You are on page 1of 48

Operation of Distribution Network

Traditional and evolved approach of grid operation

Luigi D’Orazio
Network Operation Unit
e-distribuzione S.p.A.
Distribution Network Operation
Distribution network  circuit breaker cycle operation
Generally the circuit breaker are set with an operation cycle that foresees 3 closure: First
called “Rapid”, second called “First slow” a Third and, only for overhead lines a Fouth

CP
RG RG RG
RL
RR
CS1 CS2 CS3 CSC

RG

2
Distribution Network Operation
Distribution network  circuit breaker cycle operation

Typical circuit breaker cycle operation

1° fast recl. 1° slow recl. 2° slow recl. 3° slow recl.


Circuit breaker
Close

Open
time
0,6s 30s 70s 70s

Initially the delay time of rapid closure was 0,3 second, in the second time, 90s this time was
set of 0,4 s until 2010 when was decided to set 0,6 s to increase the probably to self extinction
of the arc during the single phase to ground fault.

3
Distribution Network Operation
First Evolution of Distribution network – Network Automation
The indexes adopted to measure the continuity of supply, depends by the number of customers outages. So, ENEL develop
a particular network automation that, taking into account the neutral grounding method allow to select the fault section of
network rapidly.

In particular ENEL implement on the network two particular method of automation:

a. FNC (Funzione Neutro Compensato)  particular technique to select the earth fault on the network grounded
with impedance. This technique foresees the installation of fault detectors and Remote terminal Units directly into the
MV/LV substations to detect the fault and maneuver the disconnectors, using the chronometric coordination.
b. FRG (Funzione Ricerca Guasto)  particular technique that allow to select the earth fault on the network with
insulated neutral or grounded with resistor and the multiphase faults per each kind of network. This technique
foresees the installation of fault detectors and Remote terminal Units directly into the MV/LV substations to detect the
fault and maneuver the disconnectors, in coordination with the circuit breaker installed at the beginning of the MV
line.
c. ICS (Interruttore di Cabina Secondaria)  with this technique is possible to select the earth fault and short
circuits avoiding the intervention of the circuit breaker installed at the beginning of line. The use of circuit
breaker along the MV lines foresees the installation of a breaker into the MV/LV substations that has to be equipped
with fault detector. The fault detectors has to be set in coordination with all other protection systems present on the line.
4
Distribution Network Operation
First Evolution of Distribution network – Network Automation FNC

The FNC automation foresees the chronometrical coordination between the disconnectors installed
along the MV line and the circuit breaker, to select the earth faults.

20” 13” 7” 2” Border


disconnector
CS1 CS2 CS3 CSC

Automatic opening of Switches with a delay


increasing from the end to the beginning of the line

5
Distribution Network Operation
First Evolution of Distribution network – Network Automation FNC

Time graph to summarize the coordination for FNC automation

Fault automatic switch opening in MV/LV automatic switch opening in automatic switch opening in
t=0 substation MV/LV substation MV/LV substation

(1st level: earth fault in last section or (2nd level: earth fault in third (3rd level: earth fault in second
in branches) section) section)

1st breaker 2nd breaker 3rd breaker


0,30 reclosing in 0,30 reclosing in reclosing in 0,30
HV/MV HV/MV HV/MV
substation substation substation

0,4s 30s TN=70s

~
6s
12s 1st breaker opening in HV/MV Last trip (no more reclosing actions) in
substation HV/MV substation
18s
20s (earth fault in first section) (earth fault in first section)

6
Distribution Network Operation
First Evolution of Distribution network – Network Automation FRG

The FRG automation foresees the coordination between the disconnectors installed along the line and the
circuit breaker at the beginning of the MV feeder. After the rapid closure operated by the circuit breaker, if
the the fault is not vanished the circuit breaker opens again and during the waiting for the 2° closure
(generally 30 seconds) the disconnectors openinig themselves.

CP
RG RG RG
RR
CS1 CS2 CS3 CSC

RG

7
Distribution Network Operation
First Evolution of Distribution network – Network Automation FRG

The FRG automation foresees the coordination between the disconnectors installed along the line and the
circuit breaker at the beginning of the MV feeder. After the rapid closure operated by the circuit breaker, if
the the fault is not vanished the circuit breaker opens again and during the waiting for the 2° closure
(generally 30 seconds) the disconnectors openinig themselves.

