ACCOMPANYING LETTER 4239 - PHRC Rehabilitation Project – Port

Engineering Document: "PHRC Rehabilitation Project – Port Harcourt " Comment Review Sheet Harcourt

v.3

Owner - General TRM Number


TR-4239-PHRC-TCM-3883

Contractor Transmittal Number TR-4239-TCM-PHRC-4907 10.08.2022


Contractor Transmittal Date

Owner Custodian Reviewer Name Ebibaimo;Amar/ NETCO CIVIL Approval/Review date 18.08.2022

Review Code Legend


A Approved
I No comment - No reviewed
C Comments - To be reissued in next revision
R Rejected - To be reissued in next revision

In case of review code "A" no need that the Contractor/Supplier returns the CRS

Documents list

Document
Document class
Issue Document Number Document Title Rev Review Code
code
Reason

CONCRETE DRAWING - PUMP 52P03B


IFA 4239-AA-DC-41U52RN004 1 (OFFSITE AREA) - F/W & R/F DETAILS OF 00 R
FOUNDATION

Comments on Documents

OWNER CONTRACTOR

Name of the person


N. Owner Comments Name of person who gives the comments Contractor answers who answers to the
comment.

Please see a sample comment mark ups which are


typical in nature, in the sheet attached. Noted. Appropriately Incorporated.
&
For Reinforcement around opening see reply below --->
Ashish Jaiswal / KBR Civil; Pervaz Boocha /
#1 Circular steel pipe will be permanently embedded inside Bagchi Amit
KBR Civil
concrete pedestal to form void required for vertical
pump.Hence, no further additional reinforcement is
necessary around opening/Void.

#2 Adobe Acrobat
Document

#3

#4

#5

Remarks

Owner Custodian Signature Signature Date 8/18/2022