Ref: P.O.-HUAYOU-
Subject: Sub-contract Agreement for Fabrication, Installation Steel Bar (G40 & G60)
Formwork and Concreting works for SMDC Grace Residences Project.
Gentleman:
As per previous discussion. we herby issue the order for the following items from you. Please strictly
follow the attached construction schedule (15 days per floor to complete install) complete the work
based on standard which is subject to approval by OWNER.
DESCRIPTION UNIT UNIT PRICE REMARKS
Sub-contractor shall provide all the
P4.256/kg necessary manpower, equipments, and
Steel Bar kg (VAT consumables like tie wires, spacer and
INCLUSIVE) necessary supervision to fabricate and install
the steel bar as per requirement.
Sub-contractor shall provide labor and tools
Formworks
P224.00/m² to carry and install scaffoldings, fabrication
(Columns,
m² (VAT and installation of formworks, tie rod, pipe
shearwalls, slab,
INCLUSIVE) clamp, water stop if any and dismantle of
STP, & water tanks)
formworks after concrete pouring, etc.
Sub-contractor shall provide labor and tools
P246.40/m² to carry and install scaffoldings, fabrication
Formworks stairs,
m² (VAT and installation of formworks, tie rod, pipe
ramp
INCLUSIVE) clamp, water stop if any and dismantle of
formworks after concrete pouring, etc.
Sub-contractor shall provide all the
necessary manpower, equipment like
P201.60/m³
vibrators, consumables like nails, necessary
Concreting m³ (VAT
supervision to complete the concreting
INCLUSIVE)
works, while pumpcrete shall provide by
HUAYOU.
Straight to finish P44.80/m² Sub-contractor shall provide all the
m²
concrete (VAT necessary manpower, equipment,
consumables like nails, necessary
supervision to complete the concreting
INCLUSIVE)
works, while pumpcrete shall provide by
HUAYOU.
Prepared by:
Li Huaijun
Project Maager
Zhang Zongmin
General Manager – Huayou
Conformed by: