH 0.075 160,090.00 12,006.75
Jumlah Tenaga Kerja 73,504.95
B Bahan
1 Kaso-kaso 5 x 7 cm m³ 0.0154 2,522,000.00 38,838.80
2 Paku 7 cm - 10 cm Kg 0.200 22,400.00 4,480.00
Jumlah Harga Bahan 43,318.80

297
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 116,823.75
E Overhead + Profit ( Contoh 15% ) 15% x D 17,523.56
F Harga Satuan Pekerjaan ( D + E ) 134,347.31

A.4.6.1.20. Pemasangan 1 m² rangka langit-langit ( 60 x 60 ) cm, kayu kelas II atau III


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.200 111,700.00 22,340.00
2 Tukang Kayu L.02 OH 0.300 135,070.00 40,521.00
3 Kepala Tukang L.03 OH 0.0300 140,740.00 4,222.20
4 Mandor L.04 OH 0.010 160,090.00 1,600.90
Jumlah Tenaga Kerja 68,684.10
B Bahan
1 Kaso-kaso m³ 0.0163 2,522,000.00 41,108.60
2 Paku 7 cm - 10 cm Kg 0.250 22,400.00 5,600.00
Jumlah Harga Bahan 46,708.60
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 115,392.70
E Overhead + Profit ( Contoh 15% ) 15% x D 17,308.91
F Harga Satuan Pekerjaan ( D + E ) 132,701.61

A.4.6.1.21. Pemasangan 1 m¹ listplank ukuran ( 3 x 20 ) cm, kayu kelas I atau kelas II


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.100 111,700.00 11,170.00
2 Tukang Kayu L.02 OH 0.200 135,070.00 27,014.00
3 Kepala Tukang L.03 OH 0.0200 140,740.00 2,814.80
4 Mandor L.04 OH 0.005 160,090.00 800.45
Jumlah Tenaga Kerja 41,799.25
B Bahan
1 Papan Kayu m³ 0.0108 2,522,000.00 27,237.60
2 Paku 5 cm dan 7 cm Kg 0.100 22,400.00 2,240.00
Jumlah Harga Bahan 29,477.60
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 71,276.85
E Overhead + Profit ( Contoh 15% ) 15% x D 10,691.53
F Harga Satuan Pekerjaan ( D + E ) 81,968.38

A.4.6.1.22. Pemasangan 1 m¹ listplank ukuran ( 3 x 30 ) cm, kayu kelas I atau kelas II


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga

298
1 Pekerja L.01 OH 0.100 111,700.00 11,170.00
2 Tukang Kayu L.02 OH 0.200 135,070.00 27,014.00
3 Kepala Tukang L.03 OH 0.0200 140,740.00 2,814.80
4 Mandor L.04 OH 0.005 160,090.00 800.45
Jumlah Tenaga Kerja 41,799.25
B Bahan
1 Papan Kayu m³ 0.0110 2,522,000.00 27,742.00
2 Paku 5 cm dan 7 cm Kg 0.050 22,400.00 1,120.00
Jumlah Harga Bahan 28,862.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 70,661.25
E Overhead + Profit ( Contoh 15% ) 15% x D 10,599.19
F Harga Satuan Pekerjaan ( D + E ) 81,260.44

A.4.6.1.23. Pemasangan 1 m² rangka dinding pemisah ( 60 x 120 ) cm, kayu kelas II atau III
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.150 111,700.00 16,755.00
2 Tukang Kayu L.02 OH 0.450 135,070.00 60,781.50
3 Kepala Tukang L.03 OH 0.0450 140,740.00 6,333.30
4 Mandor L.04 OH 0.008 160,090.00 1,280.72
Jumlah Tenaga Kerja 85,150.52
B Bahan
1 Balok Kayu m³ 0.0280 2,522,000.00 70,616.00
2 Paku 5 cm dan 7 cm Kg 0.150 22,400.00 3,360.00
Jumlah Harga Bahan 73,976.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 159,126.52
E Overhead + Profit ( Contoh 15% ) 15% x D 23,868.98
F Harga Satuan Pekerjaan ( D + E ) 182,995.50

A.4.6.1.24. Pemasangan 1 m² dinding pemisah rangkap, rangka kayu kelas II


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.150 111,700.00 16,755.00
2 Tukang Kayu L.02 OH 0.450 135,070.00 60,781.50
3 Kepala Tukang L.03 OH 0.0450 140,740.00 6,333.30
4 Mandor L.04 OH 0.008 160,090.00 1,280.72
Jumlah Tenaga Kerja 85,150.52
B Bahan
1 Balok Kayu 6 x 12 m³ 0.0280 3,007,000.00 84,196.00
2 Paku 5 cm dan 10 cm Kg 0.150 22,400.00 3,360.00
3
Teakwood 4 mm, 120 x 240 Lembar 0.8600 83,000.00 71,380.00
4 Lem Kayu Kg 0.560 Err:509 Err:509
Jumlah Harga Bahan Err:509

299
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.6.1.25. Pemasangan 1 m² dinding pemisah plywood rangkap, rangka kayu kelas II


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.200 111,700.00 22,340.00
2 Tukang Kayu L.02 OH 0.600 135,070.00 81,042.00
3 Kepala Tukang L.03 OH 0.0600 140,740.00 8,444.40
4 Mandor L.04 OH 0.010 160,090.00 1,600.90
Jumlah Tenaga Kerja 113,427.30
B Bahan
1 Balok Kayu 6 x 12 m³ 0.0280 3,007,000.00 84,196.00
2 Paku 5 cm dan 10 cm Kg 0.150 22,400.00 3,360.00
3
Plywood 4 mm, 120 x 240 Lembar 0.8600 83,000.00 71,380.00
4 Lem Kayu Kg 0.560 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.6.1.28. Pemasangan 1 m² dinding bilik, rangka kayu kelas III atau IV


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.100 -
2 Tukang Kayu L.02 OH 0.050 -
3 Kepala Tukang L.03 OH 0.0050 -
4 Mandor L.04 OH 0.005 -
Jumlah Tenaga Kerja -
B Bahan
1 Bilik Bambu m² 1.5000 - -
2 Kaso-kaso 5 x 7 m³ 0.014 - -
3 Paku Kg 0.012 - -
4 List Kayu 2/4 m³ 0.003 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

300
A.4.6.2. HARGA SATUAN PEKERJAAN KUNCI DAN KACA
A.4.6.2.1. Pemasangan 1 buah kunci tanam antik
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.060 - -
2 Tukang Kayu L.02 OH 0.600 - -
3 Kepala Tukang L.03 OH 0.0600 - -
4 Mandor L.04 OH 0.003 - -
Jumlah Tenaga Kerja -
B Bahan
1 Kunci Tanam Antik Buah 1.000 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.6.2.2. Pemasangan 1 buah kunci tanam


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.010 111,700.00 1,117.00
2 Tukang Kayu L.02 OH 0.500 135,070.00 67,535.00
3 Kepala Tukang L.03 OH 0.0500 140,740.00 7,037.00
4 Mandor L.04 OH 0.005 160,090.00 800.45
Jumlah Tenaga Kerja 76,489.45
B Bahan
1 Kunci Tanam Biasa Buah 1.000 171,300.00 171,300.00
Jumlah Harga Bahan 171,300.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 247,789.45
E Overhead + Profit ( Contoh 15% ) 15% x D 37,168.42
F Harga Satuan Pekerjaan ( D + E ) 284,957.87

A.4.6.2.3. Pemasangan 1 buah kunci kamar mandi


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.005 - -
2 Tukang Kayu L.02 OH 0.500 - -
3 Kepala Tukang L.03 OH 0.0500 - -
4 Mandor L.04 OH 0.003 - -
Jumlah Tenaga Kerja -

301
B Bahan
1 Kunci Tanam KM Buah 1.000 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.6.2.4. Pemasangan 1 buah kunci slinder


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.005 - -
2 Tukang Kayu L.02 OH 0.500 - -
3 Kepala Tukang L.03 OH 0.0500 - -
4 Mandor L.04 OH 0.003 - -
Jumlah Tenaga Kerja -
B Bahan
1 Kunci Slinder Buah 1.000 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.6.2.2. Pemasangan 1 buah kunci tanam 2 daun pintu


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.010 111,700.00 1,117.00
2 Tukang Kayu L.02 OH 0.500 135,070.00 67,535.00
3 Kepala Tukang L.03 OH 0.0500 140,740.00 7,037.00
4 Mandor L.04 OH 0.005 160,090.00 800.45
Jumlah Tenaga Kerja 76,489.45
B Bahan
1 Kunci Tanam Biasa Buah 1.000 51,800.00 51,800.00
Jumlah Harga Bahan 51,800.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 128,289.45
E Overhead + Profit ( Contoh 15% ) 15% x D 19,243.42
F Harga Satuan Pekerjaan ( D + E ) 147,532.87

302
A.4.6.2.2. Pemasangan 1 pasang handle pintu
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.010 111,700.00 1,117.00
2 Tukang Kayu L.02 OH 0.500 135,070.00 67,535.00
3 Kepala Tukang L.03 OH 0.0500 140,740.00 7,037.00
4 Mandor L.04 OH 0.005 160,090.00 800.45
Jumlah Tenaga Kerja 76,489.45
B Bahan
1 Handle pintu Buah 1.000 20,000.00 20,000.00
Jumlah Harga Bahan 20,000.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 96,489.45
E Overhead + Profit ( Contoh 15% ) 15% x D 14,473.42
F Harga Satuan Pekerjaan ( D + E ) 110,962.87

A.4.6.2.5. Pemasangan 1 buah engsel pintu


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.015 111,700.00 1,675.50
2 Tukang Kayu L.02 OH 0.150 135,070.00 20,260.50
3 Kepala Tukang L.03 OH 0.0150 140,740.00 2,111.10
4 Mandor L.04 OH 0.0008 160,090.00 128.07
Jumlah Tenaga Kerja 24,175.17
B Bahan
1 Engsel Pintu Buah 1.000 22,700.00 22,700.00
Jumlah Harga Bahan 22,700.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 46,875.17
E Overhead + Profit ( Contoh 15% ) 15% x D 7,031.28
F Harga Satuan Pekerjaan ( D + E ) 53,906.45

303
A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.010 111,700.00 1,117.00
2 Tukang Kayu L.02 OH 0.100 135,070.00 13,507.00
3 Kepala Tukang L.03 OH 0.0100 140,740.00 1,407.40
4 Mandor L.04 OH 0.0005 160,090.00 80.05
Jumlah Tenaga Kerja 16,111.45
B Bahan
1 Engsel Kupu-kupu Buah 1.000 22,700.00 22,700.00
Jumlah Harga Bahan 22,700.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 38,811.45
E Overhead + Profit ( Contoh 15% ) 15% x D 5,821.72
F Harga Satuan Pekerjaan ( D + E ) 44,633.16

A.4.6.2.7. Pemasangan 1 buah engsel angin


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.100 - -
2 Tukang Kayu L.02 OH 0.200 - -
3 Kepala Tukang L.03 OH 0.0200 - -
4 Mandor L.04 OH 0.0005 - -
Jumlah Tenaga Kerja -
B Bahan
1 Engsel Angin Buah 1.000 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.6.2.8. Pemasangan 1 buah spring knip


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.015 - -
2 Tukang Kayu L.02 OH 0.150 - -
3 Kepala Tukang L.03 OH 0.0150 - -
4 Mandor L.04 OH 0.0080 - -
Jumlah Tenaga Kerja -
B Bahan
1 Spring Knip Buah 1.000 - -
Jumlah Harga Bahan -

304
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.6.2.9. Pemasangan 1 buah kait angin


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.015 111,700.00 1,675.50
2 Tukang Kayu L.02 OH 0.150 135,070.00 20,260.50
3 Kepala Tukang L.03 OH 0.0150 140,740.00 2,111.10
4 Mandor L.04 OH 0.0080 160,090.00 1,280.72
Jumlah Tenaga Kerja 25,327.82
B Bahan
1 Kait Angin Buah 1.000 22,700.00 22,700.00
Jumlah Harga Bahan 22,700.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 48,027.82
E Overhead + Profit ( Contoh 15% ) 15% x D 7,204.17
F Harga Satuan Pekerjaan ( D + E ) 55,231.99

305
A.4.6.2.9. Pemasangan 1 buah handle / grendle
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.015 111,700.00 1,675.50
2 Tukang Kayu L.02 OH 0.150 135,070.00 20,260.50
3 Kepala Tukang L.03 OH 0.0150 140,740.00 2,111.10
4 Mandor L.04 OH 0.0080 160,090.00 1,280.72
Jumlah Tenaga Kerja 25,327.82
B Bahan
1 handle Buah 1.000 22,700.00 22,700.00
Jumlah Harga Bahan 22,700.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 48,027.82
E Overhead + Profit ( Contoh 15% ) 15% x D 7,204.17
F Harga Satuan Pekerjaan ( D + E ) 55,231.99

A.4.6.2.10. Pemasangan 1 buah door closer


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.050 - -
2 Tukang Kayu L.02 OH 0.500 - -
3 Kepala Tukang L.03 OH 0.0500 - -
4 Mandor L.04 OH 0.0030 - -
Jumlah Tenaga Kerja -
B Bahan
1 Door closer Buah 1.000 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.6.2.11. Pemasangan 1 buah kunci slot


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.020 - -
2 Tukang Kayu L.02 OH 0.200 - -
3 Kepala Tukang L.03 OH 0.0200 - -
4 Mandor L.04 OH 0.0010 - -
Jumlah Tenaga Kerja -
B Bahan
1 Kunci Slot Buah 1.000 - -
Jumlah Harga Bahan -

306
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.6.2.12. Pemasangan 1 buah door holder


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.050 - -
2 Tukang Kayu L.02 OH 0.500 - -
3 Kepala Tukang L.03 OH 0.0500 - -
4 Mandor L.04 OH 0.0030 - -
Jumlah Tenaga Kerja -
B Bahan
1 Door Holder Buah 1.000 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.6.2.13. Pemasangan 1 buah door Stop


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.010 - -
2 Tukang Kayu L.02 OH 0.100 - -
3 Kepala Tukang L.03 OH 0.0100 - -
4 Mandor L.04 OH 0.0050 - -
Jumlah Tenaga Kerja -
B Bahan
1 Door Stop Buah 1.000 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.6.2.14. Pemasangan 1 buah rel pintu sorong


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.025 - -
2 Tukang Kayu L.02 OH 0.250 - -

307
3 Kepala Tukang L.03 OH 0.0250 - -
4 Mandor L.04 OH 0.0013 - -
Jumlah Tenaga Kerja -
B Bahan
1 Rel Pintu Sorong Buah 1.000 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.6.2.15. Pemasangan 1 buah kunci lemari


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.025 - -
2 Tukang Kayu L.02 OH 0.250 - -
3 Kepala Tukang L.03 OH 0.0250 - -
4 Mandor L.04 OH 0.0013 - -
Jumlah Tenaga Kerja -
B Bahan
1 Kunci Lemari Set 1.000 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.6.2.16. Pemasangan 1 m² kaca tebal 3 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.015 - -
2 Tukang Kayu L.02 OH 0.150 - -
3 Kepala Tukang L.03 OH 0.0015 - -
4 Mandor L.04 OH 0.0008 - -
Jumlah Tenaga Kerja -
B Bahan
1 Kaca Tebal 3 mm m² 1.100 - -
2 Sealant Kg 0.050 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

308
A.4.6.2.17. Pemasangan 1 m² kaca tebal 5 mm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.015 111,700.00 1,675.50
2 Tukang Kayu L.02 OH 0.150 135,070.00 20,260.50
3 Kepala Tukang L.03 OH 0.0015 140,740.00 211.11
4 Mandor L.04 OH 0.0008 160,090.00 128.07
Jumlah Tenaga Kerja 22,275.18
B Bahan
1 Kaca Tebal 5 mm m² 1.100 179,600.00 197,560.00
2 Sealant Kg 0.050 30,000.00 1,500.00
Jumlah Harga Bahan 199,060.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 221,335.18
E Overhead + Profit ( Contoh 15% ) 15% x D 33,200.28
F Harga Satuan Pekerjaan ( D + E ) 254,535.46

A.4.6.2.18. Pemasangan 1 m² kaca tebal 8 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.017 111,700.00 1,898.90
2 Tukang Kayu L.02 OH 0.170 135,070.00 22,961.90
3 Kepala Tukang L.03 OH 0.0170 140,740.00 2,392.58
4 Mandor L.04 OH 0.0009 160,090.00 144.08
Jumlah Tenaga Kerja 27,397.46
B Bahan
1 Kaca Tebal 8 mm m² 1.100 Err:509 Err:509
2 Sealant Kg 0.070 30,000.00 2,100.00
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.6.2.19. Pemasangan 1 m² kaca buram tebal 12 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.025 -
2 Tukang Kayu L.02 OH 0.250 -
3 Kepala Tukang L.03 OH 0.0250 -
4 Mandor L.04 OH 0.0013 -
Jumlah Tenaga Kerja -
B Bahan

309
1 Kaca Buram Tebal 12 mm m² 1.100 - -
2 Sealant Kg 0.070 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.6.2.20. Pemasangan 1 m² kaca cermin tebal 5 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.015 - -
2 Tukang Kayu L.02 OH 0.150 - -
3 Kepala Tukang L.03 OH 0.0150 - -
4 Mandor L.04 OH 0.0080 - -
Jumlah Tenaga Kerja -
B Bahan
1 Kaca Cermin Tebal 5 mm m² 1.100 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.6.2.21. Pemasangan 1 m² kaca cermin tebal 8 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.017 - -
2 Tukang Kayu L.02 OH 0.170 - -
3 Kepala Tukang L.03 OH 0.0170 - -
4 Mandor L.04 OH 0.0090 - -
Jumlah Tenaga Kerja -
B Bahan
1 Kaca Cermin Tebal 8 mm m² 1.100 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.6.2.22. Pemasangan 1 m² kaca wireglassed tebal 5 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7

310
A Tenaga
1 Pekerja L.01 OH 0.015 - -
2 Tukang Kayu L.02 OH 0.150 - -
3 Kepala Tukang L.03 OH 0.0150 - -
4 Mandor L.04 OH 0.0080 - -
Jumlah Tenaga Kerja -
B Bahan
1 kaca wireglassed tebal 5 mm m² 1.100 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.6.2.23. Pemasangan 1 m² kaca patri tebal 5 mm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.075 - -
2 Tukang Kayu L.02 OH 0.150 - -
3 Kepala Tukang L.03 OH 0.0150 - -
4 Mandor L.04 OH 0.0040 - -
Jumlah Tenaga Kerja -
B Bahan
1 kaca patri tebal 5 mm m² 1.100 - -
2 Sealant L.03 Kg 0.0150 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

