You are on page 1of 8

I In1bsys@

Navigate your next


I
.

IUBBSRlFAC/MoEF/2020-21/02 Date: 2i1t October 2020.

To
The Govt. of India
Ministry of Environment, Forest & Climate Change
Regional Office Eastern Zone
Al3, Chandrasekharpur
Bhubaneswar - 751 023

Kind Attn: Dr. RK. DEY, IFS, Additional Principal Chief Conservator of Forests (C).

Ref: MoEF Clearance Letter No. 21-429/2006.fA.1II.

Dear Sir,

With reference to above mentioned letter, we are submitting herewith required compliance status
as mentioned below:
As per proposed expansion of campus for Infosys Limited at E/4 Info city. Chandaka Industrial
Estate, Bhubaneswar -751024, we have completed construction of all buildings.

We are pleased to certify that we meet the various pollution norms specified in notification - 21-
429/2006-IA.1II under ref (2) carried out by reg~lar checking. We are submitting t :erewlth the hard
copies of the six monthly analysis report of Ambient Air, Noise monitoring, SoDanalysis, Ground
water as per the compliance report pertaining to April 2020 to September 2020. Also we have
malled the soft copies of analysis report to mail ld - mef.or@nic.in & roez.bsr-mef@nlc.ln,
YOI)
.-
are requested to kindly let us know If any further details need to be provided in thls !flatter. ~

Thanking you,
Yours Faithfully,

For Infoays Umrtad

Nt.1(V/h K-r Bt'.-f'Y1saJ


Navin Kumar Bansal.
Manager - Corporate Accounting Group.

Attached:
1. Compflance Report
2. Annexure -I (Monitoring Report)
3. Annexure -II (Initiative Conserve Resources)
4. Analysts reports from Apr'2020 - Sep"202Q
Copy to:
1. The Orissa State pollution control Board, Paribesh Bhawan, N118, Unit-VIII, BBSR.

INFOSVS LIMITED Corporate Office:


Plot No. E! 4, Info City ON: l8S110KAl9819t.C01311S
Bhubaneswar 751 024. India 44, Infosys Avenue
T 91 674 232 0032 Electronics City, Hosur Road
F 916742320100 BengaJuru 560 100, India
T 91 80 2852 0261
F 91 80 2852 0362
asku$@infosys.com
www.lnfosys.com
COMPLIANCE REPORT

Compliance to Environmental Clearance Letter No. 21-429/2Q06-IA.m for expansion of


campus for Infosys Limited at Ef4 Info city, Chandaka Industrial Estate, Bhubaneswar -751
024

.. .~.'
Part A: SPECIFIC CONDITIONS
I. Construction Phase

Compliance
Conditions

During construction phase, set of toilet with


septic tank and soak pit was constructed on
I All required sanitary and hygienic measures the site for construction workers.
should be In place before starting construction Presently, toilet and urinal facility Is
activities and to be maintained throughout the available at South side of the food court
construction phase. area for contract labors.

First aid facility was available at construction


office area. First aid trained personnel were
II A first aid room will be provided in the Project both available.
during construction and operation of the Project. 24 x 7 ambulance facility is available to all
• inside the campus ~ .. ...".. ..
Presently, First aid and Doctors facility Is
available within the campus.
Adequate drinking water and sanitary facilities Drinking water & sanitary facilities were
should be provided for construction workers at the provided during construction phase.
IIJ site. The safe disposal of waste water and solid Waste generated during construction phase
was processed along with the operational
wastes generated during the construction phase
should be ensured.
area wasta (was connected to existing PHE
system).
iv Provision should be made for the supply of fuel Provision for kitchen and food facility was
utensils such as pressure cooker etc. available during the construction phase.

Regular health checkups and periodical


awareness were being conducted along with
v All the labors to be engaged for construction safety awareness program. Safety standards
should be screened for health and adequately were maintained at site throughout the period
treated before engaging them to work at the site. of construction.

For disinfection of waste water, use uHras violate Waste water generated during construction
radiation, not chlorination. phase was processed along with the
vi
operational area waste (was connected to
existing PHE system).
Solid waste manapement-provide arrangements Compost pit was provided during construction
for composting biodegradable wastes at site. phase for compostlng biodegradable waste.
vii

All the top soil excavated during construction Excavated soil during construction is being
activities should be stored for use in used for filling up low area and for landscape
viii hortlcultureJlandscape development within development within the campus.
Project

Use of diesel generator sets during construction DG sets were provided with suitable acoustic
phase should be enclosed type and should metal enclosures. All D.G sets are confirmed
ill
confonn to EPA rules prescribed for air and noise to EPA Rules prescribed for air and noise
emission standards. emission standards.

