Construction Report
Intended Learning Outcomes
• Interpret and justify construction periodic
reports, documents and processes
• Explain the importance of Construction
Reports
• Define and identify the important parts of
Construction Reports
Learning Assessments
• Recitations
• Assignments
• Quizzes
CONSTRUCTION PROJECT MANAGEMENT PLAN
I . PROJECT ORGANIZATION
II . PROCEDURES
• FLOW OF COMMUNICATION
• MEETINGS
• CONSTRUCTION PROGRESS MONITORING
• PROJECT REPORTING – MONTHLY REPORT
III . PROJECT IMPLEMENTATION
PRE – CONSTRUCTION STAGE
CONSTRUCTION STAGE
• QUALITY CONTROL PLAN
• QUALITY CONTROL FORMS (CPM FORMS)
• COST CONTROL AND MONITORING FORMS (CPM FORMS)
• PROCESS FLOW CHARTS
• CONSTRUCTION SAFETY GUIDELINES
POST CONSTRUCTION STAGE
• PUNCHLISTING WORK AND PREPARATORY TO FINAL ACCEPTANCE
• PROJECT HANDOVER SUBMITTALS
17 July 2021 6
A. FLOW OF COMMUNICATION
OWNER
PROJECT OFFICER
CPMT
17 July 2021 7
B. MEETINGS
17 July 2021 8
B.1 PMG MEETINGS
Such meetings are project coordination meetings that shall be held
during design and construction stages and shall be held at the office of
Owner and/or Designers with intermittent meetings at site.
Owner R W
Project Officer W R
Designers W W
CPM W W
Contractor W W
W – Weekly
R – As required by Construction Manager
17 July 2021 9
B.2 PRE - BID MEETING
Pre-bid meetings shall be held days after release of bid documents
with all bidders invited to attend. A second pre-bid meeting may be
held before submission of bids if it is deemed necessary by the
Project Manager / Quantity Surveyor when sufficient bidders queries
and bid bulletins been issued require clarification.
17 July 2021 10
B.3 POST-BID MEETING /
CLARIFICATORY MEETING
For proper evaluation of bids a post – bid meeting may be held to clarify
issues.
17 July 2021 11
B.5 SITE MEETINGS / CONSTRUCTION
COORDINATION MEETING
The Construction Project Manager will chair and organize site meetings once
per week with the contractors. The purpose of this shall be to enhance
coordination between the contractors.
17 July 2021 12
C. CONSTRUCTION PROGRESS MONITORING
Regular Checking of the following:
1. Planned vs. Actual progress schedule
2. S – Curve
3. Cumulative Accomplishment Percentage
4. Manpower : Planned vs. Actual
5. Equipment : Planned vs. Actual
6. Key Dates / Milestones
17 July 2021 13
D. PROJECT REPORTING
Contents:
1. Project Description
2. Project Status Executive Summary
3. Construction Progress Monitoring
4. Summary of Field Instructions
5. Summary of Change Orders
6. Summary of Test Results
7. Progress Photos
8. Weather Chart
17 July 2021 14
E. PROJECT IMPLEMENTATION
1. PRE-CONSTRUCTION STAGE
2. CONSTRUCTION STAGE
17 July 2021 15
E1. PRE-CONSTRUCTION STAGE
1. Drawing Preparation
a. Conceptual / Schematic Design – By Architect
b. Design Details – By Architect and Engineers
c. Redicheck – joint drawing review
d. Contract Drawings / Bid Drawings
17 July 2021 16
E2. CONSTRUCTION STAGE
2. QUANTITY SURVEYING
17 July 2021 17
E2. CONSTRUCTION STAGE
2. QUANTITY SURVEYING
- QUALITY CONTROL FORMS
17 July 2021 18
FLOW CHART FOR SUBMITTALS/APPROVALS
RESPONSIBILITY
WORKSTAGE REMARKS
CENTER
Submit / Transmit
Submittal Form
Quality Record to CPMT
Advice of an Incoming
Contractor
Contractor Supplier to give advance notice
Materials delivery at project site
to control prior to delivery
DISAPPROVED
Conduct Inspection
CPMT
APPROVED
Concreting
17 July 2021 21
FLOW CHART FOR CAST IN-PLACE CONCRETE
RESPONSIBILITY WORKSTAGE REMARKS
CENTER
QA/QC to Conduct
Rectify Inspection to Dimensional
Observation Requirement, Quality /
Workmanship Coordinate with
Survey Team
For Checking
Approved
Concrete Pouring
(w/ CPMT Inspection)
17 July 2021 22
FIELD INSTRUCTION ISSUANCE FLOW CHART
RESPONSIBILTY
WORKSTAGE REMARKS
CENTER
CONTRACTOR
Execute / comply with the instruction Issued.
17 July 2021 23
STOP WORK ORDER / LIFT ORDER AND
NON-CONFORMANCE REPORT / CORRECTIVE ACTION FLOW CHART
RESPONSIBILITY WORKSTAGE REMARKS
CENTER
CPMT
1.Incorrect material work method is noticed.
2.Work condition is facing danger situation.
3.Contractor is in default mode.
CPMT– NTC
Issue Stop Work order / Non-Conformance
Notice to Comply
Report
OWNER / CPMT Form
Note:
Contractor to implement
CONTRACTOR Approved corrective action
17 July 2021 24
REQUEST FOR INFORMATION FLOW CHART
RESPONSIBILITY REMARKS
WORKSTAGE
CENTER
CPMT – RFI
Contractor accomplish RFI form for issues concerning::
CONTRACTOR 1. Inconsistent details between drawings. Request for
2. Lacking drawing details / information Information Form
3. Clarification on other contract documents.
Incorrect
CPMT Evaluate Correctness of RFI
Correct
17 July 2021 25
CHANGE ORDER / VARIATIONS EVALUATION FLOW CHART
RESPONSIBILITY CENTER WORKSTAGE REMARKS
Owner’s changes 1.) Incase there will be cost and time effect, it
should be cleared by Owner prior to issuance of
Owner/Designer/CPMT Designer - Design changes instruction
Site condition Adjustment
17 July 2021 28
PUNCHLISTING WORK AND PREPARATORY TO FINAL ACCEPTANCE
RESPONSIBILITY WORK STAGE REMARKS
CENTER
CONTRACTOR
Rectify Work
CPMT
Inspect, check, verify
NO
Rectification Completed?
YES
CONTRACTOR
Prepare items for hand-over and.
turnover of project
APPROVED
17 July 2021 29
SUBMITTALS FOR HAND OVER
1. Close – out Report
2. CPM / Bar Chart and S- curve
3. Contractor’s Performance Rating
4. Brochures and Maintenance Manuals
5. Door Keys
6. Warranty Certificates
7. Government Permits
8. Punchlist Close–out
17 July 2021 30
ANNEX I
17 July 2021 31
SUBMITTAL TRANSMITTAL
REQUEST FOR INFORMATION
SUBSTITUTION REQUEST
INSPECTION AND WORK REQUEST
CONCRETE POURING REQUEST
CONTRACTOR’S DAILY REPORT
WEEKLY PROGRESS REPORT
WORK ACCOMPLISHMENT REPORT
CHANGE ORDER PROPOSAL
17 July 2021 32
ANNEX II
17 July 2021 33
NOTICE TO COMPLY
SAFETY NOTICE REPORT
PROJECT MANAGER’S
INSTRUCTION
CONFIRMATION OF VERBAL
INSTRUCTION
17 July 2021 34