ANALISA REKAPITULASI JALAN RABAT BETON SIMPANG KELAPING

AHSP.4.1.1.4 Membuat 1 M3 Lantai Kerja Mutu f’c = 7,4 MPa (K 100), Slump (3-6) Cm, w/c = 0,87
A TENAGA
Pekerja L. 01 oh 1.200 98,000.00 117,600.00
Tukang L. 02 oh 0.200 120,000.00 24,000.00
Kepala tukang L. 03 oh 0.020 125,000.00 2,500.00
Mandor L. 04 oh 0.060 110,000.00 6,600.00
Jumlah Tenaga Kerja 150,700.00
B BAHAN
Semen portland kg 230.000 1,425.00 327,750.00
Pasir beton kg 893.000 110.00 98,230.00
Kerikil (Maks. 30 mm ) kg 1,027.000 270.37 277,670.37
Air ltr 200.000 100.00 20,000.00
Jumlah Harga Bahan 723,650.37
Jumlah ( A + B ) 874,350.37
Bobot isi pasir = 1.400 kg/m3, Bobot Overhead & Profit 10% 87,435.04
isi kerikil = 1.350 kg/ m3, Buckling
factor pasir = 20 % Harga Satuan Pekerjaan 961,785.41

No Jumlah Ukuran Satuan Jumlah Total

1 Panjang jalan = 61.00 M


Lebar Jalan = 3.00 M
Tinggi Jalan = 0.30 M
2.00
Ukuran Jalan = 54.90 M3
HSP = 961,785.41 RP
Jumlah = 52,802,018.87 RP = 105,604,037.73

2
Panjang jalan = 64.00 M
Lebar Jalan = 3.00 M
Tinggi Jalan = 0.30 M
1.00
Ukuran Jalan = 57.60 M3
HSP = 961,785.41 RP
Jumlah = 55,398,839.47 RP = 55,398,839.47

3
Panjang jalan = 72.00 M
Lebar Jalan = 3.00 M
Tinggi Jalan = 0.30 M
1.00
Ukuran Jalan = 64.80 M3
HSP = 961,785.41 RP
Jumlah = 62,323,694.40 RP = 62,323,694.40

4
Panjang jalan = 100.00 M
Lebar Jalan = 1.00 M
Tinggi Jalan = 0.30 M
1.00
Bur Mesir Ukuran Jalan = 30.00 M3
HSP = 961,785.41 RP
Jumlah = 28,853,562.22 RP = 28,853,562.22

5
Panjang = 22.00 M
Lebar = 11.00 M
Tinggi = 0.30 M
1.00
Lap. Voli Ukuran = 72.60 M3
HSP = 961,785.41 RP
Jumlah = 69,825,620.58 RP = 69,825,620.58