6.3 TESTING
TEST STEP ACCEPT N/A
(6.3.1) INSULATION RESISTANCE TEST PERFORMED ON CORE. ACCEPTANCE CRITERIA IS PER THE
MANUFACTURER’S INSTRUCTIONS OR IN ABSENCE OF MANUFACTURER’S CRITERIA NOT LESS THAN 1
MEGOHM.
(6.3.4) DC WINDING RESISTANCE MEASURED ON ALL TAP POSITIONS. VALUES SHOULD COMPARE WITH FACTORY
TEST VALUES.
WINDING TAP POSITION
(circle
one) ______ ______ ______ ______ ______ ______ ______ ______
A-B/A-N mΩ mΩ mΩ mΩ mΩ mΩ mΩ mΩ
B-C/B-N mΩ mΩ mΩ mΩ mΩ mΩ mΩ mΩ
C-A/C-N mΩ mΩ mΩ mΩ mΩ mΩ mΩ mΩ
(6.3.5) POWER FACTOR OR DISSIPATION FACTOR TEST PERFORMED ON WINDINGS, TEST SHEETS ARE ATTACHED.
ACCEPTANCE CRITERIA IS PER MANUFACTURE’S INSTRUCTIONS OR IN ABSENCE OF MANUFACTURER’S
CRITERIA USE TEST EQUIPMENT MANUFACTURER’S PUBLISHED DATA.
(6.3.6) POWER FACTOR OR DISSIPATION FACTOR TEST PERFORMED ON EACH BUSHING, TEST SHEETS ARE
ATTACHED. ACCEPTANCE CRITERIA IS PER BUSHING MANUFACTURER’S INSTRUCTIONS OR, IN ABSENCE
OF MANUFACTURER’S CRITERIA, VALUES ALONG WITH CAPACITANCE SHALL BE WITHIN 10% OF NAMEPLATE,
HOT COLLAR TESTS SHALL BE COMPARED TO TEST RESULTS FOR SIMILAR BUSHINGS.
RESISTANCE
(6.3.20) AFTER INITIAL ENERGIZATION ANDTHE REACTOR HAS REACHED NORMAL OPERATING TEMPERATURES,
POST ENERGIZATION OIL TESTS PERFORMED, LABORATORY TEST REPORT ATTACHED.
(6.3.21) PROJECT MAINTENANCE DATA BASE UPDATED TO INCLUDE ROUTINE OIL TESTING AND ON LINE GAS
ANALYZER READINGS AND ANALYZATION OF RESULTS.
COMMENTS:
6.4 RESTORATION
6.4.1 TEMPORARY MODIFICATIONS REMOVED OR TRANSFERRED TO STCP 520-U07-00226 COMPLETED
6.4.2 TEST EQUIPMENT REMOVED AND COVERS REPLACED COMPLETED
6.4.3 EQUIPMENT RESTORED TO CONDITIONS REQUIRED TO SUPPORT PLANT OPERATIONS COMPLETED
6.4.4 OPERATIONS SUPERVISOR NOTIFIED OF TEST COMPLETION COMPLETED
PERFORMED BY: DATE: