Professional Documents
Culture Documents
page-23
(Lead)
charges
for trucks (Lead)
(Lead)
(Lead) and charges for
charges for
charges for trucks and (Lead)
trucks and tippers for (Lead)
trucks and Cement/ tippers per charges for
tippers for
tippers for cu.meter for trucks and charges for
Rubble/Size Steel/
Sl No. Distance Earth / PCC slabs/ tippers per trucks and
stones/ Cut RCC Shahabad cu.meter for tippers for
Sand /Gravel
/ Murrum/ Stones/ poles/ AC slabs/ CC & water/ 1000 Bricks
Coarse & GI /1000 nos
Lime/ Surki/ Laterite litres
aggregate sheets/
per cu.meter blocks/
per cu.meter Packed
Wood/ cum
materials/
tonne
1 2 3 4 5 6 7 8
1 Lead up to 1 km 1 34.70 33.60 21.00 49.50 20.80 56.10
2 Lead up to 2 km 2 48.60 47.10 29.40 69.30 29.10 78.50
3 Lead up to 3 km 3 64.80 64.80 40.50 94.30 38.80 104.70
4 Lead up to 4 km 4 78.70 78.70 49.20 115.70 47.20 127.10
5 Lead up to 5 km 5 92.50 92.50 57.80 136.10 55.50 149.50
6 for Every km beyond 5 km up to 30 km 30 13.90 13.90 8.70 20.40 8.30 22.40
7 for Every km beyond 30 km 10000 11.60 11.60 7.20 17.00 6.90 18.70
Rubble/ size
Earth / stone/ cut
Sand /Gravel stone/
Cement in Steel in Bricks
Sl No. Description of item Murrum/ / Coarse
Rs/Tonne Rs/Tonne Rs/1000 Nos.
Surki/ Rs / aggregate,
cum Lime in
Rs/cum
167 Dismantling
a) Stone masonry in cement mortar 114 TBSC-U.I-01 464.00
Flat stone in roof or floors including
b) 114 TBSC-U.I-03 17.00
lifting :
Pan tiled or Mangalore tiled roof with out
c) 114 TBSC-U.I-04 15.00
roof timbers :
Wrought and framed timber in roofs or
d) 114 TBSC-U.I-06 241.00
floors
e) Old lime mortar plaster 114 TBSC-U.I-07 5.00
f) Old cement mortar plaster 114 TBSC-U.I-08 6.00
Kadapa slabs or shahabad stone slabs on
g) 115 TBSC-U.I-11 8.00
sand bed
Clean removal of lime plaster from walls
and raking out joints 20mm deep or from
h) 115 TBSC-U.I-14 5.00
terraced roof and raking out joints 100 mm
deep
Clean removal of cement plaster from
i) 115 TBSC-U.I-15 6.00
walls and raking out joint 200 mm deep
Buildings Referenc
Material hire Labour
168 Hire charges for Access Scaffolding e to SSR
charges charges
page
A) Brick Masonry / Stone Maasonry
a) 1st floor 117 10.32 83.43
b) 2nd floor 10.32 119.47
c) 3rd floor 10.32 155.49
d) 4th floor 10.32 191.53
e) 5th floor 10.32 227.56
f) 6th floor 10.32 263.58
g) 7th floor 10.32 299.60
h) 8th floor 10.32 335.63
B) Plastering to walls
a) 1st floor 117 1.03 8.35
b) 2nd floor 1.03 11.95
c) 3rd floor 1.03 15.54
d) 4th floor 1.03 19.15
e) 5th floor 1.03 22.75
f) 6th floor 1.03 26.37
g) 7th floor 1.03 29.97
h) 8th floor 1.03 33.56
171 HIRE CHARGES FOR CENTERING & SCAFFOLDING -Unsupported height of 3.66M
Buildings Referenc Material hire
e to SoR charges Lab
1st
Floor
a) Lintels 116 1180.00 1696.00
b) Sunshades of any width 233.00 260.00
c) Columns 355.00 2381.00
d) Beams 2085.00 1998.00
e) RCC roof slabs upto 150 mm depth 236.00 226.00
f) RCC slabs upto 150-300 mm depth 243.00 233.00
172 HIRE CHARGES FOR CENTERING & SCAFFOLDING -Unsupported height of 3.66M - Casurina
Part I (I&CAD
LABOUR CHARGES Works)
SKILLED
174 Bar bender 15 I-1 590.00
175 Blacksmith 15 I-2 495.00
176 Blaster (licensed) 15 I-3 590.00
177 Carpenter 15 I-4 590.00
178 Work Inspector(Non technical) 15 I -10 590.00
179 Mason / Brick layer 15 I -11 500.00
180 Operator concrete mixer 15 I -16 530.00
181 Operator Jackhammer / Pneumatic
tamper(skilled) 15 I - 23 520.00
182 Painter 15 I - 35 570.00
183 Plumber(licensed) / Pipe fitter 15 I - 36 580.00
SEMI SKILLED
183 Sprayer(semi skilled) 16 II - 1 470.00
184 Carpenter 16 II - 4 470.00
185 Plumber / Pipe fitter 16 II - 9 470.00
185 Mason / Brick layer 16 II - 35 470.00
186 Painter 16 II - 37 470.00
UN SKILLED
Heavy Mazdoor / Light Mazdoor
187 18 III - 3, 4 445.00
Cost of Materials :
188 Binding wire 1 3 55.00
189 Detonator electric 2 21 10.00
190 Sand (un-screened for concrete items) 2 27 570.00
191 Sand un-screened for filling 2 27 570.00
192 Sand(screened for mortar, plastering
items) 2 28 760.00
193 Impervious Water proof compound 4 95 95.00
194 Roads&
Bridges
Gravel / Quarry spall Works S.No.89/34 98.00
195 Aggregates 6mm nominal size (HBG) S.No.25/33 a 701.25
196 Aggregates 10mm nominal size (HBG) S.No.25/33 b 891.25
197 Aggregates 13.20 / 12.50mm nominal size
(HBG) S.No.25/33 c 1046.25
198 Aggregates 20mm nominal size (HBG) S.No.25/33 d 1157.50
199 Aggregates 40mm nominal size (HBG) S.No.25/33 f 701.25
200 SoR 2015-
Gelatin 80% 16 M - 104 73.00
201 Water charges (Urban) 276 98.00
202 Water charges (Rural) 275 73.00
203 PHE PH Items
PVC pipes 110mm dia. 4kg/cm2 Items Table17 157.00
205 Seigniorage charges G.O.Ms.No. 67 of Industries and Commerce (Mines.I) Dept. dt.
i) Coarse aggregate , stone 2 75.00
ii) Earth , Gravel 2 30.00
ii) Sand for mortar & filling 2 40.00
iv) Bricks 3 60.00
v) Polished Shahabad/Tandur stone slbs 3 8.00
vi) Black Kadapa slabs 3 8.00
vii) Colour Granite 3 39.10
viii) Black Granite 3 34.00
1000 Nos.
1 No.
1 No.
1 No.
10 Sqm
10 Sqm
1 Sqm
1 Sqm
1 Sqm
1 Sqm
1 Sqm
1 Sqm
1 Sqm
1 Sqm
1 Sqm
1 Sqm
1 Sqm
1 cum
1 cum
1 cum
1 cum
1 cum
1 cum
1 cum
1 cum
1 cum
1 sqm
1 Kg
1 sqm
1 No.
1 No.
1 No.
1 No.
1 No.
1 Sqm
1 Sqm
1 Sqm
1 Kg
1 Kg
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 Kg
1 Kg
1 Kg
1 Ltr
1 Ltr
1 Ltr
1 Kg
1 Ltr
1 Ltr
1 Ltr
1 Ltr.
1 Kg
1 Kg
1 Ltr
1 Ltr
1 Ltr
1 Ltr
1 Kg
1 Kg
1 Ltr.
1 Ltr.
1 Ltr.
1 sqm TBSC-H.IV-22
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 RM
1 RM
1 RM
1 RM
1 RM
1 RM
1 RM
1 RM
24x32 Rs. 50 45
1 RM
1 RM
1 RM
1 No.
1 No.
1 No.
1 No.
1 No.
1 Kg.
1 RM
1 Ltr
1 No.
1 RM
1 RM
1 sqm
1 RM
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
Previous SSR
1 sqm
Centre fixed both side openable
1 sqm
1 sqm
Pre painted steel Window with tw
1 sqm
Supply and fixing of UPVC slidin
1 sqm
Supply and fixing of UPVC slidin
1 sqm
Supply and fixing of prepainted s
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 No.
1 Ltr
DELETED
2019-2020 rated
adopted
1 Ltr as per
SSR
2018-19
1 sqm
1 Kg
1 Kg
1 RM
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
1 hour
1 hour
1 RM
1 RM
1 RM
1 RM
1 RM
1 Kg
1 Kg
1 Kg
1 sqm
1 sqm
1 sqm
1 cum
1 sqm
1 sqm
1 cum
1 sqm
1 sqm
1 sqm
1 sqm
1 sqm
Unit
2018-19
1 Sqm 79.46
1 Sqm 113.78
1 Sqm 148.09
1 Sqm 182.41
1 Sqm 216.72
1 Sqm 251.03
1 Sqm
1 Sqm
1 Sqm 7.95
1 Sqm 11.38
1 Sqm 14.80
1 Sqm 18.24
1 Sqm 21.67
1 Sqm 25.11
1 Sqm
1 Sqm
1 Sqm 15.91
1 Sqm 22.57
1 Sqm 29.23
1 Sqm 35.90
1 Sqm 42.56
1 Sqm 49.22
1 Sqm
1 Sqm
using Steel scaffolding pipes, jack props, wallers, Foot plates, brackets, steel centering plates etc.,
Unsupported height of 3.66M - Steel scaffolding pipes, jack props, Steel centering Plates etc.
d height of 3.66M - Casurina Ballies, Bamboos, Wooden Reapers, Runners, Wood Posts, Wall Plates etc.,
1 Each
1 Each 565.00
1 Each 470.00
1 Each 565.00
1 Each 565.00
1 Each 565.00
1 Each 470.00
1 Each 500.00
1 Each 500.00
1 Each 540.00
1 Each 540.00
1 Each 450.00
1 Each 450.00
1 Each 450.00
1 Each 450.00
1 Each 450.00
1 Each 425.00
1 Kg 50.00
1 No. 8.00
1 Cum 570.00
1 Cum 570.00
1 Cum 760.00
1 Kg 95.00
1 Cum
1 Cum 505.00 70
1 Cum 657.00 70
1 Cum 781.00 70
1 Cum 870.00 70
1 Cum 505.00 70
1 Kg
1 KL
1 KL
1 RM 164.00
Crew
charges
SoR 2017-18
1 hour 247.10 983.90 231
1 hour 389.30 237.10 107.1
1 cum
1 cum
1 RM
1 sqm
1 No.
1 No.
1 No.
1 RM
1 RM
1 No.
1 No.
1 No.
1 sqm
1 No.
1 RM
1 sqm
1 No.
1 No.
1 No.
7.125
7.1190476
Previous SSR 2017-18
TBSC-H.IV-22 667.00
24x25 Rs. 41
Previous SSR
Supply and fixing of prepainted steel sliding door - 3 track - 3 panel sliding doorsliding
2017-18
75.68
108.36
141.04
173.72
206.4
239.08
7.57
10.84
14.1
17.37
20.64
23.91
15.15
21.5
27.84
34.19
40.54
46.88
etc.,
Unit
Cum
Cum 357.5 390 422.5 455 487.5 1 Cum
Cum
Cum
2018-19
Unit Labour charges
1st 2nd 4th 5th 6th
3rd Floor
Floor Floor Floor Floor Floor
Cum 1615 1777 1938 2099 2261 2422
Sqm 248 272.80 297 322 347 372
Cum 2268 2495 2722 2948 3175 3402
Cum 1903 2093 2283 2474 2664 2854
Sqm 215 237 258 280 301 323
Sqm 222 244 266 288 310 333
1776.5 1938
ates etc.,
161.5
Unit
1776.50
195.25 1046.25
217.5 1157.50
126.25 701.25
895.1 1126.1
134.3 241.4
99.5 152.5
20.9 26.5
1094 2718
219.30 344
2017-18
10
100
40
20
26
32
600
32
10
170
80
224
100
30
30
675
641
100
75
174
1 Cum
1 Sqm
1 Cum
1 Cum
1 Sqm
1 Sqm
1 Sqm
DATA (SoR 2019-20)
WATER SUPPLY AND SANITARY ITEMS
Sl. Plumbing SoR
ITEM Item code Rate
No. Items Page No.
TBSP-F.I-01 /
15 mm brass body CP finish bib tap of
28 151 TBSP-F.VIII- 224.00
not less than 300 grams weight
01
Chromium plated finish brass body
quarter turn Bibcock cum Health Faucet TBSP-F.I-07/TBSP-
29 151/156 2929.00
with 1m long tube and wall hook with 7 - F.VIII-01
10 years warranty
15 mm brass body CP finish self type TBSP-F.III-01 /
30 152/156 247.00
conforming to IS 1711closing tap push /TBSP-F.VIII-01
15 mm nominal size CP finish brass TBSP-F.IV-03
29 152/156 216.00
angled stop valve screw type TBSP-F.VIII-02
S&F 15 mm nominal size 152.0 mm CP TBSP-F.VI-
30 153/153 170.00
finish iron body shower 01/TBSP-F.VIII-04
TBSP-F.VII-
31 CP finish brass soap dish 152/156 517.00
21/TBSP-F.VIII-04
32 S&F 31.75mm brass plumber union 155 TBSP-F.VII-30 63.00
1 RM
1 RM
1 RM
1 RM
1 Each 2017-18
1 RM
480
1 RM 878
1 RM 1266
1 RM
1 RM
1 Each
7321
1 Each
11649
1 Each
3813
1 Each
76
1 Each 124
429.00 1 Each
1306
1 Each 271
1 Each 81
301.00 1 Each
1619
87.00 1 Each
734
429.00 1 Each
1469
429.00 1 Each
4087
429.00 1 Each
4599
171.00 1 Each
767
171.00 1 Each
2555
1 Each
6224
1 Each
4448
1 Each 652
1 Each
449
53.00 1 Each
223
53.00 1 Each
2914
53.00 1 Each
246
103.00 1 Each
215
103.00 1 Each
169
103.00 1 Each
514
1 Each 63
1 RM 184
1 RM 204
1 RM 268
1 RM 375
1 RM 420
1 RM 452
1 RM
802
1 Each 577
1 Each 778
1 Each 1119
1 Each 1700
1 Each 2297
1 Each 3365
1 Each 5196
1 Each 7702
3 RM 252
3 RM 401
3 RM 479
3 RM 1140
1 Lt
7
1 Each
26
1 Each 1439
1 Each 814
1 Each 15
1 Each 17
1 Each 18
1 Each 35
1 Each 101
1 Each 143
79.00 1 Each
31.00 1 RM
49.00 1 RM
75.00 1 No.
1 Each 38
1 Each
149
1 Each
24
1 Each
101
1 Each
466
1 RM 128
1 RM 146
1 RM 193
1 RM 263
1 RM 327
1 RM 477
1 RM 141
1 RM 172
1 RM 206
1 RM 281
1 RM 348
1 RM 508
1 sqm 907
1 Each 100
A Name of the work: Providing Gas Supplying pipeline for Supplying and
Centralized Medical Oxygen to bed for COVID-19 Management in Gandhi Hospital
Secunderabab
2 Fe-500 43000.00
3 Fe-415 0.00
6 MS Flats 43000.00
D Allowances
1 Add for MA @ 40% 40%
2 Overheads&Contractors Profit @ 13.615% 0.000%
14 Aggregates 20mm nominal size (HBG) Keesara 0 S.No.25/33 d 1 Cum 32.00 1157.50 378.12 1535.62
Aggregates 13.20 / 12.50mm nominal size
15 Keesara 0 S.No.25/33 c 1 Cum 32.00 1046.25 378.12 1424.37
(HBG)
16 Aggregates 10mm nominal size (HBG) Keesara 0 S.No.25/33 b 1 Cum 32.00 891.25 378.12 1269.37
17 Aggregates 6mm nominal size (HBG) Keesara 0 S.No.25/33 a 1 Cum 32.00 701.25 378.12 1079.37
20 Gravel / Quarry spall Local 0 S.No.89/34 1 Cum 21.00 98.00 246.63 344.63
Polished Shahabad / Tandur stone slabs
21 Tandur 10 TBSC-B.I-03 10 Sqm 95.00 1640.00 247.12 3.48 1.39 1891.99
15mm to 18mm thick
Convey-
Reference
S.No./ ance Unloading MA
Sl. to SSR Lead in Initial Loading
Description Source of Materials Item Code Unit Charges charges (-) Total
No. page KM Cost charges
No. (-) 13.615%
number
13.615% 40%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
Polished black Kadapa slabs 15mm to
22 Tandur 10 TBSC-B.I-06 10 Sqm 95.00 1370.00 247.12 3.48 1.39 1621.99
18mm thick
High Polished Granite 16 to 18 mm thick
23 up to 8'-00 (2.43 M) other than black and 11 TBSC-B.III-02 1 Sqm - 2709.00 2709.00
regular colours
High Polished Granite 16 to 18 mm thick
24 11 TBSC-B.III-03 1 Sqm - 2303.00 2303.00
up to 8'-00 (2.43 M) black.
1) Certified that the leads mentioned in the lead statement are shortest and correct.
2) Certified that metal are to be obtained by blasting.
3) Certified that sufficient quantities & quanlity material are available in the quarries.
4) Certified that for non SSR items lowest market rates are adopted
5) Certified that 40% extra on labour towards Municipal area allowance is allowed
CIVIL DATA : Page-14
D A T A (SoR 2019-20)
DATA
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
1 Dismantling, clearing away and carefully stacking useful materials for re-use and disposal of unserviceable materials
with 100m lead as directed by Executive Engineer duly taking actual premeasurements before dismantling including
all labour charges , overheads & contractor profit etc., complete
2 Earth work excavation for foundations (Manual Means) of buildings, septic tank, sump, compound wall in
ordinary soils and depositing on bank with an initial lead of 10m and 1m additional lift charges over the initial
depth up to 3m including all operational,incidental, labour charges such as shoring, sheeting, planking, strutting etc.,
and overheads & contractors profit complete for finished item of work excluding dewatering charges etc., as per SS
20 B(APSS 308)
(BLD-CSTN-2-1& COM-LDLFT-6-66)
Rate with initial lead & lift 1.00 cum 226.77 1 cum 226.77
Mazdoor for extra lift ( 1 No. for 60m) 0.02 Nos. 445.00 1 Each 8.90
Add for MA @ 40% 0.40 8.90 3.56
Overheads&Contractors Profit @ 13.615% 0.00000 12.46 0.00
Rate per 1 cum 239.23
Say 239
Page 14 of 204
CIVIL DATA : Page-15
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
11 Filling with carted coarse sand in trenches,sides of foundations and basement with initial lead in layers not
exceeding 15cm thick,watering and ramming including cost and conveyance of water to work site and all
peraitonal,incidental ,labour charges,hire charges of T&P etc., and overheads & contractors profit complete for
fnished item of work(APSS NO.309&310)
12 Filling with carted gravel in trenches,sides of foundations and basement with initial lead in layers not exceeding
15cm thick,watering and ramming including cost and conveyance of water to work site and all peraitonal,incidental,
labour charges,hire charges of T&P etc., and overheads & contractors profit complete for fnished item of work(APSS
NO.309&310)
(BLD-CSTN-2-8) & Amendment in SoR 2014-15
Unit : 1 cum
Taking output = 6 cum
a) Labour
Mazdoor ( Unskilled ) 0.31 Nos. 445.00 1 No. 137.95
Add for MA @ 40% 0.40 137.95 55.18
b)Material :
Gravel 6.00 cum 344.63 1 cum 2067.78
Water 0.72 Kl 98.00 1 Kl 70.56
Rate per 6 cum (a+b+c) 2331.47
Overheads&Contractors Profit @ 13.615% 0.00000 2331.47 0.00
Rate per 6 cum 2331.47
Rate per 1 cum 388.58
Say 389
15 Plain Cement Concrete (1:5:10) (cement: fine aggregate: Coarse aggregate) for foundations and under flooring
bed using coarse aggregate 40mm size hard , machine crushed granite from approved quarry including cost
and conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, sales & other taxes on all
materials and including all charges for machine mixing, laying concrete in foundations and under flooring bed,
ramming in 15 cm layers finishing top surface to the required level curing etc.,and overheads & contractors profit
complete for finished item of work. (APSS No. 402)
(BLD-CSTN-3-7)
Unit : 1 cum
A.MATERIALS :
Cement 129.60 Kgs 5600.00 1000 Kgs 725.76
Coarse aggregate 40mm 0.90 Cum 1079.37 1 Cum 971.43
Fine aggregate ( Sand ) 0.45 Cum 1896.68 1 Cum 853.51
Water (including curing) 1.20 kl 98.00 1 kl 117.60
B.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8
cum)capacity 1.00 hour 152.50 1 hour 152.50
Crew charges 1.00 hour 260.00 1 hour 260.00
Add MA on crew charges 0.40 260.00 104.00
C.LABOUR :
1st class mason 0.10 Nos. 500.00 1 Each 50.00
Mazdoor (unskilled) 1.39 Nos. 445.00 1 Each 618.55
Add for MA @ 40% 0.40 668.55 267.42
4120.77
Overheads&Contractors Profit @ 13.615% 0.00000 4120.77 0.00
Rate per 1 cum 4120.77
Say 4121
Page 15 of 204
CIVIL DATA : Page-16
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
18 Plain Cement Concrete (1:3:6) nominal mix using 40mm size machine crushed hard granite metal (coarse
aggregate) in (2:1) ratio from approved quarry including cost and conveyance of all materials like cement, fine
aggregate (sand), coarse aggregate, water etc. to site, sales & other taxes on all materials, all charges for mixing,
laying concrete in position, vibrating, curing, centering charges, overheads & contractors profit etc.,for finished item of
work for footings and basement.
19 Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS 456 with minimum cement
content of 380 kgs per 1 cum of concrete using Concrete Batching Plant with 20mm size graded machine crushed
hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site
and sales & other taxes on all materials , centering using Steel scaffolding pipes , jack props , wallers , Foot plates ,
brackets , steel centering plates etc., including all operational, incidental and labour charges such as weigh batching,
machine mixing, laying concrete, curing etc., and overheads & contractors profit complete but excluding cost of steel
and its fabrication charges for finished item of work (APSS No. 402).
(BLD-CSTN-3-14)
FOUNDATIONS , PLINTH , PEDESTALS ( Below Plinth)
A.MATERIALS :
Cement 380.00 Kgs 5600.00 1000 Kgs 2128.00
20mm HBG graded metal 0.80 Cum 1433.38 1 Cum 1146.70
Sand 0.40 Cum 1896.68 1 Cum 758.67
B.LABOUR :
1st class Mason 0.133 Nos 500.00 1 Each 66.50
2nd class Mason 0.267 Nos 470.00 1 Each 125.49
Mazdoor (both men&women) 4.60 Nos 445.00 1 Each 2047.00
Add for MA @ 40% 0.40 2238.99 895.60
C.MACHINERY :
Batching plant 0.50 cum 1.333 hours 241.40 1 hour 321.79
Crew charges 1.333 hours 389.30 1 hour 518.94
Needle vibrator 40mm ( petrol ) 1.333 hours 26.50 1 hour 35.32
Crew charges 1.333 hours 187.20 1 hour 249.54
Add MA on crew charges 0.40 768.47 307.39
Water(including for curing) 1.20 kl 98.00 1 kl 117.60
Rate per 1 cum 8718.54
a Footings
Rate for Design mix M 25 1.00 Cum 8718.54 1 Cum 8718.54
Hire charges of centering and scaffolding 1.00 Cum 288.00 1 Cum 288.00
Labour charges 1.00 Cum 663.00 1 Cum 663.00
Add for MA @ 40% 0.40 663.00 265.20
9934.74
Overheads&Contractors Profit @ 13.615% 0.00000 9934.74 0.00
Rate per 1 cum 9934.74
Say 9935
b Column pedestals
Rate for Design mix M 25 1.00 Cum 8718.54 1 Cum 8718.54
Hire charges of centering and scaffolding 1.00 Cum 328.00 1 Cum 328.00
Page 16 of 204
CIVIL DATA : Page-17
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
Labour charges 1.00 Cum 1054.00 1 Cum 1054.00
Add for MA @ 40% 0.40 1054.00 421.60
10522.14
Overheads&Contractors Profit @ 13.615% 0.00000 10522.14 0.00
Rate per 1 cum 10522.14
Say 10522
c Plinth Beams
Rate for Design mix M 25 1.00 Cum 8718.54 1 Cum 8718.54
Hire charges of centering and scaffolding 1.00 Cum 1390.00 1 Cum 1390.00
Labour charges 1.00 Cum 1597.00 1 Cum 1597.00
Add for MA @ 40% 0.40 1597.00 638.80
12344.34
Overheads&Contractors Profit @ 13.615% 0.00000 12344.34 0.00
Rate per 1 cum 12344.34
Say 12344
20 Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS 456 with minimum cement
content of 380 kgs per 1 cum of concrete using Concrete Batching Plant with 20mm size graded machine crushed
hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site
and sales & other taxes on all materials, centering using Casurina Ballies, Bamboos, Wooden Reapers, Runners,
Wood Posts, Steel Plates etc., including all operational, incidental and labour charges such as weigh batching,
machine mixing, lifting of concrete manually, laying concrete, curing , overheads & contractors profit etc., complete
but excluding cost of steel and its fabrication charges for finished item of work (APSS No. 402)
(BLD-CSTN-3-15)
COLUMNS, LINTELS, WATER TANKS, RCC WALL IN BUILDINGS:
A.MATERIALS :
Cement 380.00 Kgs 5600.00 1000 Kgs 2128.00
20mm HBG graded metal 0.80 Cum 1433.38 1 Cum 1146.70
Sand 0.40 Cum 1896.68 1 Cum 758.67
B.LABOUR :
1st class Mason 0.167 Nos 500.00 1 Each 83.50
2nd class Mason 0.167 Nos 470.00 1 Each 78.49
Mazdoor (both men&women) 5.60 Nos 445.00 1 Each 2492.00
Add for MA @ 40% 0.40 2653.99 1061.60
C.MACHINERY :
Batching plant 0.50 cum 1.333 hours 241.40 1 hour 321.79
Crew charges 1.333 hours 389.30 1 hour 518.94
Needle vibrator 40mm ( petrol ) 1.333 hours 26.50 1 hour 35.32
Crew charges 1.333 hours 187.20 1 hour 249.54
Add MA on crew charges 0.40 768.47 307.39
Water(including for curing) 1.20 kl 98.00 1 kl 117.60
Rate per 1 cum 9299.54
a) COLUMNS :
un supported height up to 3.66 m
(i) Lifting by Manual means
Rate for other Floors FF SF TF 4F 5F
Rate as above 9299.54 9299.54 9299.54 9299.54 9299.54
Hire charges of centering and scaffolding 238.00 238.00 238.00 238.00 238.00
Labour charges 1845.00 2029.00 2213.00 2398.00 2582.00
Add for MA @ 40% 738.00 811.60 885.20 959.20 1032.80
Lift charges of materials(Manual) 0.00 265.40 530.80 796.20 1061.60
Add for MA @ 40% 0.00 106.16 212.32 318.48 424.64
Rate per 1 cum 12120.54 12749.70 13378.86 14009.41 14638.57
Overheads&Contractors Profit @ 13.615% 0.00 0.00 0.00 0.00 0.00
Rate per 1 cum 12120.54 12749.70 13378.86 14009.41 14638.57
Say 12121 12750 13379 14009 14639
Page 17 of 204
CIVIL DATA : Page-18
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
Add for MA @ 40% 530.80 636.96 743.12
Rate per 1 cum 15270.53 15899.69 16527.45
Overheads&Contractors Profit @ 13.615%
0.00 0.00 0.00
Rate per 1 cum 15270.53 15899.69 16527.45
Say 15271 15900 16527
b) LINTELS :
(i) Lifting by Manual means
Rate for other Floors FF SF TF 4F 5F
Rate as above 9299.54 9299.54 9299.54 9299.54 9299.54
Hire charges of centering and scaffolding 790.00 790.00 790.00 790.00 790.00
Labour charges 1314.00 1445.00 1575.00 1706.00 1838.00
Add for MA @ 40% 525.60 578.00 630.00 682.40 735.20
Lift charges of materials(Manual) 0.00 265.40 530.80 796.20 1061.60
Add for MA @ 40% 0.00 106.16 212.32 318.48 424.64
Rate per 1 cum 11929.14 12484.10 13037.66 13592.61 14148.97
Overheads&Contractors Profit @ 13.615% 0.00 0.00 0.00 0.00 0.00
Rate per 1 cum 11929.14 12484.10 13037.66 13592.61 14148.97
Say 11929 12484 13038 13593 14149
22 Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS 456 with minimum cement
content of 380 kgs per 1 cum of concrete using Concrete Batching Plant with 20mm size graded machine crushed
hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site
and including sales & other taxes on all materials , centering using Casurina Ballies , Bamboos , Wooden Reapers ,
Runners , Wood Posts , Wall Plates etc., for 60cm wide sun-shades 7.5cm thick at fixed end and 5cm thick at
free end with an average thickness of 6.25cm including all operational, incidental and labour charges such as
weigh batching, machine mixing, lifting of concrete manually, laying concrete, curing, overheads & contractors profit
complete etc., but excluding cost of steel and its fabrication charges for finished item of work (APSS No. 402, 403 &
903)
(BLD-CSTN-3-16)
A.MATERIALS :
Cement 380.00 Kgs 5600.00 1000 Kgs 2128.00
20mm HBG graded metal 0.80 Cum 1433.38 1 Cum 1146.70
Sand 0.40 Cum 1896.68 1 Cum 758.67
Page 18 of 204
CIVIL DATA : Page-19
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
B.LABOUR :
1st class Mason 0.067 Nos 500.00 1 Each 33.50
2nd class Mason 0.133 Nos 470.00 1 Each 62.51
Mazdoor (both men&women) 3.077 Nos 445.00 1 Each 1369.27
Add for MA @ 40% 0.40 1465.28 586.11
C.MACHINERY :
Batching plant 0.50 cum 0.308 hours 241.40 1 hour 74.35
Crew charges 0.308 hours 389.30 1 hour 119.90
Add MA on crew charges 0.40 119.90 47.96
Water(including for curing) 1.20 kl 98.00 1 kl 117.60
Rate per 1 cum 6444.58
26 Masonry work in CM(1:6) prop (Cement : Screened sand) in superstructure with fly ash cement / lime solid
blocks of size 290mm x 225mm x 140mm from approved source having minimum crushing strength of 50 Kg/Sqcm.
including cost and conveyance of all materials like cement, sand, bricks, water etc., to site, including sales & other
taxes on all materials and such as labour charges, like mixing cement mortar, scaffolding charges, constructing
masonry, lift charges, curing, overheads and contrctor profit etc., complete for finished item of work. (APSS No. 501 &
504).
