You are on page 1of 204

( No loading and unloading charges allowed for machinery loading and unloading )

page-23

(Lead)
charges
for trucks (Lead)
(Lead)
(Lead) and charges for
charges for
charges for trucks and (Lead)
trucks and tippers for (Lead)
trucks and Cement/ tippers per charges for
tippers for
tippers for cu.meter for trucks and charges for
Rubble/Size Steel/
Sl No. Distance Earth / PCC slabs/ tippers per trucks and
stones/ Cut RCC Shahabad cu.meter for tippers for
Sand /Gravel
/ Murrum/ Stones/ poles/ AC slabs/ CC & water/ 1000 Bricks
Coarse & GI /1000 nos
Lime/ Surki/ Laterite litres
aggregate sheets/
per cu.meter blocks/
per cu.meter Packed
Wood/ cum
materials/
tonne

1 2 3 4 5 6 7 8
1 Lead up to 1 km 1 34.70 33.60 21.00 49.50 20.80 56.10
2 Lead up to 2 km 2 48.60 47.10 29.40 69.30 29.10 78.50
3 Lead up to 3 km 3 64.80 64.80 40.50 94.30 38.80 104.70
4 Lead up to 4 km 4 78.70 78.70 49.20 115.70 47.20 127.10
5 Lead up to 5 km 5 92.50 92.50 57.80 136.10 55.50 149.50
6 for Every km beyond 5 km up to 30 km 30 13.90 13.90 8.70 20.40 8.30 22.40
7 for Every km beyond 30 km 10000 11.60 11.60 7.20 17.00 6.90 18.70

Rubble/ size
Earth / stone/ cut
Sand /Gravel stone/
Cement in Steel in Bricks
Sl No. Description of item Murrum/ / Coarse
Rs/Tonne Rs/Tonne Rs/1000 Nos.
Surki/ Rs / aggregate,
cum Lime in
Rs/cum

1 Loading 24.00 47.90 79.00 94.70 65.90


2 Unloading 12.00 23.95 79.00 94.70 65.90
COMMON SoR 2019-2020
Sl.
Items Reference to SoR
No S.No./ Item
Rate
Code No.
Part Page No.

1 Common burnt clay bricks (23x11x7cm) Buildings 9 TBSC-A.I-01 5700.00


Flyash cement / lime solid blocks (50 Kgs/
2 9 TBSC-A.II-08 24.00
sq.cm) 290mmx225mmx140mm
Flyash cement / lime solid blocks (50 Kgs/
3 9 TBSC-A.II-11 11.00
sq.cm) 290mmx100mmx140mm
Flyash cement / lime solid blocks (50 Kgs/
4 9 TBSC-A.II-12 6.00
sq.cm) 225mmx100mmx60mm

Polished Shahabad / Tandur stone slabs


5 10 TBSC-B.I-03 1640.00
15mm to 18mm thick
Polished black Kadapa slabs minimum of
6 10 TBSC-B.I-06 1370.00
15mm to 18mm thick
High Polished Granite 16 to 18 mm thick
7 up to 8'-00 (2.43 M) other than black and 11 TBSC-B.III-01 3118.00
premium colours
High Polished Granite 16 to 18 mm thick
8 up to 8'-00 (2.43 M) other than black and 11 TBSC-B.III-02 2709.00
regular colours
High Polished Granite 16 to 18 mm thick
9 11 TBSC-B.III-03 2303.00
up to 8'-00 (2.43 M) black.
Granite stone tiles 8mm thick (mirror
10 11 TBSC-B.III-04 1057.00
polished of all shades)

Non-skid full body ceramic floor tiles of


11 11 TBSC-C.I-01 300.00
size 300mm x 300mm, 7 - 8mm thick
Non - skid full body Ceramic tiles of size
12 11 TBSC-C.I-02 310.00
400mm x 400mm, 7 to 8mm thick

Soluble salt porcelain vitrified tiles screen


printed and polished of size 600mm x
13 12 TBSC-C.II-02 421.00
600mm , 8 to 10mm thick of any colour
and finish in all shades and designs

Nano polished / stain free soluble salt


porcelain vitrified tiles screen printed of
14 size 600mm x 600mm and thickness 12 TBSC-C.II-03 421.00
between 8 to 10mm of any colour and
finish in all shades and designs
Full body ceramic tiles of any size 5 to
15 16 TBSC-C.VI-02 480.00
7mm thick for dadooing
Glazed full body porcelain wall tiles of size
16 300 x 600 mm with any type of design 14 TBSC-C.IV-01 550.00
texture
Chequrred cement concrete heavy duty
16 17 TBSC-C.VIII-04 274.00
tiles, 25mm thick (300mm x 300mm)

17 Medium teak wood scantilings up to 2m 19 TBSC-D.I-01 72620.00

18 Medium teak wood scantilings 2 to 3m 19 TBSC-D.I-02 80689.00

19 Medium teak wood scantilings above 3m 19 TBSC-D.I-03 88759.00


Medium teak wood planks of any
20 19 TBSC-D.I-04 145240.00
thickness
19 Best teak wood scantilings up to 2m 19 TBSC-D.II-01 125068.00
20 Best teak wood scantilings 2 to 3m 19 TBSC-D.II-02 133137.00
21 Best teak wood scantilings above 3m 19 TBSC-D.II-03 141206.00

22 Best teak wood planks of any thickness 19 TBSC-D.II-04 157344.00

23 Sal wood scantlings any length 19 TBSC-D.V-01 44785.00


24 6mm thick corrugated AC sheets 19 TBSC-D.VI-01 220.00
Plain or Corrugated Galvanized iron
25 sheets as per IS 277(0.1mm to 0.8 mm 20 TBSC-D.VI-04 60.00
thickness)
Pre-painted Galvalume Trapezoidal
26 Profile Roofing sheets with 0.50mm 20 TBSC-D.VI-05 387.00
thickness
27 G.I scam bolts & nuts 21 TBSC-D.VI-14 6.00
28 8mm dia GI 'j' bolts & nuts 21 TBSC-D.VI-16 10.00
29 GI washers 21 TBSC-D.VI-17 2.00
30 Limpet washers (for scam & ‘J’ bolts) 21 TBSC-D.VI-18 2.00
31 Bitumen washers 21 TBSC-D.VI-19 2.00

32 Rolling Shutter (80x1.25mm) 21 TBSC-E.I-01 3909.00


33 Collapsable steel shutters 21 TBSC-E.I-02 3420.00
34 Rabbit wire mesh (chicken mesh) 22 TBSC-E.I-12 19.00
35 Cost of MS Tube 22 TBSC-E.I-15 61.00
36 Cost of stainless steel pipes 304 grade 23 TBSC-E.III-01 387.00

37 5mm thick plain glass 23 TBSC-F.I-02 507.00


38 12mm thick plain float glass 23 TBSC-F.I-06 1067.00
39 Pin headed glass 4mm thick 23 TBSC-F.II-01 300.00
40 Cost of 12mm thick tinted glass 23 TBSC-F.III-06 1402.00
41 5mm thick ground glass 24 TBSC-F.IV-02 678.00

Water based Cement Primer of Interior


42 24 TBSC-G.I-01 150.00
Grade- 1
Water based Cement Primer of Exterior
43 24 TBSC-G.I-02 191.00
Grade- 2
Wall putty of White Cement or Polymer or
44 24 TBSC-G.I-03 35.00
Cement based
45 Red oxide Primer Paint Grade-I 24 TBSC-G.I-05 129.00
Zinc Chromate Yellow Oxide Iron Primer
46 24 TBSC-G.I-06 185.00
paint
47 Ready made primer for Wood 24 TBSC-G.I-07 144.00
48 Putty for wood work 24 TBSC-G.I-09 144.00
49 Spirit 24 TBSC-G.I-12 101.00
50 Linseed Oil 24 TBSC-G.I-13 58.00
51 Thinner for Melamine polish 24 TBSC-G.I-14 133.00
52 French Polish 24 TBSC-G.I-16 188.00
Acrylic based Oil bound Washable
53 Distemper having VOC content less than 25 TBSC-G.II-03 54.00
50 grams/litre
54 Water proof cement paint 25 TBSC-G.II-04 51.00
Acrylic emulsion paint interior grade
55 having VOC content less than 50 25 TBSC-G.III-01 195.00
grams/litre
Supply of acrylic emulsion paint exterior
grade with silicon additives having VOC
56 (Volatile Organic Compound) content less 25 TBSC-G.III-02 204.00
than 50 grams/ liter.

Synthetic enamel paint Grade - I having


57 25 TBSC-G.V-01 251.00
VOC content less than 50 grams/litre
Synthetic enamel paint Grade - II having
58 25 TBSC-G.V-02 191.00
VOC content less than 50 grams/litre
Exterior grade Texture ready mixed paint
with sand texture added sand particles
59 Acrylic copolymers and mineral 25 TBSC-G.VI-01 37.00
compounds, bactericides and various
additives

Exterior grade Texture ready mixed paint


plaster made with natural minerals -
60 granite flakes / marble flakes / powder, 25 TBSC-G.VI-02 47.00
sand and other carefully selected and
seived minerals in acrylic binding medium

61 Melamine Polish 25 TBSC-G.VII-01 317.00


62 Interior grade Poly -Urethene polish 25 TBSC-G.VII-02 645.00
63 Exterior grade Poly -Urethene polish 25 TBSC-G.VII-03 788.00

12mm thick prelaminated paticle board


64 28 TBSC-H.III-48 783.00
(both sides laminated)
65 MDF Board Interior - BSL 18mm thick 25 TBSC-H.III-43 792.00

12.5mm Gypboard Tiles 595mm x


66 31 TBSC-K.I-01 255.00
595mm
67 Gypsom board plain sheets 12.5mm thick 31 TBSC-K.I-03 225.00

68 12mm Mineral Fiber sheet 600 x 600 31 TBSC-K.I-04 Deleted


69 14mm Mineral Fiber sheet 600 x 600 31 TBSC-K.I-05 535.00
70 15mm Mineral Fiber sheet 600 x 600 31 TBSC-K.I-06 626.00
71 12mm Thermocole sheet 32 TBSC-K.I-24 24.00

72 GI Ceiling Angle - 25mm x 10mm x 0.5mm 34 TBSC-K.II-01 67.00


GI Ceiling section - 51.5mm x 26mm x
73 34 TBSC-K.II-02 78.00
10.5mm x 0.55mm thick
Intermediate channel - 45mm x 15mm x
74 34 TBSC-K.II-03 77.00
15mm x 0.9mm
Perimeter channel - 20mm x 27mm x
75 34 TBSC-K.II-04 67.00
30mm (web) of 0.55mm thick
GI Angle - Precoated - 25mm x 25mm
76 34 TBSC-K.II-05 38.00
x0.7mm
GI pre coated - T section - 3600mm long -
77 34 TBSC-K.II-07 50.00
24mm x 38mm x 0.7mm thick
Hotdipped GI Angle - Precoated - Grid -
78 34 TBSC-K.II-08 37.00
19mmx19mmX0.7mm
Polyster painted GI - T section - 1200mm
TBSC-K.II-
79 - 24x32mm and 24x25mm (sub-cross 34 43.00
09&10
Tee)
Polyster painted GI-T Section - 300mm -
80 34 TBSC-K.II-11 42.00
24mm x 27mm
81 Aluminium angle - 24mmx 24mm 34 TBSC-K.II-12 24.00
Anodised Aluminium T section - 24mm x
82 34 TBSC-K.II-13 31.00
24.5mm x 2.4mm
83 Connecting Clips 34 TBSC-K.II-14 3.00
84 Rawl Plug 34 TBSC-K.II-15 3.00
85 6mm Nylon Rawl Plug 34 TBSC-K.II-16 3.00
86 Soffit Cleats 34 TBSC-K.II-17 3.00
87 Drywall screws - 25mm 34 TBSC-K.II-18 3.00
88 Jointing Compound 34 TBSC-K.II-19 27.00
89 Jointing Paper tape 34 TBSC-K.II-20 5.00
90 Drywall top coat 34 TBSC-K.II-21 129.00
91 Universal Holding Clips 34 TBSC-K.II-22 3.00
92 GI Rod - 4mm dia - Connecting Rod 34 TBSC-K.II-23 11.00
GI rod-prestraightened 2.0mm dia. -
93 34 TBSC-K.II-24 10.00
Connecting rod
Cement bonded Prelaminated particle
94 42 TBSC-K.IV-13 3507.00
board aluminium glazed partions

Providing and fixing door frames


95 fabricated from sections made of 47 TBSC-L.I-11 691.00
galvanized steel powder coated

96 30 mm thick flush shutter 49 TBSC-L.II-05 1192.00


97 35 mm thick flush shutter 49 TBSC-L.II-06 1349.00

Supply and fixing of UPVC sliding doors 3


98 57 TBSC-L.III-10 7083.00
track 2 glass and 1 mesh shutter
Supply and fixing of UPVC openable
99 59 TBSC-L.III-12 8029.00
doors
Scientific Door with metal door frame
100 61 TBSC-L.III-19 10307.00
(single leaf door)
Scientific Door with metal door frame
101 62 TBSC-L.III-20 10995.00
(double leaf door)

Pre painted steel windows


102 Windows with guard bars
i) Double shutter with mullion 69 TBSC-M.I-02 6697.00
Double shutter with Mullion section for
sizes 4'-6 x 4'-6 (1371.6x1371.6mm) 5'-0 x
4'-0
ii) 69 TBSC-M.I-04 5967.00
(1524x1219.2mm) and 6'-0 x 4'-0
(1828.8x1219.2mm) and 6'-0 x 4'-6
(1828.8x1371.6mm
Centre fixed both side openable shutter
window for sizes 5’0”x4’0” (1524mm
ii) 71 TBSC-M.I-07 5418.00
x1219.2mm) and 6’0”x4’0” (1828.8mm
x1219.2mm)
Pre painted steel Windows with fly
103
mesh
Double shutter Window with vertical
mullion of sizes 3’0” x 4’0” ( 914.4mm x
i) 72 TBSC-M.I-09 8036.00
1219.2mm) and 4’0” x 4’0” (1219.2mm x
1219.2mm)
Centre fixed both side open able shutter
ii) window for a size 5’0”x4’0” (1524mm 72 TBSC-M.I-10 7306.00
x1219.2mm).
Size of Window : 6’0”x4’0” (1828.8mm
iii) 72 TBSC-M.I-11 6393.00
x1219.2mm)
Supply and fixing of UPVC casement
104 78 TBSC-M.I-24 7067.00
windows (2.4mm)
Pre painted steel Window with 2 Track 2
105 81 TBSC-M.II-01 6799.00
glass shutter sliding Windows
Supply and fixing of UPVC sliding
106 86 TBSC-M.II-09 6407.00
windows 2 Track–2 Panel Sliding.
Supply and fixing of UPVC sliding
107 windows 3 track sliding windows with 87 TBSC-M.II-11 6690.00
mesh shutter
Supply and fixing of prepainted steel
sliding door - 3 track sliding window 88 TBSC-M.II-13 7518.00
/doors shutter with mesh shutter
108 Pre painted steel Ventilators
a) Top hung 89 TBSC-M.III-01 6942.00
b) Fixed louvered 90 TBSC-M.III-02 4749.00

Supplying and fixing fixed louvered


109 ventilator made out of of multi chambered 92 TBSC-M.III-07 6020.00
UPVC sections
Supplying and fixing top hung ventilator
110 made out of of multi chambered UPVC 92 TBSC-M.III-08 8470.00
sections

Curtain glazing made of pre painted


111
steel
Fixed Glazing 2'-0" x 2'-0"
a) (609.6x609.6mm) and 2'-0" x 3'-0" 93 TBSC-N.I-01 6027.00
(609.6x914.4mm)
Fixed Glazing 3'-0" x 3'-0"
b) (914.4x914.4mm), 3'-0" x 4'-0" 93 TBSC-N.I-02 5114.00
(914.4x1219.2mm)
S/F of UPVC fixed glazing 94 TBSC-N.I-04 3529.00
112 Pre painted steel Structural Glazing 94 TBSC-N.II-01 7306.00

113 Top Hung shutters in Structural Glazing 95 TBSC-N.II-02 5904.00

114 Brass tower bolt 150mm long 96 TBSC-P.I-02 236.00


115 Brass tower bolt 200mm long 96 TBSC-P.I-03 315.00
116 Al. tower bolt 150mm long 96 TBSC-P.I-08 66.00
117 Al. tower bolt 200mm long 96 TBSC-P.I-09 79.00
118 Al. tower bolt 300mm long 96 TBSC-P.I-11 109.00

119 MS powder coated tower bolt 100mm long 96 TBSC-P.I-14 24.00

120 MS powder coated tower bolt 150mm long 96 TBSC-P.I-15 35.00


121 MS powder coated tower bolt 200mm long 96 TBSC-P.I-16 52.00

122 Brass Butt hinges 150mm long 97 TBSC-P.II-04 348.00


123 Al. Butt hinges 150mm long 97 TBSC-P.II-08 93.00
124 Powder coated butt hinges 100mm long 97 TBSC-P.II-10 21.00
MS powder coated Butt hinges 150mm
125 97 TBSC-P.II-12 40.00
long
126 Friction stay hinges for windows 97 TBSC-P.II-15 213.00
127 Al. handle 125mm long 97 TBSC-P.III-03 74.00
128 Al. handle 150mm long 97 TBSC-P.III-04 87.00
129 MS powder coated handle 125mm long 97 TBSC-P.III-05 31.00
130 MS powder coated handle 150mm long 97 TBSC-P.III-06 45.00
131 Brass fancy handle 150mm long 97 TBSC-P.III-07 304.00
132 Brass fancy handle 450mm long 97 TBSC-P.III-11 1483.00
133 Brass aldrop 300mm long 98 TBSC-P.IV-01 1164.00
134 Brass aldrop 450mm long 98 TBSC-P.IV-03 3194.00
135 Al. aldrop 250mm long 98 TBSC-P.IV-05 192.00
136 Al. aldrop 300mm long 98 TBSC-P.IV-06 210.00
137 MS powder coated aldrop 250mm long 98 TBSC-P.IV-08 137.00
138 MS powder coated aldrop 300mm long 98 TBSC-P.IV-09 164.00
139 Cost of hydraulic floor springs 99 TBSC-P.VII-03 3452.00
140 Brass door stopper 100 TBSC-P.IX-01 180.00
141 MS powder coated door stopper 100 TBSC-P.IX-02 45.00
142 Heavy duty Al.door stopper 100 TBSC-P.IX-03 58.00

143 Integral water proofing liquid 101 TBSC-Q.II-01 191.00

Chloropyriphos Lindane Emulsifiable


144 102 TBSC-Q.VI-18 207.00
concentrate of 20%

Expansion joint filler board for buildings,


145 105 TBSC-Q.VIII-05 366.00
columns, beams and slabs 25 mm thick

146 White cement 106 TBSC-R.I-01 29.00


147 Powder coated Al. sections 106 TBSC-R.I-03 292.00
148 Rubber beading 106 TBSC-R.I-11 3.00

Aluminium composite cladding 4mm thick


149 107 TBSC-R.I-18 2570.00
with skin material thickness of 0.25mm

Aluminium composite cladding 4mm thick


150 107 TBSC-R.I-19 2882.00
with skin material thickness of 0.50mm

Precast RCC grills 50mm thick


151 108 TBSC-R.I-22 565.00
manufactured with M 30 grade concrete
152 24 gauge aluminium sheet 108 TBSC-R.I-23 274.00

7.5mm thick Aluminium Grill (as approved


153 108 TBSC-R.I-24 1009.00
by the department) 3.58 Kg/Sqm
Power Saw cutter - Hand Operated - Hire
154 110 TBSC-S.I-02 130.00
Charges
Power Drill - Hand Operated - Hire
155 110 TBSC-S.I-03 121.00
Charges

Rounding the edges of Kadapa /


156 Shahabad stone slab of any thickness 111 TBSC-T.I-10 122.00
including polishing the same
Half rounding the edges of Marble /
157 Granite slabs of all thicknesses and 111 TBSC-T.I-11 370.00
polishing the same
Full rounding the edges of Marble /
158 Granite slabs of all thicknesses and 111 TBSC-T.I-12 480.00
polishing the same
Machine cutting charges for Marble /
159 Granite slabs up to 50mm thickness by 111 TBSC-T.I-13 19.00
mechanical device
Flat nosing Shahabad/Kadapa slabs of
160 111 TBSC-T.I-14 58.00
any thickness

Labour charges for fabricating steel works


like Window Grills, Compound Wall Grills,
161 Iron Doors, Windows including cost of 111 TBSC-T.I-16 30.00
welding rods, power charges, excluding
cost of fixing in position.

Labour charges for fixing Iron Doors, Iron


162 112 TBSC-T.I-17 4.00
Windows and Window Grills in position

Labour charges for fabrication of stainless


163 112 TBSC-T.I-20 153.00
steel railing works
Labour charges for glass designing work
164 112 TBSC-T.I-22 1116.00
(Etching work)
Labour charges for fixing flush door
165 112 TBSC-T.I-25 447.00
shutters to the existing door frame
166 Labour charges for fixing glass 112 TBSC-T.I-26 333.00

167 Dismantling
a) Stone masonry in cement mortar 114 TBSC-U.I-01 464.00
Flat stone in roof or floors including
b) 114 TBSC-U.I-03 17.00
lifting :
Pan tiled or Mangalore tiled roof with out
c) 114 TBSC-U.I-04 15.00
roof timbers :
Wrought and framed timber in roofs or
d) 114 TBSC-U.I-06 241.00
floors
e) Old lime mortar plaster 114 TBSC-U.I-07 5.00
f) Old cement mortar plaster 114 TBSC-U.I-08 6.00
Kadapa slabs or shahabad stone slabs on
g) 115 TBSC-U.I-11 8.00
sand bed
Clean removal of lime plaster from walls
and raking out joints 20mm deep or from
h) 115 TBSC-U.I-14 5.00
terraced roof and raking out joints 100 mm
deep
Clean removal of cement plaster from
i) 115 TBSC-U.I-15 6.00
walls and raking out joint 200 mm deep
Buildings Referenc
Material hire Labour
168 Hire charges for Access Scaffolding e to SSR
charges charges
page
A) Brick Masonry / Stone Maasonry
a) 1st floor 117 10.32 83.43
b) 2nd floor 10.32 119.47
c) 3rd floor 10.32 155.49
d) 4th floor 10.32 191.53
e) 5th floor 10.32 227.56
f) 6th floor 10.32 263.58
g) 7th floor 10.32 299.60
h) 8th floor 10.32 335.63

B) Plastering to walls
a) 1st floor 117 1.03 8.35
b) 2nd floor 1.03 11.95
c) 3rd floor 1.03 15.54
d) 4th floor 1.03 19.15
e) 5th floor 1.03 22.75
f) 6th floor 1.03 26.37
g) 7th floor 1.03 29.97
h) 8th floor 1.03 33.56

169 Hire charges for Stage Scaffolding


Ceiling Plastering
a) 1st floor 117 2.46 16.71
b) 2nd floor 2.46 23.70
c) 3rd floor 2.46 30.69
d) 4th floor 2.46 37.70
e) 5th floor 2.46 44.69
f) 6th floor 2.46 51.68
g) 7th floor 2.46 58.68
h) 8th floor 2.46 65.68

170 HIRE CHARGES FOR CENTERING&SCAFFOLDING-centering using Steel scaffolding pip

Buildings Referenc Material hire


Lab
e to SoR charges
1st
Floor
a) Footings 116 288.00 663.00
b) Bed blocks, Steps 64.00 341.00
c) Pedestals 328.00 1054.00
d) Plinth beams 1390.00 1597.00

171 HIRE CHARGES FOR CENTERING & SCAFFOLDING -Unsupported height of 3.66M
Buildings Referenc Material hire
e to SoR charges Lab
1st
Floor
a) Lintels 116 1180.00 1696.00
b) Sunshades of any width 233.00 260.00
c) Columns 355.00 2381.00
d) Beams 2085.00 1998.00
e) RCC roof slabs upto 150 mm depth 236.00 226.00
f) RCC slabs upto 150-300 mm depth 243.00 233.00

172 HIRE CHARGES FOR CENTERING & SCAFFOLDING -Unsupported height of 3.66M - Casurina

Buildings Referenc Material hire


Lab
e to SoR charges
1st
Floor
a) Lintels 119 790.00 1314.00
b) Sunshades of any width 156.00 202.00
c) Columns 238.00 1845.00
d) Beams 1395.00 1547.00
e) RCC roof slabs upto 150 mm depth 158.00 175.00
f) RCC slabs upto 150-300 mm depth 163.00 181.00
g) RCC walls, water tank walls 1116.00
P&H
(RCC vertical walls)
173 Plumbing
PVC Clamps 110 mm items 164 TBSP-H.II-61 18.00

Part I (I&CAD
LABOUR CHARGES Works)
SKILLED
174 Bar bender 15 I-1 590.00
175 Blacksmith 15 I-2 495.00
176 Blaster (licensed) 15 I-3 590.00
177 Carpenter 15 I-4 590.00
178 Work Inspector(Non technical) 15 I -10 590.00
179 Mason / Brick layer 15 I -11 500.00
180 Operator concrete mixer 15 I -16 530.00
181 Operator Jackhammer / Pneumatic
tamper(skilled) 15 I - 23 520.00
182 Painter 15 I - 35 570.00
183 Plumber(licensed) / Pipe fitter 15 I - 36 580.00
SEMI SKILLED
183 Sprayer(semi skilled) 16 II - 1 470.00
184 Carpenter 16 II - 4 470.00
185 Plumber / Pipe fitter 16 II - 9 470.00
185 Mason / Brick layer 16 II - 35 470.00
186 Painter 16 II - 37 470.00
UN SKILLED
Heavy Mazdoor / Light Mazdoor
187 18 III - 3, 4 445.00
Cost of Materials :
188 Binding wire 1 3 55.00
189 Detonator electric 2 21 10.00
190 Sand (un-screened for concrete items) 2 27 570.00
191 Sand un-screened for filling 2 27 570.00
192 Sand(screened for mortar, plastering
items) 2 28 760.00
193 Impervious Water proof compound 4 95 95.00
194 Roads&
Bridges
Gravel / Quarry spall Works S.No.89/34 98.00
195 Aggregates 6mm nominal size (HBG) S.No.25/33 a 701.25
196 Aggregates 10mm nominal size (HBG) S.No.25/33 b 891.25
197 Aggregates 13.20 / 12.50mm nominal size
(HBG) S.No.25/33 c 1046.25
198 Aggregates 20mm nominal size (HBG) S.No.25/33 d 1157.50
199 Aggregates 40mm nominal size (HBG) S.No.25/33 f 701.25
200 SoR 2015-
Gelatin 80% 16 M - 104 73.00
201 Water charges (Urban) 276 98.00
202 Water charges (Rural) 275 73.00
203 PHE PH Items
PVC pipes 110mm dia. 4kg/cm2 Items Table17 157.00

204 Part I Referenc


e to SoR Hire & Fuel
Machinery Charges (I&CAD
charges
Works)
a) Air compressor 7 cmm ( diesel) 33 3 1126.10
b) Batching plant 0.50 cum (6 cum/hour) 33 9 241.40
c) Concrete Mixer 10 / 7 cft (0.2 / 0.8
cum)capacity 33 16 152.50
d) Jack hammer 34 39 20.80
e) Needle vibrator 40mm( petrol) 34 40 26.50
f) Shovel 0.850 cum 110hp 34 52 2718.00
g) Lift charges of materials(Winch 35HP-
Electric) 35 66 344.00

205 Seigniorage charges G.O.Ms.No. 67 of Industries and Commerce (Mines.I) Dept. dt.
i) Coarse aggregate , stone 2 75.00
ii) Earth , Gravel 2 30.00
ii) Sand for mortar & filling 2 40.00
iv) Bricks 3 60.00
v) Polished Shahabad/Tandur stone slbs 3 8.00
vi) Black Kadapa slabs 3 8.00
vii) Colour Granite 3 39.10
viii) Black Granite 3 34.00

206 Rough Stone (OTG) 1 (22.a) 152.00


Part II
207 Rough Stone (HBG) (Road & 12 (g) 239.00
208 Drilling 25mm dia. Holes with pneumatic Bridge
compressor works) 143 (ii)) 144.00

Non SSR items


1 Glass strips in Granolithic concrete
flooring 10.00
2 Stainless steel base Plate 75mm dia.(in
SS railing) 100.00
3 Anchor bars in SS railing 40.00
4 Bonding anchor bars in SS railing 20.00
5 Teak wood beading 12mm x 12mm 26.00
6 Teak wood beading 18mm x 12mm 32.00
7 250mm long brass butt hinges 600.00
8 Z holdfasts 300 x 40 x40x 5mm 669 100 TBSC-P.IX-08 32.00
9 Rubber bush 665 100 TBSC-P.IX-04 10.00
10 1.20mm thick PVC sheet 170.00
11 Fevicol & labour charges for fixing PVC
sheet for flush shutter 80.00
Wood Adhesive compound 203 24 TBSC-G.I-18 224.00
12 Al. round handles 150mm dia. 100.00
13 Powder coated handles 100mm long 30.00
14 Labour charges including cost of nails,
making holes to wall and in aluminium
sheet for expansion joint 30.00
15 Expansion joint treatment with poly 732
sulphide compound 104 TBSC-Q.VII-07 678.00
16 Labour charges for cup board shutters
and fixing fixtures 800.00
17 Cup board locks 100.00
18 Al. lock with handle 75.00
Encapsulated plastic steps PH 28 II 186
Unit

1000 Nos.

1 No.

1 No.

1 No.

10 Sqm

10 Sqm

1 Sqm

1 Sqm

1 Sqm

1 Sqm

1 Sqm

1 Sqm

1 Sqm

1 Sqm

1 Sqm

1 Sqm

1 Sqm

1 cum

1 cum

1 cum
1 cum

1 cum
1 cum
1 cum

1 cum

1 cum
1 sqm

1 Kg

1 sqm

1 No.
1 No.
1 No.
1 No.
1 No.

1 Sqm
1 Sqm
1 Sqm
1 Kg
1 Kg

1 sqm
1 sqm
1 sqm
1 sqm
1 sqm

1 Kg

1 Kg

1 Kg

1 Ltr

1 Ltr

1 Ltr
1 Kg
1 Ltr
1 Ltr
1 Ltr
1 Ltr.

1 Kg

1 Kg
1 Ltr

1 Ltr

1 Ltr

1 Ltr

1 Kg

1 Kg

1 Ltr.
1 Ltr.
1 Ltr.

1 sqm TBSC-H.IV-22

1 sqm

1 sqm

1 sqm

1 sqm
1 sqm
1 sqm
1 sqm

1 RM

1 RM

1 RM

1 RM

1 RM

1 RM

1 RM
1 RM
24x32 Rs. 50 45
1 RM

1 RM

1 RM

1 No.
1 No.
1 No.
1 No.
1 No.
1 Kg.
1 RM
1 Ltr
1 No.
1 RM

1 RM

1 sqm

1 RM

1 sqm
1 sqm

1 sqm

1 sqm

1 sqm

1 sqm

1 sqm

1 sqm

1 sqm
1 sqm

1 sqm
Previous SSR
1 sqm
Centre fixed both side openable
1 sqm

1 sqm
Pre painted steel Window with tw
1 sqm
Supply and fixing of UPVC slidin

1 sqm
Supply and fixing of UPVC slidin

1 sqm
Supply and fixing of prepainted s

1 sqm
1 sqm

1 sqm

1 sqm

1 sqm

1 sqm

1 sqm
1 sqm

1 sqm

1 No.
1 No.
1 No.
1 No.
1 No.

1 No.

1 No.
1 No.

1 No.
1 No.
1 No.

1 No.

1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.

1 Ltr
DELETED
2019-2020 rated
adopted
1 Ltr as per
SSR
2018-19

1 sqm

1 Kg
1 Kg
1 RM

1 sqm

1 sqm

1 sqm

1 sqm

1 sqm
1 hour

1 hour

1 RM

1 RM

1 RM

1 RM

1 RM

1 Kg

1 Kg

1 Kg

1 sqm

1 sqm

1 sqm

1 cum

1 sqm

1 sqm

1 cum

1 sqm
1 sqm

1 sqm

1 sqm

1 sqm
Unit

2018-19
1 Sqm 79.46
1 Sqm 113.78
1 Sqm 148.09
1 Sqm 182.41
1 Sqm 216.72
1 Sqm 251.03
1 Sqm
1 Sqm

1 Sqm 7.95
1 Sqm 11.38
1 Sqm 14.80
1 Sqm 18.24
1 Sqm 21.67
1 Sqm 25.11
1 Sqm
1 Sqm

1 Sqm 15.91
1 Sqm 22.57
1 Sqm 29.23
1 Sqm 35.90
1 Sqm 42.56
1 Sqm 49.22
1 Sqm
1 Sqm

using Steel scaffolding pipes, jack props, wallers, Foot plates, brackets, steel centering plates etc.,

Labour charges Unit


2nd 4th 5th 6th 7th 8th
3rd Floor
Floor Floor Floor Floor Floor Floor
1
375.10 409.20 443.30 477.40 511.50 545.60 579.70 1
1
1

Unsupported height of 3.66M - Steel scaffolding pipes, jack props, Steel centering Plates etc.

Labour charges Unit


2nd 4th 5th 6th 7th 8th
3rd Floor
Floor Floor Floor Floor floor Floor
1866.00 2035.00 2204.00 2374.00 2543.00 2713.00 2883.00 1
287.00 312.00 338.00 364.00 391.00 417.00 442.00 1
2620.00 2858.00 3095.00 3334.00 3572.00 3810.00 4049.00 1
2198.00 2397.00 2598.00 2797.00 2997.00 3196.00 3396.00 1
249.00 271.00 294.00 316.00 339.00 361.00 384.00 1
256.00 279.00 302.00 326.00 350.00 373.00 396.00 1

d height of 3.66M - Casurina Ballies, Bamboos, Wooden Reapers, Runners, Wood Posts, Wall Plates etc.,

Labour charges Unit


2nd 4th 5th 6th 7th 8th 9th
3rd Floor
Floor Floor Floor Floor Floor Floor Floor
1445.00 1575.00 1706.00 1838.00 1970.00 2101.00 2232.00 1
222.00 243.00 263.00 282.00 303.00 323.00 343.00 1
2029.00 2213.00 2398.00 2582.00 2768.00 2952.00 3135.00 1
1701.00 1856.00 2011.00 2165.00 2321.00 2475.00 2629.00 1
193.00 211.00 228.00 246.00 264.00 280.00 298.00 315.00 1
198.00 217.00 235.00 254.00 271.00 289.00 308.00 1
1

1 Each

1 Each 565.00
1 Each 470.00
1 Each 565.00
1 Each 565.00
1 Each 565.00
1 Each 470.00
1 Each 500.00

1 Each 500.00
1 Each 540.00
1 Each 540.00

1 Each 450.00
1 Each 450.00
1 Each 450.00
1 Each 450.00
1 Each 450.00

1 Each 425.00

1 Kg 50.00
1 No. 8.00
1 Cum 570.00
1 Cum 570.00

1 Cum 760.00
1 Kg 95.00

1 Cum
1 Cum 505.00 70
1 Cum 657.00 70

1 Cum 781.00 70
1 Cum 870.00 70
1 Cum 505.00 70

1 Kg
1 KL
1 KL

1 RM 164.00

Crew
charges
SoR 2017-18
1 hour 247.10 983.90 231
1 hour 389.30 237.10 107.1

1 hour 260.00 135.20 53


1 hour 386.10
1 hour 187.20 25.10 5.6
1 hour 271.70 2542.10 1624

1 hour 308.90 341.70 124.70

ommerce (Mines.I) Dept. dt.26.09.2015


1 cum
1 cum
1 cum
1000 Nos.
1 sqm
1 sqm
1 sqm
1 sqm

1 cum
1 cum

1 RM
1 sqm

1 No.
1 No.
1 No.
1 RM
1 RM
1 No.
1 No.
1 No.
1 sqm

1 sqm wood adhesive


1 kg
1 No.
1 No.

1 No.

1 RM

1 sqm
1 No.
1 No.
1 No.
7.125
7.1190476
Previous SSR 2017-18
TBSC-H.IV-22 667.00
24x25 Rs. 41
Previous SSR

Centre fixed both side openable shutters(6'x4')

Pre painted steel Window with two track - 2 panel sliding

Supply and fixing of UPVC sliding windows 2 track sliding

Supply and fixing of UPVC sliding windows 3 track sliding

Supply and fixing of prepainted steel sliding door - 3 track - 3 panel sliding doorsliding
2017-18
75.68
108.36
141.04
173.72
206.4
239.08

7.57
10.84
14.1
17.37
20.64
23.91

15.15
21.5
27.84
34.19
40.54
46.88

etc.,

Unit

Cum
Cum 357.5 390 422.5 455 487.5 1 Cum
Cum
Cum

2018-19
Unit Labour charges
1st 2nd 4th 5th 6th
3rd Floor
Floor Floor Floor Floor Floor
Cum 1615 1777 1938 2099 2261 2422
Sqm 248 272.80 297 322 347 372
Cum 2268 2495 2722 2948 3175 3402
Cum 1903 2093 2283 2474 2664 2854
Sqm 215 237 258 280 301 323
Sqm 222 244 266 288 310 333
1776.5 1938

ates etc.,
161.5
Unit
1776.50

Cum 790.00 869.00 1376.00 1500.00 1625.00 1750.00 1876.00


Sqm 156.00 192.00 211.00 231.00 250.00 269.00 289.00
Cum 238.00 1757.00 1932.00 2108.00 2284.00 2459.00 2636.00
Cum 1395.00 1473.00 1620.00 1768.00 1915.00 2062.00 2210.00
Sqm 158.00 167.00 184.00 201.00 217.00 234.00 251.00
Sqm 163.00 172.00 189.00 207.00 224.00 242.00 258.00
Sqm 1063.00
126.25 701.25
164.25 891.25

195.25 1046.25
217.5 1157.50
126.25 701.25

895.1 1126.1
134.3 241.4

99.5 152.5

20.9 26.5
1094 2718

219.30 344

2017-18
10

100
40
20
26
32
600
32
10
170

80
224
100
30

30

675

641
100
75
174
1 Cum
1 Sqm
1 Cum
1 Cum
1 Sqm
1 Sqm
1 Sqm
DATA (SoR 2019-20)
WATER SUPPLY AND SANITARY ITEMS
Sl. Plumbing SoR
ITEM Item code Rate
No. Items Page No.

Supply, laying, jointing 101.60 mm dia


1
SWG pipe
a) up to 1524mm (5') depth 131 TBSP-A.I-01 491.00
b) up to 914.40mm (3') depth 131 TBSP-A.I-02 425.00
Supply, laying, jointing 152.40mm dia
2
SWG pipe
a) up to 1524mm (5') depth 131 TBSP-A.I-03 712.00
b) up to 914.40mm (3') depth 131 TBSP-A.I-04 633.00

3 150mm x 100mm SWG gully trap 131 TBSP-A.I-09 622.00

4 Supply of 203.20mm (8") dia SWG pipe 132 TBSP-A.II-03 504.00

5 Supply of 254mm (10") dia SWG pipe 132 TBSP-A.II-04 922.00


6 Supply of 300mm (12") dia SWG pipe 132 TBSP-A.II-05 1330.00
Labour charges for laying , jointing ,
7 testing SWG pipes up to 914.40mm (3') 134 TBSP-A.III-01 265.00
depth
Labour charges for laying , jointing ,
8 testing SWG pipes up to 1524mm (5') 134 TBSP-A.III-02 329.00
depth

Inspection chamber 3' dia and upto 3'


9 135 TBSP-B.I-03 7357.00
depth
Inspection chamber 3' dia - 3' above
10 136 TBSP-B.I-04 11707.00
upto 5' depth
Inspection chamber 457.2mm x
11 457.2mm in brick masonry up to 136 TBSP-B.II-02 3832.00
914.4mm (3) depth
Constructing Brick masonry support for
G.I pipe with CM 304.8x228.6x 228.6
12 136 TBSP-B.II-04 77.00
mm size including plastering finishing
etc complete
13 CI frame and cover for gully traps 136 TBSP-B.II-06 125.00

Orissa pan 580mmx440mm - ISI TBSP-E.I-03/TBSP-


14 145/150 1313.00
marked E.VIII-02
15 Brick masonry seat 146 TBSP-E.I-06 272.00
16 C.C Squatting plate 146 TBSP-E.I-07 82.00
TBSP-E.II-
17 S&F EWC with'S' trap 146/150 1627.00
02/TBSP-E.VIII-06
TBSP-E.V-
18 S&F Plastic seat and lid for EWC 147/150 738.00
01/TBSP-E.VIII-07

Flat back Wash hand basin 1st quality TBSP-E.VI-


19 148/150 1476.00
550mmx400mm-single CP Pillar cock 04/TBSP-E.VIII-08

S & F vitreous china porcelain sink (600 TBSP-E.VI-


20 149/152 4107.00
x 400 x 250) 09/TBSP-E.VIII-012
S & F vitreous china porcelain sink (750 TBSP-E.VI-
21 149/152 4622.00
x 450 x 250) 10/TBSP-E.VIII-12

S&F flat back bowl urinal 440 x 265 x TBSP-E.VII-


22 150/151 771.00
315 01/TBSP-E.VIII-11
S&F flat back bowl urinal 590 x 375 x TBSP-E.VII-
23 150/151 2568.00
390 03/TBSP-E.VIII-11
Supplying & fixing stainless steel sink
24 size 36" x 18" (914.4x457.2mm) 1 mm 149 TBSP-E.VI-13 6255.00
thick with accessories
Supplying & fixing stainless steel sink
size 20" x 18" x 8"
25 149 TBSP-E.VI-15 4470.00
(508x457.2x203.20mm) 1 mm thick with
accessories
26 S&F RCC terrazo sink 149 TBSP-E.VI-16 655.00
Supplying & fixing white glazed
27 porcelain channel 4" x 24" (101.6 x 150 TBSP-E.VII-04 451.00
609.6mm)

TBSP-F.I-01 /
15 mm brass body CP finish bib tap of
28 151 TBSP-F.VIII- 224.00
not less than 300 grams weight
01
Chromium plated finish brass body
quarter turn Bibcock cum Health Faucet TBSP-F.I-07/TBSP-
29 151/156 2929.00
with 1m long tube and wall hook with 7 - F.VIII-01
10 years warranty
15 mm brass body CP finish self type TBSP-F.III-01 /
30 152/156 247.00
conforming to IS 1711closing tap push /TBSP-F.VIII-01
15 mm nominal size CP finish brass TBSP-F.IV-03
29 152/156 216.00
angled stop valve screw type TBSP-F.VIII-02
S&F 15 mm nominal size 152.0 mm CP TBSP-F.VI-
30 153/153 170.00
finish iron body shower 01/TBSP-F.VIII-04
TBSP-F.VII-
31 CP finish brass soap dish 152/156 517.00
21/TBSP-F.VIII-04
32 S&F 31.75mm brass plumber union 155 TBSP-F.VII-30 63.00

S& F Nominal Bore GI pipe Medium


33
Grade properties & weight
a) 15mm Nominal bore 156 TBSP-G.I-07 185.00
b) 20mm Nominal bore 156 TBSP-G.I-08 205.00
c) 25mm Nominal bore 156 TBSP-G.I-09 269.00
d) 32mm Nominal bore 157 TBSP-G.I-10 377.00
e) 40mm Nominal bore 157 TBSP-G.I-11 422.00
f) 50mm Nominal bore 157 TBSP-G.I-12 454.00
65mm Tata or Zenith make or
g) 157 TBSP-G.I-13 806.00
equivalent.

S&F Bronze Gate/ Globe valve as per


34 IS - 778 Class - I, Indian make heavy
type
a) 15mm NB 158 TBSP-G.III-01 580.00
b) 20mm NB 158 TBSP-G.III-02 782.00
c) 25mm NB 158 TBSP-G.III-03 1125.00
d) 32mm NB 158 TBSP-G.III-04 1709.00
e) 40mm NB 158 TBSP-G.III-05 2308.00
f) 50mm NB 158 TBSP-G.III-06 3382.00
g) 65mm NB 158 TBSP-G.III-07 5222.00
h) 80mm NB 158 TBSP-G.III-08 7741.00

Single socket PVC/SWR pipes 4


35
kgs/sqm
a) 75mm dia. 160 TBSP-H.I-01 252.00
b) 90mm dia. 160 TBSP-H.I-02 401.00
c) 110mm dia. 160 TBSP-H.I-03 479.00
d) 160mm dia. Double socket 160 TBSP-H.I-22 1140.00
Polyetheylene water storage tank with
36 161 TBSP-H.II-01 7.00
Double layer
Supply & fixing 30 mm nominal size dia
37 PVC flexible waste pipe of 914.4 mm 162 TBSP-H.II-04 26.00
length of Ist quality

Supply & fixing of PVC low level system


38
with internal components & short bend

a) 10ltrs capacity single flush 162 TBSP-H.II-07 1446.00


b) 8 lts capacity single flush 162 TBSP-H.II-09 818.00
39 Pipe clip
a) 75mm dia. 164 TBSP-H.II-59 15.00
b) 90mm dia. 164 TBSP-H.II-60 17.00
c) 110mm dia. 164 TBSP-H.II-61 18.00
d) 160mm dia. 164 TBSP-H.II-62 35.00
40 3" (75mm) Nahany trap with jali 164 TBSP-H.II-73 101.00
41 4" (101.6mm) multi floor trap with jali 164 TBSP-H.II-74 143.00
Labour charges for laying, fixing and
42 166 TBSP-H.IV-01
commissioning the PVC pipes

Chiseling the brick masonry wall and


43 166 TBSP-J.I-05
repairs as directed by the department
44 Cutting holes in brick masonry 167 TBSP-J.I-22
Cutting holes in RCC slab floor & repairs
45 167 TBSP-J.I-23
labour charges only
46 Cost of NP chain and rubber plug 167 TBSP-J.I-24 38.00
25.4mm dia & 609.6mm long aluminium
47 167 TBSP-J.I-25 150.00
anodized towel rod
48 Teak wood blocks 76.2mm x 101.6mm 167 TBSP-J.I-31 24.00
12.70mm PVC connection with brass
49 167 TBSP-J.I-32 102.00
union nut CP coated
S&F TV shap mirror with plastic frame
50 167 TBSP-J.I-35 468.00
size 609.60mm x 457.20mm
51 CPVC Pipes
15.90mm OD pipe - SDR 13.5 171 TBSP-J.III-01 129.00
22.20mm OD pipe - SDR 13.5 TBSP-J.III-02 147.00
28.60mm OD pipe - SDR 13.5 TBSP-J.III-03 194.00
34.90mm OD pipe - SDR 13.5 TBSP-J.III-04 264.00
41.30mm OD pipe - SDR 13.5 TBSP-J.III-05 329.00
54.00mm OD pipe - SDR 13.5 TBSP-J.III-06 479.00
15.90mm OD pipe - SDR 11 TBSP-J.III-07 142.00
22.20mm OD pipe - SDR 11 TBSP-J.III-08 173.00
28.60mm OD pipe - SDR 11 TBSP-J.III-09 207.00
34.90mm OD pipe - SDR 11 TBSP-J.III-10 282.00
41.30mm OD pipe - SDR 11 TBSP-J.III-11 350.00
54.00mm OD pipe - SDR 11 TBSP-J.III-12 510.00

52 16mm to 20mm thick marble slab 11 TBSC-B.II-03 907.00

NON SSR ITEMS


1 RCC cover for gully trap 100.00
Labour Unit

1 RM
1 RM

1 RM
1 RM

1 Each 2017-18
1 RM
480
1 RM 878
1 RM 1266

1 RM

1 RM

1 Each
7321
1 Each
11649

1 Each
3813

1 Each
76
1 Each 124

429.00 1 Each
1306
1 Each 271
1 Each 81
301.00 1 Each
1619
87.00 1 Each
734

429.00 1 Each
1469

429.00 1 Each
4087
429.00 1 Each
4599
171.00 1 Each
767
171.00 1 Each
2555

1 Each
6224

1 Each
4448
1 Each 652

1 Each
449

53.00 1 Each
223

53.00 1 Each
2914
53.00 1 Each
246
103.00 1 Each
215
103.00 1 Each
169
103.00 1 Each
514
1 Each 63

1 RM 184
1 RM 204
1 RM 268
1 RM 375
1 RM 420
1 RM 452
1 RM
802

1 Each 577
1 Each 778
1 Each 1119
1 Each 1700
1 Each 2297
1 Each 3365
1 Each 5196
1 Each 7702

3 RM 252
3 RM 401
3 RM 479
3 RM 1140
1 Lt
7

1 Each
26

1 Each 1439
1 Each 814

1 Each 15
1 Each 17
1 Each 18
1 Each 35
1 Each 101
1 Each 143
79.00 1 Each

31.00 1 RM

49.00 1 RM

75.00 1 No.

1 Each 38
1 Each
149
1 Each
24
1 Each
101
1 Each
466

1 RM 128
1 RM 146
1 RM 193
1 RM 263
1 RM 327
1 RM 477
1 RM 141
1 RM 172
1 RM 206
1 RM 281
1 RM 348
1 RM 508

1 sqm 907

1 Each 100
A Name of the work: Providing Gas Supplying pipeline for Supplying and
Centralized Medical Oxygen to bed for COVID-19 Management in Gandhi Hospital
Secunderabab

B Sources and Leads


Material Quarry Lead in KM
1 Cement
2 Steel
3 Sand for concrete Koilakonda 125.00
4 Sand for mortar, plastering Koilakonda 125.00
5 Sand for filling Local 20.00
6 Second Class Bricks Rajendranagar 45.00
7 Fly ash bricks 290 x 225 x 140 Keesara 30.00
8 Fly ash bricks 290 x 100 x 140 Keesara 30.00
9 Fly ash bricks 225 x 100 x 60 Keesara 30.00
10 40mm HBG Metal Machine crushed Keesara 32.00
11 20mm HBG Metal Machine crushed Keesara 32.00
12 12mm HBG Metal Machine crushed Keesara 32.00
13 10mm HBG Metal Machine crushed Keesara 32.00
14 6mm HBG Metal Machine crushed Keesara 32.00
15 Rough Stone OTG Keesara 32.00
16 Rough Stone HBG Keesara 32.00
17 Gravel Local 21.00
18 Shahabad stone slabs Tandur 95.00
19 Kadapa stone slabs Tandur 95.00

C Cement & Steel Rates July, 2020


1 Cement 5600.00

2 Fe-500 43000.00

3 Fe-415 0.00

4 Mild Steel 38000.00

5 Structural Steel 39000.00

6 MS Flats 43000.00

D Allowances
1 Add for MA @ 40% 40%
2 Overheads&Contractors Profit @ 13.615% 0.000%

Type of Habitation 2 1 for Rural


2 for Urban
Water charges 98.00
Hyderabad Original works
LEAD CHART (COMMON SoR 2019-2020) (Cement & Steel - July, 2020 rates)
Convey-
Reference
S.No./ ance Unloading MA
Sl. to SSR Lead in Initial Loading
Description Source of Materials Item Code Unit Charges charges (-) Total
No. page KM Cost charges
No. (-) 13.615%
number
13.615% 40%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
Ordinary Portland Cement 43 / 53 grade
1 1 MT 5600.00 5600.00
(including loading charges) NRB
2 Reinforcement steel Fe- 500 1 MT 43000.00 43000.00
3 Reinforcement steel Fe- 415 1 MT 0.00 0.00
4 Mild steel bars 1 MT 38000.00 38000.00
5 Structural steel 1 MT 39000.00 39000.00
6 MS flats 1 MT 43000.00 43000.00
7 Sand (un-screened for concrete items) Koilakonda 2 27 1 Cum 125.00 570.00 1326.68 1896.68
Sand (screened for mortar, plastering 28
8 Koilakonda 2 125.00 760.00 1326.68 2086.68
items)
9 Sand for filling Local 2 27 1 Cum 20.00 570.00 234.39 804.39
10 Common burnt clay bricks (23x11x7cm) Rajendranagar 9 TBSC-A.I-01 1000 Nos 45.00 5700.00 821.99 58.00 23.20 6603.19
Flyash cement / lime solid blocks (50 Kgs/
11 Keesara 9 TBSC-A.II-08 1000 Nos 30.00 24000.00 2966.43 26966.43
sq.cm) 290mmx225mmx140mm
Flyash cement / lime solid blocks (50 Kgs/
12 Keesara 9 TBSC-A.II-11 1000 Nos 30.00 11000.00 1318.42 12318.42
sq.cm) 290mmx100mmx140mm
13 Aggregates 40mm nominal size (HBG) Keesara 0 S.No.25/33 f 1 Cum 32.00 701.25 378.12 1079.37

14 Aggregates 20mm nominal size (HBG) Keesara 0 S.No.25/33 d 1 Cum 32.00 1157.50 378.12 1535.62
Aggregates 13.20 / 12.50mm nominal size
15 Keesara 0 S.No.25/33 c 1 Cum 32.00 1046.25 378.12 1424.37
(HBG)
16 Aggregates 10mm nominal size (HBG) Keesara 0 S.No.25/33 b 1 Cum 32.00 891.25 378.12 1269.37

17 Aggregates 6mm nominal size (HBG) Keesara 0 S.No.25/33 a 1 Cum 32.00 701.25 378.12 1079.37

(Part II) Roads


18 Rough Stone (OTG) Keesara & Bridges 1 (22.a) 1 Cum 32.00 152.00 378.12 530.12

(Part II) Roads


19 Rough Stone (HBG) Keesara & Bridges 12 (g) 1 Cum 32.00 239.00 378.12 617.12

20 Gravel / Quarry spall Local 0 S.No.89/34 1 Cum 21.00 98.00 246.63 344.63
Polished Shahabad / Tandur stone slabs
21 Tandur 10 TBSC-B.I-03 10 Sqm 95.00 1640.00 247.12 3.48 1.39 1891.99
15mm to 18mm thick
Convey-
Reference
S.No./ ance Unloading MA
Sl. to SSR Lead in Initial Loading
Description Source of Materials Item Code Unit Charges charges (-) Total
No. page KM Cost charges
No. (-) 13.615%
number
13.615% 40%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
Polished black Kadapa slabs 15mm to
22 Tandur 10 TBSC-B.I-06 10 Sqm 95.00 1370.00 247.12 3.48 1.39 1621.99
18mm thick
High Polished Granite 16 to 18 mm thick
23 up to 8'-00 (2.43 M) other than black and 11 TBSC-B.III-02 1 Sqm - 2709.00 2709.00
regular colours
High Polished Granite 16 to 18 mm thick
24 11 TBSC-B.III-03 1 Sqm - 2303.00 2303.00
up to 8'-00 (2.43 M) black.

