You are on page 1of 28

Doc.Ref.

: PPCSB/75/PQP/APP/MFL(STR)
Putra Perdana Construction Sdn Bhd
Page 1 of 28

Master Forms List (Structural Works)


The following list of forms and checklists are customized for this project and allowed for expand
as required.

No Reference Title Document Effective Date Linked To

1 PPCSB/WI/CONS/F001 Pre-Concreting Checklist 14 May 2002 PPCSB/WI/CONS/S/01,03

2 PPCSB/WI/CONS/F002 Post-Concreting Checklist 14 May 2002 PPCSB/WI/CONS/S/06

3 PPCSB/WI/CONS/F004 Steel Structure Checklist 14 May 2002 PPCSB/WI/CONS/S/04

4 PPCSB/WI/CONS/F005 Scaffolding Checklist 14 May 2002 PPCSB/WI/CONS/S/02

5 PPCSB/75/PQP/STR/FL/1 Concrete Casting Record 08 July 2004

6 PPCSB/75/PQP/STR/FL/2 Weekly Concrete Ordering Schedule 08 July 2004

7 PPCSB/75/PQP/STR/FL/3 Waterproofing System Checklist (for Retaining Wall) 08 July 2004

8 PPCSB/75/PQP/STR/FL/4 Waterbar / Watertightness Installation Checklist 08 July 2004

9 PPCSB/75/PQP/STR/FL/5 Approval for Striking Formwork 08 July 2004

10 PPCSB/75/PQP/STR/FL/6 Verticality Checklist (for Vertical Elements) 08 July 2004

11 PPCSB/75/PQP/STR/FL/7 Concreting Concrete and Formworks Striking Record 08 July 2004

12 PPCSB/75/PQP/STR/FL/8 RC Floor Concrete Inspection Checklist 08 July 2004

13 PPCSB/75/PQP/STR/FL/9 Slab & Beam Inspection Checklist 08 July 2004

14 PPCSB/75/PQP/STR/FL/10 Wall Inspection Checklist 08 July 2004

15 PPCSB/75/PQP/STR/FL/11 Column Inspection Checklist 08 July 2004

16 PPCSB/75/PQP/STR/FL/12 Grouting / Patching Inspection Checklist 08 July 2004

17 PPCSB/75/PQP/STR/FL/13 Planting of Bars Inspection Checklist 08 July 2004

18 PPCSB/75/PQP/STR/FL/14 Inspection Record 08 July 2004

19 PPCSB/75/PQP/STR/FL/15 Pilecap Inspection Checklist 08 July 2004

20 PPCSB/75/PQP/STR/FL/16 Verticality Checklist (for Lift Core Wall) 08 July 2004

Project Quality Plan for Beverly Tower Effective: 08 July 2004


Putra Perdana Construction Sdn Bhd Doc. Ref. : PPCSB / WI / CONS / F001
Page 1 of 1

Pre-Concreting Checklist
Project Ref : PPCSB/75 Date :

Location : Block No. :

Gridline / Zone Level :

Element : Slab / Beam / Column / Wall / Drawing Ref. No. :


Liftcore / Staircase / Sump
Grade of Concrete:
LEGEND : Accept ( / ) , Reject ( X ) , Not applicable ( O )

Acceptability
Item Description Subcon / PPCSB's Remark
R.E. / C.O.W.
Rep.
1st 2nd 1st 2nd
Formwork
1 Dimension (Width & Depth)
2 Setting Out Line (Control Points)
3 Transfer Level
4 Concreting Level (Markon Rebar)
5 Cast In / Box Up
6 Rigidity of Props
7 Tightness of Joints
8 Drop / Step Down
9 Cleanliness
10 Mould Oil
Reinforcement
1 Rebar / BRC - Size / Nos / Type
2 Rebar / BRC Conditions
3 Link - Size / Nos / Type
4 Anchorage
5 Spacing
6 Cover
7 Laps
8 Additional Rebars / Trimmer Bars
Water Proofing
1 Application of Waterproofing Materials
M&E Services
1 M&E Services Checked
Others

1) Non-Conformances 3) Re-Inspection

2) Disposition 4) Comments

Checked by (Subcon's Rep) Verified by (PPCSB's Rep) Approved : (RE/COW)