(BLD-CSTN-5-17)
Unit = 1 Cum
A.MATERIALS
No of blocks required for
1 Cum of Masonry 110 Nos 26966.43 1000 Nos 2966.31
Cement 24.00 Kgs 5600.00 1000 Kgs 134.40
Fine aggregate ( Sand ) 0.10 cu.m. 2086.68 1 cu.m. 208.67
B .LABOUR
Mason 1st class 0.42 Nos. 500.00 1 Each 210.00
Mason 2nd class 0.92 Nos. 470.00 1 Each 432.40
Man Mazdoor 0.70 Nos. 445.00 1 Each 311.50
Woman Mazdoor 2.10 Nos. 445.00 1 Each 934.50
Add for MA @ 40% 0.40 1888.40 755.36
water charges @ 1% 0.01 5953.14 59.53
Rate per 1 cum 6012.67
Page 19 of 204
CIVIL DATA : Page-20
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
b) Superstructure :
Rate for other Floors FF SF TF 4F 5F 6F
Rate as worked out above 6012.67 6012.67 6012.67 6012.67 6012.67 6012.67
Hire charges for Access Scaffolding 45.87 45.87 45.87 45.87 45.87 45.87
Labour charges for scaffolding 370.80 530.98 691.07 851.24 1011.38 1171.47
Add for MA @ 40% 148.32 212.39 276.43 340.50 404.55 468.59
Lift charges ( Page 131 of Std. Data ) 0.00 188.84 377.68 566.52 755.36 944.20
Add for MA @ 40% 0.00 75.54 151.07 226.61 302.14 377.68
6577.65 7066.28 7554.78 8043.40 8531.97 9020.47
Overheads&Contractors Profit @ 13.615% 0.00 0.00 0.00 0.00 0.00 0.00
Rate per 1 cum 6577.65 7066.28 7554.78 8043.40 8531.97 9020.47
Say 6578 7066 7555 8043 8532 9020
31 Plain Cement Concrete M 20 nominal mix using WEIGH BATCHER / MIXER, 20mm size hard granite machine
crushed graded metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry,
using a minimum quantity of 300 kgs. of cement per 1 cum of concrete including cost and conveyance of all materials
like cement, fine aggregate (Sand), coarse aggregate, water etc., to site including steel centering, shuttering,
machine mixing, lift charges, laying concrete,vibrating, curing, overheads & contrctors profit etc., complete for
finished item of work for coping on top of compound wall (APSS No. 402 & 403).
(BLD-CSTN-3-11)
Unit : 1 cum
A.MATERIALS :
Cement 330.00 Kgs 5600.00 1000 Kgs 1848.00
20mm HBG graded metal 0.90 Cum 1433.38 1 Cum 1290.04
Fine aggregate ( Sand ) 0.45 Cum 1896.68 1 Cum 853.51
Water (including curing) 1.20 kl 98.00 1 kl 117.60
B.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8
cum)capacity 1.00 hour 152.50 1 hour 152.50
Crew charges 1.00 hour 260.00 1 hour 260.00
Add MA on crew charges 0.40 260.00 104.00
C.LABOUR :
1st class mason 0.10 Nos. 500.00 1 Each 50.00
Mazdoor (unskilled) 1.39 Nos. 445.00 1 Each 618.55
Add for MA @ 40% 0.40 668.55 267.42
5561.62
Overheads&Contractors Profit @ 13.615% 0.00000 5561.62
0.00
Rate per 1 cum 5561.62
Say 5562
36 Providing Thermo Mechanically Treated (TMT) (Fe -500/500D/550D from Primary producer TATA, SAIL, VSP,
JSW &Shyam Steel etc as per IS 1786-2008) of different diameters for RCC works , including labour charges for
straightening, cutting, bending to required sizes and shapes, placing in position with cover blocks of approved
materials and size and tying and lap-splicing with binding wire of 18 SWG, forming grills for reinforcement work as per
approved designs and drawings, including cost and conveyance of steel bars, including all wastages such as
overlaps, couplings, chairs, spacer bars including cost and conveyance of binding wire, cover blocks and all
incidental, operational, labour charges such as cutting, bending, placing in position, tying including sales and other
taxes on all materials etc. ,and overheads & contractors profit complete for finished item of work.( APSS No.126)
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
a) Material
TMT bars including 5% for overlaps and
wastage 1.05 MT 43000.00 1 MT 45150.00
Binding wire 6.00 Kgs 55.00 1 Kgs 330.00
b) Labour for cutting , bending , shifting to
site , tying and placing in position
1st class Blacksmith / Barbender 3.00 Nos. 590.00 1 Each 1770.00
2nd class Blacksmith / Barbender 7.00 Nos. 495.00 1 Each 3465.00
Mazdoor(Unskilled) 10.00 Nos. 445.00 1 Each 4450.00
Add for MA @ 40% 0.40 9685.00 3874.00
59039.00
39 Plastering 12mm thick in two coats using screened sand with base coat of 8mm thick in CM (1:6) and top coat of
4mm thick in CM (1:4) with dubara sponge finishing including cost and conveyance of all materials like cement, sand,
water etc., to site, including sales & other taxes on all materials, and all operational, incidental charges on materials
and including cost of all labour charges for mixing mortar, finishing, scaffolding, lift charges, curing, including cutting
grooves as directed by Engineer-in-charge etc., and overheads & contractors profit complete for finished item of
work. (SS 901,903 & 904).
( BLD-CSTN-8-10)
Unit : 10 sqm
A.MATERIALS :
Base coat in CM(1:6) , 8mm thick
Cement 26.40 Kgs 5600.00 1000 Kgs 147.84
Fine aggregate (Sand) 0.11 Cum 2086.68 1 Cum 229.53
Top coat in CM(1:4) , 4mm thick
Cement 14.40 Kgs 5600.00 1000 Kgs 80.64
Fine aggregate (Sand) 0.04 Cum 2086.68 1 Cum 83.47
B.LABOUR :
1st Class Mason 0.63 Nos. 500.00 1 Each 315.00
2nd Class Mason 1.47 Nos. 470.00 1 Each 690.90
Mazdoor (Unskilled) 3.90 Nos. 445.00 1 Each 1735.50
Add for MA @ 40% 0.40 2741.40 1096.56
water charges @ 1% 0.01 4379.44 43.79
Rate per 10 Sqm 4423.24
Rate per 1 Sqm 442.32
Walls in superstructure :
Rate for other Floors FF SF TF 4F 5F 6F
Rate as worked out above 442.32 442.32 442.32 442.32 442.32 442.32
Hire charges for Access Scaffolding 1.03 1.03 1.03 1.03 1.03 1.03
Labour charges for scaffolding 8.35 11.95 15.54 19.15 22.75 26.37
Add for MA @ 40% 3.34 4.78 6.22 7.66 9.10 10.55
Lift charges ( Page 131 of Std. Data ) 0.00 27.41 54.83 82.24 109.66 137.07
Add for MA @ 40% 0.00 10.96 21.93 32.90 43.86 54.83
Rate per 1 Sqm 455.04 498.45 541.87 585.30 628.72 672.17
Overheads&Contractors Profit @ 13.615% 0.00 0.00 0.00 0.00 0.00 0.00
455.04 498.45 541.87 585.30 628.72 672.17
Say 455 498 542 585 629 672
Page 21 of 204
CIVIL DATA : Page-22
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
Rate for other Floors 7F 8F
Rate as worked out above 442.32 442.32
Hire charges for Access Scaffolding 1.03 1.03
Labour charges for scaffolding 29.97 33.56
Add for MA @ 40% 11.99 13.42
Lift charges ( Page 131 of Std. Data ) 164.48 191.90
Add for MA @ 40% 65.79 76.76
Rate per 1 Sqm 715.58 758.99
Overheads&Contractors Profit @ 13.615% 0.00 0.00
715.58 758.99
Say 716 759
46 Flooring with polished shahabad / Tandur stone slabs of 15mm to 18mm thick set over a base coat of CM
(1:8) , 12mm thick using screened sand over already laid CC bed / RCC roof slab including neat cement slurry of
honey like consistency spread @ 3.3 Kgs per Sqm and jointed with neat cement to full depth including cost and
conveyance of all materials like cement, sand, water, flooring stones etc. complete including sales & other taxes on
all materials including all labour charges like dressing of flooring stones to the required size, mixing of cement mortar,
laying, lift charges , cost of base coat, water charges etc., and overheads & contractors profit complete for finished
item of work. (APSS No.703 & 701)
(BLD-CSTN-9-1)
Unit = 10 sqm.
A. MATERIALS:
Polished shahabad stone 15 to 18mm 11.00 Sqm 1891.99 10 Sqm 2081.19
thick
Cement for CM (1:8) proportion for base
coat 21.60 Kgs 5600.00 1000 Kgs 120.96
Cement for slurry 33.00 Kgs 5600.00 1000 Kgs 184.80
Cement for pointing 20.00 Kgs 5600.00 1000 Kgs 112.00
Sand for CM(1:8) 0.12 Cum 2086.68 1 Cum 250.40
B .LABOUR
Mason 1st class 3.10 Nos 500.00 1 Each 1550.00
Mason 2nd class 1.10 Nos 470.00 1 Each 517.00
Mazdoor(un skilled) 0.86 Nos 445.00 1 Each 382.70
Add for MA @ 40% 0.40 2449.70 979.88
Add water charges 1% 0.01 6178.93 61.79
Rate for 10 sqm 6240.72
81 Supply & application of one coat water based cement primer of interior grade I and two coats of acrylic
emulsion paint having VOC (Volatile Organic Compound) content less than 50 grams/litre for internal walls
including cost and conveyance of all materials to site, sales & other taxes, incidental, operational and all labour
charges etc., and overheads & contractors profit complete for finished item of work in all floors.
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
Painter 1st class 0.21 Nos. 570.00 1 Each 119.70
Painter 2nd class 0.49 Nos. 470.00 1 Each 230.30
Acrylic emulsion paint 0.80 Ltrs 195.00 1 Ltrs 156.00
Painter 1st class 0.36 Nos. 570.00 1 Each 205.20
Painter 2nd class 0.84 Nos. 470.00 1 Each 394.80
Add for MA @ 40% 0.40 950.00 380.00
Sundries including brushes , ladders etc.,
@ 1% 0.01 1636.00
1636.00
Overheads&Contractors Profit @ 13.615% 0.00000 1636.00 0.00
Rate per 10 sqm 1636.00
Rate per 1 sqm 163.60
Say 164
82 Supply & application of one coat water based cement primer of exterior grade II and two coats of acrylic
emulsion paint exterior grade with silicon additives having VOC (Volatile Organic Compound) content less than 50
grams/ liter for exterior walls including cost and conveyance of all materials to site, sales & other taxes, incidental,
operational and all labour charges etc., and overheads & contractors profit complete for finished item of work in all
floors.
83 Painting to new wood work and flush shutters with lappam finish, over a primary coat and painting two coats
of synthetic enamel paint Grade-II VOC (Volatile Organic Compound) content less than 50 grams/litre of approved
shade including cost and conveyance of all materials to site cost of primer coat and all labour charges etc. complete
including applying sand paper on lappam coats for neat finish including sales & other taxes on cost of all materials
etc., and overheads & contractors profit complete in all floors (APSS No.1200, 1207 & 1211).
Page 23 of 204
CIVIL DATA : Page-24
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
87 Painting two coats with synthetic enamel paint Grade-II VOC (Volatile Organic Compound) content less than
50 grams/litre over primer coat of red oxide to new iron work including cost and conveyance of all materials to
site, sales & other taxes, incidental, operational and all labour charges etc., and overheads & contractors profit
complete for finished item of work in all floors. (SS No. 1201, 1212 & 1207).
(BLD-CSTN-12-7 & 12-12-197)
Unit : 10 sqm
A.MATERIALS :
Red oxide primer 0.70 Ltr 129.00 1 Ltr 90.30
Cost of Synthetic Enamel Paint 1.10 Ltr 191.00 1 Ltr 210.10
B.LABOUR :
for primer coat
1st Class Painter 0.21 Nos. 570.00 1 Each 119.70
2nd Class Painter 0.49 Nos. 470.00 1 Each 230.30
for enamel painting
1st Class Painter 0.33 Nos. 570.00 1 Each 188.10
2nd Class Painter 0.77 Nos. 470.00 1 Each 361.90
Add for MA @ 40% 0.40 900.00 360.00
Sundries including brushes , ladders etc.,
@ 1% 0.01 1560.40
1560.40
Overheads&Contractors Profit @ 13.615% 0.00000 1560.40 0.00
Rate per 10 sqm 1560.40
Rate per 1 sqm 156.04
Say 156
Unit : 10 sqm
A. MATERIALS:
G.I corrugated 0.80 mm thick sheets 103.09 Kgs 60.00 1 Kg 6185.4
G.I scam bolts & nuts 2 x 27 (laps) x 17 =
884 47.91 Nos. 6.00 1 No. 287.46
G.I ‘J’ bolts 8 mm dia 2 x 5 x 27 sheets x 3
nos = 810 nos. with washers or srews, if
wooden battens used. 43.9 Nos. 10.00 1 No. 439
Limpet washers (for scam & ‘J’ bolts) 884 +
810 = 1694 91.82 Nos. 2.00 1 No. 183.64
Bitumen washers 91.82 Nos. 2.00 1 No. 183.64
Zinc cromate yellow paint 0.14 Ltrs 185.00 1 Ltr 25.9
Ready mixed paint 0.2 Ltrs 251.00 1 Ltr 50.2
B. LABOUR
For roofing
Carpenter II class 0.84 Nos. 470.00 1 No. 394.8
Man mazdoor (beldar) 0.91 Nos. 445.00 1 No. 404.95
For primer painting one coat
Painter 1st class 0.018 Nos. 570.00 1 No. 10.26
Painter 1st class 0.042 Nos. 470.00 1 No. 19.74
Mazdoor (coolie) 0.06 Nos. 445.00 1 No. 26.7
For two coats of painting to over laps
Painter 1st class 0.042 Nos. 570.00 1 No. 23.94
Painter 1st class 0.098 Nos. 470.00 1 No. 46.06
Mazdor (coolie) 0.14 Nos. 445.00 1 No. 62.3
Add for MA @ 40% 0.4 988.75 395.5
Rate per 10 sqm 8739.49
Rate per 1 sqm 873.949
Overheads&Contractors Profit @ 13.615% 0 873.949 0
Rate per 1 sqm 873.949
say 874
Page 24 of 204
CIVIL DATA : Page-25
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
110 Supplying and fabricating, erecting and fixing in position tabular trusses of approved design with M.S tube
conforming to I.S-1161 specifications including roof frame work consisting of rafters,ties struts and purlins including
cost of foundations bolts, cleats, bearings plates,etc.,complete as per the sketch enclosed and including cost of
primary coat with red oxide paint including cost and conveyance of all materials, labour charges for erecting & fixing
all structural steel works erecting in position and fixing by using chain pulley blocks, Derek pole arrangements and
cranes etc., complete in position, labour charges for fabrication, all incidental charges, overheads and contractor
profit etc., complete for finished item of work as directed by the Engineer-in-Charge
Page 25 of 204
JOINERY DATA
Joinery data 26
COMMON SoR 2019-2020
b) Labour charges for aluminium doors ( S.No.11 of Page No. 396 of SoR 2011-12 )
1st class carpenter 0.099 Nos. 590.00 Each 58.41
2nd class carpenter 0.198 Nos. 470.00 Each 93.06
Power Saw Cutter -Hand Operated -Operator 0.099 Nos. 590.00 Each 58.41
Power Drill -Hand Operated -Operator 0.099 Nos. 590.00 Each 58.41
Mazdoor(Unskilled) 0.297 Nos. 445.00 Each 132.17
Non-technical work inspector 0.099 Nos. 590.00 Each 58.41
Add for MA @ 40% 0.40 458.87 183.55
Machinery
Power Saw Cutter -Hand Operated -Hire charges 0.793 Hrs 130.00 1 Hour 103.09
Power Drill -Hand Operated -Hire charges 0.793 Hrs 121.00 1 Hour 95.95
841.45
Power charges for Motors 1% 0.01 841.45 8.41
Labour charges per 1 sqm 849.87
c) Labour charges for aluminium sliding windows ( S.No.10 of Page No. 395 of SoR 2011-12 )
1st class carpenter 0.096 Nos. 590.00 Each 56.64
2nd class carpenter 0.289 Nos. 470.00 Each 135.83
Power Saw Cutter -Hand Operated -Operator 0.096 Nos. 590.00 Each 56.64
Power Drill -Hand Operated -Operator 0.096 Nos. 590.00 Each 56.64
Mazdoor(Unskilled) 0.289 Nos. 445.00 Each 128.61
Non-technical work inspector 0.096 Nos. 590.00 Each 56.64
Add for MA @ 40% 0.40 491.00 196.40
C.Machinery
Power Saw Cutter -Hand Operated -Hire charges 0.771 Hrs 130.00 1 Hour 100.23
Power Drill -Hand Operated -Hire charges 0.771 Hrs 121.00 1 Hour 93.29
880.91
Power charges for Motors 1% 0.01 880.91 8.81
Labour charges per 1 sqm 889.72
d) Labour charges for aluminium partitions partly glazed ( S.No.8 of Page No. 394 of SoR 2011-12 )
1st class carpenter 0.434 Nos. 590.00 Each 256.06
2nd class carpenter 0.434 Nos. 470.00 Each 203.98
Power Saw Cutter -Hand Operated -Operator 0.043 Nos. 590.00 Each 25.37
Power Drill -Hand Operated -Operator 0.058 Nos. 590.00 Each 34.22
Mazdoor(Unskilled) 0.145 Nos. 445.00 Each 64.53
Non-technical work inspector 0.072 Nos. 590.00 Each 42.48
Add for MA @ 40% 0.40 626.64 250.65
C.Machinery
Power Saw Cutter -Hand Operated -Hire charges 0.347 Hrs 130.00 1 Hour 45.11
Power Drill -Hand Operated -Hire charges 0.463 Hrs 121.00 1 Hour 56.02
978.42
Power charges for Motors 1% 0.01 978.42 9.78
Labour charges per 1 sqm 988.21
e) Labour charges for aluminium casement windows ( S.No.9 of Page No. 394 of SoR 2011-12 )
1st class carpenter 0.100 Nos. 590.00 Each 59.00
2nd class carpenter 0.300 Nos. 470.00 Each 141.00
Power Saw Cutter -Hand Operated -Operator 0.100 Nos. 590.00 Each 59.00
Power Drill -Hand Operated -Operator 0.100 Nos. 590.00 Each 59.00
Mazdoor(Unskilled) 0.300 Nos. 445.00 Each 133.50
Non-technical work inspector 0.100 Nos. 590.00 Each 59.00
Joinery data 27
Add for MA @ 40% 0.40 510.50 204.20
C.Machinery
Power Saw Cutter -Hand Operated -Hire charges 0.800 Hrs 130.00 1 Hour 104.00
Power Drill -Hand Operated -Hire charges 0.800 Hrs 121.00 1 Hour 96.80
915.50
Power charges for Motors 1% 0.01 915.50 9.16
Labour charges per 1 sqm 924.66
14 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and ISI
marked flush door shutters of 30 mm thick double shutters with bond wood solid block board type Core having
cross bands and face veneers, hot pressed bonded with water proof phenol formaldehyde synthetic resin factory
made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal lipping on all sides including cost
and conveyance to site of teak wood frame, flush shutter including
supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium
fixtures of 6 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos. tower bolts (IS:204)
of 200 mm x 10 mm dia at top, 2 Nos. 150 mm long handles (IS:208), 2 Nos. door stoppers and 2 Nos. rubber
bushes including fixing the fixtures to door with required number of screws, bolt and nuts including labour charges
for fixing the frame in position, fixing the shutter to the frame etc., including overheads & contractors profit complete
for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in flooring for a
depth of not less than 10 mm) (1200mm x 2100mm).
(BLD-CSTN-13-16)
Size : 1.20m x 2.10m 2.52 Sqm
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743 cum
Outer frame - Horizontal 1 x 1.20
= 1.20 x 0.10 x 0.065 0.00780 cum
0.03523 cum
32 Supplying and fixing of 2 shutter fully glazed windows as per drawing using Sal wood frame and one vertical
mullion of size 100mm x 65mm and shutters with Sal wood styles & rails of size 75mmx35mm and 4mm thick pin
headed glass fixed with teak wood beading of 12mm X 12mm including cost of 4 Nos MS Z hold fasts of size 300 x
40 x 5 mm including supply and fixing of ISI marked aluminium fixtures, butt hinges of size 75mm long (2 Nos per
shutter), 75mm handles (1No per shutter), 75mm x 10mm dia tower bolt (1No per shutter), and aluminium window
stopper with hook and eye 100mm long (1No per shutter) with 12mm MS square bars horizontally at 100mm centre
to centre fixed in frame including labour charges for fixing the fixtures with required No. of screws, fixing window in
position fixing shutters to frame including cost & conveyance of all materials to site, labour charges etc., complete for
finished item of work (APSS No 1001 & 1002).(1200mm x 1300mm)
Size : 1200mm x 1300mm
Joinery data1.56 Sqm 28
Frame (2x(1.20+1.30)x0.10x0.065 0.0325 Cum
Mullions (2x 1.30 x 0.10 x 0.065) 0.0169 Cum
Styles: (2x2x(0.49+1.03) x
0.075x0.035) 0.01596
Rails: (2x 2 x 0.49 x 0.075 x 0.035) 0.005145
0.07046 Cum 48543.00 1 Cum 3420.34
4mm thick pin headed glass (2x0.51x1.24). 1.26 Sqm 309.00 1 Sqm 389.34
Teak wood beading(2x2x(0.51+1.24)) 7.00 RM 20.00 1 RM 140.00
12m MS square bars (11 x 1.22 x 1.13 Kgs/m) 15.16 Kg 43052.63 1 MT 652.68
MS 'Z' hold fasts 4 Nos. 18.00 1 Each 72.00
MS powder coated butt hinges 75mm long. 4 Nos. 11.00 1 Each 44.00
MS powder coated tower bolts 100mm long 2 Nos. 23.00 1 Each 46.00
MS powder coated handles 125mm 2 Nos. 31.00 1 Each 62.00
MS powder coated hook and eye 2 Nos. 20.00 1 Each 40.00
Labour charges for frame and shutters 0.071 Cum 12872.20 1 Cum 913.93
Labour charges for fixing glass 1.26 Sqm 199.00 1 Sqm 250.74
Labour charges for shutters and fixing fixtures 2.16 1164.67 2515.68
Add for screws, nails etc., LS 4.79
8551.49
0 0.00 8551.49 0.00
8551.49
Rate for 1 sqm 5481.73
Say 5482
WS & SA DATA 2014-15 Page-29
COMMON SoR 2019-2020
DATA FOR WATER SUPPLY AND SANITARY ITEMS
Sl.No Description Qty Unit Rate Per Unit Amount
1 Supplying and laying, filling, jointing and testing SWG SP-1 pipe conforming to ISI 651 & 4127 with air
tight Cement joints in CM (1.5:1) prop. including excavation of trenches and socket pits in any soil (except
rock requiring blasting) and refilling with watering and tamping to the required slope including cost and
conveyance of all materials to site and all labour charges , overheads & contractor profit etc., complete for
finished item of work (APSS NO 1301 & 1318).
2 Constructing 904.0 mm (3’0”) dia brick masonry inspection chamber as per IS - 4111: Part-1:1986
with cement mortar (1:6) prop using 2nd Class Clay Bricks of 225 mm thick from approved source having a
minimum crushing strength of 5 N/sq.mm including plastering with cement mortar 1:3 prop; ½” thick both
inside and outside fitted with 20” dia RCC manhole covers and frames including excavating pits up to a
depth of 904 mm (3'-0") in all sorts of soils (exculding rock) and laying cement conrete (1:4:8) 150 mm
thick using 40 mm HBG Metal and P.C.C. 1:2:4 benching and channel 100 mm thick as per Standard
specification and including cost and conveyance of all materials like cement, sand, bricks, water etc., to
site, cost of seigniorage charges on all materials and all incidental and operational, labour charges like
mixing cement mortar, constructing masonry, lift charges, curing , overheads & contractors profit etc.,
complete for finished item of work as per Standard specification.
3 Constructing 904.0 mm (3’0”) dia brick masonry inspection chamber as per IS - 4111: Part-1:1986
with cement mortar (1:6) prop using 2nd Class Clay Bricks of 225 mm thick from approved source having a
minimum crushing strength of 5 N/sq.mm including plastering with cement mortar 1:3 prop; ½” thick both
inside and outside fitted with 20” dia RCC manhole covers and frames including excavating pits up to a
depth of 1524 mm (5'-0") in all sorts of soils (exculding rock) and laying cement conrete (1:4:8) 150 mm
thick using 40 mm HBG Metal and P.C.C. 1:2:4 benching and channel 100 mm thick as per Standard
specification and including cost and conveyance of all materials like cement, sand, bricks, water etc., to
site, cost of seigniorage charges on all materials and all incidental and operational, labour charges like
mixing cement mortar, constructing masonry, lift charges, curing , overheads & contractors profit etc.,
complete for finished item of work as per Standard specification.
4 Constructing 457.2 mm x 457.2 mm (1'6"x1'6") brick in CM 1:6 prop. Masonry. Inspection chamber
upto 914.4 mm (3'0") and fitted with light weight 457.2 mm x 457.2 mm (1'6"x1'6") C.I frame and cover of
20 Kg including cost and conveyance of all materials like cement, sand, bricks, water etc., to site, cost of
seigniorage charges on all materials and all incidental and operational, labour charges like mixing cement
mortar, constructing masonry, lift charges, curing , overheads & contractors profit etc., complete for
finished item of work as per Standard specification.
5 Supplying and fixing of SWG Gully traps 150mm x 100mm of ISI make confirming to IS 651 & 4127 with
C.I grating & constructing cement brick masonry in CM (1:6) prop., intermediate chamber and fitted with
304.8 mm X 288.6 mm (12"x9") C.I Frame with hinged cover of standard make as approved including cost
and conveyance of all materials to site, labour charges, overheads & contractors profit etc., complete for
finished item of work.
6 Supplying and fixing of 3" (75mm) Nahany trap with jali - UPVC/SWR pipe fittings as per site
requirements with standard practice for all floors including cost and conveyance of all materials to site,
labour charges , overheads & contractors profit etc., complete for finished item of work.
7 Supplying and fixing of 4" (101.6mm) multi floor trap with jali - UPVC/SWR pipe fittings as per site
requirements with standard practice for all floors including cost and conveyance of all materials to site,
labour charges , overheads & contractors profit etc., complete for finished item of work.
9 Supplying and fixing European Water Closet of 1st quality conforming to IS:2556-Part-2-1973 of white
glazed with 'S' trap,supplying and fixing best Indian make plastic seat and lid for European water closets
with rubber or plastic Buffers as per IS 2548-1996 and 10 litres capacity single flush PVC low level cistern
with internal components and fixed using required size of nails and screws, 15 mm nominal size CP finish
brass angled stop valve screw type with internal /external threaded conforming to IS 8931, 12mm PVC
connections with brass union nuts CP coated including cost and conveyance of all materials to site,
overheads & contractors profit etc., complete for finished item of work for all floors.
10 Supplying and fixing Indian make Flat Back Wash Hand Basin 1st quality conforming to IS:2556-Part-
4:1972 of size 550mm x 400mm with 32 mm nominal size C.P. Fitting with parallel pipe thread conforming
to IS:2963-1979 and fitted with 15 mm nominal bore Chromium Plated Pillar Tap of 1st quality Indian make
heavy duty complete with standard CI brackets including wooden blocks ,1 No.12.70mm PVC connection
with brass union nuts CP coated , angle stop cock 12.70mm dia. first quality Indian make heavy duty,
30mm dia. PVC flexible waste pipe 914.4mm length of 1st quality including cost and conveyance of all
materials to site, labour charges , overheads & contractors profit for finished item of work
11 Supplying and fixing CP finish brass soap dish of approved make ISI quality including cost and
conveyance of all materials, labour charges for fixing , overheads & contractors profit for finished item of
work in all floors
12 Supplying and fixing TV shape mirror with plastic frame of size 609.6mm x 457.2mm , plywood back
with NP screws 1st quality including cost and conveyance of all materials, labour charges , overheads &
contractors profit for finished item of work in all floors.
14 Supplying and fixing 15 mm brass body CP finish bib tap of not less than 300 grams weight screw
type (full turn) with internal / external threaded connection conforming to IS 8931 as approved by the
Engineer-In-Charge including cost and conveyance of all materials, labour charges , overheads &
contractors profit complete for finished item of work in all floors.
Rate as per SSR 1 No. 224.00 Each 224.00
Add for MA @ 40% 0.40 53.00 21.20
245.20
Overheads&Contractors Profit @ 13.615% 0.00000 245.20 0.00
245.20
Rate per Each say 245
15 Supplying and fixing 15 mm brass body CP finish self closing tap push type conforming to IS 1711
as approved by the Engineer-In-Charge including cost and conveyance of all materials, labour charges,
overheads & contractors profit complete for finished item of work in all floors.
