Professional Documents
Culture Documents
490
Hydraulic Particulars
Side slope = 1: 1
Vent way
RCC Peirs 1 Nos 3.482 m 1.000 m Top width 1.000 m bottom width
(Height)
AFFLUX CALCULATIONS
Afflux = 0.020913 m OK
Discharge q = 0.798676
0.275 0.275
0.225 0.225
4.250
0.750
0.075 m WC
0.225 94.300 94.225
0.500 93.725
0.300 93.425
1.000
0.50 0.50 1.332 PIER
5.000 qq+ 1.000 92.093 MFL
6.000
2.150
0.600
89.343
7.200 2.200
X X
4.900 2.200 1.000
(trapezium)
Y
0.50 5.000 0.50
7.200
PLAN OF PIER
SLRB @ Km. 14.710
DESIGN OF DECK SLAB:
Clear cover = 40 mm
Dia of main reinforcement bar (assumed ) = 25 mm
As per IRC: 21-2000, clause 305.4.2, effective span shall be least of the ( clear span + effective depth ) or
( centre to centre distance between supports )
As per IRC: 21-2000,clause 303.1, from tables 9, permissible flexural compressive ( σ cbc ) for
As per IRC: 21-2000,clause 303.1, from tables 10, permissible stress ( σ st ) for
As per IRC: 21-2000, from clause 303.1 for calculating stresses in section, a modular ratio ( E s/Ec ) of 10
may be adopted
m = 10
r = σ st / σ cbc
= 200 / 8.3333
= 24.00
k = m / ( m + r )
= 10 / ( 10 + 24.000 )
= 0.294
j = 1 - k / 3
= 1 - 0.294 / 3
= 0.902
Q = ( 1 / 2 ) x σ cbc x k x j
= ( 1 / 2 ) x 8.33333 x 0.294 x 0.902
= 1.105
As per IRC: 21-2000, from clause 305.16.2, for a single concentrated load, the effetctive width may be calculated
in accordance with the following equation
bef = α x a x { 1- a / lo } + b1
a = The distance of the centre of gravity of the concentrated load from the nearer support
b1 = The breadth of concentrated area of the load, i.e., the dimension of the tyre or track
contact area over the road surface of the slab in a direction at right angles to the span
plus twice the thickness of the wearing coat or surface finish above the structural slab
α = A constant having the following values depending upon the ratio b / lo, where b is the
width of the slab
b / lo = 4700 / 8447.5
= ###
b / lo = 0.50 → α = 1.72
b / lo = 0.60 → α = 1.96
For the maximum live load bending moment, the two loads of 11.4 t should be kept such that the resultant of the load
system and the load under consideration should be equidistant from the centre of span, details as shown in figure.
11.4 R 11.4
0.23 0.250
0.15 1.80
0.50 0.50
4.70
3.18 R 3.24
Ra = 25.15 / 8.4475
= 2.98 t
As per IRC: 21-2000, clause 305.18.1, distribution steel is to be provided for the resisting moment equals to
0.3 times the moment due to live load plus 0.2 times the moment due to dead load, shrikage and temparature etc.