CP
FD FD FD
CS1 CS2 CS3 CSC

FD

Automatic opening of Switches

8
Distribution Network Operation
First Evolution of Distribution network – Network Automation FRG

CP

CS1
CS1 CS2 CS3 CSC

2nd slow reclosure

9
Distribution Network Operation
First Evolution of Distribution network – Network Automation FRG

CP

CS1
CS1 CS2 CS3 CSC

Automatic
reclosure

10
Distribution Network Operation
First Evolution of Distribution network – Network Automation FRG

CP IniAp IniAp
CS1 CS2 CS3 CSC

Automatic reclosure

11
Distribution Network Operation
First Evolution of Distribution network – Network Automation FRG

CP
IniAp IniAp IniAp
CS1
CS1 CS2 CS3 CSC

Automatic reclosure

12
Distribution Network Operation
First Evolution of Distribution network – Network Automation FRG

CP

CS1 CS2 CS3 CSC

RG

Automatic reclosure

13
Distribution Network Operation
First Evolution of Distribution network – Network Automation FRG

Spontaneus
message to
Control centre
CP

CS1 CS2 CS3 CSC

BL

14
Distribution Network Operation
First Evolution of Distribution network – Network Automation FRG

CP

CS1 CS2 CS3 CSC

BL

3a slow reclosure
automatic opening

15
Distribution Network Operation
First Evolution of Distribution network – Network Automation ICS

The automation of MV line by means ICS allows to select all the faults that occurring on the part of
network following the circuit breaker.

CP

CS1 CSC

RG RR
RL

16
Distribution Network Operation
First Evolution of Distribution network – Network Automation ICS
In case of use of a circuit breaker along the MV line (ICS automation) thermal verification is need to
preserve the integrity of the feeder, in particular for:

a. the cable regarding the coordination to select the short circuits;


b. the shield of cable regarding the coordination to select the cross country faults;

Circuit breaker in
CP
RR
RL substation
CS1 CSC

RG Cricuit breaker in
substation 2

In order to calculate the maximum value of specific energy sustainable by cable shields, total time of cycle of
operation of circuit breaker has to be considered. Operative cycle of circuit breaker upstream of cable line is realized
by one rapid closure more two slow closure, conventionally 0,96 s (0,25 + 0,07 + 0,25 + 0,07 + 0,25 + 0,07).
17
Distribution Network Operation
First Evolution of Distribution network – Improving of continuity of
supply - DURATION

Minutes of interruption
(Long) SAIDI
180

160

140

120

100

80 159

60
128
103
91
40
73
63
49,6 48,5 49,6 48,2 45,1 42,2 44,7
20 40,7 38,9 44,7 36,7 43,2

0
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017

Years

18
Distribution Network Operation
First Evolution of Distribution network – Improving of
continuity of supply - NUMBER

Number of interruption
(Momentary + Long) SAIFI
6

4,89 4,97
2 4,15
3,66 3,58 3,53
3,35 3,36 3,16 3,3

0
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
Years

19
Distribution Network Operation
Second Evolution of Distribution network – Network
automation

SMART FAULT SELECTION

Definitive opening of circuit


breaker in case of non transient
fault
Rapid clousure

SFS - proposal
INT ICS

CP

ICS ICS Comando chiusura


Comando apertura OdM di confine su
dorsale

Selection of the part of network within two automatized nodes


Distribution Network Operation
Second Evolution of Distribution network – Network automation

SMART FAULT SELECTION


HV HV grid
grid
HV/MV HV/MV
station station
TR TR
HUB
Protezioni Protezioni
A3 A3

Substations
FAULT

RGDM RGDM RGDM RGDM RGDM RGDM

Customers Customers Customers Customers Customers Customers


21
Distribution Network Operation
Second Evolution of Distribution network – Network automation

SMART FAULT SELECTION


HV HV grid
grid
HV/MV HV/MV
station station
TR TR
HUB
Protezioni Protezioni
A3 A3

