Industrial Services Division

P. O. Box 2032, Doha, Qatar.


Tel: 4469 3334, Fax: 4458 3788

M/s. Voltage Engineering Limited AC/ac/21/QB.127-Rev.02


Barwa Commercial Avenue
P.O Box
Doha
Qatar 4th October 2021
Tel : 4000 9200
Fax : 4001 6445
Mob : 7478 7385
: 7478 7274
Email : prasenjitdutta@velqatar.com
Attention: Mr. Prasenjit Dutta: Project Engineer
CC: Mr. Jishu Banerjee: Resource Control Manager
Subject: RFQ for Painting of 60 metre Communication Tower for QAF

Further to our revised quotation and subsequent conversation, we herewith offer our FINAL revised
quotation for the painting of the Communication Tower

To carry out surface preparation and painting of the tower, in accordance with the specification
proposed by M/s Hempel Paints, as detailed below.

Remove soluble salts by scrubbing with stiff bristle brush and detergent
High Pressure wash with fresh water
Lightly sweep-blast the substrate using fine abrasive
Thereafter supply and apply
1 coat Polyamide Cured Surface Tolerant Epoxy [Hempadur 45881]: dft 125 µm
1 coat Aliphatic Polyurethane topcoat [Hempathane 55210]: dft 50 µm

Colours: TBA, but as per ICAO requirements. [Red / White]

Lump Sum Amount : QRs. 82,425.00

[This is equivalent to an approximate Unit Price of QRs. 48.40/m2 against an area of 1703m2]

Apollo has considered the following inclusions / exclusions in compiling our estimate and quotation.

Inclusions (Supplied by Apollo)


 All work to be conducted on a Day Shift basis in our coatings yard at Salwa Industrial Estate, Street
38 and Unit 120.
 All coating is to be completed at the yard facility and excludes for any site remedial repairs. If any
site repairs are required, then these will be conducted on a daywork [time and materials basis]
 Supervision / Inspection and all other labors categories
 Supply of Mobile Air Compressor, blast and spray equipment and consumable items
 Transportation to/from our yard work site from Doha

F 042, Rev 0, 1st Dec 2010 1


 Supply of paint materials and cleaning agents [thinners and equipment cleaners] and blast
abrasive
 Tower structures are capable of being handled by forklift, which is available with Apollo
 Quotation valid for 180 days only from date of this quotation.
 An indication of program has been requested. Voltage suggested that a 12 -15 day program was
required, this is presently unachievable by Apollo as we are limited on manpower due to contract
commitments / pre-shutdown activities. We anticipate a period of between 24 - 30 days with the
manpower available.

Exclusions (To be supplied by Voltage Eng on a free issue basis)


 Transportation of Tower sections to/from Apollo yard
 We would require assistance in designating colours to each angle piece of the tower, as the steel
sections are identified by numbers and may not be in order for coating colour identification.
 The tower will no doubt require painting in two alternate colour [red/white, or similar] where
Voltage engineering are required to provide the correct drawings / information to identify colour
coding.
 You state there will be inspection, please advise who will be present for inspection as this work is
time critical not only for Voltage, but also for Apollo as we are preparing for shutdown activities

We enclose below our schedule of Daywork rates for manpower / equipment, should there be a need
for site remedial work.

Unit Rate
Serial Number Description Unit
Qatar Riyals

A Schedule of Manpower Rates

1 Quality Control Inspector [Painting] Per Hour 54.00

2 Safety Officer Per Hour 49.00

3 Painting Supervisor Per Hour 54.00

4 Brush Painter Per Hour 16.40

5 Blaster or Spray Painter Per Hour 18.00

6 Painting Foreman Per Hour 31.50

7 Helper Per Hour 15.80

B Schedule of Equipment Rates

1 750 cfm Compressor [Excluding Fuel Costs] Per Day 650.00

2 400 cfm Compressor [Excluding Fuel Costs] Per Day 380.00

3 After Cooler Per Day 75.00

4 Airless Spray Pump Per Day 75.00

5 Blasting Equipment Set Per Day 60.00

6 Water Washing Unit [Water NOT included] Per Day 60.00

7 Buffing Grinder [excluding consumables e.g.: pads] Per Day 6.00

8 3 Ton Pick-up, with Driver Per Day 280.00

F 042, Rev 0, 1st Dec 2010 2


9 30-Seater Bus, with Driver Per Day 320.00

10 Temperature Controlled Paint Storage Per Day 210.00

11 Office Facility for QC Inspector Per Day 128.00

12 20 KVA Generator [Excluding Fuel Costs] Per Day 155.00

Payment Terms: Invoices will be submitted on completion of the work where payment is required
within 30 days of dated invoice, or other terms to be agreed. We will also require a cheque to the
contract value to be deposited in our office prior to commencement, as a guarantee cheque. A Purchase
Order will be required prior to commencement of the work and no work will commence until Apollo
approve the Purchase Order.

We trust you find our quotation of interest and request you to contact the undersigned (mobile: 5550
0387) should there be a need for clarification, assistance or negotiation.

Yours Faithfully,
For Apollo Enterprises

Alan Crozier
Division Manager

Apollo Industrial Services


Apollo Enterprises
P. O. Box 2032,
Doha, Qatar
T: (+974) 4469 3334
M: (+974) 5550 0387
E: alan.crozier@apollo-industrial.com Enquiry: enquiries@apollo-industrial.com
W: www.apollo-industrial.com
Coatings and Linings, Resinous Floorings, Online Pipe Repair Systems, Concrete Repairs, Shotcrete and Guniting, Resin
Injection, Pressure Grouting, Ground Stabilization

F 042, Rev 0, 1st Dec 2010 3