QUANTITY ESTIMATE FOR F1

Volume of Excavation
Depth of Excavation - 900mm + 350mm = 1250mm

Volume for footing - 1 x 1 x 1.25 = 1.25 cubic meter

Total Volume – 1.25 x 24pcs = 30 cubic meters

Backfill and Compaction


Volume of excavation for 1 footing = 1.25 cubic meter

Dimension of C1 supported by F1: 0.2m x 0.4m

Height of C1 embedded in soil – 900mm

Volume of C1 embedded in soil – 0.2 x 0.4 x 0.9 = 0.072 cubic meter

Dimension of C3 supported by F1: 0.15 x 0.2

Height of C3 embedded in soil – 900mm

Volume of C3 embedded in soil – 0.15 x 0.2 x 0.9 = 0.027 cubic meter

Dimension of C4 supported by F1: 0.25 x 0.25

Height of C4 embedded in soil – 900mm

Volume of C4 embedded in soil – 0.25 x 0.25 x 0.9 = 0.056 cubic meter

Volume of F1 – 1 x 1 x 0.3 = 0.3 cubic meter

Volume of Backfill – 1.25 - 0.072 - 0.027 - 0.056 - 0.3 = 0.795 cubic meter

Total Volume – 0.795 x 8pcs = 6.36 cubic meter

Gravel bed/fill
Volume of F1 – 0.35m x 8pcs = 2.8 cubic meter
QUANTITY ESTIMATE FOR F2
Volume of Excavation
Depth of Excavation - 900mm + 350mm = 1250mm

Volume for footing - 1 x 1 x 1.25 = 1.25 cubic meter

Total Volume – 1.25 x 24pcs = 30 cubic meters

Backfill and Compaction


Volume of excavation for 1 footing = 1.25 cubic meter

Dimension of C1 supported by F2: 0.2m x 0.4m

Height of C1 embedded in soil – 900mm

Volume of C1 embedded in soil – 0.2 x 0.4 x 0.9 = 0.072 cubic meter

Dimension of C2 supported by F2: 0.15 x 0.3

Height of C3 embedded in soil – 900mm

Volume of C3 embedded in soil – 0.15 x 0.3 x 0.9 = 0.041 cubic meter

Volume of F2 – 1 x 1 x 0.3 = 0.3 cubic meter

Volume of Backfill – 1.25 - 0.072 - 0.041 - 0.3 = 0.837 cubic meter

Total Volume – 0.837 x 6pcs = 5.022 cubic meter

Gravel bed/fill
Volume of F2 – 0.35m x 6pcs = 2.1 cubic meter
QUANTITY ESTIMATE FOR F3
Volume of Excavation
Depth of Excavation - 900mm + 350mm = 1250mm

Volume for footing - 1 x 1 x 1.25 = 1.25 cubic meter

Total Volume – 1.25 x 24pcs = 30 cubic meters

Backfill and Compaction


Volume of excavation for 1 footing = 1.25 cubic meter

Dimension of C5 supported by F3: 0.15m x 0.2m

Height of C5 embedded in soil – 900mm

Volume of C5 embedded in soil – 0.15 x 0.2 x 0.9 = 0.027 cubic meter

Volume of F3 – 0.6 x 0.6 x 0.25 = 0.9 cubic meter

Volume of Backfill – 1.25 - 0.027 - 0.09 = 1.133 cubic meter

Total Volume – 1.133 x 6pcs = 6.798 cubic meter

Gravel bed/fill
Volume of F3 – 0.35m x 6pcs = 2.1 cubic meter
QUANTITY ESTIMATE FOR F4
Volume of Excavation
Depth of Excavation - 900mm + 350mm = 1250mm

Volume for footing - 1 x 1 x 1.25 = 1.25 cubic meter

Total Volume – 1.25 x 24pcs = 30 cubic meters

Backfill and Compaction


Volume of excavation for 1 footing = 1.25 cubic meter

Dimension of C5 supported by F4: 0.15m x 0.2m

Height of C5 embedded in soil – 900mm

Volume of C5 embedded in soil – 0.15 x 0.2 x 0.9 = 0.027 cubic meter

Volume of F4 – 0.8 x 0.8 x 0.25 = 0.9 cubic meter

Volume of Backfill – 1.25 - 0.072 - 0.041 – 0.16 = 1.063 cubic meter

Total Volume – 1.063 x 4pcs = 4.252 cubic meter

Gravel bed/fill
Volume of F4 – 0.35m x 4pcs = 1.4 cubic meter

Hauling of Excess soil


Total Volume – 30 - 6.36 - 5.022 - 6.798 - 4.252 = 7.568 cubic meter
Costing for Earthworks

Excavation Cost
500𝑝ℎ𝑝 6.5ℎ𝑟𝑠
Labor cost – × = 406.25𝑝ℎ𝑝/𝑚3
8ℎ𝑟𝑠 𝑚3

406.26𝑝ℎ𝑝
Total Cost – × 30𝑚3 = 12187.5𝑝ℎ𝑝
𝑚3

Hauling Cost
Hauler cost 2000 php per elf w/ helper (3.5𝑚3 capacity)
500𝑝ℎ𝑝 1ℎ𝑟
Labor Cost – × = 62.5𝑝ℎ𝑝/𝑚3
8ℎ𝑟𝑠 𝑚3

2000𝑝ℎ𝑝
Hauler Cost – = 571.43𝑝ℎ𝑝/𝑚3
3.5𝑚3

Total cost (Hauler + Labor) – 633.93𝑝ℎ𝑝/𝑚3

Total cost – 633.93php x 7.568𝑚3 = 4797.58𝑝ℎ𝑝

Gravel bed/fill cost


500𝑝ℎ𝑝 2.07ℎ𝑟
Labor Cost – × = 129.38𝑝ℎ𝑝/𝑚3
8ℎ𝑟𝑠 𝑚3

Material Cost – 1500𝑝ℎ𝑝/𝑚3

Total cost (Labor and Materials) – 1629.38𝑝ℎ𝑝/𝑚3

Total Cost – 1629.38php x 8.4𝑚3 = 13686.79𝑝ℎ𝑝