NAME OF THE WORK : Detailed Estimate for Soil Investigation work for
Construction of new academic block in Government
autonomous college ,Rourkela in the district of
Sundargarh.
has been prepared for Detailed Estimate for Soil Investigation work for Construction of new academic
block in Government autonomous college ,Rourkela in the district of Sundargarh.
For computation of Safe Bearing Capacity and design purposes, Soil Investigation work is absolutely
necessary, Keeping in mind this necessity estimate has been framed.
This estimate has been prepared on the basis of approved analysis rates of the Chief Engineer
(Mechanical), Irrigation Department, BBSR Odisha. For Item No. 1 & 2. Other rates are approved by
Chief Engineer, R.D & Q.P (R & B) Odisha, BBSR letter no. 2909 dtd. 09.10.2009.
11 Hydrometer Analysis
BH No.01 10
BH No.02 10
Total 20 nos @ 674.00 per nos. Rs. 13480.00
12
Determination of shear strength parameter of
a specimen tested on unconsolidated
undrained triaxal compression with out the
measurement of pore water pressure.
BH No.1 2
BH No.2 2
Total 4 Nos @ 1225.00 per nos Rs. 4,900.00
13 Determination of Differential Free Swell Index.
BH No.1 2
2
Total 4 nos @ 210.00 per nos. Rs. 840.00
Total 106,024.00
Add cess @ 1% 1,060.24
TOTAL Rs. 107,084.24
Add GST@ 18% 19,084.32
G.Total 126,168.56
Or say 126,169.00
10 Hydrometer Analysis
BH No.01 9.00
BH No.2 12.00
BH No.3 12.00
BH No.4 12.00
BH No.5 12.00
BH No.6 12.00
Total 69 nos @ 674.00 per nos. Rs. 46506.00
11
Determination of shear strength parameter of
a specimen tested on unconsolidated
undrained triaxal compression with out the
measurement of pore water pressure.
BH No.1 2.00
BH No.2 1.00
BH No.3 1.00
BH No.4 1.00
BH No.5 1.00
BH No.6 1.00
Total 7 Nos @ 1225.00 per nos Rs. 8,575.00
12 Determination of Differential Free Swell Index.
BH No.1 9.00
BH No.2 12.00
BH No.3 12.00
BH No.4 12.00
BH No.5 12.00
BH No.6 12.00
Total 69 nos @ 210.00 per nos. Rs. 14490.00
Total 323,647.00
Add GST@ 18% 58,256.46
G.Total 381,903.46
Or say 381,903.00
1 Boring in soil/over burden in all kinds of soil excluding
soft & hard rock in HX size hole depth as directed by
the Engineer-in-charge.
(a) within in 10mtrs. Depth
BH No.1 10.00
BH No.2 10.00
BH No.3 10.00
BH No.4 10.00
Total 40.00 mtrs. @ 1031.00 per mtr. Rs. 41,240.00
(b) Below in 10mtrs. Depth
BH No.1 5.00
BH No.2 5.00
BH No.3 5.00
BH No.4 5.00
Total 20.00 mtrs. @ 1103.00 per mtr. Rs. 22,060.00
2 Conduction of S.P.T. at location as directed in
conformity with relevent I.S. specification complete in
all respect and supplying result thereof.(Ref Item No
191120)
BH No.1 10.00
BH No.2 10.00
BH No.3 10.00
BH No.4 10.00
Total 40 nos @ 293.86 per nos. Rs. 11,754.40
3 Determination of Moisture Content.(Ref Item No 191141)
BH No.1 10.00
BH No.2 10.00
BH No.3 10.00
BH No.4 10.00
Total 40 nos. @ 299.67 per nos. Rs. 11,986.80
has been prepared for Detailed Estimate for Soil Investigation for Construction of A.R.C.S
Building ,Panposh circle,Panposh ,Rourkela
For computation of Safe Bearing Capacity and design purposes, Soil Investigation work is absolutely
necessary, Keeping in mind this necessity estimate has been framed.
This estimate has been prepared on the basis of approved analysis rates of the Chief Engineer
(Mechanical), Irrigation Department, BBSR Odisha. For Item No. 1 & 2. Other rates are approved by
Chief Engineer, R.D & Q.P (R & B) Odisha, BBSR letter no. 2909 dtd. 09.10.2009.
11 Hydrometer Analysis
BH No.01 9
BH No.02 9
Total 18 nos @ 674.00 per nos. Rs. 12132.00
12
Determination of shear strength parameter of
a specimen tested on unconsolidated
undrained triaxal compression with out the
measurement of pore water pressure.
