LAMPIRAN I

PERHITUNGAN WAKTU KERJA ALAT MEKANIS

Tambang – Plant BAI

A. Alat Muat

1. Excavator Komatsu PC 200

 Waktu efektif ( We ) = 196,42

menit/shift

 Waktu Repair ( R ) = 15

menit/shift

 Waktu Stand by ( S ) = 77

menit/shift

 Waktu delay ( Wd ) = 191,58

menit/shift

 Waktu Tersedia ( T ) = 480

menit/shift

a. Kesiapan Mekanik ( Mechanical Avaibility)

W
MA = x 100%
W R

196,42
= x 100%
196,42  15

MA = 92,9 %

b. Keadaan Fisik (Physical Avaibility)


W S
PA = x 100%
W RS

196,42  77
= x 100%
196,42  15  77

PA = 94,79 %

c. Penggunaan Waktu (Use Of Avaibility Percent)

W
UA = x 100%
W S

196,42
= x 100%
196,42  77

UA = 71,8 %

d. Effective Utilization

W
EU = x 100%
W SR

196,42
= x 100%
196,42  77  15

EU = 68,10 %

Waktu kerja efektif


e. Efisiensi Kerja = x 100%
Waktu kerja tersedia

196,42
= x 100%
480

= 40,92 %

B. Alat Angkut

1. Dump Truck Fuso FV415JD


 Waktu efektif ( We ) = 355

menit/shift

 Waktu Repair ( R ) = 20

menit/shift

 Waktu Stand by ( S ) = 65

menit/shift

 Waktu delay ( Wd ) = 40

menit/shift

 Waktu Tersedia ( T ) = 480

menit/shift

a. Kesiapan Mekanik ( Mechanical


Avaibility)

W
MA = x 100%
W R

355
= x 100%
355  20

MA = 94,6 %

b. Keadaan Fisik (Physical


Avaibility)

W S
PA = x 100%
W RS

355  65
= x 100%
355  65  20

PA = 95,4 %

c. Penggunaan Waktu (Use Of


Avaibility Percent)
W
UA = x 100%
W S

355
= x 100%
355  65

UA = 84,52 %

d. Effective Utilization

W
EU = x 100%
W SR

355
= x 100%
355  65  20

EU = 80,6 %

Waktu kerja efektif


e. Efisiensi Kerja = x 100%
Waktu kerja tersedia

355
= x 100%
480

= 73,95 %

2. Dump Truck Nissan CW 520

 Waktu efektif ( We ) = 351

menit/shift

 Waktu Repair ( R ) = 18

menit/shift

 Waktu Stand by ( S ) = 71

menit/shift
 Waktu delay ( Wd ) = 40

menit/shift

 Waktu Tersedia ( T ) = 480

menit/shift

a. Kesiapan Mekanik ( Mechanical


Avaibility)

W
MA = x 100%
W R

351
= x 100%
351  18

MA = 95,12 %

b. Keadaan Fisik (Physical


Avaibility)

W S
PA = x 100%
W RS

351  71
= x 100%
351  71  18

PA = 95,9 %

c. Penggunaan Waktu (Use Of


Avaibility Percent)

W
UA = x 100%
W S

351
= x 100%
351  71

UA = 79,4 %

d. Effective Utilization
W
EU = x 100%
W SR

351
= x 100%
351  71  18

EU = 79,2 %

Waktu kerja efektif


e. Efisiensi Kerja = x 100%
Waktu kerja tersedia

351
= x 100%
480

= 73,1 %

3. Dump Truck HINO 501 FM260TI

 Waktu efektif ( We ) = 326

menit/shift

 Waktu Repair ( R ) = 18

menit/shift

 Waktu Stand by ( S ) = 88

menit/shift

 Waktu delay ( Wd ) = 48

menit/shift

 Waktu Tersedia ( T ) = 480

menit/shift

a. Kesiapan Mekanik ( Mechanical


Avaibility)
W
MA = x 100%
W R

326
= x 100%
326  18

MA = 94,7 %

b. Keadaan Fisik (Physical


Avaibility)

W S
PA = x 100%
W RS

326  88
= x 100%
326  88  18

PA = 95,8 %

c. Penggunaan Waktu (Use Of


Avaibility Percent)