Signature Signature Signature


Name : Name : Name :
Date : Date : Date :

Construction Work Instructions Manual Version 3.00 effective 14 . 05 . 2002


Putra Perdana Construction Sdn Bhd Doc. Ref. : PPCSB / WI / CONS / F002
Page 1 of 1

Post Concreting Checklist


Project Ref : PPCSB/75 Date :
Location : Block No :
Gridline / Zone : Level :
Element : Slab / Beam / Column / Drawing Ref. No. :
Lift Core / Staircase /

LEGEND : Accept ( / ) , Reject ( X ) , Not applicable ( O )

Acceptability
Subcon / PPCSB's
Item Description R.E. / C.O.W. Remark
Rep.
1st 2nd 1st 2nd
1 Striking of formwork
2 Visibility of cracks
3 Honeycomb
4 Bulging
5 Accuracy of structural members
dimension
6 Alignment, verticality, level of
structural members
7 Deviation of structural members
8 Steel bars exposed
9 Floor hardener surface level smooth
10 Tie hole
11 Curing
12 As-built

1) Non-Conformances 3) Re-Inspection

2) Disposition 4) Comments

Checked by (Subcon's Rep) Verified by (PPCSB's Rep) Approved : (RE/COW)

Signature Signature Signature


Name : Name : Name :
Date : Date : Date :
Construction Work Instructions Manual Version 3.00 effective 14 . 05 . 2002
Putra Perdana Construction Sdn Bhd Doc. Ref. : PPCSB / WI / CONS / F004
Page 1 of 1

Steel Structure Checklist


Project Ref : PPCSB/75 Date :
Location : Block No. :
Gridline / Zone : Level :
Element : Drawing Ref. No. :

LEGEND : Accept ( / ) , Reject ( X ) , Not applicable ( O )

Acceptability
Subcon / PPCSB's
Item Description R.E. / R.A. / C.O.W. Remark
Rep.
1st 2nd 1st 2nd
1 Setting out and alignment
2 Type and dimensions
3 Dimension and thickness of plate
4 Bolt and nut
5 Workmanship and type of welding
6 Grinding of weld area
7 Clearing after grinding
8 Painting and anti-rust
9 Rusting and crack
10 Protection

1) Non-Conformances 3) Re-Inspection

2) Disposition 4) Comments

Checked by (Subcon's Rep) Verified by (PPCSB's Rep) Approved : (RE/RA/COW)

Signature Signature Signature


Name : Name : Name :
Date : Date : Date :
Construction Work Instructions Manual Version 3.00 effective 14 . 05 . 2002
Putra Perdana Construction Sdn Bhd Doc. Ref. : PPCSB / WI / CONS / F005
Page 1 of 1

Scaffolding Checklist
Project Ref : PPCSB/75 Date :

Location : Block No :

Gridline / Zone : Level :

Element : Drawing Ref. No. :

LEGEND : Accept ( / ) , Reject ( X ) , Not applicable ( O )

Acceptability
Subcon / PPCSB's
Item Description R.E. / C.O.W. Remark
Rep.
1st 2nd 1st 2nd
1 Setting out
2 Condition of scaffolds & accessories
3 Ground condition ( firm / unstable)
if scaffolds started at ground
4 Adequacy of supporting system
if scaffolds rest on temporary support
5 Scaffold base support
6 Verticality of scaffolds
7 Installation of bracing

1) Non-Conformances 3) Re-Inspection

2) Disposition 4) Comments

Checked by (Subcon's Rep) Verified by (PPCSB's Rep) Approved : (RE/COW)

Signature Signature Signature


Name : Name : Name :
Date : Date : Date :
Construction Work Instructions Manual Version 3.00 effective 14 . 05 . 2002
Doc.Ref.: PPCSB/75/PQP/STR/FL/1
Putra Perdana Construction Sdn Bhd
Page 1 of 1

Concrete Casting Record


PROJECT : MARC Service Residence : MARC Service Residence PROJECT REF. NO. : PPCSB / 75
Date of Casting : Sheet :
Structural Element : Time Called To Confirm :
Block : Concrete Supplier :
Level : Total Design Vol. (A) :
Overall Grid Line : Total Vol. Delivery (B) :
B-A
RIF No. : Wastage (%) (Was =
A
x100%) :