Substations

RGDM RGDM RGDM RGDM RGDM RGDM

Customers Customers Customers Customers Customers Customers


22
Distribution Network Operation
Second Evolution of Distribution network – Network automation

SMART FAULT SELECTION


HV HV grid
grid
HV/MV HV/MV
station station
TR TR
HUB
Protezioni Protezioni
A3 A3

Substations

RGDM RGDM RGDM RGDM RGDM RGDM

Customers Customers Customers Customers Customers Customers


23
Distribution Network Operation
Second Evolution of Distribution network – Network automation

SMART FAULT SELECTION


HV HV grid
grid
HV/MV HV/MV
station station
TR TR
HUB
Protezioni Protezioni
A3 A3

Substations

RGDM RGDM RGDM RGDM RGDM RGDM

Customers Customers Customers Customers Customers Customers


24
Distribution Network Operation
Second Evolution of Distribution network – Network automation

SMART FAULT SELECTION


HV HV grid
grid
HV/MV HV/MV
station station
TR TR
HUB
Protezioni Protezioni
A3 A3

Substations

RGDM RGDM RGDM RGDM RGDM RGDM

Customers Customers Customers Customers Customers Customers


25
Distribution Network Operation
Second Evolution of Distribution network – Network automation

SMART FAULT SELECTION


HV HV grid
grid
HV/MV HV/MV
station station
TR TR
HUB
Protezioni Protezioni
A3 A3

Substations

RGDM RGDM RGDM RGDM RGDM RGDM

Customers Customers Customers Customers Customers Customers


26
Distribution Network Operation
Second Evolution of Distribution network – Improving of
continuity of supply in terms of duration and number

The Index per each configuration can be calculated with following math expressions:

Continuity of supply index (number or Continuity of supply index (number or


duration) calculated for closed-ring scheme duration) calculated for radial scheme per
per each single line each single line

27
Distribution Network Operation
Second Evolution of Distribution network –
Experimentation of some new network automation
technique: Rapid FNC/FRG/ICS
To select the earth fault rapidly and avoid to stress the earth plants of substations, ENEL is
testing a “Rapid” FNC using the circuit breakers into the MV/LV substations instead of switch
(disconnectors).

Earth fault

5” Border
4” 3” < 2” disconnector
CS1 CS2 CS3 CSC

Automatic opening of Circuit Breaker with a delay


increasing from the end to the beginning of the line 28
Distribution Network Operation
Second Evolution of Distribution network –
Experimentation of some new network automation
technique: Rapid FNC/FRG/ICS
In addition circuit breaker installed on the middle of line, it will be able to select the
multiphase faults in ICS automation with complete operation cycle (RR + RL) and in
coordination with the CS3 installed into CS3 in FRG technique.
Short circuit

ICS Border
disconnector
CS1 CS2 CS3 CSC

Automatic opening of Circuit Breaker installed at the middle of MV feeder.


The circuit breaker will operate the Rapid closure and 1 st slow closure in
coordination with switch installed in CS3.

29
Step 2: Devices for Network Monitoring
MV Field Devices – Indoor solution

Modular MV Switchboard RTU - UP

Line Line Line TR


Module Module Module Batt. 24 V
Module 230 Vca +
Charger
Vo Vo
61
Elettronics GSM/DCS
Iomo Module
I4 257
Io

I12
Connectors
Fault
Detector
MV cables

Cables for remote control

30
Step 2: Devices for Network Monitoring
MV Field Devices – Indoor solution

Output

Input:
TOmo – omopolar current
TA4,12 – phase currents Input
V4,8,12 – phase voltages

Output:
T51 – max current
T67 – directional earth fault
TPV – voltage presence
31
Step 2: Devices for Network Monitoring
MV Field Devices – Indoor solution

MV Motorized Switchboard Remote Terminal Unit - UP

Modular MV Switchboard RTU - UP

Line Line Line TR


Module Module Module Batt. 24 V
Module 230 Vca +
RGDAT Charger
Vo

Elettronics GSM/DCS
Iomo Module
I4
I12
MV Cables R S T Connectors

RGDAT

MV cables
OMOPOLAR
VOLTAGE
SENSORS Cables for remote
TOROIDAL
TRANSFORMERS
control
PHASE TOROIDAL
TRANSFORMERS

32
Global Infrastructure and Networks

Italy 1° DSO (85%)