W
UA = x 100%
W S

326
= x 100%
326  88

UA = 78,74 %

d. Effective Utilization

W
EU = x 100%
W SR

326
= x 100%
326  88  18

EU = 75,46 %

Waktu kerja efektif


e. Efisiensi Kerja = x 100%
Waktu kerja tersedia

326
= x 100%
480

= 67,91 %

4. Dump Truck HINO 502 FM260TI

 Waktu efektif ( We ) = 326

menit/shift

 Waktu Repair ( R ) = 18

menit/shift

 Waktu Stand by ( S ) = 84

menit/shift

 Waktu delay ( Wd ) = 52

menit/shift

 Waktu Tersedia ( T ) = 480

menit/shift

a. Kesiapan Mekanik ( Mechanical


Avaibility)

W
MA = x 100%
W R

326
= x 100%
326  18

MA = 94,7 %

b. Keadaan Fisik (Physical


Avaibility)
W S
PA = x 100%
W RS

326  84
= x 100%
326  84  18

PA = 95,7 %

c. Penggunaan Waktu (Use Of


Avaibility Percent)

W
UA = x 100%
W S

326
= x 100%
326  84

UA = 79,51 %

d. Effective Utilization

W
EU = x 100%
W SR

326
= x 100%
326  84  18

EU = 79,51 %

Waktu kerja efektif


e. Efisiensi Kerja = x 100%
Waktu kerja tersedia

326
= x 100%
480

= 67,9 %

5. Dump Truck HINO 503 FM260TI


 Waktu efektif ( We ) = 326

menit/shift

 Waktu Repair ( R ) = 20

menit/shift

 Waktu Stand by ( S ) = 78

menit/shift

 Waktu delay ( Wd ) = 56

menit/shift

 Waktu Tersedia ( T ) = 480

menit/shift

a. Kesiapan Mekanik ( Mechanical


Avaibility)

W
MA = x 100%
W R

326
= x 100%
326  20

MA = 94,21 %

b. Keadaan Fisik (Physical


Avaibility)

W S
PA = x 100%
W RS

326  78
= x 100%
326  20  78

PA = 95,28 %

c. Penggunaan Waktu (Use Of


Avaibility Percent)
W
UA = x 100%
W S

326
= x 100%
326  78

UA = 80,69 %

d. Effective Utilization

W
EU = x 100%
W SR

326
= x 100%
326  78  20

EU = 76,88 %

Waktu kerja efektif


e. Efisiensi Kerja = x 100%
Waktu kerja tersedia

326
= x 100%
480

= 67,91 %

Tambang – Plant KCN

A. Alat Muat

1. Excavator Komatsu PC 200

 Waktu efektif ( We ) = 79,2

menit/shift

 Waktu Repair ( R ) = 15

menit/shift
 Waktu Stand by ( S ) = 177

menit/shift

 Waktu delay ( Wd ) = 208,8

menit/shift

 Waktu Tersedia ( T ) = 480

menit/shift

a. Kesiapan Mekanik ( Mechanical


Avaibility)

W
MA = x 100%
W R

79,2
= x 100%
79,2  15

MA = 84,07 %

b. Keadaan Fisik (Physical


Avaibility)

W S
PA = x 100%
W RS

79,2  177
= x 100%
79,79,2  15  177

PA = 94,46 %

c. Penggunaan Waktu (Use Of


Avaibility Percent)
W
UA = x 100%
W S

79,2
= x 100%
79,2  177

UA = 30,91 %

d. Effective Utilization

W
EU = x 100%
W SR

79,2
= x 100%
79,2  177  15

EU = 29,2 %

Waktu kerja efektif


f. Efisiensi Kerja = x 100%
Waktu kerja tersedia

79,2
= x 100%
480

= 16,5 %

B. Alat Angkut

1. Dump Truck Fuso


FV415JD

 Waktu efektif ( We ) = 348

menit/shift

 Waktu Repair ( R ) = 20

menit/shift
 Waktu Stand by ( S ) = 80

menit/shift

 Waktu delay ( Wd ) = 32

menit/shift

 Waktu Tersedia ( T ) = 480

menit/shift

a. Kesiapan Mekanik ( Mechanical


Avaibility)

W
MA = x 100%
W R

348
= x 100%
348  20

MA = 94,56 %

b. Keadaan Fisik (Physical


Avaibility)

W S
PA = x 100%
W RS

348  80
= x 100%
348  20  80

PA = 95,53 %

c. Penggunaan Waktu (Use Of


Avaibility Percent)

