Measurement
Item Description of work Chapter / Operation Sheet
1 Liners air leak test before starting of works E1
INJECTION
16 Removal & refitting of injection pipes 02-01
17 Removal & refitting of the injectors 02-02
MOVING ELEMENTS
22 Removal & fitting of the piston-connecting rod (CR) assembly 03-02 E2
Cylinder liners and water jacket removal, liner extraction,
23 replacement of o-rings and vibration dampers 03-10 E2
24 Visual & dimensional inspection of liners 03-03 E12
25 Cylinder liners dye penetration checking E13
26 Water jacket dye penetration checking
03-06,
Service Bulletin
27 Honing of liners 480927/11.04.06
Measurement
Item Description of work Chapter / Operation Sheet
28 Replacement of ABPR (Anti Bore Polishing Rings) E40, E41
Inspection of the protection of cylinder head tie bolts anchoring in
29 the crankcase 03-14
Inspection, overhauling of pistons
(cleaning, replacement of tie bolts if necessary, clearance
measurement between piston crown and skirt before and after
works, piston grooves, piston pin/housing, dye penetration testing , E14, E15, E16, E17,
30 replacement of o-rings) 03-09 E18, E19
31 Reconditioning of pistons 03-15
32 Replacement of piston rings 03-05 E20
33 Removal & fitting of the CR into the piston 03-07
CR inspection,
big/small end measurement record
replacement of CR tie bolts and nuts
dye penetration checking and MPI test
34 CR nuts tightening 03-08 E21, E22
35 Replacement of CR small end bushes 03-16
Replacement of CR big end bearing shells
36 clearance between crankpin and CR shell after tightening 03-17 E23, E37
FLUID SYSTEMS
Inspection, cleaning of filters of starting electrovalves. Changing if
58 necessary 07-01
59 Inspection, overhauling of main starting air valve 07-02
60 Oil circuit gasket replacement
61 Fresh water circuit gasket replacement
62 Fuel oil circuit gasket replacement
63 Flexible hoses replacement
Overhauling of oil and water thermostatic valves, change of
64 thermostatic elements
SUPERCHARGING
66 Air coolers overhaul (2 pieces) (cleaning, hydraulic test)
Replacement of the expansion bellows and overhauling of the
67 exhaust manifolds 08-01
INJECTION
16 Removal & refitting of injection pipes 02-01
17 Removal & refitting of the injectors 02-02
MOVING ELEMENTS
22 Removal & fitting of the piston-connecting rod (CR) assembly 03-02 E2
Cylinder liners and water jacket removal, liner extraction,
23 replacement of o-rings and vibration dampers 03-10 E2
24 Visual & dimensional inspection of liners 03-03 E12
25 Cylinder liners dye penetration checking E13
26 Water jacket dye penetration checking
03-06,
Service Bulletin
27 Honing of liners 480927/11.04.06
Measurement
Item Description of work Chapter / Operation Sheet
28 -
Inspection of the protection of cylinder head tie bolts anchoring in
29 the crankcase 03-14
Inspection, overhauling of pistons
(cleaning, replacement of tie bolts if necessary, clearance
measurement between piston crown and skirt before and after
works, piston grooves, piston pin/housing, dye penetration testing , E14, E15, E16, E17,
30 replacement of o-rings) 03-09 E18, E19
31 Reconditioning of pistons 03-15
32 Replacement of piston rings 03-05 E20
33 Removal & fitting of the CR into the piston 03-07
CR inspection,
big/small end measurement record
replacement of CR tie bolts and nuts
dye penetration checking and MPI test
34 CR nuts tightening 03-08 E21, E22
35 Replacement of CR small end bushes 03-16
Replacement of CR big end bearing shells
36 clearance between crankpin and CR shell after tightening 03-17 E23, E37
FLUID SYSTEMS
Inspection, cleaning of filters of starting electrovalves. Changing if
58 necessary 07-01
59 Inspection, overhauling of main starting air valve 07-02
60 Oil circuit gasket replacement
61 Fresh water circuit gasket replacement
62 Fuel oil circuit gasket replacement
63 Flexible hoses replacement
Overhauling of oil and water thermostatic valves, change of
64 thermostatic elements
SUPERCHARGING
66 Air coolers overhaul (2 pieces) (cleaning, hydraulic test)
Replacement of the expansion bellows and overhauling of the
67 exhaust manifolds 08-01