Colombia2° DSO Brasil 2° DSO (26%) 227 TWh distributed
(22%)
14 TWh distributed
energy
79 TWh distributed energy energy
17 Mn customers
3 Mn customers
Peru 2° DSO
32 Mn customers
(20%)
8 TWh distributed
energy Spain 1° DSO
1.4 Mn customers (42%)
Chile2° DSO 109 TWh distributed
(33%)
energy
16 TWh distributed Romania2° DSO
Argentina 2° DSO (17%)
12 Mn clienti (36%)
energy
15 TWh distributed
1.8 Mn customers 19 TWh distributed energy
energy
2.5 Mn customers
2.9 Mn customers

Totale 73 Mn Customers
63,000 Impegnati
1 M substations for all Enel Grids worldwide
*market share in termini di client finali
Infrastructure and Networks Italy
Organization

• Central Functions (O&M, Network


Development, Network Commercial
Operations, Network Technologies, HSE and
Q)
• 6 Areas (North-west, Nord, Central-Nord,
Adriatical, Lazio-Sicily, South)
• 28 O&M Control Centers
• 1 O&M Control Room
• 57 Local Districts 3
4
Italy Network's Control and Monitoring
Como
Brescia Udine
Milano
Novara
Verona HV • 2,300 HV/MV Substations
Torino Modena
Mestre HV
150 • • 2,300 HV/MV
1,300 Substations
HV customers
Bologna 150
kV • • 1,300
125 HV
HV customers
DGs – 1,7 GW
Genova
Firenze kV
132 • 170 HV DGs – 5,1 GW
Ancona
Livorno Perugia 132
kV
L'Aquila kV • 455,000 MV/LV Substations
Viterbo
Roma Campobasso MV • • 455,000
354.000 km lines
MV/LV (53%
Substations
Cagliari
Latina MVkV
15 • 354.000 km lines (53%
overhead)
Potenza Bari
Napoli
Salerno
15
20kV
kV • overhead)
100,000 MV customers
Lecce
20 V • • 111,000 MV customers
25,700 MV DGs – 19,5 GW
• 25,500 MV DGs– 19,5 GW
Catanzaro
Palermo
• 797,000 km lines (66%
LV
Catania
LV V overhead)
• 790,000 km lines (66%
230
230 • overhead)
32 million customers
28 O&M Control Centers  Control - 400VV • • 32709,000
million customers
400 V LV DGs – 7,1 GW
Operation & Monitoring • 702,000 LV DGs – 7,5 GW
One national Control Room in Rome 
National Monitoring
Control Room  Roma
• Real-time monitoring Italy‘s Network (national level)

➢ Monitoring of events in normal conditions,


emergency or crisis conditions, according to the
current emergency plan.

➢ Geo-referenced in real time of faults with


impact on the HV-MV-LV networks

➢ Interface with Institutions and Civil authorities


during the emergencies and risk condition on
the Transmission and Generation Systems.

➢ Forecast and Now casting of Weather


conditions as critical events such as:
Earthquake, Floods, Snow, etc.

➢ Calculation of service quality indicators such as:


SAIFI, SAIDI
Global monitoring of countries with ENEL presence as DSO
Control Centers
28 Control Centers in • Monitoring and coordination of the Operation in real time at
local level:
Italy
➢ Analyzing signals and alarms from remote control and
<Scada> systems

➢ Maneuvers on the HV-MV-LV network, for Preventive and


corrective activities, in order to do maintenance or
restore the service

➢ Real-time control of all Primary Substations.


ScattoP 67
CP
CS1 CS2 CS3 CSC
➢ Managing of incoming calls for outages reporting

➢ Weather conditions on the interest area

➢ Interface with Institutions and Civil authorities during


the emergencies and risk condition on the Transmission
and Generation network.

