Professional Documents
Culture Documents
Qtct2 Wor QBC Aud Rep 00001 00
Qtct2 Wor QBC Aud Rep 00001 00
Audit Ref. No: QTCT2-WOR-QBC-AUD-RPT-00001 Date: 10th Feb 2020 to 22nd Feb 2020 Form Ref. No. QMF-0037
PQP Section 16
Control of inspection & measuring & Test Equipment.
5 +OBS ISO 9001:2015 Cl.7.5 N/A N/A N/A N/A
Evident with register and test certificates.
QCS 2014 S 02, P 02, Cl 2.1.1
PQP S.09/ PQP was submitted at the early stage of the project. No clear information from QBC to Ensure that in future Clarification from the client to be made on the use of
8 Electronic Data Management System(Aconex) to be AFI Electronic Data Management System(Aconex) to be included in next Verified the contractor response and closed
ISO 9001:2015 Cl.7/ the SC on the Electronic Data Management System(Aconex) to be used for the any Electronic Data Management System(Aconex) and to be included PQP
included in next submittal of PQP submittal of PQP
QCS 2014 S.02,P.04. project submittal.
PQP 06/
9 Competence and Qualification records not evident. AFI Competence and Qualification records was not maintained at the project site Copy of Competence and Qualification records to be provided Copy of Competence and Qualification records to be maintain Verified the contractor response and closed
ISO 9001:2015 Cl.5&7/
office
QCS 2014 S.02,P.02, CL 2.1.2
PQP S.08/
10 Quality Briefings communications at site for every AFI Quality briefings was conducted but records was missing Quality briefing to be provided QBC to ensure Quality briefing records are filed and maintain. Verified the contractor response and closed
ISO 9001:2015 Cl.5/
start of the activity must be recorded.
QCS 2014 S.02,P.01, CL 1.1.4
PQP S.15/
11 NCR register overdue close out date and CAPA AFI Original NCR due date was not complied and some Correction and corrective Revised close out date to be provided and Correction and corrective action QBC to ensure that NCR close out completed upon the schedule date and Verified the contractor response and closed
ISO 9001:2015 Cl.7/
meetings. action (CCA) was delayed pending technical verification (CCA) to be submitted Correction and corrective action are submitted
QCS 2014 S.02,P.11 & 12
PQP S.17/
Internal Audit was conducted. Evidence was not requested by the auditor QBC to esure that draft of the Audit findings from auditor is obtain and to avoid
14 Audit Plan and Internal Audit not evident. MCAR ISO 9001:2015 Cl.9.2 Copy of updated Audit Plan to be provided Verified the contractor response and closed
during audit miscommunication
QCS 2014 S.02,P.06,Cl.6.1.1
PQP S.05/
15 Key Performance Indicator not evident MCAR ISO 9001:2015 Cl.9.1/ Specific Key performance indicator were not prepared Copy of Key performance Indicator to be provided QBC to ensure copy of Key performance Indicator is maintained is maintained Verified the contractor response and closed
QCS 2014 S.02,P.02,CL.2.1.5
PQP S.05/
16 Training Records and schedule not evident MCAR ISO 9001:2015 Cl.7/ Training records was not maintained Copy of Training records to be provided QBC to ensure copy of Training records and schedule is maintained Verified the contractor response and closed
QCS 2014 S.02,P.03,CL 3.1.8
PQP S.05/
17 NCR register overdue close out date MCAR ISO 9001:2015 Cl.7/ Original NCR due date was not complied Revised close out date to be provided QBC to ensure that NCR close out completed upon the schedule date Verified the contractor response and closed
QCS 2014 S.01,P.23,CL.23.3.2
PQP S.05/
No Continual Improvement in PQP & Lessons Learnt
18 MCAR ISO 9001:2015 Cl.7/ Records of lesson learned was not maintain in the site office. Copy of the lesson learned to be provided Records of Lesson learned to be maintain at site office Verified the contractor response and closed
Register not evident.
QCS 2014 S.02,P.02,CL.2.1.1,3(x)