Rate as per SSR 1 No. 247.00 Each 247.00
Add for MA @ 40% 0.40 53.00 21.20
268.20
Overheads&Contractors Profit @ 13.615% 0.00000 268.20 0.00
268.20
Rate per Each say 268
16 Supplying and fixing Chromium plated finish brass body quarter turn Bibcock cum Health Faucet
with 1m long tube and wall hook with 7 - 10 years warranty with necessary fittings etc., complete
including cost and conveyance of all materials, labour charges, overheads & contractor profit complete for
finished item of work in all floors.
Rate as per SSR 1 No. 2929.00 Each 2929.00
Add for MA @ 40% 0.40 53.00 21.20
2950.20
Overheads&Contractors Profit @ 13.615% 0.00000 2950.20 0.00
2950.20
Rate per Each say 2950
17 Supplying and fixing of SWR PVC pipes (Prince/Sudhakar/Kisan/Supreme or any ISI brand) 4
Kg/Sq.cm. and fixing all special such as plain bends, off sets, door bends, single junctions, double
junctions as per site requirement, fixing with PVC clamps if necessary with required number of Bombay
nails including cost and conveyance of all materials to site, labour charges, overheads & contractors profit
complete for finished item of work at all floor levels. (APSS No. 1302 1319 & 1326)
a) 75mm dia
Data for 6 RM
Cost of 75mm dia pipe 6.00 RM 252.00 3 RM 504.00
Cost of PVC clamps 3 Nos. 15.00 Each 45.00
Labour charges 6.00 RM 79.00 1 RM 474.00
Add for MA @ 40% 0.40 474.00 189.60
1212.60
Rate per 1 RM 202.10
Overheads&Contractors Profit @ 13.615% 0.00000 202.10 0.00
202.10
say 202
b) 90mm dia
Data for 6 RM
Cost of 90mm dia pipe 6.00 RM 401.00 3 RM 802.00
Cost of PVC clamps 3 Nos. 17.00 Each 51.00
WS & SA DATA 2014-15 Page-34
Labour charges 6 RM 79.00 1 RM 474.00
Add for MA @ 40% 0.40 474.00 189.60
1516.60
Rate per 1 RM 252.77
Overheads&Contractors Profit @ 13.615% 0.00000 252.77 0.00
252.77
say 253
c) 110mm dia
Data for 6 RM
Cost of 110mm dia pipe 6.00 RM 479.00 3 RM 958.00
Cost of PVC clamps 3 Nos. 18.00 Each 54.00
Labour charges 6 RM 79.00 1 RM 474.00
Add for MA @ 40% 0.40 474.00 189.60
1675.60
Rate per 1 RM 279.27
Overheads&Contractors Profit @ 13.615% 0.00000 279.27 0.00
279.27
say 279
a) 15.90mm OD pipe
Rate as per SoR 1 No. 129.00 Each 129.00
Overheads&Contractors Profit @ 13.615% 0.00000 129.00 0.00
Rate per 1 RM 129.00
say 129
b) 22.20mm OD pipe
Rate as per SoR 1 No. 147.00 Each 147.00
Overheads&Contractors Profit @ 13.615% 0.00000 147.00 0.00
Rate per 1 RM 147.00
say 147
c) 28.60mm OD pipe
Rate as per SoR 1 No. 194.00 Each 194.00
Overheads&Contractors Profit @ 13.615% 0.00000 194.00 0.00
Rate per 1 RM 194.00
say 194
d) 34.90mm OD pipe
Rate as per SoR 1 No. 264.00 Each 264.00
Overheads&Contractors Profit @ 13.615% 0.00000 264.00 0.00
Rate per 1 RM 264.00
say 264
e) 41.30mm OD pipe
Rate as per SoR 1 No. 329.00 Each 329.00
Overheads&Contractors Profit @ 13.615% 0.00000 329.00 0.00
WS & SA DATA 2014-15 Page-35
Rate per 1 RM 329.00
say 329
f) 54.00mm OD pipe
Rate as per SoR 1 No. 479.00 Each 479.00
Overheads&Contractors Profit @ 13.615% 0.00000 479.00 0.00
Rate per 1 RM 479.00
say 479
18 Supply and fixing of Ashirvad/ Ajay/ Astral Flowguard or equivalent CPVC Pipes and Fittings SDR
11 to meet the requirement of ASTM-D 2846 and are produced in CTS (Copper Tube Sizes 1/2" to 2") for
hot and cold water (IS 15778:2007) including cost and conveyance of all materials to site, labour charges
for fixing, overheads & contractors profit complete for finished item of work at all floor levels.
a) 15.90mm OD pipe
Rate as per SoR 1 No. 142.00 Each 142.00
Overheads&Contractors Profit @ 13.615% 0.00000 142.00 0.00
Rate per 1 RM 142.00
say 142
b) 22.20mm OD pipe
Rate as per SoR 1 No. 173.00 Each 173.00
Overheads&Contractors Profit @ 13.615% 0.00000 173.00 0.00
Rate per 1 RM 173.00
say 173
c) 28.60mm OD pipe
Rate as per SoR 1 No. 207.00 Each 207.00
Overheads&Contractors Profit @ 13.615% 0.00000 207.00 0.00
Rate per 1 RM 207.00
say 207
d) 34.90mm OD pipe
Rate as per SoR 1 No. 282.00 Each 282.00
Overheads&Contractors Profit @ 13.615% 0.00000 282.00 0.00
Rate per 1 RM 282.00
say 282
e) 41.30mm OD pipe
Rate as per SoR 1 No. 350.00 Each 350.00
Overheads&Contractors Profit @ 13.615% 0.00000 350.00 0.00
Rate per 1 RM 350.00
say 350
f) 54.00mm OD pipe
Rate as per SoR 1 No. 510.00 Each 510.00
Overheads&Contractors Profit @ 13.615% 0.00000 510.00 0.00
Rate per 1 RM 510.00
say 510
19 Supplying & fixing GI pipe Medium Grade properties & weight as per IS 1239 ISI mark in ground or
on wall including cost of tees, elbows, bends, reducers, couplings, running joints, union flanges, unions
etc. with necessary excavation in all types of soils except rock requiring blasting, refilling, chiselling
masonry walls and making good the walls & floors to the original surface and fixing MS clamps on TW
blocks on walls including cost and conveyance of all materials and labour charges , overheads &
contractors profit complete for finished item of work.
19 Supplying and fixing 65 mm Nominal Bore GI pipe Medium Grade properties & weight as per IS
1239 in ground or on wall with GI fittings such as elbows tees couplings, nipples, plugs including
excavation for trenches and refilling the trenches ,chiselling masonry walls and making good the walls &
floors to the original surface and fixing MS clamps on TW blocks on walls including cost and conveyance
of all materials and labour charges , overheads & contractors profit complete for finished item of work
except for GI bends union and GI connectors with checkout and socket Tata or Zenith make or
equivalent.
20 Supplying and fixing Bronze Gate/ Globe valve as per IS - 778 Class - I, Indian make heavy type
including cost and conveyance of all materials , labour charges , overheads & contractors profit complete
for finished item of work.
21 Providing and placing on terrace (at all floor levels)polyetheylene water storage tank with double
layer approved brand and manufacture with cover and suitable locking arrangement and making
necessary holes for inlet and outlets and over flow pipes but without fittings and base support for tanks
including cost and conveyance of all materials and labour charges , overheads & contractors profit
complete for finished item of work.
22 Supplying and fixing of stainless steel sink of size 508.00mm x 457.2mm x 203.20mm, 1mm thick of
Indian make fixed on cantilever brackets including supply and fixing 31.75mm C.P. waste coupling, 30mm
dia PVC flexible waste pipe of 914.4 mm length of Ist quality ncluding chiselling brick masonry wall and
making good & restoring to original surfaces , overheads & contractors profit complete for finished item of
work in all floors
23 Supplying and fixing white glazed flat back half stall urinals of size 590 mm x 375 mm x 390 mm
with integral flushing rim fixed with screws complete Indian make (HSW/Parry/Neycer) conforming to
IS:2556-1995 as approved by Engineer-in-charge, including supply and fixing 12.7mm PVC connection
with brass plumber union nuts CP coated, 12.70mm push cock 1st quality of approved make, 30mm dia
PVC flexible waste pipe of 914.4 mm length of Ist quality including cost and conveyance of all materials to
site, labour charges etc., overheads & contractors profit complete for finished item of work for all floors.
24 Supplying and fixing of 16mm to 20 mm thick polished marble slab partitioins of size 4' 0" x 2' 0"
for urinals including full rounding the edges, fixing in position, polishing, including cost and conveyance of
all materials and labour charges, overheads & contractors profit complete for finished item of work for all
floors.
25 Supplying and fixing of 101.60mm x 609.60mm white glazed porcelain channels 1st quality fixed in
brick masonry to the required slopes, white cement pointing including cost and conveyance of all
materials and labour charges, overheads & contractors profit complete for finished item of work for all
floors.
Rate as per SSR 1 No 451.00 1 Each 451.00
Rate for 1 RM (1/0.6096) 451.00 739.83
Overheads&Contractors Profit @ 13.615% 0.00000 739.83 0.00
739.83
Say 740
26 Construction of brick masonry support for GI pipe of size 304.80mm x 228.60mm x 228.60 mm in
CM (1:8) prop including plastering and finishing with 12mm thick in CM (1:5) including cost and
conveyance of all materials and all labour charges, overheads & contractors profit complete for finished
item of work for all floors.
WS & SA DATA 2014-15 Page-40
Rate as per SSR 1 No 77.00 1 Each 77.00
Add for MA @ 40% 0.40 0.00 0.00
77.00
Overheads&Contractors Profit @ 13.615% 0.00000 77.00 0.00
77.00
Rate per Each Say 77
WS & SA DATA 2014-15 Page-41
Page 42 of 204
Copper Pipe for Medical use with 22 OD X 1.0 mm
5 6500 Mtr Mtr 570 3705000 1948.4 Mtr 570 1110588 0 2594412
V.P 27/ MB No.540
Copper Pipe for Medical use with 28 OD X 1.0 mm
6 4000 Mtr Mtr 857 3428000 1884 Mtr 857 1614588 0 1813412
V.P 27/ MB No.540
Copper Pipe for Medical use with 42 OD X 1.0 mm
7 300 Mtr Mtr 1499 449700 265 Mtr 1499 397235 0 52465
V.P 28/ MB No.540
Gas Outlets double lock with probe
8 Oxygen outlets(Indeginous) as per HTM 2022 1100 Nos Nos 1535 1688500 993 Nos 1535 1524255 0 164245
V.P 28/ MB No.540
9 Oxygen flowmeter complete with Humidifier bottle 1100 Nos Nos 1025 1127500 993 Nos 1025 1017825 0 109675
V.P 29/ MB No.540
14 Vacuum outlets(Indeginous) -with Probes By 300 Nos Nos 1535 460500 249 Nos 1535 382215 0 78285
considering 300 Beds for Oxygen and Vacuum
V.P 28/ MB No.540
15 Air-4 bar outlets(Indeginous) with Probes by 300 Nos Nos 1535 460500 249 Nos 1535 382215 0 78285
considering 100 beds with Oxygen, Air and Vacuum
V.P 28/ MB No.540
Ward Vacuum Unit.
Page 43 of 204
Ward Vacuum Unit complete with Regulator ,
16 collection bottle, Adapter and Bracket for collection 300 Nos Nos 1714 514200 249 Nos 1714 426786 0 87414
bottle
V.P 29/ MB No.540
Compressed Air System
Compressed Air System Consisting of 2 nos
(Reciprocating & oil free), each having 15 HP Motor
with 57.18 cfm capacity at 8.5Kg/cm2 pressure with
common receiver of Capacity 1000 ltrs, common Air
drier, Pressure Reducing Unit etc.
17 3-Stage Breathing Air Filter for 125 CFM as per ISO 1 Nos Nos 1114554 1114554 1 Nos 1114554 1114554 0 0
8573-1
Page 44 of 204
3 Gas Microprocessor Controlled Alarm With Digital
20 Display 4 Nos Nos 21580 86320 3 Nos 21580 64740 0 21580
22 High Pressure tube imported 400 Nos Nos 92 36800 350 Nos 92 32200 0 4600
23 Low Pressure Tube 400 Nos Nos 97 38800 350 Nos 97 33950 0 4850
Bed Head Panel.
bed Head Panel : The bed Head Panel should have
24 provision for Medical Gas outlet & electrical sockets 300 7069 2120700 249 Nos 7069 1760181 0 360519
for 2+2
Page 45 of 204
Fully automatic control pannel with non haloginated
polymers 1 Each 476900 476900 476900 0
Page 46 of 204
Painting two coats with synthetic enamel
paint Grade-II VOC (Volatile Organic
Compound) content less than 50 grams/litre
over primer coat of red oxide to new iron
work including cost and conveyance of all
materials to site, sales & other taxes, incidental, As psr site
6 operational and all labour charges etc., and 131.11 Sqm 156 20453 20453 0 condition it
overheads & contractors profit complete for isexcuted
finished item of work in all floors. (SS No. 1201,
1212 & 1207).
Page 47 of 204
Earth work excavation for foundations (Manual
Means) of buildings, septic tank, sump, As per
compound wall in ordinary soils and depositing on emergency work
bank with an initial lead of 10m and 1m additional for covid-19 not
lift charges over the initial depth up to 3m
avilable for
including all operational,incidental, labour charges
such as shoring, sheeting, planking, strutting etc., manifold room
8 and overheads & contractors profit complete for 73.29 Cum 239 17516 17516 0 in the premises
finished item of work excluding dewatering charges of gandhi
etc., as per SS 20 B(APSS 308) hospital for
oxygen pipe line
hence it is
excuted
Page 48 of 204
Plain Cement Concrete (1:5:10) (cement: fine
aggregate: Coarse aggregate) for foundations and
under flooring bed using coarse aggregate 40mm As per
size hard , machine crushed granite from emergency work
approved quarry including cost and conveyance of all for covid-19 not
materials like cement, sand, coarse aggregate, water avilable for
etc. to site, sales & other taxes on all materials and manifold room
10 including all charges for machine mixing, laying 24.38 Cum 4121 100470 100470 0 in the premises
concrete in foundations and under flooring bed,
of gandhi
ramming in 15 cm layers finishing top surface to the
required level curing etc.,and overheads &
hospital for
contractors profit complete for finished item of work. oxygen pipe line
(APSS No. 402) hence it is
excuted
Page 49 of 204
Supply and placing of the Design Mix Concrete
M 25 grade corresponding to IS 456 with minimum
cement content of 380 kgs per 1 cum of concrete
using Concrete Batching Plant with 20mm size
graded machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1
to Part 8) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site
and sales & other taxes on all materials , centering
using Steel scaffolding pipes , jack props , wallers ,
Foot plates , brackets , steel centering plates etc.,
including all operational, incidental and labour
charges such as weigh batching, machine mixing,
laying concrete, curing etc., and overheads &
contractors profit complete but excluding cost of steel
and its fabrication charges for finished item of work
(APSS No. 402).
Page 50 of 204
Providing Thermo Mechanically Treated (TMT)
(Fe -500/500D/550D from Primary producer
TATA, SAIL, VSP, JSW &Shyam Steel etc as
per IS 1786-2008) of different diameters for RCC
works , including labour charges for straightening,
cutting, bending to required sizes and shapes, As per
placing in position with cover blocks of approved emergency work
materials and size and tying and lap-splicing with for covid-19 not
binding wire of 18 SWG, forming grills for
avilable for
reinforcement work as per approved designs and
drawings, including cost and conveyance of steel manifold room
12 bars, including all wastages such as overlaps, 0.358 MT 59039 21136 21136 0 in the premises
couplings, chairs, spacer bars including cost and of gandhi
conveyance of binding wire, cover blocks and all hospital for
incidental, operational, labour charges such as oxygen pipe line
cutting, bending, placing in position, tying including hence it is
sales and other taxes on all materials etc. ,and excuted
overheads & contractors profit complete for finished
item of work.( APSS No.126)
Page 51 of 204
Supply and placing of the Design Mix Concrete
M 25 grade corresponding to IS 456 with minimum
cement content of 380 kgs per 1 cum of concrete
using Concrete Batching Plant with 20mm size
graded machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 As per
to Part 8) from approved quarry including cost and emergency work
conveyance of all materials like cement, fine for covid-19 not
aggregate (sand) coarse aggregate, water etc., to site avilable for
and sales & other taxes on all materials , centering manifold room
13 using Steel scaffolding pipes , jack props , wallers , in the premises
Foot plates , brackets , steel centering plates etc., of gandhi
including all operational, incidental and labour hospital for
charges such as weigh batching, machine mixing,
oxygen pipe line
laying concrete, curing etc., and overheads &
contractors profit complete but excluding cost of steel
hence it is
and its fabrication charges for finished item of work excuted
(APSS No. 402).
Page 52 of 204
Supply and placing of the Design Mix Concrete
M 25 grade corresponding to IS 456 with minimum
cement content of 380 kgs per 1 cum of concrete
using Concrete Batching Plant with 20mm size
graded machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 As per
to Part 8) from approved quarry including cost and emergency work
conveyance of all materials like cement, fine for covid-19 not
aggregate (sand) coarse aggregate, water etc., to site avilable for
and sales & other taxes on all materials, centering manifold room
14 using Casurina Ballies, Bamboos, Wooden Reapers, in the premises
Runners, Wood Posts, Steel Plates etc., including all of gandhi
operational, incidental and labour charges such as hospital for
weigh batching, machine mixing, lifting of concrete
oxygen pipe line
manually, laying concrete, curing , overheads &
contractors profit etc., complete but excluding cost of
hence it is
steel and its fabrication charges for finished item of excuted
work (APSS No. 402)
Page 53 of 204
Supply and placing of the Design Mix Concrete
M 25 grade corresponding to IS 456 with minimum
cement content of 380 kgs per 1 cum of concrete
using Concrete Batching Plant with 20mm size
graded machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1
to Part 8) from approved quarry including cost and
conveyance of all materials like cement, fine As per
aggregate (sand) coarse aggregate, water etc., to site emergency work
and including sales & other taxes on all materials , for covid-19 not
centering using Casurina Ballies , Bamboos , avilable for
Wooden Reapers , Runners , Wood Posts , Wall manifold room
Plates etc., for 60cm wide sun-shades 7.5cm thick
15 4.5 Sqm 505 2273 2273 0 in the premises
at fixed end and 5cm thick at free end with an
average thickness of 6.25cm including all
of gandhi
operational, incidental and labour charges such as hospital for
weigh batching, machine mixing, lifting of concrete oxygen pipe line
manually, laying concrete, curing, overheads & hence it is
contractors profit complete etc., but excluding cost of excuted
steel and its fabrication charges for finished item of
work (APSS No. 402, 403 & 903)
Page 54 of 204
Supplying and fixing of 2 shutter fully glazed
windows as per drawing using Sal wood frame and
one vertical mullion of size 100mm x 65mm and
shutters with Sal wood styles & rails of size
75mmx35mm and 4mm thick pin headed glass fixed
with teak wood beading of 12mm X 12mm including
cost of 4 Nos MS Z hold fasts of size 300 x 40 x 5 As per
mm including supply and fixing of ISI marked emergency work
aluminium fixtures, butt hinges of size 75mm long (2 for covid-19 not
Nos per shutter), 75mm handles (1No per shutter), avilable for
75mm x 10mm dia tower bolt (1No per shutter), and manifold room
17 aluminium window stopper with hook and eye 100mm 4.32 Sqm 5482 23682 23682 0 in the premises
long (1No per shutter) with 12mm MS square bars
of gandhi
horizontally at 100mm centre to centre fixed in frame
including labour charges for fixing the fixtures with hospital for
required No. of screws, fixing window in position oxygen pipe line
fixing shutters to frame including cost & conveyance hence it is
of all materials to site, labour charges etc., complete excuted
for finished item of work (APSS No 1001 & 1002).
(1200mm x 1300mm)
Page 55 of 204
supply and fixing 6 Nos. MS Z hold fasts of size
300 mm x 40 mm x 5mm including cost of ISI
marked Aluminium fixtures of 6 Nos. butt hinges
(IS:205) 150mm long, 1 No. aldrop (IS:2681)
300mm long, 2 Nos. tower bolts (IS:204) of 200
mm x 10 mm dia at top, 2 Nos. 150 mm long As per
handles (IS:208), 2 Nos. door stoppers and 2 emergency work
Nos. rubber bushes including fixing the fixtures for covid-19 not
to door with required number of screws, bolt and avilable for
nuts including labour charges for fixing the frame manifold room
in position, fixing the shutter to the frame etc., 5.04 Sqm 3548 17882 17882 0 in the premises
including overheads & contractors profit of gandhi
complete for finished item of work as per APSS hospital for
1001 & 1002 (The vertical frame of door shall be oxygen pipe line
embedded in flooring for a depth of not less than hence it is
10 mm) (1200mm x 2100mm). excuted
Page 56 of 204
Flooring with polished shahabad / Tandur stone
slabs of 15mm to 18mm thick set over a base coat
of CM (1:8) , 12mm thick using screened sand over
already laid CC bed / RCC roof slab including neat As per
cement slurry of honey like consistency spread @ 3.3 emergency work
Kgs per Sqm and jointed with neat cement to full for covid-19 not
depth including cost and conveyance of all materials avilable for
like cement, sand, water, flooring stones etc. manifold room
complete including sales & other taxes on all
20 61.05 Sqm 624 38095 38095 0 in the premises
materials including all labour charges like dressing of
flooring stones to the required size, mixing of cement of gandhi
mortar, laying, lift charges , cost of base coat, water hospital for
charges etc., and overheads & contractors profit oxygen pipe line
complete for finished item of work. (APSS No.703 & hence it is
701) excuted
Page 57 of 204
Supply & application of one coat water based
cement primer of exterior grade II and two coats As per
of acrylic emulsion paint exterior grade with silicon emergency work
additives having VOC (Volatile Organic Compound)
content less than 50 grams/ liter for exterior walls
for covid-19 not
including cost and conveyance of all materials to site, avilable for
sales & other taxes, incidental, operational and all manifold room
22 labour charges etc., and overheads & contractors 132.84 Sqm 240 31882 31882 0 in the premises
profit complete for finished item of work in all floors. of gandhi
hospital for
oxygen pipe line
hence it is
excuted
Page 58 of 204
Roofing with corrugated G.I sheets 0.80mm thick
fixed with G.I ‘J’ bolts & nuts 8 mm dia with bitumen & As per
G.I limpet washers filled with white lead & including a emergency work
coat of approved steel primer and two coats of for covid-19 not
approved paint on over lapping of sheets complete
avilable for
(up to a pitch of 600) etc., complete, excluding the
cost of purlins, rafters, trusses including cost and manifold room
24 conveyance of all materials , labour charges , 67.76 Sqm 874 59222 59222 0 in the premises
overheads and contractors profit etc., complete for of gandhi
finished item of work in all floors. hospital for
oxygen pipe line
hence it is
excuted
Page 59 of 204
Plain Cement Concrete M 20 nominal mix using
WEIGH BATCHER / MIXER, 20mm size hard granite
machine crushed graded metal (coarse aggregate - As per
as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) emergency work
from approved quarry, using a minimum quantity of for covid-19 not
300 kgs. of cement per 1 cum of concrete including avilable for
cost and conveyance of all materials like cement,
manifold room
fine aggregate (Sand), coarse aggregate, water etc.,
to site including steel centering, shuttering, machine 15 Cum 5562 83430 83430 0 in the premises
mixing, lift charges, laying concrete,vibrating, curing, of gandhi
overheads & contrctors profit etc., complete for hospital for
finished item of work for coping on top of oxygen pipe line
compound wall (APSS No. 402 & 403). hence it is
excuted
Electrical Work
Supply and Laying of P.V.C casing and caping (ISI
MARK) with double locking arrangments with
groover trunking of size not below 12.5mm height
25mm size with all accessories, duly sealed at points As per site
1 and erected on Wall / Ceiling including cost of all 400 Rm 50.00 20000 20000 0 condition it is
materials and labour charges complete. Makes : excuted
Modi with ISI
Page 60 of 204
Supply and fixing of 6A switchs - 2 Nos and 6A
3/2 pin socket - 2 Nos Modular type with front
cover plate including all labour charges etc.,
complete. As per site
3 Makes : Legrand Arteor / Schneider Zen celo / 176 Pts 783.00 137808 137808 0 condition it is
Honeywell Blenge Plus / Cabtree Amare / Logus excuted
Platina.(Including 3of 4Sqmm 2.0 Rmt)
Page 61 of 204
Supply & run of 5 of 10.0 Sqmm (84/0.3mm) (3
phases, neutral and earth) FRLS / HFFR PVC
insulated flexible copper cable in the existing
conduict pipe for run of mains from Power panel
board to TPN DB"s with pin type lugs and As per site
6 connections etc., complete. [for PDBs] 120 Rm 442.00 53040 53040 0 condition it is
Makes of wires :Finolex / RR kabel / Havells / excuted
APAR EBXL / KEI / Polycab / V-Guard /
MILLION
Page 62 of 204
V.P 39/ MB No.540
Supply and Installation of 125 Amps 4P MCCB
with cable end boxes on suitable angle iron
frame work for the areas mentioned in the
As per site
drawings including all Labours charges,
10 10 No's 14435.00 144350 144350 0 condition it is
massonry work etc. complete for finished item of
excuted
work. Makes:Legrand / Shneider
Page 63 of 204
Supply, Transportation and fixing of 60 W / 65
W LED LED Street light, Body made of high
grade pressure die – cast Aluminium alloy with
corrosion resistant powder coat, having
protective toughened glass cover, Less Glare, IP
66 (Silicon gasket ensures Optical & Electrical
compartments are IP 66) protected, wide
operating voltage range, P.F > 0.90, System
having efficacy >100 lumens/watt, with Ingress
protection IP66, Potted driver, Driver surge
protection >10KV, THD<15%, CCT: 3000-
6500K as desired by the department and as per
IS, CRI>80, Inbuilt Electrical protections like As per site
Over voltage, short circuit, Over load, Open requrement
14 Circuit, Miswiring, etc complete with BIS 10 No's 6559.00 65590 65590 0
hence it is
certification with warranty 50,000 burning hours. excuted
The contractor has to furnish the manufacturer
warranty letter, LM 79 and LM 80 certificates.
and fixing of luminaire on wall with 1.0Mt 40mm
dia GI pipe bracket and anti-tilting arrangements,
1.5 Sq.mm flexible copper cable including
masonary work and all labour charges and giving
connections etc., complete. LUMINAIRE
MAKE : Phillips / OSRAM / GE Venture /Wipro /
Crompton / Bajaj / Havells / Jaquar / IB LED
/Panasonic / Halonix / HPL / Syska / Eveready /
Surya /Keselec.LED MAKE : PHILIPS
LUMILEDS / CREE / NICHIA /OSRAM
/MILLION/ SAMSUNG / LG LEDs
V.P 39/ MB No.540
Page 64 of 204
Supply and fixing of 2 Module Modular type
Electronic step type Fan Regulator for sweep AC
ceiling fans of 1200mm / 1420mm complete with
connections. As per site
Makes : Legrand Myrius / Million mway / Gold requrement
16 Medal Curve / Anchor Roma viola / GM Four-
4 No's 502.00 2008 2008 0
hence it is
Five / Havells Fabio / Panasonic Vision / L&T excuted
Englaze / Hager Insista / Benlo Vesta / C&S
Primo / CPL Vysma / Polycab Levana.
Page 65 of 204
Supply and Transportation of --------------------
single phase ISI submersible motor pumpset As per site
suitable for 4" Bore well. Makes: Varuna / Flowell requrement
20 / Waterman / Techno / Mahavir /unitek/ Fitwell/ 1 No's 13770.00 13770 13770 0
hence it is
Falcon/ Ellen/ Karvel / LPS/ Duke / Varsha / excuted
Ajantha.
Page 66 of 204
500 KVA DG SET at OPD Block As per site
requrement
25 1 Job 86375.00 86375 86375 0
hence it is
excuted
V.P 82/ MB No.538
500 KVA DG SET at South Block As per site
requrement
26 1 Job 86000.00 86000 86000 0
hence it is
excuted
V.P 85/ MB No.538
500 KVA DG SET at North Block As per site
requrement
27 1 Job 80475.00 80475 80475 0
hence it is
excuted
V.P 78/ MB No.538
Page 67 of 204
Name of the work: Providing Gas Supplying pipeline for Supplying and Centralized Medical Oxygen to bed for COVID-19 Management in
Gandhi Hospital Secunderabab
GENERAL ABSTRACT
As per Sanction
Sl.No. Description As per Workdone Excess Less Remarks
Estimate
(Rs.) (Rs.)
1 OXYGEN SYSTEM
1.1
2 x 20 Oxygen Main Manifold with 19 mm O.D. x 12 mm I.D. Copper Pipe
mounted on Top Frame, Middle Frame and Bottom Frame, along with brass
1 Nos 270312 270312
blocks, NRVs/Cylinder Valves and Pigtail pipes of 1 mtr long of 8 mm O.D.
x 3 mm I.D. duly tested at 250 Kg/Cm2 pressure & Semi Automatic Control
Panel for Oxygen
1.2
2 SITC of Electrical Control panel should be automatic change over panel for
changeover from A to B and then from B to A and then from B to C. If any
pump trips then the second should start automatically. The panel should
consist of contactors Amp meter, Volt meter, Single phase protector, MCB,
phase indicator, compressor on –off trip indicator and pressure switch . 1 303450 303450
G) Vacuum System
1 2 nos. of Ingersoll Rand make Model 15V x 10 Model with 7.5 HP Motor
with 1000 litres Receiver, Filters, Electricals, etc.
Secretion Trap and bacteria filter 1 Set 941640 941640
TOTAL 23735822
GST @ 18% 4272448
Grand Total 28008270
Rounding off 51730
28060000
Say Rs. 280.60
Lakhs
Name of the work: Providing Gas Supplying pipeline for Supplying and Centralized
Medical Oxygen to bed for COVID-19 Management in Gandhi Hospital Secunderabab
ABSTRACT ESTIMATE
Roofing with corrugated G.I sheets 0.80mm thick fixed with G.I ‘J’ bolts & nuts 8
mm dia with bitumen & G.I limpet washers filled with white lead & including a coat of
approved steel primer and two coats of approved paint on over lapping of sheets
complete (up to a pitch of 600) etc., complete, excluding the cost of purlins, rafters,
trusses
Shed including cost and conveyance of1 all 1 materials
15.40, labour
4.4 charges , overheads
67.76
and contractors profit etc., complete for finished item of work in all floors.