➢ Reports to the Rome’s National Control Room


Network’s Performance
24/7
Control
Primary Substation Secondary Substation
(SCADA) 
STUX /STM / STB
Allows the maneuver's
Monitoring • 35% Remote Control with remote control
• 100% Remote Control
• 450,000 MV/LV devices on network,
• 2,300 HV/MV/MV
• 258,000+ Remote and monitoring of the
control Devices network’s status of
GD LV Feeders HV/MV/LV.
• 734,800+ Prosumers • 17,000+ LV Breakers
• 27 GW capacity Manages and monitors
SCADA/DMS (STM-STUX-STB) the automatic, remote
and manual activities
in case of failure or
preventive activities
28 CO ▪ 18 HV and MV on the network.
▪ 10 MV
▪ 28 BT
Weather Forecast
24/7
1
• PROTEZIONE Civile • SIRF Tag

Primary source of
4 forecasting until 72 h
Website before
2
Continuos
Feedback and Mitigate
monitoring
Weather variables with
3 possible negative
Planning impact or outages on
the networks.
The task force in a
preventive way,
• Meteo-web - EPSON
before the events
Control Room- CO
SSG’S  Social Media  Web Channels
24/7

Social Channels

Digital Channels

24 h 7 @ Direct communication with update


and information in real time about the network
Status, as Registers of User’s requirements.
Operational Coordination - Institutional Communication

Externals
• Terna «TSO»
• Coordination of Risk condition of the TSO
• Defense plan of the electric system
• RIGEDI.
• BME.
• EAC.
• RICALO.
• PESSE.

• Coordination with Civil Protection :


• Potential risk related with weather forecast.
• Manage relation for crisis events

• Coordination with Autostrade/Anas - Civil Authorities (MISE-Presidenti Regioni


– Sindaci):

• Potential risk related with Regions, population, Traffic and highways at national 4
3
level
THANKS
Distribution Network Operation
First Evolution of Distribution network – Quality of
Service
At the end of 90s the Italian Electrical Market changed deeply. It was created the Energy
Authority and it introduced a Regulation System to improve the Quality of Service
evaluated through the indexes of continuity of supply.

At now each DSO is monitored by through the two following indexes:

a. SAIDI  System Average Interruption Duration Index


b. SAIFI  System Average Interruption Frequency Index

On the following slides are shown the rules like calculate the SAIDI and SAIFI. The method of
calculation and the parameters that determine the final value of the indexes, had
conditioned strongly the strategy of development and operation of network.

45
Distribution Network Operation
First Evolution of Distribution network – Classification of
interruption
The electrical interruptions, like defined on the EN 50160 standard, can be classified by
means them duration. It is possible recognize three kind of interruptions:

a. Long  T > 3 minutes;


b. Short  1 second < T ≤ 3 minutes;
c. Transient  T ≤ 1 second.

The system (network) is interrupted when the value of voltage applied to the components is
lower than 5 % of the reference value.

  Taking
Taking into
into account
account the
the
standardized
standardized definitions
definitions was
was
determined
determined the
the rules
rules like
like
evaluate the
evaluate the SAIDI
SAIDI and
and SAIFI.
SAIFI.
46
Distribution Network Operation
First Evolution of Distribution network – SAIDI
calculation
SAIDI is calculated through the following algorithm:

where all the outages contribute to the summation Σ(Ni*Ri), being Ri the i-th outage duration
and Ni the number of affected customers.
Note that a single fault event generally originates several addenda of the summation
because various groups of customers are affected by different outage durations; thus, each
group of customers experiencing the same outage duration must be considered in the
algorithm separately. NT is the total number of customers in the system for which the index is
calculated.
The SAIDI can be calculated either as aggregate of all voltage levels or only at selected
The
The SAIDI
SAIDI
voltage is expressed
levels.is expressed inin minutes
minutes per
per customers
customers per per year
year

47
Distribution Network Operation
First Evolution of Distribution network – SAIFI
calculation
SAIFI is calculated as:

where λi is the number of interruption per the same group of customer, Νi is the total
amount of customers experiencing the same number of interruptions. They are divided
to NT that represent the total amount of customers in the system for which the index
is calculated.

The SAIFI
The SAIFI is
is measured
measured in
in units
units of
of interruptions
interruptions per
per customer
customer per
per
year
year

48
Distribution Network Operation
First Evolution of Distribution network – new
grounding system
Two Petersen Coil installed into the HV/MV substation (fixed + tunable +
parallel resistor)

49
Distribution Network Operation
First Evolution of Distribution network – new
grounding system
Two Petersen Coil installed into the HV/MV substation (fixed coil +
neutral former).

TFN
Fixed coil

50

You might also like