Plan for Co-Firing Test

Complete activity of 100 hrs. incorporating both GE and EPQL Timelines.


Co-Firing Plan can be clubbed into three sections:
1st Borescope – 37 hrs.
Co-Firing Test Points run – 14 hrs.
2nd Borescope – 49 hrs.

Following scenarios can be followed for executing this activity:

August September
13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

If Plant Standby for any 5 days - (Zero FO)


1 - Opportunity Based:

Test Points run before SO start – (37 hrs. FO)


2- Optimized Plan:

Zero FO – (14 hrs. Test Energy)


3- Within Scheduled Outage:

www.engro.com 1
Timeline
Time
GE Parallel Activities
(hrs.)
Fuel change-over
Test Run at part load at Unit Shutdown 1
Test
GT Shutdown 2 Back up as running code & as running
constant.
Cooling time / Turning Gear for handover for BI 16 Compare modified code & as running
1st BI 14 Pressure transmitters calibration /
1st BI
8 verification.
GT Zero Speed / Software download / upload
(in parallel) Downloading updated m6b file.
Turning Gear 4
GT Start-up 1
Ramp machine to 70% load 4 Deploy trends and forcing as per test plan.
Conduct Co-Firing & Mix fuel operation as
Test Points Run
Cofiring test points operation 10 per test plan.
Collect & upload test trends for review.
Shutdown 2
Cooling time / Turning Gear for handover for BI 16
Revert to pre test software, download
2nd BI 14
2nd BI backed up code to the Mark VI panel
TG / Offline water wash 12
Turning Gear 4
GT Start-up 1
www.engro.com 2