Say 67.76 874 59222
794658
8th Floor
Copper Pipe for Medical use with 28
OD X 1.0 mm
Coridor area 1 1 30.00 30.00
do 1 1 12.50 12.50
do 1 1 12.00 12.00
do 1 1 14.00 14.00
do 1 1 4.00 4.00
do 1 1 4.00 4.00
Right side wall 1 1 30.00 30.00
Left side wall 1 1 30.00 30.00
Corridor-2 1 1 57.00 57.00
do 1 1 30.00 30.00
Right side wall 1 1 23.00 23.00
Gate to end area 1 1 18.50 18.50
do 1 1 19.00 19.00
Corridor-3 1 1 34.00 34.00
do 1 1 30.00 30.00
do 1 1 31.00 31.00
379.00
Copper Pipe for Medical use with 22
OD X 1.0 mm
Rooms-50 Main line 1 1 3.90 3.90
Rooms-58 Main line 1 1 3.50 3.50
Rooms-51Main line 1 1 3.60 3.60
Rooms-56 Main line 1 1 3.50 3.50
Rooms-55 Main line 1 1 4.50 4.50
Rooms-54 Main line 1 1 5.00 5.00
Rooms-53 Main line 1 1 5.00 5.00
Rooms-52 Main line 1 1 5.00 5.00
Rooms-58 Main line 1 1 5.40 5.40
Rooms-59 Main line 1 1 5.50 5.50
Rooms-60 Main line 1 1 5.50 5.50
Rooms-61 Main line 1 1 5.50 5.50
Rooms-62 Main line 1 1 5.50 5.50
Rooms-49 Main line 1 1 4.50 4.50
Rooms-63 Main line 1 1 5.50 5.50
Rooms-48 Main line 1 1 4.50 4.50
Rooms-47 Main line 1 1 5.50 5.50
Rooms-46 Main line 1 1 5.50 5.50
Rooms-45 Main line 1 1 4.50 4.50
Rooms-30 Main line 1 1 5.50 5.50
Rooms-29 Main line 1 1 5.50 5.50
Rooms-28 Main line 1 1 5.50 5.50
Rooms-27 Main line 1 1 6.50 6.50
Rooms-32 Main line 1 1 3.50 3.50
Rooms-33 Main line 1 1 6.50 6.50
Rooms-34 Main line 1 1 6.50 6.50
Rooms-35 Main line 1 1 7.00 7.00
Rooms-36 Main line 1 1 7.00 7.00
Rooms-37 Main line 1 1 7.00 7.00
Rooms-38Main line 1 1 7.00 7.00
Rooms-39 Main line 1 1 7.00 7.00
Rooms-40 Main line 1 1 7.00 7.00
Rooms-41 Main line 1 1 7.00 7.00
Rooms-42 Main line 1 1 7.00 7.00
Rooms-43 Main line 1 1 7.00 7.00
Rooms-42 Main line 1 1 4.50 4.50
Rooms-28 Main line 1 1 3.50 3.50
Rooms-23 Main line 1 1 3.50 3.50
Rooms-22 Main line 1 1 5.50 5.50
Rooms-21 Main line 1 1 5.50 5.50
Rooms-15 Main line 1 1 7.00 7.00
Rooms-4 Main line 1 1 7.00 7.00
Rooms-3 Main line 1 1 7.00 7.00
Rooms-2 Main line 1 1 26.00 26.00
Session-2 Main line 1 1 3.50 3.50
Session-1Main line 1 1 3.50 3.50
Session-1Main line 1 1 3.50 3.50
Session-1Main line 1 1 3.50 3.50
Session-1Main line Right side 1 1 3.50 3.50
Session-2Main line Right side 1 1 3.50 3.50
Session-3Main line Right side 1 1 3.50 3.50
Room1Main line 1 1 4.00 4.00
Room2Main line 1 1 2.00 2.00
Room3Main line 1 1 5.00 5.00
Room 4Main line 1 1 6.00 6.00
304.90
Copper Pipe for Medical use with 12
OD X 1.0 mm
Rooms-50 Drops 1 2 1.25 2.50
Rooms-58 Drops 1 2 1.25 2.50
Rooms-51Drops 1 2 1.25 2.50
Rooms-56Drops 1 2 1.25 2.50
Rooms-55 Drops 1 2 1.50 3.00
Rooms-54 Drops 1 2 1.50 3.00
Rooms-53 Drops 1 2 1.50 3.00
Rooms-52 Drops 1 2 1.50 3.00
Rooms-58 Drops 1 3 1.50 4.50
Rooms-59 Drops 1 3 1.50 4.50
Rooms-60 Drops 1 4 1.50 6.00
Rooms-61 Drops 1 4 1.50 6.00
Rooms-62 Drops 1 3 1.50 4.50
Rooms-49 Drops 1 2 1.50 3.00
Rooms-63 Drops 1 3 1.50 4.50
Rooms-48 Drops 1 2 1.50 3.00
Rooms-47 Drops 1 2 2.00 4.00
Rooms-46 Drops 1 2 2.00 4.00
Rooms-45 Drops 1 2 2.00 4.00
Rooms-30 Drops 1 3 2.00 6.00
Rooms-29 Drops 1 3 2.00 6.00
Rooms-28 Drops 1 3 2.00 6.00
Rooms-27 Drops 1 3 2.00 6.00
Rooms-32 Drops 1 2 1.50 3.00
Rooms-33 Drops 1 3 2.00 6.00
Rooms-34 Drops 1 3 2.00 6.00
Rooms-35 Drops 1 3 2.00 6.00
Rooms-36 Drops 1 3 2.00 6.00
Rooms-37 Drops 1 3 2.00 6.00
Rooms-38Drops 1 3 2.00 6.00
Rooms-39 Drops 1 3 2.00 6.00
Rooms-40Drops 1 3 2.00 6.00
Rooms-41 Drops 1 3 2.00 6.00
Rooms-42 Drops 1 3 2.00 6.00
Rooms-43 Drops 1 3 2.00 6.00
Rooms-42 Drops 1 2 2.00 4.00
Rooms-28 Drops 1 2 1.50 3.00
Rooms-23 Drops 1 2 1.50 3.00
Rooms-22 Drops 1 2 2.00 4.00
Rooms-21 Drops 1 2 2.00 4.00
Rooms-15 Drops 1 3 2.00 6.00
Rooms-4 Drops 1 2 1.50 3.00
Rooms-3 Drops 1 3 1.50 4.50
Rooms-2 Drops 1 10 1.50 15.00
Session-2 Drops 1 2 2.00 4.00
Session-1Drops 1 2 2.00 4.00
Session-1Drops 1 2 2.00 4.00
Session-1Drops 1 2 2.00 4.00
Session-1Drops Right side 1 2 2.00 4.00
Session-2Drops Right side 1 2 2.00 4.00
Session-3DropsRight side 1 2 2.00 4.00
Room1Drops 1 2 1.50 3.00
Room2Drops 1 3 1.50 4.50
Room3Drops 1 3 1.50 4.50
Room 4Drops 1 4 1.50 6.00
255.50
OUTLETS FOR AIR & VACUUM
8th floor Value 28mm 1 12 12.00
5th Floor
Copper Pipe for Medical use with 22
OD X 1.0 mm
Dep.Surgical room 1 1 35.00 35.00
Copper Pipe for Medical use with 15
OD X 1.0 mm
Male ward 1 1 111.00 111.00
Femal ward 1 1 120.00 120.00
231.00
Copper Pipe for Medical use with 12
OD X 1.0 mm
Femal ward 1 1 81.00 81.00
Male ward 1 1 84.00 84.00
165.00
OUTLETS FOR AIR & VACUUM
5th floor Value 22mm 1 1 1.00
5th floor Value 15mm 1 2 2.00
Out lets 1 229 229.00
Road work
Earth work excavation for foundations (Manual Means) of buildings, septic
tank, sump, compound wall in ordinary soils and depositing on bank with an
initial lead of 10m and 1m additional lift charges over the initial depth up to 3m
including all operational,incidental, labour charges such as shoring, sheeting,
Road work
planking, strutting etc., and overheads & 1contractors
1 16.00 5 0.90
profit complete 72.00
for finished item
of work excluding dewatering charges etc., as per SS 20 B(APSS 308) Say 72.00 239 17208
Filling with carted coarse sand in trenches,sides of foundations and basement
with initial lead in layers not exceeding 15cm thick,watering and ramming including
cost and conveyance of water to work site and all peraitonal,incidental ,labour
charges,hire charges of T&P etc., and overheads & contractors profit complete for
Road
fnishedwork
item of work(APSS NO.309&310)1 1 16.00 5 0.10 8.00
Say 8.00 848 6784
Plain Cement Concrete (1:5:10) (cement: fine aggregate: Coarse aggregate) for
foundations and under flooring bed using coarse aggregate 40mm size hard ,
machine crushed granite from approved quarry including cost and conveyance of
all
Roadmaterials
work like cement, sand, coarse aggregate,
1 1 water etc.
16.00 5 to site,
0.15sales &12.00
other 4121 49452
taxes on all materials and including all charges for machine mixing, laying concrete
in foundations and under flooring bed, ramming in 15 cm layers finishing top surface
Masonry work in
to the required CM(1:6)
level curing prop (Cement
etc.,and : Screened
overheads sand) in profit
& contractors superstructure
completewith
for
fly ash cement / lime solid blocks
finished item of work. (APSS No. 402) of size 290mm x 225mm x 140mm from
approved source having minimum crushing strength of 50 Kg/Sqcm. including cost
and
Roadconveyance
work of all materials like cement,
1 2 sand, 16.00bricks,
0.23water
0.90 etc., to 6.62
site, 4121 27298
including sales & other taxes on all materials and such as labour charges, like
Plain Cement Concrete M 20 nominal mix using WEIGH BATCHER / MIXER,
mixing cement mortar, scaffolding charges, constructing masonry, lift charges,
20mm size hard granite machine crushed graded metal (coarse aggregate - as per
curing, overheads and contrctor profit etc., complete for finished item of work.
IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry, using a minimum
(APSS No. 501 & 504).
quantity
Road workof 300 kgs. of cement per 1 cum1of concrete
1 including
16.00 5 cost0.20
and conveyance
16.00 5562 4121
of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc.,
to site including steel centering, shuttering, machine mixing, lift charges, laying
concrete,vibrating, curing, overheads & contrctors profit etc., complete for finished
item of work for coping on top of compound wall (APSS No. 402 & 403).
Electrical Datas 2019-20
SSR
S.No Description Qty Unit Rate Amount
No
CONDUIT PIPE
1 Supply and Laying of P.V.C casing and caping (ISI MARK) with double locking arrangments with
groover trunking of size not below 12.5mm height 25mm size with all accessories, duly sealed at
points and erected on Wall / Ceiling including cost of all materials and labour charges complete.
Makes : Modi with ISI
a) Labour charges :
1 Skilled Electrician. 1.00 day 1 day 565.00 565.00
2 Lineman / Semi Skilled Electrician. 1.00 day 1 day 470.00 470.00
3 Helper (Electrical). 2.00 day 1 day 470.00 940.00
Labour Rate Per 100 Rm 1975.00
Labour Rate for 1 Mtr 19.75
b) Material
1.2.4 b)
SoR-18- Supply of 25mm width and 12.5mm
100.00 Rm 1 Rm 30.00 3000.00
19 height Casing and Caping.
Material Rate for 100 Mtrs 3000.00
Material Rate for 1 Mtr 30.00
Total Cost of Material + Labour 49.70
Charges
Add Contractors Profit 0.000% 0.00
49.70
Rate per Meter 50.00
2 Supply and Fixing of ISI 25mm outer dia medium grade with IS:9537 part 3 regid PVC pipe
surface on wall/ceiling with all required saddles and all accessories and labour charges etc.,
complete for run of mains. Makes : Sudhakar / Finolex / Modi / VIP / Precision / Universal / Million
Plast / Gold / Polycab / DEC.
a) Labour charges :
1 Skilled Electrician. 2.00 day 1 day 565.00 1130.00
2 Lineman / Semi Skilled Electrician. 2.00 day 1 day 470.00 940.00
3 Helper (Electrical). 2.00 day 1 day 470.00 940.00
Labour Rate Per 100 Rm 3010.00
Labour Rate for 1 Mtr 30.10
b) Material
9.1.2 Rawl Plugs. 200.00 Nos 100 Nos 33.00 66.00
1.4.4 d) Supply of No.8 Screws of 35/38mm. 200.00 Nos 100 Nos 100.00 200.00
(SoR-2016-17-TBSE-1.4.23)
9.4.11 Cement. 5.00 kg 1 Kg 8.00 40.00
1.1.11 Supply of 25mm Saddles with Base. 200.00 Nos 100 Nos 210.00 420.00
b)
1.2.5 b) Supply of 25mm PVC Junction Boxes 12.00 Nos 1 No 20.00 240.00
Normal.
1.2.7 b) Supply of 25mm dia 1.5mm thick PVC 12.00 Nos 1 No 8.00 96.00
Bends.
1.2.2 b) Supply of ISI 25mm outer dia medium 100.00 Mtr 1 Mtr 24.00 2400.00
(1.80mm thickness) grade FRLS with
IS:9537 part 3 regid PVC pipe.
Material Rate for 100 Mtrs 3462.00
Material Rate for 1 Mtr 34.62
Total Cost of Material + Labour 64.70
Charges
Add Contractors Profit 0.000% 0.00
64.70
Rate per Meter 65.00
Page 81 of 204
1.9.1 a) Supply of 6A / 10A 1 Way 1 Module 2 Nos 1 No 88.00 176.00
Modular Switch.
1.9.1 d) Supply of 6A / 10A 3/2 Pin 2 Module 2 Nos 1 No 135.00 270.00
Modular Socket with shutter.
Cost of Material for 1 No 576.00
Total Cost of Material + Labour 783.00
Charges
Add Contractors Profit 0.000% 0.00
783.00
Rate per Each 783.00
a) Labour charges :
1 Skilled Electrician. 0.15 day 1 day 565.00 84.75
2 Helper (Electrical). 0.15 day 1 day 470.00 70.50
Labour for 1 No 155.25
b) Material
1.3.2 d) Supply of 6 Modular Cover Frame. 1 Nos 1 No 130.00 130.00
Run of Mains
5 Supply and 3 runs of 4.0 sq mm (56/0.3 mm) (phase neutral and earth) FRLS / HFFR PVC
insulated flexible copper cable in existing conduit pipe including labour charges etc., complete
for 16A sockets.
Makes of wires :Finolex / RR kabel / Havells / APAR EBXL / KEI / Polycab / V-Guard / MILLION
a) Labour charges :
1 Skilled Electrician. 1.00 day 1 day 565.00 565.00
2 Lineman Electric / Telephone 3.00 day 1 day 470.00 1410.00
3 Helper (Electrical). 1.00 day 1 day 470.00 470.00
Labour for 100 Mtr 2445.00
Labour for 1 Mtr 24.45
b) Material
1.5.1 c) Supply of 56/0.3mm (4.0 Sqmm) FRLS / 300.00 Mtrs 100 Mtrs 3725.00 11175.00
HFFR Copper cable.
Cost of Material for 100 Metres 11175.00
Cost of Material Rate per Mtr= C/100 111.75
Total Cost of Material + Labour 136.20
Charges
Add Contractors Profit 0.000% 0.00
136.20
Rate per Meter 136.00
6 Supply & run of 5 of 10.0 Sqmm (140/0.3 mm) (3 phases, neutral and earth) FRLS / HFFR PVC
insulated flexible copper cable in the existing conduict pipe for run of mains from Power panel
board to TPN DB"s with pin type lugs and connections etc., complete. [for PDBs]
Makes of wires : Finolex / RR kabel / Havells / APAR EBXL / KEI / Polycab / V-Guard / MILLION
a) Labour charges :
1 Skilled Electrician. 2.34 day 1 day 565.00 1322.10
2 Lineman Electric / Telephone 6.50 day 1 day 470.00 3055.00
3 Helper (Electrical). 2.34 day 1 day 470.00 1099.80
Labour for 100 Mtr 5476.90
Labour for 1 Mtr 54.77
b) Material
1.5.2 Supply of 140/0.3mm (10.0 Sqmm) PVC 500.00 Mtrs 100 Mtrs 7750.00 38750.00
e) FRLS / HFFR insulated flexible Copper
cable.
Page 82 of 204
Cost of Material for 100 Metres 38750.00
Cost of Material Rate per Mtr= C/100 387.50
Total Cost of Material + Labour 442.20
Charges
Add Contractors Profit 0.000% 0.00
442.20
Rate per Meter 442.00
Distribution Boards
12 Way TPNDB
7 Supply and fixing of 12 Way TPN DB Horizontal with IP 43 Protection as per IS:13032 Makes :
Legrand / Schneider / Siemens / L&T / Hager /Cabtree Xproand Supply and Fixing of 1 No., of
63A 10 KA FP MCB as incomer and 36 Nos 6-32 A 10kA SP MCBs Makes : Legrand-DX3 /
Schneider-Acti9 / Siemens / L&T Exora / Cabtree as out goings including internal connections
and labour charges for FLUSH Mounting etc., complete for DBs.
MATERIAL
Legran Supply of 12 Way TPN DB Horizontal 1 Nos 1 No 9170.00 9170.00
d Pg.12 with IP 43 Protection as per IS:13032
and suitable for 36 Nos S.P. out goings
and 4 pole Incommer etc complete.
8 Way VTPN DB
8 Supply and fixing of 8 Way VTPN DB with IP 43 Protection Makes : Legrand / Schneider /
Siemens / L&T / Hager /Cabtree Xpro and Supply and Fixing of 1 No., of 125A TPN MCCB,
Adjustable, Confirms to IS/IEC 60947-2 having Breaking Capacity 25 KA with thermal magnetic
release Panel Mounted as incomer with 8 Nos of 63A, 10KA, TP MCBs C/D Curve ISI Mark as
Out goings including internal connections and labour charges etc., complete. Makes : L&T /
MATERIAL
2.16.3 Supply of 8/ Way
Schneider Siemens / Legrand
VTPN DB / Hager /ABB / C&S.
1 Nos 1 No 11800.00 11800.00
b)
2.13.1 Supply of 63A 10KA TPN MCB, C/D 8 Nos 1 No 1480.00 11840.00
f) Curve ISI Mark.
2.8.1 C) 125A 3 Pole MCCB, 25KA 1 Nos 1 No 7404.00 7404.00
Sundries 5.00
COST OF MATERIAL FOR Surface 31049.00
MOUNTING
LABOUR
1 Skilled Electrician. 1.25 day 1 day 565.00 706.25
2 Lineman Electric / Telephone 1.50 day 1 day 470.00 705.00
3 Helper (Electrical). 1.50 day 1 day 470.00 705.00
COST OF LABOUR FOR Surface 2116.25
MOUNTING
TOTAL COST OF MATERIAL + 33165.00
LABOUR FOR Surface MOUNTING
Add Contractors Profit 0.000% 0.00
33165.00
Rate per Each 33165.00
10 Supply and Installation of 125 Amps 4 Pole MCCB, Adjustable, Confirms to IS/IEC 60947-2
having Breaking Capacity 25 KA with thermal magnetic release etc complete with connections.
Make: L&T / Schneider / Siemens / Legrand / Hager /ABB / C&S.
MATERIAL
Fabrication: L H D
Size of panel : in Mtr 0.50 0.50 0.25
Page 83 of 204
Front and back faces 2.00 0.50 0.50 0.50
Top and bottom faces 2.00 0.50 0.25 0.25
Side faces 2.00 0.50 0.25 0.25
Sub total 1.00
Add extra 10 % for wastage 0.10
Total 1.10
7.12.1 Fabrication and erection of 14 / 16 SWG 1.10 Sqmtr 1 Sqmtr 4140.00 4554.00
b) CRCA sheet steel enclosure for power
control cubicle panel / boxes etc.,
including cutting, bending drilling,
welding and reveting etc., complete
with cleaning with 7 tank process and
2.8.1 d) painting
125 Ampswith
FP MCCB,
powder 25 KA including
coating 1 Nos 1 No 8925.00 8925.00
cost and conveyance of all materials
and labourfor
Provision charges.
angle iron frame work 203.00
etc.,
13682.00
LABOUR
1 Skilled Electrician. 0.50 day 1 day 565.00 282.50
2 Lineman Electric / Telephone 1.00 day 1 day 470.00 470.00
752.50
TOTAL COST OF MATERIAL +
14435.00
LABOUR
Add Contractors Profit 0.000% 0.00
14435.00
Rate per Each 14435.00
11 U.G Cables
a) 4.1.1 j) Supply of 70 Sqmm 3.5 Core XLPE RMS 1 1 One 420.00 420.00
insulated, 1100V grade armoured Rmt
alluminium cable with ISI mark as per
specification confirming to IS:7098 (Part
- I)
Makes : Torrent / Unicab / Universal /
Polycab / Havells / Gloster / KEI /
Finolex / Paragon.
12 Laying of PVC armoured under ground cable up to 95 Sqmm fixing on chromium plated metallic
base saddles on wall as per IS 1255 and as directed by the department including cost and
conveyance of all materials and labour charges etc., complete.
b) Labour charges
1 Skilled Electrician. 1.50 day 1 day 565.00 847.50
2 Helper (Electrical). 2.00 day 1 day 470.00 940.00
Labour Charges for 100 Mtrs 1787.50
Labour Charges for 1 Mtr 17.88
a) Material
9.1.2 Rawl Plugs. 4.00 Nos 100 Nos 33.00 1.32
1.4.4 d) Supply of No.8 Screws of 35/38mm. 4.00 Nos 100 Nos 100.00 4.00
9.4.23 Supply of Saddle / Clamps for Cable. 2.00 Nos 100 Nos 550.00 11.00
f)
Cost of Material for Laying on wall for 1.00 Mtr 16.32
Total Cost of Material + Labour 35.00
Charges
Add Contractors Profit 0.000% 0.00
35.00
Rate per Meter 35.00
13 a) Termination of UG cables of 3.5 core 70 Sq.mm including with required Heavy duty cable
glands, Lugs complete with all required accessories as directed by the department including
cost and conveyance of all materials and labour charges etc., complete.
b) Labour charges
1 Skilled Electrician. 0.020 day 1 day 565.00 11.30
Page 84 of 204
2 Lineman Electric / Telephone 0.020 day 1 day 470.00 9.40
3 Helper (Electrical). 0.020 day 1 day 470.00 9.40
Labour Charges for each 30.10
a) Material
4.3.1 d) glands for 3.5 core XLPE armoured 1.00 Nos 1 Nos 200.00 200.00
cable from 70 Sqmm
4.4.2 c) aluminium lugs for cable of 35 Sq.mm 1.00 Nos 1 Nos 17.00 17.00
4.4.2 e) aluminium lugs confirming to I.S 3.00 Nos 1 Nos 24.00 72.00
specifications for cable of 70 Sq.mm
289.00
Total Cost of Material + Labour 319.00
Charges
Add Contractors Profit 0.000% 0.00
319.00
Rate per Each 319.00
14 Supply of 10 sqmm WPTC (Weather Proof Twin Core) ISI Alluminium Wire. Makes :
Polycab / GM / Million / V-Guard / Gold Medal / Kundancab / HPL / RPG / Nandicab / Nakoda
/ Payal / Finecab / Gemini / Vimal / Suncab / Stanjo / Rajnigandha / Orbit / Airson.
a) Labour charges :
1 Skilled Electrician. 1 day 1 day 565 283
2 Lineman Electric / Telephone 1 day 1 day 470 235
3 Helper (Electrical). 1 day 1 day 470 470
Labour for 100 Mtr 988
Labour for 1 Mtr 10
b) Material
1.5.2 c) Supply of 10 sqmm WPTC (Weather 100 Mtrs 100 Mtrs 3400 3400
Proof Twin Core) ISI Alluminium Wire
1 Supply, Transportation and fixing of 60 W / 65 W LED LED Street light, Body made of high
grade pressure die – cast Aluminium alloy with corrosion resistant powder coat, having protective
toughened glass cover, Less Glare, IP 66 (Silicon gasket ensures Optical & Electrical
compartments are IP 66) protected, wide operating voltage range, P.F > 0.90, System having
efficacy >100 lumens/watt, with Ingress protection IP66, Potted driver, Driver surge protection
>10KV, THD<15%, CCT: 3000- 6500K as desired by the department and as per IS, CRI>80,
a) Labour
Inbuilt charges
Electrical protections like Over voltage, short circuit, Over load, Open Circuit, Miswiring, etc
1 Skilled Electrician.certification with warranty 50,000
complete with BIS burning hours.
0 day The contractor565
1 day has to furnish
141
the manufacturer warranty
2 Lineman Electric / Telephone letter, LM 79 and LM 80 certificates.
0 day and fixing
1 day of luminaire
470 on wall118
with 1.0Mt 40mm dia GI pipe bracket and anti-tilting arrangements, 1.5 Sq.mm flexible copper
3 Helper (Electrical).
cable including masonary work and all labour charges0 dayand giving1connections
day 470
etc., complete. 118
Labour for 1 MAKE
LUMINAIRE No : Phillips / OSRAM / GE Venture /Wipro / Crompton / Bajaj / Havells / Jaquar 376/
b) Material
IB LED /Panasonic / Halonix / HPL / Syska / Eveready / Surya /Keselec.LED MAKE : PHILIPS
LUMILEDS
1.5.2 Supply / CREE
of 2.5 Sqmm/ NICHIA
FRLS / /OSRAM
HFFR / SAMSUNG / LG LEDs.
2 Mtrs 100 Mtrs 2140 43
b) Copper cable.
9.4.15 40mm Nominal Bore Medium grade 1 Mtrs 1 Mtr 350 350
b) G.I.Pipe.
Pipe bending charges LS 40
M.S flat and welding charges LS 50
Page 85 of 204
3.11.1 60 / 65 W 1 Nos 1 Nos 5700 5700
d
Cost of Material for 1 No 6183
Total Cost of Material + Labour 6559
Charges
Add Contractors Profit 0 0
6559
Rate per Each 6559
Page 86 of 204
SPECIFICATION REPORT
Name of the work: Providing Gas Supplying pipeline for Supplying and Centralized
Medical Oxygen to bed for COVID-19 Management in Gandhi Hospital Secunderabab
The Estimate for the work of "Providing Gas Supplying pipeline for supplying and
Centralized Medical Oxygen to bed for Covid-19 Management in Gandhi Hospital Secundrabad"
was technically sanctioned for Rs. 280.60 lakhs and the work was awarded to M/s Shree Bharath
Pharma & Medical Oxygen Distributors, Contractor Hyderabad vide agreement No.
03/TSMSIDC/2020-21 dated: 05.05.2020 for Rs. 2,37,35,822/- the estimate contract value of Rs.
2,37,35,822/- (SSR 2020-21) with stipulated (i.e., by 05.05.2020) for completion of work.
The reasons for the deviations are shown in the remarks column of the comparative
statement against respective items. The following are the main item which is exceeding the
estimate quantities as per site conditions which can be accommodated against savings.
Supplemental Items:-
Page 88 of 204
Plain Cement Concrete (1:5:10) (cement:
fine aggregate: Coarse aggregate) for
foundations and under flooring bed using
coarse aggregate 40mm size hard , As per
machine crushed granite from approved emergency
quarry including cost and conveyance of all work for
materials like cement, sand, coarse covid-19 not
aggregate, water etc. to site, sales & other avilable for
taxes on all materials and including all
charges for machine mixing, laying concrete 7.43
manifold room
10 Cum 4121 30619
in foundations and under flooring bed, in the premises
ramming in 15 cm layers finishing top surface of gandhi
to the required level curing etc.,and hospital for
overheads & contractors profit complete for oxygen pipe
finished item of work. (APSS No. 402) line hence it is
excuted
Page 89 of 204
Supply and placing of the Design Mix
Concrete M 25 grade corresponding to IS
456 with minimum cement content of 380
kgs per 1 cum of concrete using Concrete
Batching Plant with 20mm size graded
machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS As per
2386 Part 1 to Part 8) from approved quarry emergency
including cost and conveyance of all work for
materials like cement, fine aggregate (sand) covid-19 not
coarse aggregate, water etc., to site and avilable for
sales & other taxes on all materials , manifold room
13 centering using Steel scaffolding pipes , jack in the premises
props , wallers , Foot plates , brackets , steel
centering plates etc., including all
of gandhi
operational, incidental and labour charges hospital for
such as weigh batching, machine mixing, oxygen pipe
laying concrete, curing etc., and overheads & line hence it is
contractors profit complete but excluding cost excuted
of steel and its fabrication charges for
finished item of work (APSS No. 402).
