Professional Documents
Culture Documents
Given data:
Assumptions:
Number of lane ( )
Therefore,
Preliminary Dimensions
Girder Depth determination:
, For simple span T-beams…….AASHTO Table 2.5.2.6.3-1
1|Page
Bridge Design PROJECT 2012/13
For cast-in-place concrete, the clear distance between parallel bars in a layer shall not be less
than:
Assume
bar
Minimum cover shall be in accordance with ERA design manual section 9.4.2
Take
Spacing of T-girder,S
S varies from 1.8m to 3.6m
2|Page
Bridge Design PROJECT 2012/13
Assumption:
Number of girders=3
Take:
3|Page
Bridge Design PROJECT 2012/13
Take
Diaphragm
For T-girders besides, diaphragms should be provided at ends and at least one diaphragm at
mid-span. Use 0.6m deep and 0.4m wide diaphragm at both at mid span and at ends of the
support.
Fig.1
Railing(parapet)
Use continuous concrete wall of height 850mm and thickness 300mm at the bottom and 100mm
at the top.
Dead Load:
Although AASHTO offers no specific dead load moment equation, for slabs continuous
over more than two supports the generally accepted expression is:
Live load:
According to Table 4.1 of AASHTO design manual maximum live load moments per unit width
(Nmm/mm):
4|Page
Bridge Design PROJECT 2012/13
S Positive Negative
moment moment
FACTORED MOMENT:
5|Page
Bridge Design PROJECT 2012/13
( )
Reinforcement design:
* √ +
* √ +
Therefore, provide
6|Page
Bridge Design PROJECT 2012/13
Distribution reinforcement:
Secondary reinforcement is placed at the bottom of the slab in the longitudinal direction to
distribute wheel loads on the bridges to the primary reinforcement in the transverse
direction.
According to Eq. 12.12, the amount of distribution reinforcement shall be the percentage of
the reinforcement steel required for positive moment as given by the following formula:
Use
Therefore, provide
7|Page
Bridge Design PROJECT 2012/13
Shrinkage and temperature reinforcement shall not be spaced farther apart than either
3.0times the component thickness or 450mm
Using
Therefore, provide
8|Page
Bridge Design PROJECT 2012/13
Design of Overhang Slab
Load Calculation
DEAD LOAD
9|Page
Bridge Design PROJECT 2012/13
Depth of post=0.25
Width of post=0.3
C/c post=1.5
Height of post=0.8
Dead load
Top slab
Table
10 | P a g e
Bridge Design PROJECT 2012/13
LIVE LOAD
A. railing load
From Art 3.24.5-2. The effective width of slab resisting post loading shall be equal to
P=44.51KN
( )
=1.26m
( )
11 | P a g e
Bridge Design PROJECT 2012/13
B. Truck Load
According to Art 7.4 slabs/longitudinal edges, the wheel is part 300mm from face of rail,
X=1.15m-(0.3m+0.3m+0.1m)
X=0.45m=450mm
E=1140+0.8339(450) = 1514.85mm=1.51m
( ) KNm/m
*(1+IM), IM=33%
=28.644+0.872= 29.516kNm/m
12 | P a g e
Bridge Design PROJECT 2012/13
Total moment
=1.25
=1.25(9.236)+1.75(29.516)=63.198
Design moment
( , )
= 65.503kNm/m
Design for flexure and shear
=√ , b =1m
=0.028875
=√
+ +cover
+50
=230mm, ok!
= mm -50mm
13 | P a g e
Bridge Design PROJECT 2012/13
Provide Φ ⁄
Cracking is controlled by limiting the tensile stress in the reinforcement under service load
to an allowed tensile stress
The crack width at the service limit state is proportional to steel stress
≤ = ≤ 0.6
Crack width
Es=200Gpa
Ec=0.043 √ =0.043* √
Ec=27691.467Mpa
Take n=7.00, The modular ratio is rounded to the nearest tenth The modular ratio must not be
less than 6.