1) Certified that the leads mentioned in the lead statement are shortest and correct.
2) Certified that metal are to be obtained by blasting.
3) Certified that sufficient quantities & quanlity material are available in the quarries.
4) Certified that for non SSR items lowest market rates are adopted
5) Certified that 40% extra on labour towards Municipal area allowance is allowed
CIVIL DATA : Page-14

D A T A (SoR 2019-20)

720 kg 480 kg 360 kg 288 kg 240 kg 180 kg


CEMENT MORTAR PER CUM CM (1:2) CM (1:3) CM (1:4) CM (1:5) CM (1:6) CM (1:8)
Cost of Sand for mortar & Plastering
(1.05 cum) 2191.01 2191.01 2191.01 2191.01 2191.01 2191.01

Cost of cement 4032.00 2688.00 2016.00 1612.80 1344.00 1008.00


Mazdoor (Unskilled ) for mixing mortar
( 0.20 Nos.) 89.00 89.00 89.00 89.00 89.00 89.00

Add for MA @ 40% 35.60 35.60 35.60 35.60 35.60 35.60


Rate per Cum 6347.61 5003.61 4331.61 3928.41 3659.61 3323.61

20 mm HBG graded metal


Arregates 20mm nominal size 0.60 1535.62 921.37
Arregates 13.20 / 12.50mm nominal size 0.15 1424.37 213.66
Arregates 10mm nominal size 0.15 1269.37 190.41
Arregates 6mm nominal size 0.10 1079.37 107.94
Rate per Cum 1433.38

12 mm HBG graded metal


Arregates 13.20 / 12.50mm nominal size 0.60 1424.37 854.62
Arregates 10mm nominal size 0.20 1269.37 253.87
Arregates 6mm nominal size 0.20 1079.37 215.87

Rate per Cum 1324.37

DATA

Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
1 Dismantling, clearing away and carefully stacking useful materials for re-use and disposal of unserviceable materials
with 100m lead as directed by Executive Engineer duly taking actual premeasurements before dismantling including
all labour charges , overheads & contractor profit etc., complete

b) Unreinforced cement concrete up to 15cm thickness


(BLD-CSTN-14-8/296)
Mazdoor(unskilled) 2.44 Nos. 445.00 1 Each 1085.80
Add for MA @ 40% 0.40 1085.80 434.32
Rate per 1 cum 1520.12
Overheads&Contractors Profit @ 13.615% 0.00000 1520.12 0.00
Rate per 1 cum 1520.12
say 1520

2 Earth work excavation for foundations (Manual Means) of buildings, septic tank, sump, compound wall in
ordinary soils and depositing on bank with an initial lead of 10m and 1m additional lift charges over the initial
depth up to 3m including all operational,incidental, labour charges such as shoring, sheeting, planking, strutting etc.,
and overheads & contractors profit complete for finished item of work excluding dewatering charges etc., as per SS
20 B(APSS 308)

(BLD-CSTN-2-1& COM-LDLFT-6-66)
Rate with initial lead & lift 1.00 cum 226.77 1 cum 226.77
Mazdoor for extra lift ( 1 No. for 60m) 0.02 Nos. 445.00 1 Each 8.90
Add for MA @ 40% 0.40 8.90 3.56
Overheads&Contractors Profit @ 13.615% 0.00000 12.46 0.00
Rate per 1 cum 239.23
Say 239

Page 14 of 204
CIVIL DATA : Page-15

Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
11 Filling with carted coarse sand in trenches,sides of foundations and basement with initial lead in layers not
exceeding 15cm thick,watering and ramming including cost and conveyance of water to work site and all
peraitonal,incidental ,labour charges,hire charges of T&P etc., and overheads & contractors profit complete for
fnished item of work(APSS NO.309&310)

(BLD-CSTN-2-8) & Amendment in page 12 of SoR 2014.15


Unit : 1 cum
Taking output = 6 cum
a) Labour
Mazdoor ( Unskilled ) 0.31 Nos. 445.00 1 No. 137.95
Add for MA @ 40% 0.40 137.95 55.18
b)Material :
Coarse sand for filling 6.00 cum 804.39 1 cum 4826.34
Water 0.72 Kl 98.00 1 Kl 70.56
5090.03
Overheads&Contractors Profit @ 13.615% 0.00000 5090.03 0.00
Rate per 6 cum 5090.03
Say 848

12 Filling with carted gravel in trenches,sides of foundations and basement with initial lead in layers not exceeding
15cm thick,watering and ramming including cost and conveyance of water to work site and all peraitonal,incidental,
labour charges,hire charges of T&P etc., and overheads & contractors profit complete for fnished item of work(APSS
NO.309&310)
(BLD-CSTN-2-8) & Amendment in SoR 2014-15
Unit : 1 cum
Taking output = 6 cum
a) Labour
Mazdoor ( Unskilled ) 0.31 Nos. 445.00 1 No. 137.95
Add for MA @ 40% 0.40 137.95 55.18
b)Material :
Gravel 6.00 cum 344.63 1 cum 2067.78
Water 0.72 Kl 98.00 1 Kl 70.56
Rate per 6 cum (a+b+c) 2331.47
Overheads&Contractors Profit @ 13.615% 0.00000 2331.47 0.00
Rate per 6 cum 2331.47
Rate per 1 cum 388.58
Say 389

15 Plain Cement Concrete (1:5:10) (cement: fine aggregate: Coarse aggregate) for foundations and under flooring
bed using coarse aggregate 40mm size hard , machine crushed granite from approved quarry including cost
and conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, sales & other taxes on all
materials and including all charges for machine mixing, laying concrete in foundations and under flooring bed,
ramming in 15 cm layers finishing top surface to the required level curing etc.,and overheads & contractors profit
complete for finished item of work. (APSS No. 402)

(BLD-CSTN-3-7)
Unit : 1 cum
A.MATERIALS :
Cement 129.60 Kgs 5600.00 1000 Kgs 725.76
Coarse aggregate 40mm 0.90 Cum 1079.37 1 Cum 971.43
Fine aggregate ( Sand ) 0.45 Cum 1896.68 1 Cum 853.51
Water (including curing) 1.20 kl 98.00 1 kl 117.60
B.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8
cum)capacity 1.00 hour 152.50 1 hour 152.50
Crew charges 1.00 hour 260.00 1 hour 260.00
Add MA on crew charges 0.40 260.00 104.00
C.LABOUR :
1st class mason 0.10 Nos. 500.00 1 Each 50.00
Mazdoor (unskilled) 1.39 Nos. 445.00 1 Each 618.55
Add for MA @ 40% 0.40 668.55 267.42
4120.77
Overheads&Contractors Profit @ 13.615% 0.00000 4120.77 0.00
Rate per 1 cum 4120.77
Say 4121

Page 15 of 204
CIVIL DATA : Page-16

Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
18 Plain Cement Concrete (1:3:6) nominal mix using 40mm size machine crushed hard granite metal (coarse
aggregate) in (2:1) ratio from approved quarry including cost and conveyance of all materials like cement, fine
aggregate (sand), coarse aggregate, water etc. to site, sales & other taxes on all materials, all charges for mixing,
laying concrete in position, vibrating, curing, centering charges, overheads & contractors profit etc.,for finished item of
work for footings and basement.

(BLD-CSTN-3-10 & 11)


Unit : 1cum
A.MATERIALS :
HBG 40mm size metal 0.90 Cum 1079.37 1 Cum 971.43
Sand 0.45 Cum 1896.68 1 Cum 853.51
Cement 220.00 Kgs 5600.00 1 MT 1232.00
Water ( including for curing ) 1.20 Kl 98.00 1 Kl 117.60
B.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8
cum)capacity 1.00 hour 152.50 1 hour 152.50
Crew Charges 1.00 hour 260.00 1 hour 260.00
Add MA on crew charges 0.40 260.00 104.00
C.LABOUR :
1st class mason 0.10 Nos. 500.00 1 Each 50.00
Mazdoor (Unskilled) 1.39 Nos. 445.00 1 Each 618.55
Add for MA @ 40% 0.40 668.55 267.42
Rate for 1 cum 4627.01
Overheads&Contractors Profit @ 13.615% 0.00000 4627.01 0.00
Rate per 1 cum 4627.01
Say 4627

19 Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS 456 with minimum cement
content of 380 kgs per 1 cum of concrete using Concrete Batching Plant with 20mm size graded machine crushed
hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site
and sales & other taxes on all materials , centering using Steel scaffolding pipes , jack props , wallers , Foot plates ,
brackets , steel centering plates etc., including all operational, incidental and labour charges such as weigh batching,
machine mixing, laying concrete, curing etc., and overheads & contractors profit complete but excluding cost of steel
and its fabrication charges for finished item of work (APSS No. 402).

(BLD-CSTN-3-14)
FOUNDATIONS , PLINTH , PEDESTALS ( Below Plinth)
A.MATERIALS :
Cement 380.00 Kgs 5600.00 1000 Kgs 2128.00
20mm HBG graded metal 0.80 Cum 1433.38 1 Cum 1146.70
Sand 0.40 Cum 1896.68 1 Cum 758.67
B.LABOUR :
1st class Mason 0.133 Nos 500.00 1 Each 66.50
2nd class Mason 0.267 Nos 470.00 1 Each 125.49
Mazdoor (both men&women) 4.60 Nos 445.00 1 Each 2047.00
Add for MA @ 40% 0.40 2238.99 895.60
C.MACHINERY :
Batching plant 0.50 cum 1.333 hours 241.40 1 hour 321.79
Crew charges 1.333 hours 389.30 1 hour 518.94
Needle vibrator 40mm ( petrol ) 1.333 hours 26.50 1 hour 35.32
Crew charges 1.333 hours 187.20 1 hour 249.54
Add MA on crew charges 0.40 768.47 307.39
Water(including for curing) 1.20 kl 98.00 1 kl 117.60
Rate per 1 cum 8718.54

a Footings
Rate for Design mix M 25 1.00 Cum 8718.54 1 Cum 8718.54
Hire charges of centering and scaffolding 1.00 Cum 288.00 1 Cum 288.00
Labour charges 1.00 Cum 663.00 1 Cum 663.00
Add for MA @ 40% 0.40 663.00 265.20
9934.74
Overheads&Contractors Profit @ 13.615% 0.00000 9934.74 0.00
Rate per 1 cum 9934.74
Say 9935

b Column pedestals
Rate for Design mix M 25 1.00 Cum 8718.54 1 Cum 8718.54
Hire charges of centering and scaffolding 1.00 Cum 328.00 1 Cum 328.00
Page 16 of 204
CIVIL DATA : Page-17

Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
Labour charges 1.00 Cum 1054.00 1 Cum 1054.00
Add for MA @ 40% 0.40 1054.00 421.60
10522.14
Overheads&Contractors Profit @ 13.615% 0.00000 10522.14 0.00
Rate per 1 cum 10522.14
Say 10522

c Plinth Beams
Rate for Design mix M 25 1.00 Cum 8718.54 1 Cum 8718.54
Hire charges of centering and scaffolding 1.00 Cum 1390.00 1 Cum 1390.00
Labour charges 1.00 Cum 1597.00 1 Cum 1597.00
Add for MA @ 40% 0.40 1597.00 638.80
12344.34
Overheads&Contractors Profit @ 13.615% 0.00000 12344.34 0.00
Rate per 1 cum 12344.34
Say 12344

20 Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS 456 with minimum cement
content of 380 kgs per 1 cum of concrete using Concrete Batching Plant with 20mm size graded machine crushed
hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site
and sales & other taxes on all materials, centering using Casurina Ballies, Bamboos, Wooden Reapers, Runners,
Wood Posts, Steel Plates etc., including all operational, incidental and labour charges such as weigh batching,
machine mixing, lifting of concrete manually, laying concrete, curing , overheads & contractors profit etc., complete
but excluding cost of steel and its fabrication charges for finished item of work (APSS No. 402)

(BLD-CSTN-3-15)
COLUMNS, LINTELS, WATER TANKS, RCC WALL IN BUILDINGS:
A.MATERIALS :
Cement 380.00 Kgs 5600.00 1000 Kgs 2128.00
20mm HBG graded metal 0.80 Cum 1433.38 1 Cum 1146.70
Sand 0.40 Cum 1896.68 1 Cum 758.67
B.LABOUR :
1st class Mason 0.167 Nos 500.00 1 Each 83.50
2nd class Mason 0.167 Nos 470.00 1 Each 78.49
Mazdoor (both men&women) 5.60 Nos 445.00 1 Each 2492.00
Add for MA @ 40% 0.40 2653.99 1061.60
C.MACHINERY :
Batching plant 0.50 cum 1.333 hours 241.40 1 hour 321.79
Crew charges 1.333 hours 389.30 1 hour 518.94
Needle vibrator 40mm ( petrol ) 1.333 hours 26.50 1 hour 35.32
Crew charges 1.333 hours 187.20 1 hour 249.54
Add MA on crew charges 0.40 768.47 307.39
Water(including for curing) 1.20 kl 98.00 1 kl 117.60
Rate per 1 cum 9299.54

a) COLUMNS :
un supported height up to 3.66 m
(i) Lifting by Manual means
Rate for other Floors FF SF TF 4F 5F
Rate as above 9299.54 9299.54 9299.54 9299.54 9299.54
Hire charges of centering and scaffolding 238.00 238.00 238.00 238.00 238.00
Labour charges 1845.00 2029.00 2213.00 2398.00 2582.00
Add for MA @ 40% 738.00 811.60 885.20 959.20 1032.80
Lift charges of materials(Manual) 0.00 265.40 530.80 796.20 1061.60
Add for MA @ 40% 0.00 106.16 212.32 318.48 424.64
Rate per 1 cum 12120.54 12749.70 13378.86 14009.41 14638.57
Overheads&Contractors Profit @ 13.615% 0.00 0.00 0.00 0.00 0.00
Rate per 1 cum 12120.54 12749.70 13378.86 14009.41 14638.57
Say 12121 12750 13379 14009 14639

Rate for other Floors 6F 7F 8F


Rate as above 9299.54 9299.54 9299.54
Hire charges of centering and scaffolding 238.00 238.00 238.00
Labour charges 2768.00 2952.00 3135.00
Add for MA @ 40% 1107.20 1180.80 1254.00
Lift charges of materials(Manual) 1327.00 1592.39 1857.79

Page 17 of 204
CIVIL DATA : Page-18

Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
Add for MA @ 40% 530.80 636.96 743.12
Rate per 1 cum 15270.53 15899.69 16527.45
Overheads&Contractors Profit @ 13.615%
0.00 0.00 0.00
Rate per 1 cum 15270.53 15899.69 16527.45
Say 15271 15900 16527

(ii) Lifting by Mechanical means


Rate for other Floors FF SF TF 4F 5F
Rate as above 9299.54 9299.54 9299.54 9299.54 9299.54
Hire charges of centering and scaffolding 238.00 238.00 238.00 238.00 238.00
Labour charges 1845.00 2029.00 2213.00 2398.00 2582.00
Add for MA @ 40% 738.00 811.60 885.20 959.20 1032.80
Lift charges of materials (Winch 35HP
0.00 458.55 504.41 550.26 596.12
Electric)
Crew charges 0.00 411.76 452.94 494.12 535.29
Add for MA @ 40% 0.00 164.71 181.18 197.65 214.12
Rate per 1 cum 12120.54 13413.16 13774.26 14136.77 14497.87
Overheads&Contractors Profit @ 13.615% 0.00 0.00 0.00 0.00 0.00
Rate per 1 cum 12120.54 13413.16 13774.26 14136.77 14497.87
Say 12121 13413 13774 14137 14498

Rate for other Floors 6TH 7TH 8TH


Rate as above 9299.54 9299.54 9299.54
Hire charges of centering and scaffolding 238.00 238.00 238.00
Labour charges 2768.00 2952.00 3135.00
Add for MA @ 40% 1107.20 1180.80 1254.00
Lift charges of materials (Winch 35HP
641.97 687.83 733.68
Electric)
Crew charges 576.47 617.65 658.82
Add for MA @ 40% 230.59 247.06 263.53
Rate per 1 cum 14861.77 15222.87 15582.57
Overheads&Contractors Profit @ 13.615%
0.00 0.00 0.00
Rate per 1 cum 14861.77 15222.87 15582.57
Say 14862 15223 15583

b) LINTELS :
(i) Lifting by Manual means
Rate for other Floors FF SF TF 4F 5F
Rate as above 9299.54 9299.54 9299.54 9299.54 9299.54
Hire charges of centering and scaffolding 790.00 790.00 790.00 790.00 790.00
Labour charges 1314.00 1445.00 1575.00 1706.00 1838.00
Add for MA @ 40% 525.60 578.00 630.00 682.40 735.20
Lift charges of materials(Manual) 0.00 265.40 530.80 796.20 1061.60
Add for MA @ 40% 0.00 106.16 212.32 318.48 424.64
Rate per 1 cum 11929.14 12484.10 13037.66 13592.61 14148.97
Overheads&Contractors Profit @ 13.615% 0.00 0.00 0.00 0.00 0.00
Rate per 1 cum 11929.14 12484.10 13037.66 13592.61 14148.97
Say 11929 12484 13038 13593 14149

22 Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS 456 with minimum cement
content of 380 kgs per 1 cum of concrete using Concrete Batching Plant with 20mm size graded machine crushed
hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site
and including sales & other taxes on all materials , centering using Casurina Ballies , Bamboos , Wooden Reapers ,
Runners , Wood Posts , Wall Plates etc., for 60cm wide sun-shades 7.5cm thick at fixed end and 5cm thick at
free end with an average thickness of 6.25cm including all operational, incidental and labour charges such as
weigh batching, machine mixing, lifting of concrete manually, laying concrete, curing, overheads & contractors profit
complete etc., but excluding cost of steel and its fabrication charges for finished item of work (APSS No. 402, 403 &
903)

(BLD-CSTN-3-16)
A.MATERIALS :
Cement 380.00 Kgs 5600.00 1000 Kgs 2128.00
20mm HBG graded metal 0.80 Cum 1433.38 1 Cum 1146.70
Sand 0.40 Cum 1896.68 1 Cum 758.67

Page 18 of 204
CIVIL DATA : Page-19

Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
B.LABOUR :
1st class Mason 0.067 Nos 500.00 1 Each 33.50
2nd class Mason 0.133 Nos 470.00 1 Each 62.51
Mazdoor (both men&women) 3.077 Nos 445.00 1 Each 1369.27
Add for MA @ 40% 0.40 1465.28 586.11

C.MACHINERY :
Batching plant 0.50 cum 0.308 hours 241.40 1 hour 74.35
Crew charges 0.308 hours 389.30 1 hour 119.90
Add MA on crew charges 0.40 119.90 47.96
Water(including for curing) 1.20 kl 98.00 1 kl 117.60
Rate per 1 cum 6444.58

Cost of RCC M 25 design mix 0.0375 cum 6444.58 1 cum 241.67

Rate for other Floors FF SF TF 4F 5F 6F


Rate as above 241.67 241.67 241.67 241.67 241.67 241.67
Hire charges of centering and scaffolding 93.60 93.60 93.60 93.60 93.60 93.60
Labour , lift charges for scaffolding 121.20 133.20 145.80 157.80 169.20 181.80
Add for MA @ 40% 48.48 53.28 58.32 63.12 67.68 72.72
Lift charges of materials(Manual) 0.00 5.49 10.99 16.48 21.98 27.47
Add for MA @ 40% 0.00 2.20 4.40 6.59 8.79 10.99
Rate per 1 RM 504.95 529.44 554.78 579.27 602.92 628.26
Overheads&Contractors Profit @ 13.615% 0 0 0 0 0 0
Rate per 1 RM 504.95 529.44 554.78 579.27 602.92 628.26
Say 505 529 555 579 603 628

Rate for other Floors 7F 8F


Rate as above 241.67 241.67
Hire charges of centering and scaffolding 93.60 93.60
Labour , lift charges for scaffolding 193.80 205.80
Add for MA @ 40% 77.52 82.32
Lift charges of materials(Manual) 32.97 38.46
Add for MA @ 40% 13.19 15.39
Rate per 1 RM 652.75 677.24
Overheads&Contractors Profit @ 13.615%
0 0
Rate per 1 RM 652.75 677.24
Say 653 677

26 Masonry work in CM(1:6) prop (Cement : Screened sand) in superstructure with fly ash cement / lime solid
blocks of size 290mm x 225mm x 140mm from approved source having minimum crushing strength of 50 Kg/Sqcm.
including cost and conveyance of all materials like cement, sand, bricks, water etc., to site, including sales & other
taxes on all materials and such as labour charges, like mixing cement mortar, scaffolding charges, constructing
masonry, lift charges, curing, overheads and contrctor profit etc., complete for finished item of work. (APSS No. 501 &
504).

(BLD-CSTN-5-17)
Unit = 1 Cum
A.MATERIALS
No of blocks required for
1 Cum of Masonry 110 Nos 26966.43 1000 Nos 2966.31
Cement 24.00 Kgs 5600.00 1000 Kgs 134.40
Fine aggregate ( Sand ) 0.10 cu.m. 2086.68 1 cu.m. 208.67
B .LABOUR
Mason 1st class 0.42 Nos. 500.00 1 Each 210.00
Mason 2nd class 0.92 Nos. 470.00 1 Each 432.40
Man Mazdoor 0.70 Nos. 445.00 1 Each 311.50
Woman Mazdoor 2.10 Nos. 445.00 1 Each 934.50
Add for MA @ 40% 0.40 1888.40 755.36
water charges @ 1% 0.01 5953.14 59.53
Rate per 1 cum 6012.67

a) Rate for Foundation , Basement , Compound wall


Rate as above 1.00 cum 6012.67 1 cum 6012.67
Overheads&Contractors Profit @ 13.615% 0.00000 6012.67 0.00
Rate per 1 cum 6012.67
say 6013

Page 19 of 204
CIVIL DATA : Page-20

Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
b) Superstructure :
Rate for other Floors FF SF TF 4F 5F 6F
Rate as worked out above 6012.67 6012.67 6012.67 6012.67 6012.67 6012.67
Hire charges for Access Scaffolding 45.87 45.87 45.87 45.87 45.87 45.87
Labour charges for scaffolding 370.80 530.98 691.07 851.24 1011.38 1171.47
Add for MA @ 40% 148.32 212.39 276.43 340.50 404.55 468.59
Lift charges ( Page 131 of Std. Data ) 0.00 188.84 377.68 566.52 755.36 944.20
Add for MA @ 40% 0.00 75.54 151.07 226.61 302.14 377.68
6577.65 7066.28 7554.78 8043.40 8531.97 9020.47
Overheads&Contractors Profit @ 13.615% 0.00 0.00 0.00 0.00 0.00 0.00
Rate per 1 cum 6577.65 7066.28 7554.78 8043.40 8531.97 9020.47
Say 6578 7066 7555 8043 8532 9020

Rate for other Floors 7F 8F


Rate as worked out above 6012.67 6012.67
Hire charges for Access Scaffolding 45.87 45.87
Labour charges for scaffolding 1331.56 1491.69
Add for MA @ 40% 532.62 596.68
Lift charges ( Page 131 of Std. Data ) 1133.04 1321.88
Add for MA @ 40% 453.22 528.75
9508.97 9997.53
Overheads&Contractors Profit @ 13.615% 0.00 0.00

Rate per 1 cum 9508.97 9997.53


Say 9509 9998

31 Plain Cement Concrete M 20 nominal mix using WEIGH BATCHER / MIXER, 20mm size hard granite machine
crushed graded metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry,
using a minimum quantity of 300 kgs. of cement per 1 cum of concrete including cost and conveyance of all materials
like cement, fine aggregate (Sand), coarse aggregate, water etc., to site including steel centering, shuttering,
machine mixing, lift charges, laying concrete,vibrating, curing, overheads & contrctors profit etc., complete for
finished item of work for coping on top of compound wall (APSS No. 402 & 403).

(BLD-CSTN-3-11)
Unit : 1 cum
A.MATERIALS :
Cement 330.00 Kgs 5600.00 1000 Kgs 1848.00
20mm HBG graded metal 0.90 Cum 1433.38 1 Cum 1290.04
Fine aggregate ( Sand ) 0.45 Cum 1896.68 1 Cum 853.51
Water (including curing) 1.20 kl 98.00 1 kl 117.60
B.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8
cum)capacity 1.00 hour 152.50 1 hour 152.50
Crew charges 1.00 hour 260.00 1 hour 260.00
Add MA on crew charges 0.40 260.00 104.00
C.LABOUR :
1st class mason 0.10 Nos. 500.00 1 Each 50.00
Mazdoor (unskilled) 1.39 Nos. 445.00 1 Each 618.55
Add for MA @ 40% 0.40 668.55 267.42
5561.62
Overheads&Contractors Profit @ 13.615% 0.00000 5561.62
0.00
Rate per 1 cum 5561.62
Say 5562

36 Providing Thermo Mechanically Treated (TMT) (Fe -500/500D/550D from Primary producer TATA, SAIL, VSP,
JSW &Shyam Steel etc as per IS 1786-2008) of different diameters for RCC works , including labour charges for
straightening, cutting, bending to required sizes and shapes, placing in position with cover blocks of approved
materials and size and tying and lap-splicing with binding wire of 18 SWG, forming grills for reinforcement work as per
approved designs and drawings, including cost and conveyance of steel bars, including all wastages such as
overlaps, couplings, chairs, spacer bars including cost and conveyance of binding wire, cover blocks and all
incidental, operational, labour charges such as cutting, bending, placing in position, tying including sales and other
taxes on all materials etc. ,and overheads & contractors profit complete for finished item of work.( APSS No.126)

(BLD-CSTN-4.2)& Amendment in SoR 2011-12 page No. 392


Unit - 1 MT
Page 20 of 204
CIVIL DATA : Page-21

Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
a) Material
TMT bars including 5% for overlaps and
wastage 1.05 MT 43000.00 1 MT 45150.00
Binding wire 6.00 Kgs 55.00 1 Kgs 330.00
b) Labour for cutting , bending , shifting to
site , tying and placing in position
1st class Blacksmith / Barbender 3.00 Nos. 590.00 1 Each 1770.00
2nd class Blacksmith / Barbender 7.00 Nos. 495.00 1 Each 3465.00
Mazdoor(Unskilled) 10.00 Nos. 445.00 1 Each 4450.00
Add for MA @ 40% 0.40 9685.00 3874.00
59039.00

Rate for other Floors FF SF TF 4F 5F 6F


Rate as worked out above 59039.00 59039.00 59039.00 59039.00 59039.00 59039.00
Lift charges ( Page 131 of Std. Data ) 0.00 968.50 1937.00 2905.50 3874.00 4842.50
Add for MA @ 40% 0.00 387.40 774.80 1162.20 1549.60 1937.00
Rate per 1 MT 59039.00 60394.90 61750.80 63106.70 64462.60 65818.50
Overheads&Contractors Profit @ 13.615% 0.00 0.00 0.00 0.00 0.00 0.00
Rate per 1 MT 59039.00 60394.90 61750.80 63106.70 64462.60 65818.50
Say 59039 60395 61751 63107 64463 65819

Rate for other Floors 7F 8F


Rate as worked out above 59039.00 59039.00
Lift charges ( Page 131 of Std. Data ) 5811.00 6779.50
Add for MA @ 40% 2324.40 2711.80
Rate per 1 MT 67174.40 68530.30
Overheads&Contractors Profit @ 13.615%
0.00 0.00
Rate per 1 MT 67174.40 68530.30
Say 67174 68530

39 Plastering 12mm thick in two coats using screened sand with base coat of 8mm thick in CM (1:6) and top coat of
4mm thick in CM (1:4) with dubara sponge finishing including cost and conveyance of all materials like cement, sand,
water etc., to site, including sales & other taxes on all materials, and all operational, incidental charges on materials
and including cost of all labour charges for mixing mortar, finishing, scaffolding, lift charges, curing, including cutting
grooves as directed by Engineer-in-charge etc., and overheads & contractors profit complete for finished item of
work. (SS 901,903 & 904).

( BLD-CSTN-8-10)
Unit : 10 sqm
A.MATERIALS :
Base coat in CM(1:6) , 8mm thick
Cement 26.40 Kgs 5600.00 1000 Kgs 147.84
Fine aggregate (Sand) 0.11 Cum 2086.68 1 Cum 229.53
Top coat in CM(1:4) , 4mm thick
Cement 14.40 Kgs 5600.00 1000 Kgs 80.64
Fine aggregate (Sand) 0.04 Cum 2086.68 1 Cum 83.47
B.LABOUR :
1st Class Mason 0.63 Nos. 500.00 1 Each 315.00
2nd Class Mason 1.47 Nos. 470.00 1 Each 690.90
Mazdoor (Unskilled) 3.90 Nos. 445.00 1 Each 1735.50
Add for MA @ 40% 0.40 2741.40 1096.56
water charges @ 1% 0.01 4379.44 43.79
Rate per 10 Sqm 4423.24
Rate per 1 Sqm 442.32

Walls in superstructure :
Rate for other Floors FF SF TF 4F 5F 6F
Rate as worked out above 442.32 442.32 442.32 442.32 442.32 442.32
Hire charges for Access Scaffolding 1.03 1.03 1.03 1.03 1.03 1.03
Labour charges for scaffolding 8.35 11.95 15.54 19.15 22.75 26.37
Add for MA @ 40% 3.34 4.78 6.22 7.66 9.10 10.55
Lift charges ( Page 131 of Std. Data ) 0.00 27.41 54.83 82.24 109.66 137.07
Add for MA @ 40% 0.00 10.96 21.93 32.90 43.86 54.83
Rate per 1 Sqm 455.04 498.45 541.87 585.30 628.72 672.17
Overheads&Contractors Profit @ 13.615% 0.00 0.00 0.00 0.00 0.00 0.00
455.04 498.45 541.87 585.30 628.72 672.17
Say 455 498 542 585 629 672

Page 21 of 204
CIVIL DATA : Page-22

Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
Rate for other Floors 7F 8F
Rate as worked out above 442.32 442.32
Hire charges for Access Scaffolding 1.03 1.03
Labour charges for scaffolding 29.97 33.56
Add for MA @ 40% 11.99 13.42
Lift charges ( Page 131 of Std. Data ) 164.48 191.90
Add for MA @ 40% 65.79 76.76
Rate per 1 Sqm 715.58 758.99
Overheads&Contractors Profit @ 13.615% 0.00 0.00

715.58 758.99
Say 716 759

46 Flooring with polished shahabad / Tandur stone slabs of 15mm to 18mm thick set over a base coat of CM
(1:8) , 12mm thick using screened sand over already laid CC bed / RCC roof slab including neat cement slurry of
honey like consistency spread @ 3.3 Kgs per Sqm and jointed with neat cement to full depth including cost and
conveyance of all materials like cement, sand, water, flooring stones etc. complete including sales & other taxes on
all materials including all labour charges like dressing of flooring stones to the required size, mixing of cement mortar,
laying, lift charges , cost of base coat, water charges etc., and overheads & contractors profit complete for finished
item of work. (APSS No.703 & 701)

(BLD-CSTN-9-1)
Unit = 10 sqm.
A. MATERIALS:
Polished shahabad stone 15 to 18mm 11.00 Sqm 1891.99 10 Sqm 2081.19
thick
Cement for CM (1:8) proportion for base
coat 21.60 Kgs 5600.00 1000 Kgs 120.96
Cement for slurry 33.00 Kgs 5600.00 1000 Kgs 184.80
Cement for pointing 20.00 Kgs 5600.00 1000 Kgs 112.00
Sand for CM(1:8) 0.12 Cum 2086.68 1 Cum 250.40
B .LABOUR
Mason 1st class 3.10 Nos 500.00 1 Each 1550.00
Mason 2nd class 1.10 Nos 470.00 1 Each 517.00
Mazdoor(un skilled) 0.86 Nos 445.00 1 Each 382.70
Add for MA @ 40% 0.40 2449.70 979.88
Add water charges 1% 0.01 6178.93 61.79
Rate for 10 sqm 6240.72

Rate for other floors FF SF TF 4F 5F 6F


Rate as worked out above 6240.72 6240.72 6240.72 6240.72 6240.72 6240.72
Lift charges ( Page 131 of Std. Data ) 0.00 244.97 489.94 734.91 979.88 1224.85
Add for MA @ 40% 0.00 97.99 195.98 293.96 391.95 489.94
6240.72 6583.68 6926.64 7269.59 7612.55 7955.51
Overheads&Contractors Profit @ 13.615% 0.00 0.00 0.00 0.00 0.00 0.00
Rate per 10 Sqm 6240.72 6583.68 6926.64 7269.59 7612.55 7955.51
Rate per 1 Sqm 624.07 658.37 692.66 726.96 761.26 795.55
Say 624 658 693 727 761 796

Rate for other floors 7F 8F


Rate as worked out above 6240.72 6240.72
Lift charges ( Page 131 of Std. Data ) 1469.82 1714.79
Add for MA @ 40% 587.93 685.92
8298.47 8641.43
Overheads&Contractors Profit @ 13.615% 0.00 0.00

Rate per 10 Sqm 8298.47 8641.43


Rate per 1 Sqm 829.85 864.14
Say 830 864

81 Supply & application of one coat water based cement primer of interior grade I and two coats of acrylic
emulsion paint having VOC (Volatile Organic Compound) content less than 50 grams/litre for internal walls
including cost and conveyance of all materials to site, sales & other taxes, incidental, operational and all labour
charges etc., and overheads & contractors profit complete for finished item of work in all floors.

(BLD-CSTN-12-2& Amendment in SoR 2011-12)


Unit 10 Sqm.
A. Materials:-
Cost of cement primer interior grade I 1.00 Kg 150.00 1 Kg 150.00
Page 22 of 204
CIVIL DATA : Page-23

Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
Painter 1st class 0.21 Nos. 570.00 1 Each 119.70
Painter 2nd class 0.49 Nos. 470.00 1 Each 230.30
Acrylic emulsion paint 0.80 Ltrs 195.00 1 Ltrs 156.00
Painter 1st class 0.36 Nos. 570.00 1 Each 205.20
Painter 2nd class 0.84 Nos. 470.00 1 Each 394.80
Add for MA @ 40% 0.40 950.00 380.00
Sundries including brushes , ladders etc.,
@ 1% 0.01 1636.00
1636.00
Overheads&Contractors Profit @ 13.615% 0.00000 1636.00 0.00
Rate per 10 sqm 1636.00
Rate per 1 sqm 163.60
Say 164

82 Supply & application of one coat water based cement primer of exterior grade II and two coats of acrylic
emulsion paint exterior grade with silicon additives having VOC (Volatile Organic Compound) content less than 50
grams/ liter for exterior walls including cost and conveyance of all materials to site, sales & other taxes, incidental,
operational and all labour charges etc., and overheads & contractors profit complete for finished item of work in all
floors.

(BLD-CSTN-12-2& Amendment in SoR 2011-12)


Unit 10 Sqm.
A. Materials:-
Cost of cement primer exterior grade II 1.00 Kg 191.00 1 Kg 191.00
Painter 1st class 0.21 Nos. 570.00 1 Each 119.70
Painter 2nd class 0.49 Nos. 470.00 1 Each 230.30
Acrylic emulsion paint 0.80 Ltrs 204.00 1 Ltrs 163.20
Painter 1st class 0.21 Nos. 570.00 1 Each 119.70
Painter 2nd class 0.49 Nos. 470.00 1 Each 230.30
Mazdoor 1.50 Nos. 445.00 1 Each 667.50
Add for MA @ 40% 0.40 1367.50 547.00
Sundries including brushes , ladders etc.,
@ 1% 0.01 2268.70
Hire charges for Access Scaffolding 10 sqm 1.03 1 sqm 10.30
Labour charges for scaffolding 10 sqm 8.35 1 sqm 83.50
Add for MA @ 40% 0.40 83.50 33.40
2395.90
Overheads&Contractors Profit @ 13.615% 0.00000 2395.90 0.00
Rate per 10 sqm 2395.90
Rate per 1 sqm 239.59
Say 240

83 Painting to new wood work and flush shutters with lappam finish, over a primary coat and painting two coats
of synthetic enamel paint Grade-II VOC (Volatile Organic Compound) content less than 50 grams/litre of approved
shade including cost and conveyance of all materials to site cost of primer coat and all labour charges etc. complete
including applying sand paper on lappam coats for neat finish including sales & other taxes on cost of all materials
etc., and overheads & contractors profit complete in all floors (APSS No.1200, 1207 & 1211).

(BLD-CSTN-12-6 & 12-12-195)


Cost of Putty for wood work 1 Kg 144.00 1 Kg 144.00
Primer Coat
Cost of Wood Primer 0.70 Ltr 144.00 1 Ltr 100.80
1st Class Painter 0.21 Nos. 570.00 1 Each 119.70
2nd Class Painter 0.49 Nos. 470.00 1 Each 230.30
2 coats of Enamel painting
Cost of Synthetic Enamel Paint 1.20 Ltr 191.00 1 Ltr 229.20
1st Class Painter 0.36 Nos. 570.00 1 Each 205.20
2nd Class Painter 0.84 Nos. 470.00 1 Each 394.80
Add for MA @ 40% 0.40 950.00 380.00
Sundries including brushes , ladders etc.,
@ 1% 0.01 1804.00
1804.00
Overheads&Contractors Profit @ 13.615% 0.00000 1804.00 0.00
Rate per 10 sqm 1804.00
Rate per 1 sqm 180.40
Say 180
1.70mts 1.80mts

Page 23 of 204
CIVIL DATA : Page-24

Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
87 Painting two coats with synthetic enamel paint Grade-II VOC (Volatile Organic Compound) content less than
50 grams/litre over primer coat of red oxide to new iron work including cost and conveyance of all materials to
site, sales & other taxes, incidental, operational and all labour charges etc., and overheads & contractors profit
complete for finished item of work in all floors. (SS No. 1201, 1212 & 1207).
(BLD-CSTN-12-7 & 12-12-197)
Unit : 10 sqm
A.MATERIALS :
Red oxide primer 0.70 Ltr 129.00 1 Ltr 90.30
Cost of Synthetic Enamel Paint 1.10 Ltr 191.00 1 Ltr 210.10
B.LABOUR :
for primer coat
1st Class Painter 0.21 Nos. 570.00 1 Each 119.70
2nd Class Painter 0.49 Nos. 470.00 1 Each 230.30
for enamel painting
1st Class Painter 0.33 Nos. 570.00 1 Each 188.10
2nd Class Painter 0.77 Nos. 470.00 1 Each 361.90
Add for MA @ 40% 0.40 900.00 360.00
Sundries including brushes , ladders etc.,
@ 1% 0.01 1560.40
1560.40
Overheads&Contractors Profit @ 13.615% 0.00000 1560.40 0.00
Rate per 10 sqm 1560.40
Rate per 1 sqm 156.04
Say 156

1.70mts 1.80mts Alround M.S flat of


107 size dia
Roofing with corrugated G.I sheets 0.80mm thick fixed with G.I ‘J’ bolts & nuts 8 mm 25 x with
6mmbitumen & G.I limpet
washers filled with white lead & including a coat of approved steel primer and two coats of approved paint on over
lapping of sheets complete (up to a pitch of 600) etc., complete, excluding the cost of purlins, rafters, trusses
including cost and conveyance of all materials , labour charges , overheads and contractors profit etc., complete for
finished item of work in all floors.

Unit : 10 sqm
A. MATERIALS:
G.I corrugated 0.80 mm thick sheets 103.09 Kgs 60.00 1 Kg 6185.4
G.I scam bolts & nuts 2 x 27 (laps) x 17 =
884 47.91 Nos. 6.00 1 No. 287.46
G.I ‘J’ bolts 8 mm dia 2 x 5 x 27 sheets x 3
nos = 810 nos. with washers or srews, if
wooden battens used. 43.9 Nos. 10.00 1 No. 439
Limpet washers (for scam & ‘J’ bolts) 884 +
810 = 1694 91.82 Nos. 2.00 1 No. 183.64
Bitumen washers 91.82 Nos. 2.00 1 No. 183.64
Zinc cromate yellow paint 0.14 Ltrs 185.00 1 Ltr 25.9
Ready mixed paint 0.2 Ltrs 251.00 1 Ltr 50.2
B. LABOUR
For roofing
Carpenter II class 0.84 Nos. 470.00 1 No. 394.8
Man mazdoor (beldar) 0.91 Nos. 445.00 1 No. 404.95
For primer painting one coat
Painter 1st class 0.018 Nos. 570.00 1 No. 10.26
Painter 1st class 0.042 Nos. 470.00 1 No. 19.74
Mazdoor (coolie) 0.06 Nos. 445.00 1 No. 26.7
For two coats of painting to over laps
Painter 1st class 0.042 Nos. 570.00 1 No. 23.94
Painter 1st class 0.098 Nos. 470.00 1 No. 46.06
Mazdor (coolie) 0.14 Nos. 445.00 1 No. 62.3
Add for MA @ 40% 0.4 988.75 395.5
Rate per 10 sqm 8739.49
Rate per 1 sqm 873.949
Overheads&Contractors Profit @ 13.615% 0 873.949 0
Rate per 1 sqm 873.949
say 874

Page 24 of 204
CIVIL DATA : Page-25

Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
110 Supplying and fabricating, erecting and fixing in position tabular trusses of approved design with M.S tube
conforming to I.S-1161 specifications including roof frame work consisting of rafters,ties struts and purlins including
cost of foundations bolts, cleats, bearings plates,etc.,complete as per the sketch enclosed and including cost of
primary coat with red oxide paint including cost and conveyance of all materials, labour charges for erecting & fixing
all structural steel works erecting in position and fixing by using chain pulley blocks, Derek pole arrangements and
cranes etc., complete in position, labour charges for fabrication, all incidental charges, overheads and contractor
profit etc., complete for finished item of work as directed by the Engineer-in-Charge

Cost of MS tube 1.00 MT 61000.00 1 MT 61000.00


Labour charges for fabrication TBSC-T.I-18 1.00 MT 26000.00 1 MT 26000.00
Labour charges for fixing TBSC-T.I-19 1.00 MT 23000.00 1 MT 23000.00
Add for MA @ 40% 40% 19600.00 7840.00
Rate per 1 MT 117840.00
Overheads&Contractors Profit @ 13.615% 0.00000 117840.00 0.00
117840.00
Rate per 1 MT Say 117840
Rate per KG 117.84
Or Say KG 118.00

Page 25 of 204
JOINERY DATA
Joinery data 26
COMMON SoR 2019-2020

a) Labour charges for wrought and put up (BLD-CSTN-13-1)


1st class carpenter 5.31 Nos. 590.00 1 Each 3132.90
2nd class carpenter 12.39 Nos. 470.00 1 Each 5823.30
Man Mazdoor 8.80 Nos. 445.00 1 Each 3916.00
Labour charges per 1 cum 12872.20

b) Labour charges for aluminium doors ( S.No.11 of Page No. 396 of SoR 2011-12 )
1st class carpenter 0.099 Nos. 590.00 Each 58.41
2nd class carpenter 0.198 Nos. 470.00 Each 93.06
Power Saw Cutter -Hand Operated -Operator 0.099 Nos. 590.00 Each 58.41
Power Drill -Hand Operated -Operator 0.099 Nos. 590.00 Each 58.41
Mazdoor(Unskilled) 0.297 Nos. 445.00 Each 132.17
Non-technical work inspector 0.099 Nos. 590.00 Each 58.41
Add for MA @ 40% 0.40 458.87 183.55
Machinery
Power Saw Cutter -Hand Operated -Hire charges 0.793 Hrs 130.00 1 Hour 103.09
Power Drill -Hand Operated -Hire charges 0.793 Hrs 121.00 1 Hour 95.95
841.45
Power charges for Motors 1% 0.01 841.45 8.41
Labour charges per 1 sqm 849.87

c) Labour charges for aluminium sliding windows ( S.No.10 of Page No. 395 of SoR 2011-12 )
1st class carpenter 0.096 Nos. 590.00 Each 56.64
2nd class carpenter 0.289 Nos. 470.00 Each 135.83
Power Saw Cutter -Hand Operated -Operator 0.096 Nos. 590.00 Each 56.64
Power Drill -Hand Operated -Operator 0.096 Nos. 590.00 Each 56.64
Mazdoor(Unskilled) 0.289 Nos. 445.00 Each 128.61
Non-technical work inspector 0.096 Nos. 590.00 Each 56.64
Add for MA @ 40% 0.40 491.00 196.40
C.Machinery

Power Saw Cutter -Hand Operated -Hire charges 0.771 Hrs 130.00 1 Hour 100.23
Power Drill -Hand Operated -Hire charges 0.771 Hrs 121.00 1 Hour 93.29
880.91
Power charges for Motors 1% 0.01 880.91 8.81
Labour charges per 1 sqm 889.72

d) Labour charges for aluminium partitions partly glazed ( S.No.8 of Page No. 394 of SoR 2011-12 )
1st class carpenter 0.434 Nos. 590.00 Each 256.06
2nd class carpenter 0.434 Nos. 470.00 Each 203.98
Power Saw Cutter -Hand Operated -Operator 0.043 Nos. 590.00 Each 25.37
Power Drill -Hand Operated -Operator 0.058 Nos. 590.00 Each 34.22
Mazdoor(Unskilled) 0.145 Nos. 445.00 Each 64.53
Non-technical work inspector 0.072 Nos. 590.00 Each 42.48
Add for MA @ 40% 0.40 626.64 250.65
C.Machinery
Power Saw Cutter -Hand Operated -Hire charges 0.347 Hrs 130.00 1 Hour 45.11
Power Drill -Hand Operated -Hire charges 0.463 Hrs 121.00 1 Hour 56.02
978.42
Power charges for Motors 1% 0.01 978.42 9.78
Labour charges per 1 sqm 988.21

e) Labour charges for aluminium casement windows ( S.No.9 of Page No. 394 of SoR 2011-12 )
1st class carpenter 0.100 Nos. 590.00 Each 59.00
2nd class carpenter 0.300 Nos. 470.00 Each 141.00
Power Saw Cutter -Hand Operated -Operator 0.100 Nos. 590.00 Each 59.00
Power Drill -Hand Operated -Operator 0.100 Nos. 590.00 Each 59.00
Mazdoor(Unskilled) 0.300 Nos. 445.00 Each 133.50
Non-technical work inspector 0.100 Nos. 590.00 Each 59.00
Joinery data 27
Add for MA @ 40% 0.40 510.50 204.20
C.Machinery
Power Saw Cutter -Hand Operated -Hire charges 0.800 Hrs 130.00 1 Hour 104.00
Power Drill -Hand Operated -Hire charges 0.800 Hrs 121.00 1 Hour 96.80
915.50
Power charges for Motors 1% 0.01 915.50 9.16
Labour charges per 1 sqm 924.66

14 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and ISI
marked flush door shutters of 30 mm thick double shutters with bond wood solid block board type Core having
cross bands and face veneers, hot pressed bonded with water proof phenol formaldehyde synthetic resin factory
made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal lipping on all sides including cost
and conveyance to site of teak wood frame, flush shutter including

supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium
fixtures of 6 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos. tower bolts (IS:204)
of 200 mm x 10 mm dia at top, 2 Nos. 150 mm long handles (IS:208), 2 Nos. door stoppers and 2 Nos. rubber
bushes including fixing the fixtures to door with required number of screws, bolt and nuts including labour charges
for fixing the frame in position, fixing the shutter to the frame etc., including overheads & contractors profit complete
for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in flooring for a
depth of not less than 10 mm) (1200mm x 2100mm).

(BLD-CSTN-13-16)
Size : 1.20m x 2.10m 2.52 Sqm
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743 cum
Outer frame - Horizontal 1 x 1.20
= 1.20 x 0.10 x 0.065 0.00780 cum
0.03523 cum

30 mm thick flush shutter 2 x 0.55 x 2.05 2.255 sqm

Cost of medium TW frame 2 m to 3m length 0.0274 cum 80689.00 1 cum 2213.30


Cost of medium TW frame below 2 m length 0.0078 cum 72620.00 1 cum 566.44
Cost of 30 mm thick flush shutter 2.255 sqm 1192.00 1 sqm 2687.96
Cost of MS Z hold fasts 6 Nos. 32.00 Each 192.00
Cost of Alumimium tower bolt 200mm long 2 Nos. 79.00 Each 158.00
Cost of Alumimium butt hinges 150mm long 6 Nos. 93.00 Each 558.00
Cost of Alumimium aldrop 300mm long 1 No. 210.00 Each 210.00
Cost of Alumimium handle 150mm long 2 Nos. 87.00 Each 174.00
Cost of Alumimium door stopper 2 Nos. 58.00 Each 116.00
Cost of rubber bush 2 Nos. 10.00 Each 20.00
Labour charges for frame work 0.035 cum 12872.20 1 cum 453.49
Add for MA @ 40% 0.40 453.49 181.40
Labour charges for fixing flush door shutter to the
frame , fixing the fixtures to the shutter 2.255 sqm 447.00 1 sqm 1007.99
Add for MA @ 40% 0.40 1007.99 403.19
Add for nails & screws etc.
Rate for 2.52 sqm 8941.76
Rate for 1 sqm 3548.32
Overheads&Contractors Profit @ 13.615% 0.00000 3548.32 0.00
Rate for 1 sqm 3548.32
Say 3548

32 Supplying and fixing of 2 shutter fully glazed windows as per drawing using Sal wood frame and one vertical
mullion of size 100mm x 65mm and shutters with Sal wood styles & rails of size 75mmx35mm and 4mm thick pin
headed glass fixed with teak wood beading of 12mm X 12mm including cost of 4 Nos MS Z hold fasts of size 300 x
40 x 5 mm including supply and fixing of ISI marked aluminium fixtures, butt hinges of size 75mm long (2 Nos per
shutter), 75mm handles (1No per shutter), 75mm x 10mm dia tower bolt (1No per shutter), and aluminium window
stopper with hook and eye 100mm long (1No per shutter) with 12mm MS square bars horizontally at 100mm centre
to centre fixed in frame including labour charges for fixing the fixtures with required No. of screws, fixing window in
position fixing shutters to frame including cost & conveyance of all materials to site, labour charges etc., complete for
finished item of work (APSS No 1001 & 1002).(1200mm x 1300mm)
Size : 1200mm x 1300mm
Joinery data1.56 Sqm 28
Frame (2x(1.20+1.30)x0.10x0.065 0.0325 Cum
Mullions (2x 1.30 x 0.10 x 0.065) 0.0169 Cum
Styles: (2x2x(0.49+1.03) x
0.075x0.035) 0.01596
Rails: (2x 2 x 0.49 x 0.075 x 0.035) 0.005145
0.07046 Cum 48543.00 1 Cum 3420.34
4mm thick pin headed glass (2x0.51x1.24). 1.26 Sqm 309.00 1 Sqm 389.34
Teak wood beading(2x2x(0.51+1.24)) 7.00 RM 20.00 1 RM 140.00
12m MS square bars (11 x 1.22 x 1.13 Kgs/m) 15.16 Kg 43052.63 1 MT 652.68
MS 'Z' hold fasts 4 Nos. 18.00 1 Each 72.00
MS powder coated butt hinges 75mm long. 4 Nos. 11.00 1 Each 44.00
MS powder coated tower bolts 100mm long 2 Nos. 23.00 1 Each 46.00
MS powder coated handles 125mm 2 Nos. 31.00 1 Each 62.00
MS powder coated hook and eye 2 Nos. 20.00 1 Each 40.00
Labour charges for frame and shutters 0.071 Cum 12872.20 1 Cum 913.93
Labour charges for fixing glass 1.26 Sqm 199.00 1 Sqm 250.74
Labour charges for shutters and fixing fixtures 2.16 1164.67 2515.68
Add for screws, nails etc., LS 4.79
8551.49
0 0.00 8551.49 0.00
8551.49
Rate for 1 sqm 5481.73
Say 5482
WS & SA DATA 2014-15 Page-29
COMMON SoR 2019-2020
DATA FOR WATER SUPPLY AND SANITARY ITEMS
Sl.No Description Qty Unit Rate Per Unit Amount
1 Supplying and laying, filling, jointing and testing SWG SP-1 pipe conforming to ISI 651 & 4127 with air
tight Cement joints in CM (1.5:1) prop. including excavation of trenches and socket pits in any soil (except
rock requiring blasting) and refilling with watering and tamping to the required slope including cost and
conveyance of all materials to site and all labour charges , overheads & contractor profit etc., complete for
finished item of work (APSS NO 1301 & 1318).

a) 101.60mm dia upto 914.40mm (3') depth


Rate as per SSR 1.00 RM 425.00 1 RM 425.00
Overheads&Contractors Profit @ 13.615% 0.00000 425.00 0.00
Rate per 1 RM 425.00
say 425

b) 152.40mm dia upto 1524.0mm (5') depth


Rate as per SSR 1.00 RM 712.00 1 RM 712.00
Overheads&Contractors Profit @ 13.615% 0.00000 712.00 0.00
712.00
Rate per 1 RM say 712

c) 203.20mm dia upto 1524mm (5') depth


Cost of SWG pipe 1.00 RM 504.00 1 RM 504.00
labour charges for laying , jointing , testing 1.00 RM 329.00 1 RM 329.00
Add for MA @ 40% 0.40 329.00 131.60
964.60
Overheads&Contractors Profit @ 13.615% 0.00000 964.60 0.00
Rate per 1 RM 964.60
say 965

d) 254mm dia upto 1524mm (5') depth


Cost of SWG pipe 1.00 RM 922.00 1 RM 922.00
labour charges for laying, jointing, testing 1.00 RM 329.00 1 RM 329.00
Add for MA @ 40% 0.40 329.00 131.60
1382.60
Overheads&Contractors Profit @ 13.615% 0.00000 1382.60 0.00
Rate per 1 RM 1382.60
say 1383

e) 300mm dia upto 1524mm (5') depth


Cost of SWG pipe 1.00 RM 1330.00 1 RM 1330.00
labour charges for laying , jointing , testing 1.00 RM 329.00 1 RM 329.00
Add for MA @ 40% 0.40 329.00 131.60
1790.60
Overheads&Contractors Profit @ 13.615% 0.00000 1790.60 0.00
Rate per 1 RM 1790.60
say 1791

2 Constructing 904.0 mm (3’0”) dia brick masonry inspection chamber as per IS - 4111: Part-1:1986
with cement mortar (1:6) prop using 2nd Class Clay Bricks of 225 mm thick from approved source having a
minimum crushing strength of 5 N/sq.mm including plastering with cement mortar 1:3 prop; ½” thick both
inside and outside fitted with 20” dia RCC manhole covers and frames including excavating pits up to a
depth of 904 mm (3'-0") in all sorts of soils (exculding rock) and laying cement conrete (1:4:8) 150 mm
thick using 40 mm HBG Metal and P.C.C. 1:2:4 benching and channel 100 mm thick as per Standard
specification and including cost and conveyance of all materials like cement, sand, bricks, water etc., to
site, cost of seigniorage charges on all materials and all incidental and operational, labour charges like
mixing cement mortar, constructing masonry, lift charges, curing , overheads & contractors profit etc.,
complete for finished item of work as per Standard specification.

Rate as per SSR 1 No. 7357.00 Each 7357.00


Overheads&Contractors Profit @ 13.615% 0.00000 7357.00 0.00
7357.00
WS & SA DATA 2014-15 Page-30
Rate per Each say 7357

3 Constructing 904.0 mm (3’0”) dia brick masonry inspection chamber as per IS - 4111: Part-1:1986
with cement mortar (1:6) prop using 2nd Class Clay Bricks of 225 mm thick from approved source having a
minimum crushing strength of 5 N/sq.mm including plastering with cement mortar 1:3 prop; ½” thick both
inside and outside fitted with 20” dia RCC manhole covers and frames including excavating pits up to a
depth of 1524 mm (5'-0") in all sorts of soils (exculding rock) and laying cement conrete (1:4:8) 150 mm
thick using 40 mm HBG Metal and P.C.C. 1:2:4 benching and channel 100 mm thick as per Standard
specification and including cost and conveyance of all materials like cement, sand, bricks, water etc., to
site, cost of seigniorage charges on all materials and all incidental and operational, labour charges like
mixing cement mortar, constructing masonry, lift charges, curing , overheads & contractors profit etc.,
complete for finished item of work as per Standard specification.

Rate as per SSR 1 No. 11707.00 Each 11707.00


Overheads&Contractors Profit @ 13.615% 0.00000 11707.00 0.00
11707.00
Rate per Each say 11707

4 Constructing 457.2 mm x 457.2 mm (1'6"x1'6") brick in CM 1:6 prop. Masonry. Inspection chamber
upto 914.4 mm (3'0") and fitted with light weight 457.2 mm x 457.2 mm (1'6"x1'6") C.I frame and cover of
20 Kg including cost and conveyance of all materials like cement, sand, bricks, water etc., to site, cost of
seigniorage charges on all materials and all incidental and operational, labour charges like mixing cement
mortar, constructing masonry, lift charges, curing , overheads & contractors profit etc., complete for
finished item of work as per Standard specification.

Rate as per SSR 1 No. 3832.00 Each 3832.00


Overheads&Contractors Profit @ 13.615% 0.00000 3832.00 0.00
3832.00
Rate per Each say 3832

5 Supplying and fixing of SWG Gully traps 150mm x 100mm of ISI make confirming to IS 651 & 4127 with
C.I grating & constructing cement brick masonry in CM (1:6) prop., intermediate chamber and fitted with
304.8 mm X 288.6 mm (12"x9") C.I Frame with hinged cover of standard make as approved including cost
and conveyance of all materials to site, labour charges, overheads & contractors profit etc., complete for
finished item of work.

Rate as per SSR 1 No. 622.00 1 Each 622.00


Deduct cost of CI frame and cover 1 No. 125.00 1 No. -125.00
Add for RCC Cover 1 No. 100.00 1 No. 100.00
597.00
Overheads&Contractors Profit @ 13.615% 0.00000 597.00 0.00
597.00
Rate per Each say 597

6 Supplying and fixing of 3" (75mm) Nahany trap with jali - UPVC/SWR pipe fittings as per site
requirements with standard practice for all floors including cost and conveyance of all materials to site,
labour charges , overheads & contractors profit etc., complete for finished item of work.

Rate as per SSR 1 No. 101.00 1 Each 101.00


Overheads&Contractors Profit @ 13.615% 0.00000 101.00 0.00
101.00
Rate per Each say 101

7 Supplying and fixing of 4" (101.6mm) multi floor trap with jali - UPVC/SWR pipe fittings as per site
requirements with standard practice for all floors including cost and conveyance of all materials to site,
labour charges , overheads & contractors profit etc., complete for finished item of work.

Rate as per SSR 1 No. 143.00 1 Each 143.00


Overheads&Contractors Profit @ 13.615% 0.00000 143.00 0.00
143.00
Rate per Each say 143
WS & SA DATA 2014-15 Page-31
8 Supplying and fixing 580mm x 440mm long Orissa pan white glazed Water Closet 1st quality ISI
marked confirming to IS:2556-Part-3-1981 with "P" or "S" trap, ISI marked and providing masonry seat,
CC squatting plate and 10 litres capacity single flush PVC low level cistern with internal components fixed
on 2 Nos. of teak wood blocks of size 76.20mm x 101.60mm using required size of nails, screws as
approved by Engineer-in-charge, 15 mm nominal size CP finish brass angled stop valve screw type with
internal /external threaded conforming to IS 8931, 12.70mm PVC connection with brass union nuts CP
coated , 31.75mm brass plumber union, P trap or S trap of Indian W.C. shall be encased on CC (1:2:4)
150mm alround well above the joint to stop leakage at the joint etc., complete including cost and
conveyance of all materials to site, cost of CC bed, labour charges and seigniorage charges, overheads &
contractors profit etc., complete for finished item of work.

