You are on page 1of 2

For 1 lift (48 Floors)

Manpower
No of days
Scope Category Nos
technicians 1
Cleaning corroded guide rails 6
Helpers 4
Technicians 1
Painting corroded areas and welded areas 3
Helper 1

technicians 1
Hoistway light replacing 0.25
Helper 1
Cable and flexible arranging in shaft technicians 2 2
Closing all trunking which are open technicians 2 2
Jamb cover fixing technicians 2 1
Calling buttons and lanterns aligning technicians 2 2
Machine room cable arranging and cleaning technicians 2 0.25
Materils
Item Qty
Diesel 20L 100
Emery papers 50 250
Primer 5L For all corroded areas 25
Gray paint 10L Brackets touch up 50
Yellow paint 250ml Car top paint 5
Silver paint 2L Door edges 10
Tube lights 10
- -
- -
- -
- -
- -