DC=1.0
14 | P a g e
Bridge Design PROJECT 2012/13
DW=1.0
=1.0
Modulus of rupture, √ √
0.8
( ( ))
15 | P a g e
Bridge Design PROJECT 2012/13
B=14.07
( ( ))
C=4841.571
X=√ √
X=56.919mm
( ( ))
Available tensile stress in the reinforcement, with z=23000N/mm for moderate exposure
A=2
126.14Mpa
16 | P a g e
Bridge Design PROJECT 2012/13
T-GIRDER
DESIGN OF GIRDER
EXTERIOR GIRDER
Load calculation
DEAD LOAD
= 0.3*0.25*24=1.80
= 0.96
= 0.8*0.25*24=4.8
17 | P a g e
Bridge Design PROJECT 2012/13
= (0.05+0.3)(1.15)
=1.1*0.4*24= 10.56
=0.075*(2.70-0.8)*22= 3.202625
=1.15*(0.6m-0.23)*0.3*24= 3.0636
Span=14.3
A X
0.00 0 214.63 0
0.05 0.715 193.63 153.62
0.10 1.430 172.62 292.22
0.2 2.145 151.62 425.8
0.15 2.860 130.62 524.37
0.25 3.575 109.62 617.92
18 | P a g e
Bridge Design PROJECT 2012/13
0.3 4.205 88.609 696.45
0.35 5.005 67.606 759.96
0.4 5.720 46.602 808.46
0.45 6.435 28.599 841.94
0.5 7.150 4.5954 860.4
= 0.4*1.1*24 = 10.56
= 2*(1.15*0.23)*24 = 12.696
(Wearing) =
Diaphragm 2*(0.6-0.23)*1.15*24=6.1272
19 | P a g e
Bridge Design PROJECT 2012/13
a X
0.00 0 208.05 0
0.05 0.715 188.16 141.64
0.10 1.430 168.28 269.07
0.2 2.145 148.39 382.28
0.15 2.860 128.5 481.27
0.25 3.575 108.62 566.04
0.3 4.205 88.733 636.59
0.35 5.005 68.848 692.93
0.4 5.720 48.962 735.04
0.45 6.435 29.076 762.94
0.5 7.150 9.3908 776.62
20 | P a g e
Bridge Design PROJECT 2012/13
LIVE LOAD
Art.3.8 Lateral distribution of wheel loads at ends of beams or stringers shall be that produced
by assuming the flooring to act as simple span between stringers or beam. For wheels or axles in
other positions on the span, the distribution for shear shall be determined by the method
prescribed for moment (lever arm)
21 | P a g e
Bridge Design PROJECT 2012/13
Exterior Beam
The live load bending moment for outside roadway stringers or beams shall be determined by
According to Art.3.8 Live load/multiple presence of live load, the multiple presence factor is
applied where the lever arm is used.
e=0.77+
Where =distance in mm from the face of rail to exterior face of exterior girder
300≤ ≤1700
e=0.77+
22 | P a g e
Bridge Design PROJECT 2012/13
b. More than one lane loaded:
( )
( )
=( )
=0.886
Therefore or for half lane loading (i.e. one line of load) multiplied by two and
the maximum is taken.
2
Therefore =1.772
a) Truck loading
23 | P a g e
Bridge Design PROJECT 2012/13
?1 ?2
1+ 2=1
2.23 1=1
1=0.448rad
Y2=2.02 2=1.168
Y=7.88 1=3.53024
MT=785.368Knm
24 | P a g e
Bridge Design PROJECT 2012/13
B) TANDEM LOADING
T 1+ 2=1
?1
?2
Y1=6.85 1=7.45 2
2=0.919 1
1+ 2=1
1.919 1=1
1=0.521rad
2=0.479
Y1=6.85 1
Y2=6.25* 2=2.994
25 | P a g e
Bridge Design PROJECT 2012/13
Comparing the results for design truck and design tandem, Design truck governs.
785.368KNm/m
Design lane: =
=1047.55KNm
Factored Moment,
Design Truck
( )
26 | P a g e
Bridge Design PROJECT 2012/13
Design Tandem
Lane load
27 | P a g e
Bridge Design PROJECT 2012/13
Factored Moment, MU
Shear Force
28 | P a g e
Bridge Design PROJECT 2012/13
Reinforcement
( )
be=2700mm
( √ )( )
( √ )( )
Provide 15 32 bar
Development length
29 | P a g e
Bridge Design PROJECT 2012/13
Design for shear
According to art 12.8 design shear stress V, shall be computed by,
β=2.0 (Art 13.7) for non- pre stressed concrete sections and not subjected to axial
tension and containing at least minimum.
30 | P a g e
Bridge Design PROJECT 2012/13
To prevent such kind of crack the calculated steel reinforcement at service load shall not exceed
dc= depth of concrete measured from extreme tension fiber center of bar or wire located
closest the there to, shall be greater than 50mm
A=area of concrete having the same centroid as the principal tensile reinforced bounded
by the surface of the cross-section and a straight line parallel to the neutral axis, divided by the
number of bars
31 | P a g e