Professional Documents
Culture Documents
Luigi D’Orazio
Network Operation Unit
e-distribuzione S.p.A.
Distribution Network Operation
Distribution network circuit breaker cycle operation
Generally the circuit breaker are set with an operation cycle that foresees 3 closure: First
called “Rapid”, second called “First slow” a Third and, only for overhead lines a Fouth
CP
RG RG RG
RL
RR
CS1 CS2 CS3 CSC
RG
2
Distribution Network Operation
Distribution network circuit breaker cycle operation
Open
time
0,6s 30s 70s 70s
Initially the delay time of rapid closure was 0,3 second, in the second time, 90s this time was
set of 0,4 s until 2010 when was decided to set 0,6 s to increase the probably to self extinction
of the arc during the single phase to ground fault.
3
Distribution Network Operation
First Evolution of Distribution network – Network Automation
The indexes adopted to measure the continuity of supply, depends by the number of customers outages. So, ENEL develop
a particular network automation that, taking into account the neutral grounding method allow to select the fault section of
network rapidly.
a. FNC (Funzione Neutro Compensato) particular technique to select the earth fault on the network grounded
with impedance. This technique foresees the installation of fault detectors and Remote terminal Units directly into the
MV/LV substations to detect the fault and maneuver the disconnectors, using the chronometric coordination.
b. FRG (Funzione Ricerca Guasto) particular technique that allow to select the earth fault on the network with
insulated neutral or grounded with resistor and the multiphase faults per each kind of network. This technique
foresees the installation of fault detectors and Remote terminal Units directly into the MV/LV substations to detect the
fault and maneuver the disconnectors, in coordination with the circuit breaker installed at the beginning of the MV
line.
c. ICS (Interruttore di Cabina Secondaria) with this technique is possible to select the earth fault and short
circuits avoiding the intervention of the circuit breaker installed at the beginning of line. The use of circuit
breaker along the MV lines foresees the installation of a breaker into the MV/LV substations that has to be equipped
with fault detector. The fault detectors has to be set in coordination with all other protection systems present on the line.
4
Distribution Network Operation
First Evolution of Distribution network – Network Automation FNC
The FNC automation foresees the chronometrical coordination between the disconnectors installed
along the MV line and the circuit breaker, to select the earth faults.
5
Distribution Network Operation
First Evolution of Distribution network – Network Automation FNC
Fault automatic switch opening in MV/LV automatic switch opening in automatic switch opening in
t=0 substation MV/LV substation MV/LV substation
(1st level: earth fault in last section or (2nd level: earth fault in third (3rd level: earth fault in second
in branches) section) section)
~
6s
12s 1st breaker opening in HV/MV Last trip (no more reclosing actions) in
substation HV/MV substation
18s
20s (earth fault in first section) (earth fault in first section)
6
Distribution Network Operation
First Evolution of Distribution network – Network Automation FRG
The FRG automation foresees the coordination between the disconnectors installed along the line and the
circuit breaker at the beginning of the MV feeder. After the rapid closure operated by the circuit breaker, if
the the fault is not vanished the circuit breaker opens again and during the waiting for the 2° closure
(generally 30 seconds) the disconnectors openinig themselves.
CP
RG RG RG
RR
CS1 CS2 CS3 CSC
RG
7
Distribution Network Operation
First Evolution of Distribution network – Network Automation FRG
The FRG automation foresees the coordination between the disconnectors installed along the line and the
circuit breaker at the beginning of the MV feeder. After the rapid closure operated by the circuit breaker, if
the the fault is not vanished the circuit breaker opens again and during the waiting for the 2° closure
(generally 30 seconds) the disconnectors openinig themselves.
CP
FD FD FD
CS1 CS2 CS3 CSC
FD
8
Distribution Network Operation
First Evolution of Distribution network – Network Automation FRG
CP
CS1
CS1 CS2 CS3 CSC
9
Distribution Network Operation
First Evolution of Distribution network – Network Automation FRG
CP
CS1
CS1 CS2 CS3 CSC
Automatic
reclosure
10
Distribution Network Operation
First Evolution of Distribution network – Network Automation FRG
CP IniAp IniAp
CS1 CS2 CS3 CSC
Automatic reclosure
11
Distribution Network Operation
First Evolution of Distribution network – Network Automation FRG
CP
IniAp IniAp IniAp
CS1
CS1 CS2 CS3 CSC
Automatic reclosure
12
Distribution Network Operation
First Evolution of Distribution network – Network Automation FRG
CP
RG
Automatic reclosure
13
Distribution Network Operation
First Evolution of Distribution network – Network Automation FRG
Spontaneus
message to
Control centre
CP
BL
14
Distribution Network Operation
First Evolution of Distribution network – Network Automation FRG
CP
BL
3a slow reclosure
automatic opening
15
Distribution Network Operation
First Evolution of Distribution network – Network Automation ICS
The automation of MV line by means ICS allows to select all the faults that occurring on the part of
network following the circuit breaker.
CP
CS1 CSC
RG RR
RL
16
Distribution Network Operation
First Evolution of Distribution network – Network Automation ICS
In case of use of a circuit breaker along the MV line (ICS automation) thermal verification is need to
preserve the integrity of the feeder, in particular for:
Circuit breaker in
CP
RR
RL substation
CS1 CSC
RG Cricuit breaker in
substation 2
In order to calculate the maximum value of specific energy sustainable by cable shields, total time of cycle of
operation of circuit breaker has to be considered. Operative cycle of circuit breaker upstream of cable line is realized
by one rapid closure more two slow closure, conventionally 0,96 s (0,25 + 0,07 + 0,25 + 0,07 + 0,25 + 0,07).