Cost of Orissa pan 1 No. 1313.00 1 Each 1313.00


Add MA on labour charges for fixing Orissa
pan 0.40 429.00 171.60
Cost of Brick masonry seat 1 No. 272.00 1 Each 272.00
Cost of C C squatting plate 1 No. 82.00 1 Each 82.00
Cost of slim line PVC flush tank 10 Ltrs.
capacity single flush 1 No. 1446.00 1 Each 1446.00
15 mm nominal size CP finish brass angled
stop valve 1 No. 216.00 1 Each 216.00
Add MA on labour charges for fixing angle stop
cock 0.40 103.00 41.20
12.70mm PVC connection with brass union
nuts 1 No. 102.00 1 Each 102.00
Add MA on labour charges for fixing PVC
connection with brass union nuts 0.40 0.00 0.00
31.75mm brass plumber union 1 No. 63.00 1 Each 63.00
Add MA on labour charges for fixing 31.75mm
brass plumber union 0.40 0.00 0.00
Cutting holes in brick masonry 1 No. 49.00 1 Each 49.00
Add MA on labour charges for cutting holes in
brick masonry 0.40 49.00 19.60
Teak wood blocks 76.2mm x 101.6mm 2 Nos. 24.00 1 Each 48.00
Add MA on labour charges for fixing Teak
wood blocks 0.40 0.00 0.00
3823.40
Overheads&Contractors Profit @ 13.615% 0.00000 3823.40 0.00
3823.40
Rate per Each 3823

9 Supplying and fixing European Water Closet of 1st quality conforming to IS:2556-Part-2-1973 of white
glazed with 'S' trap,supplying and fixing best Indian make plastic seat and lid for European water closets
with rubber or plastic Buffers as per IS 2548-1996 and 10 litres capacity single flush PVC low level cistern
with internal components and fixed using required size of nails and screws, 15 mm nominal size CP finish
brass angled stop valve screw type with internal /external threaded conforming to IS 8931, 12mm PVC
connections with brass union nuts CP coated including cost and conveyance of all materials to site,
overheads & contractors profit etc., complete for finished item of work for all floors.

Cost of EWC with 'S' trap 1 No 1627.00 1 Each 1627.00


Add MA on labour charges for fixing EWC 0.40 301.00 120.40
Supply and fixing of 10 lts. Capacity lowdown
PVC flushing tank 1 No 1446.00 1 Each 1446.00
Plastic seat and lid for European Water Closet
and rubber buffers 1 No 738.00 1 Each 738.00
Add MA on labour charges for fixing Plastic
seat and lid for EWC and rubber buffers 0.40 87.00 34.80
15 mm nominal size CP finish brass angled
stop valve 1 No. 216.00 1 Each 216.00
Add MA on labour charges for fixing angle stop
cock 0.40 103.00 41.20
12.70mm dia PVC connection with brass union
nuts 1 No 102.00 1 Each 102.00
WS & SA DATA 2014-15 Page-32
Add MA on labour charges for fixing PVC
connection with brass union nuts 0.40 0.00 0.00
Cutting holes in brick masonry 1 No. 49.00 1 Each 49.00
Add MA on labour charges for cutting holes in
brick masonry 0.40 49.00 19.60
Cost of 76.2 x 101.60 mm teakwood blocks
2 Nos 24.00 1 Each 48.00
Add MA on labour charges for fixing Teak
wood blocks 0.40 0.00 0.00
4442.00
Overheads&Contractors Profit @ 13.615% 0.00000 4442.00 0.00
4442.00
Rate per Each 4442

10 Supplying and fixing Indian make Flat Back Wash Hand Basin 1st quality conforming to IS:2556-Part-
4:1972 of size 550mm x 400mm with 32 mm nominal size C.P. Fitting with parallel pipe thread conforming
to IS:2963-1979 and fitted with 15 mm nominal bore Chromium Plated Pillar Tap of 1st quality Indian make
heavy duty complete with standard CI brackets including wooden blocks ,1 No.12.70mm PVC connection
with brass union nuts CP coated , angle stop cock 12.70mm dia. first quality Indian make heavy duty,
30mm dia. PVC flexible waste pipe 914.4mm length of 1st quality including cost and conveyance of all
materials to site, labour charges , overheads & contractors profit for finished item of work

Cost of Wash hand basin 1 No. 1476.00 1 Each 1476.00


Add MA on labour charges for fixing Wash
hand basin 0.40 429.00 171.60
Angle stop cock 12.70mm 1 No. 216.00 1 Each 216.00
Add MA on labour charges for fixing angle stop
cock 0.40 103.00 41.20
12.70mm PVC connection with brass union
nuts 1 No. 102.00 1 Each 102.00
Add MA on labour charges for fixing PVC
connection with brass union nuts 0.40 0.00 0.00
Deduct cost of NP chain and rubber plug 1 No. 38.00 1 Each -38.00
30mm dia. PVC flexible waste pipe 1 No. 26.00 1 Each 26.00
1994.80
Overheads&Contractors Profit @ 13.615% 0.00000 1994.80 0.00
1994.80
Rate per Each say 1995

11 Supplying and fixing CP finish brass soap dish of approved make ISI quality including cost and
conveyance of all materials, labour charges for fixing , overheads & contractors profit for finished item of
work in all floors

Cost of NP soap dish 1 No. 517.00 1 Each 517.00


Add for MA @ 40% 0.40 103.00 41.20
558.20
Overheads&Contractors Profit @ 13.615% 0.00000 558.20 0.00
558.20
Rate per Each say 558

12 Supplying and fixing TV shape mirror with plastic frame of size 609.6mm x 457.2mm , plywood back
with NP screws 1st quality including cost and conveyance of all materials, labour charges , overheads &
contractors profit for finished item of work in all floors.

Rate as per SSR 1 No. 468.00 Each 468.00


Add for MA @ 40% 0.40 0.00 0.00
468.00
Overheads&Contractors Profit @ 13.615% 0.00000 468.00 0.00
468.00
Rate per Each say 468
WS & SA DATA 2014-15 Page-33
13 Supplying and fixing of 25.4mm dia , 609.6mm long aluminium anodized towel rods with brackets
and aluminium screws including cost and conveyance of all materials, labour charges , overheads &
contractors profit for finished item of work.

Rate as per SSR 1 No. 150.00 Each 150.00


Add for MA @ 40% 0.40 0.00 0.00
150.00
Overheads&Contractors Profit @ 13.615% 0.00000 150.00 0.00
150.00
Rate per Each say 150

14 Supplying and fixing 15 mm brass body CP finish bib tap of not less than 300 grams weight screw
type (full turn) with internal / external threaded connection conforming to IS 8931 as approved by the
Engineer-In-Charge including cost and conveyance of all materials, labour charges , overheads &
contractors profit complete for finished item of work in all floors.
Rate as per SSR 1 No. 224.00 Each 224.00
Add for MA @ 40% 0.40 53.00 21.20
245.20
Overheads&Contractors Profit @ 13.615% 0.00000 245.20 0.00
245.20
Rate per Each say 245
15 Supplying and fixing 15 mm brass body CP finish self closing tap push type conforming to IS 1711
as approved by the Engineer-In-Charge including cost and conveyance of all materials, labour charges,
overheads & contractors profit complete for finished item of work in all floors.
Rate as per SSR 1 No. 247.00 Each 247.00
Add for MA @ 40% 0.40 53.00 21.20
268.20
Overheads&Contractors Profit @ 13.615% 0.00000 268.20 0.00
268.20
Rate per Each say 268
16 Supplying and fixing Chromium plated finish brass body quarter turn Bibcock cum Health Faucet
with 1m long tube and wall hook with 7 - 10 years warranty with necessary fittings etc., complete
including cost and conveyance of all materials, labour charges, overheads & contractor profit complete for
finished item of work in all floors.
Rate as per SSR 1 No. 2929.00 Each 2929.00
Add for MA @ 40% 0.40 53.00 21.20
2950.20
Overheads&Contractors Profit @ 13.615% 0.00000 2950.20 0.00
2950.20
Rate per Each say 2950
17 Supplying and fixing of SWR PVC pipes (Prince/Sudhakar/Kisan/Supreme or any ISI brand) 4
Kg/Sq.cm. and fixing all special such as plain bends, off sets, door bends, single junctions, double
junctions as per site requirement, fixing with PVC clamps if necessary with required number of Bombay
nails including cost and conveyance of all materials to site, labour charges, overheads & contractors profit
complete for finished item of work at all floor levels. (APSS No. 1302 1319 & 1326)
a) 75mm dia
Data for 6 RM
Cost of 75mm dia pipe 6.00 RM 252.00 3 RM 504.00
Cost of PVC clamps 3 Nos. 15.00 Each 45.00
Labour charges 6.00 RM 79.00 1 RM 474.00
Add for MA @ 40% 0.40 474.00 189.60
1212.60
Rate per 1 RM 202.10
Overheads&Contractors Profit @ 13.615% 0.00000 202.10 0.00
202.10
say 202
b) 90mm dia
Data for 6 RM
Cost of 90mm dia pipe 6.00 RM 401.00 3 RM 802.00
Cost of PVC clamps 3 Nos. 17.00 Each 51.00
WS & SA DATA 2014-15 Page-34
Labour charges 6 RM 79.00 1 RM 474.00
Add for MA @ 40% 0.40 474.00 189.60
1516.60
Rate per 1 RM 252.77
Overheads&Contractors Profit @ 13.615% 0.00000 252.77 0.00
252.77
say 253
c) 110mm dia
Data for 6 RM
Cost of 110mm dia pipe 6.00 RM 479.00 3 RM 958.00
Cost of PVC clamps 3 Nos. 18.00 Each 54.00
Labour charges 6 RM 79.00 1 RM 474.00
Add for MA @ 40% 0.40 474.00 189.60
1675.60
Rate per 1 RM 279.27
Overheads&Contractors Profit @ 13.615% 0.00000 279.27 0.00
279.27
say 279

d) 160mm dia Double socket


Data for 6 RM
Cost of 160mm dia pipe 6.00 RM 1140.00 3 RM 2280.00
Cost of PVC clamps 3 Nos. 35.00 Each 105.00
Labour charges 6 RM 79.00 1 RM 474.00
Add for MA @ 40% 0.40 474.00 189.60
3048.60
Rate per 1 RM 508.10
Overheads&Contractors Profit @ 13.615% 0.00000 508.10 0.00
508.10
say 508
18 Supply and fixing of Ashirvad/ Ajay/ Astral Flowguard or equivalent CPVC Pipes and Fittings SDR
13.5 to meet the requirement of ASTM-D 2846 and are produced in CTS (Copper Tube Sizes 1/2" to 2")
for hot and cold water (IS 15778:2007) including cost and conveyance of all materials to site, labour
charges for fixing, overheads & contractors profit complete for finished item of work at all floor levels.

a) 15.90mm OD pipe
Rate as per SoR 1 No. 129.00 Each 129.00
Overheads&Contractors Profit @ 13.615% 0.00000 129.00 0.00
Rate per 1 RM 129.00
say 129
b) 22.20mm OD pipe
Rate as per SoR 1 No. 147.00 Each 147.00
Overheads&Contractors Profit @ 13.615% 0.00000 147.00 0.00
Rate per 1 RM 147.00
say 147
c) 28.60mm OD pipe
Rate as per SoR 1 No. 194.00 Each 194.00
Overheads&Contractors Profit @ 13.615% 0.00000 194.00 0.00
Rate per 1 RM 194.00
say 194
d) 34.90mm OD pipe
Rate as per SoR 1 No. 264.00 Each 264.00
Overheads&Contractors Profit @ 13.615% 0.00000 264.00 0.00
Rate per 1 RM 264.00
say 264
e) 41.30mm OD pipe
Rate as per SoR 1 No. 329.00 Each 329.00
Overheads&Contractors Profit @ 13.615% 0.00000 329.00 0.00
WS & SA DATA 2014-15 Page-35
Rate per 1 RM 329.00
say 329
f) 54.00mm OD pipe
Rate as per SoR 1 No. 479.00 Each 479.00
Overheads&Contractors Profit @ 13.615% 0.00000 479.00 0.00
Rate per 1 RM 479.00
say 479
18 Supply and fixing of Ashirvad/ Ajay/ Astral Flowguard or equivalent CPVC Pipes and Fittings SDR
11 to meet the requirement of ASTM-D 2846 and are produced in CTS (Copper Tube Sizes 1/2" to 2") for
hot and cold water (IS 15778:2007) including cost and conveyance of all materials to site, labour charges
for fixing, overheads & contractors profit complete for finished item of work at all floor levels.

a) 15.90mm OD pipe
Rate as per SoR 1 No. 142.00 Each 142.00
Overheads&Contractors Profit @ 13.615% 0.00000 142.00 0.00
Rate per 1 RM 142.00
say 142

b) 22.20mm OD pipe
Rate as per SoR 1 No. 173.00 Each 173.00
Overheads&Contractors Profit @ 13.615% 0.00000 173.00 0.00
Rate per 1 RM 173.00
say 173

c) 28.60mm OD pipe
Rate as per SoR 1 No. 207.00 Each 207.00
Overheads&Contractors Profit @ 13.615% 0.00000 207.00 0.00
Rate per 1 RM 207.00
say 207

d) 34.90mm OD pipe
Rate as per SoR 1 No. 282.00 Each 282.00
Overheads&Contractors Profit @ 13.615% 0.00000 282.00 0.00
Rate per 1 RM 282.00
say 282

e) 41.30mm OD pipe
Rate as per SoR 1 No. 350.00 Each 350.00
Overheads&Contractors Profit @ 13.615% 0.00000 350.00 0.00
Rate per 1 RM 350.00
say 350

f) 54.00mm OD pipe
Rate as per SoR 1 No. 510.00 Each 510.00
Overheads&Contractors Profit @ 13.615% 0.00000 510.00 0.00
Rate per 1 RM 510.00
say 510

19 Supplying & fixing GI pipe Medium Grade properties & weight as per IS 1239 ISI mark in ground or
on wall including cost of tees, elbows, bends, reducers, couplings, running joints, union flanges, unions
etc. with necessary excavation in all types of soils except rock requiring blasting, refilling, chiselling
masonry walls and making good the walls & floors to the original surface and fixing MS clamps on TW
blocks on walls including cost and conveyance of all materials and labour charges , overheads &
contractors profit complete for finished item of work.

a) 15mm Nominal bore


Rate as per SSR 1.00 RM 185.00 1 RM 185.00
Add for MA @ 40% 0.40 0.00 0.00
185.00
Overheads&Contractors Profit @ 13.615% 0.00000 185.00 0.00
185.00
Rate per 1 RM say 185
WS & SA DATA 2014-15 Page-36
b) 20mm Nominal bore
Rate as per SSR 1.00 RM 205.00 1 RM 205.00
Add for MA @ 40% 0.40 0.00 0.00
205.00
Overheads&Contractors Profit @ 13.615% 0.00000 205.00 0.00
205.00
Rate per 1 RM say 205

c) 25mm Nominal bore


Rate as per SSR 1.00 RM 269.00 1 RM 269.00
Add for MA @ 40% 0.40 0.00 0.00
269.00
Overheads&Contractors Profit @ 13.615% 0.00000 269.00 0.00
269.00
Rate per 1 RM say 269

d) 32mm Nominal bore


Rate as per SSR 1.00 RM 377.00 1 RM 377.00
Add for MA @ 40% 0.40 0.00 0.00
377.00
Overheads&Contractors Profit @ 13.615% 0.00000 377.00 0.00
377.00
Rate per 1 RM say 377
WS & SA DATA 2014-15 Page-37
e) 40mm Nominal bore
Rate as per SSR 1.00 RM 422.00 1 RM 422.00
Add for MA @ 40% 0.40 0.00 0.00
422.00
Overheads&Contractors Profit @ 13.615% 0.00000 422.00 0.00
422.00
Rate per 1 RM say 422

f) 50mm Nominal bore


Rate as per SSR 1.00 RM 454.00 1 RM 454.00
Add for MA @ 40% 0.40 0.00 0.00
454.00
Overheads&Contractors Profit @ 13.615% 0.00000 454.00 0.00
454.00
Rate per 1 RM say 454

19 Supplying and fixing 65 mm Nominal Bore GI pipe Medium Grade properties & weight as per IS
1239 in ground or on wall with GI fittings such as elbows tees couplings, nipples, plugs including
excavation for trenches and refilling the trenches ,chiselling masonry walls and making good the walls &
floors to the original surface and fixing MS clamps on TW blocks on walls including cost and conveyance
of all materials and labour charges , overheads & contractors profit complete for finished item of work
except for GI bends union and GI connectors with checkout and socket Tata or Zenith make or
equivalent.

Rate as per SSR 1.00 RM 806.00 1 RM 806.00


Overheads&Contractors Profit @ 13.615% 0.00000 806.00 0.00
806.00
Rate per 1 RM say 806

20 Supplying and fixing Bronze Gate/ Globe valve as per IS - 778 Class - I, Indian make heavy type
including cost and conveyance of all materials , labour charges , overheads & contractors profit complete
for finished item of work.

a) 15mm Nominal bore


Rate as per SSR 1 No. 580.00 Each 580.00
Overheads&Contractors Profit @ 13.615% 0.00000 580.00 0.00
580.00
Rate per Each say 580

b) 20mm Nominal bore


Rate as per SSR 1 No. 782.00 Each 782.00
Overheads&Contractors Profit @ 13.615% 0.00000 782.00 0.00
782.00
Rate per Each say 782

a) 25mm Nominal bore


Rate as per SSR 1 No. 1125.00 Each 1125.00
Overheads&Contractors Profit @ 13.615% 0.00000 1125.00 0.00
1125.00
Rate per Each say 1125

b) 32mm Nominal bore


Rate as per SSR 1 No. 1709.00 Each 1709.00
Overheads&Contractors Profit @ 13.615% 0.00000 1709.00 0.00
1709.00
Rate per Each say 1709

c) 40mm Nominal bore


Rate as per SSR 1 No. 2308.00 Each 2308.00
Overheads&Contractors Profit @ 13.615% 0.00000 2308.00 0.00
2308.00
Rate per Each say 2308
WS & SA DATA 2014-15 Page-38
d) 50mm Nominal bore
Rate as per SSR 1 No. 3382.00 Each 3382.00
Overheads&Contractors Profit @ 13.615% 0.00000 3382.00 0.00
3382.00
Rate per Each say 3382

g) 65mm Nominal bore


Rate as per SSR 1 No. 5222.00 Each 5222.00
Overheads&Contractors Profit @ 13.615% 0.00000 5222.00 0.00
5222.00
Rate per Each say 5222

h) 80mm Nominal bore


Rate as per SSR 1 No. 7741.00 Each 7741.00
Overheads&Contractors Profit @ 13.615% 0.00000 7741.00 0.00
7741.00
Rate per Each say 7741

21 Providing and placing on terrace (at all floor levels)polyetheylene water storage tank with double
layer approved brand and manufacture with cover and suitable locking arrangement and making
necessary holes for inlet and outlets and over flow pipes but without fittings and base support for tanks
including cost and conveyance of all materials and labour charges , overheads & contractors profit
complete for finished item of work.

Rate as per SSR 1 Ltr 7.00 1 Ltr 7.00


Add for MA @ 40% 0.40 0.00 0.00
7.00
Overheads&Contractors Profit @ 13.615% 0.00000 7.00 0.00
Rate per 1 Ltr 7.00

22 Supplying and fixing of stainless steel sink of size 508.00mm x 457.2mm x 203.20mm, 1mm thick of
Indian make fixed on cantilever brackets including supply and fixing 31.75mm C.P. waste coupling, 30mm
dia PVC flexible waste pipe of 914.4 mm length of Ist quality ncluding chiselling brick masonry wall and
making good & restoring to original surfaces , overheads & contractors profit complete for finished item of
work in all floors

Rate as per SSR 1 No 4470.00 Each 4470.00


Add for MA @ 40% 0.40 0.00 0.00
4470.00
Overheads&Contractors Profit @ 13.615% 0.00000 4470.00 0.00
4470.00
Rate per Each say 4470
22 Supplying and fixing of stainless steel sink of size 914.4 mm x457.2mm, 1mm thick of Indian make
fixed on cantilever brackets including supply and fixing 31.75mm C.P. waste coupling, 30mm dia PVC
flexible waste pipe of 914.4 mm length of Ist quality ncluding chiselling brick masonry wall and making
good & restoring to original surfaces overheads & contractors profit complete.for finished item of work in all
floors.

Rate as per SSR 1 No 6255.00 Each 6255.00


Add for MA @ 40% 0.40 0.00 0.00
6255.00
Overheads&Contractors Profit @ 13.615% 0.00000 6255.00 0.00
6255.00
Rate per Each say 6255
23 Supplying and fixing white glazed flat back Bowl urinals of size 440 mm x 265 mm x 315 mm with
integral flushing rim fixed with screws complete Indian make (HSW/Parry/Neycer) conforming to IS:2556-
1995 as approved by Engineer-in-charge, including supply and fixing 12.7mm PVC connection with brass
plumber union nuts CP coated, 12.70mm push cock 1st quality of approved make , 30mm dia PVC flexible
waste pipe of 914.4 mm length of Ist quality including cost and conveyance of all materials to site, labour
charges , overheads & contractors profit complete for finished item of work for all floors.

Rate as per SSR 1 No 771.00 Each 771.00


WS & SA DATA 2014-15 Page-39
Add for MA @ 40% 0.40 171.00 68.40
12.7mm PVC connections with brass plumber
union nuts 1 No 102.00 Each 102.00
Add for MA @ 40% 0.40 0.00 0.00
12.70mm NP push cock 1 No 247.00 Each 247.00
30mm dia. PVC flexible waste pipe 1 No 26.00 Each 26.00
1214.40
Overheads&Contractors Profit @ 13.615% 0.00000 1214.40 0.00
1214.40
Rate per Each Say 1214

23 Supplying and fixing white glazed flat back half stall urinals of size 590 mm x 375 mm x 390 mm
with integral flushing rim fixed with screws complete Indian make (HSW/Parry/Neycer) conforming to
IS:2556-1995 as approved by Engineer-in-charge, including supply and fixing 12.7mm PVC connection
with brass plumber union nuts CP coated, 12.70mm push cock 1st quality of approved make, 30mm dia
PVC flexible waste pipe of 914.4 mm length of Ist quality including cost and conveyance of all materials to
site, labour charges etc., overheads & contractors profit complete for finished item of work for all floors.

Rate as per SSR 1 No 2568.00 Each 2568.00


Add for MA @ 40% 0.40 171.00 68.40
12.7mm PVC connections with brass plumber
union nuts 1 No 102.00 Each 102.00
Add for MA @ 40% 0.40 0.00 0.00
12.70mm NP push cock 1 No 247.00 Each 247.00
30mm dia. PVC flexible waste pipe 1 No 26.00 Each 26.00
3011.40
Overheads&Contractors Profit @ 13.615% 0.00000 3011.40 0.00
3011.40
Rate per Each Say 3011

24 Supplying and fixing of 16mm to 20 mm thick polished marble slab partitioins of size 4' 0" x 2' 0"
for urinals including full rounding the edges, fixing in position, polishing, including cost and conveyance of
all materials and labour charges, overheads & contractors profit complete for finished item of work for all
floors.

Rate as per SSR 0.72 Sqm 907.00 1 Sqm 653.04


Chiselling the brick masonry wall 1.20 RM 31.00 1 RM 37.20
Add for MA @ 40% 0.40 37.20 14.88
Rounding the edges of marble 2.40 RM 480.00 1 RM 1152.00
Labour charges for fixing ( dadooing labour
charges ) 0.72 Sqm 741.00 10 Sqm 53.35
Add for MA @ 40% 0.40 53.35 21.34
1931.81
Overheads&Contractors Profit @ 13.615% 0.00000 1931.81 0.00
1931.81
Rate per Each Say 1932

25 Supplying and fixing of 101.60mm x 609.60mm white glazed porcelain channels 1st quality fixed in
brick masonry to the required slopes, white cement pointing including cost and conveyance of all
materials and labour charges, overheads & contractors profit complete for finished item of work for all
floors.
Rate as per SSR 1 No 451.00 1 Each 451.00
Rate for 1 RM (1/0.6096) 451.00 739.83
Overheads&Contractors Profit @ 13.615% 0.00000 739.83 0.00
739.83
Say 740

26 Construction of brick masonry support for GI pipe of size 304.80mm x 228.60mm x 228.60 mm in
CM (1:8) prop including plastering and finishing with 12mm thick in CM (1:5) including cost and
conveyance of all materials and all labour charges, overheads & contractors profit complete for finished
item of work for all floors.
WS & SA DATA 2014-15 Page-40
Rate as per SSR 1 No 77.00 1 Each 77.00
Add for MA @ 40% 0.40 0.00 0.00
77.00
Overheads&Contractors Profit @ 13.615% 0.00000 77.00 0.00
77.00
Rate per Each Say 77
WS & SA DATA 2014-15 Page-41

Market Rate mentioend in Circle office Rs.1043/-


REVISEDESTIMATE
Name of the work: Providing Gas Supplying pipeline for Supplying and Centralized Medical Oxygen to bed for COVID-19 Management in Gandhi Hospital
Secunderabab

As per Sanctioned Estimate As per Workdone


Sl. No. Description of Work Excess Less Remarks
Unit Amount Amount
QTY Rate Quantity Rate
(Rs.) (Rs.)
OXYGEN SYSTEM
2x20 Oxygen Main mannifold with 19mm ODx12mm
I.D .Copper pipe mounted on top frame , Middle
frmae and Bottom frame along with brass blocks,
NRVs/ cylinder valves and pigtail pipes of 1m long of
1 8mm OD x 3mm I.D. duly tested at 250Kg/Cum 2 1.00 Each No 270312 270312 1 No 270312 270312 0 0
pressure & semi automatic control panel for Oxygen

2x4 Oxygen Emergency manifold with 19mm


ODx12mm I.D .Copper pipe mounted on top frame ,
Middle frmae and Bottom frame along with brass
blocks, NRVs/ cylinder valves and pigtail pipes of 1m
2 long of 8mm OD x 3mm I.D. duly tested at 1.00 Each No 52836 52836 1 No 52836 52836 0 0
250Kg/Cum 2 pressure & semi automatic control
panel for Oxygen

Medical Grade Copper Pipe with Required Copper


Fittings
Copper Pipe for Medical use with 12 OD X 1.0 mm
3 3200 Mtr Mtr 401 1283200 2056 Mtr 401 824456 0 458744
V.P 27/ MB No.540
Copper Pipe for Medical use with 15 OD X 1.0 mm
4 9000 Mtr Mtr 527 4743000 4187.2 Mtr 527 2206654 0 2536346
V.P 27/ MB No.540

Page 42 of 204
Copper Pipe for Medical use with 22 OD X 1.0 mm
5 6500 Mtr Mtr 570 3705000 1948.4 Mtr 570 1110588 0 2594412
V.P 27/ MB No.540
Copper Pipe for Medical use with 28 OD X 1.0 mm
6 4000 Mtr Mtr 857 3428000 1884 Mtr 857 1614588 0 1813412
V.P 27/ MB No.540
Copper Pipe for Medical use with 42 OD X 1.0 mm
7 300 Mtr Mtr 1499 449700 265 Mtr 1499 397235 0 52465
V.P 28/ MB No.540
Gas Outlets double lock with probe
8 Oxygen outlets(Indeginous) as per HTM 2022 1100 Nos Nos 1535 1688500 993 Nos 1535 1524255 0 164245
V.P 28/ MB No.540
9 Oxygen flowmeter complete with Humidifier bottle 1100 Nos Nos 1025 1127500 993 Nos 1025 1017825 0 109675
V.P 29/ MB No.540

FACTORY DEGREASED ISOLATION VALVES FOR


MEDICAL USAGE WITH BRASS ADOPTERS
10 Isolation Valve for 15 mm Copper Pipe 150 Nos Nos 1100 165000 121 Nos 1100 133100 0 31900
V.P 28/ MB No.540
11 Isolation Valve for 22 mm Copper Pipe 250 Nos Nos 1714 428500 42 Nos 1714 71988 0 356512
V.P 29/ MB No.540
12 Isolation Valve for 28 mm Copper Pipe 46 Nos Nos 2785 128110 42 Nos 2785 116970 0 11140
V.P 29/ MB No.540
13 Isolation Valve for 42 mm Copper Pipe 15 Nos Nos 3497 52455 15 Nos 3497 52455 0 0

OUTLETS FOR AIR & VACUUM

14 Vacuum outlets(Indeginous) -with Probes By 300 Nos Nos 1535 460500 249 Nos 1535 382215 0 78285
considering 300 Beds for Oxygen and Vacuum
V.P 28/ MB No.540

15 Air-4 bar outlets(Indeginous) with Probes by 300 Nos Nos 1535 460500 249 Nos 1535 382215 0 78285
considering 100 beds with Oxygen, Air and Vacuum
V.P 28/ MB No.540
Ward Vacuum Unit.

Page 43 of 204
Ward Vacuum Unit complete with Regulator ,
16 collection bottle, Adapter and Bracket for collection 300 Nos Nos 1714 514200 249 Nos 1714 426786 0 87414
bottle
V.P 29/ MB No.540
Compressed Air System
Compressed Air System Consisting of 2 nos
(Reciprocating & oil free), each having 15 HP Motor
with 57.18 cfm capacity at 8.5Kg/cm2 pressure with
common receiver of Capacity 1000 ltrs, common Air
drier, Pressure Reducing Unit etc.
17 3-Stage Breathing Air Filter for 125 CFM as per ISO 1 Nos Nos 1114554 1114554 1 Nos 1114554 1114554 0 0
8573-1

V.P 30/ MB No.540


SITC of Electrical Control panel should be automatic
change over panel for changeover from A to B and
then from B to A and then from B to C. If any pump
trips then the second should start automatically.
The panel should consist of contactors Amp meter,
Volt meter, Single phase protector, MCB, phase
18 indicator, compressor on –off trip indicator and 1 Nos Nos 303450 303450 1 Nos 303450 303450 0 0
pressure switch .

V.P 31/ MB No.540


Vacuum System
2 nos. of Ingersoll Rand make Model 15V x 10 Model
with 7.5 HP Motor with 1000 litres Receiver, Filters,
19 Electricals, etc. 1 Nos Nos 941640 941640 1 Nos 941640 941640 0 0
Secretion Trap and bacteria filter

V.P 31/ MB No.540


DIGITAL ALARM SYSTEMS
2 Gas Digital Alarm 5 Nos Nos 16111 80555 2 Nos 16111 32222 0 48333

Page 44 of 204
3 Gas Microprocessor Controlled Alarm With Digital
20 Display 4 Nos Nos 21580 86320 3 Nos 21580 64740 0 21580

VALVE BOX (WITH VALVES) FOR MEDICAL USAGE

Valve Box - 3 Gas Service (size 15mm X 15 mm X


22mm) with NIST Connection & S.S.Valve for O2
21 5 Nos Nos 11138 55690 2 Nos 11138 22276 0 33414

22 High Pressure tube imported 400 Nos Nos 92 36800 350 Nos 92 32200 0 4600
23 Low Pressure Tube 400 Nos Nos 97 38800 350 Nos 97 33950 0 4850
Bed Head Panel.
bed Head Panel : The bed Head Panel should have
24 provision for Medical Gas outlet & electrical sockets 300 7069 2120700 249 Nos 7069 1760181 0 360519
for 2+2

Sub-Total:- 23735822 14889691 0 8846131

Copper pipe Supplimental Item:-


Medical Grade Copper Pipe with Required Copper
FittingsCopper Pipe for Medical use with 54 OD X 1.2 As per site
mm
condition it is
560 Rm 2520 1411200 1411200 0 excuted and
approved
department
agreemnt

Isolation Valve for 54 mm copper pipe


As per site
condition it is
8 Each 5000 40000 40000 0 excuted and
approved
department
agreemnt

Page 45 of 204
Fully automatic control pannel with non haloginated
polymers 1 Each 476900 476900 476900 0

Supplimental Sub-Total:- 1928100 1928100 0

Civil Supplemental Items:- .

Supply and fixing of 60mm thick wall panelling, As per higher


Having materials 0.5mm thick PPGI on Both authority
Sides of the panel.Puff as infilling with Density instruction but
40± 2kg/Cu. Mtr.Panel having make ESSAR. Panel not sanction
1 Colour RAL 9002 with a Supporting structure in MS 247 Sqm 4650 1148550 1148550 0 estimate for
rectangular pipes 96x48x3mm thick, Make :-JINDAL Covi-19
Ground Floor & First Floor Emergency work
hence it is
Excuted
V.P 42/ MB No.540
Supplying and fabricating, erecting and fixing in
position tabular trusses of approved design with
M.S tube conforming to I.S-1161 specifications
including roof frame work consisting of
rafters,ties struts and purlins including cost of
foundations bolts, cleats, bearings
plates,etc.,complete as per the sketch enclosed
and including cost of primary coat with red oxide As per site
paint including cost and conveyance of all condition from
materials, labour charges for erecting & fixing all oxygen cylinder
3 structural steel works erecting in position and 7650 Kgs 118.00 902700 902700 0 to building main
fixing by using chain pulley blocks, Derek pole line per oxygen
arrangements and cranes etc., complete in pipe line hence it
position, labour charges for fabrication, all is excuted
incidental charges, overheads and contractor
profit etc., complete for finished item of work as
directed by the Engineer-in-Charge

V.P 42/ MB No.540

Page 46 of 204
Painting two coats with synthetic enamel
paint Grade-II VOC (Volatile Organic
Compound) content less than 50 grams/litre
over primer coat of red oxide to new iron
work including cost and conveyance of all
materials to site, sales & other taxes, incidental, As psr site
6 operational and all labour charges etc., and 131.11 Sqm 156 20453 20453 0 condition it
overheads & contractors profit complete for isexcuted
finished item of work in all floors. (SS No. 1201,
1212 & 1207).

V.P 41/ MB No.540


Dismantling, clearing away and carefully stacking
useful materials for re-use and disposal of As per
unserviceable materials with 100m lead as directed emergency work
by Executive Engineer duly taking actual for covid-19 not
premeasurements before dismantling including all
avilable for
labour charges , overheads & contractor profit etc.,
complete manifold room
7 in the premises
of gandhi
hospital for
oxygen pipe line
hence it is
excuted

Unreinforced cement concrete up to 15cm


2.65 Cum 1520 4028 4028 0
thickness
V.P 39/ MB No.540

Page 47 of 204
Earth work excavation for foundations (Manual
Means) of buildings, septic tank, sump, As per
compound wall in ordinary soils and depositing on emergency work
bank with an initial lead of 10m and 1m additional for covid-19 not
lift charges over the initial depth up to 3m
avilable for
including all operational,incidental, labour charges
such as shoring, sheeting, planking, strutting etc., manifold room
8 and overheads & contractors profit complete for 73.29 Cum 239 17516 17516 0 in the premises
finished item of work excluding dewatering charges of gandhi
etc., as per SS 20 B(APSS 308) hospital for
oxygen pipe line
hence it is
excuted

V.P 39/ MB No.540


Filling with carted gravel in trenches,sides of
foundations and basement with initial lead in layers As per
not exceeding 15cm thick,watering and ramming emergency work
including cost and conveyance of water to work site for covid-19 not
and all peraitonal,incidental, labour charges,hire
avilable for
charges of T&P etc., and overheads & contractors
profit complete for fnished item of work(APSS manifold room
9 NO.309&310) 11.7 Cum 389 4551 4551 0 in the premises
of gandhi
hospital for
oxygen pipe line
hence it is
excuted

V.P 39/ MB No.540

Page 48 of 204
Plain Cement Concrete (1:5:10) (cement: fine
aggregate: Coarse aggregate) for foundations and
under flooring bed using coarse aggregate 40mm As per
size hard , machine crushed granite from emergency work
approved quarry including cost and conveyance of all for covid-19 not
materials like cement, sand, coarse aggregate, water avilable for
etc. to site, sales & other taxes on all materials and manifold room
10 including all charges for machine mixing, laying 24.38 Cum 4121 100470 100470 0 in the premises
concrete in foundations and under flooring bed,
of gandhi
ramming in 15 cm layers finishing top surface to the
required level curing etc.,and overheads &
hospital for
contractors profit complete for finished item of work. oxygen pipe line
(APSS No. 402) hence it is
excuted

V.P 39/ MB No.540


Plain Cement Concrete (1:3:6) nominal mix
using 40mm size machine crushed hard granite As per
metal (coarse aggregate) in (2:1) ratio from approved emergency work
quarry including cost and conveyance of all materials for covid-19 not
like cement, fine aggregate (sand), coarse aggregate, avilable for
water etc. to site, sales & other taxes on all materials,
manifold room
all charges for mixing, laying concrete in position,
11 vibrating, curing, centering charges, overheads &
2 Cum 4627 9254 9254 0 in the premises
contractors profit etc.,for finished item of work . of gandhi
hospital for
oxygen pipe line
hence it is
excuted

V.P 39/ MB No.540

Page 49 of 204
Supply and placing of the Design Mix Concrete
M 25 grade corresponding to IS 456 with minimum
cement content of 380 kgs per 1 cum of concrete
using Concrete Batching Plant with 20mm size
graded machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1
to Part 8) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site
and sales & other taxes on all materials , centering
using Steel scaffolding pipes , jack props , wallers ,
Foot plates , brackets , steel centering plates etc.,
including all operational, incidental and labour
charges such as weigh batching, machine mixing,
laying concrete, curing etc., and overheads &
contractors profit complete but excluding cost of steel
and its fabrication charges for finished item of work
(APSS No. 402).

Footings 0.9 Cum 9935 8942 8942 0

Column pedestals 1.8 Cum 10522 18940 18940 0

Page 50 of 204
Providing Thermo Mechanically Treated (TMT)
(Fe -500/500D/550D from Primary producer
TATA, SAIL, VSP, JSW &Shyam Steel etc as
per IS 1786-2008) of different diameters for RCC
works , including labour charges for straightening,
cutting, bending to required sizes and shapes, As per
placing in position with cover blocks of approved emergency work
materials and size and tying and lap-splicing with for covid-19 not
binding wire of 18 SWG, forming grills for
avilable for
reinforcement work as per approved designs and
drawings, including cost and conveyance of steel manifold room
12 bars, including all wastages such as overlaps, 0.358 MT 59039 21136 21136 0 in the premises
couplings, chairs, spacer bars including cost and of gandhi
conveyance of binding wire, cover blocks and all hospital for
incidental, operational, labour charges such as oxygen pipe line
cutting, bending, placing in position, tying including hence it is
sales and other taxes on all materials etc. ,and excuted
overheads & contractors profit complete for finished
item of work.( APSS No.126)

V.P 39/ MB No.540

Page 51 of 204
Supply and placing of the Design Mix Concrete
M 25 grade corresponding to IS 456 with minimum
cement content of 380 kgs per 1 cum of concrete
using Concrete Batching Plant with 20mm size
graded machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 As per
to Part 8) from approved quarry including cost and emergency work
conveyance of all materials like cement, fine for covid-19 not
aggregate (sand) coarse aggregate, water etc., to site avilable for
and sales & other taxes on all materials , centering manifold room
13 using Steel scaffolding pipes , jack props , wallers , in the premises
Foot plates , brackets , steel centering plates etc., of gandhi
including all operational, incidental and labour hospital for
charges such as weigh batching, machine mixing,
oxygen pipe line
laying concrete, curing etc., and overheads &
contractors profit complete but excluding cost of steel
hence it is
and its fabrication charges for finished item of work excuted
(APSS No. 402).

Plinth Beams 2.65 Cum 12344 32712 32712 0

Page 52 of 204
Supply and placing of the Design Mix Concrete
M 25 grade corresponding to IS 456 with minimum
cement content of 380 kgs per 1 cum of concrete
using Concrete Batching Plant with 20mm size
graded machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 As per
to Part 8) from approved quarry including cost and emergency work
conveyance of all materials like cement, fine for covid-19 not
aggregate (sand) coarse aggregate, water etc., to site avilable for
and sales & other taxes on all materials, centering manifold room
14 using Casurina Ballies, Bamboos, Wooden Reapers, in the premises
Runners, Wood Posts, Steel Plates etc., including all of gandhi
operational, incidental and labour charges such as hospital for
weigh batching, machine mixing, lifting of concrete
oxygen pipe line
manually, laying concrete, curing , overheads &
contractors profit etc., complete but excluding cost of
hence it is
steel and its fabrication charges for finished item of excuted
work (APSS No. 402)

LINTELS : 0.17 Cum 11929 2028 2028 0


V.P 39/ MB No.540

Page 53 of 204
Supply and placing of the Design Mix Concrete
M 25 grade corresponding to IS 456 with minimum
cement content of 380 kgs per 1 cum of concrete
using Concrete Batching Plant with 20mm size
graded machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1
to Part 8) from approved quarry including cost and
conveyance of all materials like cement, fine As per
aggregate (sand) coarse aggregate, water etc., to site emergency work
and including sales & other taxes on all materials , for covid-19 not
centering using Casurina Ballies , Bamboos , avilable for
Wooden Reapers , Runners , Wood Posts , Wall manifold room
Plates etc., for 60cm wide sun-shades 7.5cm thick
15 4.5 Sqm 505 2273 2273 0 in the premises
at fixed end and 5cm thick at free end with an
average thickness of 6.25cm including all
of gandhi
operational, incidental and labour charges such as hospital for
weigh batching, machine mixing, lifting of concrete oxygen pipe line
manually, laying concrete, curing, overheads & hence it is
contractors profit complete etc., but excluding cost of excuted
steel and its fabrication charges for finished item of
work (APSS No. 402, 403 & 903)

Masonry work in CM(1:6) prop (Cement : Screened


sand) in superstructure with fly ash cement / lime As per
solid blocks of size 290mm x 225mm x 140mm emergency work
from approved source having minimum crushing for covid-19 not
strength of 50 Kg/Sqcm. including cost and
conveyance of all materials like cement, sand, bricks,
avilable for
water etc., to site, including sales & other taxes on all manifold room
16 materials and such as labour charges, like mixing 37.76 Cum 6578 248385 248385 0 in the premises
cement mortar, scaffolding charges, constructing of gandhi
masonry, lift charges, curing, overheads and hospital for
contrctor profit etc., complete for finished item of oxygen pipe line
work. (APSS No. 501 & 504). hence it is
excuted

Page 54 of 204
Supplying and fixing of 2 shutter fully glazed
windows as per drawing using Sal wood frame and
one vertical mullion of size 100mm x 65mm and
shutters with Sal wood styles & rails of size
75mmx35mm and 4mm thick pin headed glass fixed
with teak wood beading of 12mm X 12mm including
cost of 4 Nos MS Z hold fasts of size 300 x 40 x 5 As per
mm including supply and fixing of ISI marked emergency work
aluminium fixtures, butt hinges of size 75mm long (2 for covid-19 not
Nos per shutter), 75mm handles (1No per shutter), avilable for
75mm x 10mm dia tower bolt (1No per shutter), and manifold room
17 aluminium window stopper with hook and eye 100mm 4.32 Sqm 5482 23682 23682 0 in the premises
long (1No per shutter) with 12mm MS square bars
of gandhi
horizontally at 100mm centre to centre fixed in frame
including labour charges for fixing the fixtures with hospital for
required No. of screws, fixing window in position oxygen pipe line
fixing shutters to frame including cost & conveyance hence it is
of all materials to site, labour charges etc., complete excuted
for finished item of work (APSS No 1001 & 1002).
(1200mm x 1300mm)

V.P 39/ MB No.540


Supply and fixing doors as per drawings with
medium teak wood frame of section 100mm x 65
mm and ISI marked flush door shutters of 30 mm
thick double shutters with bond wood solid block
board type Core having cross bands and face
veneers, hot pressed bonded with water proof phenol
18 formaldehyde synthetic resin factory made
conforming to IS 2202-1991 (Part-I) both sides
commercial ply with internal lipping on all sides
including cost and conveyance to site of teak wood
frame, flush shutter including

Page 55 of 204
supply and fixing 6 Nos. MS Z hold fasts of size
300 mm x 40 mm x 5mm including cost of ISI
marked Aluminium fixtures of 6 Nos. butt hinges
(IS:205) 150mm long, 1 No. aldrop (IS:2681)
300mm long, 2 Nos. tower bolts (IS:204) of 200
mm x 10 mm dia at top, 2 Nos. 150 mm long As per
handles (IS:208), 2 Nos. door stoppers and 2 emergency work
Nos. rubber bushes including fixing the fixtures for covid-19 not
to door with required number of screws, bolt and avilable for
nuts including labour charges for fixing the frame manifold room
in position, fixing the shutter to the frame etc., 5.04 Sqm 3548 17882 17882 0 in the premises
including overheads & contractors profit of gandhi
complete for finished item of work as per APSS hospital for
1001 & 1002 (The vertical frame of door shall be oxygen pipe line
embedded in flooring for a depth of not less than hence it is
10 mm) (1200mm x 2100mm). excuted

Plastering 12mm thick in two coats using


screened sand with base coat of 8mm thick in CM As per
(1:6) and top coat of 4mm thick in CM (1:4) with emergency work
dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water
for covid-19 not
etc., to site, including sales & other taxes on all avilable for
materials, and all operational, incidental charges on manifold room
19 materials and including cost of all labour charges for 285.92 Sqm 455 130094 130094 0 in the premises
mixing mortar, finishing, scaffolding, lift charges, of gandhi
curing, including cutting grooves as directed by hospital for
Engineer-in-charge etc., and overheads & contractors oxygen pipe line
profit complete for finished item of work. (SS 901,903 hence it is
& 904). excuted

V.P 39/ MB No.540

Page 56 of 204
Flooring with polished shahabad / Tandur stone
slabs of 15mm to 18mm thick set over a base coat
of CM (1:8) , 12mm thick using screened sand over
already laid CC bed / RCC roof slab including neat As per
cement slurry of honey like consistency spread @ 3.3 emergency work
Kgs per Sqm and jointed with neat cement to full for covid-19 not
depth including cost and conveyance of all materials avilable for
like cement, sand, water, flooring stones etc. manifold room
complete including sales & other taxes on all
20 61.05 Sqm 624 38095 38095 0 in the premises
materials including all labour charges like dressing of
flooring stones to the required size, mixing of cement of gandhi
mortar, laying, lift charges , cost of base coat, water hospital for
charges etc., and overheads & contractors profit oxygen pipe line
complete for finished item of work. (APSS No.703 & hence it is
701) excuted

V.P 39/ MB No.540


Supply & application of one coat water based
cement primer of interior grade I and two coats of As per
acrylic emulsion paint having VOC (Volatile emergency work
Organic Compound) content less than 50 grams/litre
for internal walls including cost and conveyance of
for covid-19 not
all materials to site, sales & other taxes, incidental, avilable for
operational and all labour charges etc., and manifold room
21 overheads & contractors profit complete for finished 144.56 Sqm 164 23708 23708 0 in the premises
item of work in all floors. of gandhi
hospital for
oxygen pipe line
hence it is
excuted

V.P 39/ MB No.540

Page 57 of 204
Supply & application of one coat water based
cement primer of exterior grade II and two coats As per
of acrylic emulsion paint exterior grade with silicon emergency work
additives having VOC (Volatile Organic Compound)
content less than 50 grams/ liter for exterior walls
for covid-19 not
including cost and conveyance of all materials to site, avilable for
sales & other taxes, incidental, operational and all manifold room
22 labour charges etc., and overheads & contractors 132.84 Sqm 240 31882 31882 0 in the premises
profit complete for finished item of work in all floors. of gandhi
hospital for
oxygen pipe line
hence it is
excuted

V.P 39/ MB No.540


Painting to new wood work and flush shutters
with lappam finish, over a primary coat and As per
painting two coats of synthetic enamel paint emergency work
Grade-II VOC (Volatile Organic Compound) content
for covid-19 not
less than 50 grams/litre of approved shade including
cost and conveyance of all materials to site cost of avilable for
primer coat and all labour charges etc. complete manifold room
23 including applying sand paper on lappam coats for 35.6 Sqm 180 6408 6408 0 in the premises
neat finish including sales & other taxes on cost of all of gandhi
materials etc., and overheads & contractors profit hospital for
complete in all floors (APSS No.1200, 1207 & 1211). oxygen pipe line
hence it is
excuted

Page 58 of 204
Roofing with corrugated G.I sheets 0.80mm thick
fixed with G.I ‘J’ bolts & nuts 8 mm dia with bitumen & As per
G.I limpet washers filled with white lead & including a emergency work
coat of approved steel primer and two coats of for covid-19 not
approved paint on over lapping of sheets complete
avilable for
(up to a pitch of 600) etc., complete, excluding the
cost of purlins, rafters, trusses including cost and manifold room
24 conveyance of all materials , labour charges , 67.76 Sqm 874 59222 59222 0 in the premises
overheads and contractors profit etc., complete for of gandhi
finished item of work in all floors. hospital for
oxygen pipe line
hence it is
excuted

V.P 39/ MB No.540

Filling with carted coarse sand in trenches,sides of


foundations and basement with initial lead in layers As per
not exceeding 15cm thick,watering and ramming emergency work
including cost and conveyance of water to work site for covid-19 not
and all peraitonal,incidental ,labour charges,hire
charges of T&P etc., and overheads & contractors
avilable for
profit complete for fnished item of work(APSS manifold room
NO.309&310) 7.5 Cum 848 6360 6360 0 in the premises
of gandhi
hospital for
oxygen pipe line
hence it is
excuted

Page 59 of 204
Plain Cement Concrete M 20 nominal mix using
WEIGH BATCHER / MIXER, 20mm size hard granite
machine crushed graded metal (coarse aggregate - As per
as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) emergency work
from approved quarry, using a minimum quantity of for covid-19 not
300 kgs. of cement per 1 cum of concrete including avilable for
cost and conveyance of all materials like cement,
manifold room
fine aggregate (Sand), coarse aggregate, water etc.,
to site including steel centering, shuttering, machine 15 Cum 5562 83430 83430 0 in the premises
mixing, lift charges, laying concrete,vibrating, curing, of gandhi
overheads & contrctors profit etc., complete for hospital for
finished item of work for coping on top of oxygen pipe line
compound wall (APSS No. 402 & 403). hence it is
excuted

Sub-Total:- 2962701 2962701 0

Electrical Work
Supply and Laying of P.V.C casing and caping (ISI
MARK) with double locking arrangments with
groover trunking of size not below 12.5mm height
25mm size with all accessories, duly sealed at points As per site
1 and erected on Wall / Ceiling including cost of all 400 Rm 50.00 20000 20000 0 condition it is
materials and labour charges complete. Makes : excuted
Modi with ISI

V.P 39/ MB No.540


Supply and Fixing of ISI 25mm outer dia
medium grade with IS:9537 part 3 regid PVC
pipe surface on wall/ceiling with all required
As per site
saddles and all accessories and labour charges
2 1210 Rm 65.00 78650 78650 0 condition it is
etc., complete for run of mains.
excuted
Makes : Sudhakar / Finolex / Modi / VIP /
Precision / Universal / Million Plast

V.P 39/ MB No.540

Page 60 of 204
Supply and fixing of 6A switchs - 2 Nos and 6A
3/2 pin socket - 2 Nos Modular type with front
cover plate including all labour charges etc.,
complete. As per site
3 Makes : Legrand Arteor / Schneider Zen celo / 176 Pts 783.00 137808 137808 0 condition it is
Honeywell Blenge Plus / Cabtree Amare / Logus excuted
Platina.(Including 3of 4Sqmm 2.0 Rmt)

V.P 39/ MB No.540


Supply & fixing of 16A/6A, 2 in one socket - 2
Nos with 16A switch control - 2 Nos modular
type with front cover plate including all labour
charges etc., complete. As per site
4 Makes : Legrand Arteor / Schneider Zen celo / 688 No's 901.00 619888 619888 0 condition it is
Honeywell Blenge Plus / Cabtree Amare / Logus excuted
Platina.(Including 3of 4Sqmm 2.0 Rmt)

V.P 39/ MB No.540


Supply and 3 runs of 4.0 sq mm (56/0.3 mm)
(phase neutral and earth) FRLS / HFFR PVC
insulated flexible copper cable in existing
conduit pipe including labour charges etc., As per site
5 complete for 16A sockets. 3713.3 Rm 136.00 505014 505014 0 condition it is
Makes of wires : Finolex / RR kabel / Havells / excuted
APAR EBXL / KEI / Polycab / V-Guard /
MILLION

V.P 39/ MB No.540

Page 61 of 204
Supply & run of 5 of 10.0 Sqmm (84/0.3mm) (3
phases, neutral and earth) FRLS / HFFR PVC
insulated flexible copper cable in the existing
conduict pipe for run of mains from Power panel
board to TPN DB"s with pin type lugs and As per site
6 connections etc., complete. [for PDBs] 120 Rm 442.00 53040 53040 0 condition it is
Makes of wires :Finolex / RR kabel / Havells / excuted
APAR EBXL / KEI / Polycab / V-Guard /
MILLION

V.P 39/ MB No.540


Supply and fixing of 12 Way TPN DB Horizontal
with IP 43 Protection as per IS:13032 with 1 No.,
of 63A 10KA FP MCB as incomer and 36 Nos 6-
32 A 10kA SP MCBs as out goings including As per site
7 internal connections and labour charges for 5 No's 20516.00 102580 102580 0 condition it is
FLUSH Mounting etc., complete for DBs. excuted
Makes : Legrand / Schneider / L&T.

V.P 39/ MB No.540


Supply and fixing of 8 Way VTPN DB with IP 43
Protection with 1 No., of 125A TPN MCCB,
Adjustable, Confirms to IS/IEC 60947-2 having
Breaking Capacity 25 KA with thermal magnetic
release Panel Mounted as incomer with 8 Nos As per site
8 of 63A, 10KA, TP MCBs C/D Curve ISI Mark 3 No's 33165.00 99495 99495 0 condition it is
as Out goings including internal connections excuted
and labour charges etc., complete.
Makes : Legrand / Schneider / L&T.

V.P 39/ MB No.540


Supply and fixing of cable adopteres box with
cover for DBs including, massaNosry work etc., As per site
9 complete., 6 No's 600 3600 3600 0 condition it is
Makes : Legrand / Schneider. excuted

Page 62 of 204
V.P 39/ MB No.540
Supply and Installation of 125 Amps 4P MCCB
with cable end boxes on suitable angle iron
frame work for the areas mentioned in the
As per site
drawings including all Labours charges,
10 10 No's 14435.00 144350 144350 0 condition it is
massonry work etc. complete for finished item of
excuted
work. Makes:Legrand / Shneider

V.P 39/ MB No.540


Supply of the Following PVC XLPE armoured
cable 1100 V Grade with ISI mark stranded /
solid, aluminimum conductor complete As per site
11 Makes : Torrent / Unicab / Polycab / Havells / condition it is
Gloster / KEI / Finolex / Paragon. excuted

3.5 Core 70.00 Sq.mm. 120 Rm 420.00 50400 50400 0


V.P 39/ MB No.540
Laying of PVC armoured under ground cable up
to 95 Sqmm fixing on chromium plated metallic
base saddles on wall as per IS 1255 and as As per site
12 directed by the department including cost and 120 Rm 35.00 4200 4200 0 condition it is
conveyance of all materials and labour charges excuted
etc., complete.

V.P 39/ MB No.540


LT CABLE TERMINATIONS:
Supply and Fixing of single compression brass
cable glands for 3.5 core following armoured As per site
13 cable with brass washers, lugs etc., complete. condition it is
excuted

70 Sq.mm 8 No's 319.00 2552 2552 0


V.P 39/ MB No.540

Page 63 of 204
Supply, Transportation and fixing of 60 W / 65
W LED LED Street light, Body made of high
grade pressure die – cast Aluminium alloy with
corrosion resistant powder coat, having
protective toughened glass cover, Less Glare, IP
66 (Silicon gasket ensures Optical & Electrical
compartments are IP 66) protected, wide
operating voltage range, P.F > 0.90, System
having efficacy >100 lumens/watt, with Ingress
protection IP66, Potted driver, Driver surge
protection >10KV, THD<15%, CCT: 3000-
6500K as desired by the department and as per
IS, CRI>80, Inbuilt Electrical protections like As per site
Over voltage, short circuit, Over load, Open requrement
14 Circuit, Miswiring, etc complete with BIS 10 No's 6559.00 65590 65590 0
hence it is
certification with warranty 50,000 burning hours. excuted
The contractor has to furnish the manufacturer
warranty letter, LM 79 and LM 80 certificates.
and fixing of luminaire on wall with 1.0Mt 40mm
dia GI pipe bracket and anti-tilting arrangements,
1.5 Sq.mm flexible copper cable including
masonary work and all labour charges and giving
connections etc., complete. LUMINAIRE
MAKE : Phillips / OSRAM / GE Venture /Wipro /
Crompton / Bajaj / Havells / Jaquar / IB LED
/Panasonic / Halonix / HPL / Syska / Eveready /
Surya /Keselec.LED MAKE : PHILIPS
LUMILEDS / CREE / NICHIA /OSRAM
/MILLION/ SAMSUNG / LG LEDs
V.P 39/ MB No.540

Supply and transportation of 48" (1200mm)


Sweep decorative Ceiling Fan with all As per site
accessories etc., complete. requrement
15 Makes : Crompton High Speed Decora / Havells 4 No's 2244.00 8976 8976 0
hence it is
Spark Deco / Orient Summer Crown / Panasonic excuted
Sprint Deco / Halonix Erbon

V.P 39/ MB No.540

Page 64 of 204
Supply and fixing of 2 Module Modular type
Electronic step type Fan Regulator for sweep AC
ceiling fans of 1200mm / 1420mm complete with
connections. As per site
Makes : Legrand Myrius / Million mway / Gold requrement
16 Medal Curve / Anchor Roma viola / GM Four-
4 No's 502.00 2008 2008 0
hence it is
Five / Havells Fabio / Panasonic Vision / L&T excuted
Englaze / Hager Insista / Benlo Vesta / C&S
Primo / CPL Vysma / Polycab Levana.