Minimum area of distribution reinforcement in one face = ( 0.06 / 100 ) x 1000 x 500
= 300.00 mm2 < 896.01 mm2
Top reinforcement
As per IRC: 21-2000, clause 305.10, shrinkage and temparature reinforcement of 250 mm 2 is to be provided in
each direction
Provide 10 mm dia bars at 300 mm c/c at top to take care of temparature and shrinkage in either direction and
Provide distribution steel of 10 mm dia bars at 300 mm c/c at top
Check for shear
As per IRC: 21-2000, clause 305.16.3, dispersion of load along the span equal to the dimension of the tyre
contact area over the wearing surface of the slab in the direction of the span plus twice the overall depth of the
slab inclusive of the thickness of the wearing surface
For maximum shear, the load is kept at a distance of ' d ' from the support
d = 1400 / 2
= 700 mm
Case I:
2.7 2.7 11.4 11.4
0.23 0.250
0.15 1.80
0.50 0.50
4.70
0.23 0.250
0.15 1.80
0.50 0.50
4.70
Ra = 24.3 / 8.4475
= 2.88 t
Case II:
0.23 0.250
0.15 1.80
0.50 0.50
4.70
0.23 0.190
0.15 1.80
0.38 0.38
4.70
Ra = 61.7729761 / 8.4475
= 7.31 t
Dead load
Weight of pier with 15 % buoyancy = 47.75 - ( ( 29.49 / 2.5 ) x 1.0 x ### / 100 ))
= 45.98 t
Weight of pier with 100 % buoyancy = ( 47.75 / 2.5 ) x 1.5
= 28.65 t
= 52.92 - 0.00
= 52.92 t
Live load
For class A train of vehicles, the following are the cases considered for the maximum live load reaction
Case I:
RA = 28.35 / 8.5
= 3.34 t
RB = 200.5 / 8.5
= 23.59 t
RA + RB = 3.34 + 23.59
= 26.93 t
RA - RB = 3.34 - 23.59
= 20.26 t
Case II:
RA = 110.8 / 8.5
= 13.03 t
RB = 133.6 / 8.5
= 15.72 t
RA + RB = 13.03 + 15.72
= 28.75 t
RA - RB = 13.03 - 15.72
= 2.69 t
Case III:
RA = 199.3 / 8.5
= 23.45 t
RB = 43.52 / 8.5
= 5.12 t
RA + RB = 23.45 + 5.12
= 28.57 t
RA - RB = 23.45 - 5.12
= 18.33 t
Case IV:
RA = 122.6 / 8.5
= 14.42 t
RB = 116.1 / 8.5
= 13.66 t
RA + RB = 14.42 + 13.66
= 28.08 t
RA - RB = 14.42 - 13.66
= 0.76 t
As per IRC: 6-2000, clause 211.7, if height of pier below the bed block is more than 3.0 m, then the impactor
percentage is zero.
RA + RB ( MAX ) = 28.75 t
RA - RB ( MIN ) = 20.26 t
Horizontal forces
Braking force
Height at which the braking force acts above bearing level = 1.20 + 0.5 + 0.075
= 1.78 m
As per IRC: 6-2017, clause 211.5.1.2, horizontal force in longitudinal direction at bearing level shall be greater of
Fh / 2 or μ Rg
Fh / 2 = 5.00 / 2
= 2.50 t
μ x Rg = 0.50 x 33.45
= 16.72 t
Case I:
As per IRC: 6-2000, clause 212.2, wind force on the deck structure shall be assumed as horizontal force and
calculated as follows
Moment due to wind force about the base of pier = 0.72 x ( 2.37 + 2.15 )
= 3.25 t-m 6.1
Moment due to wind force about top of soil = 0.72 x ( 2.37 + 2.75 )
= 3.68 t-m 7
Moment due to wind force about the base of pier = 0.99 x ( 3.52 + 1.00 )
= 4.45 t-m 6.1
Moment due to wind force about top of soil = 0.99 x ( 3.52 + 1.60 )
= 5.04 t-m 7
As per IRC: 6-2000, clause 212.4, lateral wind force against any exposed moving live load shall be considered as
acting at 1.5 m above the roadway and shall be calculated as follows
Case II:
As per IRC: 6-2000, clause 212.6, lateral wind force calculated above shall not be less than that obtained by
450 kg per linear meter on deck spans
As per IRC: 6-2000, clause 212.7, minimum limiting wind pressure of 240 kg / m 2 is considered for calculating
the wind force on unloaded structure
As per IRC: 6-2000, clause 212.7, maximum wind force of the above three cases is to be considered
Maximum moment due to wind force about the base of pier = 20.27 t-m
Maximum moment due to wind force about top of soil = 22.48 t-m
Frictional force = μ x Rg
= 0.50 x 33.45
= 16.72 t
Right side bearing resistance (10 % variation from left side) = 0.90 x 16.72
= 15.05 t
Moment due to frictional force about the base of the pier = 1.67 x 3.782
= 6.33 t-m
As per IRC: 6-2000, clause 213.2, intensity of pressure due to water currents is calculated as follows
V = Velocity of the current at the point where the pressure intensity is being calculated
= 1.414 x mean velocity
= 1.414 x 1.245
= 1.76 m / sec
P = 52 x 0.66 x 1.76 2
= 106.36 kg/m2
As per IRC: 6-2000, clause 213.6, the moment obtained in case I should not be less than the moments due to net
hydrostatic pressure with a difference of 250 mm in water levels on opposite faces of the pier. However case I is
considered even though the case ii produces maximum moment as the flow is regulated in the canal.