QTY (m3) TIME


RE/COW Poured
Truck No D.O No Grade Slump Accu Dispatche Idling Disch Cube Ref. Remarks
Sign Location Total Reject Wastage Interval Arrived Discharged Left
Total d Time Time

Recorded By: Reviewed By:

ASA/SE/SSS/JSS Project Manager


Name : Name :

Project Quality Plan for MARC Service Residence Effective: 08 July 2004
Doc.Ref.: PPCSB/75/PQP/STR/FL/2
Putra Perdana Construction Sdn Bhd
Page 1 of 1

Weekly Concrete Ordering Schedule


PROJECT : MARC Service Residence
PROJECT REF. : PPCSB/75

BLOCK :
Date : Requested By :
Attention To : Designation :
Contact No : Contact No :
Fax No : Signature :

We herewith submit to you the weekly concrete request schedule:

INTERVAL
DATE LOCATION ELEMENT GRADE QTY (M3) REMARKS
TIME

Remark : Actual concrete request to be confirmed by phone one day early the casting activity.

Approved By PM: Company's Stamp:

Name:
Date:

Project Quality Plan for MARC Service Residence Effective: 08 July 2004
Doc.Ref.: PPCSB/75/PQP/STR/FL/3
Putra Perdana Construction Sdn Bhd
Page 1 of 1

Waterproofing System Checklist (for Retaining Wall)


Project : MARC Service Residence Date of Inspection :
Project Ref. No. : PPCSB/75 Level :
Block : Location/Gridline/Zone :
Drawing Ref. No. :
LEGEND : Accept ( / ) , Reject ( X ) , Not applicable ( O )
Acceptability
Subcon/
Item Description PPCSB's R.E. / C.O.W. Remarks
Rep.
1st 2nd 1st 2nd

A Before-Application Inspection:
1 Structural Repair (crack/spalling/void)
Surface Preparation (grinding / acid etch /
2
scabbling / needle gun / water blast)
3 Wetting Concrete (with clean water)
Mixing for Slurry Coat
4
(As per Manufacturer's Instruction)
5 Suitable Brush/Spray Equipment Employed
B During-Application Inspection
One (1) coat of Xypex Concentrate applying
1
uniformly
At least 3 days curing after Xypex applied
2

1st coat of SikaTop Seal 107 applying


3
uniformly
2nd coat of SikaTop Seal 107 applying
4
uniformly
C After-Application Inspection
1 Coverage
2 Joints / Edges
3 Protect from raining

(1) Non-Conformance: (3) Re-Inspection:

(2) Disposition: (4) Comment:

Checked By (Subcon's Rep) Verified by (PPCSB's Rep) Approved by (RE/COW)

Signature Signature Signature


Name : Name : Name :

Project Quality Plan for MARC Service Residence Effective: 08 July 2004
Doc.Ref.: PPCSB/75/PQP/STR/FL/3
Putra Perdana Construction Sdn Bhd
Page 1 of 1
Date: Date: Date:

Project Quality Plan for MARC Service Residence Effective: 08 July 2004
Doc.Ref.: PPCSB/75/PQP/STR/FL/4
Putra Perdana Construction Sdn Bhd
Page 1 of 1

Waterbar / Watertightness Installation Checklist


Project : MARC Service Residence Date of Inspection :
Project Ref. No. : PPCSB/75 Level :
Block : Location/Gridline/Zone :
Drawing Ref. No. :

LEGEND : Accept ( / ) , Reject ( X ) , Not applicable ( O )


Acceptability
Subcon/
Item Description PPCSB's R.E. / C.O.W. Remarks
Rep.
1st 2nd 1st 2nd
Check material used as specified and
1
approved sample (types, thickness, etc).
Check that site cutting and jointing are
2
properly carried out.
Check material is laid in joint centre and
3
secured to correct position.
Check the material is firmed and secured in
4
position.
Check that concrete is adequately vibrated
5
and compacted.

