Professional Documents
Culture Documents
JULY 2021
UNIVERSITI TEKNOLOGI MARA
PRACTICUM – LAND
SURVEY BASED
(GLS396)
PREPARED BY:
NURUL IZZAH BINTI ZULKURNIAN
JULY 2021
PARTITION SURVEY ON LOT 4149, MUKIM 8, SEBERANG PERAI UTARA
DISTRICT, PULAU PINANG
Prepared By:
NURUL IZZAH BINTI ZULKURNIAN
2018204474
JULY 2021
A project report submitted in partial fulfilment of the
Requirement for the award of the
Diploma in Geomatic Science.
(AP120)
NURUL IZZAH BINTI ZULKURNIAN
19 th JUNE 2000
JULY 2021
000619-08-0172
31 st JULY 2021
I
CANDIDATE’S DECLARATION
I declare that this report entitled “Partition Survey on Lot 4149, Mukim 8, Seberang
Perai Utara District, Pulau Pinang” is result of my own works except as cited in the
references. The report has not been accepted for any diploma and is not concurrently
in candidature of any diploma.
Signature of Student :
……………………………………..
II
This Report Delivered to Department of Surveying Science and Geomatics
Prepared by:
Student ID : 2018204474
Approval by:
III
EXECUTIVE SUMMARY
This internship report based on 5 month long of industrial training program that I have
undergoes at Jurukur Hikmah under branch survey of cadastral. My chosen project f or
cadastral survey included in this report is entitled Partition Survey on Lot 4149, Mukim
8, Seberang Perai Utara District, Pulau Pinang. It was appointed by client to carry out
partition survey. This project was held with area 0.9218 Ha. The purpose of this project
is to do partition into three (3) separate lots with same area which is 0.30727 Ha. The
processes involved in implementing this project is by do site visit and reconnaissance
first. Then, implemented preparatory work and carry out survey work. New number lot
was given by JUPEM after finished all the survey work, which is 20529, 59530 and
50531. The survey work was referred to the “Plan Cadangan”. Lastly, do data processing
and preparation of plan. At the end of this project, a separate title for each lot is
produced.
IV
ACKNOWLEDGEMENT
First, I would like to thank to Allah S.W.T. because with His blessings an d permission
all geomatic students has completed the practical for 16 weeks which is 6 weeks f or
Cadastral work, 5 weeks for Engineering work and 5 weeks for Hydrography work.
The internship opportunity I had with Jurukur Hikmah was a great chance for learning
and professional development. Therefore, I consider myself as a very lucky individual
as I was provided with an opportunity to be a part of it. I am also grateful for having a
chance to meet so many wonderful people and professionals who led me though this
internship period. Bearing in mind previous I am using this opportunity toexpress my
deepest gratitude and special thanks to the Sr Hj. Fakhrul Azman bin Hj. Ali, Director,
and a Licensed Surveyor of Jurukur Hikmah who is willing to give the opportunity for
me to do the internship there.