Ambient noise levels should conform to residential


standards both during day and night Incremental
x pollution loads on the ambient air and noise quality Periodical checks were In place during
should be closely monitored during construction construction phase.
phase.

Construction spoils including bituminous material


and other hazardous materials must not be
xl a'Uowed to contaminate water courses and the During construction, It was ensured that the
dump sit~ for such material be secured so that hazardous waste were kept and disposed
they should not leach Into the ground water. safely to prevent contamination Of ground
. water •

The diesel generator sets to be used during DG sets have provided with suitable acoustic
construction phase should be low Sulphur diesel metal enclosures. D.G sets have confirmed to
xII type and should conform to E(P) Rules prescribed EPA Rules prescribed for air and noise
for air and noise emission standards. emission standards.

Vehicles hired for bringing construction material to


the site should be In good condition and should
xiii conform to applicable air and noise emission All vehicles have been verified for PUC
standards and should be operated only during certification.
non-peak hours,

Fly ash should be used as building material In the All the blocks used for l'Xlnstruction of walls
construction as per the provlsfons of Fly Ash were of fly ash mix.
xlv Notification of sept.1999 and amended 8S on
August,2003 The cement used for the construction
purposes are PPC.

xv Ready mixed concrete must be used in building Same was used for all construction purposes.
construction.
Stonn water control and its reuse as per CGWB
and alS standards for various applications
xvi Yes, complied during construction

Water demand during construction should be Yes, same was followed at the time of
reduced by use of pre mixed concrete, curing construction.
xvii agents and other best practices referred.

Permission to draw ground water shall be obtained No ground water was used for construction
from the competent Authority prior to constructlon purpose.
xviii I operation of the project.

Separation of grey and black water should be done Yes, same was followed at the time of
by the use of dual plumbing line for separation of construction.
xix grey and black water.

Treatment of 100% grey water by decentralized Yes, complied during construction.


treatment should be done.
xx
Fixtures for showers, toilet flushing and drinking All buildings are designed with sensor based
should be of low flow either by use of aerators or controllers for wash basin and toilets.
xxi pressure reducing devices or sensor based
control.

Use of glass may be reduced by up to 40% to Under- deck Insulation and thermos shield
reduce the electricity consumption and load on air coating In the newer buildings, to reduce the
xxII conditioning. If necessary, use high quality double heat load
External surfaces painted In pastel shades, to
glass with special reflective coating In windows.
reflects heat
High--quality reflective and double glass are
used to reduce heat Ingress and control UV
factor
Roof should meet prescriptive requirement as per Under- deck insulation and thermos shield
Energy conservation building code by using coating in the newer buildings, to reduce the
xxiii appropriate thennal Insulation material to fulfill heat load and heat transmission
requirement

xxiv Adequate measures to reduce air and noise We are following CPCB norms to reduce air
pollution during construction keeping In mind and noise pollution at the site.
epeB norms on noise fimits.
xxv Opaque wall should meet prescriptive requirement
as per energy conservation building code which is
proposed to be mandatory for all air-conditioned All the external walls are double wall.
spaces while It is asp rational for non-air
conditioned spaces by usa of appropriate thermal
Insulation material to fulfill requirement.

xxvi Disposal of Muck should not create any adverse All precautions were taken while disposal of
effect on the neighboring communities and muck.
disposed taking necessary precautions.

II. Operation Phase


The installation of the sewage treatment plant (STP) Sewage generation fram the campus is 240
should be certified by an Independent expert and Kl/d. Third party testing Is done on monthly
I) should submit a report in this regard to the Ministry basis. The sewage is treated to tertIary level
before the project Is commissioned for operation. confirming to OSPCB standards and reuses
for gardening.

Water harvesting system and energy conservation Rain water is being collected, stored and
measures like installation of solar panels for lighting reused for Landscaping.
ii) the areas outside the building should be integral part Solar Panels are Installed on terrace and
solar energy is beIng used for heating
of the project design and should be In place before
water & lighting gardens and common
project commissioning.
areas • . ;

The solid waste generated should be properly


collected & segregated before disposal to the City
UI} Municipal Facility. The In vessel bio conversion All solid waste are properly collected and
technique should be used for composting the organic segregated before disposal.
waste.

My hazardous waste including biomedical waste Hazardous and medical waste material Is
should be disposed of as per applicable Rules & sent for safe disposal to third party (OSPCB
Iv) norms with necessary approvals of the Orissa State certified waste vendor).
Pollution Control Board.

