Volume of Excavation
Depth of Excavation - 900mm + 350mm = 1250mm
Volume of Backfill – 1.25 - 0.072 - 0.027 - 0.056 - 0.3 = 0.795 cubic meter
Gravel bed/fill
Volume of F1 – 0.35m x 8pcs = 2.8 cubic meter
QUANTITY ESTIMATE FOR F2
Volume of Excavation
Depth of Excavation - 900mm + 350mm = 1250mm
Gravel bed/fill
Volume of F2 – 0.35m x 6pcs = 2.1 cubic meter
QUANTITY ESTIMATE FOR F3
Volume of Excavation
Depth of Excavation - 900mm + 350mm = 1250mm
Gravel bed/fill
Volume of F3 – 0.35m x 6pcs = 2.1 cubic meter
QUANTITY ESTIMATE FOR F4
Volume of Excavation
Depth of Excavation - 900mm + 350mm = 1250mm
Gravel bed/fill
Volume of F4 – 0.35m x 4pcs = 1.4 cubic meter
Excavation Cost
500𝑝ℎ𝑝 6.5ℎ𝑟𝑠
Labor cost – × = 406.25𝑝ℎ𝑝/𝑚3
8ℎ𝑟𝑠 𝑚3
406.26𝑝ℎ𝑝
Total Cost – × 30𝑚3 = 12187.5𝑝ℎ𝑝
𝑚3
Hauling Cost
Hauler cost 2000 php per elf w/ helper (3.5𝑚3 capacity)
500𝑝ℎ𝑝 1ℎ𝑟
Labor Cost – × = 62.5𝑝ℎ𝑝/𝑚3
8ℎ𝑟𝑠 𝑚3
2000𝑝ℎ𝑝
Hauler Cost – = 571.43𝑝ℎ𝑝/𝑚3
3.5𝑚3