V.P 39/ MB No.540


Labour charges for fixing of ceiling fan and As per site
regulator including transportation and giving requrement
17 connections with twin core wire etc., complete. 4 No's 139.00 556 556 0
hence it is
excuted
V.P 39/ MB No.540
Supply of 10 sqmm WPTC (Weather Proof Twin
Core) ISI Alluminium Wire. Makes : Polycab /
GM / Million / V-Guard / Gold Medal / As per site
Kundancab / HPL / RPG / Nandicab / Nakoda / requrement
18 600 Rmt 44.00 26400 26400 0
Payal / Finecab / Gemini / Vimal / Suncab / hence it is
Stanjo / Rajnigandha / Orbit / Airson. excuted

V.P 39/ MB No.540


Supply and fixing of 12 V 150 AH MF battery As per site
including wire leads. Makes : Amar Raja (Power requrement
19 Zone) or Equivalent model of Exide / Panasonic / 4 No's 11500.00 46000 46000 0
hence it is
Gotech SSR-1837 excuted
V.P 39/ MB No.540

Page 65 of 204
Supply and Transportation of --------------------
single phase ISI submersible motor pumpset As per site
suitable for 4" Bore well. Makes: Varuna / Flowell requrement
20 / Waterman / Techno / Mahavir /unitek/ Fitwell/ 1 No's 13770.00 13770 13770 0
hence it is
Falcon/ Ellen/ Karvel / LPS/ Duke / Varsha / excuted
Ajantha.

V.P 80/ MB No.538


Supply and Transportation of …………………..
double walled corrugated HDPE duct made as
per specification BSEN - 500 86/IS 14930 Part-II As per site
with all accessories like couplers, bends, end requrement
21 30 Rm 119.00 3570 3570 0
caps, Ts etc., complete. Makes: DURA LINE hence it is
(Dura Guard) / Bajaj / Gamson / Ultra Plus excuted

V.P 81/ MB No.538


Providing and errecting heat shrinkable indoor
termination kit for 11 KV HTXLPE insulated As per site
armoured cable-------------with necessary requrement
22 2 Each 8599.00 17198 17198 0
materials etc., complete. Makes : Raychem / hence it is
Transeal / M Sea excuted

V.P 82/ MB No.538

Servicing of L&T ACB 'S As per site


requrement
23 24 No's 5500.00 132000 132000 0
hence it is
excuted
V.P 82/ MB No.538
Servicing of HT VCB'S As per site
requrement
24 5 No's 9000.00 45000 45000 0
hence it is
excuted
V.P 83/ MB No.538

Page 66 of 204
500 KVA DG SET at OPD Block As per site
requrement
25 1 Job 86375.00 86375 86375 0
hence it is
excuted
V.P 82/ MB No.538
500 KVA DG SET at South Block As per site
requrement
26 1 Job 86000.00 86000 86000 0
hence it is
excuted
V.P 85/ MB No.538
500 KVA DG SET at North Block As per site
requrement
27 1 Job 80475.00 80475 80475 0
hence it is
excuted
V.P 78/ MB No.538

500 KVA DG Contrle Panel micropanel cip As per site


requrement
28 3 Job 35000.00 105000 105000 0
hence it is
excuted
V.P 80/ MB No.538
Sub-Total:- 2540495 2540495 0
Grand Total:- 23735822 20392887 5503196 8846131

Page 67 of 204
Name of the work: Providing Gas Supplying pipeline for Supplying and Centralized Medical Oxygen to bed for COVID-19 Management in
Gandhi Hospital Secunderabab

GENERAL ABSTRACT

As per Sanction
Sl.No. Description As per Workdone Excess Less Remarks
Estimate

1 Providing Gas Supplying Pipe Line 23735822 14889691 0 8846131


a Copper pipe Supplemental Items 1928100 1928100 0
b Civil Supplemental Items 2962701 2962701 0
2 Electrical Supplemental 2540495 2540495 0
Sub Total: 23735822 22320987 7431296 8846131
3 Provision towards GST @ 18% 4272448 3027202 1245246
4 Provision towards GST @ 12% 660384 660384

Provision towards unforeseen items and


5 51730 277054 225324
rounding off

Provision towards Engineering Supervision


6 1774373 1774373
charges @ 7%
Grand Total:- 28060000 28060000 10091377 10091377
ESTIMATE
GANDHI HOSPITAL
Name of Work: Providing Gas Supplying Pipeline for supplying of Centralized Medical Oxygen to Beds for Covid 19
management in Gandhi Hospital, Hyderabad

800 Beds with Oxygen , 300 Beds with ICU

S. No. DECSRIPTION OF ITEM QTY UNIT RATE TOTAL VALUE

(Rs.) (Rs.)
1 OXYGEN SYSTEM
1.1
2 x 20 Oxygen Main Manifold with 19 mm O.D. x 12 mm I.D. Copper Pipe
mounted on Top Frame, Middle Frame and Bottom Frame, along with brass
1 Nos 270312 270312
blocks, NRVs/Cylinder Valves and Pigtail pipes of 1 mtr long of 8 mm O.D.
x 3 mm I.D. duly tested at 250 Kg/Cm2 pressure & Semi Automatic Control
Panel for Oxygen
1.2

2 x 4 Oxygen Emergency Manifold with 19 mm O.D. x 12 mm ID Copper 1 Set 52,836.00 52836


Pipe mounted on Top Frame, Middle Frame and Bottom Frame, along with
brass blocks, NRVs/Cylinder Valves and Pigtail Pipes of 1 mtr long of size
8 mm O.D. x 3 mm I.D. tested at 250 Kg/Cm2 pressure with Regulator
A) Medical Grade Copper Pipe with Required Copper Fittings
1 Copper Pipe for Medical use with 12 OD X 0.9 mm 3200 Mtr 401 1283200
2 Copper Pipe for Medical use with 15 OD X 1.0 mm 9000 Mtr 527 4743000
3 Copper Pipe for Medical use with 22 OD X 1.0 mm 6500 Mtr 570 3705000
4 Copper Pipe for Medical use with 28 OD X 1.0 mm 4000 Mtr 857 3428000
5 Copper Pipe for Medical use with 42 OD X 1.2 mm 300 Mtr 1499 449700
B) Gas Outlets double lock with probe
1 Oxygen outlets(Indeginous) with Probes 1100 Nos 1535 1688500
2 Oxygen flowmeter complete with Humidifier bottle 1100 Nos 1025 1127500
C) FACTORY DEGREASED ISOLATION VALVES FOR MEDICAL USAGE WITH
BRASS ADOPTERS
1 Isolation Valve for 15 mm Copper Pipe 150 Nos 1100 165000
2 Isolation Valve for 22 mm Copper Pipe 250 Nos 1714 428500
3 Isolation Valve for 28 mm Copper Pipe 46 Nos 2785 128110
4 Isolation Valve for 42 mm Copper Pipe 15 Nos 3497 52455

D) OUTLETS FOR AIR & VACUUM


1 Vacuum outlets(Indeginous) -with Probes By considering 300 Beds for 300 Nos 1535 460500
Oxygen and Vacuum
2 Air-4 bar outlets(Indeginous) with Probes by considering 100 beds with 300 Nos 1535 460500
Oxygen, Air and Vacuum
E) Ward Vacuum Unit.
1 Ward Vacuum Unit complete with Regulator , collection bottle, Adapter and 300 Nos 1714 514200
Bracket for collection bottle
F) Compressed Air System
1 Compressed Air System Consisting of 2 nos (Reciprocating & oil free), each
having 15 HP Motor with 57.18 cfm capacity at 8.5Kg/cm2 pressure with
common receiver of Capacity 1000 ltrs, common Air drier, Pressure
Reducing Unit etc. 1 set 1114554 1114554
3-Stage Breathing Air Filter for 125 CFM as per ISO 8573-1

2 SITC of Electrical Control panel should be automatic change over panel for
changeover from A to B and then from B to A and then from B to C. If any
pump trips then the second should start automatically. The panel should
consist of contactors Amp meter, Volt meter, Single phase protector, MCB,
phase indicator, compressor on –off trip indicator and pressure switch . 1 303450 303450

G) Vacuum System
1 2 nos. of Ingersoll Rand make Model 15V x 10 Model with 7.5 HP Motor
with 1000 litres Receiver, Filters, Electricals, etc.
Secretion Trap and bacteria filter 1 Set 941640 941640

H) DIGITAL ALARM SYSTEMS


1 2 Gas Digital Alarm 5 Nos 16111 80555
2 3 Gas Microprocessor Controlled Alarm With Digital Display 4 Nos 21580 86320
I) VALVE BOX (WITH VALVES) FOR MEDICAL USAGE
1 Valve Box - 3 Gas Service (size 15mm X 15 mm X 22mm) with NIST
Connection & S.S.Valve for O2 5 Nos 11138 55690
2 High Pressure tube imported 400 mtrs 92 36800
3 Low Pressure Tube 400 Mtrs 97 38800
J) Bed Head Panel.
1 bed Head Panel : The bed Head Panel should have provision for Medical
Gas outlet & electrical sockets for 2+2 300 Nos 7069 2120700

TOTAL 23735822
GST @ 18% 4272448
Grand Total 28008270
Rounding off 51730
28060000
Say Rs. 280.60
Lakhs
Name of the work: Providing Gas Supplying pipeline for Supplying and Centralized
Medical Oxygen to bed for COVID-19 Management in Gandhi Hospital Secunderabab

ABSTRACT ESTIMATE

Sl.No. Description of Work No 's L B H Qty Rate Amount

Dismantling, clearing away and carefully stacking useful materials


for re-use and disposal of unserviceable materials with 100m lead
1 as directed by Executive Engineer duly taking actual
premeasurements before dismantling including all labour charges ,
overheads & contractor profit etc., complete
Unreinforced cement concrete more than 15cm thickness
Foundation 2 6 0.50 0.5 0.20 0.60
Say 0.60 1520 912
Earth work excavation for foundations (Manual Means) of buildings,
septic tank, sump, compound wall in ordinary soils and depositing
2
on bank with an initial lead of 10m and depth up to 3m including all
operational,incidental, labour charges such as shoring, sheeting,
planking,
Footing strutting etc., and overheads2 & contractors
6 0.50 profit
0.5 complete
0.50 1.50
for finished item of work excluding dewatering charges etc., as Sayper 1.50 239 359
SS 20 B(APSS 308)
Filling with carted gravel in trenches,sides of foundations and basement with initial
lead in layers not exceeding 15cm thick,watering and ramming including cost and
conveyance of water to work site and all peraitonal,incidental, labour charges,hire
charges of T&P etc., and overheads & contractors
Flooring 1 1 profit
15.40complete
3.8 0.20for fnished item of
11.70
work(APSS NO.309&310) Say 11.70 389 4553

Plain Cement Concrete (1:5:10) (cement: fine aggregate: Coarse


aggregate) for foundations and under flooring bed using coarse
### aggregate 40mm size hard , machine crushed granite from
approved quarry including cost and conveyance of all materials like
cement, sand, coarse aggregate, water etc. to site, sales & other
Foundation
taxes on all materials and including all2 charges
6 0.50 0.5 mixing,
for machine 0.10 0.30
Fooring
laying concrete in foundations and under 1 flooring
1 15.40 3.8 0.10in
bed, ramming 5.85
15 cm layers finishing top surface to the required level curingSay 6.15 4121 25352
etc.,and overheads & contractors profit complete for finished item
of work. (APSS No. 402)
Providing Thermo Mechanically Treated (TMT) (Fe -500/500D/550D
from Primary producer TATA, SAIL, VSP, JSW &Shyam Steel etc
### as per IS 1786-2008) of different diameters for RCC works ,
including labour charges for straightening, cutting, bending to
required sizes and shapes, placing in position with cover blocks of
approved materials and size and tying and lap-splicing with binding
Bottom
wire & SWG,
of 18 Top Mat Y10grills
forming @ Bar 12 4
for reinforcement0.65
work as per 31.20
approved designs and drawings, including 12 4cost0.65
and conveyance of 31.20
steel bars, including all wastages such as overlaps, couplings, 62.40
chairs, spacer bars including cost and conveyance of binding wire,
cover blocks and all incidental, operational, labour charges such as 0.61
cutting, bending, placing in position, tying including sales and other 38.06
taxes on all materials etc. ,and overheads & contractors profit
complete
Pedastal for finished
steel Y12@item
Bar of work.( APSS
12 4No.126)
0.9 43.20
1.58
68.26

Stirupps 8mm@ 150mm C/c 12 4 0.92 44.16


44.16
0.39
17.22
Total Weight 0.124 59039 7294

Supply and placing of the Design Mix Concrete M 25 grade


corresponding to IS 456 with minimum cement content of 380
kgs per 1 cum of concrete using Concrete Batching Plant with
### 20mm size graded machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry including cost and conveyance of all materials like
cement, fine aggregate (sand) coarse aggregate, water etc., to site
Footing Concreate
and sales & other taxes on all materials 2 , centering
6 0.50 using
0.5Steel0.30 0.90
scaffolding pipes , jack props , wallers , Foot plates , brackets ,
steel centering plates etc., including all operational, incidentalSay and 0.90 9935 8942
labour charges such as weigh batching, machine
Supply and placing of the Design Mix Concrete M 25 grade mixing, laying
concrete, curing
corresponding toetc.,
IS 456andwith
overheads
minimum & contractors profit complete
cement content of 380
but
kgs per 1 cum of concrete using Concrete Batching for
excluding cost of steel and its fabrication charges finished
Plant with
item
20mm of size
workgraded
(APSSmachine
No. 402). crushed hard granite metal (coarse
Pedastal
aggregate - as per IS 383 - 1970 and2IS 2386 6 0.501 to 0.5
Part Part 8) 0.60
from 1.80
approved quarry including cost and conveyance of all materials like
cement, fine aggregate (sand) coarse aggregate, water etc., Say to site 1.80 10522 18940
and sales Thermo
Providing & other taxes on all materials
Mechanically Treated ,(TMT)
centering
(Fe using Steel
-500/500D/550D
scaffolding
from Primary producer TATA, SAIL, VSP, JSW &Shyam Steel ,etc
pipes , jack props , wallers , Foot plates , brackets
steel
as percentering plates of
IS 1786-2008) etc., including
different all operational,
diameters for RCCincidental
works , and
labour charges such as weigh batching, machine
including labour charges for straightening, cutting, bending mixing, laying
to
concrete, curing etc., and overheads & contractors profit
required sizes and shapes, placing in position with cover blocks of complete
but excluding
Plinth
approved beam cost ofand
steel
materials steel and
size and itstying
fabrication charges for
and lap-splicing finished
with binding
item
Bottom
wire of
of 18work (APSS
& SWG,
Top Mat No. 402).
Y12grills
forming @ Bar 2 4
for reinforcement 16work as per 128.00
approved
Bottom &designs
Top MatandY12 drawings,
@ Bar including 2 4cost4.4 and conveyance of 35.20
steel bars, including all wastages such as overlaps, couplings, 163.20
chairs, spacer bars including cost and conveyance of binding wire,
cover blocks and all incidental, operational, labour charges such as 0.88
cutting, bending, placing in position, tying including sales and other 143.62
taxes on all
Stirupps materials
8mm@ 150mmetc. ,and
C/c overheads 2 100 & contractors
0.92 profit 184.00
complete for finished
Stirupps 8mm@ 150mm C/c item of work.( APSS No.126)
2 26 0.92 47.84
231.84
0.39
90.42
Total Weight 0.234 59039 13817

Supply and placing of the Design Mix Concrete M 25 grade


corresponding to IS 456 with minimum cement content of 380
kgs per 1 cum of concrete using Concrete Batching Plant with
20mm size graded machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved
Plinth beamquarry including cost and conveyance
concreate 1 2 of all materials
15.40 0.23 0.30like 2.13
cement,
do fine aggregate (sand) coarse aggregate,
1 2 water
3.80 etc., 0.30
0.23 to site 0.52
and sales & other taxes on all materials , centering using Steel
scaffolding pipes , jack props , wallers , Foot plates , bracketsSay , 2.65 12344 32707
steel centering plates etc., including all operational, incidental and
labour charges such as weigh batching, machine mixing, laying
concrete,
Supply curing
and etc.,
placing ofand
the overheads
Design Mix &Concrete
contractors
M 25profit
grade complete
corresponding to IS
but excluding
456 cost ofcement
with minimum steel and its fabrication
content of 380 kgscharges
per 1 for
cumfinished
of concrete using
item of work
Concrete (APSSPlant
Batching No. 402).
with 20mm size graded machine crushed hard granite
metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site and sales & other taxes on all
materials, centering using Casurina Ballies, Bamboos, Wooden Reapers, Runners,
Wood Posts, Steel Plates etc., including all operational, incidental and labour
charges such as weigh batching, machine mixing, lifting of concrete manually, laying
LINTELS :
Windows 1 3 1.50 0.15 0.15 0.10
Door 1 2 1.50 0.15 0.15 0.07
Say 0.17 11929 2013

Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS


456 with minimum cement content of 380 kgs per 1 cum of concrete using
Concrete Batching Plant with 20mm size graded machine crushed hard granite
metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry including cost and conveyance of all materials like cement, fine
windows
aggregate (sand) coarse aggregate, water 1 etc.,
3 to1.50site and0.6 2.70
including sales & other
taxes on all materials , centering using
Doors 1 Casurina
2 1.50Ballies0.6, Bamboos , Wooden 1.80
Reapers , Runners , Wood Posts , Wall Plates etc., for 60cm wide sun-shades
Say 4.50 505 2273
7.5cm thick at fixed end and 5cm thick at free end with an average thickness of
Plain
6.25cmCement Concrete
including (1:3:6) nominal
all operational, mixand
incidental using 40mm
labour size machine
charges such ascrushed
weigh
hard granite
batching, metal (coarse
machine mixing, aggregate) in (2:1) ratio
lifting of concrete from approved
manually, quarry including
laying concrete, curing,
cost and conveyance
overheads & contractorsof profit
all materials like etc.,
complete cement, fine aggregate
but excluding cost of(sand), coarse
steel and its
aggregate, water etc. to site, sales & other taxes on all
fabrication charges for finished item of work (APSS No. 402, 403 & 903) materials, all charges for
mixing,
windows laying concrete in position, vibrating,2 curing,
3 centering
0.15 charges,
0.15 0.23 overheads &
0.03
contractors profit etc.,for finished item of work for footings and basement.
Doors 2 2 0.15 0.15 0.23 0.02
Say 0.05 4627 239

Masonry work in CM(1:6) prop (Cement : Screened sand) in superstructure with


fly ash cement / lime solid blocks of size 290mm x 225mm x 140mm from
### approved source having minimum crushing strength of 50 Kg/Sqcm. including cost
and conveyance of all materials like cement, sand, bricks, water etc., to site,
including sales & other taxes on all materials and such as labour charges, like
mixing cement mortar, scaffolding charges, constructing masonry, lift charges,
curing,walls
Long overheads and contrctor profit 1etc.,1 complete
15.40 for 0.23
finished
3.80item of 13.46
work.
(APSS No. 501 & 504).
do 1 1 15.40 0.23 3.20 11.33
Short walls 1 2 3.80 0.23 3.20 5.59
Iner wall 1 1 3.35 0.23 3.20 2.47
Deduct Door(-) 1 2 1.20 0.23 2.00 -1.10
Deduct W(-) 1 3 1.20 0.23 1.20 -0.99
Say 30.76 6578 202310
Supply and fixing doors as per drawings with medium teak wood frame of section
100mm x 65 mm and ISI marked flush door shutters of 30 mm thick double
shutters with bond wood solid block board type Core having cross bands and face
veneers, hot pressed bonded with water proof phenol formaldehyde synthetic resin
supply and
factory made fixing 6 Nos. MS
conforming to Z
IShold fasts of (Part-I)
2202-1991 size 300both
mm sides
x 40 mm x 5mm including
commercial ply with
cost of
internal
Doors ISI marked
lipping on Aluminium
all sides fixtures
including of 6
costNos.
1 2 andbutt hinges
conveyance
1.20 (IS:205)
to site
2.10150mm
of teak long,
wood1
5.04
frame, flush shutter including
Say 5.04 3548 17882
Supplying and fixing of 2 shutter fully glazed windows as per drawing using Sal
wood frame and one vertical mullion of size 100mm x 65mm and shutters with Sal
wood styles & rails of size 75mmx35mm and 4mm thick pin headed glass fixed with
teak wood beading of 12mm X 12mm including cost of 4 Nos MS Z hold fasts of size
300 x 40 x 5 mm including supply and fixing of ISI marked aluminium fixtures, butt
hinges of size 75mm long (2 Nos per shutter), 75mm handles (1No per shutter),
75mm
Windows x 10mm dia tower bolt (1No per shutter),1 3 and aluminium window
1.20 1.20 stopper4.32with
hook and eye 100mm long (1No per shutter) with 12mm MS square bars horizontally
at 100mm centre to centre fixed in frame including labour charges Say for fixing4.32
the 5482 23682
Plastering
fixtures with12mm thick
required No.in
of two coats
screws, using
fixing screened
window sand with
in position fixingbase coat to
shutters offrame
8mm
thick in CM
including (1:6)
cost and top coatofofall4mm
& conveyance thick in
materials to CM
site,(1:4) with
labour dubaraetc.,
charges sponge finishing
complete for
including costofand
finished item conveyance
work (APSS No of all materials
1001 like cement,
& 1002).(1200mm sand, water etc., to site,
x 1300mm)
including sales & other taxes on all materials, and all operational, incidental charges
on materials and including cost of all labour charges for mixing mortar, finishing,
Long walls lift charges, curing, including1cutting
scaffolding, 2 grooves
15.40 as directed3.80 117.04
by Engineer-in-
charge
do etc., and overheads & contractors 1 2profit complete
15.40 for finished
3.80 item of work.
117.04
(SS 901,903 & 904).
Short walls 1 2 3.80 3.20 24.32
do 1 2 3.80 3.20 24.32
do 1 2 3.35 3.20 21.44
Deduct Door(-) 2 2 1.20 2.00 -9.60
Deduct W(-) 2 3 1.20 1.20 -8.64
Say 285.92 455 130094
Flooring with polished shahabad / Tandur stone slabs of 15mm to 18mm thick
set over a base coat of CM (1:8) , 12mm thick using screened sand over already laid
CC bed / RCC roof slab including neat cement slurry of honey like consistency
spread @ 3.3 Kgs per Sqm and jointed with neat cement to full depth including
cost
Shedand conveyance of all materials like1 cement,1 sand, water,
16.50 3.7 flooring stones etc.
61.05
complete including sales & other taxes on all materials including all labour charges
61.05 624 38095
like dressing of flooring stones to the required size, mixing of cement mortar, laying,
lift charges , cost of base coat, water charges etc., and overheads & contractors
profit complete
Painting for finished
to new item 2of coats
walls with work. (APSS No.703
of Acrylic & 701)Oil bound Washable
based
Distemper having VOC content less than 50 grams/litre over promer coat using
white cemnt as approved by Engineer-In-Charge, making 3 coats in all to give an
even shade after thourughly brushing the surface to remove all dirt and remains of
loose powdered materials, including cost and conveyance of all materials to work
Long
site andwalls
all operational, incidental, labour1charges
2 15.40
etc., 3.80 & contractors
and overheads 117.04
Short walls
profit complete for finished item of work1 as 2 3.80 911 for internal
per APSS 3.20 walls24.32
in all
floors.
do 1 2 3.35 3.20 21.44
Deduct Door(-) 2 2 1.20 2.00 -9.60
Deduct W(-) 2 3 1.20 1.20 -8.64
Say 144.56 164 23708
Supply & application of one coat water based cement primer of exterior grade
II and two coats of acrylic emulsion paint exterior grade with silicon additives
having VOC (Volatile Organic Compound) content less than 50 grams/ liter for
exterior walls including cost and conveyance of all materials to site, sales & other
taxes, incidental, operational and all labour charges etc., and overheads &
Long walls 1 2 15.40 3.80 117.04
contractors profit complete for finished item of work in all floors.
Short walls 1 2 3.80 3.20 24.32
Deduct Door(-) 1 2 1.00 2.10 -4.20
Deduct W(-) 1 3 1.20 1.20 -4.32
Say 132.84 240 31882
Painting to new wood work and flush shutters with lappam finish, over a
primary coat and painting two coats of synthetic enamel paint Grade-II VOC
(Volatile Organic Compound) content less than 50 grams/litre of approved shade
including cost and conveyance of all materials to site cost of primer coat and all
Deduct Door(-)etc. complete including 1applying
labour charges 2 1.00 paper
sand 2.25on 2.10
lappam coats9.45
for
neat finish
Deduct including sales & other taxes 1on cost
W(-) 3 of 1.20
all materials
2.25etc.,
1.20and overheads
9.72
& contractors profit complete in all floors (APSS No.1200, 1207 & 1211).
Say 19.17 180 3451
Supplying and fabricating, erecting and fixing in position tabular
trusses of approved design with M.S tube conforming to I.S-1161
1 specifications including roof frame work consisting of rafters,ties
struts and purlins including cost of foundations bolts, cleats,
bearings plates,etc.,complete as per the sketch enclosed and
Iincluding
Section Horizontal 100x75mm
cost of primary 1 oxide
coat with red 12 paint
3.00including cost 36.00
and conveyance of all materials, labour charges for erectingCofficient
& fixing 7.50
all structural steel works erecting in position and fixing by using 270.00
chain
Circularpulley
Pipeblocks, Derek pole arrangements
60.3ODX3mm 1 6 and
15.40cranes etc., 92.40
complete in position, labour charges for fabrication, all incidental
92.40
charges, overheads and contractor profit etc., complete for finished
item of work as directed by the Engineer-in-Charge Cofficient 4.51
416.72

Circular Pipe 48.3 ODX4mm 2 6 4.95 59.40


1 6 0.60 3.60
63.00
Cofficient 4.37
275.31
Circular Pipe 26.9 ODX3.2mm 6 3 1.00 18.00
18.00
Cofficient 1.87
33.66
Circular Pipe 26.90 ODX4mm 6 2 0.60 7.20
6 2 0.50 6.00
6 2 0.40 4.80
6 2 0.30 3.60
6 2 0.20 2.40
24.00
Cofficient 1.87
44.88
Chequered Plate/300x300x 8mm 1 12
thick 12.00
Cofficient 4.24
50.88
Base Plate 100x100mm, 4mm thick 1 12
12.00
Cofficient 0.31
3.72
Bolts & Nuts16x90mm, 1 48 48.00
do 1 12 12.00
60.00
Cofficient 2.50
150.00
Total Weight 1245.17 118 146931

Roofing with corrugated G.I sheets 0.80mm thick fixed with G.I ‘J’ bolts & nuts 8
mm dia with bitumen & G.I limpet washers filled with white lead & including a coat of
approved steel primer and two coats of approved paint on over lapping of sheets
complete (up to a pitch of 600) etc., complete, excluding the cost of purlins, rafters,
trusses
Shed including cost and conveyance of1 all 1 materials
15.40, labour
4.4 charges , overheads
67.76
and contractors profit etc., complete for finished item of work in all floors.
Say 67.76 874 59222

794658
8th Floor
Copper Pipe for Medical use with 28
OD X 1.0 mm
Coridor area 1 1 30.00 30.00
do 1 1 12.50 12.50
do 1 1 12.00 12.00
do 1 1 14.00 14.00
do 1 1 4.00 4.00
do 1 1 4.00 4.00
Right side wall 1 1 30.00 30.00
Left side wall 1 1 30.00 30.00
Corridor-2 1 1 57.00 57.00
do 1 1 30.00 30.00
Right side wall 1 1 23.00 23.00
Gate to end area 1 1 18.50 18.50
do 1 1 19.00 19.00
Corridor-3 1 1 34.00 34.00
do 1 1 30.00 30.00
do 1 1 31.00 31.00
379.00
Copper Pipe for Medical use with 22
OD X 1.0 mm
Rooms-50 Main line 1 1 3.90 3.90
Rooms-58 Main line 1 1 3.50 3.50
Rooms-51Main line 1 1 3.60 3.60
Rooms-56 Main line 1 1 3.50 3.50
Rooms-55 Main line 1 1 4.50 4.50
Rooms-54 Main line 1 1 5.00 5.00
Rooms-53 Main line 1 1 5.00 5.00
Rooms-52 Main line 1 1 5.00 5.00
Rooms-58 Main line 1 1 5.40 5.40
Rooms-59 Main line 1 1 5.50 5.50
Rooms-60 Main line 1 1 5.50 5.50
Rooms-61 Main line 1 1 5.50 5.50
Rooms-62 Main line 1 1 5.50 5.50
Rooms-49 Main line 1 1 4.50 4.50
Rooms-63 Main line 1 1 5.50 5.50
Rooms-48 Main line 1 1 4.50 4.50
Rooms-47 Main line 1 1 5.50 5.50
Rooms-46 Main line 1 1 5.50 5.50
Rooms-45 Main line 1 1 4.50 4.50
Rooms-30 Main line 1 1 5.50 5.50
Rooms-29 Main line 1 1 5.50 5.50
Rooms-28 Main line 1 1 5.50 5.50
Rooms-27 Main line 1 1 6.50 6.50
Rooms-32 Main line 1 1 3.50 3.50
Rooms-33 Main line 1 1 6.50 6.50
Rooms-34 Main line 1 1 6.50 6.50
Rooms-35 Main line 1 1 7.00 7.00
Rooms-36 Main line 1 1 7.00 7.00
Rooms-37 Main line 1 1 7.00 7.00
Rooms-38Main line 1 1 7.00 7.00
Rooms-39 Main line 1 1 7.00 7.00
Rooms-40 Main line 1 1 7.00 7.00
Rooms-41 Main line 1 1 7.00 7.00
Rooms-42 Main line 1 1 7.00 7.00
Rooms-43 Main line 1 1 7.00 7.00
Rooms-42 Main line 1 1 4.50 4.50
Rooms-28 Main line 1 1 3.50 3.50
Rooms-23 Main line 1 1 3.50 3.50
Rooms-22 Main line 1 1 5.50 5.50
Rooms-21 Main line 1 1 5.50 5.50
Rooms-15 Main line 1 1 7.00 7.00
Rooms-4 Main line 1 1 7.00 7.00
Rooms-3 Main line 1 1 7.00 7.00
Rooms-2 Main line 1 1 26.00 26.00
Session-2 Main line 1 1 3.50 3.50
Session-1Main line 1 1 3.50 3.50
Session-1Main line 1 1 3.50 3.50
Session-1Main line 1 1 3.50 3.50
Session-1Main line Right side 1 1 3.50 3.50
Session-2Main line Right side 1 1 3.50 3.50
Session-3Main line Right side 1 1 3.50 3.50
Room1Main line 1 1 4.00 4.00
Room2Main line 1 1 2.00 2.00
Room3Main line 1 1 5.00 5.00
Room 4Main line 1 1 6.00 6.00
304.90
Copper Pipe for Medical use with 12
OD X 1.0 mm
Rooms-50 Drops 1 2 1.25 2.50
Rooms-58 Drops 1 2 1.25 2.50
Rooms-51Drops 1 2 1.25 2.50
Rooms-56Drops 1 2 1.25 2.50
Rooms-55 Drops 1 2 1.50 3.00
Rooms-54 Drops 1 2 1.50 3.00
Rooms-53 Drops 1 2 1.50 3.00
Rooms-52 Drops 1 2 1.50 3.00
Rooms-58 Drops 1 3 1.50 4.50
Rooms-59 Drops 1 3 1.50 4.50
Rooms-60 Drops 1 4 1.50 6.00
Rooms-61 Drops 1 4 1.50 6.00
Rooms-62 Drops 1 3 1.50 4.50
Rooms-49 Drops 1 2 1.50 3.00
Rooms-63 Drops 1 3 1.50 4.50
Rooms-48 Drops 1 2 1.50 3.00
Rooms-47 Drops 1 2 2.00 4.00
Rooms-46 Drops 1 2 2.00 4.00
Rooms-45 Drops 1 2 2.00 4.00
Rooms-30 Drops 1 3 2.00 6.00
Rooms-29 Drops 1 3 2.00 6.00
Rooms-28 Drops 1 3 2.00 6.00
Rooms-27 Drops 1 3 2.00 6.00
Rooms-32 Drops 1 2 1.50 3.00
Rooms-33 Drops 1 3 2.00 6.00
Rooms-34 Drops 1 3 2.00 6.00
Rooms-35 Drops 1 3 2.00 6.00
Rooms-36 Drops 1 3 2.00 6.00
Rooms-37 Drops 1 3 2.00 6.00
Rooms-38Drops 1 3 2.00 6.00
Rooms-39 Drops 1 3 2.00 6.00
Rooms-40Drops 1 3 2.00 6.00
Rooms-41 Drops 1 3 2.00 6.00
Rooms-42 Drops 1 3 2.00 6.00
Rooms-43 Drops 1 3 2.00 6.00
Rooms-42 Drops 1 2 2.00 4.00
Rooms-28 Drops 1 2 1.50 3.00
Rooms-23 Drops 1 2 1.50 3.00
Rooms-22 Drops 1 2 2.00 4.00
Rooms-21 Drops 1 2 2.00 4.00
Rooms-15 Drops 1 3 2.00 6.00
Rooms-4 Drops 1 2 1.50 3.00
Rooms-3 Drops 1 3 1.50 4.50
Rooms-2 Drops 1 10 1.50 15.00
Session-2 Drops 1 2 2.00 4.00
Session-1Drops 1 2 2.00 4.00
Session-1Drops 1 2 2.00 4.00
Session-1Drops 1 2 2.00 4.00
Session-1Drops Right side 1 2 2.00 4.00
Session-2Drops Right side 1 2 2.00 4.00
Session-3DropsRight side 1 2 2.00 4.00
Room1Drops 1 2 1.50 3.00
Room2Drops 1 3 1.50 4.50
Room3Drops 1 3 1.50 4.50
Room 4Drops 1 4 1.50 6.00
255.50
OUTLETS FOR AIR & VACUUM
8th floor Value 28mm 1 12 12.00

5th Floor
Copper Pipe for Medical use with 22
OD X 1.0 mm
Dep.Surgical room 1 1 35.00 35.00
Copper Pipe for Medical use with 15
OD X 1.0 mm
Male ward 1 1 111.00 111.00
Femal ward 1 1 120.00 120.00
231.00
Copper Pipe for Medical use with 12
OD X 1.0 mm
Femal ward 1 1 81.00 81.00
Male ward 1 1 84.00 84.00
165.00
OUTLETS FOR AIR & VACUUM
5th floor Value 22mm 1 1 1.00
5th floor Value 15mm 1 2 2.00
Out lets 1 229 229.00

Road work
Earth work excavation for foundations (Manual Means) of buildings, septic
tank, sump, compound wall in ordinary soils and depositing on bank with an
initial lead of 10m and 1m additional lift charges over the initial depth up to 3m
including all operational,incidental, labour charges such as shoring, sheeting,
Road work
planking, strutting etc., and overheads & 1contractors
1 16.00 5 0.90
profit complete 72.00
for finished item
of work excluding dewatering charges etc., as per SS 20 B(APSS 308) Say 72.00 239 17208
Filling with carted coarse sand in trenches,sides of foundations and basement
with initial lead in layers not exceeding 15cm thick,watering and ramming including
cost and conveyance of water to work site and all peraitonal,incidental ,labour
charges,hire charges of T&P etc., and overheads & contractors profit complete for
Road
fnishedwork
item of work(APSS NO.309&310)1 1 16.00 5 0.10 8.00
Say 8.00 848 6784

Plain Cement Concrete (1:5:10) (cement: fine aggregate: Coarse aggregate) for
foundations and under flooring bed using coarse aggregate 40mm size hard ,
machine crushed granite from approved quarry including cost and conveyance of
all
Roadmaterials
work like cement, sand, coarse aggregate,
1 1 water etc.
16.00 5 to site,
0.15sales &12.00
other 4121 49452
taxes on all materials and including all charges for machine mixing, laying concrete
in foundations and under flooring bed, ramming in 15 cm layers finishing top surface
Masonry work in
to the required CM(1:6)
level curing prop (Cement
etc.,and : Screened
overheads sand) in profit
& contractors superstructure
completewith
for
fly ash cement / lime solid blocks
finished item of work. (APSS No. 402) of size 290mm x 225mm x 140mm from
approved source having minimum crushing strength of 50 Kg/Sqcm. including cost
and
Roadconveyance
work of all materials like cement,
1 2 sand, 16.00bricks,
0.23water
0.90 etc., to 6.62
site, 4121 27298
including sales & other taxes on all materials and such as labour charges, like
Plain Cement Concrete M 20 nominal mix using WEIGH BATCHER / MIXER,
mixing cement mortar, scaffolding charges, constructing masonry, lift charges,
20mm size hard granite machine crushed graded metal (coarse aggregate - as per
curing, overheads and contrctor profit etc., complete for finished item of work.
IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry, using a minimum
(APSS No. 501 & 504).
quantity
Road workof 300 kgs. of cement per 1 cum1of concrete
1 including
16.00 5 cost0.20
and conveyance
16.00 5562 4121
of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc.,
to site including steel centering, shuttering, machine mixing, lift charges, laying
concrete,vibrating, curing, overheads & contrctors profit etc., complete for finished
item of work for coping on top of compound wall (APSS No. 402 & 403).
Electrical Datas 2019-20
SSR
S.No Description Qty Unit Rate Amount
No
CONDUIT PIPE
1 Supply and Laying of P.V.C casing and caping (ISI MARK) with double locking arrangments with
groover trunking of size not below 12.5mm height 25mm size with all accessories, duly sealed at
points and erected on Wall / Ceiling including cost of all materials and labour charges complete.
Makes : Modi with ISI

a) Labour charges :
1 Skilled Electrician. 1.00 day 1 day 565.00 565.00
2 Lineman / Semi Skilled Electrician. 1.00 day 1 day 470.00 470.00
3 Helper (Electrical). 2.00 day 1 day 470.00 940.00
Labour Rate Per 100 Rm 1975.00
Labour Rate for 1 Mtr 19.75
b) Material
1.2.4 b)
SoR-18- Supply of 25mm width and 12.5mm
100.00 Rm 1 Rm 30.00 3000.00
19 height Casing and Caping.
Material Rate for 100 Mtrs 3000.00
Material Rate for 1 Mtr 30.00
Total Cost of Material + Labour 49.70
Charges
Add Contractors Profit 0.000% 0.00
49.70
Rate per Meter 50.00
2 Supply and Fixing of ISI 25mm outer dia medium grade with IS:9537 part 3 regid PVC pipe
surface on wall/ceiling with all required saddles and all accessories and labour charges etc.,
complete for run of mains. Makes : Sudhakar / Finolex / Modi / VIP / Precision / Universal / Million
Plast / Gold / Polycab / DEC.

a) Labour charges :
1 Skilled Electrician. 2.00 day 1 day 565.00 1130.00
2 Lineman / Semi Skilled Electrician. 2.00 day 1 day 470.00 940.00
3 Helper (Electrical). 2.00 day 1 day 470.00 940.00
Labour Rate Per 100 Rm 3010.00
Labour Rate for 1 Mtr 30.10
b) Material
9.1.2 Rawl Plugs. 200.00 Nos 100 Nos 33.00 66.00
1.4.4 d) Supply of No.8 Screws of 35/38mm. 200.00 Nos 100 Nos 100.00 200.00
(SoR-2016-17-TBSE-1.4.23)
9.4.11 Cement. 5.00 kg 1 Kg 8.00 40.00
1.1.11 Supply of 25mm Saddles with Base. 200.00 Nos 100 Nos 210.00 420.00
b)
1.2.5 b) Supply of 25mm PVC Junction Boxes 12.00 Nos 1 No 20.00 240.00
Normal.
1.2.7 b) Supply of 25mm dia 1.5mm thick PVC 12.00 Nos 1 No 8.00 96.00
Bends.
1.2.2 b) Supply of ISI 25mm outer dia medium 100.00 Mtr 1 Mtr 24.00 2400.00
(1.80mm thickness) grade FRLS with
IS:9537 part 3 regid PVC pipe.
Material Rate for 100 Mtrs 3462.00
Material Rate for 1 Mtr 34.62
Total Cost of Material + Labour 64.70
Charges
Add Contractors Profit 0.000% 0.00
64.70
Rate per Meter 65.00

6A Switches - 2 Nos & 6A Sockets - 2 Nos


3 Supply and fixing of 6A switchs - 2 Nos and 6A 3/2 pin socket - 2 Nos Modular type with cover
plate and GI switch box fixing on separate board including all labour charges etc., complete.
Makes : Legrand Arteor / Schneider Zen celo / Honeywell Blenge Plus / Cabtree Amare / Logus
Platina.
a) Labour charges :
1 Skilled Electrician. 0.20 day 1 day 565.00 113.00
2 Helper (Electrical). 0.20 day 1 day 470.00 94.00
Labour for 1 No 207.00
b) Material
1.3.2 d) Supply of 6 Modular Cover Frame. 1 Nos 1 No 130.00 130.00

Page 81 of 204
1.9.1 a) Supply of 6A / 10A 1 Way 1 Module 2 Nos 1 No 88.00 176.00
Modular Switch.
1.9.1 d) Supply of 6A / 10A 3/2 Pin 2 Module 2 Nos 1 No 135.00 270.00
Modular Socket with shutter.
Cost of Material for 1 No 576.00
Total Cost of Material + Labour 783.00
Charges
Add Contractors Profit 0.000% 0.00
783.00
Rate per Each 783.00

16A Socket - 2 Nos & 16A Switch - 2 Nos


4 Supply & fixing of 16A/6A, 2 in one socket - 2 Nos with 16A switch control - 2 Nos modular type
with and GI switch box with front cover plate including all labour charges etc., complete.
Makes : Legrand Arteor / Schneider Zen celo / Honeywell Blenge Plus / Cabtree Amare / Logus
Platina.

a) Labour charges :
1 Skilled Electrician. 0.15 day 1 day 565.00 84.75
2 Helper (Electrical). 0.15 day 1 day 470.00 70.50
Labour for 1 No 155.25
b) Material
1.3.2 d) Supply of 6 Modular Cover Frame. 1 Nos 1 No 130.00 130.00

1.9.1 h) Supply of 16A / 20A 1 Way 1 Module 2 Nos 1 No 120.00 240.00


Modular Switch.
1.9.1 i) Supply of 16A/6A 1 way Combi Socket 2 Nos 1 No 188.00 376.00
Modular Socket with shutter.
Cost of Material for 1 No 746.00
Total Cost of Material + Labour
901.00
Charges
Add Contractors Profit 0.000% 0.00
901.00
Rate per Each 901.00

Run of Mains
5 Supply and 3 runs of 4.0 sq mm (56/0.3 mm) (phase neutral and earth) FRLS / HFFR PVC
insulated flexible copper cable in existing conduit pipe including labour charges etc., complete
for 16A sockets.
Makes of wires :Finolex / RR kabel / Havells / APAR EBXL / KEI / Polycab / V-Guard / MILLION
a) Labour charges :
1 Skilled Electrician. 1.00 day 1 day 565.00 565.00
2 Lineman Electric / Telephone 3.00 day 1 day 470.00 1410.00
3 Helper (Electrical). 1.00 day 1 day 470.00 470.00
Labour for 100 Mtr 2445.00
Labour for 1 Mtr 24.45
b) Material
1.5.1 c) Supply of 56/0.3mm (4.0 Sqmm) FRLS / 300.00 Mtrs 100 Mtrs 3725.00 11175.00
HFFR Copper cable.
Cost of Material for 100 Metres 11175.00
Cost of Material Rate per Mtr= C/100 111.75
Total Cost of Material + Labour 136.20
Charges
Add Contractors Profit 0.000% 0.00
136.20
Rate per Meter 136.00

6 Supply & run of 5 of 10.0 Sqmm (140/0.3 mm) (3 phases, neutral and earth) FRLS / HFFR PVC
insulated flexible copper cable in the existing conduict pipe for run of mains from Power panel
board to TPN DB"s with pin type lugs and connections etc., complete. [for PDBs]
Makes of wires : Finolex / RR kabel / Havells / APAR EBXL / KEI / Polycab / V-Guard / MILLION
a) Labour charges :
1 Skilled Electrician. 2.34 day 1 day 565.00 1322.10
2 Lineman Electric / Telephone 6.50 day 1 day 470.00 3055.00
3 Helper (Electrical). 2.34 day 1 day 470.00 1099.80
Labour for 100 Mtr 5476.90
Labour for 1 Mtr 54.77
b) Material
1.5.2 Supply of 140/0.3mm (10.0 Sqmm) PVC 500.00 Mtrs 100 Mtrs 7750.00 38750.00
e) FRLS / HFFR insulated flexible Copper
cable.

Page 82 of 204
Cost of Material for 100 Metres 38750.00
Cost of Material Rate per Mtr= C/100 387.50
Total Cost of Material + Labour 442.20
Charges
Add Contractors Profit 0.000% 0.00
442.20
Rate per Meter 442.00

Distribution Boards
12 Way TPNDB
7 Supply and fixing of 12 Way TPN DB Horizontal with IP 43 Protection as per IS:13032 Makes :
Legrand / Schneider / Siemens / L&T / Hager /Cabtree Xproand Supply and Fixing of 1 No., of
63A 10 KA FP MCB as incomer and 36 Nos 6-32 A 10kA SP MCBs Makes : Legrand-DX3 /
Schneider-Acti9 / Siemens / L&T Exora / Cabtree as out goings including internal connections
and labour charges for FLUSH Mounting etc., complete for DBs.
MATERIAL
Legran Supply of 12 Way TPN DB Horizontal 1 Nos 1 No 9170.00 9170.00
d Pg.12 with IP 43 Protection as per IS:13032
and suitable for 36 Nos S.P. out goings
and 4 pole Incommer etc complete.

2.13.1 Supply of 63A FP MCB. 1 No 1 No 1900.00 1900.00


h)
2.13.1 Supply of 6-32A 10KA SP MCB, C/D 36 Nos 1 No 210.00 7560.00
a) Curve ISI Mark.
Sundries 5.00
18635.00
LABOUR
1 Skilled Electrician. 1.25 day 1 day 565.00 706.25
2 Lineman Electric / Telephone 1.25 day 1 day 470.00 587.50
3 Helper (Electrical). 1.25 day 1 day 470.00 587.50
1881.25
TOTAL COST OF MATERIAL + FLUSH 20516.00
LABOUR FOR FLUSH MOUNTING
Add Contractors Profit 0.000% 0.00
20516.00
Rate per Each 20516.00

8 Way VTPN DB
8 Supply and fixing of 8 Way VTPN DB with IP 43 Protection Makes : Legrand / Schneider /
Siemens / L&T / Hager /Cabtree Xpro and Supply and Fixing of 1 No., of 125A TPN MCCB,
Adjustable, Confirms to IS/IEC 60947-2 having Breaking Capacity 25 KA with thermal magnetic
release Panel Mounted as incomer with 8 Nos of 63A, 10KA, TP MCBs C/D Curve ISI Mark as
Out goings including internal connections and labour charges etc., complete. Makes : L&T /
MATERIAL
2.16.3 Supply of 8/ Way
Schneider Siemens / Legrand
VTPN DB / Hager /ABB / C&S.
1 Nos 1 No 11800.00 11800.00
b)
2.13.1 Supply of 63A 10KA TPN MCB, C/D 8 Nos 1 No 1480.00 11840.00
f) Curve ISI Mark.
2.8.1 C) 125A 3 Pole MCCB, 25KA 1 Nos 1 No 7404.00 7404.00
Sundries 5.00
COST OF MATERIAL FOR Surface 31049.00
MOUNTING
LABOUR
1 Skilled Electrician. 1.25 day 1 day 565.00 706.25
2 Lineman Electric / Telephone 1.50 day 1 day 470.00 705.00
3 Helper (Electrical). 1.50 day 1 day 470.00 705.00
COST OF LABOUR FOR Surface 2116.25
MOUNTING
TOTAL COST OF MATERIAL + 33165.00
LABOUR FOR Surface MOUNTING
Add Contractors Profit 0.000% 0.00
33165.00
Rate per Each 33165.00

10 Supply and Installation of 125 Amps 4 Pole MCCB, Adjustable, Confirms to IS/IEC 60947-2
having Breaking Capacity 25 KA with thermal magnetic release etc complete with connections.
Make: L&T / Schneider / Siemens / Legrand / Hager /ABB / C&S.

MATERIAL
Fabrication: L H D
Size of panel : in Mtr 0.50 0.50 0.25

Page 83 of 204
Front and back faces 2.00 0.50 0.50 0.50
Top and bottom faces 2.00 0.50 0.25 0.25
Side faces 2.00 0.50 0.25 0.25
Sub total 1.00
Add extra 10 % for wastage 0.10
Total 1.10
7.12.1 Fabrication and erection of 14 / 16 SWG 1.10 Sqmtr 1 Sqmtr 4140.00 4554.00
b) CRCA sheet steel enclosure for power
control cubicle panel / boxes etc.,
including cutting, bending drilling,
welding and reveting etc., complete
with cleaning with 7 tank process and
2.8.1 d) painting
125 Ampswith
FP MCCB,
powder 25 KA including
coating 1 Nos 1 No 8925.00 8925.00
cost and conveyance of all materials
and labourfor
Provision charges.
angle iron frame work 203.00
etc.,
13682.00
LABOUR
1 Skilled Electrician. 0.50 day 1 day 565.00 282.50
2 Lineman Electric / Telephone 1.00 day 1 day 470.00 470.00
752.50
TOTAL COST OF MATERIAL +
14435.00
LABOUR
Add Contractors Profit 0.000% 0.00
14435.00
Rate per Each 14435.00

11 U.G Cables
a) 4.1.1 j) Supply of 70 Sqmm 3.5 Core XLPE RMS 1 1 One 420.00 420.00
insulated, 1100V grade armoured Rmt
alluminium cable with ISI mark as per
specification confirming to IS:7098 (Part
- I)
Makes : Torrent / Unicab / Universal /
Polycab / Havells / Gloster / KEI /
Finolex / Paragon.

Add Contractors Profit 0.000% 0.00


420.00
Rate per Meter 420.00

12 Laying of PVC armoured under ground cable up to 95 Sqmm fixing on chromium plated metallic
base saddles on wall as per IS 1255 and as directed by the department including cost and
conveyance of all materials and labour charges etc., complete.

b) Labour charges
1 Skilled Electrician. 1.50 day 1 day 565.00 847.50
2 Helper (Electrical). 2.00 day 1 day 470.00 940.00
Labour Charges for 100 Mtrs 1787.50
Labour Charges for 1 Mtr 17.88
a) Material
9.1.2 Rawl Plugs. 4.00 Nos 100 Nos 33.00 1.32
1.4.4 d) Supply of No.8 Screws of 35/38mm. 4.00 Nos 100 Nos 100.00 4.00

9.4.23 Supply of Saddle / Clamps for Cable. 2.00 Nos 100 Nos 550.00 11.00
f)
Cost of Material for Laying on wall for 1.00 Mtr 16.32
Total Cost of Material + Labour 35.00
Charges
Add Contractors Profit 0.000% 0.00
35.00
Rate per Meter 35.00
13 a) Termination of UG cables of 3.5 core 70 Sq.mm including with required Heavy duty cable
glands, Lugs complete with all required accessories as directed by the department including
cost and conveyance of all materials and labour charges etc., complete.

b) Labour charges
1 Skilled Electrician. 0.020 day 1 day 565.00 11.30

Page 84 of 204
2 Lineman Electric / Telephone 0.020 day 1 day 470.00 9.40
3 Helper (Electrical). 0.020 day 1 day 470.00 9.40
Labour Charges for each 30.10
a) Material
4.3.1 d) glands for 3.5 core XLPE armoured 1.00 Nos 1 Nos 200.00 200.00
cable from 70 Sqmm
4.4.2 c) aluminium lugs for cable of 35 Sq.mm 1.00 Nos 1 Nos 17.00 17.00

4.4.2 e) aluminium lugs confirming to I.S 3.00 Nos 1 Nos 24.00 72.00
specifications for cable of 70 Sq.mm

289.00
Total Cost of Material + Labour 319.00
Charges
Add Contractors Profit 0.000% 0.00
319.00
Rate per Each 319.00

14 Supply of 10 sqmm WPTC (Weather Proof Twin Core) ISI Alluminium Wire. Makes :
Polycab / GM / Million / V-Guard / Gold Medal / Kundancab / HPL / RPG / Nandicab / Nakoda
/ Payal / Finecab / Gemini / Vimal / Suncab / Stanjo / Rajnigandha / Orbit / Airson.

a) Labour charges :
1 Skilled Electrician. 1 day 1 day 565 283
2 Lineman Electric / Telephone 1 day 1 day 470 235
3 Helper (Electrical). 1 day 1 day 470 470
Labour for 100 Mtr 988
Labour for 1 Mtr 10
b) Material
1.5.2 c) Supply of 10 sqmm WPTC (Weather 100 Mtrs 100 Mtrs 3400 3400
Proof Twin Core) ISI Alluminium Wire

Cost of Material for 100 Metres 3400


Cost of Material Rate per Mtr= C/100 34

Total Cost of Material + Labour 44


Charges
Add Contractors Profit 0 0
44
Rate per Meter 44

Supply and fixing of 12 V 150AH MF


battery including wire leads. Makes :
Amar Raja (Power Zone) or
Supply andmodel
Equivalent fixing of
of 12 V 150AH
Exide MF
/ Panasonic 100 NOS 100 NOS 11500 11500
battery
/ Gotech- SSR-1897

1 Supply, Transportation and fixing of 60 W / 65 W LED LED Street light, Body made of high
grade pressure die – cast Aluminium alloy with corrosion resistant powder coat, having protective
toughened glass cover, Less Glare, IP 66 (Silicon gasket ensures Optical & Electrical
compartments are IP 66) protected, wide operating voltage range, P.F > 0.90, System having
efficacy >100 lumens/watt, with Ingress protection IP66, Potted driver, Driver surge protection
>10KV, THD<15%, CCT: 3000- 6500K as desired by the department and as per IS, CRI>80,
a) Labour
Inbuilt charges
Electrical protections like Over voltage, short circuit, Over load, Open Circuit, Miswiring, etc
1 Skilled Electrician.certification with warranty 50,000
complete with BIS burning hours.
0 day The contractor565
1 day has to furnish
141
the manufacturer warranty
2 Lineman Electric / Telephone letter, LM 79 and LM 80 certificates.
0 day and fixing
1 day of luminaire
470 on wall118
with 1.0Mt 40mm dia GI pipe bracket and anti-tilting arrangements, 1.5 Sq.mm flexible copper
3 Helper (Electrical).
cable including masonary work and all labour charges0 dayand giving1connections
day 470
etc., complete. 118
Labour for 1 MAKE
LUMINAIRE No : Phillips / OSRAM / GE Venture /Wipro / Crompton / Bajaj / Havells / Jaquar 376/
b) Material
IB LED /Panasonic / Halonix / HPL / Syska / Eveready / Surya /Keselec.LED MAKE : PHILIPS
LUMILEDS
1.5.2 Supply / CREE
of 2.5 Sqmm/ NICHIA
FRLS / /OSRAM
HFFR / SAMSUNG / LG LEDs.
2 Mtrs 100 Mtrs 2140 43
b) Copper cable.
9.4.15 40mm Nominal Bore Medium grade 1 Mtrs 1 Mtr 350 350
b) G.I.Pipe.
Pipe bending charges LS 40
M.S flat and welding charges LS 50

Page 85 of 204
3.11.1 60 / 65 W 1 Nos 1 Nos 5700 5700
d
Cost of Material for 1 No 6183
Total Cost of Material + Labour 6559
Charges
Add Contractors Profit 0 0
6559
Rate per Each 6559

Page 86 of 204
SPECIFICATION REPORT

Name of the work: Providing Gas Supplying pipeline for Supplying and Centralized
Medical Oxygen to bed for COVID-19 Management in Gandhi Hospital Secunderabab

REVISEDE STIMATE AMOUNT : Rs: 280.60Lakhs

The Estimate for the work of "Providing Gas Supplying pipeline for supplying and
Centralized Medical Oxygen to bed for Covid-19 Management in Gandhi Hospital Secundrabad"
was technically sanctioned for Rs. 280.60 lakhs and the work was awarded to M/s Shree Bharath
Pharma & Medical Oxygen Distributors, Contractor Hyderabad vide agreement No.
03/TSMSIDC/2020-21 dated: 05.05.2020 for Rs. 2,37,35,822/- the estimate contract value of Rs.
2,37,35,822/- (SSR 2020-21) with stipulated (i.e., by 05.05.2020) for completion of work.

The reasons for the deviations are shown in the remarks column of the comparative
statement against respective items. The following are the main item which is exceeding the
estimate quantities as per site conditions which can be accommodated against savings.

Sl. No. Description of Work Amount Remarks


Quantity Rate
(Rs.)