The green belt design along the periphery of the plot The landscape Is developed In approx.
shall be planned to achieve attenuation factor 40% area of the campus. There are 7500
conforming to the day and night noise standards tree species, which have planted, are of
Indigenous variety.
prescribed for residentIal land use. The open spaces
v) In the last half year, no plants & shrubs &
Inside the plot should be suitably landscaped with
creepers are added due to COV1D-19
plants of indIgenous variety pandemic situation.
Landscape development work is always In
Progress.
Incremental pollution loads on the ambient air quality, Incremental pollution loads on the ambient
noise and water quality should be periodically air quality; noise and water quality are being
vi) monitored after commissioning of the project monitored on monthly basis by third party
vendor (PCB & MOEF certified vendor)

Application of solar energy should be incorporated for Solar energy is being used to provide hot
Illumination of common areas, IIghtings for gardens water In both the Guest house and also
vII) and street lighting In addition to provisIon for solar lighting for gardens and common areas.
water heating.

Adequate measure should be taken to avoid any Entry and exit to the campus are located In
traffic congestion near the entry and exit points from such a way that it does not affect public
viii) the roads adjoining the proposed project site. traffic system on the adjoIning roads.

A report on the energy conservation measures Submitted along with application for MOEF
should be prepared incorporating details about clearance also attached highlights with this
ix) building materials & technology, R & U factors stc, report.
and submitted to the ministry in three months' time.
PART-B. GENERAL CONDITIONS

Agreed and followed.


We are certified to IS014001 and IS045OO1
STANDARDS. Infosys is the first IT company in
the world to publish its sustalnabllity report based
i) The environmental safeguards contained In on the latest Global Reporting InItiative (GRI) G4
the EIA Report should be Implemented in comprehensive frame work. GRI is the most
letter and spirit widely respected sustainability reporting
framework worldwide.

Six monthly monitoring reports should be


submItted to the ministry and its Regional
ii) Office, Bhubaneshwar. Being complied. Submitted regularly

4. Officials from the Regional Office of MOEF,


Bhubaneshwar who would be monitoring the
implementation of environmental safeguards
should be given full cooperation, facUlties and
documents! data by the project proponents
during their Inspection. A complete set of alf Agreed and is followed.
the documents submitted to MOEF should be
folWarded to the CCF, Regional office ¢f
MOEF, Bhubaneshwar.

5. In the case of any changes(s) in the scope of


the project, the project would require a fresh
appraisal by this Ministry. Point Noted

6. The Ministry reserves the right to add


additional safeguard measures subsequently,
If found necessary and to take action Including
revoking of the environment clearance under
Point Noted
the provisions of the Environmental
(Protection) Act, 1986, to ensure effective
implementatton of the suggested safeguard
measures In a tlme bound and satisfactory
manner.

7. All other statutory clearances such as the License from the Chief Controller of Explosives -
approvals for storage of diesel from Chief Ministry of Commerce and Industry
Controller of explosives. Rre Department. Petroleum and Explosives Safety organization
(PESO)
Civil Aviation Department, Forest
Ucense No: P/HQlORJ15/999(P18971) Dated
Conservation Act. 1980 and Wildlife 01.10.2002 valid 511 318t Dee 2021
(Protection) Act, 1972 etc. shall be obtained,
as applicable by project proponents from the Fire Approval: For All Buildings Fire NOe Is
competent authorities. available,
Civil Aviation: NA
Forest Conservation Act: NA
Wildlife protection Act: NA
8. The project proponent should advertise in at
least two local Newspapers widely circulated
In the region, one of which shall be in the
vernacular language Informing that the
project has been accorded environmental
clearance and copies of clearance letters are
available with the Orissa State Pollution
Control Board and may also be seen on the Done during initial stage
website of the Ministry of EnVironment and
Forests at http://www.envfor.nic.in . The
advertisement should be made within 7days
from the day of Issue of the clearance letter
and a copy of the same should be forwarded
to the Regional office of this MInistry at
Bangalore.

9. These stipulations would be enforced among


others under the provisions of Water
(Prevention and COlltrol of PollUtion) Ad,
1974 the Air (Prevention and control of Accepted. We are complying with all the rules and
Pollution) Act 1981, the Environment regulations latd against OUr projects
(Protection) Act, 1986, the Public liability
(Insurance) Act, 1991 and EIA Notification,
2006.

10 e . Under the provisions of Environment


(Protection) A~ 1986 legal action shall be
initiated against the project proponent If It was Point Noted
found that construction of the project has been
started without obtaining environmental
dearance.

11. Environmental clearance is subject to final


order of the Hon'bla Supreme Court of India in
the matter of Goa Foundation vs. Union of Point Noted
India in Writ Petition (eMI) No.460 of 2004 as
may be applicable to this project

You might also like