W
UA = x 100%
W S

348
= x 100%
348  80

UA = 81,3 %
d. Effective Utilization

W
EU = x 100%
W SR

348
= x 100%
348  80  20

EU = 77,67 %

Waktu kerja efektif


e. Efisiensi Kerja
=
x 100%
Waktu kerja tersedia

348
= x 100%
480

= 72,5 %

2. Dump Truck Nissan CW 520

 Waktu efektif ( We ) = 342

menit/shift

 Waktu Repair ( R ) = 21

menit/shift

 Waktu Stand by ( S ) = 87

menit/shift

 Waktu delay ( Wd ) = 30

menit/shift

 Waktu Tersedia ( T ) = 480

menit/shift
a. Kesiapan Mekanik ( Mechanical
Avaibility)

W
MA = x 100%
W R

342
= x 100%
342  21

MA = 94,21 %

b. Keadaan Fisik (Physical


Avaibility)

W S
PA = x 100%
W RS

342  87
= x 100%
342  21  87

PA = 95,3 %

c. Penggunaan Waktu (Use Of


Avaibility Percent)

W
UA = x 100%
W S

342
= x 100%
342  87

UA = 79,72 %

d. Effective Utilization

W
EU = x 100%
W SR

342
= x 100%
342  87  21

EU = 76 %
Waktu kerja efektif
e. Efisiensi Kerja
=
x 100%
Waktu kerja tersedia

342
= x 100%
480

= 71,25 %

3. Dump Truck HINO 501 FM260TI

 Waktu efektif ( We ) = 339

menit/shift

 Waktu Repair ( R ) = 19

menit/shift

 Waktu Stand by ( S ) = 87

menit/shift

 Waktu delay ( Wd ) = 35

menit/shift

 Waktu Tersedia ( T ) = 480

menit/shift

a. Kesiapan Mekanik ( Mechanical Avaibility)

W
MA = x 100%
W R

339
= x 100%
339  19
MA = 94,69 %

b. Keadaan Fisik (Physical Avaibility)

W S
PA = x 100%
W RS

339  87
= x 100%
339  19  87

PA = 95,73 %

c. Penggunaan Waktu (Use Of Avaibility Percent)

W
UA = x 100%
W S

339
= x 100%
339  87

UA = 79,57 %

d. Effective Utilization

W
EU = x 100%
W SR

339
= x 100%
339  87  19

EU = 76,17 %

Waktu kerja efektif


e. Efisiensi Kerja
=
x 100%
Waktu kerja tersedia

339
= x 100%
480

= 70,62 %
4. Dump Truck HINO 502 FM260TI

 Waktu efektif ( We ) = 334

menit/shift

 Waktu Repair ( R ) = 20

menit/shift

 Waktu Stand by ( S ) = 78

menit/shift

 Waktu delay ( Wd ) = 48

menit/shift

 Waktu Tersedia ( T ) = 480

menit/shift

a. Kesiapan Mekanik ( Mechanical Avaibility)

W
MA = x 100%
W R

334
= x 100%
334  20

MA = 94,35 %

b. Keadaan Fisik (Physical Avaibility)

W S
PA = x 100%
W RS

334  78
= x 100%
334  20  78

PA = 95,37 %

c. Penggunaan Waktu (Use Of Avaibility Percent)


W
UA = x 100%
W S

334
= x 100%
334  78

UA = 81,06 %

d. Effective Utilization

W
EU = x 100%
W SR

334
= x 100%
334  78  20

EU = 77,31%

Waktu kerja efektif


e. Efisiensi Kerja
=
x 100%
Waktu kerja tersedia

334
= x 100%
480

= 69,58 %

5. Dump Truck HINO 503 FM260TI

 Waktu efektif ( We ) = 330

menit/shift

 Waktu Repair ( R ) = 21

menit/shift
 Waktu Stand by ( S ) = 74

menit/shift

 Waktu delay ( Wd ) = 55

menit/shift

 Waktu Tersedia ( T ) = 480

menit/shift

a. Kesiapan Mekanik ( Mechanical Avaibility)

W
MA = x 100%
W R

330
= x 100%
330  21

MA = 94,01 %

b. Keadaan Fisik (Physical Avaibility)

W S
PA = x 100%
W RS

330  74
= x 100%
330  21  74

PA = 95,05 %

c. Penggunaan Waktu (Use Of Avaibility Percent)

W
UA = x 100%
W S

330
= x 100%
330  74

UA = 81,68 %

d. Effective Utilization
W
EU = x 100%
W SR

330
= x 100%
330  74  21

EU = 77,64 %

Waktu kerja efektif


e. Efisiensi Kerja
=
x 100%
Waktu kerja tersedia

330
= x 100%
480

= 68,75 %