Page 90 of 204
Supplying and fixing of 2 shutter fully
glazed windows as per drawing using Sal As per
wood frame and one vertical mullion of size emergency
100mm x 65mm and shutters with Sal wood work for
styles & rails of size 75mmx35mm and 4mm covid-19 not
thick pin headed glass fixed with teak wood avilable for
beading of 12mm X 12mm including cost of 4 manifold room
17 Nos MS Z hold fasts of size 300 x 40 x 5 mm 4.32 Sqm 5482 23682
in the premises
including supply and fixing of ISI marked of gandhi
aluminium fixtures, butt hinges of size 75mm hospital for
long (2 Nos per shutter), 75mm handles (1No
oxygen pipe
per shutter), 75mm x 10mm dia tower bolt
(1No per shutter), and aluminium window line hence it is
stopper with hook and eye 100mm long (1No excuted
per shutter) with 12mm MS square bars
horizontally at 100mm centre to centre fixed
Supply
in frame and fixinglabour
including doorscharges
as per drawings
for fixing
with mediumwith
the fixtures teakrequired
wood frame No. ofof screws,
section
100mm x 65 mm
fixing window in and ISI marked
position flush door
fixing shutters to
18 shutters of 30 mm
frame including costthick double shutters
& conveyance of all
with bond wood
materials to site,solid block
labourboard type Core
charges etc.,
having
complete cross bands item
for finished and offace veneers,
work (APSS hot No
pressed bonded with water
1001 & 1002).(1200mm x 1300mm)proof phenol
formaldehyde synthetic resin factory made
supply and to
conforming fixing
IS 62202-1991
Nos. MS Z hold fasts
(Part-I) both As per
of
sidessize 300 mm
commercial x 40
ply with mm lipping
internal x 5mm on emergency
including cost of ISI
all sides including costmarked Aluminium
and conveyance to work for
fixtures of 6 Nos.
site of teak wood butt hinges
frame, flush(IS:205)
shutter
including
covid-19 not
150mm long, 1 No. aldrop (IS:2681)
avilable for
300mm long, 2 Nos. tower bolts (IS:204)
manifold room
of 200 mm x 10 mm dia at top, 2 Nos. 5.04 Sqm 3548 17882
in the premises
150 mm long handles (IS:208), 2 Nos.
of gandhi
door stoppers and 2 Nos. rubber bushes
hospital for
including fixing the fixtures to door with
oxygen pipe
required number of screws, bolt and nuts
line hence it is
including labour charges for fixing the
excuted
frame in position, fixing the shutter to the
frame etc., including overheads &
contractors
Painting to profit complete
new wood workforand
finished
flush
item of work as per APSS
shutters with lappam finish, over1001 & 1002a
(The
primary vertical
coat and frame of door
painting two shall
coats beof As per
embedded
synthetic enamel paint Grade-II ofVOC
in flooring for a depth not emergency
less thanOrganic
(Volatile 10 mm) Compound)
(1200mm x 2100mm).
content less work for
than 50 grams/litre of approved shade covid-19 not
including cost and conveyance of all avilable for
materials to site cost of primer coat and all manifold room
19 labour charges etc. complete including 19.17 Sqm 180 3451
in the premises
applying sand paper on lappam coats for
neat finish including sales & other taxes on of gandhi
cost of all materials etc., and overheads & hospital for
contractors profit complete in all floors oxygen pipe
(APSS No.1200, 1207 & 1211). line hence it is
excuted
Page 91 of 204
Roofing with corrugated G.I sheets
0.80mm thick fixed with G.I ‘J’ bolts & nuts
8 mm dia with bitumen & G.I limpet washers As per
filled with white lead & including a coat of emergency
approved steel primer and two coats of work for
approved paint on over lapping of sheets covid-19 not
complete (up to a pitch of 600) etc., avilable for
complete, excluding the cost of purlins, manifold room
21 rafters, trusses including cost and 61.05 Sqm 874 53358
in the premises
conveyance of all materials , labour charges ,
overheads and contractors profit etc., of gandhi
complete for finished item of work in all hospital for
floors. oxygen pipe
line hence it is
excuted
Electrical Work
Supply and Laying of P.V.C casing and caping
(ISI MARK) with double locking arrangments As per site
1 with groover trunking of size not below 400 Rm 50.00 20000 condition it is
12.5mm height 25mm size with all
accessories, duly sealed at points and excuted
erected on Wall / Ceiling including cost of all
materials and labour charges complete.
Makes
Supply: and
ModiFixing
with ISIof ISI 25mm outer dia
medium grade with IS:9537 part 3 regid As per site
2 PVC pipe surface on wall/ceiling with all 1125 Rm 65.00 73125 condition it is
required saddles and all accessories and excuted
labour charges etc., complete for run of
mains.
Supply
Makes :and fixing of/ Finolex
Sudhakar 6A switchs - 2/ VIP
/ Modi Nos /
and 6A 3/2
Precision pin socket
/ Universal - 2 Nos
/ Million Modular
Plast As per site
3 type with front cover plate including all 176 Pts 783.00 137808 condition it is
labour charges etc., complete. excuted
Makes : Legrand Arteor / Schneider Zen
celo / Honeywell Blenge Plus / Cabtree
Amare / Logus Platina.(Including 3of
4Sqmm &
Supply 2.0fixing
Rmt) of 16A/6A, 2 in one
socket - 2 Nos with 16A switch control - As per site
4 2 Nos modular type with front cover 688 No's 901.00 619888 condition it is
plate including all labour charges etc., excuted
complete.
Makes : Legrand Arteor / Schneider Zen
celo / Honeywell Blenge Plus / Cabtree
Amare / Logus Platina.(Including 3of
4Sqmm 2.0 Rmt) Page 92 of 204
Supply and 3 runs of 4.0 sq mm (56/0.3
mm) (phase neutral and earth) FRLS / As per site
5 HFFR PVC insulated flexible copper
3713 Rm 136.00 505014 condition it is
cable in existing conduit pipe including excuted
labour charges etc., complete for 16A
sockets.
Supply
Makes of& wires
run :ofFinolex
5 of /10.0 Sqmm/
RR kabel
(84/0.3mm) (3 phases, neutral
Havells / APAR EBXL / KEI / Polycab and earth)/ As per site
6 FRLS / HFFR
V-Guard / MILLION PVC insulated flexible 120 Rm 442.00 53040 condition it is
copper cable in the existing conduict pipe excuted
for run of mains from Power panel board
to TPN DB"s with pin type lugs and
connections
Supply and etc.,
fixingcomplete.
of 12 Way [for TPN
PDBs]DB
Makes
Horizontal with IP 43 Protection kabel
of wires :Finolex / RR as per/ As per site
7 Havells
IS:13032 with 1 No., of 63A 10KA FP/ 4
/ APAR EBXL / KEI / Polycab No's 20516.00 82064 condition it is
V-Guard
MCB as /incomer
MILLIONand 36 Nos 6-32 A excuted
10kA SP MCBs as out goings including
internal connections and labour charges
Supply
for FLUSHand Mounting
fixing of etc.,
8 Way VTPN for
complete DB
with As per site
DBs.IP 43 Protection with 1 No., of 125A
8 TPN to 2 No's 33165.00 66330 condition it is
MakesMCCB,
: Legrand Adjustable,
/ SchneiderConfirms
/ L&T.
IS/IEC 60947-2 having Breaking excuted
Capacity 25 KA with thermal magnetic
release Panel Mounted as incomer with
Supply
8 Nos and fixing 10KA,
of 63A, of cableTP adopteres
MCBs C/D box
with cover As per site
Curve ISI Mark for DBsOut including,
as goings
9 massaNosry workconnections
etc., complete., 6 No's 600 3600 condition it is
including internal and labour
Makes excuted
charges: Legrand / Schneider.
etc., complete.
Makes : Legrand / Schneider / L&T.
Supply and Installation of 125 Amps 4P
MCCB with cable end boxes on suitable As per site
10 angle iron frame work for the areas 8 No's 14435.00 115480 condition it is
mentioned in the drawings including all excuted
Labours charges, massonry work etc.
complete for finished item of work.
Makes:Legrand
Supply of the/ Shneider
Following PVC XLPE As per site
11 armoured cable 1100 V Grade with ISI condition it is
mark stranded / solid, aluminimum excuted
conductor complete
3.5 Core: Torrent
Makes 70.00 Sq.mm.
/ Unicab / Polycab / 120 Rm 420.00 50400
Havells / Gloster / KEI / Finolex /
Paragon.
Laying of PVC armoured under ground
As per site
cable up to 95 Sqmm fixing on chromium 120
12 Rm 35.00 4200 condition it is
plated metallic base saddles on wall as
excuted
per IS 1255 and as directed by the
department including cost and
conveyance of all
LT CABLE TERMINATIONS: materials and labour
charges etc., complete.
Supply and Fixing of single compression As per site
13 brass cable glands for 3.5 core following condition it is
armoured cable with brass washers, excuted
lugs etc., complete.
70 Sq.mm 8 No's 319.00 2552
Page 94 of 204
CC 2nd & Part Bill
Name of the work: Providing Gas Supplying pipeline for Supplying and Centralized Medical Oxygen to bed for COVID-19
Management in Gandhi Hospital Secunderabab
2 Oxygen flowmeter complete with Humidifier bottle 772 Nos 1025 791300 772 791300 0 0
Page 95 of 204
2 Isolation Valve for 22 mm Copper Pipe 43 Nos 1714 73702 43 73702 0 0
3 Ward vacuum (out let) unit complete regulator 249 Nos 1714 426786 18 30852 231 395934
1 Vacuum outlets(Indeginous) -with Probes By 249 Nos 1535 382215 249 382215 0 0
considering 300 Beds for Oxygen and Vacuum
2 Air-4 bar outlets(Indeginous) with Probes by 249 Nos 1535 382215 249 382215 0 0
considering 100 beds with Oxygen, Air and Vacuum
F Compressed Air System
Compressed Air System Consisting of 2 nos
(Reciprocating & oil free), each having 15 HP Motor
with 57.18 cfm capacity at 8.5Kg/cm2 pressure with
common receiver of Capacity 1000 ltrs, common Air
drier, Pressure Reducing Unit etc.
1 3-Stage Breathing Air Filter for 125 CFM as per ISO 1 Nos 1114554 1114554 1 1114554 0 0
8573-1
Page 96 of 204
G Vacuum System
2 nos. of Ingersoll Rand make Model 15V x 10 Model
with 7.5 HP Motor with 1000 litres Receiver, Filters,
1 Electricals, etc. 1 Nos 941640 941640 1 941640 0 0
Secretion Trap and bacteria filter
Electrical Work
Supply & fixing of 16A/6A, 2 in one socket - 2
Nos with 16A switch control - 2 Nos modular
1 type with and GI switch box with front cover 498 Rm 721.00 359058 498 359058 0 0
plate including all labour charges etc., complete.
Page 97 of 204
Supply and Fixing of Low pressure Vacume
5 with all requrested completed of work including 311.25 Rm 97.00 30191 311.25 30191 0 0
cost and convency of matriel complet of work.
Page 99 of 204
Civil Work
CONDUIT PIPE
1 Supply and Laying of ISI 25mm outer dia heavy grade with IS:9537 part 3 regid PVC pipe concealed
in Roof Slabs with all required PVC / Metallic Deep Boxes including masonary work and labour charges
etc., complete. Makes : Sudhakar / Finolex / Modi / VIP / Precision / Universal / Million Plast / Gold /
Polycab / DEC.
a) Labour charges :
1 Skilled Electrician. 2.00 day 1 day 565.00 1130.00
2 Lineman / Semi Skilled Electrician. 2.00 day 1 day 470.00 940.00
3 Helper (Electrical). 2.00 day 1 day 470.00 940.00
Labour Rate Per 100 Rm 3010.00
Labour Rate for 1 Mtr 30.10
b) Material
1.2.1 Supply of ISI 25mm outer dia heavy 100.00 Mtr 1 Mtr 33.00 3300.00
b) grade FRLS with IS:9537 part 3 regid
PVC pipe.
1.2.6 b) Supply of PVC Junction Boxes Deep 12.00 Nos 1 Nos 26.00 312.00
size 25mm.
1.2.7 b) Supply of 25mm dia PVC Bends. 12.00 Nos 1 Nos 8.00 96.00
2 Supply and Laying of ISI 20mm outer dia heavy grade with IS:9537 part 3 regid PVC pipe concealed
in Roof Slabs with all required PVC / Metallic Deep Boxes including masonary work and labour charges
etc., complete. Makes : Sudhakar / Finolex / Modi / VIP / Precision / Universal / Million Plast / Gold /
Polycab / DEC.
a) Labour charges :
1 Skilled Electrician. 2.00 day 1 day 565.00 1130.00
2 Lineman / Semi Skilled Electrician. 2.00 day 1 day 470.00 940.00
3 Helper (Electrical). 2.00 day 1 day 470.00 940.00
Labour Rate Per 100 Rm 3010.00
Labour Rate for 1 Mtr 30.10
b) Material
1.2.1 a) Supply of ISI 20mm outer dia heavy 100.00 Mtr 1 Mtr 25.00 2500.00
grade FRLS with IS:9537 part 3 regid
PVC pipe.
1.2.6 a) Supply of PVC Junction Boxes Deep 12.00 Nos 1 Nos 23.00 276.00
size 20mm.
1.2.7 a) Supply of 20mm dia PVC Bends. 12.00 Nos 1 Nos 6.00 72.00
3 Supply and laying of ISI 25mm outer dia medium grade with IS:9537 part 3 regid PVC pipe concealed
in wall with all required PVC / Metallic Junction Boxes including masonary work and labour charges
etc., Makes : Sudhakar / Finolex / Modi / VIP / Precision / Universal / Million Plast / Gold / Polycab /
DEC.
a) Labour charges :
1 Skilled Electrician. 2.00 day 1 day 565.00 1130.00
2 Lineman / Semi Skilled Electrician. 2.00 day 1 day 470.00 940.00
3 Helper (Electrical). 2.00 day 1 day 470.00 940.00
4 Mason Cl- I / Brick layer Cl- I 2.00 day 1 day 500.00 1000.00
Labour Rate Per 100 Rm 4010.00
Labour Rate for 1 Mtr 40.10
b) Material
1.2.2 b) Supply of ISI 25mm outer dia medium 100.00 Mtr 1 Mtr 24.00 2400.00
grade FRLS with IS:9537 part 3 regid
PVC pipe.
4 Supply and laying of ISI 20mm outer dia medium grade with IS:9537 part 3 regid PVC pipe concealed
in wall with all required PVC / Metallic Junction Boxes including masonary work and labour charges
etc., Makes : Sudhakar / Finolex / Modi / VIP / Precision / Universal / Million Plast / Gold / Polycab /
DEC.
a) Labour charges :
1 Skilled Electrician. 2.00 day 1 day 565.00 1130.00
2 Lineman / Semi Skilled Electrician. 2.00 day 1 day 470.00 940.00
3 Helper (Electrical). 2.00 day 1 day 470.00 940.00
4 Mason Cl- I / Brick layer Cl- I 2.00 day 1 day 500.00 1000.00
Labour Rate Per 100 Rm 4010.00
Labour Rate for 1 Mtr 40.10
b) Material
1.2.2 a) Supply of ISI 20 mm outer dia medium 100.00 Mtr 1 Mtr 18.00 1800.00
grade FRLS with IS:9537 part 3 regid
PVC pipe.
9.4.11 Cement. 50.00 kg 1 Kg 8.00 400.00
9.1.4 U Nails. 200.00 Nos 100 Nos 32.00 64.00
1.2.5 a) Supply of 20mm PVC Junction Boxes 12.00 Nos 1 Nos 19.00 228.00
Normal.
1.2.7 a) Supply of 20mm dia 1.5mm thick PVC 12.00 Nos 1 Nos 6.00 72.00
Bends.
Material Rate for 100 Mtrs 2564.00
Material Rate for 1 Mtr 25.64
Total Cost of Material + Labour 65.70
Charges
Add Contractors Profit 0.000% 0.00
65.70
Rate per Meter 66.00
5 Supply and Laying of ISI 32mm outer dia medium grade with IS:9537 part 3 regid PVC pipe concealed
in walls with all required PVC / Metallic Deep Boxes including masonary work and labour charges etc.,
complete. Makes : Sudhakar / Finolex / Modi / VIP / Precision / Universal / Million Plast / Gold /
Polycab / DEC.
a) Labour charges :
a) Labour charges :
1 Skilled Electrician. 2.00 day 1 day 565.00 1130.00
2 Lineman / Semi Skilled Electrician. 2.00 day 1 day 470.00 940.00
3 Helper (Electrical). 2.00 day 1 day 470.00 940.00
4 Mason Cl- I / Brick layer Cl- I 2.00 day 1 day 500.00 1000.00
Labour Rate Per 100 Rm 4010.00
Labour Rate for 1 Mtr 40.10
9.4.11 Cement. 50.00 kg 1 Kg 8.00 400.00
9.1.4 U Nails. 200.00 Nos 100 Nos 32.00 64.00
1.2.5 c) Supply of 32mm PVC Junction Boxes 12.00 Nos 1 Nos 35.00 420.00
Normal.
1.2.8 c) Supply of 32mm dia 2.0 mm thick PVC 12.00 Nos 1 Nos 18.00 216.00
Bends.
1.2.2 c) Supply of ISI 32 mm outer dia medium 100.00 Mtr 1 Mtr 39.00 3900.00
grade FRLS with IS:9537 part 3 regid
PVC pipe.
Material Rate for 100 Mtrs 5000.00
Material Rate for 1 Mtr 50.00
Total Cost of Material + Labour 90.10
Charges
Add Contractors Profit 0.000% 0.00
90.10
Rate per Meter 90.00
6 Supply and Fixing of ISI 25mm outer dia medium grade with IS:9537 part 3 regid PVC pipe surface on
wall/ceiling with all required saddles and all accessories and labour charges etc., complete for run of
mains. Makes : Sudhakar / Finolex / Modi / VIP / Precision / Universal / Million Plast / Gold / Polycab /
DEC.
a) Labour charges :
1 Skilled Electrician. 2.00 day 1 day 565.00 1130.00
2 Lineman / Semi Skilled Electrician. 2.00 day 1 day 470.00 940.00
3 Helper (Electrical). 2.00 day 1 day 470.00 940.00
Labour Rate Per 100 Rm 3010.00
Labour Rate for 1 Mtr 30.10
b) Material
9.1.2 Rawl Plugs. 200.00 Nos 100 Nos 33.00 66.00
1.4.4 d) Supply of No.8 Screws of 35/38mm. 200.00 Nos 100 Nos 100.00 200.00
9.4.11 (SoR-2016-17-TBSE-1.4.23)
Cement. 5.00 kg 1 Kg 8.00 40.00
1.1.11 b) Supply of 25mm Saddles with Base. 200.00 Nos 100 Nos 210.00 420.00
1.2.5 b) Supply of 25mm PVC Junction Boxes 12.00 Nos 1 No 20.00 240.00
Normal.
1.2.7 b) Supply of 25mm dia 1.5mm thick PVC 12.00 Nos 1 No 8.00 96.00
Bends.
1.2.2 b) Supply of ISI 25mm outer dia medium 100.00 Mtr 1 Mtr 24.00 2400.00
(1.80mm thickness) grade FRLS with
IS:9537 part 3 regid PVC pipe.
7 Supply and Laying of P.V.C casing and caping (ISI MARK) with double locking arrangments with
groover trunking of size not below 12.5mm height 25mm size with all accessories, duly sealed at points
and erected on Wall / Ceiling including cost of all materials and labour charges complete. Makes : Modi
with ISI
a) Labour charges :
1 Skilled Electrician. 1.00 day 1 day 565.00 565.00
2 Lineman / Semi Skilled Electrician. 1.00 day 1 day 470.00 470.00
3 Helper (Electrical). 2.00 day 1 day 470.00 940.00
Labour Rate Per 100 Rm 1975.00
Labour Rate for 1 Mtr 19.75
b) Material
1.2.4 b)
Supply of 25mm width and 12.5mm
SoR-18-19 100.00 Rm 1 Rm 30.00 3000.00
height Casing and Caping.
Material Rate for 100 Mtrs 3000.00
Material Rate for 1 Mtr 30.00
Total Cost of Material + Labour 49.70
Charges
Add Contractors Profit 0.000% 0.00
49.70
Rate per Meter 50.00
8 Supply and erecting PVC / GI / MS Galvanished fan hook box with hook in RCC slab including all
Labour charges etc., complete.
a) Labour charges :
1 Skilled Electrician. 0.03 day 1 day 565.00 16.95
2 Helper (Electrical). 0.03 day 1 day 470.00 14.10
Labour for 1 No 31.05
a) Material
9.1.22 PVC/ MS with hook in RCC Fan hook each 1 1 Nos 103.00 103.00
134.05
1.2.6 b) PVC Box ( LESS COST OF DEEP each 1 1 Nos 26.00 26.00
BOX )
Rate 108.05
Add Contractors Profit 0.000% 0.00
Rate per Each 108.00
8a Supply and erecting MS plain rod fan hook in RCC slab including all Labour charges etc., complete.
a) Labour charges :
Rate 63.05
Add Contractors Profit 0.000% 0.00
a) Labour charges :
1 Skilled Electrician. 0.60 day 1 day 565.00 339.00
2 Lineman Electric / Telephone 1.20 day 1 day 470.00 564.00
3 Helper (Electrical). 0.60 day 1 day 470.00 282.00
Labour for 6 Points 1185.00
Labour for 1 Point 197.50
b) Material
1.3.1 b) Supply of 3 Module box. 2 Nos 1 No 80.00 160.00
1.3.2 b) Supply of 3 Modular Cover Frame. 2 Nos 1 No 76.00 152.00
1.9.1 b) Supply of 6A / 10A 1 Way 1 Module 6 Nos 1 No 88.00 528.00
Modular Switch.
1.7.1 m) Supply of 3 Plate Jumbo Ceiling Rose. 6 Nos 1 No 19.00 114.00
1.5.1 a) Supply of 22/0.3mm (1.5 Sqmm) 100.00 Mtrs 100 Mtrs 1510.00 1510.00
FRLS / HFFR PVC insulated 1100V
grade as perIS:694/1990 specification
for Copper cable.
a) Labour charges :
1 Skilled Electrician. 0.70 day 1 day 565.00 395.50
2 Lineman Electric / Telephone 1.40 day 1 day 470.00 658.00
3 Helper (Electrical). 0.70 day 1 day 470.00 329.00
Labour for 6 Points 1382.50
Labour for 1 Point 197.50
b) Material
1.3.1 b) Supply of 3 Module box. 1 Nos 1 No 80.00 80.00
1.3.1 c) Supply of 4 Module box. 1 Nos 1 No 95.00 95.00
1.3.2 b) Supply of 3 Modular Cover Frame. 1 Nos 1 No 76.00 76.00
1.3.2 c) Supply of 4 Modular Cover Frame. 1 Nos 1 No 88.00 88.00
Common Socket
11 Supply and fixing of 6A ISI Mark 3/2 pin Modular socket with 6A 1way Modular switch, 3 Module box
with cover frame and GI switch box on common switch board with connections etc., complete.
Makes: Legrand Arteor / Schneider Zen celo / Honeywell Blenge Plus / Cabtree Amare / Logus Platina.
a) Labour charges :
1 Skilled Electrician. 0.067 day 1 day 565.00 37.86
2 Helper (Electrical). 0.067 day 1 day 470.00 31.49
Labour for 1 Point 69.35
b) Material
1.3.1 b) Supply of 3 Module box. 1 No 1 No 80.00 80.00
1.3.2 b) Supply of 3 Modular Cover Frame. 1 No 1 No 76.00 76.00
1.9.1 a) Supply of 6A / 10A 1 Way 1 Module 1 No 1 No 88.00 88.00
Modular Switch.
1.9.1 d) Supply of 6A / 10A 3/2 Pin 2 Module 1 No 1 No 135.00 135.00
Modular Socket with shutter.
Separate Socket
12 Wiring with 3 of 22/0.3mm ( 1.5 Sq.mm) FRLS / HFFR P.V.C. insulated flexible copper cable (ISI
MARK) in existing pipe with 6A switch and 6A, 3/2 pin socket Modular type with 6A switch control and
MS boxes with cover plate and GI switch box fixing on separate board including all labour charges
etc., complete.
Makes of wires : Finolex / RR kabel / Havells / APAR EBXL / KEI (HFFR) / Polycab ((HR_FR-LF) / L&T /
V-Guard (HFFR).
Makes of switches: Legrand Arteor / Schneider Zen celo / Honeywell Blenge Plus / Cabtree Amare /
Logus Platina.
a) Labour charges :
1 Skilled Electrician. 1.50 day 1 day 565.00 847.50
2 Lineman Electric / Telephone 1.50 day 1 day 470.00 705.00
3 Helper (Electrical). 1.50 day 1 day 470.00 705.00
Labour for 15 Points 2257.50
Labour for 1 Point 150.50
b) Material
1.3.1 b) Supply of 3 Module box. 15 Nos 1 No 80.00 1200.00
1.3.2 b) Supply of 3 Modular Cover Frame. 15 No 1 No 76.00 1140.00
1.9.1 a) Supply of 6A / 10A 1 Way 1 Module 15 No 1 No 88.00 1320.00
Modular Switch.
1.9.1 d) Supply of 6A / 10A 3/2 Pin 2 Module 15 No 1 No 135.00 2025.00
Modular Socket with shutter.
1.5.1 a) Supply of 22/0.3mm (1.5 Sqmm) 150.00 Mtrs 100 Mtrs 1510.00 2265.00
FRLS / HFFR PVC insulated 1100V
grade as perIS:694/1990 specification
for Copper cable.
a) Labour charges :
1 Skilled Electrician. 0.20 day 1 day 565.00 113.00
2 Helper (Electrical). 0.20 day 1 day 470.00 94.00
Labour for 1 No 207.00
b) Material
1.3.1 d) Supply of 6 Module box 1 No 1 No 130.00 130.00
1.3.2 d) Supply of 6 Modular Cover Frame. 1 Nos 1 No 130.00 130.00
1.9.1 a) Supply of 6A / 10A 1 Way 1 Module 2 Nos 1 No 88.00 176.00
Modular Switch.
a) Labour charges :
1 Skilled Electrician. 0.20 day 1 day 565.00 113.00
2 Helper (Electrical). 0.20 day 1 day 470.00 94.00
Labour for 1 No 207.00
b) Material
1.3.1 e) Supply of 8/9 Module box 1 No 1 No 170.00 170.00
1.3.2 e) Supply of 8/9 Modular Cover Frame. 1 Nos 1 No 170.00 170.00
1.9.1 a) Supply of 6A / 10A 1 Way 1 Module 3 Nos 1 No 88.00 264.00
Modular Switch.
1.9.1 d) Supply of 6A / 10A 3/2 Pin 2 Module 3 Nos 1 No 135.00 405.00
Modular Socket with shutter.
Cost of Material for 1 No 1009.00
Total Cost of Material + Labour 1216.00
Charges
Add Contractors Profit 0.000% 0.00
1216.00
Rate per Each 1216.00
a) Labour charges :
1 Skilled Electrician. 0.20 day 1 day 565.00 113.00
2 Helper (Electrical). 0.20 day 1 day 470.00 94.00
Labour for 1 No 207.00
b) Material
1.3.1 e) Supply of 12 Module box 1 No 1 No 205.00 205.00
1.3.2 e) Supply of 12 Modular Cover Frame. 1 Nos 1 No 210.00 210.00
1.9.1 a) Supply of 6A / 10A 1 Way 1 Module 4 Nos 1 No 88.00 352.00
Modular Switch.
1.9.1 d) Supply of 6A / 10A 3/2 Pin 2 Module 4 Nos 1 No 135.00 540.00
Modular Socket with shutter.
Cost of Material for 1 No 1307.00
a) Labour charges :
1 Skilled Electrician. 0.10 day 1 day 565.00 56.50
2 Helper (Electrical). 0.10 day 1 day 470.00 47.00
Labour for 1 No 103.50
b) Material
1.3.1 b) Supply of 3 Module box. 1 No 1 No 80.00 80.00
1.3.2 b) Supply of 3 Modular Cover Frame. 1 No 1 No 76.00 76.00
1.9.1 h) Supply of 16A / 20A 1 Way 1 Module 1 No 1 No 120.00 120.00
Modular Switch.
1.9.1 i) Supply of 16A/6A 1 way Combi Socket 1 No 1 No 188.00 188.00
Modular Socket with shutter.
Cost of Material for 1 No 464.00
Total Cost of Material + Labour 567.00
Charges
Add Contractors Profit 0.000% 0.00
567.00
Rate per Each 567.00
a) Labour charges :
1 Skilled Electrician. 0.15 day 1 day 565.00 84.75
2 Helper (Electrical). 0.15 day 1 day 470.00 70.50
Labour for 1 No 155.25
b) Material
1.3.1 d) Supply of 6 Module box 1 No 1 No 130.00 130.00
1.3.2 d) Supply of 6 Modular Cover Frame. 1 Nos 1 No 130.00 130.00
1.9.1 a) Supply of 6A / 10A 1 Way 1 Module 1 Nos 1 No 88.00 88.00
Modular Switch.
1.9.1 d) Supply of 6A / 10A 3/2 Pin 2 Module 1 Nos 1 No 135.00 135.00
Modular Socket with shutter.
1.9.1 h) Supply of 16A / 20A 1 Way 1 Module 1 No 1 No 120.00 120.00
Modular Switch.
1.9.1 i) Supply of 16A/6A 1 way Combi Socket 1 No 1 No 188.00 188.00
Modular Socket with shutter.
Cost of Material for 1 No 791.00
Total Cost of Material + Labour 946.00
Charges
Add Contractors Profit 0.000% 0.00
946.00
Rate per Each 946.00
a) Labour charges :
1 Skilled Electrician. 0.15 day 1 day 565.00 84.75
2 Helper (Electrical). 0.15 day 1 day 470.00 70.50
Labour for 1 No 155.25
b) Material
1.3.1 d) Supply of 6 Module box 1 No 1 No 130.00 130.00
1.3.2 d) Supply of 6 Modular Cover Frame. 1 Nos 1 No 130.00 130.00
1.9.1 h) Supply of 16A / 20A 1 Way 1 Module 2 Nos 1 No 120.00 240.00
Modular Switch.
1.9.1 i) Supply of 16A/6A 1 way Combi Socket 2 Nos 1 No 188.00 376.00
Modular Socket with shutter.
Cost of Material for 1 No 876.00
Total Cost of Material + Labour
1031.00
Charges
Add Contractors Profit 0.000% 0.00
1031.00
Rate per Each 1031.00
Run of Mains
19 Supply and run of 1 of 22 /0.3mm (1.5 Sq.mm) FRLS / HFFR P.V.C. insulated flexible copper cable in
existing conduit pipe for earth continuity including all labour charges etc., complete.
Makes of wires : Finolex / RR kabel / Havells / APAR EBXL / KEI (HFFR) / Polycab ((HR_FR-LF) / L&T /
V-Guard (HFFR).
a) Labour charges :
1 Skilled Electrician. 0.34 day 1 day 565.00 192.10
2 Lineman Electric / Telephone 0.70 day 1 day 470.00 329.00
3 Helper (Electrical). 0.34 day 1 day 470.00 159.80
Labour for 100 Mtr 680.90
Labour for 1 Mtr 6.81
b) Material
1.5.1 a) Supply of 22/0.3mm (1.5 Sqmm) 100.00 Mtrs 100 Mtrs 1510.00 1510.00
FRLS / HFFR Copper cable.