Supplemental Items:-

Medical Grade Copper Pipe with Required


Copper FittingsCopper Pipe for Medical use
with 54 OD X 1.0 mm As per higher
authority
instruction but
1 330 Rm 2520 831600 not sanction
estimate for
Covi-19
Emergency
work hence it
is Excuted

Supply and Fixing of Drilling of holes to


concreare including cost and
conveyance of all materials like cement, ,
etc., to site, including sales & other taxes
on all materials, and all operational,
incidental charges on materials and As per higher
including cost of all labour finishing, 120 authority
2 Each 65 7800
instruction but
curing as directed by Engineer-in-charge
etc., and overheads & contractors profit not sanction
complete for finished item of work .(SS estimate for
901,903 & 904) Covi-19
Emergency
work hence it
is Excuted

Supplying and fabricating, erecting and As per site


fixing in position tabular trusses of condition from
approved design with M.S tube oxygen
conforming to I.S-1161 specifications cylinder to
3 including roof frame work consisting of 3816 Kgs 118.00 450325 building main
rafters,ties struts and purlins including line per
cost of foundations bolts, cleats, oxygen pipe
bearings plates,etc.,complete as per the line hence it is
sketch enclosed and including cost of excuted
primary coat with red oxide paint
including cost and conveyance of all
materials, labour charges for erecting &
fixing all structural steel works erecting
in position and fixing by using chainPage 87 of 204
pulley blocks, Derek pole arrangements
and cranes etc., complete in position,
Supply and Fixing of Anchor Bolts with As psr site
4 threding all labour charges compete of 120 No's 80 9600 condition it
work. isexcuted

Supply and Fixing of Nut bolts with As psr site


5 threding all labour charges compete of 58 No's 60 3480 condition it
work. isexcuted

Painting two coats with synthetic


enamel paint Grade-II VOC (Volatile As psr site
6 Organic Compound) content less than 69.76 Sqm 156 10883 condition it
50 grams/litre over primer coat of red isexcuted
oxide to new iron work including cost
and conveyance of all materials to site,
Dismantling
sales & , otherclearing taxes,
away andincidental,
carefully
stacking useful
operational and materials
all labourforcharges
re-use etc.,
and
disposal of unserviceable
and overheads materials profit
& contractors with As per
100m lead as directed by Executive emergency
complete for finished item of work in all
Engineer duly taking actual work for
floors. (SS No. 1201,before
premeasurements
1212 & 1207).
dismantling covid-19 not
including all labour charges , overheads & avilable for
contractor profit etc., complete
manifold room
7
in the premises
of gandhi
hospital for
oxygen pipe
line hence it is
excuted

Unreinforced cement concrete up to


2.65 Cum 1520 4028
15cm thickness

Earth work excavation for foundations


(Manual Means) of buildings, septic tank,
sump, compound wall in ordinary soils As per
and depositing on bank with an initial lead emergency
of 10m and 1m additional lift charges over work for
the initial depth up to 3m including all covid-19 not
operational,incidental, labour charges such avilable for
as shoring, sheeting, planking, strutting etc.,
manifold room
8 and overheads & contractors profit complete 5.29 Cum 239 1264
for finished item of work excluding in the premises
dewatering charges etc., as per SS 20 of gandhi
B(APSS 308) hospital for
oxygen pipe
line hence it is
excuted

Filling with carted gravel in trenches,sides


of foundations and basement with initial lead
in layers not exceeding 15cm thick,watering As per
and ramming including cost and conveyance emergency
of water to work site and all work for
peraitonal,incidental, labour charges,hire covid-19 not
charges of T&P etc., and overheads & avilable for
contractors profit complete for fnished item of
manifold room
9 work(APSS NO.309&310) 12.21 Cum 389 4750
in the premises
of gandhi
hospital for
oxygen pipe
line hence it is
excuted

Page 88 of 204
Plain Cement Concrete (1:5:10) (cement:
fine aggregate: Coarse aggregate) for
foundations and under flooring bed using
coarse aggregate 40mm size hard , As per
machine crushed granite from approved emergency
quarry including cost and conveyance of all work for
materials like cement, sand, coarse covid-19 not
aggregate, water etc. to site, sales & other avilable for
taxes on all materials and including all
charges for machine mixing, laying concrete 7.43
manifold room
10 Cum 4121 30619
in foundations and under flooring bed, in the premises
ramming in 15 cm layers finishing top surface of gandhi
to the required level curing etc.,and hospital for
overheads & contractors profit complete for oxygen pipe
finished item of work. (APSS No. 402) line hence it is
excuted

Plain Cement Concrete (1:3:6) nominal


mix using 40mm size machine crushed hard
granite metal (coarse aggregate) in (2:1) As per
ratio from approved quarry including cost and emergency
conveyance of all materials like cement, fine work for
aggregate (sand), coarse aggregate, water covid-19 not
etc. to site, sales & other taxes on all avilable for
materials, all charges for mixing, laying manifold room
11 concrete in position, vibrating, curing, 0.05 Cum 4627 231
in the premises
centering charges, overheads & contractors
profit etc.,for finished item of work for of gandhi
footings and basement. hospital for
oxygen pipe
line hence it is
excuted

Providing Thermo Mechanically Treated


(TMT) (Fe -500/500D/550D from Primary As per
producer TATA, SAIL, VSP, JSW emergency
&Shyam Steel etc as per IS 1786-2008) work for
of different diameters for RCC works , covid-19 not
including labour charges for straightening, avilable for
cutting, bending to required sizes and manifold room
12 shapes, placing in position with cover blocks
0.274 MT 59039 16177
in the premises
of approved materials and size and tying and of gandhi
lap-splicing with binding wire of 18 SWG, hospital for
forming grills for reinforcement work as per oxygen pipe
approved designs and drawings, including line hence it is
cost and conveyance of steel bars, including
all wastages such as overlaps, couplings,
excuted
chairs, spacer bars including cost and
conveyance of binding wire, cover blocks
and all incidental, operational, labour
charges such as cutting, bending, placing in
position, tying including sales and other
taxes on all materials etc. ,and overheads &
contractors profit complete for finished item
of work.( APSS No.126)

Page 89 of 204
Supply and placing of the Design Mix
Concrete M 25 grade corresponding to IS
456 with minimum cement content of 380
kgs per 1 cum of concrete using Concrete
Batching Plant with 20mm size graded
machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS As per
2386 Part 1 to Part 8) from approved quarry emergency
including cost and conveyance of all work for
materials like cement, fine aggregate (sand) covid-19 not
coarse aggregate, water etc., to site and avilable for
sales & other taxes on all materials , manifold room
13 centering using Steel scaffolding pipes , jack in the premises
props , wallers , Foot plates , brackets , steel
centering plates etc., including all
of gandhi
operational, incidental and labour charges hospital for
such as weigh batching, machine mixing, oxygen pipe
laying concrete, curing etc., and overheads & line hence it is
contractors profit complete but excluding cost excuted
of steel and its fabrication charges for
finished item of work (APSS No. 402).

Plinth Beams 3.5 Cum 12344 43204

Supply and placing of the Design Mix


Concrete M 25 grade corresponding to IS As per
456 with minimum cement content of 380 emergency
kgs per 1 cum of concrete using Concrete work for
Batching Plant with 20mm size graded
covid-19 not
machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS avilable for
2386 Part 1 to Part 8) from approved quarry manifold room
14
including cost and conveyance of all in the premises
materials like cement, fine aggregate (sand) of gandhi
coarse aggregate, water etc., to site and hospital for
sales & other taxes on all materials, oxygen pipe
centering using Casurina Ballies, Bamboos, line hence it is
Wooden Reapers, Runners, Wood Posts, excuted
Steel Plates etc., including all operational,
incidental and labour charges such as weigh
LINTELS :machine mixing, lifting of concrete 0.17
batching, Cum 11929 2028
manually, laying concrete, curing , overheads
& contractors profit etc., complete but
Supply and placing of the Design Mix
excluding cost of steel and its fabrication
Concrete
charges forMfinished
25 gradeitemcorresponding
of work (APSStoNo. IS As per
456
402) with minimum cement content of 380 emergency
kgs per 1 cum of concrete using Concrete work for
Batching Plant with 20mm size graded covid-19 not
machine crushed hard granite metal (coarse avilable for
aggregate - as per IS 383 - 1970 and IS manifold room
15 2386 Part 1 to Part 8) from approved quarry 4.5 Cum 505 2273
in the premises
including cost and conveyance of all
materials like cement, fine aggregate (sand) of gandhi
coarse aggregate, water etc., to site and hospital for
including sales & other taxes on all oxygen pipe
materials , centering using Casurina Ballies , line hence it is
Bamboos , Wooden Reapers , Runners , excuted
Wood Posts , Wall Plates etc., for 60cm
wide sun-shades 7.5cm thick at fixed end
and 5cm thick at free end with an average As per
Brick
thicknessmasonry of for panel
6.25cm walls all
including in emergency
superstructure with CM (1:8) prop:
operational, incidental and labour charges (Cement work for
:such
Screened sand)batching,
as weigh using common
machine burnt clay
mixing, covid-19 not
bricks of class as per Table- I of IS:1077-
lifting of concrete manually, laying concrete, avilable for
1992,
curing,Non- Modular &
overheads or traditional
contractorssize 23 x
profit manifold room
16 11 x 7 cms
complete fromexcluding
etc., but approvedcostsource having
of steel and
29.5 Cum 6324 186558
in the premises
minimum crushing strength of 40 Kg/Sqcm.
its fabrication charges for finished item of of gandhi
including
work (APSS cost and 403
No. 402, conveyance
& 903) of all
materials like cement, screened sand, bricks,
hospital for
water etc., to site, including sales & other oxygen pipe
taxes on all materials and such as labour line hence it is
charges, like mixing cement mortar, excuted
scaffolding charges, constructing masonry,
lift charges, curing, etc.,and overheads &
contractors profit complete for finished item
of work. (APSS No. 501 & 504).

Page 90 of 204
Supplying and fixing of 2 shutter fully
glazed windows as per drawing using Sal As per
wood frame and one vertical mullion of size emergency
100mm x 65mm and shutters with Sal wood work for
styles & rails of size 75mmx35mm and 4mm covid-19 not
thick pin headed glass fixed with teak wood avilable for
beading of 12mm X 12mm including cost of 4 manifold room
17 Nos MS Z hold fasts of size 300 x 40 x 5 mm 4.32 Sqm 5482 23682
in the premises
including supply and fixing of ISI marked of gandhi
aluminium fixtures, butt hinges of size 75mm hospital for
long (2 Nos per shutter), 75mm handles (1No
oxygen pipe
per shutter), 75mm x 10mm dia tower bolt
(1No per shutter), and aluminium window line hence it is
stopper with hook and eye 100mm long (1No excuted
per shutter) with 12mm MS square bars
horizontally at 100mm centre to centre fixed
Supply
in frame and fixinglabour
including doorscharges
as per drawings
for fixing
with mediumwith
the fixtures teakrequired
wood frame No. ofof screws,
section
100mm x 65 mm
fixing window in and ISI marked
position flush door
fixing shutters to
18 shutters of 30 mm
frame including costthick double shutters
& conveyance of all
with bond wood
materials to site,solid block
labourboard type Core
charges etc.,
having
complete cross bands item
for finished and offace veneers,
work (APSS hot No
pressed bonded with water
1001 & 1002).(1200mm x 1300mm)proof phenol
formaldehyde synthetic resin factory made
supply and to
conforming fixing
IS 62202-1991
Nos. MS Z hold fasts
(Part-I) both As per
of
sidessize 300 mm
commercial x 40
ply with mm lipping
internal x 5mm on emergency
including cost of ISI
all sides including costmarked Aluminium
and conveyance to work for
fixtures of 6 Nos.
site of teak wood butt hinges
frame, flush(IS:205)
shutter
including
covid-19 not
150mm long, 1 No. aldrop (IS:2681)
avilable for
300mm long, 2 Nos. tower bolts (IS:204)
manifold room
of 200 mm x 10 mm dia at top, 2 Nos. 5.04 Sqm 3548 17882
in the premises
150 mm long handles (IS:208), 2 Nos.
of gandhi
door stoppers and 2 Nos. rubber bushes
hospital for
including fixing the fixtures to door with
oxygen pipe
required number of screws, bolt and nuts
line hence it is
including labour charges for fixing the
excuted
frame in position, fixing the shutter to the
frame etc., including overheads &
contractors
Painting to profit complete
new wood workforand
finished
flush
item of work as per APSS
shutters with lappam finish, over1001 & 1002a
(The
primary vertical
coat and frame of door
painting two shall
coats beof As per
embedded
synthetic enamel paint Grade-II ofVOC
in flooring for a depth not emergency
less thanOrganic
(Volatile 10 mm) Compound)
(1200mm x 2100mm).
content less work for
than 50 grams/litre of approved shade covid-19 not
including cost and conveyance of all avilable for
materials to site cost of primer coat and all manifold room
19 labour charges etc. complete including 19.17 Sqm 180 3451
in the premises
applying sand paper on lappam coats for
neat finish including sales & other taxes on of gandhi
cost of all materials etc., and overheads & hospital for
contractors profit complete in all floors oxygen pipe
(APSS No.1200, 1207 & 1211). line hence it is
excuted

Supplying and fabricating, erecting and


fixing in position tabular trusses of As per
approved design with M.S tube conforming emergency
to I.S-1161 specifications including roof work for
frame work consisting of rafters,ties struts covid-19 not
and purlins including cost of foundations avilable for
bolts, cleats, bearings plates,etc.,complete manifold room
20 as per the sketch enclosed and including 1513 Kg 118 178584
in the premises
cost of primary coat with red oxide paint of gandhi
including cost and conveyance of all
materials, labour charges for erecting & fixing
hospital for
all structural steel works erecting in position oxygen pipe
and fixing by using chain pulley blocks, line hence it is
Derek pole arrangements and cranes etc., excuted
complete in position, labour charges for
fabrication, all incidental charges, overheads
and contractor profit etc., complete for
finished item of work as directed by the
Engineer-in-Charge

Page 91 of 204
Roofing with corrugated G.I sheets
0.80mm thick fixed with G.I ‘J’ bolts & nuts
8 mm dia with bitumen & G.I limpet washers As per
filled with white lead & including a coat of emergency
approved steel primer and two coats of work for
approved paint on over lapping of sheets covid-19 not
complete (up to a pitch of 600) etc., avilable for
complete, excluding the cost of purlins, manifold room
21 rafters, trusses including cost and 61.05 Sqm 874 53358
in the premises
conveyance of all materials , labour charges ,
overheads and contractors profit etc., of gandhi
complete for finished item of work in all hospital for
floors. oxygen pipe
line hence it is
excuted

Supply and Fixing of MS Rectangular


Pipe 96x48x4mm Thick
1Metre
x10No's
=104Kgs 1.80Metre x05 No's As per site
22 =94Kgs Base Plate 247 Kg 130 32110 condition it is
200x8mm=15no's =39Kgs excuted
100x100x6mm=15No's
=10Kgs Anchor Bolt 12mmx100=6
No's

Supply & fixing of MS Square pipe on the


top of puff panel Supporting structure for As per site
23 oxygen Copper pipe line & Electrical line 1434 Sqm 140 200792 condition it is
MS Square pipe 40x40x2mm thick base excuted
plate 50mmx100mmx6mm thick anchor
Bolts 10mmx100mm along with painting
Ground Floor & First Floor
Supply and fixing of 60mm thick wall
panelling, Having materials 0.5mm thick
PPGI on Both Sides of the panel.Puff as As per site
24 infilling with Density 40± 2kg/Cu. Mtr.Panel 252 Sqm 4650 1171800 condition it is
having make ESSAR. Panel Colour RAL 9002 excuted
with a Supporting structure in MS
rectangular pipes 96x48x3mm thick, Make
:-JINDAL Ground Floor & First Floor
Sub-Total:- 3286479

Electrical Work
Supply and Laying of P.V.C casing and caping
(ISI MARK) with double locking arrangments As per site
1 with groover trunking of size not below 400 Rm 50.00 20000 condition it is
12.5mm height 25mm size with all
accessories, duly sealed at points and excuted
erected on Wall / Ceiling including cost of all
materials and labour charges complete.
Makes
Supply: and
ModiFixing
with ISIof ISI 25mm outer dia
medium grade with IS:9537 part 3 regid As per site
2 PVC pipe surface on wall/ceiling with all 1125 Rm 65.00 73125 condition it is
required saddles and all accessories and excuted
labour charges etc., complete for run of
mains.
Supply
Makes :and fixing of/ Finolex
Sudhakar 6A switchs - 2/ VIP
/ Modi Nos /
and 6A 3/2
Precision pin socket
/ Universal - 2 Nos
/ Million Modular
Plast As per site
3 type with front cover plate including all 176 Pts 783.00 137808 condition it is
labour charges etc., complete. excuted
Makes : Legrand Arteor / Schneider Zen
celo / Honeywell Blenge Plus / Cabtree
Amare / Logus Platina.(Including 3of
4Sqmm &
Supply 2.0fixing
Rmt) of 16A/6A, 2 in one
socket - 2 Nos with 16A switch control - As per site
4 2 Nos modular type with front cover 688 No's 901.00 619888 condition it is
plate including all labour charges etc., excuted
complete.
Makes : Legrand Arteor / Schneider Zen
celo / Honeywell Blenge Plus / Cabtree
Amare / Logus Platina.(Including 3of
4Sqmm 2.0 Rmt) Page 92 of 204
Supply and 3 runs of 4.0 sq mm (56/0.3
mm) (phase neutral and earth) FRLS / As per site
5 HFFR PVC insulated flexible copper
3713 Rm 136.00 505014 condition it is
cable in existing conduit pipe including excuted
labour charges etc., complete for 16A
sockets.
Supply
Makes of& wires
run :ofFinolex
5 of /10.0 Sqmm/
RR kabel
(84/0.3mm) (3 phases, neutral
Havells / APAR EBXL / KEI / Polycab and earth)/ As per site
6 FRLS / HFFR
V-Guard / MILLION PVC insulated flexible 120 Rm 442.00 53040 condition it is
copper cable in the existing conduict pipe excuted
for run of mains from Power panel board
to TPN DB"s with pin type lugs and
connections
Supply and etc.,
fixingcomplete.
of 12 Way [for TPN
PDBs]DB
Makes
Horizontal with IP 43 Protection kabel
of wires :Finolex / RR as per/ As per site
7 Havells
IS:13032 with 1 No., of 63A 10KA FP/ 4
/ APAR EBXL / KEI / Polycab No's 20516.00 82064 condition it is
V-Guard
MCB as /incomer
MILLIONand 36 Nos 6-32 A excuted
10kA SP MCBs as out goings including
internal connections and labour charges
Supply
for FLUSHand Mounting
fixing of etc.,
8 Way VTPN for
complete DB
with As per site
DBs.IP 43 Protection with 1 No., of 125A
8 TPN to 2 No's 33165.00 66330 condition it is
MakesMCCB,
: Legrand Adjustable,
/ SchneiderConfirms
/ L&T.
IS/IEC 60947-2 having Breaking excuted
Capacity 25 KA with thermal magnetic
release Panel Mounted as incomer with
Supply
8 Nos and fixing 10KA,
of 63A, of cableTP adopteres
MCBs C/D box
with cover As per site
Curve ISI Mark for DBsOut including,
as goings
9 massaNosry workconnections
etc., complete., 6 No's 600 3600 condition it is
including internal and labour
Makes excuted
charges: Legrand / Schneider.
etc., complete.
Makes : Legrand / Schneider / L&T.
Supply and Installation of 125 Amps 4P
MCCB with cable end boxes on suitable As per site
10 angle iron frame work for the areas 8 No's 14435.00 115480 condition it is
mentioned in the drawings including all excuted
Labours charges, massonry work etc.
complete for finished item of work.
Makes:Legrand
Supply of the/ Shneider
Following PVC XLPE As per site
11 armoured cable 1100 V Grade with ISI condition it is
mark stranded / solid, aluminimum excuted
conductor complete
3.5 Core: Torrent
Makes 70.00 Sq.mm.
/ Unicab / Polycab / 120 Rm 420.00 50400
Havells / Gloster / KEI / Finolex /
Paragon.
Laying of PVC armoured under ground
As per site
cable up to 95 Sqmm fixing on chromium 120
12 Rm 35.00 4200 condition it is
plated metallic base saddles on wall as
excuted
per IS 1255 and as directed by the
department including cost and
conveyance of all
LT CABLE TERMINATIONS: materials and labour
charges etc., complete.
Supply and Fixing of single compression As per site
13 brass cable glands for 3.5 core following condition it is
armoured cable with brass washers, excuted
lugs etc., complete.
70 Sq.mm 8 No's 319.00 2552

Supply, Transportation and fixing of 60 As per site


14 W / 65 W LED LED Street light, Body 10 No's 6559.00 65590 condition it is
made of high grade pressure die – cast excuted
Aluminium alloyV.P 39/ with
MB corrosion
No.540 resistant
powder coat, having protective
toughened glass cover, Less Glare, IP
Supply
66 (Silicon and gasket
transportation
ensures Optical of 48" & As per site
15 (1200mm)
Electrical Sweep decorativeare
compartments Ceiling
IP Fan66) 4 No's 8976.00 35904 condition it is
with all accessories
protected, etc., complete.
wide operating voltage range, excuted
Makes : Crompton
P.F > 0.90, SystemHigh havingSpeed Decora
efficacy >100/
Havells
lumens/watt, V.P with
Spark 39/ MBIngress
Deco No.540
/ Orient protection
Summer
Crown
IP66, / and
Supply Panasonic
Potted Sprint
fixingdriver,
of Deco
Driver/ Modular
2 Module Halonix
surge
Erbon
type Electronic
protection >10KV,step type Fan Regulator
THD<15%, CCT:
for sweep
3000- AC ceiling
6500K as fans
desiredof 1200mm
by the/ As per site
16 1420mm
department complete
and as withper IS, CRI>80, 4
connections. No's 502.00 2008 condition it is
Makes
Inbuilt :Electrical
Legrand Myrius / Million
protections likemway
Over/ excuted
Gold Medal
voltage, Curve
short / Anchor
circuit, Over Roma
load, viola
Open/
GM
Circuit,Four-Five
Miswiring, /etc Havells
complete Fabiowith BIS/
Panasonic
certificationVision / L&T Englaze
with warranty 50,000 /burning
Hager
Insista
hours. The/ Benlo Vesta / has
contractor C&StoPrimo
furnish/ CPL
the
Vysma / Polycab
manufacturer Levana.
warranty letter, LM 79Page and93 of 204
LM 80 certificates. and fixing of
luminaire on wall with 1.0Mt 40mm dia
V.P 39/ MB No.540
Labour charges for fixing of ceiling fan
17 4 No's 139.00 556
and regulator including transportation
and giving V.P
connections
39/ MB No.540with twin core
wire etc., complete.
Supply of 10 sqmm WPTC (Weather
Proof Twin Core) ISI Alluminium Wire. As per site
18 Makes : Polycab / GM / Million / V-Guard 600 Rmt 44.00 26400 condition it is
/ Gold Medal / Kundancab / HPL / RPG / excuted
Nandicab / V.P
Nakoda
39/ MB/ No.540
Payal / Finecab /
Gemini / Vimal / Suncab / Stanjo /
Supply and /fixing
Rajnigandha Orbit /ofAirson.
12 V 150 AH MF
battery including wire leads. Makes : As per site
Amar Raja (Power Zone) or Equivalent 4 No's 11500.00 46000 condition it is
model of Exide / Panasonic / Gotech excuted
SSR-1837
19
V.P 39/ MB No.540

Supply and Transportation of


-------------------- single phase ISI 1 No's 13770.00 13770
20 submersible motor pumpset suitable for
4" Bore well. V.PMakes:
80/ MB Varuna
No.538 / Flowell /
Waterman / Techno / Mahavir /unitek/
Supply and Ellen/
Fitwell/ Falcon/ Transportation
Karvel / LPS/ Duke of
…………………..
/ Varsha / Ajantha. double walled 30 Rm 119.00 3570
21 corrugated HDPE duct made as per
specificationV.P BSEN
81/ MB- No.538
500 86/IS 14930
Part-II with all accessories
Providing and errecting heat likeshrinkable
couplers,
bends, end caps, Ts etc.,
indoor termination kit for 11 KV HTXLPEcomplete. 2 Each 8599.00 17198
22 Makes:
insulatedDURA LINE (Dura
armoured Guard) / Bajaj
cable-------------with
/necessary
Gamson / UltraV.P Plus
82/ MB No.538
materials etc., complete.
Makes : Raychem / Transeal / M Sea
Servicing of L&T ACB 'S As per site
24 No's 5500.00 132000 condition it is
23 excuted
V.P 82/ MB No.538
Servicing of HT VCB'S As per site
5 No's 9000.00 45000 condition it is
24 excuted
V.P 83/ MB No.538
500 KVA DG SET at OPD Block As per site
1 Job 86375.00 86375 condition it is
25 excuted
V.P 82/ MB No.538
500 KVA DG SET at South Block As per site
1 Job 86000.00 86000 condition it is
26 excuted
V.P 85/ MB No.538
500 KVA DG SET at North Block As per site
1 Job 80475.00 80475 condition it is
27 excuted
V.P 78/ MB No.538

500 KVA DG Contrle Panel micropanel As per site


cip 3 Job 35000.00 105000 condition it is
excuted
Total 2479347

Page 94 of 204
CC 2nd & Part Bill
Name of the work: Providing Gas Supplying pipeline for Supplying and Centralized Medical Oxygen to bed for COVID-19
Management in Gandhi Hospital Secunderabab

Total Value to date Deduct/Previous Since last


Sl. No. Description of Work measurements measurements
Amount Amount Amount
Quantity Rate
(Rs.) Qty (Rs.) Qty (Rs.)
OXYGEN SYSTEM

A Medical Grade Copper Pipe with Required Copper


Fittings
Copper Pipe for Medical use with 12 OD X 1.0 mm
1 1635.5 Mtr 401 655836 1635.5 655836 0 0

Copper Pipe for Medical use with 15 OD X 1.0 mm


2 3956.2 Mtr 527 2084917 3956.2 2084917 0 0

Copper Pipe for Medical use with 22 OD X 1.0 mm


3 1608.5 Mtr 570 916845 1608.5 916845 0 0

Copper Pipe for Medical use with 28 OD X 1.0 mm


4 1505 Mtr 857 1289785 1505 1289785 0 0

B Gas Outlets double lock with probe


1 Oxygen outlets(Indeginous) as per HTM 2022 772 Nos 1535 1185020 772 1185020 0 0

2 Oxygen flowmeter complete with Humidifier bottle 772 Nos 1025 791300 772 791300 0 0

C OUTLETS FOR AIR & VACUUM


1 Isolation Valve for 15 mm Copper Pipe 106 Nos 1100 116600 106 116600 0 0

Page 95 of 204
2 Isolation Valve for 22 mm Copper Pipe 43 Nos 1714 73702 43 73702 0 0

3 Isolation Valve for 28 mm Copper Pipe 18 Nos 2785 50130 18 50130 0 0

3 Ward vacuum (out let) unit complete regulator 249 Nos 1714 426786 18 30852 231 395934

D OUTLETS FOR AIR & VACUUM

1 Vacuum outlets(Indeginous) -with Probes By 249 Nos 1535 382215 249 382215 0 0
considering 300 Beds for Oxygen and Vacuum

2 Air-4 bar outlets(Indeginous) with Probes by 249 Nos 1535 382215 249 382215 0 0
considering 100 beds with Oxygen, Air and Vacuum
F Compressed Air System
Compressed Air System Consisting of 2 nos
(Reciprocating & oil free), each having 15 HP Motor
with 57.18 cfm capacity at 8.5Kg/cm2 pressure with
common receiver of Capacity 1000 ltrs, common Air
drier, Pressure Reducing Unit etc.
1 3-Stage Breathing Air Filter for 125 CFM as per ISO 1 Nos 1114554 1114554 1 1114554 0 0
8573-1

SITC of Electrical Control panel should be automatic


change over panel for changeover from A to B and
then from B to A and then from B to C. If any pump
trips then the second should start automatically.
The panel should consist of contactors Amp meter,
Volt meter, Single phase protector, MCB, phase
2 indicator, compressor on –off trip indicator and
1 Nos 303450 303450 1 303450 0 0
pressure switch .

Page 96 of 204
G Vacuum System
2 nos. of Ingersoll Rand make Model 15V x 10 Model
with 7.5 HP Motor with 1000 litres Receiver, Filters,
1 Electricals, etc. 1 Nos 941640 941640 1 941640 0 0
Secretion Trap and bacteria filter

J Bed Head Panel.


bed Head Panel : The bed Head Panel should have
1 provision for Medical Gas outlet & electrical sockets 249 Nos 7069 1760181 249 1760181 0 0
for 2+2

Sub-Total:- 12475176 12079242 231 395934

Electrical Work
Supply & fixing of 16A/6A, 2 in one socket - 2
Nos with 16A switch control - 2 Nos modular
1 type with and GI switch box with front cover 498 Rm 721.00 359058 498 359058 0 0
plate including all labour charges etc., complete.

Makes : Legrand Arteor / Schneider Zen celo /


Supply
Honeywell andBlenge
3 runs of /4.0
Plus sq mm
Cabtree (56/0.3
Amare mm)
/ Logus
2 (phase
Platina. neutral and earth) FRLS / HFFR PVC 1200 Rm 109.00 130800 1200 130800 0 0
insulated flexible copper cable in existing
conduit pipe including labour charges etc.,
complete
Supply and forLaying
16A sockets.
of P.V.C casing and caping
3 Makes
(ISI MARK)of wires :Finolexlocking
with double / RR arrangments
kabel / Havells with/ 400 Rm 26.00 10400 400 10400 0 0
APAR EBXL
groover / KEI
trunking of /size
Polycab / V-Guard
not below 12.5mm/
MILLION
height 25mm size with all accessories, duly
sealed at points and erected on Wall / Ceiling
Supply
includingandcost ofFixing of High and
all materials pressure
labour Vacume
charges 311.25
4 with all requrested completed of work including Rm 92.00 28635 311.25 28635 0 0
complete. Makes : Modi with ISI
cost and convency of matriel complet of work.

Page 97 of 204
Supply and Fixing of Low pressure Vacume
5 with all requrested completed of work including 311.25 Rm 97.00 30191 311.25 30191 0 0
cost and convency of matriel complet of work.

Copper Pipe for Medical use with 42mm OD X 1.0


6 mm 265 Each 1199.00 317735 265 317735 0 0
Copper Pipe for Medical use with 54mm OD X 1.0
7 mm 330 Each 2016.00 665280 330 665280 0 0

Isolation Valve for 42 mm Copper Pipe


8 12 Each 2798.00 33576 12 33576 0 0

Supply and Fixing of ISI 25mm outer dia


medium grade with IS:9537 part 3 regid PVC
9 1125 Rm 52.00 58500 1125 58500 0 0
pipe surface on wall/ceiling with all required
saddles and all accessories and labour charges
etc., complete for run of mains.
Makes : Sudhakar
Supply and / Finolex
fixing of 6A switchs /- 2Modi
Nos / and
VIP6A/
Precision / Universal / Million Plast
3/2 pin socket - 2 Nos Modular type with front
10 176 Pts 626.00 110176 176 110176 0 0
cover plate including all labour charges etc.,
complete.
Makes : Legrand Arteor / Schneider Zen celo /
Supply & fixing
Honeywell Blenge of Plus
16A/6A, 2 in one
/ Cabtree Amare socket - 2
/ Logus
11 Nos with 16A switch
Platina.(Including control2.0
3of 4Sqmm - 2Rmt)
Nos modular 190 No's 721.00 136990 190 136990 0 0
type with front cover plate including all labour
charges etc., complete.
Makes : Legrand Arteor / Schneider Zen celo /
Honeywell
Supply andBlenge
3 runs Plus
of /4.0
Cabtree
sq mm Amare
(56/0.3
/ Logus
mm)
12 Platina.(Including
(phase neutral and 3of earth)
4SqmmFRLS 2.0 Rmt)/ HFFR PVC 2513.34 Rm 109.00 273954 2513.34 273954 0 0
insulated flexible copper cable in existing
conduit pipe including labour charges etc.,
complete for 16A sockets.
Makes
Supply of wires
& run of :5Finolex
of 10.0 / Sqmm
RR kabel / Havells(3/
(84/0.3mm)
13 APAR
phases, neutral and earth) FRLS / HFFR PVC/ 120
EBXL / KEI / Polycab / V-Guard Rm 354.00 42480 120 42480 0 0
MILLION
insulated flexible copper cable in the existing
conduict pipe for run of mains from Power panel
board to TPN DB"s with pin type lugs and
connections etc., complete. [for PDBs]
Makes of wires :Finolex / RR kabel / Havells /
APAR EBXL / KEI / Polycab / V-Guard / Page 98 of 204
MILLION
Supply and fixing of 12 Way TPN DB Horizontal
14 with IP 43 Protection as per IS:13032 with 1 No., 4 No's 16413.00 65652 4 65652 0 0
of 63A 10KA FP MCB as incomer and 36 Nos 6-
32 A 10kA SP MCBs as out goings including
internal connections and labour charges for
Supply
FLUSH and fixing etc.,
Mounting of 8 complete
Way VTPN forDB with IP 43
DBs.
15 Protection with 1/ Schneider
Makes : Legrand No., of 125A
/ L&T. TPN MCCB, 2 No's 265322.00 530644 2 530644 0 0
Adjustable, Confirms to IS/IEC 60947-2 having
Breaking Capacity 25 KA with thermal magnetic
release Panel Mounted as incomer with 8 Nos
Supply
of 63A, and fixing
10KA, TP of cable
MCBs C/Dadopteres
Curve ISIbox
Markwith
cover for DBs including, massaNosry work
as Out goings including internal connections etc.,
16 complete., 6 No's 480 2880 6 2880 0 0
and labour charges etc., complete.
Makes
Makes :: Legrand
Legrand // Schneider.
Schneider / L&T.

Supply and Installation of 125 Amps 4P MCCB


with cable end boxes on suitable angle iron
17 8 No's 11548.00 92384 8 92384 0 0
frame work for the areas mentioned in the
drawings including all Labours charges,
massonry work etc. complete for finished item of
work.
SupplyMakes:Legrand / Shneider
of the Following PVC XLPE armoured
18 cable 1100 V Grade with ISI mark stranded /
solid, aluminimum conductor complete
Makes
3.5 Core : Torrent / Unicab / Polycab / Havells /
70.00 Sq.mm. 120 Rm 336.00 40320 120 40320 0 0
Gloster / KEI / Finolex / Paragon.
Laying of PVC armoured under ground cable up
19 to 95 Sqmm fixing on chromium plated metallic 120 Rm 28.00 3360 120 3360 0 0
base saddles on wall as per IS 1255 and as
directed by the department including cost and
conveyance of all materials and labour charges
LT
etc.,CABLE TERMINATIONS:
complete.
Supply and Fixing of single compression brass
cable glands for 3.5 core following armoured
20 cable with brass washers, lugs etc., complete.

70 Sq.mm 8 No's 255.00 2040 8 2040 0 0


Electrical Sub Total:- 2935055 2935055 0

Page 99 of 204
Civil Work

Dismantling, clearing away and carefully stacking


useful materials for re-use and disposal of
1 unserviceable materials with 100m lead as directed
by Executive Engineer duly taking actual
premeasurements before dismantling including all
Unreinforced
labour charges cement concrete
, overheads up profit
& contractor to 15cm
etc., 2.16 Cum 2763 5968 2.16 5968 0 0
thickness
complete

Earth work excavation for foundations (Manual


Means) of buildings, septic tank, sump,
2 compound wall in ordinary soils and depositing on 4.5 Cum 206 927 4.5 927 0 0
bank with an initial lead of 10m and 1m additional
lift charges over the initial depth up to 3m
including all operational,incidental, labour charges
such
Supply as and
shoring, sheeting,
placing of the planking,
Design Mix strutting etc.,
Concrete
and overheads & contractors profit
M 25 grade corresponding to IS 456 with minimum complete for
3 finished item of work excluding dewatering charges
cement content of 380 kgs per 1 cum of concrete
etc.,
usingasConcrete
per SS 20 Batching
B(APSS 308) Plant with 20mm size
graded machine crushed hard granite metal (coarse 4.26 Cum 9564 40743 4.26 40743 0 0
aggregate - as per IS 383 - 1970 and IS 2386 Part 1
to Part 8) from approved quarry including cost and
Supply
conveyanceand of Fixing
all of drilling holes
materials to concreate
like cement, fine
4 aggregate
including (sand) coarse
cost and aggregate,
convency water etc.,
of matriel to site
complet 120 Each 52 6240 120 6240 0 0
and sales & other taxes on all materials , centering
of work.
using Steel scaffolding pipes , jack props , wallers ,
Foot plates , brackets , steel centering plates etc.,
including and
Supply all operational, incidentalbolts
Fixing of Anchor andwith
labourall
charges
requrested such as weighofbatching,
completed machinecost
work including mixing,
and
5 120 Each 80 9600 120 9600 0 0
laying
convency concrete, curing
of matriel etc.,of and
complet work.overheads &
contractors profit complete but excluding cost of steel
and its fabrication charges for finished item of work
(APSS
SupplyNo. and402).
Fixing of Nutbolts with all requrested
6 completed of work including cost and convency 58 Each 48 2784 58 2784 0 0
of matriel complet of work.

Page 100 of 204


Painting two coats with synthetic enamel paint
Gr-II having VOC (Volatile Organic Compound) 69.76
7 Sqm 142 9906 69.76 9906 0 0
content less than 50 grams/litre to old iron work
including cost and conveyance of all materials to site,
sales & other taxes, incidental, operational and all
labour charges and overheads & contractors profit
Supply and fixing
etc., complete of 60mm
for finished itemthick wallinpanelling,
of work all floors.
8 Having materials
(SS No. 1201, 1212 &0.5mm
1207). thick PPGI on Both 242.88 Sqm 3720 903514 0 242.88 903514
Sides of the panel.Puff as infilling with Density
40± 2kg/Cu. Mtr.Panel having make ESSAR. Panel
Colour RAL 9002 with a Supporting structure in MS
Supplying and
rectangular pipesfabricating,
96x48x3mmerecting and fixing
thick, Make :-JINDALin
9 Ground Floor & First Floor
position tabular trusses of approved design with 5151.5 Kg 112 576968 3816.31 427427 1335.19 149541
M.S tube conforming to I.S-1161 specifications
including roof frame work consisting of
rafters,ties struts and purlins including cost of
foundations bolts, cleats, Sub-Total:-
bearings 1556650 503595 1053055
plates,etc.,complete as per the sketch Grand Total:-
enclosed 16966881 15517892 1448989
and including cost of primary coat Add with red
GST12%oxide 2036026 1862147 173879
paint including cost and conveyance of
Grand Total:- all 19002907 17380039 1622868
materials, labour charges for erecting & fixing all
structural steel works erecting in position and
fixing by using chain pulley blocks, Derek pole
arrangements and cranes etc., complete in
position, labour charges for fabrication, all
incidental charges, overheads and contractor
profit etc., complete for finished item of work as
directed by the Engineer-in-Charge

Page 101 of 204


Electrical Datas 2019-20

S.No SSR No Description Qty Unit Rate Amount

CONDUIT PIPE
1 Supply and Laying of ISI 25mm outer dia heavy grade with IS:9537 part 3 regid PVC pipe concealed
in Roof Slabs with all required PVC / Metallic Deep Boxes including masonary work and labour charges
etc., complete. Makes : Sudhakar / Finolex / Modi / VIP / Precision / Universal / Million Plast / Gold /
Polycab / DEC.

a) Labour charges :
1 Skilled Electrician. 2.00 day 1 day 565.00 1130.00
2 Lineman / Semi Skilled Electrician. 2.00 day 1 day 470.00 940.00
3 Helper (Electrical). 2.00 day 1 day 470.00 940.00
Labour Rate Per 100 Rm 3010.00
Labour Rate for 1 Mtr 30.10
b) Material
1.2.1 Supply of ISI 25mm outer dia heavy 100.00 Mtr 1 Mtr 33.00 3300.00
b) grade FRLS with IS:9537 part 3 regid
PVC pipe.
1.2.6 b) Supply of PVC Junction Boxes Deep 12.00 Nos 1 Nos 26.00 312.00
size 25mm.

1.2.7 b) Supply of 25mm dia PVC Bends. 12.00 Nos 1 Nos 8.00 96.00

Material Rate for 100 Mtrs 3708.00


Material Rate for 1 Mtr 37.08
Total Cost of Material + Labour
67.20
Charges
Add Contractors Profit 0.000% 0.00
67.20
Rate per Meter 67.00

2 Supply and Laying of ISI 20mm outer dia heavy grade with IS:9537 part 3 regid PVC pipe concealed
in Roof Slabs with all required PVC / Metallic Deep Boxes including masonary work and labour charges
etc., complete. Makes : Sudhakar / Finolex / Modi / VIP / Precision / Universal / Million Plast / Gold /
Polycab / DEC.
a) Labour charges :
1 Skilled Electrician. 2.00 day 1 day 565.00 1130.00
2 Lineman / Semi Skilled Electrician. 2.00 day 1 day 470.00 940.00
3 Helper (Electrical). 2.00 day 1 day 470.00 940.00
Labour Rate Per 100 Rm 3010.00
Labour Rate for 1 Mtr 30.10
b) Material
1.2.1 a) Supply of ISI 20mm outer dia heavy 100.00 Mtr 1 Mtr 25.00 2500.00
grade FRLS with IS:9537 part 3 regid
PVC pipe.
1.2.6 a) Supply of PVC Junction Boxes Deep 12.00 Nos 1 Nos 23.00 276.00
size 20mm.
1.2.7 a) Supply of 20mm dia PVC Bends. 12.00 Nos 1 Nos 6.00 72.00

Material Rate for 100 Mtrs 2848.00


Material Rate for 1 Mtr 28.48
Total Cost of Material + Labour 58.50
Charges
Add Contractors Profit 0.000% 0.00
58.50
Rate per Meter 59.00

3 Supply and laying of ISI 25mm outer dia medium grade with IS:9537 part 3 regid PVC pipe concealed
in wall with all required PVC / Metallic Junction Boxes including masonary work and labour charges
etc., Makes : Sudhakar / Finolex / Modi / VIP / Precision / Universal / Million Plast / Gold / Polycab /
DEC.
a) Labour charges :
1 Skilled Electrician. 2.00 day 1 day 565.00 1130.00
2 Lineman / Semi Skilled Electrician. 2.00 day 1 day 470.00 940.00
3 Helper (Electrical). 2.00 day 1 day 470.00 940.00

Page 102 of 204


S.No SSR No Description Qty Unit Rate Amount

4 Mason Cl- I / Brick layer Cl- I 2.00 day 1 day 500.00 1000.00
Labour Rate Per 100 Rm 4010.00
Labour Rate for 1 Mtr 40.10
b) Material
1.2.2 b) Supply of ISI 25mm outer dia medium 100.00 Mtr 1 Mtr 24.00 2400.00
grade FRLS with IS:9537 part 3 regid
PVC pipe.

9.4.11 Cement. 50.00 kg 1 Kg 8.00 400.00


9.1.4 U Nails. 200.00 Nos 100 Nos 32.00 64.00
1.2.5 b) Supply of 25mm PVC Junction Boxes 12.00 Nos 1 Nos 20.00 240.00
Normal.
1.2.7 b) Supply of 25mm dia PVC Bends. 12.00 Nos 1 Nos 8.00 96.00
Material Rate for 100 Mtrs 3200.00
Material Rate for 1 Mtr 32.00
Total Cost of Material + Labour 72.10
Charges Add Contractors Profit 0.000% 0.00
72.10
Rate per Meter 72.00

4 Supply and laying of ISI 20mm outer dia medium grade with IS:9537 part 3 regid PVC pipe concealed
in wall with all required PVC / Metallic Junction Boxes including masonary work and labour charges
etc., Makes : Sudhakar / Finolex / Modi / VIP / Precision / Universal / Million Plast / Gold / Polycab /
DEC.
a) Labour charges :
1 Skilled Electrician. 2.00 day 1 day 565.00 1130.00
2 Lineman / Semi Skilled Electrician. 2.00 day 1 day 470.00 940.00
3 Helper (Electrical). 2.00 day 1 day 470.00 940.00
4 Mason Cl- I / Brick layer Cl- I 2.00 day 1 day 500.00 1000.00
Labour Rate Per 100 Rm 4010.00
Labour Rate for 1 Mtr 40.10
b) Material
1.2.2 a) Supply of ISI 20 mm outer dia medium 100.00 Mtr 1 Mtr 18.00 1800.00
grade FRLS with IS:9537 part 3 regid
PVC pipe.
9.4.11 Cement. 50.00 kg 1 Kg 8.00 400.00
9.1.4 U Nails. 200.00 Nos 100 Nos 32.00 64.00
1.2.5 a) Supply of 20mm PVC Junction Boxes 12.00 Nos 1 Nos 19.00 228.00
Normal.
1.2.7 a) Supply of 20mm dia 1.5mm thick PVC 12.00 Nos 1 Nos 6.00 72.00
Bends.
Material Rate for 100 Mtrs 2564.00
Material Rate for 1 Mtr 25.64
Total Cost of Material + Labour 65.70
Charges
Add Contractors Profit 0.000% 0.00
65.70
Rate per Meter 66.00

5 Supply and Laying of ISI 32mm outer dia medium grade with IS:9537 part 3 regid PVC pipe concealed
in walls with all required PVC / Metallic Deep Boxes including masonary work and labour charges etc.,
complete. Makes : Sudhakar / Finolex / Modi / VIP / Precision / Universal / Million Plast / Gold /
Polycab / DEC.
a) Labour charges :
a) Labour charges :
1 Skilled Electrician. 2.00 day 1 day 565.00 1130.00
2 Lineman / Semi Skilled Electrician. 2.00 day 1 day 470.00 940.00
3 Helper (Electrical). 2.00 day 1 day 470.00 940.00
4 Mason Cl- I / Brick layer Cl- I 2.00 day 1 day 500.00 1000.00
Labour Rate Per 100 Rm 4010.00
Labour Rate for 1 Mtr 40.10
9.4.11 Cement. 50.00 kg 1 Kg 8.00 400.00
9.1.4 U Nails. 200.00 Nos 100 Nos 32.00 64.00
1.2.5 c) Supply of 32mm PVC Junction Boxes 12.00 Nos 1 Nos 35.00 420.00
Normal.

Page 103 of 204


S.No SSR No Description Qty Unit Rate Amount

1.2.8 c) Supply of 32mm dia 2.0 mm thick PVC 12.00 Nos 1 Nos 18.00 216.00
Bends.
1.2.2 c) Supply of ISI 32 mm outer dia medium 100.00 Mtr 1 Mtr 39.00 3900.00
grade FRLS with IS:9537 part 3 regid
PVC pipe.
Material Rate for 100 Mtrs 5000.00
Material Rate for 1 Mtr 50.00
Total Cost of Material + Labour 90.10
Charges
Add Contractors Profit 0.000% 0.00
90.10
Rate per Meter 90.00

6 Supply and Fixing of ISI 25mm outer dia medium grade with IS:9537 part 3 regid PVC pipe surface on
wall/ceiling with all required saddles and all accessories and labour charges etc., complete for run of
mains. Makes : Sudhakar / Finolex / Modi / VIP / Precision / Universal / Million Plast / Gold / Polycab /
DEC.
a) Labour charges :
1 Skilled Electrician. 2.00 day 1 day 565.00 1130.00
2 Lineman / Semi Skilled Electrician. 2.00 day 1 day 470.00 940.00
3 Helper (Electrical). 2.00 day 1 day 470.00 940.00
Labour Rate Per 100 Rm 3010.00
Labour Rate for 1 Mtr 30.10
b) Material
9.1.2 Rawl Plugs. 200.00 Nos 100 Nos 33.00 66.00
1.4.4 d) Supply of No.8 Screws of 35/38mm. 200.00 Nos 100 Nos 100.00 200.00
9.4.11 (SoR-2016-17-TBSE-1.4.23)
Cement. 5.00 kg 1 Kg 8.00 40.00
1.1.11 b) Supply of 25mm Saddles with Base. 200.00 Nos 100 Nos 210.00 420.00

1.2.5 b) Supply of 25mm PVC Junction Boxes 12.00 Nos 1 No 20.00 240.00
Normal.
1.2.7 b) Supply of 25mm dia 1.5mm thick PVC 12.00 Nos 1 No 8.00 96.00
Bends.
1.2.2 b) Supply of ISI 25mm outer dia medium 100.00 Mtr 1 Mtr 24.00 2400.00
(1.80mm thickness) grade FRLS with
IS:9537 part 3 regid PVC pipe.

Material Rate for 100 Mtrs 3462.00


Material Rate for 1 Mtr 34.62
Total Cost of Material + Labour 64.70
Charges
Add Contractors Profit 0.000% 0.00
64.70
Rate per Meter 65.00

7 Supply and Laying of P.V.C casing and caping (ISI MARK) with double locking arrangments with
groover trunking of size not below 12.5mm height 25mm size with all accessories, duly sealed at points
and erected on Wall / Ceiling including cost of all materials and labour charges complete. Makes : Modi
with ISI
a) Labour charges :
1 Skilled Electrician. 1.00 day 1 day 565.00 565.00
2 Lineman / Semi Skilled Electrician. 1.00 day 1 day 470.00 470.00
3 Helper (Electrical). 2.00 day 1 day 470.00 940.00
Labour Rate Per 100 Rm 1975.00
Labour Rate for 1 Mtr 19.75
b) Material
1.2.4 b)
Supply of 25mm width and 12.5mm
SoR-18-19 100.00 Rm 1 Rm 30.00 3000.00
height Casing and Caping.
Material Rate for 100 Mtrs 3000.00
Material Rate for 1 Mtr 30.00
Total Cost of Material + Labour 49.70
Charges
Add Contractors Profit 0.000% 0.00
49.70
Rate per Meter 50.00

Page 104 of 204


S.No SSR No Description Qty Unit Rate Amount

8 Supply and erecting PVC / GI / MS Galvanished fan hook box with hook in RCC slab including all
Labour charges etc., complete.
a) Labour charges :
1 Skilled Electrician. 0.03 day 1 day 565.00 16.95
2 Helper (Electrical). 0.03 day 1 day 470.00 14.10
Labour for 1 No 31.05
a) Material
9.1.22 PVC/ MS with hook in RCC Fan hook each 1 1 Nos 103.00 103.00

134.05
1.2.6 b) PVC Box ( LESS COST OF DEEP each 1 1 Nos 26.00 26.00
BOX )
Rate 108.05
Add Contractors Profit 0.000% 0.00
Rate per Each 108.00
8a Supply and erecting MS plain rod fan hook in RCC slab including all Labour charges etc., complete.

a) Labour charges :

1 Skilled Electrician. 0.03 day 1 day 565.00 16.95

2 Helper (Electrical). 0.03 day 1 day 470.00 14.10

Labour for 1 No 31.05


a) Material
9.1.20 MS plain rod fan hook each 1 1 Nos 32.00 32.00

Rate 63.05
Add Contractors Profit 0.000% 0.00

Rate per Each 64.00

Wiring, Switches and Sockets with 1st Grade Rate


Point wiring in Non Residential Building
9 Wiring with 2 runs of 22/0.3mm ( 1.5 Sq.mm) FRLS / HFFR P.V.C. insulated flexible copper cable (ISI
MARK) in existing pipe with 6A Modular switch, Ceiling rose/BH/SBH Modular switches with cover
plate and GI switch box including all labour charges etc., complete. (for Non-Residential Building)
Makes of wires : Finolex / RR kabel / Havells / APAR EBXL / KEI (HFFR) / Polycab ((HR_FR-LF) / L&T /
V-Guard (HFFR).
Makes of switches: Legrand Arteor / Schneider Zen celo / Honeywell Blenge Plus / Cabtree Amare /
Logus Platina.

a) Labour charges :
1 Skilled Electrician. 0.60 day 1 day 565.00 339.00
2 Lineman Electric / Telephone 1.20 day 1 day 470.00 564.00
3 Helper (Electrical). 0.60 day 1 day 470.00 282.00
Labour for 6 Points 1185.00
Labour for 1 Point 197.50
b) Material
1.3.1 b) Supply of 3 Module box. 2 Nos 1 No 80.00 160.00
1.3.2 b) Supply of 3 Modular Cover Frame. 2 Nos 1 No 76.00 152.00
1.9.1 b) Supply of 6A / 10A 1 Way 1 Module 6 Nos 1 No 88.00 528.00
Modular Switch.
1.7.1 m) Supply of 3 Plate Jumbo Ceiling Rose. 6 Nos 1 No 19.00 114.00
1.5.1 a) Supply of 22/0.3mm (1.5 Sqmm) 100.00 Mtrs 100 Mtrs 1510.00 1510.00
FRLS / HFFR PVC insulated 1100V
grade as perIS:694/1990 specification
for Copper cable.

Cost of Material for 6 Points 2464.00


Cost of Material Rate per 1 Point 410.67
Total Cost of Material + Labour 608.00
Charges

Page 105 of 204


S.No SSR No Description Qty Unit Rate Amount

Add Contractors Profit 0.000% 0.00


608.00
Rate per Each 608.00

Point wiring in Residential Building


10 Wiring with 2 runs of 22/0.3mm ( 1.5 Sq.mm) FRLS / HFFR P.V.C. insulated flexible copper cable (ISI
MARK) in existing pipe with 6A Modular switch, Ceiling rose/BH/SBH Modular switches with cover
plate and GI switch box including all labour charges etc., complete. (for Non-Residential Building)
Makes of wires : Finolex / RR kabel / Havells / APAR EBXL / KEI (HFFR) / Polycab ((HR_FR-LF) / L&T /
V-Guard (HFFR).
Makes of switches: Legrand Arteor / Schneider Zen celo / Honeywell Blenge Plus / Cabtree Amare /
Logus Platina.

a) Labour charges :
1 Skilled Electrician. 0.70 day 1 day 565.00 395.50
2 Lineman Electric / Telephone 1.40 day 1 day 470.00 658.00
3 Helper (Electrical). 0.70 day 1 day 470.00 329.00
Labour for 6 Points 1382.50
Labour for 1 Point 197.50
b) Material
1.3.1 b) Supply of 3 Module box. 1 Nos 1 No 80.00 80.00
1.3.1 c) Supply of 4 Module box. 1 Nos 1 No 95.00 95.00
1.3.2 b) Supply of 3 Modular Cover Frame. 1 Nos 1 No 76.00 76.00
1.3.2 c) Supply of 4 Modular Cover Frame. 1 Nos 1 No 88.00 88.00

1.9.1 a) Supply of 6A / 10A 1 Way 1 Module 7 Nos 1 No 88.00 616.00


Modular Switch.
1.7.1 m) Supply of 3 Plate Jumbo Ceiling Rose. 7 Nos 1 No 19.00 133.00
1.5.1 a) Supply of 22/0.3mm (1.5 Sqmm) 100.00 Mtrs 100 Mtrs 1510.00 1510.00
FRLS / HFFR PVC insulated 1100V
grade as perIS:694/1990 specification
for Copper cable.

Cost of Material for 7 Points 2598.00


Cost of Material Rate per 1 Point 371.14
Total Cost of Material + Labour 568.00
Charges
Add Contractors Profit 0.000% 0.00
568.00
Rate per Each 568.00

Common Socket
11 Supply and fixing of 6A ISI Mark 3/2 pin Modular socket with 6A 1way Modular switch, 3 Module box
with cover frame and GI switch box on common switch board with connections etc., complete.
Makes: Legrand Arteor / Schneider Zen celo / Honeywell Blenge Plus / Cabtree Amare / Logus Platina.

a) Labour charges :
1 Skilled Electrician. 0.067 day 1 day 565.00 37.86
2 Helper (Electrical). 0.067 day 1 day 470.00 31.49
Labour for 1 Point 69.35
b) Material
1.3.1 b) Supply of 3 Module box. 1 No 1 No 80.00 80.00
1.3.2 b) Supply of 3 Modular Cover Frame. 1 No 1 No 76.00 76.00
1.9.1 a) Supply of 6A / 10A 1 Way 1 Module 1 No 1 No 88.00 88.00
Modular Switch.
1.9.1 d) Supply of 6A / 10A 3/2 Pin 2 Module 1 No 1 No 135.00 135.00
Modular Socket with shutter.

Cost of Material Rate per 1 Point 379.00


Total Cost of Material + Labour 448.00
Charges
Add Contractors Profit 0.000% 0.00
448.00
Rate per Each 448.00

Page 106 of 204


S.No SSR No Description Qty Unit Rate Amount

Separate Socket
12 Wiring with 3 of 22/0.3mm ( 1.5 Sq.mm) FRLS / HFFR P.V.C. insulated flexible copper cable (ISI
MARK) in existing pipe with 6A switch and 6A, 3/2 pin socket Modular type with 6A switch control and
MS boxes with cover plate and GI switch box fixing on separate board including all labour charges
etc., complete.
Makes of wires : Finolex / RR kabel / Havells / APAR EBXL / KEI (HFFR) / Polycab ((HR_FR-LF) / L&T /
V-Guard (HFFR).
Makes of switches: Legrand Arteor / Schneider Zen celo / Honeywell Blenge Plus / Cabtree Amare /
Logus Platina.
a) Labour charges :
1 Skilled Electrician. 1.50 day 1 day 565.00 847.50
2 Lineman Electric / Telephone 1.50 day 1 day 470.00 705.00
3 Helper (Electrical). 1.50 day 1 day 470.00 705.00
Labour for 15 Points 2257.50
Labour for 1 Point 150.50
b) Material
1.3.1 b) Supply of 3 Module box. 15 Nos 1 No 80.00 1200.00
1.3.2 b) Supply of 3 Modular Cover Frame. 15 No 1 No 76.00 1140.00
1.9.1 a) Supply of 6A / 10A 1 Way 1 Module 15 No 1 No 88.00 1320.00
Modular Switch.
1.9.1 d) Supply of 6A / 10A 3/2 Pin 2 Module 15 No 1 No 135.00 2025.00
Modular Socket with shutter.
1.5.1 a) Supply of 22/0.3mm (1.5 Sqmm) 150.00 Mtrs 100 Mtrs 1510.00 2265.00
FRLS / HFFR PVC insulated 1100V
grade as perIS:694/1990 specification
for Copper cable.