17
Distribution Network Operation
First Evolution of Distribution network – Improving of continuity of
supply - DURATION
Minutes of interruption
(Long) SAIDI
180
160
140
120
100
80 159
60
128
103
91
40
73
63
49,6 48,5 49,6 48,2 45,1 42,2 44,7
20 40,7 38,9 44,7 36,7 43,2
0
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
Years
18
Distribution Network Operation
First Evolution of Distribution network – Improving of
continuity of supply - NUMBER
Number of interruption
(Momentary + Long) SAIFI
6
4,89 4,97
2 4,15
3,66 3,58 3,53
3,35 3,36 3,16 3,3
0
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
Years
19
Distribution Network Operation
Second Evolution of Distribution network – Network
automation
SFS - proposal
INT ICS
CP
Substations
FAULT
Substations
Substations
Substations
Substations
Substations
The Index per each configuration can be calculated with following math expressions:
27
Distribution Network Operation
Second Evolution of Distribution network –
Experimentation of some new network automation
technique: Rapid FNC/FRG/ICS
To select the earth fault rapidly and avoid to stress the earth plants of substations, ENEL is
testing a “Rapid” FNC using the circuit breakers into the MV/LV substations instead of switch
(disconnectors).
Earth fault
5” Border
4” 3” < 2” disconnector
CS1 CS2 CS3 CSC
ICS Border
disconnector
CS1 CS2 CS3 CSC
29
Step 2: Devices for Network Monitoring
MV Field Devices – Indoor solution
I12
Connectors
Fault
Detector
MV cables
30
Step 2: Devices for Network Monitoring
MV Field Devices – Indoor solution
Output
Input:
TOmo – omopolar current
TA4,12 – phase currents Input
V4,8,12 – phase voltages
Output:
T51 – max current
T67 – directional earth fault
TPV – voltage presence
31
Step 2: Devices for Network Monitoring
MV Field Devices – Indoor solution
Elettronics GSM/DCS
Iomo Module
I4
I12
MV Cables R S T Connectors
RGDAT
MV cables
OMOPOLAR
VOLTAGE
SENSORS Cables for remote
TOROIDAL
TRANSFORMERS
control
PHASE TOROIDAL
TRANSFORMERS
32
Global Infrastructure and Networks
Totale 73 Mn Customers
63,000 Impegnati
1 M substations for all Enel Grids worldwide
*market share in termini di client finali
Infrastructure and Networks Italy
Organization
Primary source of
4 forecasting until 72 h
Website before
2
Continuos
Feedback and Mitigate
monitoring
Weather variables with
3 possible negative
Planning impact or outages on
the networks.
The task force in a
preventive way,
• Meteo-web - EPSON
before the events
Control Room- CO
SSG’S Social Media Web Channels
24/7
Social Channels
Digital Channels
Externals
• Terna «TSO»
• Coordination of Risk condition of the TSO
• Defense plan of the electric system
• RIGEDI.
• BME.
• EAC.
• RICALO.
• PESSE.
• Potential risk related with Regions, population, Traffic and highways at national 4
3
level
THANKS
Distribution Network Operation
First Evolution of Distribution network – Quality of
Service
At the end of 90s the Italian Electrical Market changed deeply. It was created the Energy
Authority and it introduced a Regulation System to improve the Quality of Service
evaluated through the indexes of continuity of supply.
On the following slides are shown the rules like calculate the SAIDI and SAIFI. The method of
calculation and the parameters that determine the final value of the indexes, had
conditioned strongly the strategy of development and operation of network.
45
Distribution Network Operation
First Evolution of Distribution network – Classification of
interruption
The electrical interruptions, like defined on the EN 50160 standard, can be classified by
means them duration. It is possible recognize three kind of interruptions:
The system (network) is interrupted when the value of voltage applied to the components is
lower than 5 % of the reference value.
Taking
Taking into
into account
account the
the
standardized
standardized definitions
definitions was
was
determined
determined the
the rules
rules like
like
evaluate the
evaluate the SAIDI
SAIDI and
and SAIFI.
SAIFI.
46
Distribution Network Operation
First Evolution of Distribution network – SAIDI
calculation
SAIDI is calculated through the following algorithm:
where all the outages contribute to the summation Σ(Ni*Ri), being Ri the i-th outage duration
and Ni the number of affected customers.
Note that a single fault event generally originates several addenda of the summation
because various groups of customers are affected by different outage durations; thus, each
group of customers experiencing the same outage duration must be considered in the
algorithm separately. NT is the total number of customers in the system for which the index is
calculated.
The SAIDI can be calculated either as aggregate of all voltage levels or only at selected
The
The SAIDI
SAIDI
voltage is expressed
levels.is expressed inin minutes
minutes per
per customers
customers per per year
year
47
Distribution Network Operation
First Evolution of Distribution network – SAIFI
calculation
SAIFI is calculated as:
where λi is the number of interruption per the same group of customer, Νi is the total
amount of customers experiencing the same number of interruptions. They are divided
to NT that represent the total amount of customers in the system for which the index
is calculated.
The SAIFI
The SAIFI is
is measured
measured in
in units
units of
of interruptions
interruptions per
per customer
customer per
per
year
year
48
Distribution Network Operation
First Evolution of Distribution network – new
grounding system
Two Petersen Coil installed into the HV/MV substation (fixed + tunable +
parallel resistor)
49
Distribution Network Operation
First Evolution of Distribution network – new
grounding system
Two Petersen Coil installed into the HV/MV substation (fixed coil +
neutral former).
TFN
Fixed coil
50