Schneider Electric Received by:

Project: QCA2
Equipment: PANELBOARDS ATS Date:

Item
Checklist Item Responsible // Date Reference Document Status
No.
GENERAL
Installation is in conformance with the contract documents. All applicable
a
details have been checked and found in conformance.
Inspect the anchorage, alignment and grounding is complete per drawings and
b
specifications.
Resilient mounts are free and any installed shipping or temporary protective
c
materials have been removed.
All elements in the system have been inspected for damage and it has been
d
verified free from consequential damage.
e Electrical clearances verified.
f Unit is clean and free of foreign materials.
g Exterior is free from scratches, dents, tape marks, and physical damage.
h All sections and cover panels are correctly aligned and fastened.
All conductors ID tags complete and visible.
i

j All terminals are clearly marked with wire number.


k Crimping record primary and secondary conductors is complete.
l Verify all cable terminations have at least1/16" copper showing at lug.
Verify all wires are supported properly not touching sides or sharp edges.
m

TORQUE REQUIREMENTS
Using a calibrated torque wrench, verify that the tightness of all accesible
1 bolted connections, including factory installed bolts, is in accordance with the
manufacturer`s published data.
Verify each connection is marked. Torque mark colors shall be also marked on
2
an inside cover with the date of the torque.
Torque records are complete and accurate according to Owner`s torque
3
verification requirements.
Permanent nameplate label(s) match one-line drawnings (and/orper DCOps
n
coordination) and are securely fastened to unit.
Document equipment nameplate data. Verify that equipment nameplate rating
o are in accordance with the final approved or record drawnings and
specifications.
p Arc flash labels installed per final Arc Falsh Study.
q All enclosures shall be troroughly cleaned prior to be energized.

Page 1 of 2 07/08/2022
Schneider Electric Received by:
Project: QCA2
Equipment: PANELBOARDS ATS Date:

Item
Checklist Item Responsible // Date Reference Document Status
No.
Perform insulation-resistance tests for one
1 minute on each feeder - phase to phase and
phase-to-ground.
Perform ground resistance testing on
2 panelboard.

Page 2 of 2 07/08/2022