311
A.4.7.1. HARGA SATUAN PEKERJAAN PENGECATAN
A.4.7.1.1. 1 m² pengikisan / pengerokan permukaan cat lama
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.150 111,700.00 16,755.00
2 Mandor L.04 OH 0.003 160,090.00 480.27
Jumlah Tenaga Kerja 17,235.27
B Bahan
1 Soda Api Kg 0.050 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.7.1.2. 1 m² pencucian bidang permukaan tembok yang pernah dicat


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.150 111,700.00 16,755.00
2 Mandor L.04 OH 0.003 160,090.00 480.27
Jumlah Tenaga Kerja 16,755.00
B Bahan
1 Sabun Kg 0.050 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.7.1.3. 1 m² pengerokan karat pada permukaan baja cara manual


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.150 111,700.00 16,755.00
2 Mandor L.04 OH 0.008 160,090.00 1,280.72
Jumlah Tenaga Kerja 16,755.00
B Bahan
1 Sabun Kg 0.050 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509

312
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.4.7.1.4. 1 m² pengecatan bidang kayu baru ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.070 111,700.00 7,819.00
2 Tukang Cat L.02 OH 0.009 135,070.00 1,215.63
3 Kepala Tukang L.03 OH 0.006 140,740.00 844.44
4 Mandor L.04 OH 0.003 160,090.00 480.27
Jumlah Tenaga Kerja 10,359.34
B Bahan
1 Cat Menie Kg 0.200 33,600.00 6,720.00
2 Plamir Kg 0.150 6,200.00 930.00
3 Cat Dasar Kg 0.170 51,800.00 8,806.00
4 Cat Penutup Kg 0.260 51,800.00 13,468.00
5 Kuas Buah 0.010 10,500.00 105.00
6 Pengencer Kg 0.030 25,800.00 774.00
7 Ampelas Lembar 0.200 5,600.00 1,120.00
Jumlah Harga Bahan 31,923.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 42,282.34
E Overhead + Profit ( Contoh 15% ) 15% x D 6,342.35
F Harga Satuan Pekerjaan ( D + E ) 48,624.69

A.4.7.1.5. 1 m² pengecatan bidang kayu baru ( 1 lapis plamir, 1 lapis cat dasar, 3 lapis cat penutup )
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.070 111,700.00 7,819.00
2 Tukang Cat L.02 OH 0.105 135,070.00 14,182.35
3 Kepala Tukang L.03 OH 0.004 140,740.00 562.96
4 Mandor L.04 OH 0.003 160,090.00 480.27
Jumlah Tenaga Kerja 23,044.58
B Bahan
1 Cat Menie Kg 0.200 33,600.00 6,720.00
2 Plamir Kg 0.150 6,200.00 930.00
3 Cat Dasar Kg 0.170 51,800.00 8,806.00
4 Cat Penutup Kg 0.350 51,800.00 18,130.00
5 Kuas Buah 0.010 10,500.00 105.00
6 Pengencer Kg 0.030 25,800.00 774.00
7 Ampelas Lembar 0.200 5,600.00 1,120.00
Jumlah Harga Bahan 36,585.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 59,629.58
E Overhead + Profit ( Contoh 15% ) 15% x D 8,944.44

313
F Harga Satuan Pekerjaan ( D + E ) 68,574.02

A.4.7.1.6. Pelaburan 1 m² bidang kayu teak oil


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.040 - -
2 Tukang Cat L.02 OH 0.063 - -
3 Kepala Tukang L.03 OH 0.063 - -
4 Mandor L.04 OH 0.003 - -
Jumlah Tenaga Kerja -
B Bahan
1 Teak Oil Liter 0.360 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.7.1.9. Pelaburan 1 m² bidang kayu dengan vernis


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.160 -
2 Tukang Cat L.02 OH 0.160 -
3 Kepala Tukang L.03 OH 0.016 -
4 Mandor L.04 OH 0.003 -
Jumlah Tenaga Kerja -
B Bahan
1 Vernis Liter 0.150 - -
2 Dempul Kg 0.050 - -
3 Ampelas Lembar 0.100 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.7.1.10. Pengecataan 1 m² tembok baru ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.020 111,700.00 2,234.00
2 Tukang Cat L.02 OH 0.063 135,070.00 8,509.41
3 Kepala Tukang L.03 OH 0.0063 140,740.00 886.66
4 Mandor L.04 OH 0.003 160,090.00 480.27

314
Jumlah Tenaga Kerja 12,110.34
B Bahan
1 Plamir Kg 0.100 6,200.00 620.00
2 Cat Dasar Kg 0.100 83,000.00 8,300.00
3 Cat Penutup Kg 0.260 83,000.00 21,580.00
Jumlah Harga Bahan 30,500.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 42,610.34
E Overhead + Profit ( Contoh 15% ) 15% x D 6,391.55
F Harga Satuan Pekerjaan ( D + E ) 49,001.89

A.4.7.1.11. Pengecataan 1 m² tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup )
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.028 111,700.00 3,127.60
2 Tukang Cat L.02 OH 0.042 135,070.00 5,672.94
3 Kepala Tukang L.03 OH 0.0042 140,740.00 591.11
4 Mandor L.04 OH 0.003 160,090.00 480.27
Jumlah Tenaga Kerja 9,871.92
B Bahan
1 Cat Dasar Kg 0.120 83,000.00 9,960.00
2 Cat Penutup Kg 0.180 83,000.00 14,940.00
Jumlah Harga Bahan 24,900.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 34,771.92
E Overhead + Profit ( Contoh 15% ) 15% x D 5,215.79
F Harga Satuan Pekerjaan ( D + E ) 39,987.71

A.4.7.1.13. Pelaburan 1 m² tembok dengan kapur sirih


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.150 - -
2 Tukang Cat L.02 OH 0.001 - -
3 Kepala Tukang L.03 OH 0.0001 - -
4 Mandor L.04 OH 0.0025 - -
Jumlah Tenaga Kerja -
B Bahan
1 Kapur Sirih Kg 0.150 - -
2 Ampelas Lembar 0.100 - -
3 Alang-alang Ikat 0.250 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -

315
F Harga Satuan Pekerjaan ( D + E ) -

A.4.7.1.14. Pelaburan 1 m² tembok lama dengan kapur sirih ( Pemeliharaan )


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.040 - -
2 Tukang Cat L.02 OH 0.005 - -
3 Kepala Tukang L.03 OH 0.0005 - -
4 Mandor L.04 OH 0.0025 - -
Jumlah Tenaga Kerja -
B Bahan
1 Kapur Sirih Kg 0.300 - -
2 Ampelas Lembar 0.300 - -
3 Alang-alang Ikat 0.250 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.7.1.15. Pemasangan 1 m² wallpaper


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.020 - -
2 Tukang Cat L.02 OH 0.200 - -
3 Kepala Tukang L.03 OH 0.020 - -
4 Mandor L.04 OH 0.0025 - -
Jumlah Tenaga Kerja -
B Bahan
1 Wallpaper m 1.200 - -
2 Lem Kg 0.200 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.7.1.16. Pengecatan 1 m² permukaan baja dengan menie besi


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.020 111,700.00 2,234.00
2 Tukang Cat L.02 OH 0.200 135,070.00 27,014.00
3 Kepala Tukang L.03 OH 0.020 140,740.00 2,814.80

316
4 Mandor L.04 OH 0.0025 160,090.00 400.23
Jumlah Tenaga Kerja 32,463.03
B Bahan
1 Menie Besi m 0.100 33,600.00 3,360.00
2 Kuas Buah 0.010 10,500.00 105.00
Jumlah Harga Bahan 3,465.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 35,928.03
E Overhead + Profit ( Contoh 15% ) 15% x D 5,389.20
F Harga Satuan Pekerjaan ( D + E ) 41,317.23

A.4.7.1.17. Pengecatan 1 m² permukaan baja dengan menie besi dengan perancah


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.020 - -
2 Tukang Cat L.02 OH 0.200 - -
3 Kepala Tukang L.03 OH 0.020 - -
4 Mandor L.04 OH 0.0025 - -
Jumlah Tenaga Kerja -
B Bahan
1 Menie Besi Kg 0.100 - -
2 Pengencer Liter 0.010 - -
3 Kuas Buah 0.010 - -
4 Perancah Kayu m³ 0.002 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.7.1.18. Pengecatan 1 m² permukaan baja galvanis secara manual 4 lapis


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.250 - -
2 Tukang Cat L.02 OH 0.250 - -
3 Kepala Tukang L.03 OH 0.025 - -
4 Mandor L.04 OH 0.0013 - -
Jumlah Tenaga Kerja -
B Bahan
1 Menie Besi A Kg 0.100 - -
2 Menie Besi B Kg 0.100 - -
3 Cat Kg 0.080 - -
4 Kuas Buah 0.010 - -
5 Pengencer Liter 0.010 - -
Jumlah Harga Bahan -

317
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.7.1.19. Pengecatan 1 m² permukaan baja galvanis secara manual sistem 1 lapis cat mutakhir
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.060 - -
2 Tukang Cat L.02 OH 0.060 - -
3 Kepala Tukang L.03 OH 0.012 - -
4 Mandor L.04 OH 0.0030 - -
Jumlah Tenaga Kerja -
B Bahan
1 Cat Kg 0.300 - -
2 Kuas Buah 0.010 - -
3 Pengencer Liter 0.010 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.7.1.20. Pengecatan 1 m² permukaan baja galvanis secara manual sistem 3 lapis


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.400 - -
2 Tukang Cat L.02 OH 0.800 - -
3 Kepala Tukang L.03 OH 0.080 - -
4 Mandor L.04 OH 0.0200 - -
Jumlah Tenaga Kerja -
B Bahan
1 Cat Dasar Kg 0.110 - -
2 Cat Antara Kg 0.170 - -
3 Cat Penutup Kg 0.080 - -
4 Kuas Buah 0.010 - -
5 Pengencer Liter 0.010 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.4.7.1.21. Pengecatan 1 m² permukaan baja galvanis secara semprot sistem 3 lapis cat
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian

318
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.400 - -
2 Tukang Cat L.02 OH 0.700 - -
3 Kepala Tukang L.03 OH 0.070 - -
4 Mandor L.04 OH 0.0200 - -
Jumlah Tenaga Kerja -
B Bahan
1 Cat Dasar Kg 0.300 - -
2 Pengencer Liter 0.010 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.5.1.1. HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG


A.5.1.1.1. Pemasangan 1 buah closet duduk / monoblock
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 3.300 111,700.00 368,610.00
2 Tukang Batu L.02 OH 1.100 135,070.00 148,577.00
3 Kepala Tukang L.03 OH 0.010 140,740.00 1,407.40
4 Mandor L.04 OH 0.160 160,090.00 25,614.40
Jumlah Tenaga Kerja 544,208.80
B Bahan
1 Closet Duduk Unit 1.000 1,714,000.00 1,714,000.00
2 Perlengkapan Ls 6% x Closet 102,840.00 102,840.00
Jumlah Harga Bahan 1,816,840.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 2,361,048.80
E Overhead + Profit ( Contoh 15% ) 15% x D 354,157.32
F Harga Satuan Pekerjaan ( D + E ) 2,715,206.12

A.5.1.1.2. Pemasangan 1 buah closet jongkok porslen


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.000 111,700.00 111,700.00
2 Tukang Batu L.02 OH 1.500 135,070.00 202,605.00
3 Kepala Tukang L.03 OH 0.150 140,740.00 21,111.00
4 Mandor L.04 OH 0.160 160,090.00 25,614.40

319
Jumlah Tenaga Kerja 361,030.40
B Bahan
1 Closet Jongkok Unit 1.000 Err:509 Err:509
2 Semen Portland Kg 6.000 2,000.00 12,000.00
3 Pasir Pasang m³ 0.010 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.5.1.1.3. Pemasangan 1 buah closet jongkok teraso


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.000 - -
2 Tukang Batu L.02 OH 1.500 - -
3 Kepala Tukang L.03 OH 0.150 - -
4 Mandor L.04 OH 0.050 - -
Jumlah Tenaga Kerja -
B Bahan
1 Closet Jongkok Unit 1.000 - -
2 Semen Portland Kg 6.000 - -
3 Pasir Pasang m³ 0.010 - -
4 Bata Merah Bh 7.000 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.5.1.1.4. Pemasangan 1 buah urinoir


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.000 111,700.00 111,700.00
2 Tukang Batu L.02 OH 1.000 135,070.00 135,070.00
3 Kepala Tukang L.03 OH 0.100 140,740.00 14,074.00
4 Mandor L.04 OH 0.050 160,090.00 8,004.50
Jumlah Tenaga Kerja 268,848.50
B Bahan
1 Urinoir Unit 1.000 Err:509 Err:509
2 Semen Portland Kg 6.000 2,000.00 12,000.00
3 Pasir Pasang m³ 0.010 187,900.00 1,879.00
4 Perlengkapan % 30.000 0.30 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0

320
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.5.1.1.5. Pemasangan 1 buah washtafel


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 1.200 111,700.00 134,040.00
2 Tukang Batu L.02 OH 1.450 135,070.00 195,851.50
3 Kepala Tukang L.03 OH 0.150 140,740.00 21,111.00
4 Mandor L.04 OH 0.060 160,090.00 9,605.40
Jumlah Tenaga Kerja 360,607.90
B Bahan
1 Washtafel Unit 1.200 1,428,400.00 1,714,080.00
2 Semen Portland Kg 6.000 2,000.00 12,000.00
3 Pasir Pasang m³ 0.010 187,900.00 1,879.00
4 Perlengkapan % 12.000 0.12 207,355.08
Jumlah Harga Bahan 1,935,314.08
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 2,295,921.98
E Overhead + Profit ( Contoh 15% ) 15% x D 344,388.30
F Harga Satuan Pekerjaan ( D + E ) 2,640,310.28

321
A.5.1.1.6. Pemasangan 1 buah bathcuip porselen
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.075 - -
2 Tukang Batu L.02 OH 0.750 - -
3 Kepala Tukang L.03 OH 0.075 - -
4 Mandor L.04 OH 0.003 - -
Jumlah Tenaga Kerja -
B Bahan
1 Bathcuip Unit 1.200 - -
2 Perlengkapan % 20.000 0.20 0.20
Jumlah Harga Bahan 0.20
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 0.20
E Overhead + Profit ( Contoh 15% ) 15% x D 0.03
F Harga Satuan Pekerjaan ( D + E ) 0.23

A.5.1.1.7. Pemasangan 1 buah bak fibreglass vol 1 m³


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 3.000 - -
2 Tukang Batu L.02 OH 4.500 - -
3 Kepala Tukang L.03 OH 0.050 - -
4 Mandor L.04 OH 0.900 - -
Jumlah Tenaga Kerja -
B Bahan
1 Bak Fibreglass Unit 1.000 - -
2 Perlengkapan Ls 12% x bak - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.5.1.1.8. Pemasangan 1 buah bak mandi batu bata vol 0,30 m³


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 6.000 111,700.00 670,200.00
2 Tukang Batu L.02 OH 3.000 135,070.00 405,210.00
3 Kepala Tukang L.03 OH 0.300 140,740.00 42,222.00
4 Mandor L.04 OH 0.030 160,090.00 4,802.70
Jumlah Tenaga Kerja 1,122,434.70
B Bahan

322
1 Bata Merah m³ 150.000 900.00 135,000.00
2 Semen Portland Kg 120.000 2,000.00 240,000.00
3 Pasir Pasang m³ 0.300 Err:509 Err:509
4 Porselen 11 x 11 Buah 360.000 1,400.00 504,000.00
5 Semen Warna Kg 6.000 2,294.00 13,764.00
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.5.1.1.9. Pemasangan 1 buah bak mandi traso vol 0,30 m³


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 3.000 - -
2 Tukang Batu L.02 OH 4.500 - -
3 Kepala Tukang L.03 OH 0.050 - -
4 Mandor L.04 OH 0.900 - -
Jumlah Tenaga Kerja -
B Bahan
1 Bak Fibreglass Unit 1.000 - -
2 Perlengkapan Ls 12% x Bak - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan Per - M³ ( D + E ) -

A.5.1.1.10. Pemasangan 1 buah bak air fibreglass vol 1 m³


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.300 - -
2 Tukang Batu L.02 OH 0.450 - -
3 Kepala Tukang L.03 OH 0.045 - -
4 Mandor L.04 OH 0.015 - -
Jumlah Tenaga Kerja -
B Bahan
1 Bak Fibreglass Unit 1.000 - -
2 Perlengkapan % 12.000 0.12 0.12
Jumlah Harga Bahan 0.12
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 0.12
E Overhead + Profit ( Contoh 15% ) 15% x D 0.02
F Harga Satuan Pekerjaan ( D + E ) 0.14

323
A.5.1.1.11. Pemasangan 1 buah bak beton vol 1 m³
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7

A Tenaga
1 Pekerja L.01 OH 3.500 - -
2 Tukang Batu L.02 OH 4.500 - -
3 Kepala Tukang L.03 OH 0.050 - -
4 Mandor L.04 OH 0.018 - -
Jumlah Tenaga Kerja -
B Bahan
1 Beton 1 : 2 : 3 m³ 0.900 - -
2 Baja Tulangan Kg 180.000 - -
3 Kayu Eksisting m² 8.000 - -
4 Ubin Porselen Buah 500.000 - -
5 Perlengkapan % 10.000 0.10 0.10
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.5.1.1.12. Pemasangan 1 buah bak cuci piring


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.030 111,700.00 3,351.00
2 Tukang Batu L.02 OH 0.300 135,070.00 40,521.00
3 Kepala Tukang L.03 OH 0.030 140,740.00 4,222.20
4 Mandor L.04 OH 0.015 160,090.00 2,401.35
Jumlah Tenaga Kerja 50,495.55
B Bahan
1 Bak Cuci Piring Unit 0.900 212,900.00 191,610.00
2 Waterdrain Buah 180.000 - -
Jumlah Harga Bahan 191,610.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 242,105.55
E Overhead + Profit ( Contoh 15% ) 15% x D 36,315.83
F Harga Satuan Pekerjaan ( D + E ) 278,421.38

A.5.1.1.13. Pemasangan 1 buah bak cuci piring traso


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.050 - -
2 Tukang Batu L.02 OH 0.500 - -
3 Kepala Tukang L.03 OH 0.050 - -

324
4 Mandor L.04 OH 0.025 - -
Jumlah Tenaga Kerja -
B Bahan
1 Bak Cuci Piring Unit 1.000 - -
2 Waterdrain Buah 1.000 - -
3 Semen Portland Kg 20.000 - -
4 Pasir Pasang m³ 0.050 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.5.1.1.14. Pemasangan 1 buah floor drain


