PLAN
Reclaimer-2
Ashraful Inspection
1 5th Span 25 72 8:00 AM KB Choi Ariful YI Choi 1 CEM-II New Agg.
(01739658515) Done
FDN Conc.
Stacker-4
Ashraful Inspection
2 2nd Span 25 110 8:00 AM KB Choi Ariful YI Choi 1 CEM-II New Agg.
(01739658515) Done
FDN Conc.
Power House-1
STB Wall Remaining Rakib Inspection
3 25 13 8:00 AM TB Kim Mehedi CS Jung 1 CEM-I Old Agg.
Portion (01718200280) Today
(GL 4~5,A)
Elec.Manhole
Jaber Inspection
4 EMH-Z02 & Z04 12 1 9:00 AM KB Choi Solaiman YC Chang 1 CEM-II New Agg.
(01811840061) Done
Lean
Reclaimer-2
Ashraful Inspection
6 6th Span 25 72 10:30 AM KB Choi Ariful YI Choi 1 CEM-II New Agg.
(01739658515) Done
FDN Conc.
Stacker-2
Ashraful Inspection
8 Span -6 25 40 11:00 AM KB Choi Ariful YI Choi 1 CEM-II New Agg.
(01739658515) Done
Pedestal
Total 690
*This Schedule can be delayed and changed based on inspection status and Pump Car status .