20 Supply and run of 3 of 2.5 sq.mm (36/0.mm) (phase, neutral and earth) FRLS / HFFR PVC insulated
flexible copper cable in existing conduit pipe for individual lighting circuits including labour charges etc.,
complete as required for switch boards.
Makes of wires :Finolex / RR kabel / Havells / APAR EBXL / KEI (HFFR) / Polycab ((HR_FR-LF) / L&T /
V-Guard (HFFR).
a) Labour charges :
1 Skilled Electrician. 1.00 day 1 day 565.00 565.00
2 Lineman Electric / Telephone 2.50 day 1 day 470.00 1175.00
3 Helper (Electrical). 1.00 day 1 day 470.00 470.00
Labour for 100 Mtr 2210.00
Labour for 1 Mtr 22.10
b) Material
1.5.1 b) Supply of 36/0.3mm (2.5 Sqmm) 300.00 Mtrs 100 Mtrs 2440.00 7320.00
FRLS / HFFR Copper cable.
Cost of Material for 100 Metres 7320.00
Cost of Material Rate per Mtr= C/100 73.20
Total Cost of Material + Labour 95.30
Charges
Add Contractors Profit 0.000% 0.00
95.30
Rate per Meter 95.00
21 Supply and 3 runs of 4.0 sq mm (56/0.3 mm) (phase neutral and earth) FRLS / HFFR PVC insulated
flexible copper cable in existing conduit pipe including labour charges etc., complete for 16A sockets.
Makes of wires : Finolex / RR kabel / Havells / APAR EBXL / KEI (HFFR) / Polycab ((HR_FR-LF) / L&T /
V-Guard (HFFR).
a) Labour charges :
1 Skilled Electrician. 1.00 day 1 day 565.00 565.00
2 Lineman Electric / Telephone 3.00 day 1 day 470.00 1410.00
3 Helper (Electrical). 1.00 day 1 day 470.00 470.00
Labour for 100 Mtr 2445.00
Labour for 1 Mtr 24.45
b) Material
1.5.1 c) Supply of 56/0.3mm (4.0 Sqmm) 300.00 Mtrs 100 Mtrs 3725.00 11175.00
FRLS / HFFR Copper cable.
Cost of Material for 100 Metres 11175.00
Cost of Material Rate per Mtr= C/100 111.75
Total Cost of Material + Labour 136.20
Charges
Add Contractors Profit 0.000% 0.00
136.20
Rate per Meter 136.00
22 Supply and 3 runs of 6.0 sq mm (84/0.3mm) (phase neutral and earth) PVC FRLS / HFFR insulated
flexible copper cable in existing conduit pipe for AC's and SPNDB's including labour charges etc.,
Makes of wires : Finolex / RR kabel / Havells / APAR EBXL / KEI (HFFR) / Polycab ((HR_FR-LF) / L&T /
V-Guard (HFFR).
a) Labour charges :
1 Skilled Electrician. 1.00 day 1 day 565.00 565.00
2 Lineman Electric / Telephone 3.00 day 1 day 470.00 1410.00
3 Helper (Electrical). 1.00 day 1 day 470.00 470.00
Labour for 100 Mtr 2445.00
Labour for 1 Mtr 24.45
b) Material
1.5.1 d) Supply of 84/0.3mm (6.0 Sqmm) FRLS/ 300.00 Mtrs 100 Mtrs 5700.00 17100.00
HFFR Copper cable.
23 Supply & run of 5 of 6.0 Sqmm (84/0.3mm) (3 phases, neutral and earth) FRLS / HFFR PVC insulated
flexible copper cable in the existing conduict pipe for run of mains from Power panel board to TPN DB"s
with pin type lugs and connections etc., complete. [for LDBs]
Makes of wires :Finolex / RR kabel / Havells / APAR EBXL / KEI (HFFR) / Polycab ((HR_FR-LF) / L&T /
V-Guard (HFFR).
a) Labour charges :
1 Skilled Electrician. 2.00 day 1 day 565.00 1130.00
2 Lineman Electric / Telephone 5.50 day 1 day 470.00 2585.00
3 Helper (Electrical). 2.00 day 1 day 470.00 940.00
Labour for 100 Mtr 4655.00
Labour for 1 Mtr 46.55
b) Material
1.5.1 d) Supply of 84/0.3mm (6.0 Sqmm) 500.00 Mtrs 100 Mtrs 5700.00 28500.00
FRLS / HFFR Copper cable.
Cost of Material for 100 Metres 28500.00
Cost of Material Rate per Mtr= C/100 285.00
Total Cost of Material + Labour 331.50
Charges
Add Contractors Profit 0.000% 0.00
331.50
Rate per Meter 332.00
24 Supply & run of 5 of 10.0 Sqmm (140/0.3 mm) (3 phases, neutral and earth) FRLS / HFFR PVC
insulated flexible copper cable in the existing conduict pipe for run of mains from Power panel board to
TPN DB"s with pin type lugs and connections etc., complete. [for PDBs]
Makes of wires : Finolex / RR kabel / Havells / APAR EBXL / KEI (HFFR) / Polycab ((HR_FR-LF) / L&T /
V-Guard (HFFR).
a) Labour charges :
1 Skilled Electrician. 2.34 day 1 day 565.00 1322.10
2 Lineman Electric / Telephone 6.50 day 1 day 470.00 3055.00
3 Helper (Electrical). 2.34 day 1 day 470.00 1099.80
Labour for 100 Mtr 5476.90
Labour for 1 Mtr 54.77
b) Material
1.5.1 e) Supply of 140/0.3mm (10.0 Sqmm) 500.00 Mtrs 100 Mtrs 8800.00 44000.00
PVC FRLS / HFFR insulated flexible
Copper cable.
Cost of Material for 100 Metres 44000.00
Cost of Material Rate per Mtr= C/100 440.00
Total Cost of Material + Labour 494.70
Charges
Add Contractors Profit 0.000% 0.00
494.70
Rate per Meter 495.00
a) Labour charges :
1 Skilled Electrician. 0.60 day 1 day 565.00 339.00
2 Lineman Electric / Telephone 1.20 day 1 day 470.00 564.00
3 Helper (Electrical). 0.60 day 1 day 470.00 282.00
Labour for 6 Points 1185.00
Labour for 1 Point 197.50
b) Material
1.3.1 b) Supply of 3 Module box. 2 Nos 1 No 80.00 160.00
1.3.3 b) Supply of 3 Modular Cover Frame. 2 Nos 1 No 68.00 136.00
1.9.2 b) Supply of 6A / 10A 1 Way 1 Module 6 Nos 1 No 61.00 366.00
Modular Switch.
1.7.1 m) Supply of 3 Plate Jumbo Ceiling Rose. 6 Nos 1 No 19.00 114.00
1.5.2 a) Supply of 22/0.3mm (1.5 Sqmm) 100.00 Mtrs 100 Mtrs 1320.00 1320.00
FRLS / HFFR PVC insulated 1100V
grade as perIS:694/1990 specification
for Copper cable.
a) Labour charges :
1 Skilled Electrician. 0.70 day 1 day 565.00 395.50
2 Lineman Electric / Telephone 1.40 day 1 day 470.00 658.00
3 Helper (Electrical). 0.70 day 1 day 470.00 329.00
Labour for 6 Points 1382.50
Labour for 1 Point 197.50
b) Material
1.3.1 b) Supply of 3 Module box. 1 Nos 1 No 80.00 80.00
1.3.1 c) Supply of 4 Module box. 1 Nos 1 No 95.00 95.00
1.3.3 b) Supply of 3 Modular Cover Frame. 1 Nos 1 No 68.00 68.00
1.3.3 c) Supply of 4 Modular Cover Frame. 1 Nos 1 No 80.00 80.00
Common Socket
27 Supply and fixing of 6A ISI Mark 3/2 pin Modular socket with 6A 1way Modular switch, 3 Module box
with cover frame and GI switch box on common switch board with connections etc., complete.
Makes : Legrand Myrius / Million mway / Gold Medal Curve / Anchor Roma viola / GM Four-Five /
Havells Fabio / Panasonic Vision / L&T Englaze / Hager Insista / Benlo Vesta / C&S Primo / CPL Vysma
/ Polycab Levana.
a) Labour charges :
1 Skilled Electrician. 0.067 day 1 day 565.00 37.86
2 Helper (Electrical). 0.067 day 1 day 470.00 31.49
Labour for 1 Point 69.35
b) Material
1.3.1 b) Supply of 3 Module box. 1 No 1 No 80.00 80.00
1.3.3 b) Supply of 3 Modular Cover Frame. 1 No 1 No 68.00 68.00
1.9.2 a) Supply of 6A / 10A 1 Way 1 Module 1 No 1 No 61.00 61.00
Modular Switch.
1.9.2 d) Supply of 6A / 10A 3/2 Pin 2 Module 1 No 1 No 90.00 90.00
Modular Socket with shutter.
Separate Socket
28 Wiring with 3 of 22/0.3mm ( 1.5 Sq.mm) FRLS / HFFR P.V.C. insulated flexible copper cable (ISI
MARK) in existing pipe with 6A switch and 6A, 3/2 pin socket Modular type with 6A switch control and
MS boxes with cover plate and GI switch box fixing on separate board including all labour charges
etc., complete.
Makes of wires : HPL / RPG / Kundancab / Nakoda / Anchor / GM / Million / Gold Medal / Power Flex /
Fortune Art / Gloster.
Makes of switches: Legrand Myrius / Million mway / Gold Medal Curve / Anchor Roma viola / GM Four-
Five / Havells Fabio / Panasonic Vision / L&T Englaze / Hager Insista / Benlo Vesta / C&S Primo / CPL
Vysma / Polycab Levana.
a) Labour charges :
1 Skilled Electrician. 1.50 day 1 day 565.00 847.50
2 Lineman Electric / Telephone 1.50 day 1 day 470.00 705.00
3 Helper (Electrical). 1.50 day 1 day 470.00 705.00
Labour for 15 Points 2257.50
Labour for 1 Point 150.50
b) Material
1.3.1 b) Supply of 3 Module box. 15 Nos 1 No 80.00 1200.00
1.3.3 b) Supply of 3 Modular Cover Frame. 15 No 1 No 68.00 1020.00
1.9.2 a) Supply of 6A / 10A 1 Way 1 Module 15 No 1 No 61.00 915.00
Modular Switch.
1.9.2 d) Supply of 6A / 10A 3/2 Pin 2 Module 15 No 1 No 90.00 1350.00
Modular Socket with shutter.
1.5.2 a) Supply of 22/0.3mm (1.5 Sqmm) 150.00 Mtrs 100 Mtrs 1320.00 1980.00
FRLS / HFFR PVC insulated 1100V
grade as perIS:694/1990 specification
for Copper cable.
a) Labour charges :
a) Labour charges :
1 Skilled Electrician. 0.20 day 1 day 565.00 113.00
2 Helper (Electrical). 0.20 day 1 day 470.00 94.00
Labour for 1 No 207.00
b) Material
1.3.1 e) Supply of 8/9 Module box 1 No 1 No 170.00 170.00
1.3.3 e) Supply of 8/9 Modular Cover Frame. 1 Nos 1 No 135.00 135.00
1.9.2 a) Supply of 6A / 10A 1 Way 1 Module 3 Nos 1 No 61.00 183.00
Modular Switch.
1.9.2 d) Supply of 6A / 10A 3/2 Pin 2 Module 3 Nos 1 No 90.00 270.00
Modular Socket with shutter.
Cost of Material for 1 No 758.00
Total Cost of Material + Labour 965.00
Charges
Add Contractors Profit 0.000% 0.00
965.00
Rate per Each 965.00
a) Labour charges :
1 Skilled Electrician. 0.20 day 1 day 565.00 113.00
2 Helper (Electrical). 0.20 day 1 day 470.00 94.00
Labour for 1 No 207.00
b) Material
1.3.1 e) Supply of 12 Module box 1 No 1 No 205.00 205.00
1.3.3 e) Supply of 12 Modular Cover Frame. 1 Nos 1 No 165.00 165.00
1.9.2 a) Supply of 6A / 10A 1 Way 1 Module 4 Nos 1 No 61.00 244.00
Modular Switch.
1.9.2 d) Supply of 6A / 10A 3/2 Pin 2 Module 4 Nos 1 No 90.00 360.00
Modular Socket with shutter.
Cost of Material for 1 No 974.00
Total Cost of Material + Labour 1181.00
Charges
Add Contractors Profit 0.000% 0.00
1181.00
a) Labour charges :
1 Skilled Electrician. 0.10 day 1 day 565.00 56.50
2 Helper (Electrical). 0.10 day 1 day 470.00 47.00
Labour for 1 No 103.50
b) Material
1.3.1 b) Supply of 3 Module box. 1 No 1 No 80.00 80.00
1.3.3 b) Supply of 3 Modular Cover Frame. 1 No 1 No 68.00 68.00
1.9.2 h) Supply of 16A / 20A 1 Way 1 Module 1 No 1 No 80.00 80.00
Modular Switch.
1.9.2 i) Supply of 16A/6A 1 way Combi Socket 1 No 1 No 130.00 130.00
Modular Socket with shutter.
Cost of Material for 1 No 358.00
Total Cost of Material + Labour 461.00
Charges
Add Contractors Profit 0.000% 0.00
461.00
Rate per Each 461.00
a) Labour charges :
1 Skilled Electrician. 0.15 day 1 day 565.00 84.75
2 Helper (Electrical). 0.15 day 1 day 470.00 70.50
Labour for 1 No 155.25
b) Material
1.3.1 d) Supply of 6 Module box 1 No 1 No 130.00 130.00
1.3.3 d) Supply of 6 Modular Cover Frame. 1 Nos 1 No 110.00 110.00
1.9.2 a) Supply of 6A / 10A 1 Way 1 Module 1 Nos 1 No 61.00 61.00
Modular Switch.
1.9.2 d) Supply of 6A / 10A 3/2 Pin 2 Module 1 Nos 1 No 90.00 90.00
Modular Socket with shutter.
1.9.2 h) Supply of 16A / 20A 1 Way 1 Module 1 No 1 No 80.00 80.00
Modular Switch.
1.9.2 i) Supply of 16A/6A 1 way Combi Socket 1 No 1 No 130.00 130.00
Modular Socket with shutter.
Cost of Material for 1 No 601.00
Total Cost of Material + Labour 756.00
Charges
Add Contractors Profit 0.000% 0.00
756.00
Rate per Each 756.00
a) Labour charges :
1 Skilled Electrician. 0.15 day 1 day 565.00 84.75
2 Helper (Electrical). 0.15 day 1 day 470.00 70.50
Labour for 1 No 155.25
b) Material
1.3.1 d) Supply of 6 Module box 1 No 1 No 130.00 130.00
1.3.3 d) Supply of 6 Modular Cover Frame. 1 Nos 1 No 110.00 110.00
1.9.2 h) Supply of 16A / 20A 1 Way 1 Module 2 Nos 1 No 80.00 160.00
Modular Switch.
1.9.2 i) Supply of 16A/6A 1 way Combi Socket 2 Nos 1 No 130.00 260.00
Modular Socket with shutter.
Cost of Material for 1 No 660.00
Total Cost of Material + Labour
Charges 815.00
Add Contractors Profit 0.000% 0.00
815.00
Rate per Each 815.00
Run of Mains
35 Supply and run of 1 of 22 /0.3mm (1.5 Sq.mm) FRLS / HFFR P.V.C. insulated flexible copper cable in
existing conduit pipe for earth continuity including all labour charges etc., complete.
Makes of wires : HPL / RPG / Kundancab / Nakoda / Anchor / GM / Million / Gold Medal / Power Flex /
Fortune Art / Gloster.
a) Labour charges :
1 Skilled Electrician. 0.34 day 1 day 565.00 192.10
2 Lineman Electric / Telephone 0.70 day 1 day 470.00 329.00
3 Helper (Electrical). 0.34 day 1 day 470.00 159.80
Labour for 100 Mtr 680.90
Labour for 1 Mtr 6.81
b) Material
1.5.2 a) Supply of 22/0.3mm (1.5 Sqmm) 100.00 Mtrs 100 Mtrs 1320.00 1320.00
FRLS / HFFR Copper cable.
36 Supply and run of 3 of 2.5 sq.mm (36/0.mm) (phase, neutral and earth) FRLS / HFFR PVC insulated
flexible copper cable in existing conduit pipe for individual lighting circuits including labour charges etc.,
complete as required for switch boards.
Makes of wires :HPL / RPG / Kundancab / Nakoda / Anchor / GM / Million / Gold Medal / Power Flex /
Fortune Art / Gloster.
a) Labour charges :
1 Skilled Electrician. 1.00 day 1 day 565.00 565.00
2 Lineman Electric / Telephone 2.50 day 1 day 470.00 1175.00
3 Helper (Electrical). 1.00 day 1 day 470.00 470.00
Labour for 100 Mtr 2210.00
Labour for 1 Mtr 22.10
b) Material
1.5.2 b) Supply of 36/0.3mm (2.5 Sqmm) 300.00 Mtrs 100 Mtrs 2140.00 6420.00
FRLS / HFFR Copper cable.
Cost of Material for 100 Metres 6420.00
Cost of Material Rate per Mtr= C/100 64.20
Total Cost of Material + Labour 86.30
Charges
Add Contractors Profit 0.000% 0.00
86.30
Rate per Meter 86.00
37 Supply and 3 runs of 4.0 sq mm (56/0.3 mm) (phase neutral and earth) FRLS / HFFR PVC insulated
flexible copper cable in existing conduit pipe including labour charges etc., complete for 16A sockets.
Makes of wires : HPL / RPG / Kundancab / Nakoda / Anchor / GM / Million / Gold Medal / Power Flex /
Fortune Art / Gloster.
a) Labour charges :
a) Labour charges :
1 Skilled Electrician. 0.50 day 1 day 565.00 282.50
2 Lineman Electric / Telephone 0.50 day 1 day 470.00 235.00
3 Helper (Electrical). 1.00 day 1 day 470.00 470.00
Labour for 100 Mtr 987.50
Labour for 1 Mtr 9.88
b) Material
1.5.2 c) Supply of 10 sqmm WPTC (Weather 100.00 Mtrs 100 Mtrs 3400.00 3400.00
Proof Twin Core) ISI Alluminium Wire
Cost of Material for 100 Metres 3400.00
Supply and fixing of 12 V 150AH MF battery including wire leads. Makes : Amar Raja (Power Zone) or
Equivalent model of Exide / Panasonic / Gotech- SSR-1897
Supply and fixing of 12 V 150AH MF 100.00 NOS 100 NOS 11500.00 11500.00
battery
1 Supply, Transportation and fixing of 60 W / 65 W LED LED Street light, Body made of high grade
pressure
a) Labourdie – cast Aluminium alloy with corrosion resistant powder coat, having protective toughened
charges
1 Skilled Electrician. 0.25 day 1 day 565.00 141.25
2 Lineman Electric / Telephone 0.25 day 1 day 470.00 117.50
3 Helper (Electrical). 0.25 day 1 day 470.00 117.50
Labour for 1 No 376.25
b) Material
1.5.2 b) Supply of 2.5 Sqmm FRLS / HFFR 2.00 Mtrs 100 Mtrs 2140.00 42.80
Copper cable.
9.4.15 b) 40mm Nominal Bore Medium grade 1.00 Mtrs 1 Mtr 350.00 350.00
G.I.Pipe.
Pipe bending charges LS 40.00
M.S flat and welding charges LS 50.00
3.11.1 d 60 / 65 W 1 Nos 1 Nos 5700.00 5700.00
Cost of Material for 1 No 6182.80
Total Cost of Material + Labour
Charges 6559.00
Add Contractors Profit 0.000% 0.00
6559.00
Rate per Each 6559.00
3 7.6.2 a) Supply and fixing of suitable out door 1 No 1 each 21719.00 21719.00
feeder piller box of size made with 14
SWG CRCA sheet with double door
arrangement, making powder coating
after processing of 7 Tank process,
lock and key, hinges, rubber gasket,
danger board,suitable angle iron stand
for mounting the feeder pillar with
cement concrete, including Supply and
fixing of 63A, 4 Pole MCB as incomer,
6 Nos 6-32A SP MCBs as out goings,
indication lamps, din channel, 6 Sqmm
3 core copper cable for invidual light
control, connectors, gland plates and
provision for 3 phase energy meter etc.,
complete for finished item of work and
suitable wiring provision for connecting
the nature switch with following.
Makes : Legrand / Schnieder
5 Supply, Transportation and fixing of 120 W LED Flood light Luminaire made of pressure die cast
aluminum housing with powder coated, having toughened glass cover, IP 66 (Silicon gasket ensures
a) Labour charges
1 Skilled Electrician. 0.50 day 1 day 565.00 282.50
2 Lineman Electric / Telephone 0.50 day 1 day 470.00 235.00
3 Helper (Electrical). 0.50 day 1 day 470.00 235.00
Labour for 1 No 752.50
b) Material
1.5.7 i) 4.0 Sqmm (56/0.3) 3 Core Flexible 25.00 Mtrs 1 Mtrs 145.00 3625.00
Armouring Flexible Copper cable
3.11.4 c) 120 W 1 Nos 1 Nos 12674.00 12674.00
Cost of Material for 1 No 16299.00
Total Cost of Material + Labour
17052.00
Charges
1 Supply & run of 5 of 6.0 Sqmm (84/0.3mm) (3 phases, neutral and earth) FRLS / HFFR PVC insulated
flexible
a) Labourcopper cable
charges : in the existing conduict pipe for run of mains from Power panel board to TPN DB"s
1 Skilled Electrician. 2.00 day 1 day 565.00 1130.00
2 Lineman Electric / Telephone 5.50 day 1 day 470.00 2585.00
3 Helper (Electrical). 2.00 day 1 day 470.00 940.00
Labour for 100 Mtr 4655.00
Labour for 1 Mtr 46.55
b) Material
1.5.2 d) Supply of 84/0.3mm (6.0 Sqmm) 500.00 Mtrs 100 Mtrs 5100.00 25500.00
FRLS / HFFR Copper cable.
Cost of Material for 100 Metres 25500.00
301.50
2 Supply & run of 5 of 10.0 Sqmm (140/0.3 mm) (3 phases, neutral and earth) FRLS / HFFR PVC
insulated flexible copper cable in the existing conduict pipe for run of mains from Power panel board to
a)
TPNLabour
DB"s charges
with pin :type lugs and connections etc., complete. [for PDBs]
1 Skilled Electrician.
Makes of wires : HPL / RPG / Kundancab / Nakoda 2.34 /day
Anchor / GM 1 day 565.00
/ Million / Gold Medal / Power 1322.10
Flex /
2 Fortune Art / Gloster.
Lineman Electric / Telephone 6.50 day 1 day 470.00 3055.00
b) Material
1.5.2 e) Supply of 140/0.3mm (10.0 Sqmm) 500.00 Mtrs 100 Mtrs 7750.00 38750.00
PVC FRLS / HFFR insulated flexible
Copper cable. for 100 Metres
Cost of Material 38750.00
Cost of Material Rate per Mtr= C/100 387.50
Total Cost of Material + Labour 442.20
Charges
Add Contractors Profit 0.000% 0.00
442.20
Rate per Meter 442.00
Distribution Boards
AC BOX
25 Supply and fixing 20A Plug and Socket with SS enclosure with 20A SP MCB including connections for
AC's. Makes : Legrand-DX3 / Schneider-Acti9 / Siemens / L&T Exora / Cabtree
MATERIAL
2.16.8 a) Supply of 20A Plug and Socket with SS 1 Nos 1 No 1035.00 1035.00
enclosure.
3 Mason Cl- I / Brick layer Cl- I 0.15 day 1 day 500.00 75.00
1438.75
27 Supply and fixing of FP Metal Enclosure with IP 20 Protection DB Make with 1 No 63A, 10 KA FP MCB
including internal connection and labour charges for Flush Mounting etc., complete. Makes : Legrand-
MATERIAL
DX3 / Schneider-Acti9 / Siemens / L&T Exora / Cabtree
2.16.11 b) Supply of DP/TP/FP Metal Enclosure 1 Nos 1 No 440.00 440.00
with IP 20 Protection.
2.13.1 h) Supply of 63A FP MCB, C/D Curve ISI 1 Nos 1 No 1900.00 1900.00
Mark.
9.4.11 Cement. 5.00 Kg 1 Kg 8.00 40.00
COST OF MATERIAL FOR FULSH 2380.00
MOUNTING
LABOUR
Skilled Electrician. 0.25 day 1 day 540.00 135.00
Helper (Electrical). 0.25 day 1 day 450.00 112.50
Mason Cl- I / Brick layer Cl- I 0.15 day 1 day 470.00 70.50
COST OF LABOUR FOR FULSH 318.00
MOUNTING
TOTAL COST OF MATERIAL + 2698.00
LABOUR FOR FULSH MOUNTING
Add Contractors Profit 0.000% 0.00
2698.00
LDB
28 Supply and fixing of 4 Way TPN DB Horizontal with IP 43 Protection as per IS:13032 makes Legrand /
Schneider / Siemens / L&T / Hager / Cabtree Xproand Supply and Fixing of 1 No., of 63A FP Isolator as
incomer and 12 Nos 6-32 A 10kA SP MCBs of makes Legrand-DX3 / Schneider-Acti9 / Siemens / L&T
MATERIAL
Exora / Cabtree as out goings including internal connections and labour charges for FLUSH Mounting
etc., complete. (For Lighting DBs)
Makes : Legrand / Shneider
8001.00
Rate per Each 8001.00
PDB
29 Supply and fixing of 4 Way TPN DB Horizontal with IP 43 Protection as per IS:13032 Makes : Legrand /
Schneider
MATERIAL/ Siemens / L&T / Hager /Cabtree Xproand Supply and Fixing of 1 No., of 100A FP Isolator as
2.16.1 b) Supply of 4 Way TPN DB Horizontal 1 Nos 1 No 2860.00 2860.00
with IP 43 Protection as per IS:13032
and suitable for 12 Nos S.P. out goings
and for 1 No 4 pole Incommer etc
complete.
2.14.1 h) Supply of 100A FP Isolator . 1 No 1 No 1000.00 1000.00
Supply of 6-32A 10KA SP MCB, C/D 12 Nos 1 No 210.00 2520.00
2.13.1 a)
Curve ISI Mark.
9.4.11 Cement. 12.50 Kg 1 Kg 8.00 100.00
Sundries 5.00
6485.00
LABOUR
1 Skilled Electrician. 0.70 day 1 day 565.00 395.50
2 Lineman Electric / Telephone 1.00 day 1 day 470.00 470.00
3 Helper (Electrical). 1.00 day 1 day 470.00 470.00
4 Mason Cl- I / Brick layer Cl- I 0.50 day 1 day 500.00 250.00
1585.50
TOTAL COST OF MATERIAL + FLUSH 8071.00
LABOUR FOR FLUSH MOUNTING
Add Contractors Profit 0.000% 0.00
8071.00
30 Supply and fixing of 6 Way TPN DB Horizontal with IP 43 Protection as per IS:13032 Makes : Legrand /
Schneider / Siemens / L&T / Hager / Cabtree Xpro and Supply and Fixing of 1 No., of 100A FP Isolator
as incomer and 18 Nos 6-32 A 10kA SP MCBs Makes : Legrand-DX3 / Schneider-Acti9 / Siemens /
MATERIAL
L&T Exora / Cabtree as out goings including internal connections and labour charges for FLUSH
Mounting etc., complete for DBs.
10668.00
Rate per Each
8 Way VTPN DB
31 Supply and fixing of 8 Way VTPN DB with IP 43 Protection Makes : Legrand / Schneider / Siemens /
L&T / Hager /Cabtree Xpro and Supply and Fixing of 1 No., of 125A 4 Pole MCCB, Adjustable, Confirms
MATERIAL
2.16.3 b) Supply of 8 Way VTPN DB 1 Nos 1 No 11800.00 11800.00
2.13.1 f) Supply of 63A 10KA TPN MCB, C/D 8 Nos 1 No 1480.00 11840.00
Curve ISI Mark.
2.8.1 d) 125A 4 Pole MCCB, 25KA 1 Nos 1 No 8952.00 8952.00
Sundries 5.00
COST OF MATERIAL FOR Surface 32597.00
MOUNTING
LABOUR
1 Skilled Electrician. 1.25 day 1 day 565.00 706.25
2 Lineman Electric / Telephone 1.50 day 1 day 470.00 705.00
3 Helper (Electrical). 1.50 day 1 day 470.00 705.00
COST OF LABOUR FOR Surface 2116.25
MOUNTING
TOTAL COST OF MATERIAL + 34713.00
LABOUR FOR Surface MOUNTING
34713.00
Rate per Each
8 Way VTPN DB
32 Supply and fixing of 8 Way VTPN DB with IP 43 Protection Makes : Legrand / Schneider / Siemens /
L&T / Hager / Cabtree Xpro and Supply and Fixing of 1 No., of 125A 4 Pole MCCB, Adjustable,
MATERIAL
2.16.3 b) Supply of 8 Way VTPN DB 1 Nos 1 No 11800.00 11800.00
Supply of 6-32A 10KA SP MCB, C/D 24 Nos 1 No 210.00 5040.00
2.13.1 a)
Curve ISI Mark.
26361.00
26361.00
Rate per Each
4 Way VTPN DB
33 Supply and fixing of 4 Way VTPN DB with IP 43 Protection as per IS:13032 Makes : Legrand /
Schneider / Siemens / L&T / Hager /Cabtree Xpro and Supply and Fixing of 1 No., of 125A 4 Pole
MATERIAL
MCCB, Adjustable, Confirms to IS/IEC 60947-2 having Breaking Capacity 25 KA with thermal magnetic
2.16.3 a) Supply
release ofPanel
4 Way VTPN DBas incomer with 4 Nos of163A,
Mounted Nos 10KA, TP
1 NoMCBs C/D 9400.00
Curve ISI Mark as9400.00
Out
goings including internal connections
2.13.1 f) Supply of 63A 10KA TPN MCB, C/D and labour charges
4 Nos for etc.,
1 Nocomplete. Makes :
1480.00 L&T / Schneider
5920.00/
Siemens
Curve ISI/Mark.
Legrand / Hager /ABB / C&S.