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.010 111,700.00 1,117.00
2 Tukang Batu L.02 OH 0.100 135,070.00 13,507.00
3 Kepala Tukang L.03 OH 0.010 140,740.00 1,407.40
4 Mandor L.04 OH 0.005 160,090.00 800.45
Jumlah Tenaga Kerja 16,831.85
B Bahan
1 Floor Drain Unit 1.000 57,100.00 57,100.00
Jumlah Harga Bahan 57,100.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 73,931.85
E Overhead + Profit ( Contoh 15% ) 15% x D 11,089.78
F Harga Satuan Pekerjaan ( D + E ) 85,021.63

325
A.5.1.1.15. Pemasangan 1 buah bak kontrol pasangan bata 30 x 30 tinggi 35 cm
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7

A Tenaga
1 Pekerja L.01 OH 2.160 111,700.00 241,272.00
2 Tukang Batu L.02 OH 0.720 135,070.00 97,250.40
3 Kepala Tukang L.03 OH 0.072 140,740.00 10,133.28
4 Mandor L.04 OH 0.011 160,090.00 1,760.99
Jumlah Tenaga Kerja 350,416.67
B Bahan
1 Bata Merah Buah 40.000 900.00 36,000.00
2 Semen Portland Kg 44.000 2,000.00 88,000.00
3 Pasir Pasang m³ 0.070 Err:509 Err:509
4 Pasir Beton m³ 0.060 Err:509 Err:509
5 Kerikil m³ 0.070 573,600.00 40,152.00
6 Baja Tulangan Kg 1.600 15,900.00 25,440.00
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.5.1.1.16. Pemasangan 1 buah bak kontrol pasangan bata 45 x 45 tinggi 50 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 3.200 111,700.00 357,440.00
2 Tukang Batu L.02 OH 1.150 135,070.00 155,330.50
3 Kepala Tukang L.03 OH 0.011 140,740.00 1,548.14
4 Mandor L.04 OH 0.016 160,090.00 2,561.44
Jumlah Tenaga Kerja 516,880.08
B Bahan
1 Bata Merah Buah 70.000 900.00 63,000.00
2 Semen Portland Kg 77.000 2,000.00 154,000.00
3 Pasir Pasang m³ 0.130 Err:509 Err:509
4 Pasir Beton m³ 0.090 Err:509 Err:509
5 Kerikil m³ 0.020 573,600.00 11,472.00
6 Baja Tulangan Kg 2.600 15,900.00 41,340.00
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.5.1.1.17. Pemasangan 1 buah bak kontrol pasangan bata 60 x 60 tinggi 65 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )

326
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 3.200 111,700.00 357,440.00
2 Tukang Batu L.02 OH 1.150 135,070.00 155,330.50
3 Kepala Tukang L.03 OH 0.011 140,740.00 1,548.14
4 Mandor L.04 OH 0.016 160,090.00 2,561.44
Jumlah Tenaga Kerja 516,880.08
B Bahan
1 Bata Merah Buah 123.000 900.00 110,700.00
2 Semen Portland Kg 114.000 2,000.00 228,000.00
3 Pasir Pasang m³ 0.184 Err:509 Err:509
4 Pasir Beton m³ 0.120 Err:509 Err:509
5 Kerikil m³ 0.033 573,600.00 18,928.80
6 Baja Tulangan Kg 4.850 15,900.00 77,115.00
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.5.1.1.18. Pemasangan 1 m¹ pipa galvanis ؽ"


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.010 111,700.00 1,117.00
2 Tukang Batu L.02 OH 0.400 135,070.00 54,028.00
3 Kepala Tukang L.03 OH 0.040 140,740.00 5,629.60
4 Mandor L.04 OH 0.005 160,090.00 800.45
Jumlah Tenaga Kerja 61,575.05
B Bahan
1 Pipa Galvanis ؽ" m¹ 1.200 Err:509 Err:509
2 Perlengkapan Ls 35% x Pipa Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.5.1.1.14. Pemasangan 1 buah shower


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.010 111,700.00 1,117.00
2 Tukang Batu L.02 OH 0.100 135,070.00 13,507.00
3 Kepala Tukang L.03 OH 0.010 140,740.00 1,407.40
4 Mandor L.04 OH 0.005 160,090.00 800.45
Jumlah Tenaga Kerja 16,831.85

327
B Bahan
1 shower Unit 1.000 206,100.00 206,100.00
Jumlah Harga Bahan 206,100.00
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 222,931.85
E Overhead + Profit ( Contoh 15% ) 15% x D 33,439.78
F Harga Satuan Pekerjaan ( D + E ) 256,371.63

A.5.1.1.19. Pemasangan 1 buah kran air ؽ" atau ؾ"


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.010 111,700.00 1,117.00
2 Tukang Batu L.02 OH 0.400 135,070.00 54,028.00
3 Kepala Tukang L.03 OH 0.040 140,740.00 5,629.60
4 Mandor L.04 OH 0.005 160,090.00 800.45
Jumlah Tenaga Kerja 61,575.05
B Bahan
1 Kran Air ؽ" atau ؾ m¹ 1.000 43,900.00 43,900.00
2 Sealtape Buah 0.025 15,365.00 384.13
Jumlah Harga Bahan 44,284.13
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 105,859.18
E Overhead + Profit ( Contoh 15% ) 15% x D 15,878.88
F Harga Satuan Pekerjaan ( D + E ) 121,738.05

328
A.5.1.1.20. Pemasangan 1 m¹ pipa galvanis ؾ"
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.054 111,700.00 6,031.80
2 Tukang Batu L.02 OH 0.090 135,070.00 12,156.30
3 Kepala Tukang L.03 OH 0.009 140,740.00 1,266.66
4 Mandor L.04 OH 0.027 160,090.00 4,322.43
Jumlah Tenaga Kerja 23,777.19
B Bahan
1 Pipa Galvanis ؾ" m¹ 1.200 Err:509 Err:509
2 Perlengkapan % 35.000 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.5.1.1.21. Pemasangan 1 m¹ pipa galvanis Ø1"


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.054 111,700.00 6,031.80
2 Tukang Batu L.02 OH 0.090 135,070.00 12,156.30
3 Kepala Tukang L.03 OH 0.009 140,740.00 1,266.66
4 Mandor L.04 OH 0.027 160,090.00 4,322.43
Jumlah Tenaga Kerja 23,777.19
B Bahan
1 Pipa Galvanis Ø1" m¹ 1.200 Err:509 Err:509
2 Perlengkapan % 35.000 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.5.1.1.22. Pemasangan 1 m¹ pipa galvanis Ø1½"


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.108 111,700.00 12,063.60
2 Tukang Batu L.02 OH 0.180 135,070.00 24,312.60
3 Kepala Tukang L.03 OH 0.018 140,740.00 2,533.32
4 Mandor L.04 OH 0.005 160,090.00 800.45
Jumlah Tenaga Kerja 39,709.97
B Bahan

329
1 Pipa Galvanis Ø1½" m¹ 1.200 Err:509 Err:509
2 Perlengkapan % 35.000 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 10% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.5.1.1.23. Pemasangan 1 m¹ pipa galvanis Ø2"


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.135 111,700.00 15,079.50
2 Tukang Batu L.02 OH 0.225 135,070.00 30,390.75
3 Kepala Tukang L.03 OH 0.023 140,740.00 3,237.02
4 Mandor L.04 OH 0.007 160,090.00 1,120.63
Jumlah Tenaga Kerja 49,827.90
B Bahan
1 Pipa Galvanis Ø3" m¹ 1.200 Err:509 Err:509
2 Perlengkapan % 35.000 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 10% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.5.1.1.23. Pemasangan 1 m¹ pipa galvanis Ø3"


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.135 111,700.00 15,079.50
2 Tukang Batu L.02 OH 0.225 135,070.00 30,390.75
3 Kepala Tukang L.03 OH 0.023 140,740.00 3,237.02
4 Mandor L.04 OH 0.007 160,090.00 1,120.63
Jumlah Tenaga Kerja 49,827.90
B Bahan
1 Pipa Galvanis Ø3" m¹ 1.200 Err:509 Err:509
2 Perlengkapan + Assesoris (cat) % 35.000 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 10% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.5.1.1.24. Pemasangan 1 m¹ pipa galvanis Ø4"


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian

330
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.135 111,700.00 15,079.50
2 Tukang Batu L.02 OH 0.225 135,070.00 30,390.75
3 Kepala Tukang L.03 OH 0.023 140,740.00 3,237.02
4 Mandor L.04 OH 0.007 160,090.00 1,120.63
Jumlah Tenaga Kerja 49,827.90
B Bahan
1 Pipa Galvanis Ø4" m¹ 1.200 Err:509 Err:509
2 Perlengkapan % 35.000 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.5.1.1.25. Pemasangan 1 m¹ PVC type AW ؽ"


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.036 111,700.00 4,021.20
2 Tukang Batu L.02 OH 0.060 135,070.00 8,104.20
3 Kepala Tukang L.03 OH 0.006 140,740.00 844.44
4 Mandor L.04 OH 0.002 160,090.00 320.18
Jumlah Tenaga Kerja 13,290.02
B Bahan
1 Pipa PVC ؽ" m¹ 1.200 5,150.00 6,180.00
2 Perlengkapan % 35.000 1,802.50 1,802.50
Jumlah Harga Bahan 7,982.50
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 21,272.52
E Overhead + Profit ( Contoh 15% ) 10% x D 2,127.25
F Harga Satuan Pekerjaan ( D + E ) 23,399.77

331
A.5.1.1.26. Pemasangan 1 m¹ PVC type AW ؾ"
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.036 111,700.00 4,021.20
2 Tukang Batu L.02 OH 0.060 135,070.00 8,104.20
3 Kepala Tukang L.03 OH 0.006 140,740.00 844.44
4 Mandor L.04 OH 0.002 160,090.00 320.18
Jumlah Tenaga Kerja 13,290.02
B Bahan
1 Pipa PVC ؾ" m¹ 1.200 6,250.00 7,500.00
2 Perlengkapan % 35.000 2,187.50 2,187.50
Jumlah Harga Bahan 9,687.50
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 22,977.52
E Overhead + Profit ( Contoh 10% ) 10% x D 2,297.75
F Harga Satuan Pekerjaan ( D + E ) 25,275.27

A.5.1.1.27. Pemasangan 1 m¹ PVC type AW Ø1"


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.036 111,700.00 4,021.20
2 Tukang Batu L.02 OH 0.060 135,070.00 8,104.20
3 Kepala Tukang L.03 OH 0.006 140,740.00 844.44
4 Mandor L.04 OH 0.002 160,090.00 320.18
Jumlah Tenaga Kerja 13,290.02
B Bahan
1 Pipa PVC Ø1" m¹ 1.200 Err:509 Err:509
2 Perlengkapan % 35.000 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) Err:509
E Overhead + Profit ( Contoh 15% ) 15% x D Err:509
F Harga Satuan Pekerjaan ( D + E ) Err:509

A.5.1.1.28. Pemasangan 1 m¹ PVC type AW Ø1½"


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.054 - -
2 Tukang Batu L.02 OH 0.090 - -
3 Kepala Tukang L.03 OH 0.009 - -
4 Mandor L.04 OH 0.003 - -
Jumlah Tenaga Kerja -
B Bahan

332
1 Pipa PVC Ø1½" m¹ 1.200 - -
2 Perlengkapan % 35.000 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.5.1.1.29. Pemasangan 1 m¹ PVC type AW Ø2"


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.054 111,700.00 6,031.80
2 Tukang Batu L.02 OH 0.090 135,070.00 12,156.30
3 Kepala Tukang L.03 OH 0.009 140,740.00 1,266.66
4 Mandor L.04 OH 0.003 160,090.00 480.27
Jumlah Tenaga Kerja 19,935.03
B Bahan
1 Pipa PVC Ø2" m¹ 1.200 18,475.00 22,170.00
2 Perlengkapan % 35.000 6,466.25 6,466.25
Jumlah Harga Bahan 28,636.25
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 48,571.28
E Overhead + Profit ( Contoh 10% ) 10% x D 4,857.13
F Harga Satuan Pekerjaan ( D + E ) 53,428.41

333
A.5.1.1.30. Pemasangan 1 m¹ PVC type AW Ø2½"
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.081 - -
2 Tukang Batu L.02 OH 0.135 - -
3 Kepala Tukang L.03 OH 0.0135 - -
4 Mandor L.04 OH 0.004 - -
Jumlah Tenaga Kerja -
B Bahan
1 Pipa PVC Ø2½" m¹ 1.200 - -
2 Perlengkapan % 35.000 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.5.1.1.31. Pemasangan 1 m¹ PVC type AW Ø3"


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7

A Tenaga
1 Pekerja L.01 OH 0.081 111,700.00 9,047.70
2 Tukang Batu L.02 OH 0.135 135,070.00 18,234.45
3 Kepala Tukang L.03 OH 0.0135 140,740.00 1,899.99
4 Mandor L.04 OH 0.004 160,090.00 640.36
Jumlah Tenaga Kerja 29,822.50
B Bahan
1 Pipa PVC Ø3" m¹ 1.200 32,625.00 39,150.00
2 Perlengkapan % 35.000 11,418.75 11,418.75
Jumlah Harga Bahan 50,568.75
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 80,391.25
E Overhead + Profit ( Contoh 10% ) 10% x D 8,039.13
F Harga Satuan Pekerjaan ( D + E ) 88,430.38

A.5.1.1.32. Pemasangan 1 m¹ PVC type AW Ø4"


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.081 111,700.00 9,047.70
2 Tukang Batu L.02 OH 0.135 135,070.00 18,234.45
3 Kepala Tukang L.03 OH 0.0135 140,740.00 1,899.99
4 Mandor L.04 OH 0.004 160,090.00 640.36
Jumlah Tenaga Kerja 29,822.50
B Bahan

334
1 Pipa PVC Ø4" m¹ 1.200 52,750.00 63,300.00
2 Perlengkapan % 35.000 18,462.50 18,462.50
Jumlah Harga Bahan 81,762.50
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 111,585.00
E Overhead + Profit ( Contoh 10% ) 10% x D 11,158.50
F Harga Satuan Pekerjaan ( D + E ) 122,743.50

335
A.5.1.1.32. Pemasangan 1 m¹ PVC type AW Ø6"
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.081 111,700.00 9,047.70
2 Tukang Batu L.02 OH 0.135 135,070.00 18,234.45
3 Kepala Tukang L.03 OH 0.0135 140,740.00 1,899.99
4 Mandor L.04 OH 0.004 160,090.00 640.36
Jumlah Tenaga Kerja 29,822.50
B Bahan
1 Pipa PVC Ø6" m¹ 1.200 138,750.00 166,500.00
2 Perlengkapan % 35.000 48,562.50 48,562.50
Jumlah Harga Bahan 215,062.50
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 244,885.00
E Overhead + Profit ( Contoh 10% ) 10% x D 24,488.50
F Harga Satuan Pekerjaan ( D + E ) 269,373.50

A.5.1.1.33. Pemasangan 1 m¹ pipa air limbah jenis pipa tanah Ø20 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.080 - -
2 Tukang Batu L.02 OH 0.040 - -
3 Kepala Tukang L.03 OH 0.0040 - -
4 Mandor L.04 OH 0.004 - -
Jumlah Tenaga Kerja -
B Bahan
1 Pipa Tanah Ø20 cm Buah 1.600 - -
2 Semen Portland Kg 35.000 - -
3 Pasir Pasang m³ 0.014 - -
4 Pasir Urug m³ 0.014 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.5.1.1.34. Pemasangan 1 m¹ pipa air limbah jenis pipa tanah Ø15 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.060 - -
2 Tukang Batu L.02 OH 0.030 - -
3 Kepala Tukang L.03 OH 0.0030 - -
4 Mandor L.04 OH 0.003 - -

336
Jumlah Tenaga Kerja -
B Bahan
1 Pipa Tanah Ø15cm Buah 1.600 - -
2 Semen Portland Kg 0.680 - -
3 Pasir Pasang m³ 0.013 - -
4 Pasir Urug m³ 0.011 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.5.1.1.35. Pemasangan 1 m¹ pipa beton Ø15 - Ø20 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.140 - -
2 Tukang Batu L.02 OH 0.070 - -
3 Kepala Tukang L.03 OH 0.0070 - -
4 Mandor L.04 OH 0.007 - -
Jumlah Tenaga Kerja -
B Bahan
1 Pipa Tanah Ø15 - Ø20 cm Buah 1.100 - -
2 Bata Merah m³ 0.027 - -
3 Semen Portland Kg 3.920 - -
4 Pasir Pasang m³ 0.056 - -
5 Pasir Urug m³ 0.024 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.5.1.1.36. Pemasangan 1 m¹ pipa beton Ø30 - Ø100 cm


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.380 - -
2 Tukang Batu L.02 OH 0.190 - -
3 Kepala Tukang L.03 OH 0.0190 - -
4 Mandor L.04 OH 0.019 - -
Jumlah Tenaga Kerja -
B Bahan
1 Pipa Tanah Ø30 - Ø100 cm Buah 1.100 - -
2 Bata Merah m³ 0.550 - -
3 Semen Portland Kg 10.300 - -
4 Pasir Pasang m³ 0.061 - -

337
5 Pasir Urug m³ 0.069 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) -
E Overhead + Profit ( Contoh 15% ) 15% x D -
F Harga Satuan Pekerjaan ( D + E ) -

A.5.1.1. HARGA SATUAN PEKERJAAN PEMANCANGAN


A.5.1.1.1. Pemancangan 1 m Tiang Beton Dengan Drop Hammer Mini Pile
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.040 111,700.00 4,468.00
2 Mandor L.04 OH 0.002 160,090.00 320.18
Jumlah Tenaga Kerja 4,788.18
B Bahan
1 - -
Jumlah Harga Bahan -
C Peralatan
1 Drop Hammer Mini Pile Jam 0.117 - -
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 4,788.18
E Overhead + Profit ( Contoh 10% ) 10% x D 478.82
F Harga Satuan Pekerjaan ( D + E ) 5,267.00

338
A.5.1.1.1. Pemotongan 1 Buah Tiang Beton
Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH 0.125 111,700.00 13,962.50
2 Mandor L.04 OH 0.030 160,090.00 4,802.70
Jumlah Tenaga Kerja 18,765.20
B Bahan
1 Alat bantu 1.000 20,000.00 20,000.00
Jumlah Harga Bahan 20,000.00
C Peralatan
1 - -
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 38,765.20
E Overhead + Profit ( Contoh 10% ) 10% x D 3,876.52
F Harga Satuan Pekerjaan ( D + E ) 42,641.72

