REPORT
Revision History
Page 1 of 3
Introduction:
This report refers to non-conformances observed while witnessing the internal inspection on 15th September 2022 for item Nr 9 on the
schedule ‘Installation of Cables and Wires” at Linen storage (Grid location 2.9-2.12/2.K-3.A) at Level 01 in Building 02.
Level Cable Identification tag Cable Type as per the approved drawing Installed cable type at site Cable schedule reference
01 MDB.2.2/ES.2.2 1R×1×4C 6sqmm Cu/XLPE/LSZH + 1R×1×5C 6sqmm Cu/XLPE/LSZH Refer Figure 03 Extracted from HKN-SPD-EL-EF-
1Rx1x1C 6sqmm Cu/LSZH/E 2020003
Table 1: Comparison of site installed cable type against the approved (As per the drawing) cable type
Page 2 of 3
Figure 2: Installed 5C 6sqmm Cable at site
HKN shall replace above non-approved cables with approved type and the inspection shall be re-raised for the Engineer to confirm the
installation.