2.8.1 c) Supply of 125A 3 Pole MCCB 1 Nos 1 No 7404.00 7404.00
9.4.11 Cement. 12.50 Kg 1 Kg 8.00 100.00
Sundries 6.00
COST OF MATERIAL FOR SURFACE 22830.00
MOUNTING
LABOUR
1 Skilled Electrician. 1.00 day 1 day 565.00 565.00
2 Lineman Electric / Telephone 1.50 day 1 day 470.00 705.00
3 Helper (Electrical). 1.00 day 1 day 470.00 470.00
COST OF LABOUR FOR SURFACE 1740.00
MOUNTING
TOTAL COST OF MATERIAL + SURFACE 24570.00
LABOUR FOR SURFACE MOUNTING
8 Way SPNDB
34 Supply and fixing of 8 Way SPN DB with IP 43 Protection as per IS:13032 and suitable for 8Nos
10A 10KA SP MCB as out goings and for 1 No 40A DP Isolator Incommer, concealing in wall etc
MATERIAL
2.15.1 d) Supply of 8 Way SPN DB 1 Nos 1 No 1365.00 1365.00
1 No 1 No 385.00 385.00
2.14.1 b) Supply of 40A DP Isolator .
8 Nos 1 No 210.00 1680.00
9.4.11 Cement.
Sundries 2.00
3532.00
LABOUR
1 Skilled Electrician. 0.50 day 1 day 565.00 282.50
2 Lineman Electric / Telephone 0.50 day 1 day 470.00 235.00
3 Mason Cl- I / Brick layer Cl- I 0.50 day 1 day 500.00 250.00
767.50
TOTAL COST OF MATERIAL + 4300.00
LABOUR FOR FLUSH MOUNTING
35 Supply and Installation of 63A 4 Pole MCCB, Adjustable, Confirms to IS/IEC 60947-2 having Breaking
Capacity
MATERIAL 25 KA with thermal magnetic release with cable end boxes on suitable angle iron frame work
Fabrication: L H D
Size of panel : in Mtr 0.25 0.25 0.15
Front and back faces 2.00 0.25 0.25 0.13
Top and bottom faces 2.00 0.25 0.15 0.08
Side faces 2.00 0.25 0.15 0.08
Sub total 0.28
Add extra 10 % for wastage 0.03
Total 0.30
36 Supply and Installation of 125 Amps 4 Pole MCCB, Adjustable, Confirms to IS/IEC 60947-2 having
Breaking
MATERIAL Capacity 25 KA with thermal magnetic release etc complete with connections. Make: L&T /
Fabrication: L H D
Size of panel : in Mtr 0.50 0.50 0.25
Front and back faces 2.00 0.50 0.50 0.50
Top and bottom faces 2.00 0.50 0.25 0.25
Side faces 2.00 0.50 0.25 0.25
Sub total 1.00
Add extra 10 % for wastage 0.10
Total 1.10
37 Supply and Installation of 250 Amps 4 Pole MCCB, Adjustable, Confirms to IS/IEC 60947-2 having
Breaking Capacity 35 KA with cable end boxes on suitable angle iron frame work including all Labours
charges massonry work etc complete with connections. Make: L&T / Schneider / Siemens / Legrand /
Hager /ABB / C&S.
MATERIAL
Fabrication: L H D
Total 1.84
LABOUR
752.50
Earthings
38 Providing independent earthing by exacavating a pit to a depth of 2.25Mtr in all soils as per size
specified in the data for Important equipment with 2.5Mtr length 40mm dia 'B' class G.I pipe and 18"
b) labour charges for fixing pipe
dia 3" thick hume pipe ring with R.C.C. Slab cover duly providing staggered holes filling with 20Kg
1 Skilled
Salt andElectrician.
40Kg Charcoal or 40Kg bentonite powder1.00 No 1 No of the pipe
from the bottom 565.00
giving earth 565.00
connection
Sub Total from electrode through G.I strip of 25 x 6mm x 200mm length to be bolted with nut565.00
bolts
including supply and termination of No.8 G.I.wire from bottm of the pipe with all accessories and
a) Material
labour charges complete, as per IS specifications 732/1982 (Part II)
9.4.15 d) 40mm Nominal Bore Medium grade 2.50 Mtr 1 Mtr 350.00 875.00
G.I.Pipe.
9.4.20 Drilling of through holes of 12mm dia 16.00 Nos 1 No 6.00 96.00
to G.I pipe.
9.4.21 G.I Nuts, Bolts an Washers each set. 4.00 Sets 1 Set 12.00 48.00
9.4.23 18" dia 3" hume pipe ring. 1.00 No 1 No 300.00 300.00
9.1.10 Hard Coke. 40.00 Kg 1 Kg 21.00 840.00
9.1.11 Salt. 20.00 Kg 1 Kg 16.00 320.00
9.4.17 Earth work excavation of hard gravel 1.27 cum 1 cum 250.00 317.50
soil with small boulders for trench 1st
step of size 1.2 x 0.6 x 0.9 m
(4'x2'x3')
9.4.17 Earth work hard disintegrated rock 1.87 cum 1 cum 250.00 467.50
and boulders for trench 2nd Step of
size 0.9 x 0.6 x 1.2 m (3'x2'x4')
25% extra for narrow trench & pit and 25% 785.00 196.25
back filling with Sand, Coke, Salt etc.,
and leveling
Sundries 5.00
Rate per each 3534.80
Total Cost of Material + Labour 4100.00
Charges Add Contractors Profit 0.000% 0.00
4100.00
Rate per Each 4100.00
39 Providing independent earthing by exacavating a pit to a depth of 2.25Mtr in all soils as per size
specified
b) labour in the data
charges forforfixing
Sophisticated
pipe Electronic equipment with 600mm x 600mm x 3.15mm thick
9.4.20 Drilling of through holes of 12mm dia 16.00 Nos 1 No 6.00 96.00
to G.I pipe.
9.4.21 G.I Nuts, Bolts an Washers each set. 4.00 Set 1 Set 12.00 48.00
40 Supply and Run of 25mm x 6mm G.I Strip including cost of all accessories and labour charges etc.,
complete. (1.18Kgs/1Mtr)
a) Labour charges :
1 Skilled Electrician. 1.00 day 1 day 565.00 565.00
2 Helper (Electrical). 1.00 day 1 day 470.00 470.00
Labour for 100 Mtrs 1035.00
Labour for 1 Mtr 10.35
b) Material
9.3.6 G.I. Strip / Plate / Wire (per K. G). 118.00 Kgs 1 Kg 65.00 7670.00
Sundries.
41 Supply and Run of 40mm x 6mm G.I Strip including cost of all accessories and labour charges etc.,
complete. (1.88 Kg:/ Mtr)
a) Labour charges
1 Skilled Electrician. 1.50 day 1 day 565.00 847.50
2 Helper (Electrical). 1.50 day 1 day 470.00 705.00
Labour for 100 Mtrs 1552.50
Labour for 1 Mtr 15.53
b) Material
9.3.6 G.I. Strip / Plate / Wire (per K. G). 188.00 Kgs 1 Kg 65.00 12220.00
Sundries.
42 Supply and Run of 50mm x 6mm G.I Strip including cost of all accessories and labour charges etc.,
complete. (2.36 Kg:/ Mtr)
a) Labour charges
1 Skilled Electrician. 2.00 day 1 day 565.00 1130.00
2 Helper (Electrical). 2.00 day 1 day 470.00 940.00
Sundries.
43 Supply and Run of 75mm x 6mm G.I Strip including cost of all accessories and labour charges etc.,
complete. ( 3.54 Kg: / Mtr)
a) Labour charges
1 Skilled Electrician. 2.00 day 1 day 565.00 1130.00
2 Helper (Electrical). 3.00 day 1 day 470.00 1410.00
Labour for 100 Mtrs 2540.00
Labour for 1 Mtr 25.40
b) Material
9.3.6 G.I. Strip / Plate / Wire (per K. G). 354.00 Kgs 1 Kg 65.00 23010.00
Sundries.
44 Supply and Run of 25mm x 3mm copper strip (Cuurrent Carrying Capacity 270A) including cost of all
accessories and labour
a) Labour charges : charges etc., complete. (0.663Kgs/1Mtr)
1 Skilled Electrician. 1.00 day 1 day 565.00 565.00
2 Helper (Electrical). 1.50 day 1 day 470.00 705.00
Labour for 100 Mtrs 1270.00
Labour for 1 Mtr 12.70
b) Material
9.3.1 Copper plate / Copper strip (Per K.G). 66.30 Kgs 1 Kg 590.00 39117.00
Sundries.
45 Supply and Run of 25mm x 6mm copper strip (Cuurrent Carrying Capacity 270A) including cost of all
accessories and labour
a) Labour charges : charges etc., complete. (1.34 Kg / Mtr)
1 Skilled Electrician. 1.00 day 1 day 565.00 565.00
2 Helper (Electrical). 1.75 day 1 day 470.00 822.50
Labour for 100 Mtrs 1387.50
Labour for 1 Mtr 13.88
b) Material
Copper plate / Copper strip (Per K.G).
9.3.1 134.00 Kgs 1 Kg 590.00 79060.00
Sundries.
Cost of Material for 100 Metres 79060.00
46 Supply and Run of No.8 SWG G.I wire including cost of all accessories and labour charges etc.,
complete. (0.104Kgs/1Mtr)
a) Labour charges :
1 Helper (Electrical). 2.00 day 1 day 470.00 940.00
Labour for 100 Mtrs 940.00
b) Material
9.3.6 G.I. Strip / Plate / Wire (per K. G). 10.40 Kgs 1 Kg 65.00 676.00
9.1.4 U Nails. 150.00 Nos 100 Nos 32.00 48.00
Sundries.
Cost of Material for 100 Metres 724.00
Cost of Material Rate per Mtr= C/100 7.24
Total Cost of Material + Labour
17.00
Charges
Add Contractors Profit 0.000% 0.00
17.00
FIXTURES
36/40W Box type tube light
47 Supply and fixing of 1 x 36/40W Box type tube light luminaire powder coated CRCA sheet steel housing
with Electronic
a) Labour Ballast Chokes, with 40 W tube light and all standard accessories Makes : Phillips /
charges
Crompton / Bajaj / Surya.
b) Material
1.5.4 Supply of 23 / 0060 twin core twisted / 1.00 Mtr 100 Mtrs 980.00 9.80
flat heavy Copper wire.
1.4.4 d) Supply of No.8 Screws of 35/38mm. 2 Nos 100 Nos 100.00 2.00
9.1.2 Rawl Plugs. 2.00 Nos 100 Nos 33.00 0.66
Fixing arrangements on wall with 2 Nos 1 Nos 5.00 10.00
3.6.3 a)
required support on wall
1 x 36/40W Box type tube light 1 Nos 1 Nos 651.00 651.00
SoR-18-19
luminaire
3.8.4 Supply of 36/40W fluorescent tube. 1 Nos 1 Nos 40.00 40.00
Cost of Material for fixing luminaire 713.46
Total Cost of Material + Labour
Charges
817.00
817.00
Rate per Each 817.00
b) Material
1.5.4 Supply of 23 / 0060 twin core twisted / 1.00 Mtr 100 Mtrs 980.00 9.80
flat heavy Copper wire.
1.4.4 d) Supply of No.8 Screws of 35/38mm. 2 Nos 100 Nos 100.00 2.00
9.1.2 Rawl Plugs. 2.00 Nos 100 Nos 33.00 0.66
Fixing arrangements on wall with 2 Nos 1 Nos 5.00 10.00
required support on wall
3.9.16 22W, 2300 lumens, 1200mm LED 1 Nos 1 Nos 800.00 800.00
Tube light alluminium body
Cost of Material 822.46
Total Cost of Material + Labour 926.00
Charges
b) Material
1.5.4 Supply of 23 / 0060 twin core twisted / 1.00 Mtr 100 Mtrs 980.00 9.80
flat heavy Copper wire.
1.4.4 d) Supply of No.8 Screws of 35/38mm. 2 Nos 100 Nos 100.00 2.00
9.1.2 Rawl Plugs. 2.00 Nos 100 Nos 33.00 0.66
Fixing arrangements on wall with 2 Nos 1 Nos 5.00 10.00
required support on wall
3.9.10 20W, 2000 lumens, 1200mm LED Tube 1 Nos 1 Nos 730.00 730.00
light alluminium body
Cost of Material 752.46
Total Cost of Material + Labour 856.00
Charges
1.5.4 Supply of 23 / 0060 twin core twisted / 1.00 Mtr 100 Mtrs 980.00 9.80
flat heavy Copper wire.
1.4.4 d) Supply of No.8 Screws of 35/38mm. 2 Nos 100 Nos 100.00 2.00
9.1.2 Rawl Plugs. 2.00 Nos 100 Nos 33.00 0.66
Fixing arrangements on wall with 2 Nos 1 Nos 5.00 10.00
required support on wall
3.9.14 20W, 2000 lumens, 1200mm LED Tube 1 Nos 1 Nos 525.00 525.00
light PC Body
Cost of Material 547.46
1438.00
1438.00
Rate per Each
BH/SBH
53 Supply and fixing of ISI mark batten holder / slanting holder Makes : Anchor / Gold Medal Olive / Million
Zoom in lieu of ceiling rose of light point complete with all connections and all labour charges with 3.0W
a) Labour
LED Lamp.charges
Makes:: Phillips / OSRAM / Wipro / Crompton / Bajaj / Havells / Halonix / Jaquar / HPL.
b) Material
78.00
78.00
Rate per Each
b) Material
55 Supply and fixing of Ding Dong Bell of Makes : GM / Million / Gold Medal / Anchor / Great white on 4"x7"
decolam block including giving connections, cost of all accessories and labour charges etc., complete.
a) Labour charges :
57 Supply and transportation of 48" (1200mm) Sweep decorative Ceiling Fan with all accessories etc.,
complete.
Makes : Crompton High Speed Decora / Havells Spark Deco / Orient Summer Crown / Panasonic Sprint
5.1.3 Deco / Halonix Sweep
48" (1200mm) Erbon decorative Each 1 1 Nos 2200.00 2200.00
Ceiling Fan
Transportation 0.02 44.00
2244
Add Contractors Profit 0.000% 0.00
2244.00
Rate per Each 2244.00
57 Supply and fixing of 2 Module Modular type Electronic step type Fan Regulator for sweep AC ceiling
fans of 1200mm / 1420mm complete with connections.
Makes : Legrand Myrius / Million mway / Gold Medal Curve / Anchor Roma viola / GM Four-Five /
Havells Fabio / Panasonic Vision / L&T Englaze / Hager Insista / Benlo Vesta / C&S Primo / CPL Vysma
/ Polycab Levana.
a) Labour charges
1 Lineman Electric / Telephone 0.05 Nos 1 Nos 470.00 23.50
Labour for 1 No 23.50
b) Material
1.9.2 n) Supply of Electronic type stepped type 1 Nos 1 Nos 365.00 365.00
Electronic Regulator.
1.3.1 a) Supply of 2 Module box. 1 No 1 No 57.00 57.00
1.3.3 a) Supply of 2 Modular Cover Frame. 1 No 1 No 56.00 56.00
Cost of Material for 1 No 478.00
Total Cost of Material + Labour
502.00
Charges
Add Contractors Profit 0.000% 0.00
502.00
Rate per Each 502.00
58 Labour charges for fixing of ceiling fan and regulator including transportation and giving connections
with twin core wire etc., complete.
a) Labour charges
1 Skilled Electrician. 0.125 day 1 day 565.00 70.63
b) Material
1.5.4 Supply of 23 / 0060 twin core twisted / 1.00 Mtrs 100 Mtrs 980.00 9.80
flat heavy Copper wire.
Cost of Material for fixing fan 9.80
Total Cost of Material + Labour
139.00
Charges
Add Contractors Profit 0.000% 0.00
139.00
139.00
Rate per Each
59 Supply and erecting 19/20mm steel tube down rod of one meter length with bolts & nuts duly painted
with matching colour of fan complete
a) Labour charges
Helper (Electrical). 0.100 day 1 day 470.00 47.00
Labour for 1 No 47.00
b) Material
9.1.21 19/20mm steel tube down rod with bolts 1.00 Mtrs 1 Mtrs 87.00 87.00
& nuts for fan with maching colour.
60 Supply,Transportation of light duty exhaust fan 12"(300 mm) size with metal blades wiremesh with all
accessories
5.1.9 b) Supply etcduty
of light complete
exhaustMakes
fan : CromptonEach/ Havells1 Ventil Air-DB
1 Nos/ Orient 1435.00
hill air. 1435.00
12"(300 mm) size
Transportation 0.02 28.70
1464.00
Add Contractors Profit 0.000% 0.00
1464.00
Rate per Each 1464.00
61 Supply,Transportation of 12" (300mm) ISI, 900 RPM Heavy duty exhaust fan with metallic blades
wiremesh with all accessories etc complete Makes : Crompton / Almounard / Havells Turbo Force SP.
5.1.11 a) Supply of 12" (300mm) ISI, 900 RPM Each 1 1 Nos 2830.00 2830.00
Heavy duty exhaust fan
Transportation 0.02 56.60
2887.00
Add Contractors Profit 0.000% 0.00
2887.00
62 Labour charges for fixing the Light duty exhaust fan in wall with connections with twin core wire and
masonary work of making hole, finishing etc., complete.
a) Labour charges
1 Skilled Electrician. 0.250 day 1 day 565.00 141.25
2 Lineman Electric / Telephone 0.250 day 1 day 470.00 117.50
3 Mason Cl- I / Brick layer Cl- I 0.250 day 1 day 500.00 125.00
Labour for 1 No 383.75
1.5.4 Supply of 23 / 0060 twin core twisted / 1.00 Mtrs 100 Mtrs 980.00 9.80
flat heavy Copper wire.
9.4.11 Cement. 25 Kg 1 Kg 8.00 200.00
Sundries such as Sand, Bolt, Nuts etc. 1 Job 1 Job 6.00 6.00
600.00
63 Supply, Transportation and Fixing of GI Louver shutter suitable for 12" (300mm) Exhaust fan of Best
quality and makes as directed with fixing arrangments and all labour charges etc., complete.
a) Labour charges
1 Skilled Electrician. 0.050 day 1 day 565.00 28.25
2 Lineman Electric / Telephone 0.050 day 1 day 470.00 23.50
Labour for 1 No 51.75
b) Material
3 Sundries such as Sand, Bolt, Nuts etc. 1 Job 1 Job 10.50 10.50
212.00
Rate per Each 212.00
U.G Cables
64 4.1.1 f) Supply of 16 Sqmm 4 Core XLPE RMS 1 1 One Rmt 162.00 162.00
insulated, 1100V grade armoured
alluminium cable with ISI mark as per
specification confirming to IS:7098
(Part - I)
Makes : Torrent / Unicab / Universal /
Polycab / Havells / Gloster / KEI /
Finolex / Paragon.
162.00
Rate per Meter 162.00
65 4.1.1 g) Supply of 25 Sqmm 3.5 Core XLPE RMS 1 1 One Rmt 207.00 207.00
insulated, 1100V grade armoured
alluminium cable with ISI mark as per
specification confirming to IS:7098
(Part - I)
Makes :Torrent / Unicab / Universal /
Polycab / Havells / Gloster / KEI /
Finolex / Paragon.
207.00
Rate per Meter 207.00
66 4.1.1 h) Supply of 35 Sqmm 3.5 Core XLPE RMS 1 1 One Rmt 247.00 247.00
insulated, 1100V grade armoured
alluminium cable with ISI mark as per
specification confirming to IS:7098
(Part - I)
Makes :Torrent / Unicab / Universal /
Polycab / Havells / Gloster / KEI /
Finolex / Paragon.
247.00
Rate per Meter 247.00
67 4.1.1 i) Supply of 50 Sqmm 3.5 Core XLPE RMS 1 1 One Rmt 326.00 326.00
insulated, 1100V grade armoured
alluminium cable with ISI mark as per
specification confirming to IS:7098
(Part - I)
Makes :Torrent / Unicab / Universal /
Polycab / Havells / Gloster / KEI /
Finolex / Paragon.
326.00
Rate per Meter 326.00
68 4.1.1 j) Supply of 70 Sqmm 3.5 Core XLPE RMS 1 1 One Rmt 420.00 420.00
insulated, 1100V grade armoured
alluminium cable with ISI mark as per
specification confirming to IS:7098
(Part - I)
Makes : Torrent / Unicab / Universal /
Polycab / Havells / Gloster / KEI /
Finolex / Paragon.
420.00
Rate per Meter 420.00
69 4.1.1 k) Supply of 95 Sqmm 3.5 Core XLPE RMS 1 1 One Rmt 547.00 547.00
insulated, 1100V grade armoured
alluminium cable with ISI mark as per
specification confirming to IS:7098
(Part - I)
Makes : Torrent / Unicab / Universal /
Polycab / Havells / Gloster / KEI /
Finolex / Paragon.
547.00
Rate per Meter 547.00
70 4.1.1 L) Supply of 120 Sqmm 3.5 Core XLPE RMS 1 1 One Rmt 670.00 670.00
insulated, 1100V grade armoured
alluminium cable with ISI mark as per
specification confirming to IS:7098
(Part - I)
Makes : Torrent / Unicab / Universal /
Polycab / Havells / Gloster / KEI /
Finolex / Paragon.
670.00
Rate per Meter 670.00
71 4.1.1 m) Supply of 150 Sqmm 3.5 Core XLPE RMS 1 1 One Rmt 760.00 760.00
insulated, 1100V grade armoured
alluminium cable with ISI mark as per
specification confirming to IS:7098
(Part - I)
Makes : Torrent / Unicab / Universal /
Polycab / Havells / Gloster / KEI /
Finolex / Paragon.
760.00
Rate per Meter 760.00
72 4.1.1 n) Supply of 185 Sqmm 3.5 Core XLPE RMS 1 1 One Rmt 933.00 933.00
insulated, 1100V grade armoured
alluminium cable with ISI mark as per
specification confirming to IS:7098
(Part - I)
Makes : Torrent / Unicab / Universal /
Polycab / Havells / Gloster / KEI /
Finolex / Paragon.
73 4.1.1 o) Supply of 240 Sqmm 3.5 Core XLPE RMS 1 1 One Rmt 1185.00 1185.00
insulated, 1100V grade armoured
alluminium cable with ISI mark as per
specification confirming to IS:7098
(Part - I)
Makes : Torrent / Unicab / Universal /
Polycab / Havells / Gloster / KEI /
Finolex / Paragon.
74 4.1.1 p) Supply of 300 Sqmm 3.5 Core XLPE RMS 1 1 One Rmt 1447.00 1447.00
insulated, 1100V grade armoured
alluminium cable with ISI mark as per
specification confirming to IS:7098
(Part - I)
Makes : Torrent / Unicab / Universal /
Polycab / Havells / Gloster / KEI /
Finolex / Paragon.
75 4.1.1 q) Supply of 400 Sqmm 3.5 Core XLPE RMS 1 1 One Rmt 1815.00 1815.00
insulated, 1100V grade armoured
alluminium cable with ISI mark as per
specification confirming to IS:7098
(Part - I)
Makes : Torrent / Unicab / Universal /
Polycab / Havells / Gloster / KEI /
Finolex / Paragon.
1815.00
76 Earth work excavation of Trench in hard ground soil and Sand filling shall be provided at the bottom of
trench before
b) Labour laying the cable and laying of U.G cables up to 70 sqmm covering the cable with back
charges
1 Skilled Electrician. 1.00 day 1 day 565.00 565.00
2 Helper (Electrical). 2.00 day 1 day 470.00 940.00
3 Man Mazdoor for spreading the sand 2.50 day 1 day 445.00 1112.50
and back filling of the exacavated soils.
4 Man Mazdoor for concreating and 2.00 day 1 day 445.00 890.00
embedding of cable route indicators.
Labour Charges for 100 Mtrs 3507.50
Labour Charges for 1 Mtr 35.08
a) Material
9.4.17 Earth work excacvation including all 36.00 Cum 1 Cum 250.00 9000.00
soils for trench,
9.4.12 Cost of Sand. 4.00 Cum 1 Cum 600.00 2400.00
9.4.13 Cost of Bricks. 1000.00 Nos 952 Nos 4000.00 3808.00
9.4.11 Cement. 25.00 Kg 1 Kg 8.00 200.00
9.1.25 Cable root Indicators. 12.00 Nos 1 Nos 92.00 1104.00
Cost of Material for laying of cable in 100.00 Mtrs 16512.00
trench for
Cost of Material for laying of cable in 1.00 Mtrs 165.12
trench for
Total Cost of Material + Labour 200.00
Charges
Add Contractors Profit 0.000% 0.00
200.00
77 Earth work excavation of Trench in hard ground soil and Sand filling shall be provided at the bottom of
trench before
b) Labour laying the cable and laying of U.G cables from 95 Sqmm up to 420 sqmm covering the
charges
1 Skilled Electrician. 1.60 day 1 day 565.00 904.00
2 Helper (Electrical). 3.30 day 1 day 470.00 1551.00
3 Man Mazdoor for spreading the sand 2.50 day 1 day 445.00 1112.50
and back filling of the exacavated soils.
4 Man Mazdoor for concreating and 2.00 day 1 day 445.00 890.00
embedding of cable route indicators.
Labour Charges for 100 Mtrs 4457.50
Labour Charges for 1 Mtr 44.58
a) Material
9.4.17 Earth work excacvation 36.00 Cum 1 Cum 250.00 9000.00
9.1.51 Cost of Sand. 4.00 Cum 1 Cum 600.00 2400.00
9.4.13 Cost of Bricks. 1000.00 Nos 952 Nos 4000.00 3808.00
9.4.11 Cement. 25.00 Kg 1 Kg 8.00 200.00
9.1.25 Cable root Indicators. 12.00 Nos 1 Nos 92.00 1104.00
78 Laying of PVC armoured under ground cable up to 95 Sqmm fixing on chromium plated metallic base
saddles on wall as per IS 1255 and as directed by the department including cost and conveyance of all
b) Labour charges
materials and labour charges etc., complete.