A.5.1.1.1. Penyambungan 1 m tiang pancang beton


Harga Satuan JUMLAH
No. URAIAN KODE Satuan Koefesian
( Rp. ) ( Rp. )
1 2 3 4 5 6 7
A Tenaga
1 Pekerja L.01 OH - 111,700.00 -
1 Tukang las L.02 OH 0.330 135,070.00 44,573.10
Jumlah Tenaga Kerja 44,573.10
B Bahan
1 Besi pelat kg 0.091 - -
1 Kawat las kg 3.200 17,650.00 56,480.00
Jumlah Harga Bahan 56,480.00
C Peralatan
1 Mesin las jam 0.083 - -
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C ) 101,053.10
E Overhead + Profit ( Contoh 10% ) 10% x D 10,105.31
F Harga Satuan Pekerjaan ( D + E ) 111,158.41

339
PT. BUMI KALTARA KONSULTAN
Perencanaan, Pengawasan, Pengukuran, dan Manajemen Konstruksi
Alamat : JL. P. Diponegoro RT. 22 RW.08 kel. Sebengkok Tarakan – Kalimantan Utara
email : pt.bumikaltara@yahoo.com

DAFTAR ANALISA HARGA SATUAN

HARGA
JUMLAH
No. URAIAN PEKERJAAN SATUAN
( Rp ) ( Rp )
1 2 3 4
I PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan 1 m bouwplank
a. Tenaga Kerja
0.100 oh Pekerja 82,500.00 8,250.00
0.100 oh Tukang 88,000.00 8,800.00
0.010 oh Kepala tukang 88,000.00 880.00
0.005 oh Mandor 99,000.00 495.00
Jumlah Harga Tenaga Kerja 18,425.00
b. Bahan
0.012 m3 kayu 5/7 3,600,000.00 43,200.00
0.020 kg Paku biasa 2" - 3" 24,200.00 484.00
0.007 m3 Kayu papan 3/20 3,600,000.00 25,200.00
Jumlah Harga Bahan 68,884.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 87,309.00
e. Overhead + Profit (15% x d) 13,096.35
f. Harga Satuan Pekerjaan (d+e) 100,405.35
II PEKERJAAN TANAH
1 Penggalian 1 m3 tanah biasa sedalam 1 m
a. Tenaga Kerja
0.750 oh Pekerja 82,500.00 61,875.00
0.025 oh Mandor 99,000.00 2,475.00
Jumlah Harga Tenaga Kerja 64,350.00
b. Bahan
- - - -
Jumlah Harga Bahan -
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 64,350.00
e. Overhead + Profit (15% x d) 9,652.50
f. Harga Satuan Pekerjaan (d+e) 74,002.50

2 Pengurugan kembali 1 m3 galian tanah


a. Tenaga Kerja
0.500 oh Pekerja 82,500.00 41,250.00
0.050 oh Mandor 99,000.00 4,950.00
Jumlah Harga Tenaga Kerja 46,200.00
b. Bahan
HARGA
JUMLAH
No. URAIAN PEKERJAAN SATUAN
( Rp ) ( Rp )
- - - -
Jumlah Harga Bahan -
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 46,200.00
e. Overhead + Profit (15% x d) 6,930.00
f. Harga Satuan Pekerjaan (d+e) 53,130.00

3 Pengurugan 1 m3 dengan pasir urug


a. Tenaga Kerja
0.300 oh Pekerja 82,500.00 24,750.00
0.010 oh Mandor 99,000.00 990.00
Jumlah Harga Tenaga Kerja 25,740.00
b. Bahan
1.20 m3 Pasir urug 117,000.00 140,400.00
Jumlah Harga Bahan 140,400.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 166,140.00
e. Overhead + Profit (15% x d) 24,921.00
f. Harga Satuan Pekerjaan (d+e) 191,061.00

III PEKERJAAN FONDASI


1 Memasang 1 m3 pondasi batu Gunung, campuran 1 PC : 4 PP
a. Tenaga Kerja
1.500 OH Pekerja 82,500.00 123,750.00
0.750 OH Tukang batu 88,000.00 66,000.00
0.075 OH Kepala tukang 88,000.00 6,600.00
0.075 OH Mandor 99,000.00 7,425.00
Jumlah Harga Tenaga Kerja 14,025.00
b. Bahan
1.20 m3 Batu belah 15 cm/20 cm 598,000.00 717,600.00
163.00 kg Portland Cement 1,760.00 286,880.00
0.52 m3 Pasir Pasang 121,000.00 62,920.00
Jumlah Harga Bahan 62,920.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 780,520.00
e. Overhead + Profit (15% x d) 117,078.00
f. Harga Satuan Pekerjaan (d+e) 897,598.00

IV PEKERJAAN BETON
1 Pembesian 1 kg dengan besi polos
a. Tenaga Kerja
0.700 oh Pekerja 82,500.00 57,750.00
0.700 oh Tukang 88,000.00 61,600.00
0.070 oh Kepala tukang 88,000.00 6,160.00
0.070 oh Mandor 99,000.00 6,930.00
Jumlah Harga Tenaga Kerja 132,440.00
HARGA
JUMLAH
No. URAIAN PEKERJAAN SATUAN
( Rp ) ( Rp )
b. Bahan
105.00 kg Besi beton (polos) 17,600.00 1,848,000.00
1.50 kg Kawat ikat 22,000.00 33,000.00
Jumlah Harga Bahan 1,881,000.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c)/100 20,134.40
e. Overhead + Profit (15% x d) 3,020.16
f. Harga Satuan Pekerjaan (d+e) 23,154.56

2 Pembesian 1 kg dengan besi ulir


a. Tenaga Kerja
0.700 OH Pekerja 82,500.00 57,750.00
0.700 OH Tukang 88,000.00 61,600.00
0.070 OH Kepala tukang 88,000.00 6,160.00
0.070 OH Mandor 99,000.00 6,930.00
Jumlah Harga Tenaga Kerja 132,440.00
b. Bahan
105.00 kg Besi beton (ulir) 22,000.00 2,310,000.00
1.50 kg Kawat beton 22,000.00 33,000.00
Jumlah Harga Bahan 2,343,000.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c)/100 24,754.40
e. Overhead + Profit (15% x d) 3,713.16
f. Harga Satuan Pekerjaan (d+e) 28,467.56

3 Membuat 1 M3 beton mutu f'c=9.8 MPa (K 125), Slump(12±2) cm, w/c=0.78


a. Tenaga Kerja
1.650 oh Pekerja 82,500.00 136,125.00
0.275 oh Tukang 88,000.00 24,200.00
0.028 oh Kepala tukang 88,000.00 2,464.00
0.165 oh Mandor 99,000.00 16,335.00
Jumlah Harga Tenaga Kerja 179,124.00
b. Bahan
276.00 kg Semen Portland 1,760.00 485,760.00
0.59 m3 Pasir beton 121,000.00 71,562.86
0.75 m3 Batu Pecah 580,000.00 434,785.19
215.00 liter Air 36.36 7,818.18
Jumlah Harga Bahan 999,926.22
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 1,179,050.22
e. Overhead + Profit (15% x d) 176,857.53
f. Harga Satuan Pekerjaan (d+e) 1,355,907.76

4 Membuat 1 M3 beton mutu f'c=14.5 MPa (K 175), Slump(12±2) cm, w/c=0.66


a. Tenaga Kerja
1.650 oh Pekerja 82,500.00 136,125.00
HARGA
JUMLAH
No. URAIAN PEKERJAAN SATUAN
( Rp ) ( Rp )
0.275 oh Tukang 88,000.00 24,200.00
0.028 oh Kepala tukang 88,000.00 2,464.00
0.165 oh Mandor 99,000.00 16,335.00
Jumlah Harga Tenaga Kerja 179,124.00
b. Bahan
326.00 kg Semen Portland 1,760.00 573,760.00
0.54 m3 Pasir beton 121,000.00 65,685.71
0.76 m3 Batu Pecah 580,000.00 442,088.89
215.00 liter Air 36.36 7,818.18
Jumlah Harga Bahan 1,089,352.78
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 1,268,476.78
e. Overhead + Profit (15% x d) 190,271.52
f. Harga Satuan Pekerjaan (d+e) 1,458,748.30

5 Membuat 1 M3 beton mutu f'c=19.3 MPa (K 225), Slump(12±2) cm,


a. Tenaga Kerja
1.650 oh Pekerja 82,500.00 136,125.00
0.275 oh Tukang 88,000.00 24,200.00
0.028 oh Kepala tukang 88,000.00 2,464.00
0.083 oh Mandor 99,000.00 8,217.00
Jumlah Harga Tenaga Kerja 171,006.00
b. Bahan
371.00 kg Semen Portland 1,760.00 652,960.00
0.50 m3 Pasir beton 121,000.00 60,327.14
0.78 m3 Koral beton 580,000.00 449,822.22
215.00 Liter Air 36.36 7,818.18
Jumlah Harga Bahan 1,170,927.55
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 1,341,933.55
e. Overhead + Profit (15% x d) 201,290.03
f. Harga Satuan Pekerjaan (d+e) 1,543,223.58

6 Membuat 1 M3 beton mutu f'c=19.3 MPa (K 300), Slump(12±2) cm,


a. Tenaga Kerja
1.650 oh Pekerja 82,500.00 136,125.00
0.275 oh Tukang 88,000.00 24,200.00
0.028 oh Kepala tukang 88,000.00 2,464.00
0.083 oh Mandor 99,000.00 8,217.00
Jumlah Harga Tenaga Kerja 171,006.00
b. Bahan
413.00 kg Semen Portland 1,760.00 726,880.00
0.49 m3 Pasir beton 121,000.00 58,857.86
0.76 m3 Koral beton 580,000.00 438,651.85
215.00 Liter Air 36.36 7,818.18
Jumlah Harga Bahan 1,232,207.89
c. Peralatan
- - - -
HARGA
JUMLAH
No. URAIAN PEKERJAAN SATUAN
( Rp ) ( Rp )
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 1,403,213.89
e. Overhead + Profit (15% x d) 210,482.08
f. Harga Satuan Pekerjaan (d+e) 1,613,695.97

6 Pemasangan 1 m2 bekisting untuk pondasi


a. Tenaga Kerja
0.520 oh Pekerja 82,500.00 42,900.00
0.260 oh Tukang kayu 88,000.00 22,880.00
0.026 oh Kepala tukang 88,000.00 2,288.00
0.026 oh Mandor 99,000.00 2,574.00
Jumlah Harga Tenaga Kerja 70,642.00
b. Bahan
0.040 m3 Kayu kelas III 3,600,000.00 144,000.00
0.300 kg Paku 5 cm – 12 cm 24,200.00 7,260.00
0.100 Liter Minyak bekisting 9,000.00 900.00
Jumlah Harga Bahan 152,160.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 222,802.00
e. Overhead + Profit (15% x d) 33,420.30
f. Harga Satuan Pekerjaan (d+e) 256,222.30

7 Pemasangan 1 m2 bekisting untuk sloof


a. Tenaga Kerja
0.520 oh Pekerja 82,500.00 42,900.00
0.260 oh Tukang kayu 88,000.00 22,880.00
0.026 oh Kepala tukang 88,000.00 2,288.00
0.026 oh Mandor 99,000.00 2,574.00
Jumlah Harga Tenaga Kerja 70,642.00
b. Bahan
0.045 m3 Kayu kelas III 3,600,000.00 162,000.00
0.300 kg Paku 5 cm – 12 cm 24,200.00 7,260.00
0.100 Liter Minyak bekisting 9,000.00 900.00
Jumlah Harga Bahan 170,160.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 240,802.00
e. Overhead + Profit (15% x d) 36,120.30
f. Harga Satuan Pekerjaan (d+e) 276,922.30

8 Pemasangan 1 m2 bekisting untuk kolom


a. Tenaga Kerja
0.660 oh Pekerja 82,500.00 54,450.00
0.330 oh Tukang kayu 88,000.00 29,040.00
0.033 oh Kepala tukang 88,000.00 2,904.00
0.033 oh Mandor 99,000.00 3,267.00
Jumlah Harga Tenaga Kerja 89,661.00
b. Bahan
0.040 m3 Kayu kelas III 3,600,000.00 144,000.00
HARGA
JUMLAH
No. URAIAN PEKERJAAN SATUAN
( Rp ) ( Rp )
0.400 kg Paku 5 cm – 12 cm 24,200.00 9,680.00
0.200 Liter Minyak bekisting 9,000.00 1,800.00
0.015 m3 Balok kayu kelas II 3,600,000.00 54,000.00
0.350 Lbr Plywood tebal 9 mm 120,000.00 42,000.00
2.000 Btg Dolken kayu galam, Ö (8 - 10) cm, panjang 4 m 60,000.00 120,000.00
Jumlah Harga Bahan 371,480.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 461,141.00
e. Overhead + Profit (15% x d) 69,171.15
f. Harga Satuan Pekerjaan (d+e) 530,312.15

9 Pemasangan 1 m2 bekisting untuk balok


a. Tenaga Kerja
0.660 oh Pekerja 82,500.00 54,450.00
0.330 oh Tukang kayu 88,000.00 29,040.00
0.033 oh Kepala tukang 88,000.00 2,904.00
0.033 oh Mandor 99,000.00 3,267.00
Jumlah Harga Tenaga Kerja 89,661.00
b. Bahan
0.040 m3 Kayu kelas III 3,600,000.00 144,000.00
0.400 kg Paku 5 cm – 12 cm 24,200.00 9,680.00
0.200 Liter Minyak bekisting 9,000.00 1,800.00
0.018 m3 Balok kayu kelas II 3,600,000.00 64,800.00
0.350 Lbr Plywood tebal 9 mm 120,000.00 42,000.00
2.000 Btg Dolken kayu galam, Ö (8 - 10) cm, panjang 4 m 60,000.00 120,000.00
Jumlah Harga Bahan 382,280.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 471,941.00
e. Overhead + Profit (15% x d) 70,791.15
f. Harga Satuan Pekerjaan (d+e) 542,732.15

10 Pemasangan 1 m2 bekisting untuk lantai


a. Tenaga Kerja
0.660 oh Pekerja 82,500.00 54,450.00
0.330 oh Tukang kayu 88,000.00 29,040.00
0.033 oh Kepala tukang 88,000.00 2,904.00
0.033 oh Mandor 99,000.00 3,267.00
Jumlah Harga Tenaga Kerja 89,661.00
b. Bahan
0.040 m3 Kayu kelas III 3,600,000.00 144,000.00
0.400 kg Paku 5 cm – 12 cm 24,200.00 9,680.00
0.200 Liter Minyak bekisting 9,000.00 1,800.00
0.015 m3 Balok kayu kelas II 3,600,000.00 54,000.00
0.350 Lbr Plywood tebal 9 mm 120,000.00 42,000.00
6.000 Btg Dolken kayu galam, Ö (8 - 10) cm, panjang 4 m 60,000.00 360,000.00
Jumlah Harga Bahan 611,480.00
c. Peralatan
- - - -
HARGA
JUMLAH
No. URAIAN PEKERJAAN SATUAN
( Rp ) ( Rp )
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 701,141.00
e. Overhead + Profit (15% x d) 105,171.15
f. Harga Satuan Pekerjaan (d+e) 806,312.15

11 Pemasangan 1 m2 bekisting untuk tangga


a. Tenaga Kerja
0.660 oh Pekerja 82,500.00 54,450.00
0.330 oh Tukang kayu 88,000.00 29,040.00
0.033 oh Kepala tukang 88,000.00 2,904.00
0.033 oh Mandor 99,000.00 3,267.00
Jumlah Harga Tenaga Kerja 89,661.00
b. Bahan
0.030 m3 Kayu kelas III 3,600,000.00 108,000.00
0.400 kg Paku 5 cm – 12 cm 24,200.00 9,680.00
0.150 Liter Minyak bekisting 9,000.00 1,350.00
0.015 m3 Balok kayu kelas II 3,600,000.00 54,000.00
0.350 Lbr Plywood tebal 9 mm 120,000.00 42,000.00
2.000 Btg Dolken kayu galam, Ö (8 - 10) cm, panjang 4 m 60,000.00 120,000.00
Jumlah Harga Bahan 335,030.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 424,691.00
e. Overhead + Profit (15% x d) 63,703.65
f. Harga Satuan Pekerjaan (d+e) 488,394.65

V PEKERJAAN DINDING
1 Pemasangan 1 m2 dinding bata merah ukuran (8 x 8 x 17.5) cm tebal 1/2 bata, campuran spesi 1 PC : 4 PP
a. Tenaga Kerja
0.300 oh Pekerja 82,500.00 24,750.00
0.100 oh Tukang 88,000.00 8,800.00
0.010 oh Kepala tukang 88,000.00 880.00
0.015 oh Mandor 99,000.00 1,485.00
Jumlah Harga Tenaga Kerja 35,915.00
b. Bahan
52.000 Buah Bata merah 1,600.00 83,200.00
11.500 kg Portland Cement 1,760.00 20,240.00
0.043 m3 Pasir Pasang 121,000.00 5,203.00
Jumlah Harga Bahan 108,643.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 144,558.00
e. Overhead + Profit (15% x d) 21,683.70
f. Harga Satuan Pekerjaan (d+e) 166,241.70

VI PEKERJAAN PLESTERAN
1 Memasang 1 m2 plesteran 1 SP : 4 PP, tebal 15 mm
a. Tenaga Kerja
0.300 oh Pekerja 82,500.00 24,750.00
0.150 oh Tukang 88,000.00 13,200.00
HARGA
JUMLAH
No. URAIAN PEKERJAAN SATUAN
( Rp ) ( Rp )
0.015 oh Kepala tukang 88,000.00 1,320.00
0.015 oh Mandor 99,000.00 1,485.00
Jumlah Harga Tenaga Kerja 40,755.00
b. Bahan
6.240 kg Portland Cement 1,760.00 10,982.40
0.024 m3 Pasir Pasang 121,000.00 2,904.00
Jumlah Harga Bahan 13,886.40
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 54,641.40
e. Overhead + Profit (15% x d) 8,196.21
f. Harga Satuan Pekerjaan (d+e) 62,837.61

