Professional Documents
Culture Documents
CAP TO SRI
Prepared BY
Project Engineer Edo Faizal Candrawinata
1. PURPOSE
2. SCOPE
3. DEFINITIONS
4. REFERENCE
5. RESPONSIBILITIES
6. PROCEDURE
- General
- Work Flow
- Preparation
- System Drying Procedure
- Acceptance criteria and Medium
- Reinstatement
7. PRECAUTIONS
8. RECORDS
ATTACHMENT
Attachment-1: Record Sheet for System Drying
NATURAL GAS PIPELINE AND METERING STATION AT
CAP TO SRI
2. Schope
This document is applied to drying activity to be performed by CONTRACTOR, and will be used as
the basis of a detailed procedure to be prepared by CONTRACTOR.
It is carried out after gross leak test. The systems required drying are specified in Section 6.1
3. Definitions
Definition of Contracting Parties
EMPLOYER : Synthetic Rubber Indonesia
CONTRACTOR : P.T. Banten Inti Gasindo
VENDOR : The Manufacturer and/or Supplier of a commodity, system or piece of
equipment to perform the specified duty.
4. Reference
N/A
5. RESPONSIBILITIES
CONTRACTOR will be responsible to make sure in accordance with this Execution Plan that a
SYSTEM which is required to remove water or moisture from where residue water and moisture
makes trouble during start up and operation for some Process systems. Required source for system
drying such as Compressed Dry Air or Nitrogen is arranged by CONTRACTOR. System drying will
be inspected/witnessed by EMPLOYER’s representative. CONTRACTOR will give notice to
EMPLOYER at least one (1) day prior to witness of System drying.
6. Procedure
General
System drying is performed to make sure the SYSTEM free from water and moisture where residual
water or moisture inside the system will make trouble during start up and/or operation.
Work Flow
System drying will be conducted in accordance with following work flow.
Preparation
- Gross leak test for the system shall complete by test report signed by Employer.
NATURAL GAS PIPELINE AND METERING STATION AT
CAP TO SRI
- Conduct system drying according to the marked up P&ID with highlighted of lowest
drain point.
- Repeat draining at low drain points drain until water is not found in the vent gas.
- Periodically check the system for dew point reading on specified sampling points
using dew point meter.
- After drying is completed in hydrocarbon lines, perform nitrogen purging till 98,2%
N2 reading. Then perform soak test using nitrogen, allow on stand for 1 to 2 hrs and
check the dew point reading to verify no moisture left in the system.
- Maintain the dried system under a slight positive pressure with nitrogen to prevent the
ingress of moisture.
7. Precautions
Precautions to be observed during the execution of System drying are described as below:
General
5. Ensure that drying area will be patrolled prior to introduction of the dry
gas in order to make sure that all safety precautions have been established.
6. Ensure that permit to work will be arranged for all of System drying.
7. Ensure that isolation devices such as valves and spades which separate
drying area must be tagged with cautionary statement like “Danger! Do
not touch! System drying by Pre-Commissioning”. Responsible person’s
name must be written on the TAG and the contact info.
Technical Aspects
1. Ensure that no water is remaining inside hose prior to connecting it to the
system.
2. Ensure that hose is connected properly to dry air supply nozzle.
Especially, when System drying medium is taking from hose station,
miss-connection to water nozzle gives serious impact on the activity.
3. Ensure that no water is accumulated at the low point drain in case that it
is a dew point measurement location because water generally damages
dew point meter.
8. The records as an evidence of the accomplishment of System drying in accordance with the above
Execution Plan will be retained in each System’s Completion Dossier using the System drying record
NATURAL GAS PIPELINE AND METERING STATION AT
CAP TO SRI
Date issued:
1. System/Sub-system No :
4. Date/Time :
5. Test media :
6. Test pressure :
7. Dew point(degC)(Limit/Actual) :
8. Remarks :
Inspected by
SRI:
Signature Date
PT BIG:
Signature Date