You are on page 1of 2

1.1.1.1.

1 Project : WATERFRONT INTERGRATED RESORT


Reference : GTEC - IRE – 0202

REPORT

OBSERVATION REPORT FOR NONCONFORMANCE OBSERVED IN


INSTALLATION OF CABLES AND WIRES IN
LEVEL-01 KITCHEN AREA
Building – 02

HKN Internal inspection Schedule item Nr 5 dated 04th October 2022

Revision History

00 06th October 2022 SHH/AEA FOR REFERENCE PGA GBE


Revision Date Prepared by Reference Checked by Approved by

Page 1 of 2
Introduction
This report refers to non-conformances during the internal inspection on 06 July 2022 for item Nr. 5 on
the schedule: ‘Installation of Cables and Wires’ (TN, FD, SA, LT, EM & PA SystemS) in Kitchen areas
at level 01 in Building 2 (2.30-2.38/2.J-2.L)
Observation:
01. Cable installation was not carried out as per the approved documents.
Power and lighting cables feeding from the SDB.2.B.2.3.1 were routed to an incorrect
distribution board (SDB.2.B.2.1).

Figure 1: Extracted from HKN-SPD-EL-EF-21101D1

Remarks and Recommendation:

HKN shall take measures to correct the installation as per the approved documents. And the same
inspection shall be re-raised for Engineer to witness the rectification upon completion of the works.

Page 2 of 2

You might also like