VII PEKERJAAN PENUTUP LANTAI & DINDING


1 Pemasangan 1 m2 lantai Keramik (40 x 40) cm
a. Tenaga Kerja
0.700 oh Pekerja 82,500.00 57,750.00
0.350 oh Tukang 88,000.00 30,800.00
0.035 oh Kepala tukang 88,000.00 3,080.00
0.035 oh Mandor 99,000.00 3,465.00
Jumlah Harga Tenaga Kerja 95,095.00
b. Bahan
1.000 kotak Keramik 145,000.00 145,000.00
9.800 kg Portland Cement 1,760.00 17,248.00
0.045 m3 Pasir Pasang 121,000.00 5,445.00
1.300 kg Semen warna 2,508.00 3,260.40
Jumlah Harga Bahan 170,953.40
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 266,048.40
e. Overhead + Profit (15% x d) 39,907.26
f. Harga Satuan Pekerjaan (d+e) 305,955.66

2 Memasang 1 m2 lantai Keramik (30 x 30) cm


a. Tenaga Kerja
0.700 oh Pekerja 82,500.00 57,750.00
0.350 oh Tukang 88,000.00 30,800.00
0.035 oh Kepala tukang 88,000.00 3,080.00
0.035 oh Mandor 99,000.00 3,465.00
Jumlah Harga Tenaga Kerja 95,095.00
b. Bahan
12.222 bh Keramik 6,930.00 84,700.00
10.000 kg Portland Cement 1,760.00 17,600.00
0.045 m3 Pasir Pasang 121,000.00 5,445.00
1.500 kg Semen warna 2,508.00 3,762.00
Jumlah Harga Bahan 111,507.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 206,602.00
HARGA
JUMLAH
No. URAIAN PEKERJAAN SATUAN
( Rp ) ( Rp )
e. Overhead + Profit (15% x d) 30,990.30
f. Harga Satuan Pekerjaan (d+e) 237,592.30

1 Pemasangan 1 m2 lantai Keramik (20x20) cm


a. Tenaga Kerja
0.700 oh Pekerja 82,500.00 57,750.00
0.350 oh Tukang 88,000.00 30,800.00
0.035 oh Kepala tukang 88,000.00 3,080.00
0.035 oh Mandor 99,000.00 3,465.00
Jumlah Harga Tenaga Kerja 95,095.00
b. Bahan
1.000 Kotak Keramik 106,000.00 106,000.00
10.400 kg Portland Cement 1,760.00 18,304.00
0.045 m3 Pasir Pasang 121,000.00 5,445.00
1.620 kg Semen warna 2,508.00 4,062.96
Jumlah Harga Bahan 133,811.96
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 228,906.96
e. Overhead + Profit (15% x d) 34,336.04
f. Harga Satuan Pekerjaan (d+e) 263,243.00

2 Memasang 1 m2 Dinding Keramik (20x25) cm


a. Tenaga Kerja
0.700 oh Pekerja 82,500.00 57,750.00
0.350 oh Tukang 88,000.00 30,800.00
0.035 oh Kepala tukang 88,000.00 3,080.00
0.035 oh Mandor 99,000.00 3,465.00
Jumlah Harga Tenaga Kerja 95,095.00
b. Bahan
1.000 Kotak Keramik 106,000.00 106,000.00
10.200 kg Portland Cement 1,760.00 17,952.00
0.045 m3 Pasir Pasang 121,000.00 5,445.00
1.560 kg Semen warna 2,508.00 3,912.48
Jumlah Harga Bahan 133,309.48
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 228,404.48
e. Overhead + Profit (15% x d) 34,260.67
f. Harga Satuan Pekerjaan (d+e) 262,665.15

VIII PEKERJAAN KACA


1 Pemasangan 1 m2 kaca tebal 5 mm
a. Tenaga Kerja
0.015 oh Pekerja 82,500.00 1,237.50
0.150 oh Tukang 88,000.00 13,200.00
0.015 oh Kepala tukang 88,000.00 1,320.00
0.001 oh Mandor 99,000.00 79.20
Jumlah Harga Tenaga Kerja 15,836.70
b. Bahan
HARGA
JUMLAH
No. URAIAN PEKERJAAN SATUAN
( Rp ) ( Rp )
1.100 m2 Kaca Polos 151,000.00 166,100.00
0.050 tube Sealant 41,000.00 2,050.00
Jumlah Harga Bahan 168,150.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 183,986.70
e. Overhead + Profit (15% x d) 27,598.01
f. Harga Satuan Pekerjaan (d+e) 211,584.71

2 Pemasangan 1 m2 kaca tebal 12 mm


a. Tenaga Kerja
0.025 oh Pekerja 82,500.00 2,062.50
0.250 oh Tukang 88,000.00 22,000.00
0.025 oh Kepala tukang 88,000.00 2,200.00
0.001 oh Mandor 99,000.00 128.70
Jumlah Harga Tenaga Kerja 26,391.20
b. Bahan
1.100 m2 Kaca 550,000.00 605,000.00
0.070 tube Sealant 41,000.00 2,870.00
Jumlah Harga Bahan 607,870.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 634,261.20
e. Overhead + Profit (15% x d) 95,139.18
f. Harga Satuan Pekerjaan (d+e) 729,400.38

IX PEKERJAAN PENGGANTUNG & PENGUNCI


1 Pemasangan 1 buah kunci tanam biasa
a. Tenaga Kerja
0.010 oh Pekerja 82,500.00 825.00
0.500 oh Tukang 88,000.00 44,000.00
0.050 oh Kepala tukang 88,000.00 4,400.00
0.005 oh Mandor 99,000.00 495.00
Jumlah Harga Tenaga Kerja 49,720.00
b. Bahan
1.000 bh kunci Tanam Biasa 176,000.00 176,000.00
Jumlah Harga Bahan 176,000.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 225,720.00
e. Overhead + Profit (15% x d) 33,858.00
f. Harga Satuan Pekerjaan (d+e) 259,578.00

2 Pemasangan 1 buah engsel pintu


a. Tenaga Kerja
0.015 oh Pekerja 82,500.00 1,237.50
0.150 oh Tukang 88,000.00 13,200.00
0.015 oh Kepala tukang 88,000.00 1,320.00
0.001 oh Mandor 99,000.00 79.20
HARGA
JUMLAH
No. URAIAN PEKERJAAN SATUAN
( Rp ) ( Rp )
Jumlah Harga Tenaga Kerja 15,836.70
b. Bahan
1.000 bh Engsel Pintu 66,000.00 66,000.00
Jumlah Harga Bahan 66,000.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 81,836.70
e. Overhead + Profit (15% x d) 12,275.51
f. Harga Satuan Pekerjaan (d+e) 94,112.21

X PEKERJAAN KAYU
1 Pemasangan 1 m2 rangka langit-langit (60x60) cm, kayu kelas II atau III
a. Tenaga Kerja
0.200 oh Pekerja 82,500.00 16,500.00
0.300 oh Tukang 88,000.00 26,400.00
0.030 oh Kepala tukang 88,000.00 2,640.00
0.075 oh Mandor 99,000.00 7,425.00
Jumlah Harga Tenaga Kerja 52,965.00
b. Bahan
0.016 m3 Kaso-kaso (5 x 7) cm 3,600,000.00 58,680.00
0.250 kg Paku 7 cm – 10 cm 24,200.00 6,050.00
Jumlah Harga Bahan 64,730.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 117,695.00
e. Overhead + Profit (15% x d) 17,654.25
f. Harga Satuan Pekerjaan (d+e) 135,349.25

1 Pemasangan 1 m list langit-langit kayu profil


a. Tenaga Kerja
0.050 oh Pekerja 82,500.00 4,125.00
0.050 oh Tukang 88,000.00 4,400.00
0.005 oh Kepala tukang 88,000.00 440.00
0.003 oh Mandor 99,000.00 297.00
Jumlah Harga Tenaga Kerja 9,262.00
b. Bahan
1.050 m List kayu profil 15,000.00 15,750.00
0.010 kg Paku 24,200.00 242.00
Jumlah Harga Bahan 25,254.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 34,516.00
e. Overhead + Profit (15% x d) 5,177.40
f. Harga Satuan Pekerjaan (d+e) 39,693.40

2 Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas I, II, dan III


a. Tenaga Kerja
4.000 oh Pekerja 82,500.00 330,000.00
12.000 oh Tukang 88,000.00 1,056,000.00
HARGA
JUMLAH
No. URAIAN PEKERJAAN SATUAN
( Rp ) ( Rp )
1.200 oh Kepala tukang 88,000.00 105,600.00
0.200 oh Mandor 99,000.00 19,800.00
Jumlah Harga Tenaga Kerja 1,511,400.00
b. Bahan
1.100 m3 Balok kayu 4,800,000.00
15.000 kg Besi strip tebal 5 mm -
5.600 kg Paku 12 cm 24,200.00
Jumlah Harga Bahan 1,511,400.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 3,022,800.00
e. Overhead + Profit (15% x d) 453,420.00
f. Harga Satuan Pekerjaan (d+e) 3,476,220.00

3 Pemasangan 1 m3 konstruksi gordeng, kayu kelas II


a. Tenaga Kerja
6.700 oh Pekerja 82,500.00 552,750.00
20.100 oh Tukang 88,000.00 1,768,800.00
2.010 oh Kepala tukang 88,000.00 176,880.00
0.335 oh Mandor 99,000.00 33,165.00
Jumlah Harga Tenaga Kerja 2,531,595.00
b. Bahan
1.100 m3 Balok kayu 4,800,000.00 5,280,000.00
15.000 kg Besi strip tebal 5 mm - -
3.000 kg Paku 12 cm 24,200.00 72,600.00
Jumlah Harga Bahan 5,352,600.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 7,884,195.00
e. Overhead + Profit (15% x d) 1,182,629.25
f. Harga Satuan Pekerjaan (d+e) 9,066,824.25

4 Pemasangan 1 m lisplank ukuran (3 x 20) cm, kayu kelas kelas I atau kelas II
a. Tenaga Kerja
0.100 oh Pekerja 82,500.00 8,250.00
0.200 oh Tukang 88,000.00 17,600.00
0.020 oh Kepala tukang 88,000.00 1,760.00
0.005 oh Mandor 99,000.00 495.00
Jumlah Harga Tenaga Kerja 28,105.00
b. Bahan
0.011 m3 Papan kayu 4,800,000.00 51,840.00
0.100 kg Paku 5 cm dan 7 cm 24,200.00 2,420.00
Jumlah Harga Bahan 54,260.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 82,365.00
e. Overhead + Profit (15% x d) 12,354.75
f. Harga Satuan Pekerjaan (d+e) 94,719.75
HARGA
JUMLAH
No. URAIAN PEKERJAAN SATUAN
( Rp ) ( Rp )
XI PEKERJAAN LANGIT-LANGIT
1 Pemasangan 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 3mm, 4 mm, dan 6 mm
a. Tenaga Kerja
0.100 oh Pekerja 82,500.00 8,250.00
0.100 oh Tukang 88,000.00 8,800.00
0.010 oh Kepala tukang 88,000.00 880.00
0.005 oh Mandor 99,000.00 495.00
Jumlah Harga Tenaga Kerja 18,425.00
b. Bahan
0.375 lbr Tripleks 80,000.00 30,000.00
0.030 kg Paku 24,200.00 726.00
Jumlah Harga Bahan 30,726.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 49,151.00
e. Overhead + Profit (15% x d) 7,372.65
f. Harga Satuan Pekerjaan (d+e) 56,523.65

XII PEKERJAAN PENGECATAN


1 Pengecatan 1 m2 Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup )
a. Tenaga Kerja
0.020 oh Pekerja 82,500.00 1,650.00
0.063 oh Tukang 88,000.00 5,544.00
0.006 oh Kepala tukang 88,000.00 554.40
0.003 oh Mandor 99,000.00 297.00
Jumlah Harga Tenaga Kerja 8,045.40
b. Bahan
0.100 kg Plamir 55,000.00 5,500.00
0.100 kg Cat dasar 26,000.00 2,600.00
0.260 kg Cat penutup 26,000.00 6,760.00
Jumlah Harga Bahan 14,860.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 22,905.40
e. Overhead + Profit (15% x d) 3,435.81
f. Harga Satuan Pekerjaan (d+e) 26,341.21

2 Pengecatan 1 m2 Bidang Kayu Baru ( 1 Lapis Plamir ), 1 Lapis Cat Dasar, 2 Lapis Cat Penutup
a. Tenaga Kerja
0.070 oh Pekerja 82,500.00 5,775.00
0.009 oh Tukang 88,000.00 792.00
0.006 oh Kepala tukang 88,000.00 528.00
0.003 oh Mandor 99,000.00 297.00
Jumlah Harga Tenaga Kerja 7,392.00
b. Bahan
0.200 kg Cat menie 59,000.00 11,800.00
0.150 kg Plamir 55,000.00 8,250.00
0.170 kg Cat dasar 59,000.00 10,030.00
0.260 kg Cat penutup 59,000.00 15,340.00
0.010 bh Kuas 30,000.00 300.00
HARGA
JUMLAH
No. URAIAN PEKERJAAN SATUAN
( Rp ) ( Rp )
0.030 kg Minyak cat 29,000.00 870.00
0.200 lbr Ampelas 13,000.00 2,600.00
Jumlah Harga Bahan 49,190.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 56,582.00
e. Overhead + Profit (15% x d) 8,487.30
f. Harga Satuan Pekerjaan (d+e) 65,069.30

XIII PEKERJAAN PIPA DAN SANITASI


1 Pemasangan 1 bh Kran Ø ¾" atau ½"
a. Tenaga Kerja
0.010 oh Pekerja 82,500.00 825.00
0.100 oh Tukang 88,000.00 8,800.00
0.010 oh Kepala tukang 88,000.00 880.00
0.005 oh Mandor 99,000.00 495.00
Jumlah Harga Tenaga Kerja 11,000.00
b. Bahan
1.000 bh Kran Air 27,500.00 27,500.00
0.025 bh Seal tape 2,000.00 50.00
Jumlah Harga Bahan 27,550.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 38,550.00
e. Overhead + Profit (15% x d) 5,782.50
f. Harga Satuan Pekerjaan (d+e) 44,332.50

2 Pemasangan 1 m'Pipa PVC tipe AW Ø ½"


a. Tenaga Kerja
0.036 oh Pekerja 82,500.00 2,970.00
0.060 oh Tukang 88,000.00 5,280.00
0.006 oh Kepala tukang 88,000.00 528.00
0.002 oh Mandor 99,000.00 178.20
Jumlah Harga Tenaga Kerja 8,956.20
b. Bahan
1.200 M' Pipa PVC D 1/2" 10,450.00 12,540.00
35.000 % Perlengkapan 10,450.00 3,657.50
Jumlah Harga Bahan 16,197.50
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 25,153.70
e. Overhead + Profit (15% x d) 3,773.06
f. Harga Satuan Pekerjaan (d+e) 28,926.76

3 Pemasangan 1 m'Pipa PVC tipe AW Ø 2"


a. Tenaga Kerja
0.054 oh Pekerja 82,500.00 4,455.00
0.090 oh Tukang 88,000.00 7,920.00
0.009 oh Kepala tukang 88,000.00 792.00
HARGA
JUMLAH
No. URAIAN PEKERJAAN SATUAN
( Rp ) ( Rp )
0.003 oh Mandor 99,000.00 297.00
Jumlah Harga Tenaga Kerja 13,464.00
b. Bahan
1.200 M' Pipa PVC D 2" 28,875.00 34,650.00
35.000 % Perlengkapan 28,875.00 10,106.25
Jumlah Harga Bahan 44,756.25
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 58,220.25
e. Overhead + Profit (15% x d) 8,733.04
f. Harga Satuan Pekerjaan (d+e) 66,953.29

4 Pemasangan 1 m'Pipa PVC tipe AW Ø 3"


a. Tenaga Kerja
0.081 oh Pekerja 82,500.00 6,682.50
0.135 oh Tukang 88,000.00 11,880.00
0.014 oh Kepala tukang 88,000.00 1,188.00
0.004 oh Mandor 99,000.00 396.00
Jumlah Harga Tenaga Kerja 20,146.50
b. Bahan
1.200 m Pipa PVC D 3" 34,750.00 41,700.00
35.000 % Perlengkapan 34,750.00 12,162.50
Jumlah Harga Bahan 53,862.50
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 74,009.00
e. Overhead + Profit (15% x d) 11,101.35
f. Harga Satuan Pekerjaan (d+e) 85,110.35

5 Pemasangan 1 m'Pipa PVC tipe AW Ø 4"


a. Tenaga Kerja
0.081 oh Pekerja 82,500.00 6,682.50
0.135 oh Tukang 88,000.00 11,880.00
0.014 oh Kepala tukang 88,000.00 1,188.00
0.004 oh Mandor 99,000.00 396.00
Jumlah Harga Tenaga Kerja 20,146.50
b. Bahan
1.200 m Pipa PVC D 4" 54,250.00 65,100.00
35.000 % Perlengkapan 54,250.00 18,987.50
Jumlah Harga Bahan 84,087.50
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 104,234.00
e. Overhead + Profit (15% x d) 15,635.10
f. Harga Satuan Pekerjaan (d+e) 119,869.10

7 Pemasangan 1 buah Kloset jongkok


a. Tenaga Kerja
1.000 oh Pekerja 82,500.00 82,500.00
HARGA
JUMLAH
No. URAIAN PEKERJAAN SATUAN
( Rp ) ( Rp )
1.500 oh Tukang 88,000.00 132,000.00
0.150 oh Kepala tukang 88,000.00 13,200.00
0.160 oh Mandor 99,000.00 15,840.00
Jumlah Harga Tenaga Kerja 243,540.00
b. Bahan
1.000 unit kloset jongkok 313,000.00 313,000.00
6.000 kg semen portland 1,760.00 10,560.00
0.010 m3 pasir pasangan 121,000.00 1,210.00
Jumlah Harga Bahan 324,770.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 568,310.00
e. Overhead + Profit (15% x d) 85,246.50
f. Harga Satuan Pekerjaan (d+e) 653,556.50

7 Pemasangan 1 buah floor drain


a. Tenaga Kerja
0.010 oh Pekerja 82,500.00 825.00
0.100 oh Tukang 88,000.00 8,800.00
0.010 oh Kepala tukang 88,000.00 880.00
0.005 oh Mandor 99,000.00 495.00
Jumlah Harga Tenaga Kerja 11,000.00
b. Bahan
1.000 unit Floor drain 17,000.00 17,000.00
Jumlah Harga Bahan 17,000.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 28,000.00
e. Overhead + Profit (15% x d) 4,200.00
f. Harga Satuan Pekerjaan (d+e) 32,200.00