Direct loads
Live loads
Live load 28.75 t 28.75 t
Change in vertical reaction due to braking force 1.04 t 1.04 t
Moments
Stress on soil
Stress on soil
Stresses in the pier at base on top of foundation concrete and on top of soil with wind effect:
Stress on soil
Stress table
As per IRC: 21-2000, clause 303.1 and from table 9, permissible direct compressive stress ( σ cc ) for
As per IRC: 21-2000, clause 303.1 and from table 9, permissible flexural compressive stress ( σ bc ) for
As per IRC: 21-2000, clause 303.3 and from table 11, permissible tensile stress with wind for
( f cc / σ cc ) + ( f bc / σ bc ) ≤ 1
As per IRC: 21-2000, clause 306.2.2, the minimum area of steel provided shall not be less than 0.3 % of the gross
sectional area of concrete
Transverse reinforcement
As per IRC: 21-2000, clause 306.3.2, the diameter of transverse reinforcement shall not be less than 1/4 th of the
diameter of the largest longitudinal bar, and in no case less than 8 mm.
As per IRC: 21-2000, clause 306.3.2, the pitch of the transverse reinforcement shall not exceed 300 mm or the
lesser of the following two dimensions
Area of steel required in longitudinal direction ( top & bottom ) = 1 % of gross area of bed block
.= 1.0 / 100 ) x 1000 x 300
= 3000 mm2
Area of steel required in transverse direction at top and bottom = 0.2 % of gross area of bed block
= ( 0.2 / 100 ) x 1000 x 300
= 988.57 mm2
0.30 0.30
0.50
0.761 1.10
0.60
4.60
P1 P2
6.00 7.20
P3 P4
0.483 1.017
1.62
7.61
7.44
7.08
6.98
5.99
Stresses at corners:
Clear cover = 75 mm
Dia of main steel bar ( assumed ) = 16 mm
Effective depth ( de ) = 1100 - 75 - 8
= 1017 mm
Grade of concrete = M 25
Grade of steel = Fe 415
As per IRC: 21-2000,clause 303.1, from tables 9, permissible flexural compressive ( σ cbc ) for
As per IRC: 21-2000,clause 303.1, from tables 10, permissible stress ( σ st ) for
m = 10
r = σ st / σ cbc
= 200 / 6.25
= 32.00
k = m / ( m + r )
= 10 / ( 10 + 32.000 )
= 0.238
j = 1 - k / 3
= 1 - 0.24 / 3
= 0.921
Q = ( 1 / 2 ) x σ cbc x k x j
= ( 1 / 2 ) x 6.25 x 0.24 x 0.92
= 0.685
Net stress at the distance ' de ' from face of the pedestal = 7.44 - 1.60
= 5.84 t/m2
Provide 12 mm dia of bars at 175 mm c/c at top in both directions as minimum steel
For one way shear critical section is at a distance ' de ' from face of the pier pedastal
= 0.16 x √ 20
= 0.716 N /m m2
= 71.6 t / m2 > 8.75 t / m2
V
94.300 RL
1.200
94.225 Top of approach slab
Approach slab 0.225 W9 94.075 Bottom of approach slab
225 thk Gravel base 0.300 W10 W4 93.775 Bottom of Gravel base
W8
0.350 W1 0.3 93.425 Bottom of Bed block
W11
W7
W5 W3
-114.465
W12
W2
W6
207.390 B 3800
Load from dead weight of super structure = 52.88 + 6.89 + 2.28 + 4.86
= 66.90 t
1) REACTION ON ABUTMENT:
Dead load coming on to the abutment from 8.50 m span 33.45 t ( From pier calculations)
Live load coming on to the Abutment:
Span = 8.50 m
Live load for Class - A train of vehicles
2.7 2.7 11.4 11.4 6.8 6.8 6.8 6.8
1.2 4.3 0 0 0 3
RA 8.5 RB
282.874 -1147.369
15 PH = 0.158 x ### 2 - 1.20 2
) x 2.1 4201.267 -47.739 ( +) ###
4205.612 -201218.662
CG of the vertical load system from 'A' = ### / 282.874
= -711.336 m
B/6 = 3.200 / 6
= 0.533 m
As per IRC: 21-2000, clause 303.1 and from table 9, permissible direct compressive stress for
M15 grade of concrete = 375 t/m2
As per IRC: 21-2000, clause 303.3 and from table 11, permissible tensile stress in plain concrete elements for
M15 grade of concrete = 40 t/m2
206.618 -1378.869
16 PH = 0.134 x ### 2 - 1.20 2
) x 2.1 3522.546 -47.529 ( + ) ###
3526.891 -168310.931
CG of the vertical load system from 'A' = ### / 206.618
= -814.601 m
B/6 = 3.800 / 6
= 0.633 m
As per IRC: 78-2000, clause 706.3.4, factors of safety against sliding and over turning should be more than 1.5 and
2.0 respectively.