V
TABLE OF CONTENT
PAGE
DECLARATION OF INDUSTRIAL TRAINING REPORT I
CANDIDATE’S DECLARATION II
EXECUTIVE SUMMARY IV
ACKNOWLEGMENT V
LIST OF TABLES X
LIST OF FIGURES XI
1.3.1 Vision 4
1.3.2 Mission 4
VI
1.4.3 Topography Survey 6
VII
2.10 Week 10 (24 May – 28 May 2021) 13
3.5 Quotation 21
VIII
3.7.3 Calibration and Field Check 24
3.7.4 Differential Field Test (DFT) 26
3.7.5 Methodology of Fieldwork 28
3.8 Data Processing 32-47
3.8.1 List of Software 33
3.8.2 Calculation Volume 34
3.8.3 Bowditch Adjustment 35
3.8.4 Linear Misclosure 35
3.8.5 Baseline Calculation 37
3.8.6 Third Mark Calculation 39
45
CHAPTER FOUR: CONCLUSION
50
4.1 Conclusion of Project 50
4.2 Suggestions 50
REFERENCES 51
APPENDIX A 52-55
APPENDIX B 56-60
IX
LIST OF TABLES
X
LIST OF FIGURES
XI
LIST OF ABBREVIATIONS
CP - Certified Plan
QT - Qualified Title
ASCII - American Standard Code for Information Interchange
JUPEM - Jabatan Ukur dan Pemetaan Malaysia
PKPUP - Pekeliling Ketua Pengarah Ukur dan Pemetaan Malaysia
LLS - Licensed Land Surveyor
CV - Calculation Volume
CSR - Cadastral Survey Regulations
CAD - Computer Aided Design
TBM - Temporary BenchMark
MCO - Movement Control Order
LJT - Lembaga Jurukur Tanah
EDM - Electronic Digital Measurement
DFT - Differential Field Test
CRM - Cadastral Reference Mark
NDCDB - National Digital Cadastral Database
BKB - Batu Konkrit Baru
BKL - Batu Konkrit Lama
BL - Batu Lama
XII
CHAPTER 1
INTRODUCTION
This company is own by Licensed Land Surveyor who is also act as Director to
this company, Sr Hj. Fakhrul Azman bin Hj. Ali. The following are the
information of the Licensed Surveyor.
1
Education :
• High School Bukit Mertajam, (1987-1991)
• Diploma in Land Surveying, ITM, Shah Alam (1992-1995).
• Bachelor Surveying Science & Geomatic (Hons), UiTM (1995-1997).
• Underground Utility Detection Survey ( No 115) , LJT (2017)
• FIG/IHO/ICA CATEGORY A (Hydrography), UTM (2018-2019
Working Experience :
• 1997 - Dec 2000 : Jurukur at Firma JURUKUR LATIFF
• May 2007 – April 2008 : Jurukur Kedah Utara District (Alor Star)
2
1.1.2 Company Registration Name
This company was registered under LJT as Licensed Land Survey company
entitled JURUKUR HIKMAH (LJT 529).
No. 20,
Tingkat 1,
Lorong Perda Utama 7,
Bandar Perda,
14000 Bukit Mertajam,
Pulau Pinang.
3
1.3 Company Overview
Jurukur Hikmah is survey consultant firm that has been established since 2012 and
fully owned by licensed land surveyor, Sr Hj. Fakhrul Azman bin Hj. Ali. This firm as
identify as registered with LEMBAGA JURUKUR TANAH (LJT) Semenanjung
Malaysia. The firm objective is to establish a survey consultant firm that provide
highest quality of survey works that will ensure the successful achievement to each
development projects acquired by clients. Also, with highly skilled and professional
employees and high technology equipment. We ensure to be ready in accepting any
survey works incoming with highest capability of execution following the correct
procedures and rightful work ethic.
1.3.1 Vision
To provide advisory services as consultants to government agencies, p rivate companies,
and individuals in maximizing land use for development purposes.
1.3.2 Mission
The aim of J urukur Hikmah is to create a name as a Land Survey Consultancy firm that
produces high quality survey work to ensure the success of every development project that will be
implemented by its clients. With sufficient equipment and a wide range of experienced,
competent, and dedicated staff, we are ready to accept any offer of survey work within
the scope of our services and will be carried out in accordance with professional survey
procedures and procedures. We adhere to the fact that measuring works are very
important in any development projects and that they need to be ca rried out with high
precision to suit those projects. We will not consider whether a project to be implemented
is large or small, our philosophy remains the same as to provide services and produce
high quality of work.
4
1.4 Services and Function Provided by Jurukur Hikmah
Jurukur Hikmah offering many services and survey consultant as follow below.
7
1.5 Organization Chart
Licensed Land
Surveyor
Sr Hj Fakhrul Azman
Bin Hj. Ali
Administrative
Technical Manager
Executive
Rizaudin Bin Yusoff
Nor Shuhana Binti Taha
Site Team
1. Mohamad Khairi Bin
Mahmud
Technical/Processing
2. Shahrul Nizam Bin
1. Aida Orkid Binti
Mohd Rosek Ahmad
Administrative
3. Shamsul Bahari Bin 2.Rodziatul Adawiyah
Abdul Rahman Nor Shakirah Binti Abd Binti Azimi
4. Muhamad Mazree Bin Manas 3.Mohamad Firdaus
Abdullah Bin Ayob
5. Muhammad Syazani
Bin Muhammad KhairiI
6. Haris Murshidi Bin
Bukhari
7. Muhamad Huzaifah
Bin Fakhrul Azman
8. Muhamad Nurzikri Bin
Zilmajdi
8
1.6 Scope Of Works by Each Department.
1.6.1 Administration
1.6.2 Technical
1.6.3 Fieldwork
9
CHAPTER 2
SUMMARY OF DUTY
10
Figure 2.1 : Example of Pre-Computation Plan Done by Student
11
2.4 Week Four (12/04/2021 – 16/04/2021)
I have been instructed to do a site survey for partition at Chenaam, Pulau
Pinang. We used Topcon Sino T300 to find the point area and if we cannot
detect the area, we used another method using total station due to the
obstacles to reach the receiver. Then I search foe the data needed for report
and continue my report and update my logbook.
12
On this week, I spent my time to do report and update the logbook as this
week is a holiday week in conjunction with Hari Raya Aidilfitri.
13
This week, since there is not much work to do, I took this opportunity to
study any files related to cadastral survey work. So that, I can get to know
how this survey work is carried out included the process involved. I also
search any files and relevant data related cadastral survey work to make a
report soon.
14
CHAPTER 3
WORKING EXPERIENCE
This project was appointed by client to carry out partition survey. This project was held
with area 0.9218 Ha. Survey work related to cadastral are carried out that aimed to
obtain separate title for each parcel which is parcel 1 and parcel 2. The processes
involved in implementing this project is by do site visit and reconnaissance f irst. Then,
implemented preparatory work and carry out survey work. New number lot was given by
JUPEM after finished all the survey work, which is 20529, 59530 and 50531. The survey
work was referred to the “Plan Cadangan”. Lastly, do data processing and preparation of
plan. At the end of this project, a separate title for each lot is produced.
• do partition into three (3) separate lots with same area which is 0.30727 Ha.
• To obtain separate title for each parcel which is parcel 1 and parcel 2 as
requested by clients on lot 4149, Mukim 8, Seberang Perai Utara
District, Pulau Pinang.
15
3.3 Scope of Works
In this project, there are three (3) stages to be completed to complete this
job which are:
- Pre-computation plan
16
3.4 Study Area
3.4.1 Location of Site
17
3.4.2 Flow Of Works
Application
File registration Fieldwork
approval
Data processing
18
3.4.3 Explanation of Workflow
iii. Quotation
v. Application approval
• Received Sijil Akuan from Land Office after settle the payment by the client
to Lembaga Jurukur Tanah (LJT).
19
vi. Fieldwork
• Instrument Calibration
• Generate 16 ASCII
20
3.5 Quotation
Quotation is the cost regards the survey works from the beginning until the
last part which is produce final plan. It must calculate all the cost before the
survey is carrying out and need to give to the client. All the fees are f ixed and
follow the LJT. The quotation attached at Appendix A.
v. Sijil Akuan
21
3.7 Data Acquisition
22
3.7.2 Instrument Used for Cadastral Survey
Survey equipment was always an important asset to any licensed surveyor firm. the
equipment was always ensured to be calibrated for our observation will always in top
notch condition.
Instruments Function
Tripod
to support any one of a number of
surveying instruments
Prism
Used as a target for distance
measurement
23
3.7.3 Calibration and Field check
i. Daily Check
Daily check should be carried out at the start of the everyday job. It can be
done by re- measuring the distance of the last surveyed line on the previous
day. If the error is greater than 10mm, the differential field test needs to be
carried out to determine the instruments are acceptable working order.
24
iii. EDM Baseline Test
An EDM baseline test should be performed to ensure the correct operation of a pair of
GPS receivers and data processing software that will be used for baseline measurement.
• The GPS instrumentation shall be tested on an EDM baseline that itself has
been calibrated to a local standard of distance using a special a high quality EDM
instrument.
• The test shall be used to study the precision of the receiver measurements (and
hence its correct operation),as well as validate the data processing software.
• The test should be carried out at an established EDM baseline test site, by
occupying pillars with at least 90% sky visibility.
• The GPS receivers should be tested against the established EDM baseline lengths
(between pillars), varying from twenty (20) meters to about one (1) kilometer.
• Each GPS receiver is to be connected to its designated antenna (mounted on
the pillar) using the same antenna cable used during surveys.
• The test should be performed for a minimum of ten (10) minutes observation
sessions.
• The receivers shall track at least five (5) satellites during the test session with a
GDOP of less than six (6).
• Cut-off angle of fifteen degrees (15°) should be applied during the baseline
processing.
• The resulting difference in slope distance between the GPS measurement and
the standard must be less than ten (10) millimeters. If this tolerance is not met the
test should be repeated, and if the equipment fails again the instrument should be
returned to the GPS agent for repair.
25
3.7.4 Differential Field Test (DFT)
The differential field test should be carried out at the starting new survey job. It is
important to ascertain if the EDM is the acceptable working order. The differential f ield
test can be done in the traverse line which is on the first line or second lin e of the
traverse. The procedure for DFT is:
1. Set up the total station at STN A and the prism at STN B with the distance
140.532m. Observe and record the data into the field book.
2. Move the total station at STN C on the line between STN A and STN B.
3. Measure CA and CB.
4. Compare the distance AB with the resultant of CA and CB.
5. Calculate the tolerance of the observation to know the result.
A 140.532m B
A 65.89m C 74.635m B
26
• Calculation of DFT
27
3.7.5 Methodology and Fieldwork
Site Visit is required before starting a job to determine the location and scope
of work provided. The purpose was carrying out to planning our work. During
reconnaissance survey, boundary mark can be found as much as can that in
the good quality. So, wecan do a planning for starting datum.
a. Datum
Datum serves as a starting point for surveying projects and help to put your work in a
large context. A datum, on the other hand, can be any reference used to measure an
object, such as planes, lines, or points. Geodetic datum is points that are used in
surveying. Horizontal and vertical geodetic datum is the two types of geodetic datum.
There are 3 types of datum that has been mentioned in Pekeliling Ketua Pengarah Ukur
dan Pemetaan (PKPUP) 6/2009 which is:
28
i) Cadastral References Mark (CRM)
In this work, we used three boundary marks that in good position as our datum to
start survey works.
b. Traverse
Traverse is one of the methods for data collection. It is a series along the lines or
network. It has two types which is closed traverse and open traverse. For closed
traverse, we have polygon and link. For this project, we used closed traverse and it is
polygon. During doing the traverse, we picked up any boundary marks for this lot and
certain for its adjacent lot.
Procedure of traversing:
1. Set up total station and prism on the selected Batu Konkrit Lama (BKL).
2. Start the traversing with known bearing and distance based on CP.
3. Booking the traverse data using booking form.
4. Calculate and apply c-correction using bearing misclosure formula.
29
Figure 3.8 : Traverse Diagram
30
c. Field book
Field book is the booking form during survey work which is standard to all LLS and
JUPEM. It is very important to write down all important data especially about data
collection. In this booking form, we wrote all data about traversing which is starting fro m
datum until closed bearing. So, we can calculate the m-correction and c-correction. The
field book for this survey work attached on Appendix B.
d. C-correction
The error can be eliminated by doing m-correction and c-correction. M-correction is the
correction of the orientation is applied in all traverse networks. It can be orientated either
in negative which is anti-clockwise or positive which is clockwise. It also depends on the
calculation of proving the true azimuth by solar observation. However, c -correction is
applied to all closed traverse either polygon or link traverse. In this project, we just apply
c-correction by using this formula:
Calculation of c-correction:
Garisan 2-1 dibaca 320°29‟08”
Sepatut dibaca 320°29‟08”
Tikaian ialah 0°00‟00” dlm 9 stn iaitu 2,3,5,6,7,8,11,12,2
Pembetulan ialah +0°00‟00” satu stn
According to CSR 2002, tolerance for traverse correction must be not exceeding
1‟15” for the first-class survey of bearing misclosure. In this booking of
traverse, the c- correction is +0” which is acceptable.
31
3.8 Data Processing
Data processing is process of carrying out of operations on data, especially by computer
to retrieve, transform or classify information. After all the fieldwork was done, all the
data will be transferred then, it will be processed in the CAD software. The flow of data
processing is as follow:
Compute offset of
Produce final CP
re-fixation
32
3.8.1 List of Software
Survey equipment such as software is an important asset of a Licensed
Surveyor firm. The software is used to process the data that had been recorded
or received. Without the software that the surveyors used now, their survey
work may had been complete in a long period or cannot be completed at all.
Below are the softwares used for this project:
Software Picture
BRICSCAD V7 PRO
T ITOOL
33
3.8.2 Calculation Volume
The calculation volume represents as a summary report of cadastral calculation that
consists of lot number, final bearing and distance, field book reference number, final
coordinates, lot station and no, area of lot and lot precision.
34
3.8.3 Bowditch Adjustment
Bowditch adjustment is one of the strategies essentially utilized in adjusting the linear
misclosure of the traverse network. This strategy changes the latitudes and departures of
the traverse network about their lengths. The error is circulated by adjusting the linear
misclosure.
ADJUSTED ADJUSTED
STN DISTANCE BEARING LATITUDE DEPARTURE LATITUDE DEPARTURE COORDINATES
(m)
N S E W N S E W N/S E/W
2 9430.111 6806.855
3 187.483 250 52 10 61.442 177.129 61.442 177.130 9368.669 6629.726
5 65.745 336 51 20 60.454 25.841 60.454 25.8410 9429.123 6603.885
6 63.950 337 51 20 59.233 24.105 59.233 24.105 9488.356 6579.780
7 54.715 313 52 50 37.926 39.438 37.926 39.438 9526.282 6549.342
8 161.448 54 38 40 93.422 131.673 93.422 131.673 9619.704 6672.015
11 91.115 146 48 10 76.244 49.888 76.244 49.888 9543.460 6721.903
12 76.295 144 24 10 62.038 44.410 62.038 44.410 9481.422 6766.313
2 65.395 141 41 10 51.311 40.543 51.311 40.543 9430.111 6806.856
TOTAL DIFF = DIFF = DIFF = DIFF =
=766.146 251.034 251.035 266.514 266.514
-0.001 0.000
35
Calculation of Linear Misclosure:
(∆𝑙𝑎𝑡i𝑡𝑢𝑑𝑒) ² + (∆𝑑𝑒𝑝𝑎𝑟𝑡𝑢𝑟𝑒) ²
𝑇𝑟𝑎𝑣𝑒𝑟𝑠𝑒 𝐷i𝑠𝑡𝑎𝑛𝑐𝑒
√(∆𝑙𝑎𝑡i𝑡𝑢𝑑𝑒) ² + (∆𝑑𝑒𝑝𝑎𝑟𝑡𝑢𝑟𝑒) ²
=
𝑇𝑟𝑎𝑣𝑒𝑟𝑠𝑒 𝐷i𝑠𝑡𝑎𝑛𝑐𝑒
√ (−0.001 ) ² +(0.000) ²
=
766.146
= 1 / 0.00056
= 1365478
= 1: 1365478
The accuracy of linear misclosure must not be less than 1:8000 for the first class. Based
on the calculation using the Bowditch method for the traverse, the linear misclosure is 1:
1365478 which are acceptable.
36
3.8.5 Baseline Calculation
A baseline is a connection line between two boundary marks that have been proven to
be in their original position using a calculation based on the traverse.
Calculation of Baseline:
37
Bearing PO (BKL 22 – BKL 13) = 100 42 39
Distance PO (BKL 22 – BKL 13) = 210.927
38
3.8.6 Third Mark Calculation
The third mark is any boundary marks that have been proven to be in their original
position which is an independent checking for baseline.
39
ii. PO Third Mark (BKL 16 – BKL 22)
Difference Bearing = 00 00 01
Difference Distance = 0.001m
40
3.8.7 Interior Angle Calculation
41
New
PO
Comparison NEW – PO
= 55 58 26 – 55 58 21
= 00 00 05
42
3.8.8 Bearing Factor Calculation
= 100 42 35 – 100 42 39
= -00 00 04
43
3.8.9 Distance Factor Calculation
= 210.936m / 210.927m
= 1.000042669 m
Distance (PO)
STN Distance Factor Adjusted Distance
(m)
(m)
BKL 13 – BKL 16 174.870 174.887
BKL 16 – BKL 22 113.430 113.435
BKL 22 – BKL 23 4.080 4.080
BKL 23 – BKB 24 19.029 1.000042669 19.030
BKB 24 – BL 21 43.309 43.309
BL 21 – BL 20 3.780 3.780
BL 20 – BL 19 15.600 15.601
BL 19 – BL 17 36.860 36.862
BL 17 – BKB 25 153.704 153.711
BKB 25 – BKL 13 56.700 56.702
44
3.8.10 Offset Calculation
45
Table 3.14 : Offset STN 5 – BKB 18
46
Table 3.16 : Offset STN 3 – BKB 15
47
3.9 Result and Analysis
3.9.1 Submission ASCII
By using the software to process the data, ASCII files can be generated then submit to
JUPEM. These are the following ASCII file:
48
3.9.2 Final Product
At the end of the project, the Certified Plan was produced by JUPEM as a final product.
49
CHAPTER 4
RFERENCES
50
i. Format Laporan
ii. Panduan Laporan
iii. Example Report / Template given by Lecturer
iv. Raw Data from Company
v. Sr Hj. Fakhrul Azman Ali (2021), Director, Jurukur Hikmah
vi. Mohamad Firdaus bin Ayob (2021), Project Manager, Jurukur Hikmah
vii. Gua Langsuir Kilim, Karst Geoforest Park, Mukim Ayer Hangat, Langkawi.
Retrieved from
https://www.google.com.my/maps/place/Gua+Langsuir/@6.4187871,99.8804617,
741m/data=!3m2!1e3!4b1!4m5!3m4!1s0x304c7df8b214a235:0x2cb85a84d5739c
e!8m2!3d6.4187818!4d99.8826504
viii. Mohd Adhar Abd Samad, Mohamad Azril Bin Che Aziz, Hj Ahmad Nadzari Yahaya
(2018), Introduction To Cadastral Survey, Edition 2, Arau , Perlis, Universiti
Teknologi Mara.
ix. Lot 4149, Mukim 8, Sebarang Perai Utara, Pulau Pinang. Retrived from
https://iplan.townplan.gov.my/public/geoportal?view=semasa
x. Mukim 8, Seberang Perai Utara, Pulau Pinang. Retrived from
https://www.google.com.my/maps/place/Mukim+8,+Kepala+Batas,+Pulau+Pinang/@
5.5060598,100.4051682,676m/data=!3m1!1e3!4m5!3m4!1s0x304ad075fe445b6f:0x31
fc905351852ca1!8m2!3d5.4961546!4d100.4399189
xi. Cadastral Survey Regulations 2002
xii. Pekeliling Ketua Pengarah Ukur dan Pemetaan (PKPUP) 6/2009
51
APPENDIX A
QUOTATION
52
53
54
55
APPENDIX B
FIELDBOOK
56
57
58
59
60