华 友 建 设 发 展 菲 律 宾 有 限 公 司

HUAYOU CONSTRUCTION DEVELOPMENT PHILIPPINES CORPORATION


Address: 101# Cedar Mansion II, Escriva Drive, Ortigas, Pasig City Tel: 638-1108 Fax: 638-1109

Ref: P.O.-HUAYOU-

August 17, 2013

Attention: Sorcon Bicol Builders (SBB)


Brgy. 702 Zone-77 #1924 Ma. Orosa St.
Malate Metro Manila, Philippines
Tel No. 02-425-0849

Subject: Sub-contract Agreement for Fabrication, Installation Steel Bar (G40 & G60)
Formwork and Concreting works for SMDC Grace Residences Project.

Gentleman:
As per previous discussion. we herby issue the order for the following items from you. Please strictly
follow the attached construction schedule (15 days per floor to complete install) complete the work
based on standard which is subject to approval by OWNER.
DESCRIPTION UNIT UNIT PRICE REMARKS
Sub-contractor shall provide all the
P4.256/kg necessary manpower, equipments, and
Steel Bar kg (VAT consumables like tie wires, spacer and
INCLUSIVE) necessary supervision to fabricate and install
the steel bar as per requirement.
Sub-contractor shall provide labor and tools
Formworks
P224.00/m² to carry and install scaffoldings, fabrication
(Columns,
m² (VAT and installation of formworks, tie rod, pipe
shearwalls, slab,
INCLUSIVE) clamp, water stop if any and dismantle of
STP, & water tanks)
formworks after concrete pouring, etc.
Sub-contractor shall provide labor and tools
P246.40/m² to carry and install scaffoldings, fabrication
Formworks stairs,
m² (VAT and installation of formworks, tie rod, pipe
ramp
INCLUSIVE) clamp, water stop if any and dismantle of
formworks after concrete pouring, etc.
Sub-contractor shall provide all the
necessary manpower, equipment like
P201.60/m³
vibrators, consumables like nails, necessary
Concreting m³ (VAT
supervision to complete the concreting
INCLUSIVE)
works, while pumpcrete shall provide by
HUAYOU.
Straight to finish P44.80/m² Sub-contractor shall provide all the

concrete (VAT necessary manpower, equipment,
consumables like nails, necessary
supervision to complete the concreting
INCLUSIVE)
works, while pumpcrete shall provide by
HUAYOU.

TERMS AND CONDITIONS:


 This agreement is Unit price basis. Payment is subject to actual installed quantity time above
unit price. Any cutting/bending shall be subjected to prior approval; otherwise, the wrong
cutting/bending caused expenses shall be shouldered by sub-contractor.
 Subcontractor to provide bender, cutter for fabrication of steel bar, tie wires, electricity and
consumables etc, shall be provided by sub-contractor.
 Workmanship shall comply with standard requirement, specification, plan, drawing and
instruction given by Huayou engineers, Safety hamlets, safety belts, shoes, etc. with related
to his work shall be provided by sub-con.
 Terms of payment: No down payment, progress payment every 14 days. Subcon shall submit
progress billing atleast three working days before expected payment which is subject for
evaluation by Huayou. Five percent (5%) retention will be released after acceptance by
Owner.
 Warranty for workmanship is one year since taken over by Owner.
 Sub-contractor shall provide barracks for his labor group.
 The above price is VAT INCLUSIVE price.

Prepared by:

Li Huaijun
Project Maager

Zhang Zongmin
General Manager – Huayou

Conformed by:

Sorcon Bicol Builders (SBB)