Location Of

Grade/Class Production Day Project Name Age Date of Testing


Sampling

C25 Mpa CASE-C 20-07-2021 Auxiliary boiler Electrical B/D 3 23-07-2021

C25 Mpa CASE-C 20-07-2021 Auxiliary boiler Electrical B/D 7 27-07-2021

C25 Mpa CASE-C 20-07-2021 Auxiliary boiler Electrical B/D 28 17-08-2021

Discharge box
C 21 Mpa(Type B) 20-07-2021 27th span 7 27-07-2021
culvert
Discharge box
C 21 Mpa(Type B) 20-07-2021 27th span 28 17-08-2021
culvert
Fire water
C25 Mpa CASE-C 20-07-2021 booster pump WTP 7 27-07-2021
house
Fire water
C25 Mpa CASE-C 20-07-2021 booster pump WTP 28 17-08-2021
house
C25 Mpa CASE-C 20-07-2021 CV06,F7 Coal yard 7 27-07-2021

C25 Mpa CASE-C 20-07-2021 CV06,F7 Coal yard 28 17-08-2021

C 30 Mpa(Type B) 20-07-2021 Boiler-02 Pedestal 7 27-07-2021

C 30 Mpa(Type B) 20-07-2021 Boiler-02 Pedestal 28 17-08-2021

C25 Mpa CASE-C 20-07-2021 GL:1-3/A-G Power house-01 3 23-07-2021

C25 Mpa CASE-C 20-07-2021 GL:1-3/A-G Power house-01 5 25-07-2021

C25 Mpa CASE-C 20-07-2021 GL:1-3/A-G Power house-01 7 27-07-2021


Location Of
Grade/Class Production Day Project Name Age Date of Testing
Sampling

C25 Mpa CASE-C 20-07-2021 GL:1-3/A-G Power house-01 28 17-08-2021

C25 Mpa CASE-C 20-07-2021 GL:1-3/A-G Power house-01 7 27-07-2021

C25 Mpa CASE-C 20-07-2021 GL:1-3/A-G Power house-01 28 17-08-2021

C25 Mpa CASE-C 20-07-2021 GL:1-3/A-G Power house-01 7 27-07-2021

C25 Mpa CASE-C 20-07-2021 GL:1-3/A-G Power house-01 28 17-08-2021


Location Of
Grade/Class Production Day Project Name Age Date of Testing
Sampling

C25 Mpa CASE-C 22-07-2021 Chemical shed-01 WWTP 3 25-07-2021

C25 Mpa CASE-C 22-07-2021 Chemical shed-01 WWTP 7 29-07-2021

C25 Mpa CASE-C 22-07-2021 Chemical shed-01 WWTP 28 19-08-2021

C 30 Mpa(Type B) 22-07-2021 Boiler-02 Pedestal 7 29-07-2021

C 30 Mpa(Type B) 22-07-2021 Boiler-02 Pedestal 28 19-08-2021

C25 Mpa CASE-C 22-07-2021 Pump shed-02 WTP 7 29-07-2021

C25 Mpa CASE-C 22-07-2021 Pump shed-02 WTP 28 19-08-2021

Coal portal
C25 Mpa CASE-C 22-07-2021 CV05-F2 7 29-07-2021
reclaimer
Coal portal
C25 Mpa CASE-C 22-07-2021 CV05-F2 28 19-08-2021
reclaimer

