Professional Documents
Culture Documents
Chapter 6 Tunnelling Method TBM 2021
Chapter 6 Tunnelling Method TBM 2021
6.
Tunnelling Method
2.
TBM
INTRODUCTION
1
14/09/2021
2
14/09/2021
Tunnelling approaches
• New Austrian Tunnelling Method (NATM)
• Norwegian Method of Tunnelling (NMT)
• Analysis of control deformation in rocks and
soils (ADECO_RS)
• (translated from Italian)
INTRODUCTION
3
14/09/2021
INTRODUCTION
Introduction
• The first successful tunnelling shield was
developed by Sir Marc Isambard Brunel to
excavate the Thames Tunnel in 1825
• In the United States, the first boring machine
to have been built was used in 1853 during
the construction of the Hoosac Tunnel.
4
14/09/2021
Introduction
• Engineers should not use TBM where
engineering geological investigations
have not been done in detail and the
rock mass conditions are very
heterogeneous.
Introduction
• Contractors can design
TBM according to the
given rockmass
conditions which are
normally homogeneous
non-squeezing ground
conditions.
• TBM is unsuitable for the
squeezing or flowing
grounds (Bhasin, 2004).
5
14/09/2021
Introduction
• A tunnel boring machine (TBM) is used to
excavate tunnels with a circular cross section
through a variety of soil and rock strata.
• They can bore through hard rock, sand, and
almost anything in between.
• Tunnel diameters can range from a meter (done
with a micro-TBMs) to almost 16m to date.
• Tunnels of less than a meter or so in diameter are
typically done using trenchless construction
methods or horizontal directional drilling rather
than TBMs.
MICROTUNELLING
TERRATEC MTBMs are suitable for the construction of
tunnels with an inner diameter ranging from 500mm up
to 2,800mm.
6
14/09/2021
Introduction
• Tunnel boring machines are used as an alternative to drilling
and blasting (D&B) methods in rock and conventional ‘hand
mining’ in soil.
• TBMs have the advantages of limiting the disturbance to the
surrounding ground and producing a smooth tunnel wall.
• This significantly reduces the cost of lining the tunnel, and
makes them suitable to use in heavily urbanized areas.
• The major disadvantage is the upfront cost. TBMs are
expensive to construct, and can be difficult to transport.
• However, as modern tunnels become longer, the cost of
tunnel boring machines versus drill and blast is actually less
this is because tunnelling with TBMs is much more efficient
and results in a shorter project.
Introduction
• The largest diameter TBM, at 15.43 m, was built by
Herrenknecht AG for a recent project in Shanghai,
China.
• The machine was built to bore through soft ground
including sand and clay. The largest diameter hard
rock TBM, at 14.4 m, was manufactured by The
Robbins Company for Canada’s Niagara Tunnel
Project.
• The machine is currently boring a hydroelectric tunnel
beneath Niagara Falls, the machine has been named
“Big Becky” in reference to the Sir Adam Beck
hydroelectric dams to which it is tunneling to provide
an additional hydroelectric tunnel.
7
14/09/2021
8
14/09/2021
PRINCIPLE
• The principle of TBM is to push cutters against
the tunnel face and then rotate the cutters for
breaking the rocks in chips
WORKING OF TBM
• A TBM is shaped like a tube.
• At the front is a rotating disk with cutting
teeth that can shear through rock
• The pulverized rock falls to a conveyor belt
that carries it to the back of the TBM
• Hydraulic feet grip the sides of the tunnel and
push the machine forward
• There is also the ability to insert plates to line
the interior of the tunnel
9
14/09/2021
WORKING OF TBM
Cutting head
10
14/09/2021
WORKING OF TBM
WORKING OF TBM
11
14/09/2021
WORKING OF TBM
APPLICATION
• IN ROAD TRAFFICS
• IN SEWERS
• IN MININGS
• IN RAIL TRAFFICS
• IN HYDROPOWER
12
14/09/2021
13
14/09/2021
GRIPPER TBM
14
14/09/2021
GRIPPER TBM
GRIPPER TBM
15
14/09/2021
GRIPPER TBM
16
14/09/2021
GRIPPER TBM
GRIPPER TBM
17
14/09/2021
18
14/09/2021
19
14/09/2021
20
14/09/2021
21
14/09/2021
22
14/09/2021
23
14/09/2021
24
14/09/2021
25
14/09/2021
26
14/09/2021
27
14/09/2021
28
14/09/2021
29