Cost of Material for 15 Points 7950.00


Cost of Material Rate per 1 Point 530.00
Total Cost of Material + Labour 680.00
Charges
Add Contractors Profit 0.000% 0.00
680.00
Rate per Each 680.00

Page 107 of 204


S.No SSR No Description Qty Unit Rate Amount

6A Switches - 2 Nos & 6A Sockets - 2 Nos


13 Supply and fixing of 6A switchs - 2 Nos and 6A 3/2 pin socket - 2 Nos Modular type with cover plate
and GI switch box fixing on separate board including all labour charges etc., complete.
Makes : Legrand Arteor / Schneider Zen celo / Honeywell Blenge Plus / Cabtree Amare / Logus Platina.

a) Labour charges :
1 Skilled Electrician. 0.20 day 1 day 565.00 113.00
2 Helper (Electrical). 0.20 day 1 day 470.00 94.00
Labour for 1 No 207.00
b) Material
1.3.1 d) Supply of 6 Module box 1 No 1 No 130.00 130.00
1.3.2 d) Supply of 6 Modular Cover Frame. 1 Nos 1 No 130.00 130.00
1.9.1 a) Supply of 6A / 10A 1 Way 1 Module 2 Nos 1 No 88.00 176.00
Modular Switch.

1.9.1 d) Supply of 6A / 10A 3/2 Pin 2 Module 2 Nos 1 No 135.00 270.00


Modular Socket with shutter.
Cost of Material for 1 No 706.00
Total Cost of Material + Labour 913.00
Charges
Add Contractors Profit 0.000% 0.00
913.00
Rate per Each 913.00

6A Switches - 3 Nos & 6A Sockets - 3 Nos


14 Supply and fixing of 6A switchs - 3 Nos and 6A 3/2 pin socket - 3 Nos Modular type with cover plate
and GI switch box fixing on separate board including all labour charges etc., complete.
Makes : Legrand Arteor / Schneider Zen celo / Honeywell Blenge Plus / Cabtree Amare / Logus Platina.

a) Labour charges :
1 Skilled Electrician. 0.20 day 1 day 565.00 113.00
2 Helper (Electrical). 0.20 day 1 day 470.00 94.00
Labour for 1 No 207.00
b) Material
1.3.1 e) Supply of 8/9 Module box 1 No 1 No 170.00 170.00
1.3.2 e) Supply of 8/9 Modular Cover Frame. 1 Nos 1 No 170.00 170.00
1.9.1 a) Supply of 6A / 10A 1 Way 1 Module 3 Nos 1 No 88.00 264.00
Modular Switch.
1.9.1 d) Supply of 6A / 10A 3/2 Pin 2 Module 3 Nos 1 No 135.00 405.00
Modular Socket with shutter.
Cost of Material for 1 No 1009.00
Total Cost of Material + Labour 1216.00
Charges
Add Contractors Profit 0.000% 0.00
1216.00
Rate per Each 1216.00

6A Switches - 4 Nos & 6A Sockets - 4 Nos


15 Supply and fixing of 6A switchs - 4 Nos and 6A 3/2 pin socket - 4 Nos Modular type with cover plate
and GI switch box fixing on separate board including all labour charges etc., complete.
Makes : Legrand Arteor / Schneider Zen celo / Honeywell Blenge Plus / Cabtree Amare / Logus Platina.

a) Labour charges :
1 Skilled Electrician. 0.20 day 1 day 565.00 113.00
2 Helper (Electrical). 0.20 day 1 day 470.00 94.00
Labour for 1 No 207.00
b) Material
1.3.1 e) Supply of 12 Module box 1 No 1 No 205.00 205.00
1.3.2 e) Supply of 12 Modular Cover Frame. 1 Nos 1 No 210.00 210.00
1.9.1 a) Supply of 6A / 10A 1 Way 1 Module 4 Nos 1 No 88.00 352.00
Modular Switch.
1.9.1 d) Supply of 6A / 10A 3/2 Pin 2 Module 4 Nos 1 No 135.00 540.00
Modular Socket with shutter.
Cost of Material for 1 No 1307.00

Page 108 of 204


S.No SSR No Description Qty Unit Rate Amount

Total Cost of Material + Labour 1514.00


Charges
Add Contractors Profit 0.000% 0.00
1514.00
Rate per Each 1514.00
16 A Socket
16 Supply & fixing of 16A/6A, 2 in one socket with 16A switch control modular type with and GI switch box
with front cover plate including all labour charges etc., complete.
Makes : Legrand Arteor / Schneider Zen celo / Honeywell Blenge Plus / Cabtree Amare / Logus Platina.

a) Labour charges :
1 Skilled Electrician. 0.10 day 1 day 565.00 56.50
2 Helper (Electrical). 0.10 day 1 day 470.00 47.00
Labour for 1 No 103.50
b) Material
1.3.1 b) Supply of 3 Module box. 1 No 1 No 80.00 80.00
1.3.2 b) Supply of 3 Modular Cover Frame. 1 No 1 No 76.00 76.00
1.9.1 h) Supply of 16A / 20A 1 Way 1 Module 1 No 1 No 120.00 120.00
Modular Switch.
1.9.1 i) Supply of 16A/6A 1 way Combi Socket 1 No 1 No 188.00 188.00
Modular Socket with shutter.
Cost of Material for 1 No 464.00
Total Cost of Material + Labour 567.00
Charges
Add Contractors Profit 0.000% 0.00
567.00
Rate per Each 567.00

Page 109 of 204


S.No SSR No Description Qty Unit Rate Amount

16A Socket - 1 No & 6A Socket - 1 No


17 Supply and fixing of 1 No. of 6A / 10A 1 Way Modular Switch with 6A / 10A 3/2 Pin Modular Socket with
shutter & 1 No of 16A / 20A 1 Way Modular switch with 16A/6A 1 way Combi Modular Socket with
shutter on the suitable size Modular box with required cover frame including cost and conveyance of all
material and all labour charges etc., complete.
Makes : Legrand Arteor / Schneider Zen celo / Honeywell Blenge Plus / Cabtree Amare / Logus Platina.

a) Labour charges :
1 Skilled Electrician. 0.15 day 1 day 565.00 84.75
2 Helper (Electrical). 0.15 day 1 day 470.00 70.50
Labour for 1 No 155.25
b) Material
1.3.1 d) Supply of 6 Module box 1 No 1 No 130.00 130.00
1.3.2 d) Supply of 6 Modular Cover Frame. 1 Nos 1 No 130.00 130.00
1.9.1 a) Supply of 6A / 10A 1 Way 1 Module 1 Nos 1 No 88.00 88.00
Modular Switch.
1.9.1 d) Supply of 6A / 10A 3/2 Pin 2 Module 1 Nos 1 No 135.00 135.00
Modular Socket with shutter.
1.9.1 h) Supply of 16A / 20A 1 Way 1 Module 1 No 1 No 120.00 120.00
Modular Switch.
1.9.1 i) Supply of 16A/6A 1 way Combi Socket 1 No 1 No 188.00 188.00
Modular Socket with shutter.
Cost of Material for 1 No 791.00
Total Cost of Material + Labour 946.00
Charges
Add Contractors Profit 0.000% 0.00
946.00
Rate per Each 946.00

16A Socket - 2 Nos & 16A Switch - 2 Nos


18 Supply & fixing of 16A/6A, 2 in one socket - 2 Nos with 16A switch control - 2 Nos modular type with
and GI switch box with front cover plate including all labour charges etc., complete.
Makes : Legrand Arteor / Schneider Zen celo / Honeywell Blenge Plus / Cabtree Amare / Logus Platina.

a) Labour charges :
1 Skilled Electrician. 0.15 day 1 day 565.00 84.75
2 Helper (Electrical). 0.15 day 1 day 470.00 70.50
Labour for 1 No 155.25
b) Material
1.3.1 d) Supply of 6 Module box 1 No 1 No 130.00 130.00
1.3.2 d) Supply of 6 Modular Cover Frame. 1 Nos 1 No 130.00 130.00
1.9.1 h) Supply of 16A / 20A 1 Way 1 Module 2 Nos 1 No 120.00 240.00
Modular Switch.
1.9.1 i) Supply of 16A/6A 1 way Combi Socket 2 Nos 1 No 188.00 376.00
Modular Socket with shutter.
Cost of Material for 1 No 876.00
Total Cost of Material + Labour
1031.00
Charges
Add Contractors Profit 0.000% 0.00
1031.00
Rate per Each 1031.00

Run of Mains
19 Supply and run of 1 of 22 /0.3mm (1.5 Sq.mm) FRLS / HFFR P.V.C. insulated flexible copper cable in
existing conduit pipe for earth continuity including all labour charges etc., complete.
Makes of wires : Finolex / RR kabel / Havells / APAR EBXL / KEI (HFFR) / Polycab ((HR_FR-LF) / L&T /
V-Guard (HFFR).

a) Labour charges :
1 Skilled Electrician. 0.34 day 1 day 565.00 192.10
2 Lineman Electric / Telephone 0.70 day 1 day 470.00 329.00
3 Helper (Electrical). 0.34 day 1 day 470.00 159.80
Labour for 100 Mtr 680.90
Labour for 1 Mtr 6.81
b) Material

Page 110 of 204


S.No SSR No Description Qty Unit Rate Amount

1.5.1 a) Supply of 22/0.3mm (1.5 Sqmm) 100.00 Mtrs 100 Mtrs 1510.00 1510.00
FRLS / HFFR Copper cable.

Cost of Material for 100 Metres 1510.00


Cost of Material Rate per Mtr= C/100 15.10
Total Cost of Material + Labour 21.90
Charges
Add Contractors Profit 0.000% 0.00
21.90
Rate per Meter 22.00

20 Supply and run of 3 of 2.5 sq.mm (36/0.mm) (phase, neutral and earth) FRLS / HFFR PVC insulated
flexible copper cable in existing conduit pipe for individual lighting circuits including labour charges etc.,
complete as required for switch boards.
Makes of wires :Finolex / RR kabel / Havells / APAR EBXL / KEI (HFFR) / Polycab ((HR_FR-LF) / L&T /
V-Guard (HFFR).

a) Labour charges :
1 Skilled Electrician. 1.00 day 1 day 565.00 565.00
2 Lineman Electric / Telephone 2.50 day 1 day 470.00 1175.00
3 Helper (Electrical). 1.00 day 1 day 470.00 470.00
Labour for 100 Mtr 2210.00
Labour for 1 Mtr 22.10
b) Material
1.5.1 b) Supply of 36/0.3mm (2.5 Sqmm) 300.00 Mtrs 100 Mtrs 2440.00 7320.00
FRLS / HFFR Copper cable.
Cost of Material for 100 Metres 7320.00
Cost of Material Rate per Mtr= C/100 73.20
Total Cost of Material + Labour 95.30
Charges
Add Contractors Profit 0.000% 0.00
95.30
Rate per Meter 95.00

21 Supply and 3 runs of 4.0 sq mm (56/0.3 mm) (phase neutral and earth) FRLS / HFFR PVC insulated
flexible copper cable in existing conduit pipe including labour charges etc., complete for 16A sockets.
Makes of wires : Finolex / RR kabel / Havells / APAR EBXL / KEI (HFFR) / Polycab ((HR_FR-LF) / L&T /
V-Guard (HFFR).

a) Labour charges :
1 Skilled Electrician. 1.00 day 1 day 565.00 565.00
2 Lineman Electric / Telephone 3.00 day 1 day 470.00 1410.00
3 Helper (Electrical). 1.00 day 1 day 470.00 470.00
Labour for 100 Mtr 2445.00
Labour for 1 Mtr 24.45
b) Material
1.5.1 c) Supply of 56/0.3mm (4.0 Sqmm) 300.00 Mtrs 100 Mtrs 3725.00 11175.00
FRLS / HFFR Copper cable.
Cost of Material for 100 Metres 11175.00
Cost of Material Rate per Mtr= C/100 111.75
Total Cost of Material + Labour 136.20
Charges
Add Contractors Profit 0.000% 0.00
136.20
Rate per Meter 136.00

22 Supply and 3 runs of 6.0 sq mm (84/0.3mm) (phase neutral and earth) PVC FRLS / HFFR insulated
flexible copper cable in existing conduit pipe for AC's and SPNDB's including labour charges etc.,
Makes of wires : Finolex / RR kabel / Havells / APAR EBXL / KEI (HFFR) / Polycab ((HR_FR-LF) / L&T /
V-Guard (HFFR).
a) Labour charges :
1 Skilled Electrician. 1.00 day 1 day 565.00 565.00
2 Lineman Electric / Telephone 3.00 day 1 day 470.00 1410.00
3 Helper (Electrical). 1.00 day 1 day 470.00 470.00
Labour for 100 Mtr 2445.00
Labour for 1 Mtr 24.45
b) Material

Page 111 of 204


S.No SSR No Description Qty Unit Rate Amount

1.5.1 d) Supply of 84/0.3mm (6.0 Sqmm) FRLS/ 300.00 Mtrs 100 Mtrs 5700.00 17100.00
HFFR Copper cable.

Cost of Material for 100 Metres 17100.00


Cost of Material Rate per Mtr= C/100 171.00
Total Cost of Material + Labour 195.40
Charges
Add Contractors Profit 0.000% 0.00
195.40
Rate per Meter 195.00

23 Supply & run of 5 of 6.0 Sqmm (84/0.3mm) (3 phases, neutral and earth) FRLS / HFFR PVC insulated
flexible copper cable in the existing conduict pipe for run of mains from Power panel board to TPN DB"s
with pin type lugs and connections etc., complete. [for LDBs]
Makes of wires :Finolex / RR kabel / Havells / APAR EBXL / KEI (HFFR) / Polycab ((HR_FR-LF) / L&T /
V-Guard (HFFR).

a) Labour charges :
1 Skilled Electrician. 2.00 day 1 day 565.00 1130.00
2 Lineman Electric / Telephone 5.50 day 1 day 470.00 2585.00
3 Helper (Electrical). 2.00 day 1 day 470.00 940.00
Labour for 100 Mtr 4655.00
Labour for 1 Mtr 46.55
b) Material
1.5.1 d) Supply of 84/0.3mm (6.0 Sqmm) 500.00 Mtrs 100 Mtrs 5700.00 28500.00
FRLS / HFFR Copper cable.
Cost of Material for 100 Metres 28500.00
Cost of Material Rate per Mtr= C/100 285.00
Total Cost of Material + Labour 331.50
Charges
Add Contractors Profit 0.000% 0.00
331.50
Rate per Meter 332.00

24 Supply & run of 5 of 10.0 Sqmm (140/0.3 mm) (3 phases, neutral and earth) FRLS / HFFR PVC
insulated flexible copper cable in the existing conduict pipe for run of mains from Power panel board to
TPN DB"s with pin type lugs and connections etc., complete. [for PDBs]
Makes of wires : Finolex / RR kabel / Havells / APAR EBXL / KEI (HFFR) / Polycab ((HR_FR-LF) / L&T /
V-Guard (HFFR).

a) Labour charges :
1 Skilled Electrician. 2.34 day 1 day 565.00 1322.10
2 Lineman Electric / Telephone 6.50 day 1 day 470.00 3055.00
3 Helper (Electrical). 2.34 day 1 day 470.00 1099.80
Labour for 100 Mtr 5476.90
Labour for 1 Mtr 54.77
b) Material
1.5.1 e) Supply of 140/0.3mm (10.0 Sqmm) 500.00 Mtrs 100 Mtrs 8800.00 44000.00
PVC FRLS / HFFR insulated flexible
Copper cable.
Cost of Material for 100 Metres 44000.00
Cost of Material Rate per Mtr= C/100 440.00
Total Cost of Material + Labour 494.70
Charges
Add Contractors Profit 0.000% 0.00
494.70
Rate per Meter 495.00

Wiring, Switches and Sockets with 2nd Grade Rate


Point wiring in Non Residential Building
25 Wiring with 2 runs of 22/0.3mm ( 1.5 Sq.mm) FRLS / HFFR P.V.C. insulated flexible copper cable (ISI
MARK) in existing pipe with 6A Modular switch, Ceiling rose/BH/SBH Modular switches with cover
plate and GI switch box including all labour charges etc., complete. (for Non-Residential Building)
Makes of wires : HPL / RPG / Kundancab / Nakoda / Anchor / GM / Million / Gold Medal / Power Flex /
Fortune Art / Gloster.
Makes of switches: Legrand Myrius / Million mway / Gold Medal Curve / Anchor Roma viola / GM Four-
Five / Havells Fabio / Panasonic Vision / L&T Englaze / Hager Insista / Benlo Vesta / C&S Primo / CPL
Vysma / Polycab Levana.

Page 112 of 204


S.No SSR No Description Qty Unit Rate Amount

a) Labour charges :
1 Skilled Electrician. 0.60 day 1 day 565.00 339.00
2 Lineman Electric / Telephone 1.20 day 1 day 470.00 564.00
3 Helper (Electrical). 0.60 day 1 day 470.00 282.00
Labour for 6 Points 1185.00
Labour for 1 Point 197.50
b) Material
1.3.1 b) Supply of 3 Module box. 2 Nos 1 No 80.00 160.00
1.3.3 b) Supply of 3 Modular Cover Frame. 2 Nos 1 No 68.00 136.00
1.9.2 b) Supply of 6A / 10A 1 Way 1 Module 6 Nos 1 No 61.00 366.00
Modular Switch.
1.7.1 m) Supply of 3 Plate Jumbo Ceiling Rose. 6 Nos 1 No 19.00 114.00
1.5.2 a) Supply of 22/0.3mm (1.5 Sqmm) 100.00 Mtrs 100 Mtrs 1320.00 1320.00
FRLS / HFFR PVC insulated 1100V
grade as perIS:694/1990 specification
for Copper cable.

Cost of Material for 6 Points 2096.00


Cost of Material Rate per 1 Point 349.33
Total Cost of Material + Labour 546.00
Charges
Add Contractors Profit 0.000% 0.00
546.00
Rate per Each 546.00

Point wiring in Residential Building


26 Wiring with 2 runs of 22/0.3mm ( 1.5 Sq.mm) FRLS / HFFR P.V.C. insulated flexible copper cable (ISI
MARK) in existing pipe with 6A Modular switch, Ceiling rose/BH/SBH Modular switches with cover
plate and GI switch box including all labour charges etc., complete. (for Non-Residential Building)
Makes of wires : HPL / RPG / Kundancab / Nakoda / Anchor / GM / Million / Gold Medal / Power Flex /
Fortune Art / Gloster.
Makes of switches: Legrand Myrius / Million mway / Gold Medal Curve / Anchor Roma viola / GM Four-
Five / Havells Fabio / Panasonic Vision / L&T Englaze / Hager Insista / Benlo Vesta / C&S Primo / CPL
Vysma / Polycab Levana.

a) Labour charges :
1 Skilled Electrician. 0.70 day 1 day 565.00 395.50
2 Lineman Electric / Telephone 1.40 day 1 day 470.00 658.00
3 Helper (Electrical). 0.70 day 1 day 470.00 329.00
Labour for 6 Points 1382.50
Labour for 1 Point 197.50
b) Material
1.3.1 b) Supply of 3 Module box. 1 Nos 1 No 80.00 80.00
1.3.1 c) Supply of 4 Module box. 1 Nos 1 No 95.00 95.00
1.3.3 b) Supply of 3 Modular Cover Frame. 1 Nos 1 No 68.00 68.00
1.3.3 c) Supply of 4 Modular Cover Frame. 1 Nos 1 No 80.00 80.00

1.9.2 a) Supply of 6A / 10A 1 Way 1 Module 7 Nos 1 No 61.00 427.00


Modular Switch.
1.7.1 m) Supply of 3 Plate Jumbo Ceiling Rose. 7 Nos 1 No 19.00 133.00
1.5.2 a) Supply of 22/0.3mm (1.5 Sqmm) 100.00 Mtrs 100 Mtrs 1320.00 1320.00
FRLS / HFFR PVC insulated 1100V
grade as perIS:694/1990 specification
for Copper cable.

Cost of Material for 7 Points 2203.00


Cost of Material Rate per 1 Point 314.71
Total Cost of Material + Labour 512.00
Charges
Add Contractors Profit 0.000% 0.00
512.00
Rate per Each 512.00

Common Socket

Page 113 of 204


S.No SSR No Description Qty Unit Rate Amount

27 Supply and fixing of 6A ISI Mark 3/2 pin Modular socket with 6A 1way Modular switch, 3 Module box
with cover frame and GI switch box on common switch board with connections etc., complete.
Makes : Legrand Myrius / Million mway / Gold Medal Curve / Anchor Roma viola / GM Four-Five /
Havells Fabio / Panasonic Vision / L&T Englaze / Hager Insista / Benlo Vesta / C&S Primo / CPL Vysma
/ Polycab Levana.

a) Labour charges :
1 Skilled Electrician. 0.067 day 1 day 565.00 37.86
2 Helper (Electrical). 0.067 day 1 day 470.00 31.49
Labour for 1 Point 69.35
b) Material
1.3.1 b) Supply of 3 Module box. 1 No 1 No 80.00 80.00
1.3.3 b) Supply of 3 Modular Cover Frame. 1 No 1 No 68.00 68.00
1.9.2 a) Supply of 6A / 10A 1 Way 1 Module 1 No 1 No 61.00 61.00
Modular Switch.
1.9.2 d) Supply of 6A / 10A 3/2 Pin 2 Module 1 No 1 No 90.00 90.00
Modular Socket with shutter.

Cost of Material Rate per 1 Point 299.00


Total Cost of Material + Labour 368.00
Charges
Add Contractors Profit 0.000% 0.00
368.00
Rate per Each 368.00

Separate Socket
28 Wiring with 3 of 22/0.3mm ( 1.5 Sq.mm) FRLS / HFFR P.V.C. insulated flexible copper cable (ISI
MARK) in existing pipe with 6A switch and 6A, 3/2 pin socket Modular type with 6A switch control and
MS boxes with cover plate and GI switch box fixing on separate board including all labour charges
etc., complete.
Makes of wires : HPL / RPG / Kundancab / Nakoda / Anchor / GM / Million / Gold Medal / Power Flex /
Fortune Art / Gloster.
Makes of switches: Legrand Myrius / Million mway / Gold Medal Curve / Anchor Roma viola / GM Four-
Five / Havells Fabio / Panasonic Vision / L&T Englaze / Hager Insista / Benlo Vesta / C&S Primo / CPL
Vysma / Polycab Levana.

a) Labour charges :
1 Skilled Electrician. 1.50 day 1 day 565.00 847.50
2 Lineman Electric / Telephone 1.50 day 1 day 470.00 705.00
3 Helper (Electrical). 1.50 day 1 day 470.00 705.00
Labour for 15 Points 2257.50
Labour for 1 Point 150.50
b) Material
1.3.1 b) Supply of 3 Module box. 15 Nos 1 No 80.00 1200.00
1.3.3 b) Supply of 3 Modular Cover Frame. 15 No 1 No 68.00 1020.00
1.9.2 a) Supply of 6A / 10A 1 Way 1 Module 15 No 1 No 61.00 915.00
Modular Switch.
1.9.2 d) Supply of 6A / 10A 3/2 Pin 2 Module 15 No 1 No 90.00 1350.00
Modular Socket with shutter.
1.5.2 a) Supply of 22/0.3mm (1.5 Sqmm) 150.00 Mtrs 100 Mtrs 1320.00 1980.00
FRLS / HFFR PVC insulated 1100V
grade as perIS:694/1990 specification
for Copper cable.

Cost of Material for 15 Points 6465.00


Cost of Material Rate per 1 Point 431.00
Total Cost of Material + Labour 581.00
Charges
Add Contractors Profit 0.000% 0.00
581.00
Rate per Each 581.00

6A Switches - 2 Nos & 6A Sockets - 2 Nos


29 Supply and fixing of 6A switchs - 2 Nos and 6A 3/2 pin socket - 2 Nos Modular type with cover plate
and GI switch box fixing on separate board including all labour charges etc., complete.
Makes of switches: Legrand Myrius / Million mway / Gold Medal Curve / Anchor Roma viola / GM Four-
Five / Havells Fabio / Panasonic Vision / L&T Englaze / Hager Insista / Benlo Vesta / C&S Primo / CPL
Vysma / Polycab Levana.

a) Labour charges :

Page 114 of 204


S.No SSR No Description Qty Unit Rate Amount

1 Skilled Electrician. 0.20 day 1 day 565.00 113.00


2 Helper (Electrical). 0.20 day 1 day 470.00 94.00
Labour for 1 No 207.00
b) Material
1.3.1 d) Supply of 6 Module box 1 No 1 No 130.00 130.00
1.3.3 d) Supply of 6 Modular Cover Frame. 1 Nos 1 No 110.00 110.00
1.9.2 a) Supply of 6A / 10A 1 Way 1 Module 2 Nos 1 No 61.00 122.00
Modular Switch.

1.9.2 d) Supply of 6A / 10A 3/2 Pin 2 Module 2 Nos 1 No 90.00 180.00


Modular Socket with shutter.
Cost of Material for 1 No 542.00
Total Cost of Material + Labour 749.00
Charges
Add Contractors Profit 0.000% 0.00
749.00
Rate per Each 749.00

6A Switches - 3 Nos & 6A Sockets - 3 Nos


30 Supply and fixing of 6A switchs - 3 Nos and 6A 3/2 pin socket - 3 Nos Modular type with cover plate
and GI switch box fixing on separate board including all labour charges etc., complete.
Makes of switches: Legrand Myrius / Million mway / Gold Medal Curve / Anchor Roma viola / GM Four-
Five / Havells Fabio / Panasonic Vision / L&T Englaze / Hager Insista / Benlo Vesta / C&S Primo / CPL
Vysma / Polycab Levana.

a) Labour charges :
1 Skilled Electrician. 0.20 day 1 day 565.00 113.00
2 Helper (Electrical). 0.20 day 1 day 470.00 94.00
Labour for 1 No 207.00
b) Material
1.3.1 e) Supply of 8/9 Module box 1 No 1 No 170.00 170.00
1.3.3 e) Supply of 8/9 Modular Cover Frame. 1 Nos 1 No 135.00 135.00
1.9.2 a) Supply of 6A / 10A 1 Way 1 Module 3 Nos 1 No 61.00 183.00
Modular Switch.
1.9.2 d) Supply of 6A / 10A 3/2 Pin 2 Module 3 Nos 1 No 90.00 270.00
Modular Socket with shutter.
Cost of Material for 1 No 758.00
Total Cost of Material + Labour 965.00
Charges
Add Contractors Profit 0.000% 0.00
965.00
Rate per Each 965.00

6A Switches - 4 Nos & 6A Sockets - 4 Nos


31 Supply and fixing of 6A switchs - 4 Nos and 6A 3/2 pin socket - 4 Nos Modular type with cover plate
and GI switch box fixing on separate board including all labour charges etc., complete.
Makes of switches: Legrand Myrius / Million mway / Gold Medal Curve / Anchor Roma viola / GM Four-
Five / Havells Fabio / Panasonic Vision / L&T Englaze / Hager Insista / Benlo Vesta / C&S Primo / CPL
Vysma / Polycab Levana.

a) Labour charges :
1 Skilled Electrician. 0.20 day 1 day 565.00 113.00
2 Helper (Electrical). 0.20 day 1 day 470.00 94.00
Labour for 1 No 207.00
b) Material
1.3.1 e) Supply of 12 Module box 1 No 1 No 205.00 205.00
1.3.3 e) Supply of 12 Modular Cover Frame. 1 Nos 1 No 165.00 165.00
1.9.2 a) Supply of 6A / 10A 1 Way 1 Module 4 Nos 1 No 61.00 244.00
Modular Switch.
1.9.2 d) Supply of 6A / 10A 3/2 Pin 2 Module 4 Nos 1 No 90.00 360.00
Modular Socket with shutter.
Cost of Material for 1 No 974.00
Total Cost of Material + Labour 1181.00
Charges
Add Contractors Profit 0.000% 0.00
1181.00

Page 115 of 204


S.No SSR No Description Qty Unit Rate Amount

Rate per Each 1181.00


16 A Socket
32 Supply & fixing of 16A/6A, 2 in one socket with 16A switch control modular type with and GI switch box
with front cover plate including all labour charges etc., complete.
Makes of switches: Legrand Myrius / Million mway / Gold Medal Curve / Anchor Roma viola / GM Four-
Five / Havells Fabio / Panasonic Vision / L&T Englaze / Hager Insista / Benlo Vesta / C&S Primo / CPL
Vysma / Polycab Levana.

a) Labour charges :
1 Skilled Electrician. 0.10 day 1 day 565.00 56.50
2 Helper (Electrical). 0.10 day 1 day 470.00 47.00
Labour for 1 No 103.50
b) Material
1.3.1 b) Supply of 3 Module box. 1 No 1 No 80.00 80.00
1.3.3 b) Supply of 3 Modular Cover Frame. 1 No 1 No 68.00 68.00
1.9.2 h) Supply of 16A / 20A 1 Way 1 Module 1 No 1 No 80.00 80.00
Modular Switch.
1.9.2 i) Supply of 16A/6A 1 way Combi Socket 1 No 1 No 130.00 130.00
Modular Socket with shutter.
Cost of Material for 1 No 358.00
Total Cost of Material + Labour 461.00
Charges
Add Contractors Profit 0.000% 0.00
461.00
Rate per Each 461.00

16A Socket - 1 No & 6A Socket - 1 No


33 Supply and fixing of 1 No. of 6A / 10A 1 Way Modular Switch with 6A / 10A 3/2 Pin Modular Socket with
shutter & 1 No of 16A / 20A 1 Way Modular switch with 16A/6A 1 way Combi Modular Socket with
shutter on the suitable size Modular box with required cover frame including cost and conveyance of all
material and all labour charges etc., complete.
Makes of switches: Legrand Myrius / Million mway / Gold Medal Curve / Anchor Roma viola / GM Four-
Five / Havells Fabio / Panasonic Vision / L&T Englaze / Hager Insista / Benlo Vesta / C&S Primo / CPL
Vysma / Polycab Levana.

a) Labour charges :
1 Skilled Electrician. 0.15 day 1 day 565.00 84.75
2 Helper (Electrical). 0.15 day 1 day 470.00 70.50
Labour for 1 No 155.25
b) Material
1.3.1 d) Supply of 6 Module box 1 No 1 No 130.00 130.00
1.3.3 d) Supply of 6 Modular Cover Frame. 1 Nos 1 No 110.00 110.00
1.9.2 a) Supply of 6A / 10A 1 Way 1 Module 1 Nos 1 No 61.00 61.00
Modular Switch.
1.9.2 d) Supply of 6A / 10A 3/2 Pin 2 Module 1 Nos 1 No 90.00 90.00
Modular Socket with shutter.
1.9.2 h) Supply of 16A / 20A 1 Way 1 Module 1 No 1 No 80.00 80.00
Modular Switch.
1.9.2 i) Supply of 16A/6A 1 way Combi Socket 1 No 1 No 130.00 130.00
Modular Socket with shutter.
Cost of Material for 1 No 601.00
Total Cost of Material + Labour 756.00
Charges
Add Contractors Profit 0.000% 0.00
756.00
Rate per Each 756.00

16A Socket - 2 Nos & 16A Switch - 2 Nos


34 Supply & fixing of 16A/6A, 2 in one socket - 2 Nos with 16A switch control - 2 Nos modular type with
and GI switch box with front cover plate including all labour charges etc., complete.
Makes of switches: Legrand Myrius / Million mway / Gold Medal Curve / Anchor Roma viola / GM Four-
Five / Havells Fabio / Panasonic Vision / L&T Englaze / Hager Insista / Benlo Vesta / C&S Primo / CPL
Vysma / Polycab Levana.

a) Labour charges :
1 Skilled Electrician. 0.15 day 1 day 565.00 84.75
2 Helper (Electrical). 0.15 day 1 day 470.00 70.50
Labour for 1 No 155.25

Page 116 of 204


S.No SSR No Description Qty Unit Rate Amount

b) Material
1.3.1 d) Supply of 6 Module box 1 No 1 No 130.00 130.00
1.3.3 d) Supply of 6 Modular Cover Frame. 1 Nos 1 No 110.00 110.00
1.9.2 h) Supply of 16A / 20A 1 Way 1 Module 2 Nos 1 No 80.00 160.00
Modular Switch.
1.9.2 i) Supply of 16A/6A 1 way Combi Socket 2 Nos 1 No 130.00 260.00
Modular Socket with shutter.
Cost of Material for 1 No 660.00
Total Cost of Material + Labour
Charges 815.00
Add Contractors Profit 0.000% 0.00
815.00
Rate per Each 815.00

Run of Mains
35 Supply and run of 1 of 22 /0.3mm (1.5 Sq.mm) FRLS / HFFR P.V.C. insulated flexible copper cable in
existing conduit pipe for earth continuity including all labour charges etc., complete.
Makes of wires : HPL / RPG / Kundancab / Nakoda / Anchor / GM / Million / Gold Medal / Power Flex /
Fortune Art / Gloster.

a) Labour charges :
1 Skilled Electrician. 0.34 day 1 day 565.00 192.10
2 Lineman Electric / Telephone 0.70 day 1 day 470.00 329.00
3 Helper (Electrical). 0.34 day 1 day 470.00 159.80
Labour for 100 Mtr 680.90
Labour for 1 Mtr 6.81
b) Material
1.5.2 a) Supply of 22/0.3mm (1.5 Sqmm) 100.00 Mtrs 100 Mtrs 1320.00 1320.00
FRLS / HFFR Copper cable.

Cost of Material for 100 Metres 1320.00


Cost of Material Rate per Mtr= C/100 13.20
Total Cost of Material + Labour 20.00
Charges
Add Contractors Profit 0.000% 0.00
20.00
Rate per Meter 20.00

36 Supply and run of 3 of 2.5 sq.mm (36/0.mm) (phase, neutral and earth) FRLS / HFFR PVC insulated
flexible copper cable in existing conduit pipe for individual lighting circuits including labour charges etc.,
complete as required for switch boards.
Makes of wires :HPL / RPG / Kundancab / Nakoda / Anchor / GM / Million / Gold Medal / Power Flex /
Fortune Art / Gloster.

a) Labour charges :
1 Skilled Electrician. 1.00 day 1 day 565.00 565.00
2 Lineman Electric / Telephone 2.50 day 1 day 470.00 1175.00
3 Helper (Electrical). 1.00 day 1 day 470.00 470.00
Labour for 100 Mtr 2210.00
Labour for 1 Mtr 22.10
b) Material
1.5.2 b) Supply of 36/0.3mm (2.5 Sqmm) 300.00 Mtrs 100 Mtrs 2140.00 6420.00
FRLS / HFFR Copper cable.
Cost of Material for 100 Metres 6420.00
Cost of Material Rate per Mtr= C/100 64.20
Total Cost of Material + Labour 86.30
Charges
Add Contractors Profit 0.000% 0.00
86.30
Rate per Meter 86.00

37 Supply and 3 runs of 4.0 sq mm (56/0.3 mm) (phase neutral and earth) FRLS / HFFR PVC insulated
flexible copper cable in existing conduit pipe including labour charges etc., complete for 16A sockets.
Makes of wires : HPL / RPG / Kundancab / Nakoda / Anchor / GM / Million / Gold Medal / Power Flex /
Fortune Art / Gloster.

a) Labour charges :

Page 117 of 204


S.No SSR No Description Qty Unit Rate Amount

1 Skilled Electrician. 1.00 day 1 day 565.00 565.00


2 Lineman Electric / Telephone 3.00 day 1 day 470.00 1410.00
3 Helper (Electrical). 1.00 day 1 day 470.00 470.00
Labour for 100 Mtr 2445.00
Labour for 1 Mtr 24.45
b) Material
1.5.2 c) Supply of 56/0.3mm (4.0 Sqmm) 300.00 Mtrs 100 Mtrs 3300.00 9900.00
FRLS / HFFR Copper cable.
Cost of Material for 100 Metres 9900.00
Cost of Material Rate per Mtr= C/100 99.00
Total Cost of Material + Labour 123.40
Charges
Add Contractors Profit 0.000% 0.00
123.40
Rate per Meter 123.00
1 Supply of 10 sqmm WPTC (Weather Proof Twin Core) ISI Alluminium Wire. Makes : Polycab / GM /
Million / V-Guard / Gold Medal / Kundancab / HPL / RPG / Nandicab / Nakoda / Payal / Finecab /
Gemini / Vimal / Suncab / Stanjo / Rajnigandha / Orbit / Airson.

a) Labour charges :
1 Skilled Electrician. 0.50 day 1 day 565.00 282.50
2 Lineman Electric / Telephone 0.50 day 1 day 470.00 235.00
3 Helper (Electrical). 1.00 day 1 day 470.00 470.00
Labour for 100 Mtr 987.50
Labour for 1 Mtr 9.88
b) Material
1.5.2 c) Supply of 10 sqmm WPTC (Weather 100.00 Mtrs 100 Mtrs 3400.00 3400.00
Proof Twin Core) ISI Alluminium Wire
Cost of Material for 100 Metres 3400.00

Cost of Material Rate per Mtr= C/100 34.00


Total Cost of Material + Labour 43.80
Charges
Add Contractors Profit 0.000% 0.00
43.80
Rate per Meter 44.00

Supply and fixing of 12 V 150AH MF battery including wire leads. Makes : Amar Raja (Power Zone) or
Equivalent model of Exide / Panasonic / Gotech- SSR-1897

Supply and fixing of 12 V 150AH MF 100.00 NOS 100 NOS 11500.00 11500.00
battery

1 Supply, Transportation and fixing of 60 W / 65 W LED LED Street light, Body made of high grade
pressure
a) Labourdie – cast Aluminium alloy with corrosion resistant powder coat, having protective toughened
charges
1 Skilled Electrician. 0.25 day 1 day 565.00 141.25
2 Lineman Electric / Telephone 0.25 day 1 day 470.00 117.50
3 Helper (Electrical). 0.25 day 1 day 470.00 117.50
Labour for 1 No 376.25
b) Material
1.5.2 b) Supply of 2.5 Sqmm FRLS / HFFR 2.00 Mtrs 100 Mtrs 2140.00 42.80
Copper cable.
9.4.15 b) 40mm Nominal Bore Medium grade 1.00 Mtrs 1 Mtr 350.00 350.00
G.I.Pipe.
Pipe bending charges LS 40.00
M.S flat and welding charges LS 50.00
3.11.1 d 60 / 65 W 1 Nos 1 Nos 5700.00 5700.00
Cost of Material for 1 No 6182.80
Total Cost of Material + Labour
Charges 6559.00
Add Contractors Profit 0.000% 0.00
6559.00
Rate per Each 6559.00

Page 118 of 204


S.No SSR No Description Qty Unit Rate Amount

1 ELEC- Fabrication, transportation and supply 1 No 1 each 106000.00 106000.00


7.4.1 of 12 Mtrs Polygon High Mast with
single section of 3mm thick of Bottom
360mm and Top 150mm dia with BSEN
- 10025 grade S 355 JO steel plate for
shaft, IS 2062 for base plate, having a
base plate of size 520mm dia 16mm
thick with its accessories. Mast shall be
in single section for 12 Mtrs and 2
sections for 16 and 20 Mtrs. Mast shall
be hot dip galvanized and suiatble for
wind velocity of 180 KMPH as per IS
875 part 3 including head frame, 2
point suspension system with steel
rope 6mm dia (7/19) construction
double drum winch / power tool
operating speed of 900 RPM, and
necessary cable trailer connections and
single speed motor with M 24 x 800
mm foundation bolts of required
quantity, suitable for 6 luminaires with
GLS type aviation twin lamp.
Makes: BAJAJ / VALMONT /
TRANSRAIL /
SKIPPER / UTKARSH / LAASMA /
CONSOUL.

Rate per Each 106000.00

2 ELEC- Errection of 12 Mtrs high mast with 1 No 1 each 28100.00 28100.00


7.6.1 Earth work exacavation with a
approximate quantity of 4.0 Cum and
refilling with a quantity of 0.53 Cum of
PCC 1:4:8, 1.50 Cum M 20 grade
concrete and (80 Kgs) reinforced steel
of 12mm / 10mm / 8mm, Soil bearing
capacity of 10 T/Sqm, Anchor plate with
cost and conveyance of all above
materials including labour charges for
errection of High Mast and Carraige etc
complete including soil testing.

Rate per Each 28100.00

Page 119 of 204


S.No SSR No Description Qty Unit Rate Amount

3 7.6.2 a) Supply and fixing of suitable out door 1 No 1 each 21719.00 21719.00
feeder piller box of size made with 14
SWG CRCA sheet with double door
arrangement, making powder coating
after processing of 7 Tank process,
lock and key, hinges, rubber gasket,
danger board,suitable angle iron stand
for mounting the feeder pillar with
cement concrete, including Supply and
fixing of 63A, 4 Pole MCB as incomer,
6 Nos 6-32A SP MCBs as out goings,
indication lamps, din channel, 6 Sqmm
3 core copper cable for invidual light
control, connectors, gland plates and
provision for 3 phase energy meter etc.,
complete for finished item of work and
suitable wiring provision for connecting
the nature switch with following.
Makes : Legrand / Schnieder

Rate per Each 21719.00

4 3.5.2 a) Supply and fixing of Automatic Street 1 No 1 each 14800.00 14800.00


Light Control System with Optical
Sensor, Low volatage / High voltage
trip and reset, operating voltage 380 -
450 V AC, 50 HZ with suitable SMC
enclousure of IP 54 protection, MCBs
of Legrand / Schneider / L&T / Siemens
of 10KA C/D curve and Contactor
suitable to control the load of 5KW
Three phase load with necessary
clamping arrangements.
Makes : Swadeep Nature Switch / Light
Mate / L&T /
Siemens / Bajaj.

Rate per Each 14800.00

5 Supply, Transportation and fixing of 120 W LED Flood light Luminaire made of pressure die cast
aluminum housing with powder coated, having toughened glass cover, IP 66 (Silicon gasket ensures
a) Labour charges
1 Skilled Electrician. 0.50 day 1 day 565.00 282.50
2 Lineman Electric / Telephone 0.50 day 1 day 470.00 235.00
3 Helper (Electrical). 0.50 day 1 day 470.00 235.00
Labour for 1 No 752.50
b) Material
1.5.7 i) 4.0 Sqmm (56/0.3) 3 Core Flexible 25.00 Mtrs 1 Mtrs 145.00 3625.00
Armouring Flexible Copper cable
3.11.4 c) 120 W 1 Nos 1 Nos 12674.00 12674.00
Cost of Material for 1 No 16299.00
Total Cost of Material + Labour
17052.00
Charges

Rate per Each

Page 120 of 204


S.No SSR No Description Qty Unit Rate Amount

1 Supply & run of 5 of 6.0 Sqmm (84/0.3mm) (3 phases, neutral and earth) FRLS / HFFR PVC insulated
flexible
a) Labourcopper cable
charges : in the existing conduict pipe for run of mains from Power panel board to TPN DB"s
1 Skilled Electrician. 2.00 day 1 day 565.00 1130.00
2 Lineman Electric / Telephone 5.50 day 1 day 470.00 2585.00
3 Helper (Electrical). 2.00 day 1 day 470.00 940.00
Labour for 100 Mtr 4655.00
Labour for 1 Mtr 46.55
b) Material
1.5.2 d) Supply of 84/0.3mm (6.0 Sqmm) 500.00 Mtrs 100 Mtrs 5100.00 25500.00
FRLS / HFFR Copper cable.
Cost of Material for 100 Metres 25500.00

Cost of Material Rate per Mtr= C/100 255.00


Total Cost of Material + Labour 301.50
Charges
Add Contractors Profit 0.000% 0.00

301.50

Rate per Meter 302.00

2 Supply & run of 5 of 10.0 Sqmm (140/0.3 mm) (3 phases, neutral and earth) FRLS / HFFR PVC
insulated flexible copper cable in the existing conduict pipe for run of mains from Power panel board to
a)
TPNLabour
DB"s charges
with pin :type lugs and connections etc., complete. [for PDBs]
1 Skilled Electrician.
Makes of wires : HPL / RPG / Kundancab / Nakoda 2.34 /day
Anchor / GM 1 day 565.00
/ Million / Gold Medal / Power 1322.10
Flex /
2 Fortune Art / Gloster.
Lineman Electric / Telephone 6.50 day 1 day 470.00 3055.00

3 Helper (Electrical). 2.34 day 1 day 470.00 1099.80


Labour for 100 Mtr 5476.90

Labour for 1 Mtr 54.77

b) Material
1.5.2 e) Supply of 140/0.3mm (10.0 Sqmm) 500.00 Mtrs 100 Mtrs 7750.00 38750.00
PVC FRLS / HFFR insulated flexible
Copper cable. for 100 Metres
Cost of Material 38750.00
Cost of Material Rate per Mtr= C/100 387.50
Total Cost of Material + Labour 442.20
Charges
Add Contractors Profit 0.000% 0.00
442.20
Rate per Meter 442.00
Distribution Boards
AC BOX
25 Supply and fixing 20A Plug and Socket with SS enclosure with 20A SP MCB including connections for
AC's. Makes : Legrand-DX3 / Schneider-Acti9 / Siemens / L&T Exora / Cabtree
MATERIAL
2.16.8 a) Supply of 20A Plug and Socket with SS 1 Nos 1 No 1035.00 1035.00
enclosure.

2.13.1 a) Supply of 20A 10KA SP MCB, C/D 1 Nos 1 No 210.00 210.00


Curve ISI Mark.
COST OF MATERIAL FOR FULSH 1245.00
MOUNTING
LABOUR

1 Skilled Electrician. 0.25 day 1 day 565.00 141.25

Page 121 of 204


S.No SSR No Description Qty Unit Rate Amount

2 Helper (Electrical). 0.25 day 1 day 470.00 117.50


COST OF LABOUR FOR FULSH 258.75
MOUNTING
Rate per Each 1504.00
26 Supply and fixing of DP/FP Metal Enclosure with IP 20 Protection DB Make with 1 No 20A, 10 KA DP
MCB including internal connection and labour charges for Flush Mounting etc., complete.Makes :
MATERIAL
2.16.11 b) Supply of DP/TP/FP Metal Enclosure 1 Nos 1 No 440.00 440.00
with IP 20 Protection.
2.13.1 c) Supply of 6-32A 10KA DP MCB, C/D 1 Nos 1 No 625.00 625.00
Curve ISI Mark.
9.4.11 Cement. 5.00 Kg 1 Kg 8.00 40.00
COST OF MATERIAL FOR FULSH 1105.00
MOUNTING
LABOUR
1 Skilled Electrician. 0.25 day 1 day 565.00 141.25
2 Helper (Electrical). 0.25 day 1 day 470.00 117.50

3 Mason Cl- I / Brick layer Cl- I 0.15 day 1 day 500.00 75.00

COST OF LABOUR FOR FULSH 333.75


MOUNTING
TOTAL COST OF MATERIAL + 1438.75
LABOUR FOR FULSHMOUNTING

Add Contractors Profit 0.000% 0.00

1438.75

Rate per Each 1438.00

27 Supply and fixing of FP Metal Enclosure with IP 20 Protection DB Make with 1 No 63A, 10 KA FP MCB
including internal connection and labour charges for Flush Mounting etc., complete. Makes : Legrand-
MATERIAL
DX3 / Schneider-Acti9 / Siemens / L&T Exora / Cabtree
2.16.11 b) Supply of DP/TP/FP Metal Enclosure 1 Nos 1 No 440.00 440.00
with IP 20 Protection.
2.13.1 h) Supply of 63A FP MCB, C/D Curve ISI 1 Nos 1 No 1900.00 1900.00
Mark.
9.4.11 Cement. 5.00 Kg 1 Kg 8.00 40.00
COST OF MATERIAL FOR FULSH 2380.00
MOUNTING
LABOUR
Skilled Electrician. 0.25 day 1 day 540.00 135.00
Helper (Electrical). 0.25 day 1 day 450.00 112.50
Mason Cl- I / Brick layer Cl- I 0.15 day 1 day 470.00 70.50
COST OF LABOUR FOR FULSH 318.00
MOUNTING
TOTAL COST OF MATERIAL + 2698.00
LABOUR FOR FULSH MOUNTING
Add Contractors Profit 0.000% 0.00
2698.00

Rate per Each 2698.00

LDB

28 Supply and fixing of 4 Way TPN DB Horizontal with IP 43 Protection as per IS:13032 makes Legrand /
Schneider / Siemens / L&T / Hager / Cabtree Xproand Supply and Fixing of 1 No., of 63A FP Isolator as
incomer and 12 Nos 6-32 A 10kA SP MCBs of makes Legrand-DX3 / Schneider-Acti9 / Siemens / L&T
MATERIAL
Exora / Cabtree as out goings including internal connections and labour charges for FLUSH Mounting
etc., complete. (For Lighting DBs)
Makes : Legrand / Shneider

Page 122 of 204


S.No SSR No Description Qty Unit Rate Amount

2.16.1 b) Supply of 4 Way TPN DB Horizontal 1 Nos 1 No 2860.00 2860.00


with IP 43 Protection as per IS:13032
and suitable for 12 Nos S.P. out goings
and for 1 No 4 pole Incommer etc
complete.
2.14.1 g) Supply of 63A FP Isolator . 1 No 1 No 935.00 935.00
Supply of 6-32A 10KA SP MCB, C/D 12 Nos 1 No 210.00 2520.00
2.13.1 a)
Curve ISI Mark.
9.4.11 Cement. 12.50 Kg 1 Kg 8.00 100.00
Sundries 0.00
6415.00
LABOUR
1 Skilled Electrician. 0.70 day 1 day 565.00 395.50
2 Lineman Electric / Telephone 1.00 day 1 day 470.00 470.00
3 Helper (Electrical). 1.00 day 1 day 470.00 470.00
4 Mason Cl- I / Brick layer Cl- I 0.50 day 1 day 500.00 250.00
1585.50
TOTAL COST OF MATERIAL + FLUSH 8001.00
LABOUR FOR FLUSH MOUNTING
Add Contractors Profit 0.000% 0.00

8001.00
Rate per Each 8001.00

PDB
29 Supply and fixing of 4 Way TPN DB Horizontal with IP 43 Protection as per IS:13032 Makes : Legrand /
Schneider
MATERIAL/ Siemens / L&T / Hager /Cabtree Xproand Supply and Fixing of 1 No., of 100A FP Isolator as
2.16.1 b) Supply of 4 Way TPN DB Horizontal 1 Nos 1 No 2860.00 2860.00
with IP 43 Protection as per IS:13032
and suitable for 12 Nos S.P. out goings
and for 1 No 4 pole Incommer etc
complete.
2.14.1 h) Supply of 100A FP Isolator . 1 No 1 No 1000.00 1000.00
Supply of 6-32A 10KA SP MCB, C/D 12 Nos 1 No 210.00 2520.00
2.13.1 a)
Curve ISI Mark.
9.4.11 Cement. 12.50 Kg 1 Kg 8.00 100.00
Sundries 5.00
6485.00
LABOUR
1 Skilled Electrician. 0.70 day 1 day 565.00 395.50
2 Lineman Electric / Telephone 1.00 day 1 day 470.00 470.00
3 Helper (Electrical). 1.00 day 1 day 470.00 470.00
4 Mason Cl- I / Brick layer Cl- I 0.50 day 1 day 500.00 250.00
1585.50
TOTAL COST OF MATERIAL + FLUSH 8071.00
LABOUR FOR FLUSH MOUNTING
Add Contractors Profit 0.000% 0.00
8071.00

Rate per Each 8071.00

30 Supply and fixing of 6 Way TPN DB Horizontal with IP 43 Protection as per IS:13032 Makes : Legrand /
Schneider / Siemens / L&T / Hager / Cabtree Xpro and Supply and Fixing of 1 No., of 100A FP Isolator
as incomer and 18 Nos 6-32 A 10kA SP MCBs Makes : Legrand-DX3 / Schneider-Acti9 / Siemens /
MATERIAL
L&T Exora / Cabtree as out goings including internal connections and labour charges for FLUSH
Mounting etc., complete for DBs.

Page 123 of 204


S.No SSR No Description Qty Unit Rate Amount

2.16.1 c) Supply of 6 Way TPN DB Horizontal 1 Nos 1 No 4200.00 4200.00


with IP 43 Protection as per IS:13032
and suitable for 18 Nos S.P. out goings
and for 1 No 4 pole Incommer etc
complete.
2.14.1 h) Supply of 100A FP Isolator . 1 No 1 No 1000.00 1000.00
Supply of 6-32A 10KA SP MCB, C/D 18 Nos 1 No 210.00 3780.00
2.13.1 a)
Curve ISI Mark.
9.4.11 Cement. 12.50 Kg 1 Kg 8.00 100.00
Sundries 2.00
9082.00
LABOUR
1 Skilled Electrician. 0.70 day 1 day 565.00 395.50
2 Lineman Electric / Telephone 1.00 day 1 day 470.00 470.00
3 Helper (Electrical). 1.00 day 1 day 470.00 470.00
4 Mason Cl- I / Brick layer Cl- I 0.50 day 1 day 500.00 250.00
1585.50

TOTAL COST OF MATERIAL + FLUSH 10668.00


LABOUR FOR FLUSH MOUNTING

Add Contractors Profit 0.000% 0.00


10668.00

10668.00
Rate per Each

8 Way VTPN DB
31 Supply and fixing of 8 Way VTPN DB with IP 43 Protection Makes : Legrand / Schneider / Siemens /
L&T / Hager /Cabtree Xpro and Supply and Fixing of 1 No., of 125A 4 Pole MCCB, Adjustable, Confirms
MATERIAL
2.16.3 b) Supply of 8 Way VTPN DB 1 Nos 1 No 11800.00 11800.00
2.13.1 f) Supply of 63A 10KA TPN MCB, C/D 8 Nos 1 No 1480.00 11840.00
Curve ISI Mark.
2.8.1 d) 125A 4 Pole MCCB, 25KA 1 Nos 1 No 8952.00 8952.00
Sundries 5.00
COST OF MATERIAL FOR Surface 32597.00
MOUNTING
LABOUR
1 Skilled Electrician. 1.25 day 1 day 565.00 706.25
2 Lineman Electric / Telephone 1.50 day 1 day 470.00 705.00
3 Helper (Electrical). 1.50 day 1 day 470.00 705.00
COST OF LABOUR FOR Surface 2116.25
MOUNTING
TOTAL COST OF MATERIAL + 34713.00
LABOUR FOR Surface MOUNTING

Add Contractors Profit 0.000% 0.00


34713.00

34713.00
Rate per Each

8 Way VTPN DB
32 Supply and fixing of 8 Way VTPN DB with IP 43 Protection Makes : Legrand / Schneider / Siemens /
L&T / Hager / Cabtree Xpro and Supply and Fixing of 1 No., of 125A 4 Pole MCCB, Adjustable,
MATERIAL
2.16.3 b) Supply of 8 Way VTPN DB 1 Nos 1 No 11800.00 11800.00
Supply of 6-32A 10KA SP MCB, C/D 24 Nos 1 No 210.00 5040.00
2.13.1 a)
Curve ISI Mark.

Page 124 of 204


S.No SSR No Description Qty Unit Rate Amount

2.8.1 c) Supply of 125A 3 Pole MCCB 1 Nos 1 No 7404.00 7404.00


Sundries 1.00
COST OF MATERIAL 24245.00
LABOUR
1 Skilled Electrician. 1.25 day 1 day 565.00 706.25
2 Lineman Electric / Telephone 1.50 day 1 day 470.00 705.00
3 Helper (Electrical). 1.50 day 1 day 470.00 705.00
COST OF LABOUR 2116.25
TOTAL COST OF MATERIAL 26361.00
Add Contractors Profit 0.000% 0.00

26361.00
26361.00
Rate per Each

4 Way VTPN DB

33 Supply and fixing of 4 Way VTPN DB with IP 43 Protection as per IS:13032 Makes : Legrand /
Schneider / Siemens / L&T / Hager /Cabtree Xpro and Supply and Fixing of 1 No., of 125A 4 Pole
MATERIAL
MCCB, Adjustable, Confirms to IS/IEC 60947-2 having Breaking Capacity 25 KA with thermal magnetic
2.16.3 a) Supply
release ofPanel
4 Way VTPN DBas incomer with 4 Nos of163A,
Mounted Nos 10KA, TP
1 NoMCBs C/D 9400.00
Curve ISI Mark as9400.00
Out
goings including internal connections
2.13.1 f) Supply of 63A 10KA TPN MCB, C/D and labour charges
4 Nos for etc.,
1 Nocomplete. Makes :
1480.00 L&T / Schneider
5920.00/
Siemens
Curve ISI/Mark.
Legrand / Hager /ABB / C&S.
2.8.1 c) Supply of 125A 3 Pole MCCB 1 Nos 1 No 7404.00 7404.00
9.4.11 Cement. 12.50 Kg 1 Kg 8.00 100.00
Sundries 6.00
COST OF MATERIAL FOR SURFACE 22830.00
MOUNTING
LABOUR
1 Skilled Electrician. 1.00 day 1 day 565.00 565.00
2 Lineman Electric / Telephone 1.50 day 1 day 470.00 705.00
3 Helper (Electrical). 1.00 day 1 day 470.00 470.00
COST OF LABOUR FOR SURFACE 1740.00
MOUNTING
TOTAL COST OF MATERIAL + SURFACE 24570.00
LABOUR FOR SURFACE MOUNTING

Add Contractors Profit 0.000% 0.00


24570.00
Rate per Each 24570.00

8 Way SPNDB
34 Supply and fixing of 8 Way SPN DB with IP 43 Protection as per IS:13032 and suitable for 8Nos
10A 10KA SP MCB as out goings and for 1 No 40A DP Isolator Incommer, concealing in wall etc
MATERIAL
2.15.1 d) Supply of 8 Way SPN DB 1 Nos 1 No 1365.00 1365.00

1 No 1 No 385.00 385.00
2.14.1 b) Supply of 40A DP Isolator .
8 Nos 1 No 210.00 1680.00

Supply of 6-32A 10KA SP MCB, C/D


2.13.1 a)
Curve ISI Mark.

