Professional Documents
Culture Documents
Saep 27
Saep 27
1 Scope............................................................. 2
2 Conflicts and Deviations…………………….... 2
3 Applicable Documents................................... 2
4 Definitions...................................................... 4
5 Instructions.................................................... 5
6 Responsibilities............................................ 11
Exhibits............................................................... 12
1 Scope
2.1 Any conflicts between this standard and other applicable Saudi Aramco
Engineering Standards (SAESs) or industry standards, codes, and forms shall be
resolved in writing through the Manager, Process & Control Systems Department
of Saudi Aramco, Dhahran.
2.2 Direct all requests to deviate from this standard in writing to the Company, who
shall follow internal company procedure SAEP-302 and forward such requests to
the Manager, Process & Control Systems Department of Saudi Aramco, Dhahran.
3 Applicable Documents
To ensure compliance with the appropriate Saudi Aramco and International Standards
and Codes for over pressure protection of pipelines, the following Engineering
Standards shall be reviewed in conjunction with hydraulic surge analysis studies. These
Standards encompass hydraulic analysis, surge analysis, over pressure protection of
pipelines, design pressure, materials, operating conditions, Maximum Allowable
Operating Pressures and Maximum Allowable Surge Pressures.
Page 2 of 14
Document Responsibility: Process and Control Systems Dept. SAEP-27
Issue Date: 19 July 2014
Next Planned Update: 19 July 2014 Pipelines/Piping Hydraulic Surge Analysis
Page 3 of 14
Document Responsibility: Process and Control Systems Dept. SAEP-27
Issue Date: 19 July 2014
Next Planned Update: 19 July 2014 Pipelines/Piping Hydraulic Surge Analysis
4 Definitions
PHA (Preliminary Hazards Analysis): An initial screening exercise that can be used
to identify, describe, and rank major hazards. This technique can also be used to
Page 4 of 14
Document Responsibility: Process and Control Systems Dept. SAEP-27
Issue Date: 19 July 2014
Next Planned Update: 19 July 2014 Pipelines/Piping Hydraulic Surge Analysis
5 Instructions
5.1.3 The engineering design contractor shall use the approved pipeline
simulation software that is defined in the Saudi Aramco Recommended
Simulation Software Vendor List. The approved list can be obtained
from P&CSD/Pipelines & Simulation Unit.
5.1.4 At the completion of the hydraulic surge studies, the engineering design
contractor shall submit an electronic copy of complete simulation models
and supporting documents to P&CSD/Pipelines & Simulation Unit, the
Proponent and FPD for review and approval.
Page 5 of 14
Document Responsibility: Process and Control Systems Dept. SAEP-27
Issue Date: 19 July 2014
Next Planned Update: 19 July 2014 Pipelines/Piping Hydraulic Surge Analysis
The study shall not be limited to the mentioned transient risk situations and
P&CSD shall endorse the hydraulic surge analysis study timing.
Before the surge analysis commences, a technical specification for the surge
analysis study shall be prepared and approved by Proponent or SAPMT’s
engineering contractor to acknowledge the problem for further assessment,
scope development, and possible surge protection solution. The following list
shall be completed to define full scope of the surge analysis for pipelines to
ensure a consistent approach for all projects.
The objective of the analysis will determine the extent of the pipeline
system to be modeled and the accuracy of data required during pipeline
model development and evaluation. A clear surge analysis objective
shall be prepared and agreed with the pipeline hydraulic and surge
analysis specialist of P&CSD prior to conducting the analysis.
Page 6 of 14
Document Responsibility: Process and Control Systems Dept. SAEP-27
Issue Date: 19 July 2014
Next Planned Update: 19 July 2014 Pipelines/Piping Hydraulic Surge Analysis
The following list identifies data that shall be gathered before a surge
analysis study is conducted:
a) Pipeline system data: General description of the pipeline system,
function and a summary of the likely hazard scenarios as identified
in the PHA and HAZOP studies. Pipeline data including length,
elevation profile, diameter, wall thickness, roughness or friction
factor, elastic (Young’s) modulus, pressure rating, maximum
permissible pressure (pipes, components, joints, support), minimum
acceptable pressure (pipes, components, joints, supports).
b) Operating conditions: pipeline inlet pressure and temperature,
arrival pressure, maximum and minimum flow rates.
c) Fluid data: The key data required are the physical properties at the
relevant operating pressure and temperature for the evaluated
pipeline system. Physical properties include: density, viscosity, true
vapor pressure, bulk modulus, working temperature. Alternatively,
for compositional analysis, the fluid composition shall be defined.
d) Ambient conditions (summer/winter temperatures), thermal
conductivities for pipelines and soil and/or the overall heat transfer
coefficient between the pipeline and soil.
