THE DESIGN, PROCUREMENT, FURNISHING AND EXECUTION OF ETHIOPIAN SKYLIGHT 5-STAR HOTEL PHASE -II PROJECT
Project No. & Title: Ref: 697
ON SITE STAFF & LABOUR RECORD Day: Sunday Date: 2021/9/5 ON SITE PLANT & EQUIPMENT RECORD
No. Trade No. Hrs No. Trade No. Hrs No. Category No. Hrs No. Category No.
2 DGM 1 9 √ 2 Lorry 1 9
12 Office Staff 7 9 5
14 7
15 8
4 Electrical cable installation for the the roof E,F,H block 25%
REMARKS 7 Fan coil branch pipe installation for the "E""F""H" block Following
8 AC water supply main pipe installation E1,balance valve installation "E"9 25%
The confirmed cases of COVID-19 in Ethiopian have seriously affected
the project progress .And it has resulted the mobilization delay of chinese 9 Firefighting branch pipe installation for the financial room H1,firefighting hydrant installation for H9, 25%
1
technican and local labor based the site progress and the local workers
10 Firefighting spray branch pipe installation for E8,H4 25%
have decreased rapidly at site.
11 Ventilation damper and sound reducer installation for B1 25%
Working time of the local workers has to be decreased from 9 hours to 7 hours Fan coil installation and fresh air duct installation for guest room H8 25%
for one day due to transportation problem caused by COVID -19 and they also 12
2
need more payments such as special transportation fee for their work. AC fresh air duct installation for the daily restaurant and leisure area 1F. 25%
13
3 Covid-19 case appears on the project camp , this seriously affect the project
14 Aluminium frame installation and glass installation for guest room "E,F,H" block 25%
progress.
15 Steel bracket installation and waterproof primer applicationfor the west elevation "E" block Following
17 Wire mesh installation for the toilet for the plastering. Following
18 light steel frame for the dry wall and rock rool fill Following
Submission: Noted: