You are on page 1of 4

SAUDI ARAMCO ID/Project Inspection Engineering Support Unit Rev. 2014.09.

00 30-Sep-14

SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

Weld Repair Verification and Inspection (API Tanks) SAIC-W-2091 8-Nov-15 WELD
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
T&I OF CONCRETE RAW WATER TANK # M-15-T-103 6511057288/6511057280 QUMAISH Y.AL-DAGHREER CO
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
N/A N/A N/A N/A
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
N/A N/A N/A N/A
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
- -2022 - -2022 SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL


W
CONTRACTOR INSPECTION LEVEL
H
YES
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

A Weld Identification Numbering System (As Applicable):

In addition to the spool number and line number identification, each weld shall
be identified as follows:
A) W-01R1. W-01 weld has been completed and examination has
revealed an unacceptable discontinuity that was repaired.
B) W-01R2 - W-01R1 weld repair has been completed and exam has revealed
an unacceptable discontinuity. C) W-01RW - W-
SAEP-1160,
A1 01R2 has been cut out & joint has been rewelded
Para. 6.2
D) W-01T1 - W-01 weld has been
completed. Exam revealed ... E)
W01T2 - An unacceptable weld discontinuity or HT tests have been rejected.
Progressive sampling is reqd & "tracer" welds will be identified. Repairs on
tracer welds require further sampling and the suffix numbering system shall
progress accordingly.

Welds fabricated in the field shall be prefixed with the letter 'F' and welds SAEP-1160,
A2
fabricated in a weld shop with the letter 'S'. Para. 6.2

B General Requirements (Repairs)

Repair welding shall be performed using a properly qualified and approved SAES-W-017,
B1
procedure. AVAILABLE AT SITE FOR INSTRUCTION!!! Para. 17.3

If a weld is still not acceptable after a second repair, then PID has sole authority
SAES-W-017,
B2 for the decision to permit additional repair attempts or to require that the entire
Para. 17.1
weld be cut out.

Repair of fabrication related cracks requires the approval of SA assigned


inspector. Procedure includes inspection, excavation, approved NDT methods SAES-W-017,
B3
to verify removal of defects, and rewelding per WPS. This shall be reviewed and Para. 17.2
approved by the inspector.

Cracks that are related to the base metal or welding consumable shall be
SAES-W-017,
B4 evaluated by CSD before any repair attempts.
Para. 17.2
Crater cracks do not require special repair & shall be ground out.

The repair procedure may utilize a welding procedure previously approved by


SAES-W-017,
B5 CSD in conjunction a separate method statement, or it may be a separate
Para. 17.4
detailed welding procedure.

Repaired welds shall, as a minimum, be inspected using the original testing


SAES-W-017,
B6 method. Additional test methods (NDE, HT, PMI, etc) are also required, if
Para. 17.5
deemed necessary by the authorized SA Inspector.

C Repair of welds and base metal :

Damage or deformation to the base metal or welds, including dimensional


changes, caused by external forces (intentional or accidental) requires special
repair and inspection procedures be submitted to Saudi Aramco Inspection and
if necessary forwarded to CSD for review and approval prior to undertaking the SAES-W-017,
C1
repairs. All external bulging, Para. 17.6
deformation and damages shall be evaluated by a certified API 653
Inspector or Tank Engineer experienced in repair prior to the beginning of
any work.

Saudi Aramco: Company General Use


ER

OR
CO
PLANT NO.

PMCC / MCC NO.


N/A
TRAVEL TIME
SE ONLY
ORK PERMIT REQUIRED?

YES
RE-INSP DATE

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/Project Inspection Engineering Support Unit Rev. 2014.09.00 30-Sep-14

SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

Weld Repair Verification and Inspection (API Tanks) SAIC-W-2091 8-Nov-15 WELD
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

T&I OF CONCRETE RAW WATER TANK # M-15-T-103 6511057288/6511057280 QUMAISH Y.AL-DAGHREER CO

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

Arc strikes, gouges, and other indications of careless workmanship (such as


SAES-W-017,
C2 surface porosity, uneven weld profiles, and undercut) shall be removed by
Para. 10.6
grinding.

Temporary welded attachments or temporary tack welds shall be removed by a


method that will not cause tearing or bending of the base metal. The method
used shall not reduce the thickness of the base metal below the minimum
specified thickness. (Technique) 1. Tank
construction aids (temporary attachments) holding shell courses together
shall not be removed by hammer. 2. Rather,
SAES-W-017,
C3 grinding of temporary welds shall be sufficient to decrease weld size so
Para. 10.7
that attachments can be tapped off and removed by hammer, not beaten.
One hand taps with the hammer and one hand holds the attachment from
fall. 3. Complete repairs by removing all weld
protrusions flush to sound metal & MT.
EVIDENCE OF HAMMER MARKS ARE UNACCEPTABLE TO
SA.

If the component thickness exceeds 20 mm, or the SMYS > 290 MPa, MT or PT
of areas are performed where temporary welds have been removed, or weld SAES-W-017,
C4
repairs to ground areas of the base material have been made, or arc strikes Para. 10.9
after repair by grinding.

If any grinding reduces the base metal thickness < the design minimum, the
ground area shall be rewelded and ground flush with the original base metal SAES-W-017,
C5
surface or the component shall be replaced. Rewelding shall be done only with Para. 10.8
the prior approval SA/PID.

D Welder & Welding Operator Qualification:

All welders shall be qualified in accordance with ASME SEC IX and SAEP-321, SAES-W-017,
D1
SAEP-323, and SAEP-324, as applicable, for all welding, including repair welds. Para. 8.1

All properly certified Contractor welders shall be registered by PID and issued a SAES-W-017,
D3
valid JCC prior to the start of the work. Para. 8.1

Remarks

REFERENCE DOCUMENTS:
1. SAEP-1160, Tracking and Reporting of Welding, NDT and Pressure Testing for Capital Projects, (10 July 2011)
2. SAES-W-017, Welding Requirements for API Tanks, (13 December 2011)
3. SAEP-324, Certification Review and Registration of Project Welders and Brazers, (27 September 2009)
Contractor / Third-Party Saudi Aramco
Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:
khaleem khan
QC Supervisor Proponent and Others
Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED

Saudi Aramco: Company General Use


ER

OR

GHREER CO

RE-INSP DATE

Work Verified

Work Verified

Work Verified

ES N = NO F = FAILED

Saudi Aramco: Company General Use

You might also like