BH No.1 3.00
BH No.2 3.00
Total 6 Nos @ 1225.00 per nos Rs. 7,350.00
13 Determination of Differential Free Swell Index.
BH No.1 9.00
BH No.2 9.00
Total 18 nos @ 210.00 per nos. Rs. 3780.00
Total 120,290.00
Add cess @ 1% 1,202.90
TOTAL Rs. 121,492.90
Add GST@ 18% 21,652.20
G.Total 143,145.10
Or say 143,145.00
NAME OF THE WORK : Detailed Estimate for Soil Investigation work for
Construction of Proposed 100 users Rental Housing
Complex (RHC) for Migrant Construction Workers at
Premises of Ashraya Sthali ,Plant Side ,Rourkela in
the Dist of Sundargarh..
This estimate amounting to Rs. 59,936.00 (Rupees Ffty nine Thousand Nine hundred thirty six Only)
has been prepared for Detailed Estimate for Soil Investigation work for Construction of Proposed 100
users Rental Housing Complex (RHC) for Migrant Construction Workers at Premises of Ashraya
Sthali ,Plant Side ,Rourkela in the Dist of Sundargarh..
For computation of Safe Bearing Capacity and design purposes, Soil Investigation work is absolutely
necessary, Keeping in mind this necessity estimate has been framed.
This estimate has been prepared on the basis of approved analysis rates of the Chief Engineer
(Mechanical), Irrigation Department, BBSR Odisha. For Item No. 1 & 2. Other rates are approved by
Chief Engineer, R.D & Q.P (R & B) Odisha, BBSR letter no. 2909 dtd. 09.10.2009.
11 Hydrometer Analysis
BH No.01 8
Total 8 nos @ 674.00 per nos. Rs. 5392.00
12
Determination of shear strength parameter of
a specimen tested on unconsolidated
undrained triaxal compression with out the
measurement of pore water pressure.
BH No.1 3
Total 3 Nos @ 1225.00 per nos Rs. 3,675.00
Total 50,366.00
Add cess @ 1% 503.66
GST @ 18% 9,065.88
G.Total 59,935.54
Or say 59,936.00
(Rupees Ffty nine Thousand Nine hundred thirty six Only)
NAME OF THE WORK : Detailed Estimate for Geo Technical Investigation for
proposed Sluice cum VRM over Lunigaon -Satakalia
D/C at RD 90 mtr under Niali Block .
This estimate amounting to Rs. 255,156.00 (Rupees two lakh fifty five Thousand one hundred fifty six
Only)
has been prepared for Detailed Estimate for Geo Technical Investigation for proposed Sluice cum
VRM over Lunigaon -Satakalia D/C at RD 90 mtr under Niali Block .
For computation of Safe Bearing Capacity and design purposes, Soil Investigation work is absolutely
necessary, Keeping in mind this necessity estimate has been framed.
This estimate has been prepared on the basis of approved analysis rates of the Chief Engineer
(Mechanical), Irrigation Department, BBSR Odisha. For Item No. 1 & 2. Other rates are approved by
Chief Engineer, R.D & Q.P (R & B) Odisha, BBSR letter no. 2909 dtd. 09.10.2009.
BH No.1 4.00
BH No.2 5.00
BH No.3 5.00
BH No.4 3.00
Total 17 Nos @ 1225.00 per nos Rs. 20,825.00
Total 214,417.00
Add cess @ 1% 2,144.17
GST @ 18% 38,595.06
G.Total 255,156.23
Or say 255,156.00
(Rupees two lakh fifty five Thousand one hundred fifty six Only)
NAME OF THE WORK : Detailed Estimate for Geo Technical Investigation for
Driving Institute and Mega Educational Complex in
the District of Sundargarh.
This estimate amounting to Rs. 408,706.00 (Rupees Four lakh eight thousand seven hundred six Only)
has been prepared for Detailed Estimate for Geo Technical Investigation for Driving Institute and
Mega Educational Complex in the District of Sundargarh.
For computation of Safe Bearing Capacity and design purposes, Soil Investigation work is absolutely
necessary, Keeping in mind this necessity estimate has been framed.
This estimate has been prepared on the basis of approved analysis rates of the Chief Engineer
(Mechanical), Irrigation Department, BBSR Odisha. For Item No. 1 & 2. Other rates are approved by
Chief Engineer, R.D & Q.P (R & B) Odisha, BBSR letter no. 2909 dtd. 09.10.2009.
BH No.1 2.00
BH No.2 2.00
BH No.3 2.00
BH No.4 2.00
BH No.5 2.00
BH No.6 2.00
BH No.7 2.00
Total 14 Nos @ 1225.00 per nos Rs. 17,150.00
13 Conducting Total station survey ,Preparation of Site plan and Contour etc
complete
Total 343,450.80
Add cess @ 1% 3,434.51
GST @ 18% 61,821.14
G.Total 408,706.45
Or say 408,706.00
(Rupees Four lakh eight thousand seven hundred six Only)