XIV PEKERJAAN BESI DAN ALUMINIUM


1 Pemasangan 1 m talang air
a. Tenaga Kerja
0.090 oh Pekerja 82,500.00 7,425.00
0.230 oh Tukang 88,000.00 20,240.00
0.030 oh Kepala tukang 88,000.00 2,640.00
0.030 oh Mandor 99,000.00 2,970.00
Jumlah Harga Tenaga Kerja 33,275.00
b. Bahan
1.000 M' Talang Air - -
15 % Perlengkapan - -
Jumlah Harga Bahan -
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 33,275.00
e. Overhead + Profit (15% x d) 4,991.25
f. Harga Satuan Pekerjaan (d+e) 38,266.25
HARGA
JUMLAH
No. URAIAN PEKERJAAN SATUAN
( Rp ) ( Rp )
2 Pemasangan 1 m2 Dinding Pemisah Rangkap, Rangka Baja ringan
a. Tenaga Kerja
0.150 oh Pekerja 82,500.00 12,375.00
0.450 oh Tukang 88,000.00 39,600.00
0.045 oh Kepala tukang 88,000.00 3,960.00
0.008 oh Mandor 99,000.00 792.00
Jumlah Harga Tenaga Kerja 56,727.00
b. Bahan
4.700 M' Zincalume 60,000.00 282,000.00
0.150 Kg Sekrup 27,000.00 4,050.00
Jumlah Harga Bahan 286,050.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 342,777.00
e. Overhead + Profit (15% x d) 51,416.55
f. Harga Satuan Pekerjaan (d+e) 394,193.55

3 Pemasangan 1 m2 dinding GRC


a. Tenaga Kerja
0.025 oh Pekerja 82,500.00 2,062.50
0.075 oh Tukang 88,000.00 6,600.00
0.008 oh Kepala tukang 88,000.00 704.00
0.001 oh Mandor 99,000.00 99.00
Jumlah Harga Tenaga Kerja 9,465.50
b. Bahan
0.400 Lbr GRC - -
0.050 Kg Sekrup 27,000.00 1,350.00
Jumlah Harga Bahan 1,350.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 10,815.50
e. Overhead + Profit (15% x d) 1,622.33
f. Harga Satuan Pekerjaan (d+e) 12,437.83

1 Pemasangan 1 m kusen aluminium


a. Tenaga Kerja
0.043 oh Pekerja 82,500.00 3,547.50
0.043 oh Tukang 88,000.00 3,784.00
0.004 oh Kepala tukang 88,000.00 378.40
0.002 oh Mandor 99,000.00 207.90
Jumlah Harga Tenaga Kerja 7,917.80
b. Bahan
1.100 m Profil Aluminium 159,000.00 174,900.00
2.000 Bh Sekrup 2,700.00 5,400.00
0.060 Tube Sealant 41,000.00 2,460.00
Jumlah Harga Bahan 182,760.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 190,677.80
HARGA
JUMLAH
No. URAIAN PEKERJAAN SATUAN
( Rp ) ( Rp )
e. Overhead + Profit (15% x d) 28,601.67
f. Harga Satuan Pekerjaan (d+e) 219,279.47

2 Pemasangan 1 m2 kuda-kuda dan rangka atap baja ringan (zincalume) bersertifikasi iso
a. Tenaga Kerja
0.500 oh Pekerja 82,500.00 41,250.00
0.025 oh Tukang 88,000.00 2,200.00
0.250 oh Kepala tukang 88,000.00 22,000.00
0.025 oh Mandor 99,000.00 2,475.00
Jumlah Harga Tenaga Kerja 67,925.00
b. Bahan
1.000 m2 Kuda-kuda Zincalume 72,000.00 72,000.00
1.000 m2 Reng Zincalume 107,000.00 107,000.00
1.000 ls Asesories 30,000.00 30,000.00
Jumlah Harga Bahan 209,000.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 276,925.00
e. Overhead + Profit (15% x d) 41,538.75
f. Harga Satuan Pekerjaan (d+e) 318,463.75

2 Pemasangan 1 m2 penutup atap spandek


a. Tenaga Kerja
0.120 oh Pekerja 82,500.00 9,900.00
0.060 oh Tukang 88,000.00 5,280.00
0.006 oh Kepala tukang 88,000.00 528.00
0.006 oh Mandor 99,000.00 594.00
Jumlah Harga Tenaga Kerja 16,302.00
b. Bahan
1.100 m2 Spandek 90,000.00 99,000.00
0.020 kg Paku Biasa ½" - 1" 24,200.00 484.00
Jumlah Harga Bahan 99,484.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 115,786.00
e. Overhead + Profit (15% x d) 17,367.90
f. Harga Satuan Pekerjaan (d+e) 133,153.90

3 Pemasangan 1 m bubungan atap galvalume


a. Tenaga Kerja
0.015 oh Pekerja 82,500.00 1,237.50
0.070 oh Tukang 88,000.00 6,160.00
0.008 oh Kepala tukang 88,000.00 704.00
0.006 oh Mandor 99,000.00 594.00
Jumlah Harga Tenaga Kerja 8,695.50
b. Bahan
0.300 Lbr Galvalum Plat 85,000.00 25,500.00
0.040 Kg Paku Biasa ½" - 1" 24,200.00 968.00
Jumlah Harga Bahan 26,468.00
c. Peralatan
HARGA
JUMLAH
No. URAIAN PEKERJAAN SATUAN
( Rp ) ( Rp )
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 35,163.50
e. Overhead + Profit (15% x d) 5,274.53
f. Harga Satuan Pekerjaan (d+e) 40,438.03

4 Pemasangan 1 m2 Aluminium Composite Panel (ACP)


a. Tenaga Kerja
1.000 oh Pekerja 82,500.00 82,500.00
1.000 oh Tukang 88,000.00 88,000.00
0.100 oh Kepala tukang 88,000.00 8,800.00
0.050 oh Mandor 99,000.00 4,950.00
Jumlah Harga Tenaga Kerja 184,250.00
b. Bahan
0.375 lbr ACP 1,500,000.00 562,500.00
0.110 kg Ripet/Skrup 42,000.00 4,620.00
0.060 tube Sealant 115,500.00 6,930.00
4.100 m Rangka Aluminium/Hollow 4/4 34,750.00 142,475.00
0.400 m Spigot 54,000.00 21,600.00
Jumlah Harga Bahan 738,125.00
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 922,375.00
e. Overhead + Profit (15% x d) 138,356.25
f. Harga Satuan Pekerjaan (d+e) 1,060,731.25

5 Memasang 1 Kg rangka kuda-kuda baja IWF (SNI Edisi 2008)


a. Tenaga Kerja
0.060 oh Pekerja 82,500.00 4,950.00
0.060 oh Tukang 88,000.00 5,280.00
0.006 oh Kepala tukang 88,000.00 528.00
0.003 oh Mandor 99,000.00 297.00
Jumlah Harga Tenaga Kerja 11,055.00
b. Bahan
1.100 kg Besi baja IWF 24,000.00 26,400.00
0.090 kg Kawat Las 37,125.00 3,341.25
0.060 Jam Mesin Las 30,000.00 1,800.00
Jumlah Harga Bahan 31,541.25
c. Peralatan
- - - -
Jumlah Harga Peralatan -
d. Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (a+b+c) 42,596.25
e. Overhead + Profit (15% x d) 6,389.44
f. Harga Satuan Pekerjaan (d+e) 48,985.69
PT. BUMI KALTARA KONSULTAN
Perencanaan, Pengawasan, Pengukuran, dan Manajemen Konstruksi
Alamat : JL. P. Diponegoro RT. 22 RW.08 kel. Sebengkok Tarakan – Kalimantan Utara
email : pt.bumikaltara@yahoo.com

DAFTAR HARGA SATUAN


PAKET KEGIATAN : USULAN PEMBANGUNAN RUMAH DINAS
LOKASI : TARAKAN
TAHUN : 2020

No Uraian Bahan Harga Satuan (Rp) Satuan


1 2 3 4
I SATUAN UPAH
1 Pekerja Rp. 82,500.00 / Hari
2 Tukang Rp. 88,000.00 / Hari
3 Kepala Tukang Rp. 88,000.00 / Hari
4 Mandor Rp. 99,000.00 / Hari

II SATUAN BAHAN
1 Semen ( 50 ) Rp. 88,000.00 / Zak
2 Semen Warna ( 50 ) Rp. 125,400.00 / Zak
3 Pasir Pasangan Rp. 121,000.00 / M3
4 Pasir urug Rp. 117,000.00 / M3
5 Tanah Urug Rp. 117,000.00 / M3
6 Besi Beton Polos Rp. 17,600.00 / Kg
7 Besi Beton Ulir Rp. 22,000.00 / Kg
8 Batu Pecah / Agregat Kasar Rp. 580,000.00 / Kg
9 Batu Bata Merah Rp. 1,600.00 / Bh
10 Kawat Ikat Rp. 22,000.00 / Kg
11 Kayu Meranti Rp. 3,600,000.00 / M3
12 Kayu Kapur/ Bengkirai/ Lembasung Rp. 4,800,000.00 / M3
13 Paku Biasa Rp. 24,200.00 / Kg
14 Paku Sekrup Rp. 27,000.00 / Kg
15 Plywood Tebal 9 mm Rp. 120,000.00 / Lbr
16 Plywood Tebal 6 mm Rp. 96,000.00 / Lbr
17 Plywood Tebal 4 mm Rp. 80,000.00 / Lbr
18 List Kayu Profil Rp. 30,000.00 / btg
19 Kaca Polos Tebal 5 mm Rp. 151,000.00 / M2
20 Kaca temperd Tebal 12 mm Rp. 550,000.00 / M2
21 Kaca Ryben 5 mm Rp. 149,000.00 / M2
22 Keramik 40x40 EX-Roman Rp. 145,000.00 / M2
23 Keramik 30x30 EX-Roman Rp. 6,930.00 / Bh
No Uraian Bahan Harga Satuan (Rp) Satuan
1 2 3 4
24 Keramik 20x20 Rp. 106,000.00 / M2
25 Keramik 20x25 Rp. 106,000.00 / M2
26 Dempul / plamir Rp. 55,000.00 / Kg
27 Amplas Rp. 13,000.00 / Lbr
28 Cat Air Rp. 26,000.00 / Kg
29 Cat Kilap Rp. 59,000.00 / Kg
30 Minyak Begesting Rp. 9,000.00 / Ltr
31 Minyak Cat A Rp. 29,000.00 / Kg
32 Meni Rp. 59,000.00 / Kg
33 Sealent Rp. 41,000.00 / Tube
34 Kunci Tanam Rp. 176,000.00 / Bh
35 Hak Angin Rp. 22,000.00 / Bh
36 Grendel Rp. 27,500.00 / Bh
37 Handle Rp. 27,500.00 / Bh
38 Engsel Kupu-Kupu 4" Rp. 66,000.00 / Psg
39 Engsel Kupu-Kupu 3" Rp. 49,500.00 / Psg
40 Dolken kayu galam, Ö (8 - 10) cm, panjang 4 m Rp. 60,000.00 / Btg
41 Besi baja C- 75. 0,8 Rp. 72,000.00 / Btg
42 Besi baja C- 75. 0,6 Rp. 72,000.00 / Btg
42 Reng Zincalume Rp. 107,000.00 / M2
43 Baja ringan (Zincalume) Rp. 60,000.00 / M
44 Seng Gelombang BJLS 30 Rp. 110,000.00 / Lbr
45 Seng Plat BJLS 30 Rp. 106,000.00 / Lbr
46 Multy colour Rp. 77,000.00 / Lbr
47 Nok multy colour Rp. 59,000.00 / Lbr
39 Kran Air Rp. 27,500.00 / Bh
40 Closed Jongkok Rp. 313,000.00 / Bh
41 Pipa PVC 1/2" Rp. 41,800.00 / Btg
42 Pipa PVC 2" Rp. 115,500.00 / Btg
43 Pipa PVC 3" Rp. 139,000.00 / Btg
44 Pipa PVC 4" Rp. 217,000.00 / Btg
45 Floor Drain Rp. 54,000.00 / Bh
46 Saklar Ganda Rp. 42,000.00 / Bh
47 Saklar Tunggal Rp. 31,000.00 / Bh
48 Stop Kontak Rp. 42,000.00 / Bh
49 Baut (screw driver) Rp. 23,000.00 / Kg
49 Kusen Aluminium Rp. 159,000.00 / M
49 Atap Spandek Rp. 90,000.00 / M2
50 Tiang Pancang 20x20x400 Rp. 1,500,000.00 / Btg
51 Hollow 4/4 Rp. 223,000.00 / Btg
No Uraian Bahan Harga Satuan (Rp) Satuan
1 2 3 4
52 Hollow 2/4 Rp. 169,000.00 / Btg
53 Kuas Rp. 30,000.00 / Bh
54 Baja WF Rp. 24,000.00 / Kg
55 Kawat las Rp. 37,125.00 / Kg
56 Mesin las Rp. 30,000.00 / Jam
ENGINEERING ESTIMATE (EE)
KEGIATAN : PEMBANGUNANFASILITAS UMUM DAN SOSIAL
PAKET KEGIATAN : MCK DAN PROFIL RT 06 MAMBURUNGAN TIMUR
LOKASI : KOTA TARAKAN
TAHUN ANGGARAN : 2011

Harga Satuan Jumlah Harga


No. Uraian Pekerjaan Volume
( Rp. ) ( Rp. )
1 2 3 4 5
I PEKERJAAN PENDAHULUAN
1 Pemasangan Bouwplank 1.00 Ls 300,000.00 300,000.00
2 Dokumentasi Dan Pelaporan 1.00 Ls 150,000.00 150,000.00
3 Papan Nama Proyek ( Digital Printing Image ) 1.00 Ls 150,000.00 150,000.00
Jumlah I 600,000.00
II PEKERJAAN TANAH
1 Galian Tanah 13.76 M3 #REF! #REF!
2 Timbunan Tanah Kembali 3.44 M3 #REF! #REF!
Jumlah II #REF!
III PEKERJAAN PASANGAN
1 Pas. Batu gunung, Camp. 1 : 4 9.36 M3 #REF! #REF!
Jumlah II #REF!
IV PEKERJAAN BETON
1 Cor Plat Lantai , t = 12 cm
Cor Beton 36.00 M3 #REF! #REF!
Pembesian 434.57 Kg #REF! #REF!
Begesting 8.20 M2 #REF! #REF!
2 Angkur Ø 8 - 50 43.68 Kg #REF! #REF!
Jumlah III #REF!
V PEKERJAAN LAIN-LAIN
1 Pemasangan Tiang Net Galvanis 3 " 6.00 M' 200,000.00 1,200,000.00
2 Pemasangan Net Volly Ball 1.00 Bh 250,000.00 250,000.00
Jumlah XI 1,450,000.00
Jumlah I s/d XI #REF!
PLAT LANTAI 100 x 1000 x 10 cm

1 x 10 x 0.1 m

beton cover atas-bawah = 2.5 cm = 0.025 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang = 20 cm = 0.2 m

P R O C E S S I N G

Pembesian

Sumbu-X

D10 ------> 0.62 kg/m' L= 1m x 51.00 bh = 51.00 m -----------> Wtul.sumbu X = 31.62 kg

Sumbu-Y

D10 ------> 0.62 kg/m' L= 10 m x 6.00 bh = 60.00 m -----------> Wtul.sumbu Y = 37.20 kg

Wtul.bagian bawah = 68.82 kg

Wtul.bagian atas = - kg

Wtul.TOTAL = 68.82 kg

Begesting

Volume 1 Unit = ### m3

Luasan begesting =
Samping = = - m2

Bawah = 10 m2 = 10.00 m2

L total = 10.00 m2

Jadi utk Vol 1 m3 beton diperlukan luasan begesting = 10.000 m2


PLAT LANTAI 100 x 666.67 x 15 cm

1 x 6.6667 x 0.15 m

beton cover atas-bawah = 2.5 cm = 0.025 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang = 20 cm = 0.2 m

P R O C E S S I N G

Pembesian

Sumbu-X

D10 ------> 0.62 kg/m' L= 1m x 35.00 bh = 35.00 m -----------> Wtul.sumbu X = 21.70 kg

Sumbu-Y

D10 ------> 0.62 kg/m' L= 6.67 m x 6.00 bh = 40.00 m -----------> Wtul.sumbu Y = 24.80 kg

Wtul.bagian bawah = 46.50 kg

Wtul.bagian atas = - kg

Wtul.TOTAL = 46.50 kg

Begesting

Volume 1 Unit = ### m3

Luasan begesting =
Samping = = - m2

Bawah = 7 m2 = 6.67 m2

L total = 6.67 m2

Jadi utk Vol 1 m3 beton diperlukan luasan begesting = 6.667 m2


KOLOM 15 x 15 cm

0.15 x 0.15 m

beton cover atas-bawah = 5 cm = 0.05 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang di daerah tumpuan = 15 cm = 0.15 m

jarak sengkang di daerah lapangan 15 cm = 0.15 m

Overlap sambungan besi sengkang = 10 cm = 0.10 m

Panjang KOLOM 1 M3 = 44.44 m

Jumlah tulangan Pokok = 4 bh

Volume beton dalam 1 buah kolom = 1.00 m3

P R O C E S S I N G

Pembesian

Tulangan Pokok

1. D12 ----> 0.887 kg/m' L= 44.34 m x 4 bh = 177.38 m

Wtul. Pokok = 158.00 kg

Tulangan Sengkang

3. D8 ----> 0.393 kg/m' L= 0.30 m x 149 bh = 44.70 m

Wtul. Sengkang = 18.00 kg

4. D8 ----> 0.393 kg/m' L= 0.30 m x 149 bh = 44.70 m

Wtul. Sengkang = 18.00 kg

Begesting

Luasan begesting
= 13.33 m2 x 2 sisi = 26.67 m2

= = - m2

L total = 26.67 m2 / per 1 bh kolom

Jadi utk Vol 1 m3 beton diperlukan luasan begesting L total = 26.67 m2 / per 1 m3 beton
PLAT LANTAI 100 x 1000 x 10 cm

1 x 10 x 0.1 m

beton cover atas-bawah = 2.5 cm = 0.025 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang = 25 cm = 0.25 m

P R O C E S S I N G

Pembesian

Sumbu-X

D8 ------> 0.393 kg/m' L= 1m x 41.00 bh = 41.00 m -----------> Wtul.sumbu X = 16.11 kg

Sumbu-Y

D8 ------> 0.393 kg/m' L= 10 m x 5.00 bh = 50.00 m -----------> Wtul.sumbu Y = 19.65 kg