C25 Mpa CASE-C 22-07-2021 Ball strainer-02 Power block 7 29-07-2021

C25 Mpa CASE-C 22-07-2021 Ball strainer-02 Power block 28 19-08-2021

C25 Mpa CASE-C 22-07-2021 Auxiliary boiler F1 7 29-07-2021

C25 Mpa CASE-C 22-07-2021 Auxiliary boiler F1 28 19-08-2021

C25 Mpa CASE-C 22-07-2021 Auxiliary boiler F1 7 29-07-2021


Location Of
Grade/Class Production Day Project Name Age Date of Testing
Sampling

C25 Mpa CASE-C 22-07-2021 Auxiliary boiler F1 28 19-08-2021

C 35 Mpa(Type B) 22-07-2021 GL:04 STG-D-4 Power house-01 3 25-07-2021

C 35 Mpa(Type B) 22-07-2021 GL:04 STG-D-4 Power house-01 5 27-07-2021

C 35 Mpa(Type B) 22-07-2021 GL:04 STG-D-4 Power house-01 7 29-07-2021

C 35 Mpa(Type B) 22-07-2021 GL:04 STG-D-4 Power house-01 28 19-08-2021


Location Of
Grade/Class Production Day Project Name Age Date of Testing
Sampling

C25 Mpa CASE-C 23-07-2021 Pump shed-01 WTP 3 26-07-2021

C25 Mpa CASE-C 23-07-2021 Pump shed-01 WTP 7 30-07-2021

C25 Mpa CASE-C 23-07-2021 Pump shed-01 WTP 28 20-08-2021

C25 Mpa CASE-C 23-07-2021 GL:16-17/F-G BFP Power house-02 3 26-07-2021

C25 Mpa CASE-C 23-07-2021 GL:16-17/F-G BFP Power house-02 5 28-07-2021

C25 Mpa CASE-C 23-07-2021 GL:16-17/F-G BFP Power house-02 7 30-07-2021

C25 Mpa CASE-C 23-07-2021 GL:16-17/F-G BFP Power house-02 28 20-08-2021

Centrifuge
C25 Mpa CASE-C 23-07-2021 WWTP 3 26-07-2021
building
Centrifuge
C25 Mpa CASE-C 23-07-2021 WWTP 5 28-07-2021
building
Centrifuge
C25 Mpa CASE-C 23-07-2021 WWTP 7 30-07-2021
building
Centrifuge
C25 Mpa CASE-C 23-07-2021 WWTP 28 20-08-2021
building
C3&C4 pedestal
C 35 Mpa(Type B) 23-07-2021 Power house-01 3 26-07-2021
GL:5-6/B-D STG
C3&C4 pedestal
C 35 Mpa(Type B) 23-07-2021 Power house-01 5 28-07-2021
GL:5-6/B-D STG
C3&C4 pedestal
C 35 Mpa(Type B) 23-07-2021 Power house-01 7 30-07-2021
GL:5-6/B-D STG
Location Of
Grade/Class Production Day Project Name Age Date of Testing
Sampling
C3&C4 pedestal
C 35 Mpa(Type B) 23-07-2021 Power house-01 28 20-08-2021
GL:5-6/B-D STG
C3&C4 pedestal
C 35 Mpa(Type B) 23-07-2021 Power house-01 7 30-07-2021
GL:5-6/B-D STG
C3&C4 pedestal
C 35 Mpa(Type B) 23-07-2021 Power house-01 28 20-08-2021
GL:5-6/B-D STG

C25 Mpa CASE-C 23-07-2021 GL:15-18/B-D Power house-02 3 26-07-2021

C25 Mpa CASE-C 23-07-2021 GL:15-18/B-D Power house-02 5 28-07-2021

C25 Mpa CASE-C 23-07-2021 GL:15-18/B-D Power house-02 7 30-07-2021

C25 Mpa CASE-C 23-07-2021 GL:15-18/B-D Power house-02 28 20-08-2021


Location Of
Grade/Class Production Day Project Name Age Date of Testing
Sampling
CEM Sump
C 30 Mpa(Type B) 24-07-2021 &Neutrilization WWTP 3 27-07-2021
Pond
CEM Sump
C 30 Mpa(Type B) 24-07-2021 &Neutrilization WWTP 7 31-07-2021
Pond
CEM Sump
C 30 Mpa(Type B) 24-07-2021 &Neutrilization WWTP 28 21-08-2021
Pond
CEM Sump
C 30 Mpa(Type B) 24-07-2021 &Neutrilization WWTP 7 31-07-2021
Pond
CEM Sump
C 30 Mpa(Type B) 24-07-2021 &Neutrilization WWTP 28 21-08-2021
Pond
CEM Sump
C 30 Mpa(Type B) 24-07-2021 &Neutrilization WWTP 7 31-07-2021
Pond
CEM Sump
C 30 Mpa(Type B) 24-07-2021 &Neutrilization WWTP 28 21-08-2021
Pond
400kv GIS
C25 Mpa CASE-C 24-07-2021 &switch GIS area 3 27-07-2021
yard&Relay
400kv GIS
C25 Mpa CASE-C 24-07-2021 &switch GIS area 7 31-07-2021
yard&Relay
400kv GIS
C25 Mpa CASE-C 24-07-2021 &switch GIS area 28 21-08-2021
yard&Relay
Location Of
Grade/Class Production Day Project Name Age Date of Testing
Sampling

C 30 Mpa(Type B) 25-07-2021 Boiler-02 Pedestal 7 01-08-2021

C 30 Mpa(Type B) 25-07-2021 Boiler-02 Pedestal 28 22-08-2021

RCCP Cooling
C 30 Mpa(Type B) 25-07-2021 11th span 7 01-08-2021
water line
RCCP Cooling
C 30 Mpa(Type B) 25-07-2021 11th span 28 22-08-2021
water line
RCCP Cooling
C 30 Mpa(Type B) 25-07-2021 11th span 7 01-08-2021
water line
RCCP Cooling
C 30 Mpa(Type B) 25-07-2021 11th span 28 22-08-2021
water line

C 30 Mpa(Type B) 26-07-2021 CW pump pit Intake structure 7 02-08-2021

C 30 Mpa(Type B) 26-07-2021 CW pump pit Intake structure 28 23-08-2021

C 30 Mpa(Type B) 26-07-2021 CW pump pit Intake structure 7 02-08-2021

C 30 Mpa(Type B) 26-07-2021 CW pump pit Intake structure 28 23-08-2021

ID FAN DUCT
C25 Mpa CASE-C 26-07-2021 Pedestal 7 02-08-2021
Support
ID FAN DUCT
C25 Mpa CASE-C 26-07-2021 Pedestal 28 23-08-2021
Support

C 21 Mpa(Type B) 26-07-2021 HCSD Building HCSD 7 02-08-2021

C 21 Mpa(Type B) 26-07-2021 HCSD Building HCSD 28 23-08-2021


Location Of
Grade/Class Production Day Project Name Age Date of Testing
Sampling

C 12 Mpa(Type B) 26-07-2021 HCSD Building HCSD 7 02-08-2021

C 12 Mpa(Type B) 26-07-2021 HCSD Building HCSD 28 23-08-2021

C 30 Mpa(Type B) 26-07-2021 Box culvert 27th span 7 02-08-2021

C 30 Mpa(Type B) 26-07-2021 Box culvert 27th span 28 23-08-2021

C25 Mpa CASE-C 26-07-2021 GIS building GIS area 7 02-08-2021

C25 Mpa CASE-C 26-07-2021 GIS building GIS area 28 23-08-2021