Professional Documents
Culture Documents
00 30-Sep-14
Weld Repair Verification and Inspection (API Tanks) SAIC-W-2091 8-Nov-15 WELD
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
T&I OF CONCRETE RAW WATER TANK # M-15-T-103 6511057288/6511057280 QUMAISH Y.AL-DAGHREER CO
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
N/A N/A N/A N/A
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
N/A N/A N/A N/A
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
- -2022 - -2022 SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
In addition to the spool number and line number identification, each weld shall
be identified as follows:
A) W-01R1. W-01 weld has been completed and examination has
revealed an unacceptable discontinuity that was repaired.
B) W-01R2 - W-01R1 weld repair has been completed and exam has revealed
an unacceptable discontinuity. C) W-01RW - W-
SAEP-1160,
A1 01R2 has been cut out & joint has been rewelded
Para. 6.2
D) W-01T1 - W-01 weld has been
completed. Exam revealed ... E)
W01T2 - An unacceptable weld discontinuity or HT tests have been rejected.
Progressive sampling is reqd & "tracer" welds will be identified. Repairs on
tracer welds require further sampling and the suffix numbering system shall
progress accordingly.
Welds fabricated in the field shall be prefixed with the letter 'F' and welds SAEP-1160,
A2
fabricated in a weld shop with the letter 'S'. Para. 6.2
Repair welding shall be performed using a properly qualified and approved SAES-W-017,
B1
procedure. AVAILABLE AT SITE FOR INSTRUCTION!!! Para. 17.3
If a weld is still not acceptable after a second repair, then PID has sole authority
SAES-W-017,
B2 for the decision to permit additional repair attempts or to require that the entire
Para. 17.1
weld be cut out.
Cracks that are related to the base metal or welding consumable shall be
SAES-W-017,
B4 evaluated by CSD before any repair attempts.
Para. 17.2
Crater cracks do not require special repair & shall be ground out.
OR
CO
PLANT NO.
YES
RE-INSP DATE
Weld Repair Verification and Inspection (API Tanks) SAIC-W-2091 8-Nov-15 WELD
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
If the component thickness exceeds 20 mm, or the SMYS > 290 MPa, MT or PT
of areas are performed where temporary welds have been removed, or weld SAES-W-017,
C4
repairs to ground areas of the base material have been made, or arc strikes Para. 10.9
after repair by grinding.
If any grinding reduces the base metal thickness < the design minimum, the
ground area shall be rewelded and ground flush with the original base metal SAES-W-017,
C5
surface or the component shall be replaced. Rewelding shall be done only with Para. 10.8
the prior approval SA/PID.
All welders shall be qualified in accordance with ASME SEC IX and SAEP-321, SAES-W-017,
D1
SAEP-323, and SAEP-324, as applicable, for all welding, including repair welds. Para. 8.1
All properly certified Contractor welders shall be registered by PID and issued a SAES-W-017,
D3
valid JCC prior to the start of the work. Para. 8.1
Remarks
REFERENCE DOCUMENTS:
1. SAEP-1160, Tracking and Reporting of Welding, NDT and Pressure Testing for Capital Projects, (10 July 2011)
2. SAES-W-017, Welding Requirements for API Tanks, (13 December 2011)
3. SAEP-324, Certification Review and Registration of Project Welders and Brazers, (27 September 2009)
Contractor / Third-Party Saudi Aramco
Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:
OR
GHREER CO
RE-INSP DATE
Work Verified
Work Verified
Work Verified
ES N = NO F = FAILED