1 Skilled Electrician. 1.50 day 1 day 565.00 847.50
2 Helper (Electrical). 2.00 day 1 day 470.00 940.00
Labour Charges for 100 Mtrs 1787.50
Labour Charges for 1 Mtr 17.88
a) Material
9.1.2 Rawl Plugs. 4.00 Nos 100 Nos 33.00 1.32
1.4.4 d) Supply of No.8 Screws of 35/38mm. 4.00 Nos 100 Nos 100.00 4.00
9.4.23 f) Supply of Saddle / Clamps for Cable. 2.00 Nos 100 Nos 550.00 11.00
79 Laying of PVC armoured under ground cable from 120 Sq.mm to 400 Sqmm fixing on chromium plated
metallic
b) Labourbase saddles on wall as per IS 1255 and as directed by the department including cost and
charges
1 Skilled Electrician. 1.50 day 1 day 565.00 847.50
2 Helper (Electrical). 2.00 day 1 day 470.00 940.00
Labour Charges for 100 Mtrs 1787.50
Labour Charges for 1 Mtr 17.88
a) Material
9.1.2 Rawl Plugs. 4.00 Nos 100 Nos 33.00 1.32
1.4.4 f) Supply of No.8 Screws of 63/75mm. 4.00 Nos 100 Nos 140.00 5.60
9.4.23 g) Supply of Saddle / Clamps for Cable. 2.00 Nos 100 Nos 850.00 17.00
23.92
Total Cost of Material + Labour
Charges 42.00
Add Contractors Profit 0.000% 0.00
42.00
Rate per Meter 42.00
Cable Terminations:
80 Termination of UG cables of 4 core 10 sq.mm & 4 core 16 sq.mm including with required Heavy
duty cablecharges
b) Labour glands & Lugs complete with all required accessories as directed by the department
1 Skilled Electrician. 0.020 day 1 day 565.00 11.30
2 Lineman Electric / Telephone 0.020 day 1 day 470.00 9.40
3 Helper (Electrical). 0.020 day 1 day 470.00 9.40
Labour Charges for each 30.10
a) Material
4.3.1 b) Glands for 4 core XLPE armoured 1.00 Nos 1 Nos 90.00 90.00
cable up to 16.0 Sq.mm
4.4.2 a) aluminium lugs for cable upto 16 4.00 Nos 1 Nos 12.00 48.00
Sq.mm
138.00
Total Cost of Material + Labour 168.00
Charges
Add Contractors Profit 0.000% 0.00
168.00
Rate per Each 168.00
81 Termination of UG cables of 3.5 core 25 Sq.mm including with required Heavy duty cable glands,
Lugs complete
b) Labour with all required accessories as directed by the department including cost and
charges
1 Skilled Electrician. 0.020 day 1 day 565.00 11.30
2 Lineman Electric / Telephone 0.020 day 1 day 470.00 9.40
3 Helper (Electrical). 0.020 day 1 day 470.00 9.40
Labour Charges for each 30.10
a) Material
4.3.1 c) glands for 3.5 core XLPE armoured 1.00 Nos 1 Nos 130.00 130.00
cable from 25 Sqmm to 50.0 Sq.mm
4.4.2 a) aluminium lugs for cable upto 16 1.00 Nos 1 Nos 12.00 12.00
Sq.mm
4.4.2 b) aluminium lugs confirming to I.S 3.00 Nos 1 Nos 14.00 42.00
specifications for cable of 25 Sq.mm
184.00
Total Cost of Material + Labour 214.00
Charges
Add Contractors Profit 0.000% 0.00
214.00
Rate per Each 214.00
82 Termination of UG cables of 3.5 core 35 Sq.mm including with required Heavy duty cable glands,
Lugs complete
b) Labour with all required accessories as directed by the department including cost and
charges
1 Skilled Electrician. 0.020 day 1 day 565.00 11.30
2 Lineman Electric / Telephone 0.020 day 1 day 470.00 9.40
3 Helper (Electrical). 0.020 day 1 day 470.00 9.40
Labour Charges for each 30.10
a) Material
4.3.1 c) glands for 3.5 core XLPE armoured 1.00 Nos 1 Nos 130.00 130.00
cable from 25 Sqmm to 50.0 Sq.mm
4.4.2 a) aluminium lugs for cable upto 16 1.00 Nos 1 Nos 12.00 12.00
Sq.mm
4.4.2 c) aluminium lugs for cable of 35 3.00 Nos 1 Nos 17.00 51.00
Sq.mm
193.00
Total Cost of Material + Labour
Charges 223.00
Add Contractors Profit 0.000% 0.00
223.00
Rate per Each 223.00
83 Termination of UG cables of 3.5 core 50 Sq.mm including with required Heavy duty cable glands,
Lugs complete
b) Labour with all required accessories as directed by the department including cost and
charges
4.4.2 b) aluminium lugs for cable of 25 1.00 Nos 1 Nos 14.00 14.00
Sq.mm
4.4.2 d) aluminium lugs for cable of 50 3.00 Nos 1 Nos 19.00 57.00
Sq.mm
201.00
Total Cost of Material + Labour
Charges 231.00
Add Contractors Profit 0.000% 0.00
231.00
Rate per Each 231.00
84 Termination of UG cables of 3.5 core 70 Sq.mm including with required Heavy duty cable glands,
Lugs complete with all required accessories as directed by the department including cost and
conveyance of all materials and labour charges etc., complete.
b) Labour charges
4.4.2 e) aluminium lugs confirming to I.S 3.00 Nos 1 Nos 24.00 72.00
specifications for cable of 70 Sq.mm
289.00
Total Cost of Material + Labour 319.00
Charges
Add Contractors Profit 0.000% 0.00
319.00
Rate per Each 319.00
85 Termination of UG cables of 3.5 core 95 Sq.mm including with required Heavy duty cable glands,
Lugs complete
b) Labour with all required accessories as directed by the department including cost and
charges
1 Skilled Electrician. 0.030 day 1 day 565.00 16.95
2 Lineman Electric / Telephone 0.030 day 1 day 470.00 14.10
3 Helper (Electrical). 0.030 day 1 day 470.00 14.10
Labour Charges for each 45.15
a) Material
4.3.1 d) glands for 3.5 core XLPE armoured 1.00 Nos 1 Nos 200.00 200.00
cable from 95 Sqmm
4.4.2 d) aluminium lugs for cable of 50 Sq.mm 1.00 Nos 1 Nos 19.00 19.00
4.4.2 f) aluminium lugs for cable of 95 3.00 Nos 1 Nos 25.00 75.00
Sq.mm
294.00
Total Cost of Material + Labour
Charges 339.00
Add Contractors Profit 0.000% 0.00
339.00
Rate per Each 339.00
86 Termination of UG cables of 3.5 core 120 Sq.mm including with required Heavy duty cable glands,
Lugs complete
b) Labour with all required accessories as directed by the department including cost and
charges
1 Skilled Electrician. 0.030 day 1 day 565.00 16.95
2 Lineman Electric / Telephone 0.030 day 1 day 470.00 14.10
3 Helper (Electrical). 0.030 day 1 day 470.00 14.10
Labour Charges for each 45.15
a) Material
4.3.1 e) glands for 3.5 core XLPE armoured 1.00 Nos 1 Nos 335.00 335.00
cable from 120 Sqmm
4.4.2 e) aluminium lugs for cable of 70 1.00 Nos 1 Nos 24.00 24.00
Sq.mm
4.4.2 g) aluminium lugs for cable of 120 3.00 Nos 1 Nos 35.00 105.00
Sq.mm
464.00
Total Cost of Material + Labour
Charges 509.00
Add Contractors Profit 0.000% 0.00
509.00
Rate per Each 509.00
87 Termination of UG cables of 3.5 core 150 Sq.mm including with required Heavy duty cable glands,
Lugs complete
b) Labour with all required accessories as directed by the department including cost and
charges
1 Skilled Electrician. 0.040 day 1 day 565.00 22.60
2 Lineman Electric / Telephone 0.030 day 1 day 470.00 14.10
3 Helper (Electrical). 0.030 day 1 day 470.00 14.10
Labour Charges for each 50.80
a) Material
4.3.1 e) glands for 3.5 core XLPE armoured 1.00 Nos 1 Nos 335.00 335.00
cable from 150.0 Sq.mm
4.4.2 f) aluminium lugs for cable of 95 Sq.mm 1.00 Nos 1 Nos 25.00 25.00
4.4.2 h) aluminium lugs confirming to I.S 3.00 Nos 1 Nos 45.00 135.00
specifications for cable of 150 Sq.mm
495.00
Total Cost of Material + Labour
Charges 546.00
Add Contractors Profit 0.000% 0.00
546.00
Rate per Each 546.00
88 Termination of UG cables of 3.5 core 185 Sq.mm including with required Heavy duty cable glands,
Lugs complete
b) Labour with all required accessories as directed by the department including cost and
charges
1 Skilled Electrician. 0.080 day 1 day 565.00 45.20
2 Lineman Electric / Telephone 0.080 day 1 day 470.00 37.60
3 Helper (Electrical). 0.080 day 1 day 470.00 37.60
Labour Charges for each 120.40
a) Material
4.3.1 f) glands for 3.5 core XLPE armoured 1.00 Nos 1 Nos 415.00 415.00
cable for 185 Sqmm
4.4.2 f) aluminium lugs confirming to I.S 1.00 Nos 1 Nos 25.00 25.00
specifications for cable of 95 Sq.mm.
4.4.2 i) aluminium lugs confirming to I.S 3.00 Nos 1 Nos 58.00 174.00
specifications for cable of 185 Sq.mm
614.00
Total Cost of Material + Labour
Charges 734.00
Add Contractors Profit 0.000% 0.00
734.00
Rate per Each 734.00
89 Termination of UG cables of 3.5 core 240 Sq.mm including with required Heavy duty cable glands,
Lugs complete
b) Labour with all required accessories as directed by the department including cost and
charges
1 Skilled Electrician. 0.100 day 1 day 565.00 56.50
2 Lineman Electric / Telephone 0.100 day 1 day 470.00 47.00
3 Helper (Electrical). 0.100 day 1 day 470.00 47.00
Labour Charges for each 150.50
a) Material
4.3.1 g) glands for 3.5 core XLPE armoured 1.00 Nos 1 Nos 480.00 480.00
cable for 240Sqmm
4.4.2 g) aluminium lugs for cable of 120 1.00 Nos 1 Nos 35.00 35.00
Sq.mm
4.4.2 j) aluminium lugs for cable of 240 3.00 Nos 1 Nos 84.00 252.00
Sq.mm
767.00
Total Cost of Material + Labour
Charges 918.00
Add Contractors Profit 0.000% 0.00
918.00
Rate per Each 918.00
90 Termination of UG cables of 3.5 core 300 Sq.mm including with required Heavy duty cable glands,
Lugs complete with all required accessories as directed by the department including cost and
b) Labour charges
1 Skilled Electrician. 0.100 day 1 day 565.00 56.50
2 Lineman Electric / Telephone 0.100 day 1 day 470.00 47.00
3 Helper (Electrical). 0.100 day 1 day 470.00 47.00
Labour Charges for each 150.50
a) Material
4.3.1 h) glands for 3.5 core XLPE armoured 1.00 Nos 1 Nos 600.00 600.00
cable for 300Sqmm
4.4.2 h) aluminium lugs for cable of 150 1.00 Nos 1 Nos 45.00 45.00
Sq.mm
4.4.2 k) aluminium lugs for cable of 300 3.00 Nos 1 Nos 110.00 330.00
Sq.mm
975.00
Total Cost of Material + Labour
Charges 1126.00
Add Contractors Profit 0.000% 0.00
1126.00
91 Termination of UG cables of 3.5 core 400 Sq.mm including with required Heavy duty cable glands,
Lugs complete
b) Labour with all required accessories as directed by the department including cost and
charges
1 Skilled Electrician. 0.150 day 1 day 565.00 84.75
1298.00
Total Cost of Material + Labour
Charges 1547.00
Add Contractors Profit 0.000% 0.00
1547.00
Rate per Each 1547.00
92 4.9.1 k) Supply and Installation of 300mm x 1.00 Mtr 1 Mtr 600.00 600.00
50mm x 1.6 mm thick GI perforated
cable tray with out cover along with
required angle supports, with coupler
plates, Anchor bolts and nuts etc
complete and the tray should be fitted
on the wall / Ceiling etc. complete for
finished item of Add
work.Contractors Profit 0.000% 0.00
600.00
Rate per Meter 600.00
93 4.9.1 L) Supply and Installation of 150mm x 1.00 Mtr 1 Mtr 325.00 325.00
50mm x 1.6 mm thick GI perforated
cable tray withAddoutContractors
cover alongProfit
with 0.000% 0.00
required angle supports, with coupler
plates, Anchor bolts and nuts etc 325.00
complete and the tray should be fitted
on the wall / Ceiling etc. complete for
finished item of work for Rate peritem
finished Meter
of 325.00
work.
Telephone
94 Supply, Transportation and Run of 1 of 2 Pair, 0.5mm telephone copper wire in the existing cable tray /
conduit pipe and
Taking Output labour
= 100 M charges etc., complete. Makes : Finolex / Delton / Surabi / Polycab
a) Material
8.1.1 a) 2 pair telephone wire 0.5mm 100 M 1 1 rmt 910.00 910
b) Labour charges :
95 Supply and fixing of Modular telephone Jack with connector on modular box with cover frame in
existing
a) Labourconsealed
charges : pipe wiring including cost and coveyance of all material and all labour charges etc.,
1 Lineman Electric / Telephone 0.050 day 1 day 470.00 23.50
Labour for 1 No 23.50
b) Material
1.3.1 a) Supply of 1 or 2 Module box. 1.00 Nos 1 No 57.00 57.00
96 Supply, Transportation and Run of 1 of 10 Pair, telephone copper wire in the existing cable tray/
conduit pipe
b) Labour and labour charges etc., complete. Makes : Finolex / Delton / Surabi / Polycab.
charges
1 Skilled Electrician. 0.50 day 1 day 565.00 282.50
2 Lineman Electric / Telephone 1.00 day 1 day 470.00 470.00
3 Helper (Electrical). 1.00 day 1 day 470.00 470.00
Labour for 100 Mtrs 1222.50
Labour for 1 Mtr 12.23
a) Material
8.1.1 c) Supply of 10 Pair telephone Copper 1.00 Mtrs 1 Mtrs 36.00 36.00
wire.
Cost of Material for 1 Mtrs 36.00
Total Cost of Material + Labour
Charges 48.00
Add Contractors Profit 0.000% 0.00
48.00
Rate per Meter 48.00
97 Supply, Transportation and Run of 1 of 20 Pair, telephone copper wire in the existing cable tray/
conduit pipe
b) Labour and labour charges etc., complete. Makes : Finolex / Delton / Surabi / Polycab.
charges
a) Material
8.1.1 d) Supply of 20 Pair telephone Copper 1.00 Mtrs 1 Mtrs 70.00 70.00
wire.
Cost of Material for 1 Mtrs 70.00
Total Cost of Material + Labour
Charges 82.00
Add Contractors Profit 0.000% 0.00
82.00
Rate per Meter 82.00
98 Supply, Transportation and Run of 1 of 50 Pair, telephone copper wire in the existing cable tray/ conduit
pipe and labour
b) Labour chargescharges etc., complete. Makes : Finolex / Delton / Surabi / Polycab.
1 Skilled Electrician. 0.50 day 1 day 565.00 282.50
2 Lineman Electric / Telephone 1.00 day 1 day 470.00 470.00
3 Helper (Electrical). 1.00 day 1 day 470.00 470.00
Labour for 100 Mtrs 1222.50
Labour for 1 Mtr 12.23
a) Material
8.1.1 e) Supply of 50 Pair telephone Copper 1.00 Mtrs 1 Mtrs 175.00 175.00
wire.
Cost of Material for 1 Mtrs 175.00
Total Cost of Material + Labour
Charges 187.00
Add Contractors Profit 0.000% 0.00
187.00
Rate per Meter 187.00
99 Supply, Transportation and Run of 1 of 100 Pair raiser cable for telephone in the existing cable tray/
conduit pipe
b) Labour and labour charges etc., complete. Makes : Finolex / Delton / Surabi / Polycab.
charges
1 Skilled Electrician. 0.50 day 1 day 565.00 282.50
2 Lineman Electric / Telephone 1.00 day 1 day 470.00 470.00
3 Helper (Electrical). 1.00 day 1 day 470.00 470.00
100 Supply anf fixing of 200 pair Telephone distribution box with back mount frame, krone connector,
powder coated metal body with lock and key arrangement. Make:Krone
b) Labour charges
1 Skilled Electrician. 0.50 day 1 day 565.00 282.50
101 Supply anf fixing of 100 pair Telephone distribution box with back mount frame, krone connector,
powder coated metal body with lock and key arrangement. Make:Krone
b) Labour charges
1 Skilled Electrician. 0.15 day 1 day 565.00 84.75
102 Supply anf fixing of 50 pair Telephone distribution box with back mount frame, krone connector, powder
coated metal body with lock and key arrangement. Make:Krone
b) Labour charges
1 Skilled Electrician. 0.15 day 1 day 565.00 84.75
103 Supply anf fixing of 20 pair Telephone distribution box with back mount frame, krone connector, powder
coated metal body with lock and key arrangement. Make:Krone
b) Labour charges
1 Skilled Electrician. 0.15 day 1 day 565.00 84.75
2 Lineman Electric / Telephone 0.15 day 1 day 470.00 70.50
Supply anf fixing of 10 pair Telephone distribution box with back mount frame, krone connector, powder
104
coated metal body with lock and key arrangement. Make:Krone
b) Labour charges
1 Skilled Electrician. 0.10 day 1 day 565.00 56.50
2 Lineman Electric / Telephone 0.10 day 1 day 470.00 47.00
Labour Charges 103.50
a) Material
8.1.2 a) 10 Pair MDF box 1.00 No 1 Each 580.00 580.00
Cost of Material for 1 Mtrs 580.00
Total Cost of Material + Labour
Charges 684.00
Add Contractors Profit 0.000% 0.00
684.00
Rate per Each 684.00
LAN
105 Supply and termination of cat-6 RJ 45 out lets including dual face plate of Makes:D Link / AMP / Molex /
Legrand / Krone.
a) Material
8.1.4 a) cat-6 RJ 45 out lets each 1 1 Nos 305.00 305
b) Labour charges :
1 Skilled Electrician. day 0.067 1 day 565.00 37.855
2 Lineman Electric / Telephone day 0.067 1 day 470.00 31.49
Rate per each 374.00
Add Contractors Profit 0.000% 0.00
Rate per Each 374.00
106 Supply and laying of Cat 6 UTP cable including all taxes etc complete.Make:D Link / AMP / Molex /
Legrand / Krone.
a) Material
8.1.3 a) LAN cat -6 100 M 1 1 One RM 2100 2100
b) Labour charges :
1 Skilled Electrician day 0.5 1 day 565.00 282.5
2 Semi Skilled Electrician day 0.5 1 day 470.00 211.5
3 Helpers day 1 1 day 470.00 470
Sundries LS 1 3.25
C) Cost for 100 RM 3067.25
Rate per Metre 31.00
107 Supply and Fixing of 24 port patch panels etc., complete of Make:D Link / AMP / Molex / Legrand /
Krone
a) Material
8.1.8 24 port patch panels each 1 1 Nos 5800 5800
b) Labour charges :
1 Skilled Electrician day 0.3 1 day 565.00 169.5
2 Semi Skilled Electrician day 0.3 1 day 470.00 141
108 Supply and Fixing of 8 port managable switch etc., complete of Make:CISCO / Net Gear / HP / D link.
a) Material
8.1.5 c) 8 port switch each 1 1 Nos 1100 1100
b) Labour charges :
1 Skilled Electrician day 0.1 1 day 565.00 56.5
2 Semi Skilled Electrician day 0.1 1 day 470.00 47
Cost for Each 1204.00
109 Supply and Fixing of 24 port managable switch etc., complete of Make:CISCO / Net Gear / HP / D link.
a) Material
8.1.5 b) 24 port switch each 1 1 Nos 6000 6000
b) Labour charges :
1 Skilled Electrician day 0.3 1 day 565.00 169.5
2 Semi Skilled Electrician day 0.3 1 day 470.00 141
Cost for Each 6311.00
110 Supply and Fixing of 48 port managable switch etc., complete of Make:CISCO / Net Gear / HP / D link.
a) Material
111 Supply and fixing of 6 U Floor / Wall mounting net work Rack with power spike including all
accessories
a) Material etc., complete. Make:HCL / Vall
8.1.11 a) 6 U Floor / Wall mounting net work each 1 1 Nos 4200 4200
Rack
b) Labour charges :
1 Skilled Electrician day 0.3 1 day 565.00 169.5
2 Semi Skilled Electrician day 0.3 1 day 470.00 141
Cost for Each
4511.00
112 Supply and fixing of 9 U Floor / Wall mounting net work Rack with power spike including all
accessories
a) Material etc., complete. Make:HCL / Vall
8.1.11 b) 9 U Floor / Wall mounting net work each 1 1 Nos 5000 5000
Rack
b) Labour charges :
1 Skilled Electrician day 0.3 1 day 565.00 169.5
2 Semi Skilled Electrician day 0.3 1 day 470.00 141
Cost for Each 5311.00
Add Contractors Profit 0.000% 0.00
113 Supply and fixing of 12 U Floor / Wall mounting net work Rack with power spike including all
accessories
a) Material etc., complete. Make:HCL / Vall
8.1.11 c) 12 U Floor / Wall mounting net work each 1 1 Nos 5800 5800
Rack
b) Labour charges :
Skilled Electrician day 0.3 1 day 565.00 169.5
Semi Skilled Electrician day 0.3 1 day 470.00 141
Cost for Each 6111.00
Add Contractors Profit 0.000% 0.00
Rate per Each 6111.00
114 Supply and fixing of 15 U Floor / Wall mounting net work Rack with power spike including all
accessories
a) Material etc., complete. Make:HCL / Vall
8.1.11 d) 15 U Floor / Wall mounting net work each 1 1 Nos 6600 6600
Rack
b) Labour charges :
1 Skilled Electrician day 0.3 1 day 565.00 169.5
2 Semi Skilled Electrician day 0.3 1 day 470.00 141
Cost for Each 6911.00
Street Lights
115 Supply, Transportation and fixing of 1X400 W MH Flood light luminaire with integral weather proof
diecast alluminium
a) Labour charges housing with IP66 protection with Control Gear Box with all standard accessories
1 Skilled Electrician. 0.25 day 1 day 565.00 141.25
2 Lineman Electric / Telephone 0.25 day 1 day 470.00 117.50
3 Helper (Electrical). 0.25 day 1 day 470.00 117.50
Labour for 1 No 376.25
b) Material
1.5.2 b) Supply of 2.5 Sqmm FRLS / HFFR 2.00 Mtrs 100 Mtrs 2140.00 42.80
Copper cable.
9.4.15 b) 40mm Nominal Bore Medium grade 1.00 Mtrs 1 Mtr 350.00 350.00
G.I.Pipe.
Pipe bending charges LS 40.00
M.S flat and welding charges LS 48.00
3.1.1 a) Supply of 400W MH Street light 1 Nos 1 Nos 5500.00 5500.00
luminaire
3.4.1 l) Supply of 400W MH Lamp with ISI 1 Nos 1 Nos 1300.00 1300.00
mark.
116 Supply, Transportation and fixing of 60 W / 65 W LED LED Street light, Body made of high grade
pressure
a) Labourdie – cast Aluminium alloy with corrosion resistant powder coat, having protective toughened
charges
1 Skilled Electrician. 0.25 day 1 day 565.00 141.25
2 Lineman Electric / Telephone 0.25 day 1 day 470.00 117.50
3 Helper (Electrical). 0.25 day 1 day 470.00 117.50
Labour for 1 No 376.25
b) Material
1.5.2 b) Supply of 2.5 Sqmm FRLS / HFFR 2.00 Mtrs 100 Mtrs 2140.00 42.80
Copper cable.
9.4.15 b) 40mm Nominal Bore Medium grade 1.00 Mtrs 1 Mtr 350.00 350.00
G.I.Pipe.
Pipe bending charges LS 40.00
M.S flat and welding charges LS 50.00
117 Supply, Transportation and fixing of 72 W LED LED Street light, Body made of high grade pressure
die – cast charges
a) Labour Aluminium alloy with corrosion resistant powder coat, having protective toughened glass
1 Skilled Electrician. 0.25 day 1 day 565.00 141.25
2 Lineman Electric / Telephone 0.25 day 1 day 470.00 117.50
3 Helper (Electrical). 0.25 day 1 day 470.00 117.50
Labour for 1 No 376.25
b) Material
1.5.2 c) Supply of 2.5 Sqmm FRLS / HFFR 2.00 Mtrs 100 Mtrs 2140.00 42.80
Copper cable.
9.4.15 b) 40mm Nominal Bore Medium grade 1.00 Mtrs 1 Mtr 350.00 350.00
G.I.Pipe.
Pipe bending charges LS 40.00
M.S flat and welding charges LS 50.00
7059.00
118 Supply, Transportation and fixing of 90 W LED LED Street light, Body made of high grade pressure
die – cast charges
a) Labour Aluminium alloy with corrosion resistant powder coat, having protective toughened glass
1 Skilled Electrician. 0.25 day 1 day 565.00 141.25
2 Lineman Electric / Telephone 0.25 day 1 day 470.00 117.50
3 Helper (Electrical). 0.25 day 1 day 470.00 117.50
Labour for 1 No 376.25
b) Material
1.5.2 c) Supply of 2.5 Sqmm FRLS / HFFR 2.00 Mtrs 100 Mtrs 2140.00 42.80
Copper cable.
9.4.15 b) 40mm Nominal Bore Medium grade 1.00 Mtrs 1 Mtr 350.00 350.00
G.I.Pipe.
Pipe bending charges LS 40.00
M.S flat and welding charges LS 50.00
3.11.1 f) 90 W 1 Nos 1 Nos 8450.00 8450.00
Cost of Material for 1 No 8932.80
Split Airconditioners
Supply, transportation and installation of split AC unit with high wall mounted 100% copper indoor
unit and outdoor condencing unit Hermetically sealed compressor suitable for operation on 230V,
50Hz, 1Phase AC supply capable of performing cooling dehumidifying air circulating and filtering
with cooling andTR
( 1.5 condensing
3 STAR) units with 3.0 mts of copper piping, insulation kit and 4 mts of 3 core
117 copper
1.5 TR 3 Star capable(Voltage
flexible chord range18000
of delivering 160- 264 volts) and cordless remote control with 2 years
BTU/hr
warranty and annual
6.1.1 a) Makes
1.5 Ton: (Carrier
maintenance3 star / Daikin / Blue Star / Hitachi.
rates)
contract. 1 Nos 1 Each 38300 38300.00
6.5.28 Installation charges 1600.00
LS for Hard ware etc.,
( 2.0 TR 2 STAR)
118 2.0 / 1.8 TR 2-3 Star capable of delivering 21600 BTU/hr
6.1.1 b) Makes
2.0 / 1.8: Daikin
TR 2-3/ Star
Thoshiba / O General / Carrier
1 / Blue
NosStar /1Hitachi.
Each 44000 44000.00
6.5.28 Installation charges 1600.00
LS for Hard ware etc.,
Rate per each 45600
Add Contractors Profit 0.000% 0.00
45600.00
Rate per each 45600.00
Stabilizers
121 Supply and erecting fully automatic line voltage stabilizer for operation on input voltage 200 to 250V.
rated for 3 KVA / maximum load and time delay model with Volt meter, selector switch, 6A / 16A
flush type, 5 pin socket for out put and with 3 core flexible chord and 3 pin 6/16A plug top suitable
for refrigerator for continuous operation including cost and conveyance of all mateials and all labour
charges etc., complete. Makes : V-Guard / Real Guard / Uni Stab / ITL
a) Material
6.7.1 c) 3 KVA Stabilizer 1 No 1 each 1900 1900.00
b) Labour Charges
122 Supply and erecting fully automatic line voltage stabilizer for operation on input voltage 200 to 250V.
rated for 4 KVA maximum load and time delay model with Volt meter, selector switch, 6A / 16A
a) Material
6.7.1 d) 4 KVA Stabilizer 1 No 1 each 2500 2500.00
b) Labour Charges
Skilled Electrician 0.1 day 1 day 565 56.50
Helper 0.1 day 1 day 470 47.00
Transportation Charges on Unit Cost 2% 50.00
Rate per Each 2654.00
Add Contractors Profit 0.000% 0.00
2654.00
Hence Rate allowed 2654.00
123 Supply and erecting fully automatic line voltage stabilizer for operation on input voltage 200 to 250V.
rated for 5 KVA maximum load and time delay model with Volt meter, selector switch, 6A / 16A
a) Material
6.7.1 e) 5 KVA Stabilizer 1 No 1 each 3000 3000.00
b) Labour Charges
Skilled Electrician 0.1 day 1 day 565 56.50
Helper 0.1 day 1 day 470 47.00
Transportation Charges on Unit Cost 2% 60.00
Rate per Each 3164.00
Add Contractors Profit 0.000% 0.00
3164.00
Hence Rate allowed 3164.00
1 Supply and Transportation of -------------------- single phase ISI submersible motor pumpset suitable for 4"
Bore well. Makes: Varuna / Flowell / Waterman / Techno / Mahavir /unitek/ Fitwell/ Falcon/ Ellen/
Karvel / LPS/ Duke / Varsha / Ajantha.
5.1.2 0.75 HP 8 Stage 5052 Ele SSR Each 1 1 Nos 13500.00 13500.00
Transportation 0.02 270.00
13770
Add Contractors Profit 0.000% 0.00
13770.00
Rate per Each 13770.00
1 Supply and Transportation of ………………….. double walled corrugated HDPE duct made as per
specification BSEN - 500 86/IS 14930 Part-II with all accessories like couplers, bends, end caps, Ts
etc., complete. Makes: DURA LINE (Dura Guard) / Bajaj / Gamson / Ultra Plus
4.8.1 Outer dia 63mm and Inner dia 51mm Rm 1 1 Rm 117.00 117.00
5052 Ele SSR
Transportation 0.02 2.34
119
Add Contractors Profit 0.000% 0.00
119.34
Rate per Each 119.00
1 Providing and errecting heat shrinkable indoor termination kit for 11 KV HTXLPE insulated armoured
cable-------------with necessary materials etc., complete. Makes : Raychem / Transeal / M Sea
4.7.1 70-95 Sqmm 3 core Ele SSR 4.7.1 Each 1 1 Each 8430.00 8430.00
Transportation 0.02 168.60
8599
Add Contractors Profit 0.000% 0.00
8598.60
Rate per Each 8599.00
Name of the work: Providing Gas Supplying pipeline for Supplying and Centralized
Medical Oxygen to bed for COVID-19 Management in Gandhi Hospital Secunderabab
The Estimate for the work of "Providing Gas Supplying pipeline for supplying and
Centralized Medical Oxygen to bed for Covid-19 Management in Gandhi Hospital Secundrabad"
was technically sanctioned for Rs. 280.60 lakhs and the work was awarded to M/s Shree Bharath
Pharma & Medical Oxygen Distributors, Contractor Hyderabad vide agreement No.
03/TSMSIDC/2020-21 dated: 05.05.2020 for Rs. 2,37,35,822/- the estimate contract value of Rs.
2,37,35,822/- (SSR 2020-21) with stipulated (i.e., by 05.05.2020) for completion of work.
The reasons for the deviations are shown in the remarks column of the comparative
statement against respective items. The following are the main item which is exceeding the
estimate quantities as per site conditions which can be accommodated against savings.
Electrical Work
Supply and Laying of P.V.C casing and
caping (ISI MARK) with double locking
arrangments with groover trunking of size As per site
1 not below 12.5mm height 25mm size with 400 Rm 50.00 20000 condition it is
all accessories, duly sealed at points and excuted
erected on Wall / Ceiling including cost of
all materialsV.Pand39/
labour charges complete.
MB No.540
Makes : Modi with ISI
Supply and Fixing of ISI 25mm outer
dia medium grade with IS:9537 part 3
regid PVC pipe surface on wall/ceiling As per site
2 with all required saddles and all
1210 Rm 65.00 78650 condition it is
accessories and labour charges etc., excuted
complete for run of mains.
Makes : Sudhakar
V.P 39/ MB/ No.540
Finolex / Modi /
VIP / Precision / Universal / Million
Supply
Plast and fixing of 6A switchs - 2
Nos and 6A 3/2 pin socket - 2 Nos As per site
3 Modular type with front cover plate 176 Pts 783.00 137808 condition it is
including all labour charges etc., excuted
complete.
Makes : Legrand
V.P 39/ MB Arteor
No.540 / Schneider
Zen celo / Honeywell Blenge Plus /
Supply
Cabtree& Amarefixing of /16A/6A,
Logus2 in one
Platina.
socket - 2
(Including 3ofNos4Sqmm with
2.016A
Rmt)switch As per site
4 control - 2 Nos modular type with front 688 No's 901.00 619888 condition it is
cover plate including all labour excuted
charges etc., complete.
Makes : Legrand
V.P 39/ MB Arteor
No.540 / Schneider
Zen celo / Honeywell Blenge Plus /
Supply
Cabtree and Amare 3 runs of 4.0 sq
/ Logus mm
Platina.
(56/0.3 mm) (phase neutral
(Including 3of 4Sqmm 2.0 Rmt) and earth) As per site
5 FRLS / HFFR PVC insulated flexible 3713.3 Rm 136.00 505014 condition it is
copper cable in existing conduit pipe excuted
including labour charges etc.,
complete for 16A sockets.
Makes of wiresV.P 39/: MB
Finolex
No.540 / RR kabel /
Havells / APAR EBXL
Supply & run of 5 of 10.0 / KEI / Polycab
Sqmm/
V-Guard / MILLION
(84/0.3mm) (3 phases, neutral and
As per site
earth) FRLS / HFFR PVC insulated
6 120 Rm 442.00 53040 condition it is
flexible copper cable in the existing
excuted
conduict pipe for run of mains from
Power panel board to TPN DB"s with
pin type lugs V.P 39/ and
MB connections
No.540 etc.,
complete. [for PDBs]
Makes of wires :Finolex / RR kabel /
Havells / APAR EBXL / KEI / Polycab /
V-Guard / MILLION