Start

Plan Review, Permit


Material
T.O Engineer and Inspection Shop Drawing
submittal Process

No MS Document
Approved No
Approved

Yes
Resubmit Resubmit

Drawing
Material Approved From
Civil Defense
Procurement Civil Defense
T.O Engineer Approved

Material
T.O Engineer Internal P.O Document
Request

Survey Engineer Survey


Internal Request

Site Engineer
FF First Fix Release A/B

Q.C Engineer

Pipe Work
Site Engineer Installation and Internal Request
test

Site Engineer Internal Request


FF -Second Fix
Q.C Engineer

Release C&D

Site Engineer Equipment and


valve
Installation
Q.C Engineer
Internal Request

Survey Engineer Survey

Internal Request

Site Engineer
Final Fix
Q.C Engineer Installation
Internal Request

FF testing Release E
Q.C Engineer

Testing Report

Final
Q.C Engineer
Commissioning

Snag List

End