Area of steel required in longitudinal direction ( top & bottom ) = 1.0 % of gross area of bed block
= ( 1.0 / 100 ) x 1000 x 300
= 3000 mm2
Area of steel required in transverse direction at top and bottom = 0.2 % of gross area of bed block
= ( 0.2 / 100 ) x 1000 x 300
= 988.6 mm2
0
However provide 10 mm dia two legged strriups
V
94.300 RL
1.200
94.225 Top of approach slab
Approach slab 0.225 W9 94.075 Bottom of approach slab
225 thk Gravel base 0.300 W10 W4 93.775 Bottom of Gravel base
W8
0.350 W1 0.3 93.425 Bottom of Bed block
W11
W7
W5 W3
-114.465
W12
W2
W6
207.390 B 4550
Load from dead weight of super structure = 52.88 + 6.89 + 2.28 + 4.86
= 66.90 t
1) REACTION ON ABUTMENT:
Dead load coming on to the abutment from 8.50 m span 33.45 t ( From pier calculations)
Live load coming on to the Abutment:
Span = 8.50 m
Live load for Class - A train of vehicles
2.7 2.7 11.4 11.4 6.8 6.8 6.8 6.8
1.2 4.3 0 0 0 3
RA 8.5 RB
217.070 -1592.842
15 PH = 0.158 x ### 2 - 1.20 2
) x 2.1 4201.267 -47.739 ( -) ###
4205.612 199466.974
CG of the vertical load system from 'A' = ### / 217.070
= 918.907 m
B/6 = 3.550 / 6
= 0.592 m
As per IRC: 21-2000, clause 303.1 and from table 9, permissible direct compressive stress for
M15 grade of concrete = 375 t/m2
As per IRC: 21-2000, clause 303.3 and from table 11, permissible tensile stress in plain concrete elements for
M15 grade of concrete = 40 t/m2
94.037 2216.312
16 PH = 0.134 x ### 2 - 1.20 2
) x 2.1 3522.546 -47.529 ( -) ###
3526.891 170132.550
CG of the vertical load system from 'A' = ### / 94.037
= 1809.206 m
B/6 = 4.550 / 6
= 0.758 m
As per IRC: 78-2000, clause 706.3.4, factors of safety against sliding and over turning should be more than 1.5 and
2.0 respectively.
Area of steel required in longitudinal direction ( top & bottom ) = 1.0 % of gross area of bed block
= ( 1.0 / 100 ) x 1000 x 300
= 3000 mm2
Area of steel required in transverse direction at top and bottom = 0.2 % of gross area of bed block
= ( 0.2 / 100 ) x 1000 x 300
= 988.6 mm2
0
However provide 10 mm dia two legged strriups
W4
W6 W2
-113.590
W3
W5
0
500 3100 0 500 207.890
A
0.500 W7
207.390
B 4700
92.669 -1808.539
4201.267 -202241.753
B/6 = 3.700 / 6
= 0.617 m
As per IRC: 21-2000, clause 303.3 and from table 11, permissible tensile stress in plain concrete elements for
-452.818 -4077.330
4163.965 -201856.504
B/6 = 4.700 / 6
= 0.783 m
W4
W6 W2
11.320
W3
W5
150
300 1600 1600 300 93.000
A
0.600 W7
92.400
B 4400
93.594 124.985
56.780 394.939
B/6 = 3.800 / 6
= 0.633 m
As per IRC: 21-2000, clause 303.3 and from table 11, permissible tensile stress in plain concrete elements for
108.398 163.824
62.137 474.905
B/6 = 4.400 / 6
= 0.733 m