(1) Non-Conformance: (3) Re-Inspection:

(2) Disposition: (4) Comment:

Checked By (Subcon's Rep) Verified by (PPCSB's Rep) Approved by (RE/COW)

Signature Signature Signature


Name : Name : Name :

Project Quality Plan for MARC Service Residence Effective: 08 July 2004
Doc.Ref.: PPCSB/75/PQP/STR/FL/4
Putra Perdana Construction Sdn Bhd
Page 1 of 1

Date: Date: Date:

Project Quality Plan for MARC Service Residence Effective: 08 July 2004
Doc.Ref.: PPCSB/75/PQP/STR/FL/5
Putra Perdana Construction Sdn Bhd
Page 1 of 1

Approval for Striking Formwork

Project : MARC Service Residence

Project Ref. No. : PPCSB/75

Block :

Level :

Grid Line : .

Structure Element : Slab + Beam

Casting Date :

Age of Concrete :

Remark:

Important Note: Patching up to concrete surface upon formwork striking is not allowed prior to
inspection.

Requested by (Sub-Con's Rep.) Approved by (PPCSB's Rep.)

Signature Signature
Name : Name :
Date: Date:

Project Quality Plan for MARC Service Residence Effective: 08 July 2004
Doc.Ref.: PPCSB/75/PQP/STR/FL/5
Putra Perdana Construction Sdn Bhd
Page 1 of 1

Project Quality Plan for MARC Service Residence Effective: 08 July 2004
Doc.Ref.: PPCSB/75/PQP/STR/FL/6
Putra Perdana Construction Sdn Bhd
Page 1 of 1

Verticality Checklist (for Vertical Elements)


Project : MARC Service Residence Date of Inspection :
Project Ref. No. : PPCSB/75 Level :
Block : Location/Gridline/Zone :
Drawing Ref. No. :
Elements : Wall / Column / Other

1st Measurement 2nd Measurement


Description Remarks
Top Middle Bottom Required Status Top Middle Bottom Required Status
Control Line - X
Control Line - Y
Point - A
Point - B
Point - C
Point - D
Point - E
Point - F
Point - G
Point - H
Point - I
Point - J
Point - K
Point - L
Corner -
Corner -
Corner -
Corner -

Checked By (Subcon's Rep) Verified by (PPCSB's Rep) Approved by (RE/COW)

Signature Signature Signature


Name : Name : Name :

Project Quality Plan for MARC Service Residence Effective: 08 July 2004
Doc.Ref.: PPCSB/75/PQP/STR/FL/6
Putra Perdana Construction Sdn Bhd
Page 1 of 1
Date: Date: Date:

Project Quality Plan for MARC Service Residence Effective: 08 July 2004
Doc.Ref.: PPCSB/75/PQP/STR/FL/7
Putra Perdana Construction Sdn Bhd
Page 1 of 1

Concreting Concrete and Formworks Striking Record


PROJECT : MARC Service Residence PROJECT REF. : PPCSB/75
BLOCK :

Nos of
Concrete Formworks
Location Date Cast Qty (m3) Cube Cube Ref. Remarks
Waste (m3) Removal Date
Taken

Reported By Certified By Confirmed By

Signature Signature Signature


Name : Name : Name :
Date: Date: Date:

Project Quality Plan for MARC Service Residence Effective: 08 July 2004
Doc.Ref.: PPCSB/75/PQP/STR/FL/8
Putra Perdana Construction Sdn Bhd
Page 1 of 1

RC Floor Concrete Inspection Checklist


Project : MARC Service Residence Date of Inspection :
Project Ref. No. : PPCSB/75 Level :
Block : Location/Gridline/Zone :
Drawing Ref. No. :
LEGEND : Accept ( / ) , Reject ( X ) , Not applicable ( O )
INSPECTION- - -Status
DATE DATE
Sign off / Remarks Sign off / Remarks
A ) After Installing of beam soffit form work PPCSB GRA PPCSB GRA
1 Construction joint Column top surface

(Remove laitanc, Loose meterial, Block out area

sponge , polystyrene Wall top surface

& exposed surface couse Block out area

aggregates. ) Beam previous casting

Slab previous casting

B ) Before installing of Rebars


2 Form work as-built level ( with Chamber if Require)

3 Structure Finish level marking On vertical bars & etc

4 Marking of M&E services/opening/pipe sleeve to form .


. Approval from GRA of M&E services (if not Indicate in Drg)
**Trimmer bar for opening hight less than 50D of main bar for vertical member