Wtul.bagian bawah = 35.76 kg

Wtul.bagian atas = - kg

Wtul.TOTAL = 35.76 kg
SLOOF 15 x 20 cm

0.15 x 0.2 m

beton cover atas-bawah = 5 cm = 0.05 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang di daerah tumpuan = 10 cm = 0.1 m

jarak sengkang di daerah lapangan 15 cm = 0.15 m

Overlap sambungan besi = 10 cm = 0.1 m

Panjang sloof dalam 1 m3 = = 33.33 m

Jumlah tulangan Pokok = 6 bh

Jumlah tulangan Puntir = - bh

P R O C E S S I N G

Pembesian

Tulangan Pokok

D12 ------> 0.887 kg/m' L= 33.33 m x 6 bh = 200.00 m

Wtul. Pokok = 178.00 kg

D12 ------> 0.887 kg/m' L= 33.33 m x - bh = - m

Wtul. Pokok = - kg
Tulangan Sengkang

D8 ------> 0.393 kg/m' L= 0.40 m x 168 bh = 67.20 m

Wtul. Sengkang = 26.41 kg

D8 ------> 0.393 kg/m' L= 0.40 m x 113 bh = 45.20 m

Wtul. Sengkang = 17.76 kg

Begesting

Luasan begesting
Samping = 6.67 m2 x 2 sisi = 13.33 m2

Bawah = = - m2

L total = 13.33 m2
Jadi utk Vol 1 m3 beton diperlukan luasan begesting = 13.33 m2
x y t

POER PLAT 70 x 70 x 20 cm

0.7 x 0.7 x 0.2 m

beton cover atas-bawah = 8 cm = 0.08 m

beton cover samping = 8 cm = 0.08 m

jarak sengkang = 20 cm = 0.2 m

Overlap sambungan besi sengkang = 10 cm = 0.1 m

Volume 1 Unit = 0.10 m3

Poer Plat 8 unit x 0.10 M3 = 0.78 m3

P R O C E S S I N G

Pembesian
Panjang Total
D12 ------> 0.887 kg/m' Arah- X L= 1.26 m x 5 bh = 6.30 m
12.60 m'
Arah- Y L= 1.26 m x 5 bh = 6.30 m

Wtul.Total = 11.18 kg/bh

Wtul.Total = 114.04 kg/m3

Begesting
Luasan begesting
Samping Arah- X = 0.14 m2 x 2 sisi = 0.28 m2

Arah- Y = 0.14 m2 x 2 sisi = 0.28 m2

L total = 0.56 m2/bh

Jadi utk Vol 1 m3 beton diperlukan luasan begesting LTotal = 5.71 m2/m3
KOLOM 10 x 15 cm

0.1 x 0.15 m

beton cover atas-bawah = 5 cm = 0.05 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang di daerah tumpuan = 15 cm = 0.15 m

jarak sengkang di daerah lapangan 15 cm = 0.15 m

Overlap sambungan besi sengkang = 10 cm = 0.10 m

Panjang KOLOM 1 M3 = 66.67 m

Jumlah tulangan Pokok = 4 bh

Volume beton dalam 1 buah kolom = 1.00 m3

P R O C E S S I N G

Pembesian

Tulangan Pokok

1. D12 ----> 0.887 kg/m' L= 66.57 m x 4 bh = 266.27 m

Wtul. Pokok = 237.00 kg

Tulangan Sengkang

3. D8 ----> 0.393 kg/m' L= 0.20 m x 223 bh = 44.60 m

Wtul. Sengkang = 18.00 kg

4. D8 ----> 0.393 kg/m' L= 0.20 m x 223 bh = 44.60 m

Wtul. Sengkang = 18.00 kg

Begesting

Luasan begesting
= 16.67 m2 x 2 sisi = 33.33 m2

= = - m2

L total = 33.33 m2 / per 1 bh kolom

Jadi utk Vol 1 m3 beton diperlukan luasan begesting L total = 33.33 m2 / per 1 m3 beton
Balok 10 x 15 cm

0.1 x 0.15 m

beton cover atas-bawah = 5 cm = 0.05 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang di daerah tumpuan = 15 cm = 0.15 m

jarak sengkang di daerah lapangan 20 cm 0.2 m

Overlap sambungan besi sengkang = 20 cm = 0.2 m

Panjang BALOK dalam 1 m3 = 66.67 m

Jumlah tulangan Pokok = 4 bh

Jumlah tulangan Tengah = - bh

P R O C E S S I N G

Pembesian

Tulangan Pokok

1. D10 ----> 0.62 kg/m' L= 66.67 m x 4 bh = 266.67 m

Wtul. Pokok = 166.00 kg

2. D10 ----> 0.62 kg/m' L= 66.67 m x - bh = - m

Wtul. Pokok = - kg

Tulangan Sengkang

3. D8 ----> 0.393 kg/m' L= 0.30 m x 224 bh = 67.20 m

Wtul. Sengkang = 27.00 kg

4. D8 ----> 0.393 kg/m' L= 0.30 m x 168 bh = 50.40 m

Wtul. Sengkang = 20.00 kg

Begesting

Luasan begesting
Sisi Samping = 10.00 m2 x 2 sisi = 20.00 m2

Sisi Bawah balok = 6.67 m2 x 1 sisi = 6.67 m2

Jadi utk Vol 1 m3 beton diperlukan luasan begesting L total = 26.67 m2 / per 1 m3 beton
DAK ATAP 100 x 1000 x 10 cm

1 x 10 x 0.1 m

beton cover atas-bawah = 2.5 cm = 0.025 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang = 20 cm = 0.2 m

P R O C E S S I N G

Pembesian

Sumbu-X

D8 ------> 0.393 kg/m' L= 1m x 51.00 bh = 51.00 m -----------> Wtul.sumbu X = 20.04 kg

Sumbu-Y

D8 ------> 0.393 kg/m' L= 10 m x 6.00 bh = 60.00 m -----------> Wtul.sumbu Y = 23.58 kg

Wtul.bagian bawah = 43.62 kg

Wtul.bagian atas = - kg

Wtul.TOTAL = 43.62 kg

Begesting

Volume 1 Unit = 1.000 m3

Luasan begesting =
Samping = = - m2

Bawah = 10 m2 = 10.00 m2

L total = 10.00 m2

Jadi utk Vol 1 m3 beton diperlukan luasan begesting = 10.000 m2


Balok 10 x 15 cm

0.1 x 0.15 m

beton cover atas-bawah = 5 cm = 0.05 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang di daerah tumpuan = 15 cm = 0.15 m

jarak sengkang di daerah lapangan 20 cm 0.2 m

Overlap sambungan besi sengkang = 20 cm = 0.2 m

Panjang BALOK dalam 1 m3 = 66.67 m

Jumlah tulangan Pokok = 4 bh

Jumlah tulangan Tengah = - bh

P R O C E S S I N G

Pembesian

Tulangan Pokok

1. D10 ----> 0.62 kg/m' L= 66.67 m x 4 bh = 266.67 m

Wtul. Pokok = 166.00 kg

2. D10 ----> 0.62 kg/m' L= 66.67 m x - bh = - m

Wtul. Pokok = - kg

Tulangan Sengkang

3. D8 ----> 0.393 kg/m' L= 0.30 m x 224 bh = 67.20 m

Wtul. Sengkang = 27.00 kg

4. D8 ----> 0.393 kg/m' L= 0.30 m x 168 bh = 50.40 m

Wtul. Sengkang = 20.00 kg

Begesting

Luasan begesting
Sisi Samping = 10.00 m2 x 2 sisi = 20.00 m2

Sisi Bawah balok = 6.67 m2 x 1 sisi = 6.67 m2

Jadi utk Vol 1 m3 beton diperlukan luasan begesting L total = 26.67 m2 / per 1 m3 beton
x y t

POER PLAT 130 x 130 x 40 cm

1.3 x 1.3 x 0.4 m

beton cover atas-bawah = 8 cm = 0.08 m

beton cover samping = 8 cm = 0.08 m

jarak sengkang = 20 cm = 0.2 m

Overlap sambungan besi sengkang = 10 cm = 0.1 m

Volume 1 Unit = 0.68 m3

Poer Plat 8 unit x 0.68 M3 = 5.41 m3

P R O C E S S I N G

Pembesian
Panjang Total
D16 ------> 1.58 kg/m' Arah- X L= 2.86 m x 8 bh = 22.88 m
45.76 m'
Arah- Y L= 2.86 m x 8 bh = 22.88 m

Wtul.Total = 72.30 kg/bh

Wtul.Total = 106.95 kg/m3

Begesting
Luasan begesting
Samping Arah- X = 0.52 m2 x 2 sisi = 1.04 m2

Arah- Y = 0.52 m2 x 2 sisi = 1.04 m2

L total = 2.08 m2/bh

Jadi utk Vol 1 m3 beton diperlukan luasan begesting LTotal = 3.08 m2/m3
x y t

POER PLAT 100 x 100 x 40 cm

1 x 1 x 0.4 m

beton cover atas-bawah = 8 cm = 0.08 m

beton cover samping = 8 cm = 0.08 m

jarak sengkang = 20 cm = 0.2 m

Overlap sambungan besi sengkang = 10 cm = 0.1 m

Volume 1 Unit = 0.40 m3

Poer Plat 16 unit x 0.40 M3 = 6.40 m3

P R O C E S S I N G

Pembesian Ulir
Panjang Total
D16 ------> 1.58 kg/m' Arah- X L= 2.26 m x 6 bh = 13.56 m
27.12 m'
Arah- Y L= 2.26 m x 6 bh = 13.56 m

Wtul.Total = 42.85 kg/bh

Wtul.Total = 107.12 kg/m3

Begesting
Luasan begesting
Samping Arah- X = 0.4 m2 x 2 sisi = 0.80 m2

Arah- Y = 0.4 m2 x 2 sisi = 0.80 m2

L total = 1.60 m2/bh

Jadi utk Vol 1 m3 beton diperlukan luasan begesting LTotal = 4.00 m2/m3
KOLOM 25 x 40 cm

0.25 x 0.4 m

beton cover atas-bawah = 5 cm = 0.05 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang di daerah tumpuan = 10 cm = 0.1 m

jarak sengkang di daerah lapangan 10 cm = 0.10 m

Overlap sambungan besi sengkang = 10 cm = 0.10 m

Panjang KOLOM 1 M3 = 10.00 m

Jumlah tulangan Pokok = 10 bh

Volume beton dalam 1 buah kolom = 1.00 m3

P R O C E S S I N G

Pembesian

Tulangan Pokok

1. D16 ----> 1.58 kg/m' L= 9.90 m x 10 bh = 99.00 m

Wtul. Pokok = 157.00 kg

Tulangan Sengkang

3. D10 ----> 0.62 kg/m' L= 1.00 m x 50 bh = 50.00 m

Wtul. Sengkang = 31.00 kg

4. D10 ----> 0.62 kg/m' L= 1.00 m x 50 bh = 50.00 m

Wtul. Sengkang = 31.00 kg

Begesting

Luasan begesting
= 5.79 m2 x 2 sisi = 11.57 m2

= = - m2

L total = 11.57 m2 / per 1 bh kolom

Jadi utk Vol 1 m3 beton diperlukan luasan begesting L total = 11.57 m2 / per 1 m3 beton
KOLOM 25 x 25 cm

0.25 x 0.25 m

beton cover atas-bawah = 5 cm = 0.05 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang di daerah tumpuan = 10 cm = 0.1 m

jarak sengkang di daerah lapangan 10 cm = 0.10 m

Overlap sambungan besi sengkang = 10 cm = 0.10 m

Panjang KOLOM 1 M3 = 16.00 m

Jumlah tulangan Pokok = 6 bh

Volume beton dalam 1 buah kolom = 1.00 m3

P R O C E S S I N G

Pembesian

Tulangan Pokok

1. D16 ----> 1.58 kg/m' L= 15.90 m x 6 bh = 95.40 m

Wtul. Pokok = 151.00 kg

Tulangan Sengkang

3. D10 ----> 0.62 kg/m' L= 0.70 m x 80 bh = 56.00 m

Wtul. Sengkang = 35.00 kg

4. D10 ----> 0.62 kg/m' L= 0.70 m x 80 bh = 56.00 m

Wtul. Sengkang = 35.00 kg

Begesting

Luasan begesting
= 8.00 m2 x 2 sisi = 16.00 m2

= = - m2

L total = 16.00 m2 / per 1 bh kolom

Jadi utk Vol 1 m3 beton diperlukan luasan begesting L total = 16.00 m2 / per 1 m3 beton
SLOOF 25 x 40 cm

0.25 x 0.4 m

beton cover atas-bawah = 5 cm = 0.05 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang di daerah tumpuan = 10 cm = 0.1 m

jarak sengkang di daerah lapangan 15 cm = 0.15 m

Overlap sambungan besi = 10 cm = 0.1 m

Panjang sloof dalam 1 m3 = = 10.00 m

Jumlah tulangan Pokok = 8 bh

Jumlah tulangan Puntir = 2 bh

P R O C E S S I N G

Pembesian

Tulangan Pokok

D16 ------> 1.58 kg/m' L= 10.00 m x 8 bh = 80.00 m

Wtul. Pokok = 127.00 kg

D12 ------> 0.887 kg/m' L= 10.00 m x 2 bh = 20.00 m

Wtul. Pokok = 18.00 kg


Tulangan Sengkang

D10 ------> 0.62 kg/m' L= 1.00 m x 51 bh = 51.00 m

Wtul. Sengkang = 31.62 kg

D10 ------> 0.62 kg/m' L= 1.00 m x 35 bh = 35.00 m

Wtul. Sengkang = 21.70 kg

Begesting

Luasan begesting
Samping = 4.00 m2 x 2 sisi = 8.00 m2

Bawah = = - m2

L total = 8.00 m2

Jadi utk Vol 1 m3 beton diperlukan luasan begesting = 8.00 m2


SLOOF 25 x 40 cm

0.25 x 0.4 m

beton cover atas-bawah = 5 cm = 0.05 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang di daerah tumpuan = 10 cm = 0.1 m

jarak sengkang di daerah lapangan 15 cm = 0.15 m

Overlap sambungan besi = 10 cm = 0.1 m

Panjang sloof dalam 1 m3 = = 10.00 m

Jumlah tulangan Pokok = 6 bh

Jumlah tulangan Puntir = 2 bh

P R O C E S S I N G

Pembesian

Tulangan Pokok

D16 ------> 1.58 kg/m' L= 10.00 m x 6 bh = 60.00 m

Wtul. Pokok = 95.00 kg

D12 ------> 0.887 kg/m' L= 10.00 m x 2 bh = 20.00 m

Wtul. Pokok = 18.00 kg


Tulangan Sengkang

D10 ------> 0.62 kg/m' L= 1.00 m x 51 bh = 51.00 m

Wtul. Sengkang = 31.62 kg

D10 ------> 0.62 kg/m' L= 1.00 m x 35 bh = 35.00 m

Wtul. Sengkang = 21.70 kg

Begesting

Luasan begesting
Samping = 4.00 m2 x 2 sisi = 8.00 m2

Bawah = = - m2

L total = 8.00 m2

Jadi utk Vol 1 m3 beton diperlukan luasan begesting = 8.00 m2


SLOOF 15 x 20 cm

0.15 x 0.2 m

beton cover atas-bawah = 5 cm = 0.05 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang di daerah tumpuan = 15 cm = 0.15 m

jarak sengkang di daerah lapangan 15 cm = 0.15 m

Overlap sambungan besi = 10 cm = 0.1 m

Panjang sloof dalam 1 m3 = = 33.33 m

Jumlah tulangan Pokok = 4 bh

Jumlah tulangan Puntir = - bh

P R O C E S S I N G

Pembesian

Tulangan Pokok

D12 ------> 0.887 kg/m' L= 33.33 m x 4 bh = 133.33 m

Wtul. Pokok = 119.00 kg

D10 ------> 0.62 kg/m' L= 33.33 m x - bh = - m

Wtul. Pokok = - kg
Tulangan Sengkang

D8 ------> 0.393 kg/m' L= 0.40 m x 113 bh = 45.20 m

Wtul. Sengkang = 17.76 kg

D8 ------> 0.393 kg/m' L= 0.40 m x 113 bh = 45.20 m

Wtul. Sengkang = 17.76 kg

Begesting

Luasan begesting
Samping = 6.67 m2 x 2 sisi = 13.33 m2

Bawah = = - m2

L total = 13.33 m2

Jadi utk Vol 1 m3 beton diperlukan luasan begesting = 13.33 m2


PLAT LANTAI 100 x 1000 x 10 cm

1 x 10 x 0.1 m

beton cover atas-bawah = 2.5 cm = 0.025 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang = 20 cm = 0.2 m

P R O C E S S I N G

Pembesian

Sumbu-X

D8 ------> 0.393 kg/m' L= 1m x 51.00 bh = 51.00 m -----------> Wtul.sumbu X = 20.04 kg

Sumbu-Y

D8 ------> 0.393 kg/m' L= 10 m x 6.00 bh = 60.00 m -----------> Wtul.sumbu Y = 23.58 kg

Wtul.bagian bawah = 43.62 kg

Wtul.bagian atas = - kg

Wtul.TOTAL = 43.62 kg
KOLOM 10 x 15 cm

0.1 x 0.15 m

beton cover atas-bawah = 5 cm = 0.05 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang di daerah tumpuan = 20 cm = 0.2 m

jarak sengkang di daerah lapangan 20 cm = 0.20 m

Overlap sambungan besi sengkang = 10 cm = 0.10 m

Panjang KOLOM 1 M3 = 66.67 m

Jumlah tulangan Pokok = 4 bh

Volume beton dalam 1 buah kolom = 1.00 m3

P R O C E S S I N G

Pembesian

Tulangan Pokok

1. 10 ----> 0 kg/m' L= 66.57 m x 4 bh = 266.27 m

Wtul. Pokok = - kg

Tulangan Sengkang

3. D8 ----> 0.393 kg/m' L= 0.20 m x 168 bh = 33.60 m

Wtul. Sengkang = 14.00 kg

4. D8 ----> 0.393 kg/m' L= 0.20 m x 168 bh = 33.60 m

Wtul. Sengkang = 14.00 kg

Begesting

Luasan begesting
= 16.67 m2 x 2 sisi = 33.33 m2

= = - m2

L total = 33.33 m2 / per 1 bh kolom

Jadi utk Vol 1 m3 beton diperlukan luasan begesting L total = 33.33 m2 / per 1 m3 beton
RINGBALK 10 x 20 cm