e) Pumps: Type, number, location, performance characteristics, with
operating curves and the following rated conditions: (head, flow,
speed, power and efficiency), Inertia of rotating elements (impeller,
motor and coupling)
f) Valves: Type, number, location, dynamic performance characteristic
(Cv curve), open/close time, pressure rating and maximum
permissible pressure. Additional data for pressure relief valves: set
Page 7 of 14
Document Responsibility: Process and Control Systems Dept. SAEP-27
Issue Date: 19 July 2014
Next Planned Update: 19 July 2014 Pipelines/Piping Hydraulic Surge Analysis
pressures for opening and closing, time needed to open and close,
discharge pressure.
g) Tanks: Location, general layout, dimensions, maximum, minimum
and normal levels of the liquid surface, elevation relative to the
main pipeline, length and diameter of the connecting piping.
h) Bypass piping: Location, length, diameter, head loss.
i) Surge and transient event data: Time scale of valve and pumps
operation (Control Logic) and sequence of events to be investigated.
j) Units of measurements must be consistent.
Page 8 of 14
Document Responsibility: Process and Control Systems Dept. SAEP-27
Issue Date: 19 July 2014
Next Planned Update: 19 July 2014 Pipelines/Piping Hydraulic Surge Analysis
When plant and pipeline operating data is available, the model shall be
validated against a set of operating data within the known constraints of,
1) accuracy of plant measurements, 2) tolerance and convergence
limitations within the simulator, and 3) the errors associated with
simplifying assumptions made during model development. Models shall
be validated also during project proposal and/or detailed design by
SAPMT’s engineering contractor.
A surge analysis specific sheet shall be developed per Exhibit I and submitted
for approval prior to performing surge analysis.
Page 9 of 14
Document Responsibility: Process and Control Systems Dept. SAEP-27
Issue Date: 19 July 2014
Next Planned Update: 19 July 2014 Pipelines/Piping Hydraulic Surge Analysis
Describe the purpose of the study and the role that simulation plays in
addressing that purpose. The objective of the simulation must be clearly
stated. The model shall be represented as a tool to help solve specific
problems or answer specific questions rather than as an end product. The
simulation package and version used to build the model shall be defined.
In order to understand the model and its limitations, all assumptions shall
be identified. Discuss the limitations of the model’s representation of the
actual system and the impact those limitations have on the results and
conclusions presented.
Page 10 of 14
Document Responsibility: Process and Control Systems Dept. SAEP-27
Issue Date: 19 July 2014
Next Planned Update: 19 July 2014 Pipelines/Piping Hydraulic Surge Analysis
All the prepared document shall be submitted to P&CSD for review and
approval.
6 Responsibilities
P&CSD provides technical guidance for all hydraulic and surge analysis, or pipeline
control system studies during DBSP, Project Proposal, and Detailed Design phases of a
project. P&CSD proactively works with Proponent and SAPMT on pipeline design;
reviews all related pipelines studies and models; and provide guidance during each
design stage. It is P&CSD responsibility to approve and endorse the pipeline studies
and models.
SAPMT or proponent shall be responsible for obtaining approval for the surge analysis
technical specification (Exhibit I) from the appropriate organizations prior to
performing the analysis. If any changes are made to the system or its operating
conditions or procedures, the technical specification shall be revised.
Suppliers for pipeline and related components such as surge relief, rotating equipments
shall provide Saudi Aramco and the design contractor the required equation data for
conducting detailed surge analysis studies.
Revision Summary
19 July 2014 New Saudi Aramco Engineering Procedure.
Page 11 of 14
Document Responsibility: Process and Control Systems Dept. SAEP-27
Issue Date: 19 July 2014
Next Planned Update: 19 July 2014 Pipelines/Piping Hydraulic Surge Analysis
EXHIBITS
TABLE OF CONTENTS
Page 12 of 14
Document Responsibility: Process and Control Systems Dept. SAEP-27
Issue Date: 19 July 2014
Next Planned Update: 19 July 2014 Pipelines/Piping Hydraulic Surge Analysis
Scope:
Design and Operating Criteria: Pipelines & Piping Design as per Saudi Aramco Engineering
Standards (SAES-L-100, SAES-L-132, SAES-L-310 and
SAES-L-410)
Fire and Safety related system design as per Saudi Aramco
Engineering Standards (SAES-B-017, SAES-B-060,
SAES-B-064 and SAES-B-070)
Design Constrains:
Maximum operating Pressure
Minimum operating Pressure
Maximum Flow Rate
Minimum Flow Rate
Other Parameters
Date:
Specification completed by: ______________________
*Approved by:
Page 13 of 14
Document Responsibility: Process and Control Systems Dept. SAEP-27
Issue Date: 19 July 2014
Next Planned Update: 19 July 2014 Pipelines/Piping Hydraulic Surge Analysis
Page 14 of 14