12.50 Kg 1 Kg 8.00 100.00

9.4.11 Cement.

Page 125 of 204


S.No SSR No Description Qty Unit Rate Amount

Sundries 2.00

3532.00
LABOUR
1 Skilled Electrician. 0.50 day 1 day 565.00 282.50
2 Lineman Electric / Telephone 0.50 day 1 day 470.00 235.00
3 Mason Cl- I / Brick layer Cl- I 0.50 day 1 day 500.00 250.00
767.50
TOTAL COST OF MATERIAL + 4300.00
LABOUR FOR FLUSH MOUNTING

Add Contractors Profit 0.000% 0.00


4300.00
Rate per Each 4300.00

35 Supply and Installation of 63A 4 Pole MCCB, Adjustable, Confirms to IS/IEC 60947-2 having Breaking
Capacity
MATERIAL 25 KA with thermal magnetic release with cable end boxes on suitable angle iron frame work
Fabrication: L H D
Size of panel : in Mtr 0.25 0.25 0.15
Front and back faces 2.00 0.25 0.25 0.13
Top and bottom faces 2.00 0.25 0.15 0.08
Side faces 2.00 0.25 0.15 0.08
Sub total 0.28
Add extra 10 % for wastage 0.03
Total 0.30

7.12.1 b) Fabrication and erection of 14 / 16 0.30 Sqmtr 1 Sqmtr 4140.00 1252.35


SWG CRCA sheet steel enclosure for
power control cubicle panel / boxes
2.8.1 b) Supply of 63A 4 Pole MCCB, 1 Nos 1 No 7012.00 7012.00
etc., including cutting, bending drilling,
Adjustable, Confirms to IS/IEC 60947-2
welding and reveting etc., complete
having Breaking Capacity 16 KA with
with cleaning with 7 tank process and
thermal magnetic release Panel
painting with powder coating including
Mounted.
cost and conveyance of all materials
and labour charges.

Page 126 of 204


S.No SSR No Description Qty Unit Rate Amount

Provision for angle iron frame work 150.00


etc.,
8414.35
LABOUR
1 Skilled Electrician. 0.50 day 1 day 565.00 282.50
2 Lineman Electric / Telephone 1.00 day 1 day 470.00 470.00
752.50
TOTAL COST OF MATERIAL +
9167.00
LABOUR
Add Contractors Profit 0.000% 0.00
9167.00
Rate per Each 9167.00

36 Supply and Installation of 125 Amps 4 Pole MCCB, Adjustable, Confirms to IS/IEC 60947-2 having
Breaking
MATERIAL Capacity 25 KA with thermal magnetic release etc complete with connections. Make: L&T /
Fabrication: L H D
Size of panel : in Mtr 0.50 0.50 0.25
Front and back faces 2.00 0.50 0.50 0.50
Top and bottom faces 2.00 0.50 0.25 0.25
Side faces 2.00 0.50 0.25 0.25
Sub total 1.00
Add extra 10 % for wastage 0.10
Total 1.10

7.12.1 b) Fabrication and erection of 14 / 16 1.10 Sqmtr 1 Sqmtr 4140.00 4554.00


SWG CRCA sheet steel enclosure for
2.8.1 d) power
125 Amps control cubicle
FP MCCB, 25 panel
KA / boxes 1 Nos 1 No 8925.00 8925.00
etc., including cutting, bending drilling,
welding and reveting etc., complete
Provision for with
with cleaning angle7 iron
tank frame work
process and 203.00
etc.,
painting with powder coating including 13682.00
cost
LABOUR and conveyance of all materials
1 and labour charges.
Skilled Electrician. 0.50 day 1 day 565.00 282.50
2 Lineman Electric / Telephone 1.00 day 1 day 470.00 470.00
752.50
TOTAL COST OF MATERIAL +
14435.00
LABOUR
Add Contractors Profit 0.000% 0.00
14435.00
Rate per Each 14435.00

37 Supply and Installation of 250 Amps 4 Pole MCCB, Adjustable, Confirms to IS/IEC 60947-2 having
Breaking Capacity 35 KA with cable end boxes on suitable angle iron frame work including all Labours
charges massonry work etc complete with connections. Make: L&T / Schneider / Siemens / Legrand /
Hager /ABB / C&S.

MATERIAL

Fabrication: L H D

Size of panel : in Mtr 0.75 0.65 0.25

Front and back faces 2.00 0.75 0.65 0.98

Top and bottom faces 2.00 0.65 0.25 0.33

Side faces 2.00 0.75 0.25 0.38

Sub total 1.68

Page 127 of 204


S.No SSR No Description Qty Unit Rate Amount

Add extra 10 % for wastage 0.17

Total 1.84

7.12.1 b) Fabrication and erection of 14 / 16 1.84 Sqmtr 1 Sqmtr 4140.00 7628


SWG CRCA sheet steel enclosure for
power control cubicle panel / boxes
2.8.1 h) 250
etc., Amps FP MCCB,
including cutting,35bending
KA drilling, 1 Nos 1 No 21423.00 21423.00
welding and reveting etc., complete
Provision for angle iron frame work 246.00
with
etc., cleaning with 7 tank process and
painting with powder coating including
cost and conveyance of all materials
and labour charges. 29297

LABOUR

1 Skilled Electrician. 0.50 day 1 day 565.00 282.50

2 Lineman Electric / Telephone 1.00 day 1 day 470.00 470.00

752.50

TOTAL COST OF MATERIAL +


30049.00
LABOUR
Add Contractors Profit 0.000% 0.00
30049.00
30049.00
Rate per Each

Page 128 of 204


S.No SSR No Description Qty Unit Rate Amount

Earthings

38 Providing independent earthing by exacavating a pit to a depth of 2.25Mtr in all soils as per size
specified in the data for Important equipment with 2.5Mtr length 40mm dia 'B' class G.I pipe and 18"
b) labour charges for fixing pipe
dia 3" thick hume pipe ring with R.C.C. Slab cover duly providing staggered holes filling with 20Kg
1 Skilled
Salt andElectrician.
40Kg Charcoal or 40Kg bentonite powder1.00 No 1 No of the pipe
from the bottom 565.00
giving earth 565.00
connection
Sub Total from electrode through G.I strip of 25 x 6mm x 200mm length to be bolted with nut565.00
bolts
including supply and termination of No.8 G.I.wire from bottm of the pipe with all accessories and
a) Material
labour charges complete, as per IS specifications 732/1982 (Part II)

9.4.15 d) 40mm Nominal Bore Medium grade 2.50 Mtr 1 Mtr 350.00 875.00
G.I.Pipe.

9.3.6 25mm x 6 mm G.I.Strip 0.24 Kgs 1 Kg 65.00 15.60

9.3.6 No.8 G.I.Wire 0.83 Kgs 1 kg 65.00 53.95

9.4.20 Drilling of through holes of 12mm dia 16.00 Nos 1 No 6.00 96.00
to G.I pipe.
9.4.21 G.I Nuts, Bolts an Washers each set. 4.00 Sets 1 Set 12.00 48.00

9.4.23 18" dia 3" hume pipe ring. 1.00 No 1 No 300.00 300.00
9.1.10 Hard Coke. 40.00 Kg 1 Kg 21.00 840.00
9.1.11 Salt. 20.00 Kg 1 Kg 16.00 320.00
9.4.17 Earth work excavation of hard gravel 1.27 cum 1 cum 250.00 317.50
soil with small boulders for trench 1st
step of size 1.2 x 0.6 x 0.9 m
(4'x2'x3')
9.4.17 Earth work hard disintegrated rock 1.87 cum 1 cum 250.00 467.50
and boulders for trench 2nd Step of
size 0.9 x 0.6 x 1.2 m (3'x2'x4')

25% extra for narrow trench & pit and 25% 785.00 196.25
back filling with Sand, Coke, Salt etc.,
and leveling
Sundries 5.00
Rate per each 3534.80
Total Cost of Material + Labour 4100.00
Charges Add Contractors Profit 0.000% 0.00
4100.00
Rate per Each 4100.00

39 Providing independent earthing by exacavating a pit to a depth of 2.25Mtr in all soils as per size
specified
b) labour in the data
charges forforfixing
Sophisticated
pipe Electronic equipment with 600mm x 600mm x 3.15mm thick

1 Skilled Electrician. 1.00 No 1 No 565.00 565.00


Sub Total 565.00
a) Material
9.4.15 d) 40mm Nominal Bore Medium grade 2.50 Mtr 1 Mtr 350.00 875.00
G.I.Pipe.
9.3.1 600mm x600mm x 3.15mm thick 10.00 kg 1 kg 590.00 5900.00
copper plate (Per K.G).
9.3.1 25mm x 3mm x 6Mtrs Length Copper 2.98 Kgs 1 Kg 590.00 1758.20
Strip (Per K.G).
9.3.1 Copper plate / Copper strip (Per K.G). 0.22 Kgs 1 Kg 590.00 129.80

Page 129 of 204


S.No SSR No Description Qty Unit Rate Amount

9.4.20 Drilling of through holes of 12mm dia 16.00 Nos 1 No 6.00 96.00
to G.I pipe.
9.4.21 G.I Nuts, Bolts an Washers each set. 4.00 Set 1 Set 12.00 48.00

9.1.10 Hard Coke. 40.00 kg 1 kg 21.00 840.00


9.1.111 Salt. 20.00 kg 1 kg 16.00 320.00
9.4.23 18" dia 3" hume pipe ring. 1.00 No 1 No 300.00 300.00
9.4.17 Earth work excavation of hard gravel 1.27 cum 1 cum 250.00 317.50
soil with small boulders for trench 1st
step of size 1.5 x 0.9 x 0.9 m
(5'x3'x3')
9.4.17 Earth work hard disintegrated rock 1.87 cum 1 cum 250.00 467.50
and boulders for trench 2nd Step of
25% extra
size 1.2 x 0.9forx 1.65
trenches and narrow
m (4'x3'x5.5') 25% 785.00 196.25
Pit, back filling and blending. 11248.25

Sundries such as Lugs and Saddles 7.00

Rate per each 11255.25


Total Cost of Material + Labour 11820.00
Charges
Add Contractors Profit 0.000% 0.00
11820.00
Rate per Each 11820.00

40 Supply and Run of 25mm x 6mm G.I Strip including cost of all accessories and labour charges etc.,
complete. (1.18Kgs/1Mtr)
a) Labour charges :
1 Skilled Electrician. 1.00 day 1 day 565.00 565.00
2 Helper (Electrical). 1.00 day 1 day 470.00 470.00
Labour for 100 Mtrs 1035.00
Labour for 1 Mtr 10.35
b) Material
9.3.6 G.I. Strip / Plate / Wire (per K. G). 118.00 Kgs 1 Kg 65.00 7670.00

Sundries.

Cost of Material for 100 Metres 7670.00


Cost of Material Rate per Mtr= C/100 76.70
Total Cost of Material + Labour
Charges 87.00
Add Contractors Profit 0.000% 0.00
87.00
Rate per Meter 87.00

41 Supply and Run of 40mm x 6mm G.I Strip including cost of all accessories and labour charges etc.,
complete. (1.88 Kg:/ Mtr)
a) Labour charges
1 Skilled Electrician. 1.50 day 1 day 565.00 847.50
2 Helper (Electrical). 1.50 day 1 day 470.00 705.00
Labour for 100 Mtrs 1552.50
Labour for 1 Mtr 15.53
b) Material
9.3.6 G.I. Strip / Plate / Wire (per K. G). 188.00 Kgs 1 Kg 65.00 12220.00

Sundries.

Cost of Material for 100 Metres 12220.00


Cost of Material Rate per Mtr= C/100 122.20
Total Cost of Material + Labour 138.00
Charges
Add Contractors Profit 0.000% 0.00
138.00
Rate per Meter 138.00

42 Supply and Run of 50mm x 6mm G.I Strip including cost of all accessories and labour charges etc.,
complete. (2.36 Kg:/ Mtr)
a) Labour charges
1 Skilled Electrician. 2.00 day 1 day 565.00 1130.00
2 Helper (Electrical). 2.00 day 1 day 470.00 940.00

Page 130 of 204


S.No SSR No Description Qty Unit Rate Amount

Labour for 100 Mtrs 2070.00


Labour for 1 Mtr 20.70
b) Material
9.3.6 G.I. Strip / Plate / Wire (per K. G). 236.00 Kgs 1 Kg 65.00 15340.00

Sundries.

Cost of Material for 100 Metres 15340.00


Cost of Material Rate per Mtr= C/100 153.40
Total Cost of Material + Labour 174.00
Charges
Add Contractors Profit 0.000% 0.00
174.00
Rate per Meter 174.00

43 Supply and Run of 75mm x 6mm G.I Strip including cost of all accessories and labour charges etc.,
complete. ( 3.54 Kg: / Mtr)
a) Labour charges
1 Skilled Electrician. 2.00 day 1 day 565.00 1130.00
2 Helper (Electrical). 3.00 day 1 day 470.00 1410.00
Labour for 100 Mtrs 2540.00
Labour for 1 Mtr 25.40
b) Material
9.3.6 G.I. Strip / Plate / Wire (per K. G). 354.00 Kgs 1 Kg 65.00 23010.00

Sundries.

Cost of Material for 100 Metres 23010.00


Cost of Material Rate per Mtr= C/100 230.10
Total Cost of Material + Labour 256.00
Charges
Add Contractors Profit 0.000% 0.00
256.00
Rate per Meter 256.00

44 Supply and Run of 25mm x 3mm copper strip (Cuurrent Carrying Capacity 270A) including cost of all
accessories and labour
a) Labour charges : charges etc., complete. (0.663Kgs/1Mtr)
1 Skilled Electrician. 1.00 day 1 day 565.00 565.00
2 Helper (Electrical). 1.50 day 1 day 470.00 705.00
Labour for 100 Mtrs 1270.00
Labour for 1 Mtr 12.70
b) Material

9.3.1 Copper plate / Copper strip (Per K.G). 66.30 Kgs 1 Kg 590.00 39117.00

Sundries.

Cost of Material for 100 Metres 39117.00


Cost of Material Rate per Mtr= C/100 391.17
Total Cost of Material + Labour
404.00
Charges
Add Contractors Profit 0.000% 0.00
404.00
Rate per Meter 404.00

45 Supply and Run of 25mm x 6mm copper strip (Cuurrent Carrying Capacity 270A) including cost of all
accessories and labour
a) Labour charges : charges etc., complete. (1.34 Kg / Mtr)
1 Skilled Electrician. 1.00 day 1 day 565.00 565.00
2 Helper (Electrical). 1.75 day 1 day 470.00 822.50
Labour for 100 Mtrs 1387.50
Labour for 1 Mtr 13.88
b) Material
Copper plate / Copper strip (Per K.G).
9.3.1 134.00 Kgs 1 Kg 590.00 79060.00
Sundries.
Cost of Material for 100 Metres 79060.00

Page 131 of 204


S.No SSR No Description Qty Unit Rate Amount

Cost of Material Rate per Mtr= C/100 790.60

Total Cost of Material + Labour


804.00
Charges
Add Contractors Profit 0.000% 0.00
804.00
Rate per Meter 804.00

46 Supply and Run of No.8 SWG G.I wire including cost of all accessories and labour charges etc.,
complete. (0.104Kgs/1Mtr)
a) Labour charges :
1 Helper (Electrical). 2.00 day 1 day 470.00 940.00
Labour for 100 Mtrs 940.00

Labour for 1 Mtr 9.40

b) Material
9.3.6 G.I. Strip / Plate / Wire (per K. G). 10.40 Kgs 1 Kg 65.00 676.00
9.1.4 U Nails. 150.00 Nos 100 Nos 32.00 48.00
Sundries.
Cost of Material for 100 Metres 724.00
Cost of Material Rate per Mtr= C/100 7.24
Total Cost of Material + Labour
17.00
Charges
Add Contractors Profit 0.000% 0.00
17.00

Rate per Meter 17.00

FIXTURES
36/40W Box type tube light
47 Supply and fixing of 1 x 36/40W Box type tube light luminaire powder coated CRCA sheet steel housing
with Electronic
a) Labour Ballast Chokes, with 40 W tube light and all standard accessories Makes : Phillips /
charges
Crompton / Bajaj / Surya.

1 Skilled Electrician. 0.10 day 1 day 565.00 56.50

2 Lineman Electric / Telephone 0.10 day 1 day 470.00 47.00


Labour for 1 No 103.50

b) Material

1.5.4 Supply of 23 / 0060 twin core twisted / 1.00 Mtr 100 Mtrs 980.00 9.80
flat heavy Copper wire.
1.4.4 d) Supply of No.8 Screws of 35/38mm. 2 Nos 100 Nos 100.00 2.00
9.1.2 Rawl Plugs. 2.00 Nos 100 Nos 33.00 0.66
Fixing arrangements on wall with 2 Nos 1 Nos 5.00 10.00
3.6.3 a)
required support on wall
1 x 36/40W Box type tube light 1 Nos 1 Nos 651.00 651.00
SoR-18-19
luminaire
3.8.4 Supply of 36/40W fluorescent tube. 1 Nos 1 Nos 40.00 40.00
Cost of Material for fixing luminaire 713.46
Total Cost of Material + Labour
Charges

817.00

Add Contractors Profit 0.000% 0.00

Page 132 of 204


S.No SSR No Description Qty Unit Rate Amount

817.00
Rate per Each 817.00

Page 133 of 204


S.No SSR No Description Qty Unit Rate Amount

22W, 2300 lumens alluminium body Tubelight


48 Supply, transportation and fixing of 22W, 2300 lumens, 1200mm length LED light housing made with
alluminium anodised body, wide operating voltage with PF≥0.9, Surge protection: > 2KV, THD<10%,
with inbuilt driver and frosted cover CCT: 3000K - 6500K as desired by the department as per IS,
a) Labour charges
minimum CRI≥80 etc., complete with 50,000 burning hours with BIS Certification. LUMINAIRE MAKE:
1 Phillips / OSRAM / GE Venture /Wipro / Crompton
Skilled Electrician. 0.10/ Bajaj
day / Havells / Jaquar / IB565.00
1 day LED /Panasonic / 56.50
Halonix / HPL / Syska / Eveready / Surya /Keselec.LED MAKE : PHILIPS LUMILEDS / CREE /
2 Lineman Electric // Telephone
NICHIA /OSRAM SAMSUNG / LG LEDs. 0.10 day 1 day 470.00 47.00

Labour for 1 No 103.50

b) Material
1.5.4 Supply of 23 / 0060 twin core twisted / 1.00 Mtr 100 Mtrs 980.00 9.80
flat heavy Copper wire.
1.4.4 d) Supply of No.8 Screws of 35/38mm. 2 Nos 100 Nos 100.00 2.00
9.1.2 Rawl Plugs. 2.00 Nos 100 Nos 33.00 0.66
Fixing arrangements on wall with 2 Nos 1 Nos 5.00 10.00
required support on wall
3.9.16 22W, 2300 lumens, 1200mm LED 1 Nos 1 Nos 800.00 800.00
Tube light alluminium body
Cost of Material 822.46
Total Cost of Material + Labour 926.00
Charges

Add Contractors Profit 0.000% 0.00


926.00
Rate per Each 926.00

20W, 2000 lumens alluminium body Tubelight


49 Supply, transportation and fixing of 20W, 2000 lumens, 1200mm length LED retro tube light, housing
made with alluminium anodised body, wide operating voltage with double side connection, PF≥0.9,
Surge protection: > 2KV, THD<15%, with inbuilt driver and frosted cover CCT: 3000K - 6500K as
a) Labour charges
desired by the department and as per IS specifications, minimum CRI≥80,.etc complete with 50,000
1 burning hours with BIS Certification. LUMINAIRE
Skilled Electrician. MAKE:
0.10 day Phillips1 /day
OSRAM / GE Venture /Wipro / 56.50
565.00
Crompton / Bajaj / Havells / Jaquar / IB LED /Panasonic / Halonix / HPL / Syska / Eveready / Surya
2 Lineman Electric
/Keselec.LED / Telephone
MAKE 0.10 day
: PHILIPS LUMILEDS / CREE 1 day / SAMSUNG
/ NICHIA /OSRAM 470.00/ LG LEDs. 47.00

Labour for 1 No 103.50

b) Material
1.5.4 Supply of 23 / 0060 twin core twisted / 1.00 Mtr 100 Mtrs 980.00 9.80
flat heavy Copper wire.
1.4.4 d) Supply of No.8 Screws of 35/38mm. 2 Nos 100 Nos 100.00 2.00
9.1.2 Rawl Plugs. 2.00 Nos 100 Nos 33.00 0.66
Fixing arrangements on wall with 2 Nos 1 Nos 5.00 10.00
required support on wall
3.9.10 20W, 2000 lumens, 1200mm LED Tube 1 Nos 1 Nos 730.00 730.00
light alluminium body
Cost of Material 752.46
Total Cost of Material + Labour 856.00
Charges

Add Contractors Profit 0.000% 0.00


856.00
Rate per Each 856.00

Page 134 of 204


S.No SSR No Description Qty Unit Rate Amount

20W, 2000 lumens PC body Tubelight


50 Supply, transportation and fixing of 20W, 2000 lumens, 1200mm length LED retro tube light, housing
made withcharges
a) Labour PC body, wide operating voltage with Single / double side connection, PF≥0.9, Surge
protection: > 2KV, THD<15%, with inbuilt driver and frosted cover CCT: 3000K - 6500K as desired by
the department and as per IS specifications, minimum CRI≥80,.etc complete with 50,000 burning hours
1 Skilled
with BISElectrician.
Certification. LUMINAIRE MAKE: Phillips0.10/ day
OSRAM / GE 1 day 565.00
Venture /Wipro 56.50
/ Crompton / Bajaj /
2 Havells / Jaquar / IB LED
Lineman Electric / Telephone/Panasonic / Halonix / HPL /
0.10 day Syska / Eveready
1 day / Surya /Keselec.LED
470.00 MAKE
47.00:
PHILIPS LUMILEDS / CREE / NICHIA /OSRAM / SAMSUNG / LG LEDs.

Labour for 1 No 103.50


b) Material

1.5.4 Supply of 23 / 0060 twin core twisted / 1.00 Mtr 100 Mtrs 980.00 9.80
flat heavy Copper wire.
1.4.4 d) Supply of No.8 Screws of 35/38mm. 2 Nos 100 Nos 100.00 2.00
9.1.2 Rawl Plugs. 2.00 Nos 100 Nos 33.00 0.66
Fixing arrangements on wall with 2 Nos 1 Nos 5.00 10.00
required support on wall
3.9.14 20W, 2000 lumens, 1200mm LED Tube 1 Nos 1 Nos 525.00 525.00
light PC Body
Cost of Material 547.46

Total Cost of Material + Labour 651.00


Charges
Add Contractors Profit 0.000% 0.00
651.00
Rate per Each 651.00

36W, 2' x2' (600mm x 600mm) Slim Panel LED luminaire


51 Supply, Transportation and fixing of 36 W Edge lit, 2' x2' (600mm x 600mm) slim panel LED
luminaire
a) Labour Square
chargesHousing Made of Aluminum alloy with corrosion resistant powder coat, with high
1 Skilled Electrician. 0.066 day 1 day 565.00 37.29
2 Lineman Electric / Telephone 0.066 day 1 day 470.00 31.02

3 Helper (Electrical). 0.100 day 1 day 470.00 47.00

Labour for 1 No 115.31


b) Material
1.5.4 Supply of 23 / 0060 twin core twisted / 2.00 Mtr 100 Mtrs 980.00 19.60
flat heavy Copper wire.
Alluminium Flat (As per requirement) 50.00
3.9.15 a) 36W Edge lit, 2' x2' (600mm x600mm) 1 Nos 1 Nos 3620.00 3620.00
slim panel LED luminaire
Cost of Material 3689.60
Total Cost of Material + Labour 3805.00
Charges

Add Contractors Profit 0.000% 0.00


3805.00
Rate per Each 3805.00

18W edge lit LED slimline panel Light


52 Supply, transportation and fixing of 18W edge lit LED slimline panel light Housing made of Pressure
die cast aluminium with Powder coated, round / Square with Protruded high efficiency diffuser, IP20,
a) Labour
with charges voltage range, Power factor > 0.9, Surge protection: > 2KV, System efficacy of >100
wide operating
lumens/watt, CCT: 3000K - 6500K as desired by the department and as per IS, CRI >80, and THD is
1 Skilled
less Electrician.
than 0.066
15% etc., complete with 50,000 burning day with BIS1Certification.
hours day 565.00
LUMINAIRE MAKE:37.29
Phillips / OSRAM / GE Venture /Wipro / Crompton / Bajaj / Havells / Jaquar / IB LED /Panasonic /
Halonix / HPL / Syska / Eveready / Surya /Keselec.LED MAKE : PHILIPS LUMILEDS / CREE /
2 Lineman Electric // Telephone
NICHIA /OSRAM SAMSUNG / LG LEDs. 0.066 day 1 day 470.00 31.02

Page 135 of 204


S.No SSR No Description Qty Unit Rate Amount

3 Helper (Electrical). 0.100 day 1 day 470.00 47.00

Labour for 1 No 115.31


b) Material
1.5.4 Supply of 23 / 0060 twin core twisted / 1.00 Mtr 100 Mtrs 980.00 9.80
1.4.4 d) flat heavy
Supply Copper
of No.8 wire. of 35/38mm.
Screws 2 Nos 100 Nos 100.00 2.00

9.1.2 Rawl Plugs. 2.00 Nos 100 Nos 33.00 0.66

Fixing arrangements on wall with 2 Nos 1 Nos 5.00 10.00


required support on wall
3.9.7 d) 18W edge lit LED slimline panel Ligh 1 Nos 1 Nos 1300.00 1300.00

Cost of Material 1322.46

Total Cost of Material + Labour 1438.00


Charges
Add Contractors Profit 0.000% 0.00

1438.00

1438.00
Rate per Each

BH/SBH
53 Supply and fixing of ISI mark batten holder / slanting holder Makes : Anchor / Gold Medal Olive / Million
Zoom in lieu of ceiling rose of light point complete with all connections and all labour charges with 3.0W
a) Labour
LED Lamp.charges
Makes:: Phillips / OSRAM / Wipro / Crompton / Bajaj / Havells / Halonix / Jaquar / HPL.

Skilled Electrician. 0.03 day 1 day 565.00 16.95

Helper (Electrical). 0.03 day 1 day 470.00 14.10

Labour for 1 No 31.05

b) Material

1.7.1 n) Supply of BH / SBH 1 No 1 No 18.00 18.00

3.10.1 a) Supply of 0.5W LED Lamp 1 No 1 No 48.00 48.00

1.7.1 m) Less Cost of 3 Plate Jumbo Ceiling 1 No -1 No 19.00 -19.00


Rose
Cost of Material 47.00

Total Cost of Material + Labour 78.00


Charges
Add Contractors Profit 0.000% 0.00

78.00

78.00
Rate per Each

Call Bells & Musical Bells


54 Supply and fixing of Buzzer Type Calling Bell of on 4"x7" decolam block including giving connections,
cost of all accessories and labour charges etc., complete. Makes : GM / Million / Gold Medal / Anchor /
a) Labour charges :
Great white.
1 Skilled Electrician. 0.05 day 1 day 565.00 28.25
2 Helper (Electrical). 0.05 day 1 day 470.00 23.50
Labour for 1 No 51.75

b) Material

1.4.2 b) Supply of Decolam board of size 4" X 1 Nos 1 No 25.00 25.00


7"

Page 136 of 204


S.No SSR No Description Qty Unit Rate Amount

1.7.2 b) Supply of Buzzer Type calling bell 1 Nos 1 No 45.00 45.00

Cost of Material 70.00


Total Cost of Material + Labour
Charges 122.00
Add Contractors Profit 0.000% 0.00
122.00
Rate per Each 122.00

55 Supply and fixing of Ding Dong Bell of Makes : GM / Million / Gold Medal / Anchor / Great white on 4"x7"
decolam block including giving connections, cost of all accessories and labour charges etc., complete.
a) Labour charges :

1 Skilled Electrician. 0.05 day 1 day 565.00 28.25


2 Helper (Electrical). 0.05 day 1 day 470.00 23.50
Labour for 1 No 51.75
b) Material
1.4.2 b) Supply of Decolam board of size 4" X 1 Nos 1 No 25.00 25.00
7"

1.7.2 b) Supply of Ding Dong Bell 1 Nos 1 No 95.00 95.00


Cost of Material 120.00
Total Cost of Material + Labour
172.00
Charges
Add Contractors Profit 0.000% 0.00
172.00
Rate per Each 172.00
Ceiling Fans
56 Supply and transportation of 48" (1200mm) 5 star rated Sweep Ceiling Fan with all accessories etc.,
complete.
Makes : Crompton HS Plus / Havells ES NEO / Orient Energy Star
5.1.2 48" (1200mm) 5 star rated Sweep Each 1 1 Nos 2095.00 2095.00
Ceiling Fan
Transportation 0.02 41.90
2137
Add Contractors Profit 0.000% 0.00
2136.90
Rate per Each 2137.00

Page 137 of 204


S.No SSR No Description Qty Unit Rate Amount

57 Supply and transportation of 48" (1200mm) Sweep decorative Ceiling Fan with all accessories etc.,
complete.
Makes : Crompton High Speed Decora / Havells Spark Deco / Orient Summer Crown / Panasonic Sprint
5.1.3 Deco / Halonix Sweep
48" (1200mm) Erbon decorative Each 1 1 Nos 2200.00 2200.00
Ceiling Fan
Transportation 0.02 44.00
2244
Add Contractors Profit 0.000% 0.00

2244.00
Rate per Each 2244.00

57 Supply and fixing of 2 Module Modular type Electronic step type Fan Regulator for sweep AC ceiling
fans of 1200mm / 1420mm complete with connections.
Makes : Legrand Myrius / Million mway / Gold Medal Curve / Anchor Roma viola / GM Four-Five /
Havells Fabio / Panasonic Vision / L&T Englaze / Hager Insista / Benlo Vesta / C&S Primo / CPL Vysma
/ Polycab Levana.
a) Labour charges
1 Lineman Electric / Telephone 0.05 Nos 1 Nos 470.00 23.50
Labour for 1 No 23.50

b) Material
1.9.2 n) Supply of Electronic type stepped type 1 Nos 1 Nos 365.00 365.00
Electronic Regulator.
1.3.1 a) Supply of 2 Module box. 1 No 1 No 57.00 57.00
1.3.3 a) Supply of 2 Modular Cover Frame. 1 No 1 No 56.00 56.00
Cost of Material for 1 No 478.00
Total Cost of Material + Labour
502.00
Charges
Add Contractors Profit 0.000% 0.00
502.00
Rate per Each 502.00

58 Labour charges for fixing of ceiling fan and regulator including transportation and giving connections
with twin core wire etc., complete.

a) Labour charges
1 Skilled Electrician. 0.125 day 1 day 565.00 70.63

2 Helper (Electrical). 0.125 day 1 day 470.00 58.75


Labour for 1 No 129.38

b) Material

1.5.4 Supply of 23 / 0060 twin core twisted / 1.00 Mtrs 100 Mtrs 980.00 9.80
flat heavy Copper wire.
Cost of Material for fixing fan 9.80
Total Cost of Material + Labour
139.00
Charges
Add Contractors Profit 0.000% 0.00
139.00

139.00
Rate per Each

Page 138 of 204


S.No SSR No Description Qty Unit Rate Amount

59 Supply and erecting 19/20mm steel tube down rod of one meter length with bolts & nuts duly painted
with matching colour of fan complete
a) Labour charges
Helper (Electrical). 0.100 day 1 day 470.00 47.00
Labour for 1 No 47.00
b) Material
9.1.21 19/20mm steel tube down rod with bolts 1.00 Mtrs 1 Mtrs 87.00 87.00
& nuts for fan with maching colour.

Cost of Material for fixing fan 87.00


Total Cost of Material + Labour 134.00
Charges
Less cost of fan down rod supplied with 0.23 Mtrs 1 Mtrs 87.00 20.01
new fan of about 9" in length equal to
0.23 Metre at above rate
113.99
Add Contractors Profit 0.000% 0.00
Rate per Each 114.00

60 Supply,Transportation of light duty exhaust fan 12"(300 mm) size with metal blades wiremesh with all
accessories
5.1.9 b) Supply etcduty
of light complete
exhaustMakes
fan : CromptonEach/ Havells1 Ventil Air-DB
1 Nos/ Orient 1435.00
hill air. 1435.00
12"(300 mm) size
Transportation 0.02 28.70
1464.00
Add Contractors Profit 0.000% 0.00
1464.00
Rate per Each 1464.00

61 Supply,Transportation of 12" (300mm) ISI, 900 RPM Heavy duty exhaust fan with metallic blades
wiremesh with all accessories etc complete Makes : Crompton / Almounard / Havells Turbo Force SP.
5.1.11 a) Supply of 12" (300mm) ISI, 900 RPM Each 1 1 Nos 2830.00 2830.00
Heavy duty exhaust fan
Transportation 0.02 56.60
2887.00
Add Contractors Profit 0.000% 0.00
2887.00

Rate per Each 2887.00

62 Labour charges for fixing the Light duty exhaust fan in wall with connections with twin core wire and
masonary work of making hole, finishing etc., complete.
a) Labour charges
1 Skilled Electrician. 0.250 day 1 day 565.00 141.25
2 Lineman Electric / Telephone 0.250 day 1 day 470.00 117.50
3 Mason Cl- I / Brick layer Cl- I 0.250 day 1 day 500.00 125.00
Labour for 1 No 383.75

1.5.4 Supply of 23 / 0060 twin core twisted / 1.00 Mtrs 100 Mtrs 980.00 9.80
flat heavy Copper wire.
9.4.11 Cement. 25 Kg 1 Kg 8.00 200.00
Sundries such as Sand, Bolt, Nuts etc. 1 Job 1 Job 6.00 6.00

Cost of Material for fixing fan 215.80

Page 139 of 204


S.No SSR No Description Qty Unit Rate Amount

Total Cost of Material + Labour


Charges

600.00

Add Contractors Profit 0.000% 0.00


600.00
Rate per Each 600.00

63 Supply, Transportation and Fixing of GI Louver shutter suitable for 12" (300mm) Exhaust fan of Best
quality and makes as directed with fixing arrangments and all labour charges etc., complete.

a) Labour charges
1 Skilled Electrician. 0.050 day 1 day 565.00 28.25
2 Lineman Electric / Telephone 0.050 day 1 day 470.00 23.50
Labour for 1 No 51.75
b) Material

3 Sundries such as Sand, Bolt, Nuts etc. 1 Job 1 Job 10.50 10.50

5.1.12 b) Louver shutter suitable for 12" (300mm) 1 No 1 No 150.00 150.00


Exhaust fan (MR)
Cost of Material for 1 No 160.50
Total Cost of Material + Labour 212.00
Charges
Add Contractors Profit 0.000% 0.00

212.00
Rate per Each 212.00
U.G Cables
64 4.1.1 f) Supply of 16 Sqmm 4 Core XLPE RMS 1 1 One Rmt 162.00 162.00
insulated, 1100V grade armoured
alluminium cable with ISI mark as per
specification confirming to IS:7098
(Part - I)
Makes : Torrent / Unicab / Universal /
Polycab / Havells / Gloster / KEI /
Finolex / Paragon.

Page 140 of 204


S.No SSR No Description Qty Unit Rate Amount

Add Contractors Profit 0.000% 0.00

162.00
Rate per Meter 162.00

65 4.1.1 g) Supply of 25 Sqmm 3.5 Core XLPE RMS 1 1 One Rmt 207.00 207.00
insulated, 1100V grade armoured
alluminium cable with ISI mark as per
specification confirming to IS:7098
(Part - I)
Makes :Torrent / Unicab / Universal /
Polycab / Havells / Gloster / KEI /
Finolex / Paragon.

Add Contractors Profit 0.000% 0.00

207.00
Rate per Meter 207.00

66 4.1.1 h) Supply of 35 Sqmm 3.5 Core XLPE RMS 1 1 One Rmt 247.00 247.00
insulated, 1100V grade armoured
alluminium cable with ISI mark as per
specification confirming to IS:7098
(Part - I)
Makes :Torrent / Unicab / Universal /
Polycab / Havells / Gloster / KEI /
Finolex / Paragon.

Add Contractors Profit 0.000% 0.00

247.00
Rate per Meter 247.00

67 4.1.1 i) Supply of 50 Sqmm 3.5 Core XLPE RMS 1 1 One Rmt 326.00 326.00
insulated, 1100V grade armoured
alluminium cable with ISI mark as per
specification confirming to IS:7098
(Part - I)
Makes :Torrent / Unicab / Universal /
Polycab / Havells / Gloster / KEI /
Finolex / Paragon.

Page 141 of 204


S.No SSR No Description Qty Unit Rate Amount

Add Contractors Profit 0.000% 0.00

326.00
Rate per Meter 326.00

68 4.1.1 j) Supply of 70 Sqmm 3.5 Core XLPE RMS 1 1 One Rmt 420.00 420.00
insulated, 1100V grade armoured
alluminium cable with ISI mark as per
specification confirming to IS:7098
(Part - I)
Makes : Torrent / Unicab / Universal /
Polycab / Havells / Gloster / KEI /
Finolex / Paragon.

Add Contractors Profit 0.000% 0.00

420.00
Rate per Meter 420.00

69 4.1.1 k) Supply of 95 Sqmm 3.5 Core XLPE RMS 1 1 One Rmt 547.00 547.00
insulated, 1100V grade armoured
alluminium cable with ISI mark as per
specification confirming to IS:7098
(Part - I)
Makes : Torrent / Unicab / Universal /
Polycab / Havells / Gloster / KEI /
Finolex / Paragon.

Add Contractors Profit 0.000% 0.00

547.00
Rate per Meter 547.00

70 4.1.1 L) Supply of 120 Sqmm 3.5 Core XLPE RMS 1 1 One Rmt 670.00 670.00
insulated, 1100V grade armoured
alluminium cable with ISI mark as per
specification confirming to IS:7098
(Part - I)
Makes : Torrent / Unicab / Universal /
Polycab / Havells / Gloster / KEI /
Finolex / Paragon.

Add Contractors Profit 0.000% 0.00

Page 142 of 204


S.No SSR No Description Qty Unit Rate Amount

670.00
Rate per Meter 670.00

71 4.1.1 m) Supply of 150 Sqmm 3.5 Core XLPE RMS 1 1 One Rmt 760.00 760.00
insulated, 1100V grade armoured
alluminium cable with ISI mark as per
specification confirming to IS:7098
(Part - I)
Makes : Torrent / Unicab / Universal /
Polycab / Havells / Gloster / KEI /
Finolex / Paragon.

Add Contractors Profit 0.000% 0.00

760.00
Rate per Meter 760.00

72 4.1.1 n) Supply of 185 Sqmm 3.5 Core XLPE RMS 1 1 One Rmt 933.00 933.00
insulated, 1100V grade armoured
alluminium cable with ISI mark as per
specification confirming to IS:7098
(Part - I)
Makes : Torrent / Unicab / Universal /
Polycab / Havells / Gloster / KEI /
Finolex / Paragon.

Add Contractors Profit 0.000% 0.00


933.00
Rate per Meter 933.00

73 4.1.1 o) Supply of 240 Sqmm 3.5 Core XLPE RMS 1 1 One Rmt 1185.00 1185.00
insulated, 1100V grade armoured
alluminium cable with ISI mark as per
specification confirming to IS:7098
(Part - I)
Makes : Torrent / Unicab / Universal /
Polycab / Havells / Gloster / KEI /
Finolex / Paragon.

Add Contractors Profit 0.000% 0.00


1185.00
Rate per Meter 1185.00

74 4.1.1 p) Supply of 300 Sqmm 3.5 Core XLPE RMS 1 1 One Rmt 1447.00 1447.00
insulated, 1100V grade armoured
alluminium cable with ISI mark as per
specification confirming to IS:7098
(Part - I)
Makes : Torrent / Unicab / Universal /
Polycab / Havells / Gloster / KEI /
Finolex / Paragon.

Add Contractors Profit 0.000% 0.00


1447.00
Rate per Meter 1447.00

75 4.1.1 q) Supply of 400 Sqmm 3.5 Core XLPE RMS 1 1 One Rmt 1815.00 1815.00
insulated, 1100V grade armoured
alluminium cable with ISI mark as per
specification confirming to IS:7098
(Part - I)
Makes : Torrent / Unicab / Universal /
Polycab / Havells / Gloster / KEI /
Finolex / Paragon.

Add Contractors Profit 0.000% 0.00

Page 143 of 204


S.No SSR No Description Qty Unit Rate Amount

1815.00

Rate per Meter 1815.00

76 Earth work excavation of Trench in hard ground soil and Sand filling shall be provided at the bottom of
trench before
b) Labour laying the cable and laying of U.G cables up to 70 sqmm covering the cable with back
charges
1 Skilled Electrician. 1.00 day 1 day 565.00 565.00
2 Helper (Electrical). 2.00 day 1 day 470.00 940.00
3 Man Mazdoor for spreading the sand 2.50 day 1 day 445.00 1112.50
and back filling of the exacavated soils.

4 Man Mazdoor for concreating and 2.00 day 1 day 445.00 890.00
embedding of cable route indicators.
Labour Charges for 100 Mtrs 3507.50
Labour Charges for 1 Mtr 35.08
a) Material
9.4.17 Earth work excacvation including all 36.00 Cum 1 Cum 250.00 9000.00
soils for trench,
9.4.12 Cost of Sand. 4.00 Cum 1 Cum 600.00 2400.00
9.4.13 Cost of Bricks. 1000.00 Nos 952 Nos 4000.00 3808.00
9.4.11 Cement. 25.00 Kg 1 Kg 8.00 200.00
9.1.25 Cable root Indicators. 12.00 Nos 1 Nos 92.00 1104.00
Cost of Material for laying of cable in 100.00 Mtrs 16512.00
trench for
Cost of Material for laying of cable in 1.00 Mtrs 165.12
trench for
Total Cost of Material + Labour 200.00
Charges
Add Contractors Profit 0.000% 0.00
200.00

Rate per Meter 200.00

77 Earth work excavation of Trench in hard ground soil and Sand filling shall be provided at the bottom of
trench before
b) Labour laying the cable and laying of U.G cables from 95 Sqmm up to 420 sqmm covering the
charges
1 Skilled Electrician. 1.60 day 1 day 565.00 904.00
2 Helper (Electrical). 3.30 day 1 day 470.00 1551.00
3 Man Mazdoor for spreading the sand 2.50 day 1 day 445.00 1112.50
and back filling of the exacavated soils.

4 Man Mazdoor for concreating and 2.00 day 1 day 445.00 890.00
embedding of cable route indicators.
Labour Charges for 100 Mtrs 4457.50
Labour Charges for 1 Mtr 44.58
a) Material
9.4.17 Earth work excacvation 36.00 Cum 1 Cum 250.00 9000.00
9.1.51 Cost of Sand. 4.00 Cum 1 Cum 600.00 2400.00
9.4.13 Cost of Bricks. 1000.00 Nos 952 Nos 4000.00 3808.00
9.4.11 Cement. 25.00 Kg 1 Kg 8.00 200.00
9.1.25 Cable root Indicators. 12.00 Nos 1 Nos 92.00 1104.00

Cost of Material for laying of cable in 100.00 Mtrs 16512.00


trench for
Cost of Material for laying of cable in 1.00 Mtrs 165.12
trench for
Total Cost of Material + Labour 209.00
Charges
Add Contractors Profit 0.000% 0.00
209.00

Page 144 of 204


S.No SSR No Description Qty Unit Rate Amount

Rate per Meter 209.00

78 Laying of PVC armoured under ground cable up to 95 Sqmm fixing on chromium plated metallic base
saddles on wall as per IS 1255 and as directed by the department including cost and conveyance of all
b) Labour charges
materials and labour charges etc., complete.
1 Skilled Electrician. 1.50 day 1 day 565.00 847.50
2 Helper (Electrical). 2.00 day 1 day 470.00 940.00
Labour Charges for 100 Mtrs 1787.50
Labour Charges for 1 Mtr 17.88
a) Material
9.1.2 Rawl Plugs. 4.00 Nos 100 Nos 33.00 1.32
1.4.4 d) Supply of No.8 Screws of 35/38mm. 4.00 Nos 100 Nos 100.00 4.00
9.4.23 f) Supply of Saddle / Clamps for Cable. 2.00 Nos 100 Nos 550.00 11.00

Cost of Material for Laying on wall for 1.00 Mtr 16.32


Total Cost of Material + Labour 35.00
Charges
Add Contractors Profit 0.000% 0.00
35.00
Rate per Meter 35.00

79 Laying of PVC armoured under ground cable from 120 Sq.mm to 400 Sqmm fixing on chromium plated
metallic
b) Labourbase saddles on wall as per IS 1255 and as directed by the department including cost and
charges
1 Skilled Electrician. 1.50 day 1 day 565.00 847.50
2 Helper (Electrical). 2.00 day 1 day 470.00 940.00
Labour Charges for 100 Mtrs 1787.50
Labour Charges for 1 Mtr 17.88
a) Material
9.1.2 Rawl Plugs. 4.00 Nos 100 Nos 33.00 1.32
1.4.4 f) Supply of No.8 Screws of 63/75mm. 4.00 Nos 100 Nos 140.00 5.60

9.4.23 g) Supply of Saddle / Clamps for Cable. 2.00 Nos 100 Nos 850.00 17.00

23.92
Total Cost of Material + Labour
Charges 42.00
Add Contractors Profit 0.000% 0.00
42.00
Rate per Meter 42.00

Page 145 of 204


S.No SSR No Description Qty Unit Rate Amount

Cable Terminations:
80 Termination of UG cables of 4 core 10 sq.mm & 4 core 16 sq.mm including with required Heavy
duty cablecharges
b) Labour glands & Lugs complete with all required accessories as directed by the department
1 Skilled Electrician. 0.020 day 1 day 565.00 11.30
2 Lineman Electric / Telephone 0.020 day 1 day 470.00 9.40
3 Helper (Electrical). 0.020 day 1 day 470.00 9.40
Labour Charges for each 30.10
a) Material
4.3.1 b) Glands for 4 core XLPE armoured 1.00 Nos 1 Nos 90.00 90.00
cable up to 16.0 Sq.mm

4.4.2 a) aluminium lugs for cable upto 16 4.00 Nos 1 Nos 12.00 48.00
Sq.mm
138.00
Total Cost of Material + Labour 168.00
Charges
Add Contractors Profit 0.000% 0.00
168.00
Rate per Each 168.00

81 Termination of UG cables of 3.5 core 25 Sq.mm including with required Heavy duty cable glands,
Lugs complete
b) Labour with all required accessories as directed by the department including cost and
charges
1 Skilled Electrician. 0.020 day 1 day 565.00 11.30
2 Lineman Electric / Telephone 0.020 day 1 day 470.00 9.40
3 Helper (Electrical). 0.020 day 1 day 470.00 9.40
Labour Charges for each 30.10
a) Material
4.3.1 c) glands for 3.5 core XLPE armoured 1.00 Nos 1 Nos 130.00 130.00
cable from 25 Sqmm to 50.0 Sq.mm

4.4.2 a) aluminium lugs for cable upto 16 1.00 Nos 1 Nos 12.00 12.00
Sq.mm

4.4.2 b) aluminium lugs confirming to I.S 3.00 Nos 1 Nos 14.00 42.00
specifications for cable of 25 Sq.mm

184.00
Total Cost of Material + Labour 214.00
Charges
Add Contractors Profit 0.000% 0.00
214.00
Rate per Each 214.00

82 Termination of UG cables of 3.5 core 35 Sq.mm including with required Heavy duty cable glands,
Lugs complete
b) Labour with all required accessories as directed by the department including cost and
charges
1 Skilled Electrician. 0.020 day 1 day 565.00 11.30
2 Lineman Electric / Telephone 0.020 day 1 day 470.00 9.40
3 Helper (Electrical). 0.020 day 1 day 470.00 9.40
Labour Charges for each 30.10
a) Material
4.3.1 c) glands for 3.5 core XLPE armoured 1.00 Nos 1 Nos 130.00 130.00
cable from 25 Sqmm to 50.0 Sq.mm

4.4.2 a) aluminium lugs for cable upto 16 1.00 Nos 1 Nos 12.00 12.00
Sq.mm

Page 146 of 204


S.No SSR No Description Qty Unit Rate Amount

4.4.2 c) aluminium lugs for cable of 35 3.00 Nos 1 Nos 17.00 51.00
Sq.mm
193.00
Total Cost of Material + Labour
Charges 223.00
Add Contractors Profit 0.000% 0.00
223.00
Rate per Each 223.00

83 Termination of UG cables of 3.5 core 50 Sq.mm including with required Heavy duty cable glands,
Lugs complete
b) Labour with all required accessories as directed by the department including cost and
charges

1 Skilled Electrician. 0.020 day 1 day 565.00 11.30

2 Lineman Electric / Telephone 0.020 day 1 day 470.00 9.40


3 Helper (Electrical). 0.020 day 1 day 470.00 9.40
Labour Charges for each 30.10
a) Material
4.3.1 c) glands for 3.5 core XLPE armoured 1.00 Nos 1 Nos 130.00 130.00
cable from 25 Sqmm to 50.0 Sq.mm

4.4.2 b) aluminium lugs for cable of 25 1.00 Nos 1 Nos 14.00 14.00
Sq.mm

4.4.2 d) aluminium lugs for cable of 50 3.00 Nos 1 Nos 19.00 57.00
Sq.mm
201.00
Total Cost of Material + Labour
Charges 231.00
Add Contractors Profit 0.000% 0.00
231.00
Rate per Each 231.00

84 Termination of UG cables of 3.5 core 70 Sq.mm including with required Heavy duty cable glands,
Lugs complete with all required accessories as directed by the department including cost and
conveyance of all materials and labour charges etc., complete.
b) Labour charges

1 Skilled Electrician. 0.020 day 1 day 565.00 11.30


2 Lineman Electric / Telephone 0.020 day 1 day 470.00 9.40
3 Helper (Electrical). 0.020 day 1 day 470.00 9.40
Labour Charges for each 30.10
a) Material
4.3.1 d) glands for 3.5 core XLPE armoured 1.00 Nos 1 Nos 200.00 200.00
cable from 70 Sqmm
4.4.2 c) aluminium lugs for cable of 35 1.00 Nos 1 Nos 17.00 17.00
Sq.mm

4.4.2 e) aluminium lugs confirming to I.S 3.00 Nos 1 Nos 24.00 72.00
specifications for cable of 70 Sq.mm

289.00
Total Cost of Material + Labour 319.00
Charges
Add Contractors Profit 0.000% 0.00
319.00
Rate per Each 319.00

Page 147 of 204


S.No SSR No Description Qty Unit Rate Amount

85 Termination of UG cables of 3.5 core 95 Sq.mm including with required Heavy duty cable glands,
Lugs complete
b) Labour with all required accessories as directed by the department including cost and
charges
1 Skilled Electrician. 0.030 day 1 day 565.00 16.95
2 Lineman Electric / Telephone 0.030 day 1 day 470.00 14.10
3 Helper (Electrical). 0.030 day 1 day 470.00 14.10
Labour Charges for each 45.15
a) Material
4.3.1 d) glands for 3.5 core XLPE armoured 1.00 Nos 1 Nos 200.00 200.00
cable from 95 Sqmm
4.4.2 d) aluminium lugs for cable of 50 Sq.mm 1.00 Nos 1 Nos 19.00 19.00

4.4.2 f) aluminium lugs for cable of 95 3.00 Nos 1 Nos 25.00 75.00
Sq.mm
294.00
Total Cost of Material + Labour
Charges 339.00
Add Contractors Profit 0.000% 0.00
339.00
Rate per Each 339.00

86 Termination of UG cables of 3.5 core 120 Sq.mm including with required Heavy duty cable glands,
Lugs complete
b) Labour with all required accessories as directed by the department including cost and
charges
1 Skilled Electrician. 0.030 day 1 day 565.00 16.95
2 Lineman Electric / Telephone 0.030 day 1 day 470.00 14.10
3 Helper (Electrical). 0.030 day 1 day 470.00 14.10
Labour Charges for each 45.15
a) Material
4.3.1 e) glands for 3.5 core XLPE armoured 1.00 Nos 1 Nos 335.00 335.00
cable from 120 Sqmm
4.4.2 e) aluminium lugs for cable of 70 1.00 Nos 1 Nos 24.00 24.00
Sq.mm

4.4.2 g) aluminium lugs for cable of 120 3.00 Nos 1 Nos 35.00 105.00
Sq.mm
464.00
Total Cost of Material + Labour
Charges 509.00
Add Contractors Profit 0.000% 0.00
509.00
Rate per Each 509.00

87 Termination of UG cables of 3.5 core 150 Sq.mm including with required Heavy duty cable glands,
Lugs complete
b) Labour with all required accessories as directed by the department including cost and
charges
1 Skilled Electrician. 0.040 day 1 day 565.00 22.60
2 Lineman Electric / Telephone 0.030 day 1 day 470.00 14.10
3 Helper (Electrical). 0.030 day 1 day 470.00 14.10
Labour Charges for each 50.80
a) Material
4.3.1 e) glands for 3.5 core XLPE armoured 1.00 Nos 1 Nos 335.00 335.00
cable from 150.0 Sq.mm

Page 148 of 204


S.No SSR No Description Qty Unit Rate Amount

4.4.2 f) aluminium lugs for cable of 95 Sq.mm 1.00 Nos 1 Nos 25.00 25.00

4.4.2 h) aluminium lugs confirming to I.S 3.00 Nos 1 Nos 45.00 135.00
specifications for cable of 150 Sq.mm

495.00
Total Cost of Material + Labour
Charges 546.00
Add Contractors Profit 0.000% 0.00
546.00
Rate per Each 546.00

88 Termination of UG cables of 3.5 core 185 Sq.mm including with required Heavy duty cable glands,
Lugs complete
b) Labour with all required accessories as directed by the department including cost and
charges
1 Skilled Electrician. 0.080 day 1 day 565.00 45.20
2 Lineman Electric / Telephone 0.080 day 1 day 470.00 37.60
3 Helper (Electrical). 0.080 day 1 day 470.00 37.60
Labour Charges for each 120.40
a) Material
4.3.1 f) glands for 3.5 core XLPE armoured 1.00 Nos 1 Nos 415.00 415.00
cable for 185 Sqmm
4.4.2 f) aluminium lugs confirming to I.S 1.00 Nos 1 Nos 25.00 25.00
specifications for cable of 95 Sq.mm.