0.1 x 0.2 m

beton cover atas-bawah = 5 cm = 0.05 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang di daerah tumpuan = 20 cm = 0.2 m

jarak sengkang di daerah lapangan 20 cm 0.2 m

Overlap sambungan besi sengkang = 10 cm = 0.1 m

Panjang BALOK dalam 1 m3 = 50.00 m

Jumlah tulangan Pokok = 4 bh

Jumlah tulangan Tengah = - bh

P R O C E S S I N G

Pembesian

Tulangan Pokok

1. D10 ----> 0.62 kg/m' L= 50.00 m x 4 bh = 200.00 m

Wtul. Pokok = 124.00 kg

2. D10 ----> 0.62 kg/m' L= 50.00 m x - bh = - m

Wtul. Pokok = - kg

Tulangan Sengkang

3. D8 ----> 0.393 kg/m' L= 0.30 m x 126 bh = 37.80 m

Wtul. Sengkang = 15.00 kg

4. D8 ----> 0.393 kg/m' L= 0.30 m x 126 bh = 37.80 m

Wtul. Sengkang = 15.00 kg

Begesting

Luasan begesting
Sisi Samping = 10.00 m2 x 2 sisi = 20.00 m2

Sisi Bawah balok = 5.00 m2 x 1 sisi = 5.00 m2


Jadi utk Vol 1 m3 beton diperlukan luasan begesting L total = 25.00 m2 / per 1 m3 beton
Balok 15 x 25 cm

0.15 x 0.25 m

beton cover atas-bawah = 5 cm = 0.05 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang di daerah tumpuan = 15 cm = 0.15 m

jarak sengkang di daerah lapangan 20 cm 0.2 m

Overlap sambungan besi sengkang = 10 cm = 0.1 m

Panjang BALOK dalam 1 m3 = 26.67 m

Jumlah tulangan Pokok = 6 bh

Jumlah tulangan Tengah = - bh

P R O C E S S I N G

Pembesian

Tulangan Pokok

1. D12 ----> 0.887 kg/m' L= 26.67 m x 6 bh = 160.00 m

Wtul. Pokok = 142.00 kg

2. D10 ----> 0.62 kg/m' L= 26.67 m x - bh = - m

Wtul. Pokok = - kg

Tulangan Sengkang

3. D8 ----> 0.393 kg/m' L= 0.50 m x 90 bh = 45.00 m

Wtul. Sengkang = 18.00 kg

4. D8 ----> 0.393 kg/m' L= 0.50 m x 68 bh = 34.00 m

Wtul. Sengkang = 14.00 kg

Begesting

Luasan begesting
Sisi Samping = 6.67 m2 x 2 sisi = 13.33 m2

Sisi Bawah balok = 4.00 m2 x 1 sisi = 4.00 m2


Jadi utk Vol 1 m3 beton diperlukan luasan begesting L total = 17.33 m2 / per 1 m3 beton
Balok 25 x 40 cm

0.25 x 0.4 m

beton cover atas-bawah = 5 cm = 0.05 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang di daerah tumpuan = 10 cm = 0.1 m

jarak sengkang di daerah lapangan 15 cm 0.15 m

Overlap sambungan besi sengkang = 10 cm = 0.1 m

Panjang BALOK dalam 1 m3 = 10.00 m

Jumlah tulangan Pokok = 10 bh

Jumlah tulangan Tengah = 2 bh

P R O C E S S I N G

Pembesian

Tulangan Pokok

1. D16 ----> 1.58 kg/m' L= 10.00 m x 10 bh = 100.00 m

Wtul. Pokok = 158.00 kg

2. D12 ----> 0.887 kg/m' L= 10.00 m x 2 bh = 20.00 m

Wtul. Pokok = 18.00 kg

Tulangan Sengkang

3. D10 ----> 0.62 kg/m' L= 1.00 m x 51 bh = 51.00 m

Wtul. Sengkang = 32.00 kg

4. D10 ----> 0.62 kg/m' L= 1.00 m x 35 bh = 35.00 m

Wtul. Sengkang = 22.00 kg

Begesting

Luasan begesting
Sisi Samping = 4.00 m2 x 2 sisi = 8.00 m2

Sisi Bawah balok = 2.50 m2 x 1 sisi = 2.50 m2


Jadi utk Vol 1 m3 beton diperlukan luasan begesting L total = 10.50 m2 / per 1 m3 beton
kanopi 100 x 1250 x 8 cm

1 x 12.5 x 0.08 m

beton cover atas-bawah = 2.5 cm = 0.025 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang = 25 cm = 0.25 m

P R O C E S S I N G

Pembesian

Sumbu-X

D8 ------> 0.393 kg/m' L= 1m x 51.00 bh = 51.00 m -----------> Wtul.sumbu X = 20.04 kg

Sumbu-Y

D8 ------> 0.393 kg/m' L= 12.5 m x 5.00 bh = 62.50 m -----------> Wtul.sumbu Y = 24.56 kg

Wtul.bagian bawah = 44.61 kg

Wtul.bagian atas = kg

Wtul.TOTAL = 44.61 kg

Begesting

Volume 1 Unit = 1.000 m3

Luasan begesting =
Samping = = - m2

Bawah = 12.5 m2 = 12.50 m2

L total = 12.50 m2

Jadi utk Vol 1 m3 beton diperlukan luasan begesting = 12.500 m2


plat bordes 100 x 833.33 x 12 cm

1 x 8.3333 x 0.12 m

beton cover atas-bawah = 2.5 cm = 0.025 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang = 20 cm = 0.2 m

P R O C E S S I N G

Pembesian

Sumbu-X

D10 ------> 0.62 kg/m' L= 1m x 43.00 bh = 43.00 m -----------> Wtul.sumbu X = 26.66 kg

Sumbu-Y

D10 ------> 0.62 kg/m' L= 8.33 m x 6.00 bh = 50.00 m -----------> Wtul.sumbu Y = 31.00 kg

Wtul.bagian bawah = 57.66 kg

Wtul.bagian atas = 57.66 kg

Wtul.TOTAL = ### kg

Begesting

Volume 1 Unit = 1.000 m3

Luasan begesting =
Samping = = - m2

Bawah = 8.3333 m2 = 8.33 m2

L total = 8.33 m2

Jadi utk Vol 1 m3 beton diperlukan luasan begesting = 8.333 m2


Balok 25 x 40 cm

0.25 x 0.4 m

beton cover atas-bawah = 5 cm = 0.05 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang di daerah tumpuan = 10 cm = 0.1 m

jarak sengkang di daerah lapangan 15 cm 0.15 m

Overlap sambungan besi sengkang = 10 cm = 0.1 m

Panjang BALOK dalam 1 m3 = 10.00 m

Jumlah tulangan Pokok = 7 bh

Jumlah tulangan Tengah = 2 bh

P R O C E S S I N G

Pembesian

Tulangan Pokok

1. D16 ----> 1.58 kg/m' L= 10.00 m x 7 bh = 70.00 m

Wtul. Pokok = 111.00 kg

2. D12 ----> 0.887 kg/m' L= 10.00 m x 2 bh = 20.00 m

Wtul. Pokok = 18.00 kg

Tulangan Sengkang

3. D10 ----> 0.62 kg/m' L= 1.00 m x 51 bh = 51.00 m

Wtul. Sengkang = 32.00 kg

4. D10 ----> 0.62 kg/m' L= 1.00 m x 35 bh = 35.00 m

Wtul. Sengkang = 22.00 kg

Begesting

Luasan begesting
Sisi Samping = 4.00 m2 x 2 sisi = 8.00 m2

Sisi Bawah balok = 2.50 m2 x 1 sisi = 2.50 m2


Jadi utk Vol 1 m3 beton diperlukan luasan begesting L total = 10.50 m2 / per 1 m3 beton
PLAT LANTAI 100 x 833.33 x 12 cm

1 x 8.3333 x 0.12 m

beton cover atas-bawah = 2.5 cm = 0.025 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang = 25 cm = 0.25 m

P R O C E S S I N G

Pembesian

Sumbu-X

D10 ------> 0.62 kg/m' L= 1m x 35.00 bh = 35.00 m -----------> Wtul.sumbu X = 21.70 kg

Sumbu-Y

D10 ------> 0.62 kg/m' L= 8.33 m x 5.00 bh = 41.67 m -----------> Wtul.sumbu Y = 25.83 kg

Wtul.bagian bawah = 47.53 kg

Wtul.bagian atas = 47.53 kg

Wtul.TOTAL = 95.07 kg

Begesting

Volume 1 Unit = 1.000 m3

Luasan begesting =
Samping = = - m2

Bawah = 8.3333 m2 = 8.33 m2

L total = 8.33 m2

Jadi utk Vol 1 m3 beton diperlukan luasan begesting = 8.333 m2


Ring Balk 25 x 40 cm

0.25 x 0.4 m

beton cover atas-bawah = 5 cm = 0.05 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang di daerah tumpuan = 10 cm = 0.1 m

jarak sengkang di daerah lapangan 15 cm 0.15 m

Overlap sambungan besi sengkang = 10 cm = 0.1 m

Panjang BALOK dalam 1 m3 = 10.00 m

Jumlah tulangan Pokok = 8 bh

Jumlah tulangan Tengah = 2 bh

P R O C E S S I N G

Pembesian

Tulangan Pokok

1. D16 ----> 1.58 kg/m' L= 10.00 m x 8 bh = 80.00 m

Wtul. Pokok = 127.00 kg

2. D12 ----> 0.887 kg/m' L= 10.00 m x 2 bh = 20.00 m

Wtul. Pokok = 18.00 kg

Tulangan Sengkang

3. D10 ----> 0.62 kg/m' L= 1.00 m x 51 bh = 51.00 m

Wtul. Sengkang = 32.00 kg

4. D10 ----> 0.62 kg/m' L= 1.00 m x 35 bh = 35.00 m

Wtul. Sengkang = 22.00 kg

Begesting

Luasan begesting
Sisi Samping = 4.00 m2 x 2 sisi = 8.00 m2

Sisi Bawah balok = 2.50 m2 x 1 sisi = 2.50 m2


Jadi utk Vol 1 m3 beton diperlukan luasan begesting L total = 10.50 m2 / per 1 m3 beton
Ring Balk 25 x 40 cm

0.25 x 0.4 m

beton cover atas-bawah = 5 cm = 0.05 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang di daerah tumpuan = 10 cm = 0.1 m

jarak sengkang di daerah lapangan 15 cm 0.15 m

Overlap sambungan besi sengkang = 10 cm = 0.1 m

Panjang BALOK dalam 1 m3 = 10.00 m

Jumlah tulangan Pokok = 6 bh

Jumlah tulangan Tengah = 2 bh

P R O C E S S I N G

Pembesian

Tulangan Pokok

1. D16 ----> 1.58 kg/m' L= 10.00 m x 6 bh = 60.00 m

Wtul. Pokok = 95.00 kg

2. D10 ----> 0.62 kg/m' L= 10.00 m x 2 bh = 20.00 m

Wtul. Pokok = 13.00 kg

Tulangan Sengkang

3. D10 ----> 0.62 kg/m' L= 1.00 m x 51 bh = 51.00 m

Wtul. Sengkang = 32.00 kg

4. D10 ----> 0.62 kg/m' L= 1.00 m x 35 bh = 35.00 m

Wtul. Sengkang = 22.00 kg

Begesting

Luasan begesting
Sisi Samping = 4.00 m2 x 2 sisi = 8.00 m2

Sisi Bawah balok = 2.50 m2 x 1 sisi = 2.50 m2


Jadi utk Vol 1 m3 beton diperlukan luasan begesting L total = 10.50 m2 / per 1 m3 beton
Ring Balk 10 x 20 cm

0.1 x 0.2 m

beton cover atas-bawah = 5 cm = 0.05 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang di daerah tumpuan = 10 cm = 0.1 m

jarak sengkang di daerah lapangan 20 cm 0.2 m

Overlap sambungan besi sengkang = 20 cm = 0.2 m

Panjang BALOK dalam 1 m3 = 50.00 m

Jumlah tulangan Pokok = 4 bh

Jumlah tulangan Tengah = - bh

P R O C E S S I N G

Pembesian

Tulangan Pokok

1. D10 ----> 0.62 kg/m' L= 50.00 m x 4 bh = 200.00 m

Wtul. Pokok = 124.00 kg

2. D10 ----> 0.62 kg/m' L= 50.00 m x - bh = - m

Wtul. Pokok = - kg

Tulangan Sengkang

3. D8 ----> 0.393 kg/m' L= 0.40 m x 251 bh = 100.40 m

Wtul. Sengkang = 40.00 kg

4. D8 ----> 0.393 kg/m' L= 0.40 m x 126 bh = 50.40 m

Wtul. Sengkang = 20.00 kg

Begesting

Luasan begesting
Sisi Samping = 10.00 m2 x 2 sisi = 20.00 m2

Sisi Bawah balok = 5.00 m2 x 1 sisi = 5.00 m2


Jadi utk Vol 1 m3 beton diperlukan luasan begesting L total = 25.00 m2 / per 1 m3 beton
Ring Balk 20 x 40 cm

0.2 x 0.4 m

beton cover atas-bawah = 5 cm = 0.05 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang di daerah tumpuan = 10 cm = 0.1 m

jarak sengkang di daerah lapangan 15 cm 0.15 m

Overlap sambungan besi sengkang = 20 cm = 0.2 m

Panjang BALOK dalam 1 m3 = 12.50 m

Jumlah tulangan Pokok = 6 bh

Jumlah tulangan Tengah = 2 bh

P R O C E S S I N G

Pembesian

Tulangan Pokok

1. D16 ----> 1.58 kg/m' L= 12.50 m x 6 bh = 75.00 m

Wtul. Pokok = 119.00 kg

2. D12 ----> 0.887 kg/m' L= 12.50 m x 2 bh = 25.00 m

Wtul. Pokok = 23.00 kg

Tulangan Sengkang

3. D10 ----> 0.62 kg/m' L= 1.00 m x 64 bh = 64.00 m

Wtul. Sengkang = 40.00 kg

4. D10 ----> 0.62 kg/m' L= 1.00 m x 43 bh = 43.00 m

Wtul. Sengkang = 27.00 kg

Begesting
Luasan begesting
Sisi Samping = 5.00 m2 x 2 sisi = 10.00 m2

Sisi Bawah balok = 2.50 m2 x 1 sisi = 2.50 m2

Jadi utk Vol 1 m3 beton diperlukan luasan begesting L total = 12.50 m2 / per 1 m3 beton
KOLOM 25 x 25 cm

0.25 x 0.25 m

beton cover atas-bawah = 5 cm = 0.05 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang di daerah tumpuan = 10 cm = 0.1 m

jarak sengkang di daerah lapangan 10 cm = 0.10 m

Overlap sambungan besi sengkang = 10 cm = 0.10 m

Panjang KOLOM 1 M3 = 16.00 m

Jumlah tulangan Pokok = 6 bh

Volume beton dalam 1 buah kolom = 1.00 m3

P R O C E S S I N G

Pembesian

Tulangan Pokok

1. D16 ----> 1.58 kg/m' L= 15.90 m x 6 bh = 95.40 m

Wtul. Pokok = 151.00 kg

Tulangan Sengkang

3. D10 ----> 0.62 kg/m' L= 0.70 m x 80 bh = 56.00 m

Wtul. Sengkang = 35.00 kg

4. D10 ----> 0.62 kg/m' L= 0.70 m x 80 bh = 56.00 m

Wtul. Sengkang = 35.00 kg

Begesting

Luasan begesting
= 8.00 m2 x 2 sisi = 16.00 m2

= = - m2

L total = 16.00 m2 / per 1 bh kolom

Jadi utk Vol 1 m3 beton diperlukan luasan begesting L total = 16.00 m2 / per 1 m3 beton
luifel 100 x 1000 x 10 cm

1 x 10 x 0.1 m

beton cover atas-bawah = 2.5 cm = 0.025 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang = 25 cm = 0.25 m

P R O C E S S I N G

Pembesian

Sumbu-X

D8 ------> 0.393 kg/m' L= 1m x 41.00 bh = 41.00 m -----------> Wtul.sumbu X = 16.11 kg

Sumbu-Y

D8 ------> 0.393 kg/m' L= 10 m x 5.00 bh = 50.00 m -----------> Wtul.sumbu Y = 19.65 kg

Wtul.bagian bawah = 35.76 kg

Wtul.bagian atas = kg

Wtul.TOTAL = 35.76 kg

Begesting

Volume 1 Unit = 1.000 m3

Luasan begesting =
Samping = = - m2

Bawah = 10 m2 = 10.00 m2

L total = 10.00 m2

Jadi utk Vol 1 m3 beton diperlukan luasan begesting = 10.000 m2


dak otak 100 x 666.67 x 15 cm

1 x 6.6667 x 0.15 m

beton cover atas-bawah = 2.5 cm = 0.025 m

beton cover samping = 5 cm = 0.05 m

jarak sengkang = 20 cm = 0.2 m

P R O C E S S I N G

Pembesian

Sumbu-X

D10 ------> 0.62 kg/m' L= 1m x 35.00 bh = 35.00 m -----------> Wtul.sumbu X = 21.70 kg

Sumbu-Y

D10 ------> 0.62 kg/m' L= 6.67 m x 6.00 bh = 40.00 m -----------> Wtul.sumbu Y = 24.80 kg

Wtul.bagian bawah = 46.50 kg

Wtul.bagian atas = 46.50 kg

Wtul.TOTAL = 93.00 kg

Begesting

Volume 1 Unit = 1.000 m3

Luasan begesting =
Samping = = - m2

Bawah = 6.6667 m2 = 6.67 m2

L total = 6.67 m2

Jadi utk Vol 1 m3 beton diperlukan luasan begesting = 6.667 m2


x y t

anak tangga 52 x 139 x 34 cm

0.52 x 1.39 x 0.34 m 0.62129 0.31

beton cover a - b = 3 cm = 0.03 m

beton cover c = 3 cm = 0.03 m

jarak sengkang = 15 cm = 0.15 m

Overlap sambungan besi sengkang = 10 cm = 0.1 m

Volume 1 Unit = 0.12 m3

P R O C E S S I N G

Pembesian Polos
D8 ------> 0.393 kg/m' L= 0.84 m x 11 bh = 9.24 m 3.63

D10 ------> 0.62 kg/m' L= 0.86 m x 11 bh = 9.46 m 5.87

D10 ------> 0.62 kg/m' L= 0.93 m x 11 bh = 10.25 m 6.36

D8 ------> 0.393 kg/m' L= 1.39 m x 4 bh = 5.56 m 2.19

Wtul.Total = 18.04 kg/bh

Wtul.Total = 146.79 kg/m3

Begesting
Luasan begesting
Arah- X = 0.6213 m2 x 1 sisi = 0.86 m2

Arah- Y = 1.39 0 = 0.28 m2

L total = 1.14 m2/bh

Jadi utk Vol 1 m3 beton diperlukan luasan begesting LTotal = 9.29 m2/m3