Weekly Progress Report #31
Weekly Progress Report #31
Approved
PERTAMINA EP
Approved
Rev. Date Description Prepare By Checked By
By
CONTRACTOR
PO NO. 4500196323
PROJECT PROGRESS REPORT PERIOD #31
FROM DATE 18 Oct 2021
PENGADAAN POMPA RECIPROCATING API 674 UNTUK AREA UNTIL DATE 22 Oct 2021
SPU-E DAN SPU-F SANGASANGA FIELD NO. OF PAGES 2
1. EXECUTIVE SUMMARY
PO from Pertamina EP Asset 5: 16 December 2020
Kick Off Meeting: 17 December 2020
Current Status: Pump Only Stage
2. PROGRESS SUMMARY
Progress Report
Period Report : 18 Oct – 22 Oct 2021
Progress Plan Accumulative: 89.17%
Progress Actual Accumulative: 87.08%
Deviasi : -2.09%
3. ACTIVITIES THIS PERIOD
2.1 Unit Engineering and Design 10.00% 15 100% 10.00% 10.00% 0.00%
2.2 Drawing 10.00% 45 100% 10.00% 10.00% 0.00%
6. AREA CONCERNS
1. Dokumentasi untuk beberapa Part terlampir.
7. ATTACHMENT
1. S-Curve
2. Berikut Dokumentasi untuk Unit Assembly Stage
S‐Curve
100,00%
90,00%
80,00%
70,00%
60,00%
PROGRESS
50,00%
40,00%
30,00%
20,00%
10,00%
0,00%
W‐2 W‐3 W‐4 W‐1 W‐2 W‐3 W‐4 W‐1 W‐2 W‐3 W‐4 W‐1 W‐2 W‐3 W‐4 W‐1 W‐2 W‐3 W‐4 W‐1 W‐2 W‐3 W‐4 W‐1 W‐2 W‐3 W‐4 W‐1 W‐2 W‐3 W‐4 W‐1 W‐2 W‐3 W‐4 W‐1 W‐2 W‐3 W‐4 W‐1 W‐2 W‐3 W‐4 W‐5 W‐1 W‐2 W‐3 W‐4 W‐1 W‐2 W‐3 W‐4
Dec‐20 Jan‐21 Feb‐21 Mar‐21 Apr‐21 May‐21 Jun‐21 Jul‐21 Aug‐21 Sep‐21 Oct‐21 Nov‐21 Dec‐21
TIME
Plan Cumulative Actual Cumulative