4.4.2 i) aluminium lugs confirming to I.S 3.00 Nos 1 Nos 58.00 174.00
specifications for cable of 185 Sq.mm

614.00
Total Cost of Material + Labour
Charges 734.00
Add Contractors Profit 0.000% 0.00
734.00
Rate per Each 734.00

89 Termination of UG cables of 3.5 core 240 Sq.mm including with required Heavy duty cable glands,
Lugs complete
b) Labour with all required accessories as directed by the department including cost and
charges
1 Skilled Electrician. 0.100 day 1 day 565.00 56.50
2 Lineman Electric / Telephone 0.100 day 1 day 470.00 47.00
3 Helper (Electrical). 0.100 day 1 day 470.00 47.00
Labour Charges for each 150.50
a) Material
4.3.1 g) glands for 3.5 core XLPE armoured 1.00 Nos 1 Nos 480.00 480.00
cable for 240Sqmm
4.4.2 g) aluminium lugs for cable of 120 1.00 Nos 1 Nos 35.00 35.00
Sq.mm

4.4.2 j) aluminium lugs for cable of 240 3.00 Nos 1 Nos 84.00 252.00
Sq.mm
767.00
Total Cost of Material + Labour
Charges 918.00
Add Contractors Profit 0.000% 0.00
918.00
Rate per Each 918.00

90 Termination of UG cables of 3.5 core 300 Sq.mm including with required Heavy duty cable glands,
Lugs complete with all required accessories as directed by the department including cost and

Page 149 of 204


S.No SSR No Description Qty Unit Rate Amount

b) Labour charges
1 Skilled Electrician. 0.100 day 1 day 565.00 56.50
2 Lineman Electric / Telephone 0.100 day 1 day 470.00 47.00
3 Helper (Electrical). 0.100 day 1 day 470.00 47.00
Labour Charges for each 150.50
a) Material
4.3.1 h) glands for 3.5 core XLPE armoured 1.00 Nos 1 Nos 600.00 600.00
cable for 300Sqmm
4.4.2 h) aluminium lugs for cable of 150 1.00 Nos 1 Nos 45.00 45.00
Sq.mm

4.4.2 k) aluminium lugs for cable of 300 3.00 Nos 1 Nos 110.00 330.00
Sq.mm
975.00
Total Cost of Material + Labour
Charges 1126.00
Add Contractors Profit 0.000% 0.00
1126.00

Rate per Each 1126.00

91 Termination of UG cables of 3.5 core 400 Sq.mm including with required Heavy duty cable glands,
Lugs complete
b) Labour with all required accessories as directed by the department including cost and
charges
1 Skilled Electrician. 0.150 day 1 day 565.00 84.75

2 Lineman Electric / Telephone 0.150 day 1 day 470.00 70.50


3 Helper (Electrical). 0.200 day 1 day 470.00 94.00
Labour Charges for each 249.25
a) Material
4.3.1 i) glands for 3.5 core XLPE armoured 1.00 Nos 1 Nos 700.00 700.00
cable for 400 Sqmm
4.4.2 i) aluminium lugs for cable of 185 1.00 Nos 1 Nos 58.00 58.00
Sq.mm.
4.4.2 L) aluminium lugs confirming to I.S 3.00 Nos 1 Nos 180.00 540.00
specifications for cable of 400 Sq.mm

1298.00
Total Cost of Material + Labour
Charges 1547.00
Add Contractors Profit 0.000% 0.00
1547.00
Rate per Each 1547.00

92 4.9.1 k) Supply and Installation of 300mm x 1.00 Mtr 1 Mtr 600.00 600.00
50mm x 1.6 mm thick GI perforated
cable tray with out cover along with
required angle supports, with coupler
plates, Anchor bolts and nuts etc
complete and the tray should be fitted
on the wall / Ceiling etc. complete for
finished item of Add
work.Contractors Profit 0.000% 0.00

Page 150 of 204


S.No SSR No Description Qty Unit Rate Amount

600.00
Rate per Meter 600.00

93 4.9.1 L) Supply and Installation of 150mm x 1.00 Mtr 1 Mtr 325.00 325.00
50mm x 1.6 mm thick GI perforated
cable tray withAddoutContractors
cover alongProfit
with 0.000% 0.00
required angle supports, with coupler
plates, Anchor bolts and nuts etc 325.00
complete and the tray should be fitted
on the wall / Ceiling etc. complete for
finished item of work for Rate peritem
finished Meter
of 325.00
work.
Telephone
94 Supply, Transportation and Run of 1 of 2 Pair, 0.5mm telephone copper wire in the existing cable tray /
conduit pipe and
Taking Output labour
= 100 M charges etc., complete. Makes : Finolex / Delton / Surabi / Polycab
a) Material
8.1.1 a) 2 pair telephone wire 0.5mm 100 M 1 1 rmt 910.00 910
b) Labour charges :

1 Skilled Electrician day 0.50 1 day 565.00 282.5


2 Semi Skilled Electrician day 1.00 1 day 470.00 470
3 Helpers day 0.50 1 day 470.00 235
Sundries LS 1
C) Cost for 100 RM 1897.5
Rate per Metre 19.00
Add Contractors Profit 0.000% 0.00
Rate per Meter 19.00

95 Supply and fixing of Modular telephone Jack with connector on modular box with cover frame in
existing
a) Labourconsealed
charges : pipe wiring including cost and coveyance of all material and all labour charges etc.,
1 Lineman Electric / Telephone 0.050 day 1 day 470.00 23.50
Labour for 1 No 23.50
b) Material
1.3.1 a) Supply of 1 or 2 Module box. 1.00 Nos 1 No 57.00 57.00

1.3.3 a) Supply of 1 or 2 Modular Cover Frame. 1.00 Nos 1 No 56.00 56.00

1.9.2 o) Supply of Modular socket type 1.00 Nos 1 No 63.00 63.00


Telephone jack with Connector.
Cost of Material 176.00
Total Cost of Material + Labour
200.00
Charges
Add Contractors Profit 0.000% 0.00
200.00
Hence Rate allowed 200.00

96 Supply, Transportation and Run of 1 of 10 Pair, telephone copper wire in the existing cable tray/
conduit pipe
b) Labour and labour charges etc., complete. Makes : Finolex / Delton / Surabi / Polycab.
charges
1 Skilled Electrician. 0.50 day 1 day 565.00 282.50
2 Lineman Electric / Telephone 1.00 day 1 day 470.00 470.00
3 Helper (Electrical). 1.00 day 1 day 470.00 470.00
Labour for 100 Mtrs 1222.50
Labour for 1 Mtr 12.23

a) Material
8.1.1 c) Supply of 10 Pair telephone Copper 1.00 Mtrs 1 Mtrs 36.00 36.00
wire.
Cost of Material for 1 Mtrs 36.00
Total Cost of Material + Labour
Charges 48.00
Add Contractors Profit 0.000% 0.00
48.00
Rate per Meter 48.00

97 Supply, Transportation and Run of 1 of 20 Pair, telephone copper wire in the existing cable tray/
conduit pipe
b) Labour and labour charges etc., complete. Makes : Finolex / Delton / Surabi / Polycab.
charges

Page 151 of 204


S.No SSR No Description Qty Unit Rate Amount

1 Skilled Electrician. 0.50 day 1 day 565.00 282.50


2 Lineman Electric / Telephone 1.00 day 1 day 470.00 470.00
3 Helper (Electrical). 1.00 day 1 day 470.00 470.00
Labour for 100 Mtrs 1222.50
Labour for 1 Mtr 12.23

a) Material
8.1.1 d) Supply of 20 Pair telephone Copper 1.00 Mtrs 1 Mtrs 70.00 70.00
wire.
Cost of Material for 1 Mtrs 70.00
Total Cost of Material + Labour
Charges 82.00
Add Contractors Profit 0.000% 0.00
82.00
Rate per Meter 82.00

98 Supply, Transportation and Run of 1 of 50 Pair, telephone copper wire in the existing cable tray/ conduit
pipe and labour
b) Labour chargescharges etc., complete. Makes : Finolex / Delton / Surabi / Polycab.
1 Skilled Electrician. 0.50 day 1 day 565.00 282.50
2 Lineman Electric / Telephone 1.00 day 1 day 470.00 470.00
3 Helper (Electrical). 1.00 day 1 day 470.00 470.00
Labour for 100 Mtrs 1222.50
Labour for 1 Mtr 12.23

a) Material
8.1.1 e) Supply of 50 Pair telephone Copper 1.00 Mtrs 1 Mtrs 175.00 175.00
wire.
Cost of Material for 1 Mtrs 175.00
Total Cost of Material + Labour
Charges 187.00
Add Contractors Profit 0.000% 0.00
187.00
Rate per Meter 187.00

99 Supply, Transportation and Run of 1 of 100 Pair raiser cable for telephone in the existing cable tray/
conduit pipe
b) Labour and labour charges etc., complete. Makes : Finolex / Delton / Surabi / Polycab.
charges
1 Skilled Electrician. 0.50 day 1 day 565.00 282.50
2 Lineman Electric / Telephone 1.00 day 1 day 470.00 470.00
3 Helper (Electrical). 1.00 day 1 day 470.00 470.00

Labour for 100 Mtrs 1222.50


Labour for 1 Mtr 12.23
a) Material
8.1.10 100 Pair raiser cable for telephone 1.00 Mtrs 1 Mtrs 350.00 350.00
Cost of Material for 1 Mtrs 350.00
Total Cost of Material + Labour
362.00
Charges
Add Contractors Profit 0.000% 0.00
362.00
Rate per Meter 362.00

100 Supply anf fixing of 200 pair Telephone distribution box with back mount frame, krone connector,
powder coated metal body with lock and key arrangement. Make:Krone
b) Labour charges
1 Skilled Electrician. 0.50 day 1 day 565.00 282.50

2 Lineman Electric / Telephone 0.50 day 1 day 470.00 235.00


Labour Charges 517.50
a) Material
8.1.2 d) 200 Pair MDF box 1.00 No 1 Each 7000.00 7000.00
Cost of Material for 1 Mtrs 7000.00
Total Cost of Material + Labour
7518.00
Charges
Add Contractors Profit 0.000% 0.00
7518.00

Page 152 of 204


S.No SSR No Description Qty Unit Rate Amount

Rate per Each 7518.00

101 Supply anf fixing of 100 pair Telephone distribution box with back mount frame, krone connector,
powder coated metal body with lock and key arrangement. Make:Krone
b) Labour charges
1 Skilled Electrician. 0.15 day 1 day 565.00 84.75

2 Lineman Electric / Telephone 0.15 day 1 day 470.00 70.50


Labour Charges 155.25
a) Material
8.1.9 100 Pair MDF box 1.00 No 1 Each 3300.00 3300.00
Cost of Material for 1 Mtrs 3300.00
Total Cost of Material + Labour
3455.00
Charges
Add Contractors Profit 0.000% 0.00
3455.00
Rate per Each 3455.00

102 Supply anf fixing of 50 pair Telephone distribution box with back mount frame, krone connector, powder
coated metal body with lock and key arrangement. Make:Krone
b) Labour charges
1 Skilled Electrician. 0.15 day 1 day 565.00 84.75

2 Lineman Electric / Telephone 0.15 day 1 day 470.00 70.50


Labour Charges 155.25
a) Material
8.1.2 c) 50 Pair MDF box 1.00 No 1 Each 1850.00 1850.00
Cost of Material for 1 Mtrs 1850.00
Total Cost of Material + Labour
2005.00
Charges
Add Contractors Profit 0.000% 0.00
2005.00
Rate per Each 2005.00

103 Supply anf fixing of 20 pair Telephone distribution box with back mount frame, krone connector, powder
coated metal body with lock and key arrangement. Make:Krone
b) Labour charges
1 Skilled Electrician. 0.15 day 1 day 565.00 84.75
2 Lineman Electric / Telephone 0.15 day 1 day 470.00 70.50

Labour Charges 155.25


a) Material
8.1.2 b) 20 Pair MDF box 1.00 No 1 Each 880.00 880.00
Cost of Material for 1 Mtrs 880.00
Total Cost of Material + Labour
1035.00
Charges
Add Contractors Profit 0.000% 0.00
1035.00

Rate per Each 1035.00

Supply anf fixing of 10 pair Telephone distribution box with back mount frame, krone connector, powder
104
coated metal body with lock and key arrangement. Make:Krone
b) Labour charges
1 Skilled Electrician. 0.10 day 1 day 565.00 56.50
2 Lineman Electric / Telephone 0.10 day 1 day 470.00 47.00
Labour Charges 103.50
a) Material
8.1.2 a) 10 Pair MDF box 1.00 No 1 Each 580.00 580.00
Cost of Material for 1 Mtrs 580.00
Total Cost of Material + Labour
Charges 684.00
Add Contractors Profit 0.000% 0.00
684.00
Rate per Each 684.00

Page 153 of 204


S.No SSR No Description Qty Unit Rate Amount

LAN

105 Supply and termination of cat-6 RJ 45 out lets including dual face plate of Makes:D Link / AMP / Molex /
Legrand / Krone.
a) Material
8.1.4 a) cat-6 RJ 45 out lets each 1 1 Nos 305.00 305
b) Labour charges :
1 Skilled Electrician. day 0.067 1 day 565.00 37.855
2 Lineman Electric / Telephone day 0.067 1 day 470.00 31.49
Rate per each 374.00
Add Contractors Profit 0.000% 0.00
Rate per Each 374.00

106 Supply and laying of Cat 6 UTP cable including all taxes etc complete.Make:D Link / AMP / Molex /
Legrand / Krone.
a) Material
8.1.3 a) LAN cat -6 100 M 1 1 One RM 2100 2100
b) Labour charges :
1 Skilled Electrician day 0.5 1 day 565.00 282.5
2 Semi Skilled Electrician day 0.5 1 day 470.00 211.5
3 Helpers day 1 1 day 470.00 470
Sundries LS 1 3.25
C) Cost for 100 RM 3067.25
Rate per Metre 31.00

Add Contractors Profit 0.000% 0.00


Rate per Meter 31.00

107 Supply and Fixing of 24 port patch panels etc., complete of Make:D Link / AMP / Molex / Legrand /
Krone
a) Material
8.1.8 24 port patch panels each 1 1 Nos 5800 5800
b) Labour charges :
1 Skilled Electrician day 0.3 1 day 565.00 169.5
2 Semi Skilled Electrician day 0.3 1 day 470.00 141

Cost for Each 6111.00

Add Contractors Profit 0.000% 0.00


Rate per Each 6111.00

108 Supply and Fixing of 8 port managable switch etc., complete of Make:CISCO / Net Gear / HP / D link.
a) Material
8.1.5 c) 8 port switch each 1 1 Nos 1100 1100
b) Labour charges :
1 Skilled Electrician day 0.1 1 day 565.00 56.5
2 Semi Skilled Electrician day 0.1 1 day 470.00 47
Cost for Each 1204.00

Add Contractors Profit 0.000% 0.00


1204.00
Rate per Each

109 Supply and Fixing of 24 port managable switch etc., complete of Make:CISCO / Net Gear / HP / D link.
a) Material
8.1.5 b) 24 port switch each 1 1 Nos 6000 6000
b) Labour charges :
1 Skilled Electrician day 0.3 1 day 565.00 169.5
2 Semi Skilled Electrician day 0.3 1 day 470.00 141
Cost for Each 6311.00

Add Contractors Profit 0.000% 0.00


6311.00
Rate per Each

110 Supply and Fixing of 48 port managable switch etc., complete of Make:CISCO / Net Gear / HP / D link.
a) Material

Page 154 of 204


S.No SSR No Description Qty Unit Rate Amount

8.1.5 b) 48 port switch each 1 1 Nos 13870 13870


b) Labour charges :
1 Skilled Electrician day 0.3 1 day 565.00 169.5
2 Semi Skilled Electrician day 0.3 1 day 470.00 141
Cost for Each 14181.00

Add Contractors Profit 0.000% 0.00


14181.00
Rate per Each

111 Supply and fixing of 6 U Floor / Wall mounting net work Rack with power spike including all
accessories
a) Material etc., complete. Make:HCL / Vall
8.1.11 a) 6 U Floor / Wall mounting net work each 1 1 Nos 4200 4200
Rack
b) Labour charges :
1 Skilled Electrician day 0.3 1 day 565.00 169.5
2 Semi Skilled Electrician day 0.3 1 day 470.00 141
Cost for Each
4511.00

Add Contractors Profit 0.000% 0.00


4511.00
Rate per Each

112 Supply and fixing of 9 U Floor / Wall mounting net work Rack with power spike including all
accessories
a) Material etc., complete. Make:HCL / Vall
8.1.11 b) 9 U Floor / Wall mounting net work each 1 1 Nos 5000 5000
Rack
b) Labour charges :
1 Skilled Electrician day 0.3 1 day 565.00 169.5
2 Semi Skilled Electrician day 0.3 1 day 470.00 141
Cost for Each 5311.00
Add Contractors Profit 0.000% 0.00

Rate per Each 5311.00

113 Supply and fixing of 12 U Floor / Wall mounting net work Rack with power spike including all
accessories
a) Material etc., complete. Make:HCL / Vall
8.1.11 c) 12 U Floor / Wall mounting net work each 1 1 Nos 5800 5800
Rack
b) Labour charges :
Skilled Electrician day 0.3 1 day 565.00 169.5
Semi Skilled Electrician day 0.3 1 day 470.00 141
Cost for Each 6111.00
Add Contractors Profit 0.000% 0.00
Rate per Each 6111.00

114 Supply and fixing of 15 U Floor / Wall mounting net work Rack with power spike including all
accessories
a) Material etc., complete. Make:HCL / Vall
8.1.11 d) 15 U Floor / Wall mounting net work each 1 1 Nos 6600 6600
Rack
b) Labour charges :
1 Skilled Electrician day 0.3 1 day 565.00 169.5
2 Semi Skilled Electrician day 0.3 1 day 470.00 141
Cost for Each 6911.00

Page 155 of 204


S.No SSR No Description Qty Unit Rate Amount

Add Contractors Profit 0.000% 0.00

Rate per Each 6911.00

Street Lights
115 Supply, Transportation and fixing of 1X400 W MH Flood light luminaire with integral weather proof
diecast alluminium
a) Labour charges housing with IP66 protection with Control Gear Box with all standard accessories
1 Skilled Electrician. 0.25 day 1 day 565.00 141.25
2 Lineman Electric / Telephone 0.25 day 1 day 470.00 117.50
3 Helper (Electrical). 0.25 day 1 day 470.00 117.50
Labour for 1 No 376.25
b) Material
1.5.2 b) Supply of 2.5 Sqmm FRLS / HFFR 2.00 Mtrs 100 Mtrs 2140.00 42.80
Copper cable.
9.4.15 b) 40mm Nominal Bore Medium grade 1.00 Mtrs 1 Mtr 350.00 350.00
G.I.Pipe.
Pipe bending charges LS 40.00
M.S flat and welding charges LS 48.00
3.1.1 a) Supply of 400W MH Street light 1 Nos 1 Nos 5500.00 5500.00
luminaire
3.4.1 l) Supply of 400W MH Lamp with ISI 1 Nos 1 Nos 1300.00 1300.00
mark.

Cost of Material for 1 No 7280.80

Total Cost of Material + Labour


Charges 7657.00
Add Contractors Profit 0.000% 0.00
7657.00
Rate per Each 7657.00

116 Supply, Transportation and fixing of 60 W / 65 W LED LED Street light, Body made of high grade
pressure
a) Labourdie – cast Aluminium alloy with corrosion resistant powder coat, having protective toughened
charges
1 Skilled Electrician. 0.25 day 1 day 565.00 141.25
2 Lineman Electric / Telephone 0.25 day 1 day 470.00 117.50
3 Helper (Electrical). 0.25 day 1 day 470.00 117.50
Labour for 1 No 376.25
b) Material
1.5.2 b) Supply of 2.5 Sqmm FRLS / HFFR 2.00 Mtrs 100 Mtrs 2140.00 42.80
Copper cable.
9.4.15 b) 40mm Nominal Bore Medium grade 1.00 Mtrs 1 Mtr 350.00 350.00
G.I.Pipe.
Pipe bending charges LS 40.00
M.S flat and welding charges LS 50.00

3.11.1 d 60 / 65 W 1 Nos 1 Nos 5700.00 5700.00

Page 156 of 204


S.No SSR No Description Qty Unit Rate Amount

Cost of Material for 1 No 6182.80

Total Cost of Material + Labour


6559.00
Charges
Add Contractors Profit 0.000% 0.00
6559.00
Rate per Each 6559.00

117 Supply, Transportation and fixing of 72 W LED LED Street light, Body made of high grade pressure
die – cast charges
a) Labour Aluminium alloy with corrosion resistant powder coat, having protective toughened glass
1 Skilled Electrician. 0.25 day 1 day 565.00 141.25
2 Lineman Electric / Telephone 0.25 day 1 day 470.00 117.50
3 Helper (Electrical). 0.25 day 1 day 470.00 117.50
Labour for 1 No 376.25
b) Material
1.5.2 c) Supply of 2.5 Sqmm FRLS / HFFR 2.00 Mtrs 100 Mtrs 2140.00 42.80
Copper cable.
9.4.15 b) 40mm Nominal Bore Medium grade 1.00 Mtrs 1 Mtr 350.00 350.00
G.I.Pipe.
Pipe bending charges LS 40.00
M.S flat and welding charges LS 50.00

3.11.1 e 72 W 1 Nos 1 Nos 6200.00 6200.00


Cost of Material for 1 No 6682.80

Total Cost of Material + Labour


Charges

7059.00

Add Contractors Profit 0.000% 0.00


7059.00

Rate per Each 7059.00

118 Supply, Transportation and fixing of 90 W LED LED Street light, Body made of high grade pressure
die – cast charges
a) Labour Aluminium alloy with corrosion resistant powder coat, having protective toughened glass
1 Skilled Electrician. 0.25 day 1 day 565.00 141.25
2 Lineman Electric / Telephone 0.25 day 1 day 470.00 117.50
3 Helper (Electrical). 0.25 day 1 day 470.00 117.50
Labour for 1 No 376.25
b) Material
1.5.2 c) Supply of 2.5 Sqmm FRLS / HFFR 2.00 Mtrs 100 Mtrs 2140.00 42.80
Copper cable.

9.4.15 b) 40mm Nominal Bore Medium grade 1.00 Mtrs 1 Mtr 350.00 350.00
G.I.Pipe.
Pipe bending charges LS 40.00
M.S flat and welding charges LS 50.00
3.11.1 f) 90 W 1 Nos 1 Nos 8450.00 8450.00
Cost of Material for 1 No 8932.80

Page 157 of 204


S.No SSR No Description Qty Unit Rate Amount

Total Cost of Material + Labour


Charges 9309.00
Add Contractors Profit 0.000% 0.00
9309.00
Rate per Each 9309.00

Split Airconditioners
Supply, transportation and installation of split AC unit with high wall mounted 100% copper indoor
unit and outdoor condencing unit Hermetically sealed compressor suitable for operation on 230V,
50Hz, 1Phase AC supply capable of performing cooling dehumidifying air circulating and filtering
with cooling andTR
( 1.5 condensing
3 STAR) units with 3.0 mts of copper piping, insulation kit and 4 mts of 3 core
117 copper
1.5 TR 3 Star capable(Voltage
flexible chord range18000
of delivering 160- 264 volts) and cordless remote control with 2 years
BTU/hr
warranty and annual
6.1.1 a) Makes
1.5 Ton: (Carrier
maintenance3 star / Daikin / Blue Star / Hitachi.
rates)
contract. 1 Nos 1 Each 38300 38300.00
6.5.28 Installation charges 1600.00
LS for Hard ware etc.,

Page 158 of 204


S.No SSR No Description Qty Unit Rate Amount

Rate per each 39900


Add Contractors Profit 0.000% 0.00
39900.00
Rate per each 39900.00

( 2.0 TR 2 STAR)
118 2.0 / 1.8 TR 2-3 Star capable of delivering 21600 BTU/hr
6.1.1 b) Makes
2.0 / 1.8: Daikin
TR 2-3/ Star
Thoshiba / O General / Carrier
1 / Blue
NosStar /1Hitachi.
Each 44000 44000.00
6.5.28 Installation charges 1600.00
LS for Hard ware etc.,
Rate per each 45600
Add Contractors Profit 0.000% 0.00
45600.00
Rate per each 45600.00

INVERTER SPLIT AC UNITS (COOLING ONLY)


Supply, transportation and installation of Supply and Transportation of of INVERTER Model Cool
type split AC unit
( 1.5 TRwith high wall mounted Single Split 100% copper indoor and outdoor condencing
3 STAR)
119 1.5 TR 3 Star capable of delivering 18000 BTU/hr and above with operating on refrigerant R-32 / R-
6.2.1 a) 410
1.5 Ton ( 3 star rates) 1 Nos 1 Each 40000 40000.00
6.5.28 Installation charges 1600.00
LS for Hard ware etc.,
Rate per each 41600
Add Contractors Profit 0.000% 0.00
41600.00
Rate per each 41600.00

( 1.8 TR / 2.0 TR 3 STAR)


120 2.0 / 1.8 TR 3 Star capable of delivering 21600 BTU/hr and above with operating on refrigerant R-32
6.2.1 c) /1.8
R-410
TR / 2.0 TR 3 STAR 1 Nos 1 Each 54000 54000.00
6.5.28 Installation charges 1600.00
LS for Hard ware etc.,
Rate per each 55600
Add Contractors Profit 0.000% 0.00
55600.00
Rate per each 55600.00

Stabilizers
121 Supply and erecting fully automatic line voltage stabilizer for operation on input voltage 200 to 250V.
rated for 3 KVA / maximum load and time delay model with Volt meter, selector switch, 6A / 16A
flush type, 5 pin socket for out put and with 3 core flexible chord and 3 pin 6/16A plug top suitable
for refrigerator for continuous operation including cost and conveyance of all mateials and all labour
charges etc., complete. Makes : V-Guard / Real Guard / Uni Stab / ITL

a) Material
6.7.1 c) 3 KVA Stabilizer 1 No 1 each 1900 1900.00
b) Labour Charges

Page 159 of 204


S.No SSR No Description Qty Unit Rate Amount

Skilled Electrician 0.1 day 1 day 565 56.50


Helper 0.1 day 1 day 470 47.00

Transportation Charges on Unit Cost 2% 38.00


Rate per Each 2042.00
Add Contractors Profit 0.000% 0.00
2042.00
Rate per each 2042.00

122 Supply and erecting fully automatic line voltage stabilizer for operation on input voltage 200 to 250V.
rated for 4 KVA maximum load and time delay model with Volt meter, selector switch, 6A / 16A
a) Material
6.7.1 d) 4 KVA Stabilizer 1 No 1 each 2500 2500.00
b) Labour Charges
Skilled Electrician 0.1 day 1 day 565 56.50
Helper 0.1 day 1 day 470 47.00
Transportation Charges on Unit Cost 2% 50.00
Rate per Each 2654.00
Add Contractors Profit 0.000% 0.00
2654.00
Hence Rate allowed 2654.00

Page 160 of 204


S.No SSR No Description Qty Unit Rate Amount

123 Supply and erecting fully automatic line voltage stabilizer for operation on input voltage 200 to 250V.
rated for 5 KVA maximum load and time delay model with Volt meter, selector switch, 6A / 16A
a) Material
6.7.1 e) 5 KVA Stabilizer 1 No 1 each 3000 3000.00
b) Labour Charges
Skilled Electrician 0.1 day 1 day 565 56.50
Helper 0.1 day 1 day 470 47.00
Transportation Charges on Unit Cost 2% 60.00
Rate per Each 3164.00
Add Contractors Profit 0.000% 0.00
3164.00
Hence Rate allowed 3164.00
1 Supply and Transportation of -------------------- single phase ISI submersible motor pumpset suitable for 4"
Bore well. Makes: Varuna / Flowell / Waterman / Techno / Mahavir /unitek/ Fitwell/ Falcon/ Ellen/
Karvel / LPS/ Duke / Varsha / Ajantha.
5.1.2 0.75 HP 8 Stage 5052 Ele SSR Each 1 1 Nos 13500.00 13500.00
Transportation 0.02 270.00
13770
Add Contractors Profit 0.000% 0.00
13770.00
Rate per Each 13770.00

1 Supply and Transportation of ………………….. double walled corrugated HDPE duct made as per
specification BSEN - 500 86/IS 14930 Part-II with all accessories like couplers, bends, end caps, Ts
etc., complete. Makes: DURA LINE (Dura Guard) / Bajaj / Gamson / Ultra Plus

4.8.1 Outer dia 63mm and Inner dia 51mm Rm 1 1 Rm 117.00 117.00
5052 Ele SSR
Transportation 0.02 2.34
119
Add Contractors Profit 0.000% 0.00
119.34
Rate per Each 119.00

1 Providing and errecting heat shrinkable indoor termination kit for 11 KV HTXLPE insulated armoured
cable-------------with necessary materials etc., complete. Makes : Raychem / Transeal / M Sea

4.7.1 70-95 Sqmm 3 core Ele SSR 4.7.1 Each 1 1 Each 8430.00 8430.00
Transportation 0.02 168.60
8599
Add Contractors Profit 0.000% 0.00
8598.60
Rate per Each 8599.00

Page 161 of 204


SPECIFICATION REPORT

Name of the work: Providing Gas Supplying pipeline for Supplying and Centralized
Medical Oxygen to bed for COVID-19 Management in Gandhi Hospital Secunderabab

REVISEDE STIMATE AMOUNT : Rs: 280.60Lakhs

The Estimate for the work of "Providing Gas Supplying pipeline for supplying and
Centralized Medical Oxygen to bed for Covid-19 Management in Gandhi Hospital Secundrabad"
was technically sanctioned for Rs. 280.60 lakhs and the work was awarded to M/s Shree Bharath
Pharma & Medical Oxygen Distributors, Contractor Hyderabad vide agreement No.
03/TSMSIDC/2020-21 dated: 05.05.2020 for Rs. 2,37,35,822/- the estimate contract value of Rs.
2,37,35,822/- (SSR 2020-21) with stipulated (i.e., by 05.05.2020) for completion of work.

The reasons for the deviations are shown in the remarks column of the comparative
statement against respective items. The following are the main item which is exceeding the
estimate quantities as per site conditions which can be accommodated against savings.

Sl. No. Description of Work Remarks


Amount
Quantity Rate
(Rs.)
OXYGEN SYSTEM
Copper pipe Supplimental Item:-
Medical Grade Copper Pipe with Required
Copper FittingsCopper Pipe for Medical As per site
use with 54 OD X 1.2 mm
condition it is
560 Rm 2520 1411200 excuted and
approved
department
agreemnt

Isolation Valve for 54 mm copper pipe


As per site
condition it is
8 Each 5000 40000 excuted and
approved
department
agreemnt

Fully automatic control pannel with non


haloginated polymers 1 Each 476900 476900

Supplimental Sub-Total:- 1928100

Civil Supplemental Items:-

Supply and fixing of 60mm thick wall As per higher


panelling, Having materials 0.5mm authority
thick PPGI on Both Sides of the instruction but
panel.Puff as infilling with Density 40± not sanction
1 2kg/Cu. Mtr.Panel having make ESSAR. 247 Sqm 4650 1148550 estimate for
Panel Colour RAL 9002 with a Supporting Covi-19
structure in MS rectangular pipes Emergency work
96x48x3mm thick, Make :-JINDAL Ground hence it is
Floor & First Floor Excuted
V.P 42/ MB No.540

Page 162 of 204


Supplying and fabricating, erecting and
fixing in position tabular trusses of As per site
approved design with M.S tube condition from
conforming to I.S-1161 specifications oxygen cylinder
3 including roof frame work consisting of 7650 Kgs 118.00 902700 to building main
rafters,ties struts and purlins including line per oxygen
cost of foundations bolts, cleats, pipe line hence it
bearings plates,etc.,complete as per is excuted
the sketch enclosed and including
cost of primary coat with red oxide
V.P 42/
paint including costMBandNo.540
conveyance of
all materials,
Painting two coats labourwith charges
syntheticfor
As psr site
erecting paint
enamel & fixing all structural
Grade-II VOC (Volatilesteel 131.11
6 Sqm 156 20453 condition it
works erecting
Organic Compound) in position and fixing
content less isexcuted
by using
than chain pulley
50 grams/litre over blocks,
primerDerek
coat
polered
of arrangements
oxide
V.P 41/to MB and
new
No.540cranes
iron worketc.,
complete
including in
cost position,
and labour
conveyance
Dismantling, clearing away and carefullycharges
of all
for fabrication,
materials to all
site, incidental
sales & charges,
other
stacking useful materials for re-use and taxes, As per
overheads
incidental,
disposal and contractor
of operational
unserviceable and profit etc.,
all labour
materials with emergency work
complete
charges
100m leadfor finished
etc.,
as and item
directed byof Executive
work as
overheads & for covid-19 not
directed by the
Engineer
contractors Engineer-in-Charge
duly
profit takingfor finished
complete actual
avilable for
premeasurements before(SSdismantling
item of work in all floors. No. 1201,
including all labour charges , overheads & manifold room
7 1212 & 1207). in the premises
contractor profit etc., complete
of gandhi
hospital for
oxygen pipe line
hence it is
excuted

Unreinforced cement concrete up to


2.65 Cum 1520 4028
15cm thickness
V.P 39/ MB No.540
Earth work excavation for foundations
(Manual Means) of buildings, septic
tank, sump, compound wall in ordinary As per
soils and depositing on bank with an emergency work
initial lead of 10m and 1m additional lift for covid-19 not
charges over the initial depth up to 3m avilable for
including all operational,incidental, labour manifold room
8 charges such as shoring, sheeting, 73.29 Cum 239 17516 in the premises
planking, strutting etc., and overheads &
contractors profit complete for finished
of gandhi
item of work excluding dewatering charges hospital for
etc., as per SS 20 B(APSS 308) oxygen pipe line
hence it is
excuted

V.P 39/ MB No.540


Filling with carted gravel in
trenches,sides of foundations and As per
basement with initial lead in layers not emergency work
exceeding 15cm thick,watering and for covid-19 not
ramming including cost and conveyance of
water to work site and all
avilable for
peraitonal,incidental, labour charges,hire manifold room
9 charges of T&P etc., and overheads & 11.7 Cum 389 4551 in the premises
contractors profit complete for fnished item of gandhi
of work(APSS NO.309&310) hospital for
oxygen pipe line
hence it is
excuted

V.P 39/ MB No.540

Page 163 of 204


Plain Cement Concrete (1:5:10)
(cement: fine aggregate: Coarse
aggregate) for foundations and under
flooring bed using coarse aggregate
40mm size hard , machine crushed As per
granite from approved quarry including emergency work
cost and conveyance of all materials like for covid-19 not
cement, sand, coarse aggregate, water avilable for
etc. to site, sales & other taxes on all manifold room
10 materials and including all charges for 24.38 Cum 4121 100470 in the premises
machine mixing, laying concrete in of gandhi
foundations and under flooring bed, hospital for
ramming in 15 cm layers finishing top oxygen pipe line
surface to the required level curing hence it is
etc.,and overheads & contractors profit
complete for finished item of work. (APSS
excuted
No. 402)

V.P 39/ MB No.540


Plain Cement Concrete (1:3:6) nominal
mix using 40mm size machine crushed As per
hard granite metal (coarse aggregate) in emergency work
(2:1) ratio from approved quarry including
for covid-19 not
cost and conveyance of all materials like
cement, fine aggregate (sand), coarse avilable for
aggregate, water etc. to site, sales & other manifold room
11 taxes on all materials, all charges for 2 Cum 4627 9254 in the premises
mixing, laying concrete in position, of gandhi
vibrating, curing, centering charges, hospital for
overheads & contractors profit etc.,for oxygen pipe line
finished item of work . hence it is
excuted

V.P 39/ MB No.540

Supply and placing of the Design Mix


Concrete M 25 grade corresponding to
IS 456 with minimum cement content of
380 kgs per 1 cum of concrete using
Concrete Batching Plant with 20mm size
graded machine crushed hard granite
metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from
approved quarry including cost and
conveyance of all materials like cement,
fine aggregate (sand) coarse aggregate,
water etc., to site and sales & other taxes
on all materials , centering using Steel
scaffolding pipes , jack props , wallers ,
Foot plates , brackets , steel centering
plates etc., including all operational,
incidental and labour charges such as
weigh batching, machine mixing, laying
concrete, curing etc., and overheads &
contractors profit complete but excluding
cost of steel and its fabrication charges for
finished item of work (APSS No. 402).

Footings 0.9 Cum 9935 8942

Column pedestals 1.8 Cum 10522 18940

Page 164 of 204


Providing Thermo Mechanically
Treated (TMT) (Fe -500/500D/550D
from Primary producer TATA, SAIL, As per
VSP, JSW &Shyam Steel etc as per IS emergency work
1786-2008) of different diameters for for covid-19 not
avilable for
RCC works , including labour charges for
straightening, cutting, bending to required manifold room
12 sizes and shapes, placing in position with 0.358 MT 59039 21136 in the premises
cover blocks of approved materials and of gandhi
size and tying and lap-splicing with binding hospital for
wire of 18 SWG, forming grills for oxygen pipe line
reinforcement work as per approved hence it is
designs and drawings, including cost and excuted
conveyance of steel bars, including all
wastages such as overlaps, couplings,
chairs, spacer bars
V.P 39/ MBincluding
No.540 cost and
conveyance of binding wire, cover blocks
Supply and placing of the Design Mix
and all incidental, operational, labour
Concrete
charges such M 25 grade corresponding
as cutting, bending, placing to
As per
IS 456 with minimum cement content
in position, tying including sales and other of
380 emergency work
taxeskgs permaterials
on all 1 cum etc.of concrete using
,and overheads for covid-19 not
Concrete Batching Plant with 20mm
& contractors profit complete for finished size
graded machine crushed hard granite avilable for
item of work.( APSS No.126)
metal (coarse aggregate - as per IS 383 - manifold room
13 1970 and IS 2386 Part 1 to Part 8) from in the premises
approved quarry including cost and of gandhi
conveyance of all materials like cement, hospital for
fine aggregate (sand) coarse aggregate, oxygen pipe line
water etc., to site and sales & other taxes hence it is
on all materials , centering using Steel excuted
scaffolding pipes , jack props , wallers ,
Foot plates , brackets , steel centering
plates etc., including all operational, 2.65
Plinth Beams Cum 12344 32712
incidental and labour charges such as
weigh batching, machine mixing, laying
Supply
concrete,and placing
curing etc.,ofand
the overheads
Design Mix &
contractorsMprofit
Concrete 25 grade
complete but excluding
corresponding to As per
cost
IS of with
456 steel minimum
and its fabrication
cement charges
content forof emergency work
finished
380 kgsitem perof1work
cum(APSS No. 402).using
of concrete for covid-19 not
Concrete Batching Plant with 20mm size avilable for
graded machine crushed hard granite manifold room
14 metal (coarse aggregate - as per IS 383 - in the premises
1970 and IS 2386 Part 1 to Part 8) from
approved quarry including cost and
of gandhi
conveyance of all materials like cement, hospital for
fine aggregate (sand) coarse aggregate, oxygen pipe line
water etc., to site and sales & other taxes hence it is
on all materials, centering using Casurina excuted
Ballies, Bamboos, Wooden Reapers,
Runners,
LINTELS :Wood Posts, Steel Plates etc., 0.17 Cum 11929 2028
including all operational, incidental and
V.P 39/ MB No.540
labour charges such as weigh batching,
Supply
machine and placinglifting
mixing, of the ofDesign Mix
concrete As per
manually, Mlaying
Concrete 25 gradeconcrete, curing to,
corresponding emergency work
overheads
IS 456 with & contractors
minimum cementprofit etc.,of
content
complete for covid-19 not
380 kgs but per excluding
1 cum ofcost of steelusing
concrete and
its fabrication
Concrete charges
Batching for with
Plant finished
20mm item
sizeof avilable for
work (APSS
graded No. 402)
machine crushed hard granite manifold room
15 metal (coarse aggregate - as per IS 383 - 4.5 Sqm 505 2273 in the premises
1970 and IS 2386 Part 1 to Part 8) from of gandhi
approved quarry including cost and hospital for
conveyance of all materials like cement, oxygen pipe line
fine aggregate (sand) coarse aggregate, hence it is
water etc., to site and including sales & excuted
other taxes on all materials , centering
using Casurina Ballies , Bamboos ,
Wooden Reapers , Runners , Wood
Posts , Wall Plates etc., for 60cm wide
sun-shades 7.5cm thick at fixed end
and 5cm thick at free end with an
average thickness of 6.25cm including all
operational, incidental and labour charges
such as weigh batching, machine mixing,
lifting of concrete manually, laying
concrete, curing, overheads & contractors
profit complete etc., but excluding cost of
steel and its fabrication charges for
finished item of work (APSS No. 402, 403
& 903)

Page 165 of 204


Masonry work in CM(1:6) prop
(Cement : Screened sand) in As per
superstructure with fly ash cement / lime emergency work
solid blocks of size 290mm x 225mm x for covid-19 not
140mm from approved source having
avilable for
minimum crushing strength of 50
Kg/Sqcm. including cost and conveyance manifold room
16 of all materials like cement, sand, bricks, 37.76 Cum 6578 248385 in the premises
water etc., to site, including sales & other of gandhi
taxes on all materials and such as labour hospital for
charges, like mixing cement mortar, oxygen pipe line
scaffolding charges, constructing masonry, hence it is
lift charges, curing, overheads and excuted
contrctor profit etc., complete for finished
item of work. (APSS No. 501 & 504).

Supplying and fixing of 2 shutter fully


glazed windows as per drawing using Sal
wood frame and one vertical mullion of
size 100mm x 65mm and shutters with Sal
wood styles & rails of size 75mmx35mm
and 4mm thick pin headed glass fixed with
teak wood beading of 12mm X 12mm
including cost of 4 Nos MS Z hold fasts of
size 300 x 40 x 5 mm including supply and
fixing of ISI marked aluminium fixtures, As per
butt hinges of size 75mm long (2 Nos per emergency work
shutter), 75mm handles (1No per shutter),
75mm x 10mm dia tower bolt (1No per
for covid-19 not
shutter), and aluminium window stopper avilable for
with hook and eye 100mm long (1No per manifold room
17 shutter) with 12mm MS square bars 4.32 Sqm 5482 23682 in the premises
horizontally at 100mm centre to centre of gandhi
fixed in frame including labour charges for hospital for
fixing the fixtures with required No. of oxygen pipe line
screws, fixing window in position fixing hence it is
shutters to frame including cost & excuted
conveyance of all materials to site, labour
charges etc., complete for finished item of
work (APSS No 1001 & 1002).(1200mm x
1300mm)

V.P 39/ MB No.540


Supply and fixing doors as per drawings
with medium teak wood frame of section
100mm x 65 mm and ISI marked flush
door shutters of 30 mm thick double
shutters with bond wood solid block board
type Core having cross bands and face
veneers, hot pressed bonded with water
proof phenol formaldehyde synthetic resin
18 factory made conforming to IS 2202-1991
(Part-I) both sides commercial ply with
internal lipping on all sides including cost
and conveyance to site of teak wood
frame, flush shutter including

Page 166 of 204


supply and fixing 6 Nos. MS Z hold
fasts of size 300 mm x 40 mm x 5mm
including cost of ISI marked Aluminium As per
fixtures of 6 Nos. butt hinges (IS:205) emergency work
150mm long, 1 No. aldrop (IS:2681) for covid-19 not
300mm long, 2 Nos. tower bolts avilable for
(IS:204) of 200 mm x 10 mm dia at manifold room
top, 2 Nos. 150 mm long handles 5.04 Sqm 3548 17882 in the premises
(IS:208), 2 Nos. door stoppers and 2 of gandhi
Nos. rubber bushes including fixing hospital for
the fixtures to door with required oxygen pipe line
number of screws, bolt and nuts hence it is
including labour charges for fixing the excuted
frame in position, fixing the shutter to
the frame etc., including overheads &
contractors profit complete for finished
Plastering
item of work 12mm thickAPSS
as per in two1001coats
&
using screened
1002 (The sandframe
vertical with of
base coat
door of
shall
8mm thick in CM
be embedded (1:6) and
in flooring for top coat of
a depth of
4mm thick in CM (1:4) with
not less than 10 mm) (1200mm xdubara sponge
finishing including cost and conveyance of As per
2100mm). emergency work
all materials like cement, sand, water etc.,
to site, including sales & other taxes on all for covid-19 not
materials, and all operational, incidental avilable for
charges on materials and including cost of manifold room
19 all labour charges for mixing mortar, 285.92 Sqm 455 130094 in the premises
finishing, scaffolding, lift charges, curing, of gandhi
including cutting grooves as directed by hospital for
Engineer-in-charge etc., and overheads & oxygen pipe line
contractors profit complete for finished hence it is
item of work. (SS 901,903 & 904).
excuted

V.P 39/ MB No.540


Flooring with polished shahabad /
Tandur stone slabs of 15mm to 18mm As per
thick set over a base coat of CM (1:8) , emergency work
12mm thick using screened sand over for covid-19 not
already laid CC bed / RCC roof slab
including neat cement slurry of honey like
avilable for
consistency spread @ 3.3 Kgs per Sqm manifold room
20 and jointed with neat cement to full depth 61.05 Sqm 624 38095 in the premises
including cost and conveyance of all of gandhi
materials like cement, sand, water, flooring hospital for
stones etc. complete including sales & oxygen pipe line
other taxes on all materials including all hence it is
labour charges like dressing of flooring excuted
stones to the required size, mixing of
cement mortar, laying, lift charges , cost of
base coat,V.Pwater
39/ MBcharges
No.540 etc., and
Supply
overheads & application
& contractorsof one
profitcoat water
complete
based cement
for finished itemprimer
of work.of(APSS
interior grade&I
No.703 As per
and
701) two coats of acrylic emulsion paint emergency work
having VOC (Volatile Organic Compound)
content less than 50 grams/litre for
for covid-19 not
internal walls including cost and avilable for
conveyance of all materials to site, sales & manifold room
21 other taxes, incidental, operational and all 144.56 Sqm 164 23708 in the premises
labour charges etc., and overheads & of gandhi
contractors profit complete for finished hospital for
item of work in all floors. oxygen pipe line
hence it is
excuted

V.P 39/ MB No.540

Page 167 of 204


Supply & application of one coat water
based cement primer of exterior grade As per
II and two coats of acrylic emulsion
emergency work
paint exterior grade with silicon additives
having VOC (Volatile Organic Compound)
for covid-19 not
content less than 50 grams/ liter for avilable for
exterior walls including cost and manifold room
22 conveyance of all materials to site, sales & 132.84 Sqm 240 31882 in the premises
other taxes, incidental, operational and all of gandhi
labour charges etc., and overheads & hospital for
contractors profit complete for finished oxygen pipe line
item of work in all floors. hence it is
excuted

V.P 39/ MB No.540


Painting to new wood work and flush
shutters with lappam finish, over a
primary coat and painting two coats of
synthetic enamel paint Grade-II VOC As per
(Volatile Organic Compound) content less emergency work
than 50 grams/litre of approved shade for covid-19 not
including cost and conveyance of all avilable for
materials to site cost of primer coat and all manifold room
labour charges etc. complete including
23 35.6 Sqm 180 6408 in the premises
applying sand paper on lappam coats for
neat finish including sales & other taxes on of gandhi
cost of all materials etc., and overheads & hospital for
contractors profit complete in all floors oxygen pipe line
(APSS No.1200, 1207 & 1211). hence it is
excuted

Roofing with corrugated G.I sheets


0.80mm thick fixed with G.I ‘J’ bolts & As per
nuts 8 mm dia with bitumen & G.I limpet emergency work
washers filled with white lead & including a
for covid-19 not
coat of approved steel primer and two
coats of approved paint on over lapping of avilable for
sheets complete (up to a pitch of 600) etc., manifold room
24 complete, excluding the cost of purlins, 67.76 Sqm 874 59222 in the premises
rafters, trusses including cost and of gandhi
conveyance of all materials , labour hospital for
charges , overheads and contractors profit oxygen pipe line
etc., complete for finished item of work in hence it is
all floors. excuted

V.P 39/ MB No.540

Filling with carted coarse sand in


trenches,sides of foundations and As per
basement with initial lead in layers not emergency work
exceeding 15cm thick,watering and for covid-19 not
ramming including cost and conveyance of
water to work site and all
avilable for
peraitonal,incidental ,labour charges,hire manifold room
charges of T&P etc., and overheads & 7.5 Cum 848 6360 in the premises
contractors profit complete for fnished item of gandhi
of work(APSS NO.309&310) hospital for
oxygen pipe line
hence it is
excuted

Page 168 of 204


Plain Cement Concrete M 20 nominal
mix using WEIGH BATCHER / MIXER,
20mm size hard granite machine crushed As per
graded metal (coarse aggregate - as per emergency work
IS 383 - 1970 and IS 2386 Part 1 to Part for covid-19 not
8) from approved quarry, using a minimum avilable for
quantity of 300 kgs. of cement per 1 cum manifold room
of concrete including cost and conveyance 15 Cum 5562 83430 in the premises
of all materials like cement, fine of gandhi
aggregate (Sand), coarse aggregate, hospital for
water etc., to site including steel oxygen pipe line
centering, shuttering, machine mixing, lift hence it is
charges, laying concrete,vibrating, curing,
excuted
overheads & contrctors profit etc.,
complete for finished item of work for
coping on top of compound wall (APSS
No. 402 & 403).
Sub-Total:- 2962701

Electrical Work
Supply and Laying of P.V.C casing and
caping (ISI MARK) with double locking
arrangments with groover trunking of size As per site
1 not below 12.5mm height 25mm size with 400 Rm 50.00 20000 condition it is
all accessories, duly sealed at points and excuted
erected on Wall / Ceiling including cost of
all materialsV.Pand39/
labour charges complete.
MB No.540
Makes : Modi with ISI
Supply and Fixing of ISI 25mm outer
dia medium grade with IS:9537 part 3
regid PVC pipe surface on wall/ceiling As per site
2 with all required saddles and all
1210 Rm 65.00 78650 condition it is
accessories and labour charges etc., excuted
complete for run of mains.
Makes : Sudhakar
V.P 39/ MB/ No.540
Finolex / Modi /
VIP / Precision / Universal / Million
Supply
Plast and fixing of 6A switchs - 2
Nos and 6A 3/2 pin socket - 2 Nos As per site
3 Modular type with front cover plate 176 Pts 783.00 137808 condition it is
including all labour charges etc., excuted
complete.
Makes : Legrand
V.P 39/ MB Arteor
No.540 / Schneider
Zen celo / Honeywell Blenge Plus /
Supply
Cabtree& Amarefixing of /16A/6A,
Logus2 in one
Platina.
socket - 2
(Including 3ofNos4Sqmm with
2.016A
Rmt)switch As per site
4 control - 2 Nos modular type with front 688 No's 901.00 619888 condition it is
cover plate including all labour excuted
charges etc., complete.
Makes : Legrand
V.P 39/ MB Arteor
No.540 / Schneider
Zen celo / Honeywell Blenge Plus /
Supply
Cabtree and Amare 3 runs of 4.0 sq
/ Logus mm
Platina.
(56/0.3 mm) (phase neutral
(Including 3of 4Sqmm 2.0 Rmt) and earth) As per site
5 FRLS / HFFR PVC insulated flexible 3713.3 Rm 136.00 505014 condition it is
copper cable in existing conduit pipe excuted
including labour charges etc.,
complete for 16A sockets.
Makes of wiresV.P 39/: MB
Finolex
No.540 / RR kabel /
Havells / APAR EBXL
Supply & run of 5 of 10.0 / KEI / Polycab
Sqmm/
V-Guard / MILLION
(84/0.3mm) (3 phases, neutral and
As per site
earth) FRLS / HFFR PVC insulated
6 120 Rm 442.00 53040 condition it is
flexible copper cable in the existing
excuted
conduict pipe for run of mains from
Power panel board to TPN DB"s with
pin type lugs V.P 39/ and
MB connections
No.540 etc.,
complete. [for PDBs]
Makes of wires :Finolex / RR kabel /
Havells / APAR EBXL / KEI / Polycab /
V-Guard / MILLION

Page 169 of 204


Supply and fixing of 12 Way TPN DB
Horizontal with IP 43 Protection as per
IS:13032 with 1 No., of 63A 10KA FP
MCB as incomer and 36 Nos 6-32 A
10kA SP MCBs as out goings As per site
7 including internal connections and 5 No's 20516.00 102580 condition it is
labour charges for FLUSH Mounting excuted
etc., complete for DBs.
Makes : Legrand / Schneider / L&T.

V.P 39/ MB No.540


Supply and fixing of 8 Way VTPN DB
with IP 43 Protection with 1 No., of
125A TPN MCCB, Adjustable, As per site
8 Confirms to IS/IEC 60947-2 having 3 No's 33165.00 99495 condition it is
Breaking Capacity 25 KA with thermal excuted
magnetic release Panel Mounted as
incomer with 8 Nos of 63A, 10KA, TP
MCBs C/DV.P 39/ MB
Curve ISINo.540
Mark as Out
Supply
goings and fixing internal
including of cableconnections
adopteres
box with charges
and labour cover for etc.,DBs including,
complete. As per site
9 massaNosry work/ etc.,
Makes : Legrand complete.,
Schneider / L&T. 6 No's 600 3600 condition it is
Makes : Legrand / Schneider. excuted

V.P 39/ MB No.540


Supply and Installation of 125 Amps
4P MCCB with cable end boxes on As per site
10 suitable angle iron frame work for the 10 No's 14435.00 144350 condition it is
areas mentioned in the drawings excuted
including all Labours charges,
massonry work etc. complete for
V.P 39/ MB No.540
finished item of work. Makes:Legrand /
Supply
Shneiderof the Following PVC XLPE
armoured cable 1100 V Grade with ISI As per site
11 mark stranded / solid, aluminimum condition it is
conductor complete excuted
Makes : Torrent / Unicab / Polycab /
3.5 Core/ 70.00
Havells Sq.mm.
Gloster / KEI / Finolex / 120 Rm 420.00 50400
Paragon. V.P 39/ MB No.540
Laying of PVC armoured under ground
cable up to 95 Sqmm fixing on As per site
12 chromium plated metallic base saddles 120 Rm 35.00 4200 condition it is
on wall as per IS 1255 and as directed excuted
by the department including cost and
V.Pof39/
all MB
No.540and labour
conveyance materials
LT CABLE
charges TERMINATIONS:
etc., complete.
Supply and Fixing of single
compression brass cable glands for As per site
13 3.5 core following armoured cable condition it is
with brass washers, lugs etc., excuted
complete.

70 Sq.mm 8 No's 319.00 2552


V.P 39/ MB No.540

Supply, Transportation and fixing of


60 W / 65 W LED LED Street light, As per site
Body made of high grade pressure die requrement
14 – cast Aluminium alloy with corrosion
10 No's 6559.00 65590
hence it is
resistant powder coat, having excuted
protective toughened glass cover,
Less Glare, IP MB
V.P 39/ 66 No.540
(Silicon gasket
ensures Optical & Electrical
compartments are IP 66) protected,
wide operating voltage range, P.F >
0.90, System having efficacy >100
lumens/watt, with Ingress protection
IP66, Potted driver, Driver surge
protection >10KV, THD<15%, CCT:
3000- 6500K as desired by the
department and as per IS, CRI>80,
Inbuilt Electrical protections like Over
Page 170 of 204
voltage, short circuit, Over load, Open
Circuit, Miswiring, etc complete with
Supply and transportation of 48"
(1200mm) Sweep decorative Ceiling
Fan with all accessories etc.,
As per site
complete.
requrement
15 Makes : Crompton High Speed Decora 4 No's 2244.00 8976
hence it is
/ Havells Spark Deco / Orient Summer
excuted
Crown / Panasonic Sprint Deco /
Halonix Erbon

V.P 39/ MB No.540


Supply and fixing of 2 Module Modular
type Electronic step type Fan As per site
Regulator for sweep AC ceiling fans of requrement
16 1200mm / 1420mm complete with 4 No's 502.00 2008
hence it is
connections. excuted
Makes : Legrand Myrius / Million mway
/ Gold Medal Curve / Anchor Roma
viola / GM V.P 39/ MB No.540
Four-Five / Havells Fabio /
Panasonic
Labour Vision
charges / L&Tof Englaze
for fixing ceiling fan/
Hagerregulator
and Insista including
/ Benlo Vesta / C&S
transportation As per site
Primogiving
and / CPLconnections
Vysma / Polycab Levana.
with twin core requrement
17 4 No's 139.00 556
wire etc., complete. hence it is
excuted

V.P 39/ MB No.540


Supply of 10 sqmm WPTC (Weather
Proof Twin Core) ISI Alluminium Wire. As per site
Makes : Polycab / GM / Million / V- requrement
18 Guard / Gold Medal / Kundancab /
600 Rmt 44.00 26400
hence it is
HPL / RPG / Nandicab / Nakoda / excuted
Payal / Finecab / Gemini / Vimal /
Suncab / Stanjo
V.P 39// MB
Rajnigandha
No.540 / Orbit /
Airson.
Supply and fixing of 12 V 150 AH MF
battery including wire leads. Makes : As per site
Amar Raja (Power Zone) or Equivalent 4 requrement
19 No's 11500.00 46000
model of Exide / Panasonic / Gotech hence it is
SSR-1837 excuted

V.P 39/ MB No.540

Supply and Transportation of


-------------------- single phase ISI
submersible motor pumpset suitable
As per site
for 4" Bore well. Makes: Varuna /
requrement
20 Flowell / Waterman / Techno / Mahavir 1 No's 13770.00 13770
hence it is
/unitek/ Fitwell/ Falcon/ Ellen/ Karvel /
excuted
LPS/ Duke / Varsha / Ajantha.

V.P 80/ MB No.538


Supply and Transportation of
………………….. double walled As per site
corrugated HDPE duct made as per requrement
21 30 Rm 119.00 3570
specification BSEN - 500 86/IS 14930 hence it is
Part-II with all accessories like excuted
couplers, bends, end caps, Ts etc.,
complete. V.P
Makes:
81/ MBDURA
No.538LINE (Dura
Guard) /
Providing Bajaj /
andGamson / Ultra Plus
errecting heat
shrinkable indoor termination kit for 11 As per site
KV HTXLPE insulated armoured requrement
22 cable-------------with necessary 2 Each 8599.00 17198
hence it is
materials etc., complete. Makes : excuted
Raychem / Transeal / M Sea

V.P 82/ MB No.538

Page 171 of 204


Servicing of L&T ACB 'S As per site
requrement
23 24 No's 5500.00 132000
hence it is
excuted
V.P 82/ MB No.538
Servicing of HT VCB'S As per site
requrement
24 5 No's 9000.00 45000
hence it is
excuted
V.P 83/ MB No.538
500 KVA DG SET at OPD Block As per site
requrement
25 1 Job 86375.00 86375
hence it is
excuted
V.P 82/ MB No.538
500 KVA DG SET at South Block As per site
requrement
26 1 Job 86000.00 86000
hence it is
excuted
V.P 85/ MB No.538
500 KVA DG SET at North Block As per site
requrement
27 1 Job 80475.00 80475
hence it is
excuted
V.P 78/ MB No.538

500 KVA DG Contrle Panel micropanel As per site


cip requrement
28 3 Job 35000.00 105000
hence it is
excuted
V.P 80/ MB No.538
Sub-Total:- 2540495
Grand Total:- 20392887

Page 172 of 204

You might also like