REQUEST FOR INSPECTION

MSK
Group
Contractor: MSK
Client: ZFOD Contract No. 5000012973 RFI No. MSK/RFI/0891
GROUP
Project: Water Injection Network EPC MSK work
Location: Shop
Date: 17-Mar-2021
Installation

Discipline: Mech. ITP No.:250600DBPLN0001 ITP Activity : Welder Qualification Test

Description of inspection:
Welder Qualification Test for pipeline as per WPS No (WPS-BW-003) .

INSPECTION DATE INSPECTION TIME LOCATION/AREA Ref. DOCs / DWGs

18-Mar-21 to 18-Mar-21 09:00:00 AM MSK work Shop

The above mentioned work activity has been final inspected and accepted.

CONTRACTOR / CONSTRUCTION CONTRACTOR / QA/QC CONTRACTOR / OTHER

Name: Name: Name:

Date: Date: Date:

Signature: Signature: Signature:

Validated by ENI/ZFOD CONSTRUCTION

Name: Date & Time Signature:

Received by ENI/ZFOD QA-QC

Name: Date & Time Signature:

RFI Acceptance & Inspection Result

ACCEPTABLE YES NO

A) Work is not ready at the inspection time

B) Result of inspection is not acceptable.


NOT ACCEPTED
C
New RFI shall be issued
)
D
See Eni comments attached
)
ENI/ZFOD QA-QC
Date &
Name: Signature:
Time