5 Embeded material Water stopper / R.W.D.P / Lift moto room U bar /

Scupper drain pipe / Bolts & etc

C ) After installation of Reinforcement & etc


6 Form work Support check & sign 0ff by a competent person

Contruction joint
Drop area
Opening / block out area
Check side fwk support
Sealing against grout loss
7 Inspection of Post tention Checking List (Sign off )

M & E services Checking List (Sign off )

8 Rebar inspection Stater Bars Column

No:& size of bar Walls

& setting out, Stair case

secure in position Ramp

Stiffener

(Extra bars to Compensate higher grade concrete)

Trimmer bar

Beam & Slab Checking List (Sign off )

Attatch all planting stater bars sign off forms (if any)

Steel Structure Holding down Bolts


9 General cleaning
10 Structure finish level
D) Concreting
11 Method of casting to prevent cold joint
12 Workability & mix of concrete to be use
13 No of vibrator poker
14 Lighting
15 Cover in case of rain
16 Conform floor finishes / Prevention of shrinkage crack
17 Concrete pour list Sign off

18 Curing
Remarks :

Checked By (Subcon's Rep) Verified by (PPCSB's Rep) Approved by (RE/COW)

Signature Signature Signature


Name : Name : Name :
Date: Date: Date:

Project Quality Plan for MARC Service Residence Effective: 08 July 2004
Putra Perdana Construction Sdn Bhd Doc.Ref.: PPCSB/75/PQP/STR/FL/9
Page 1 of 1
Slab & Beam Inspection Checklist
Project : MARC Service Residence Date of Inspection :
Project Ref. No. : PPCSB/75 Level :
Block : Location/Gridline/Zone :
Drawing Ref. No. : LEGEND : Accept ( / ) , Reject ( X ) , Not applicable ( O )

BEAM GRIDLINE
Beam no:
BEAMS INSPECTION DATE
1st 2nd 1st 2nd 1st 2nd 1st 2nd 1st 2nd 1st 2nd 1st 2nd 1st 2nd 1st 2nd 1st 2nd 1st 2nd 1st 2nd 1st 2nd
SIZE
TOP bars size
No of bars
Length
Anchorage length
spacer bars
Lapping area
length
BOTTOM bars size
No of bars
Length
Anchorage length
spacer bars
Lapping area
length
Links size
no of links
spacing
distance
Spacer bottom
side
Beam Stater bar length over -
Slab Construction joint
PANEL Gridline
SLAB DATE
Panel type
Top layer Bar size
Spacing
Length
Anchorage length ( if any )
Steel Chair
Lapping Area
Length
Bottom Bar size
Spacing
Area
Anchorage length ( if any )
Lapping Area
Length
Spacer
TRIMMER BAR

Checked By (Subcon's Rep) Verified by (PPCSB's Rep) Approved by (RE/COW)

Signature Signature Signature


Name : Name : Name :
Date: Date: Date:

Project Quality Plan for MARC Service Residence Effective: 08 July 2004
Doc.Ref.: PPCSB/75/PQP/STR/FL/10
Putra Perdana Construction Sdn Bhd
Page 1 of 1

Wall Inspection Checklist


Project : MARC Service Residence Date of Inspection :
Project Ref. No. : PPCSB/75 Level :
Block : Location/Gridline/Zone :
Drawing Ref. No. :

Attach Plan View of Area LEGEND : Accept ( / ) , Reject ( X ) , Not applicable ( O )


Core Wall no : Date : Time : Date : Time :
REINFORCEMENT Status 1st Inspection Sign-off / Remarks Status 2nd Inspection Sign-off / Remarks
No of Stater Bars
Spacing
Lapping Length
Length over casting level
U - Bars ( Width between-
Internal & External Bars )
Horizontal bar Size
Spacing
Hight till casting level
Lapping Length
Spacer
Construction joint surface
Survey Setting Level
Out Marking Vertical
Planting of Bar's FORM ( sign off ) If any

Embedded Item (if any)


Attach sign off M&E checking list
FORMWORK Date :
Block out- Door opening
area Size / Button hole
Position Level indecator
** Trimmer Bar **
General Cleaning
Proper working plat form
Verticality As-built Sign-0ff
Form ties secure properly
Sealing against grout loss
Secure main Bars in position

CONCRETING Date :
Method of casting / Trimie pipe
Concrete Mix / workability
No & length of Vibrator poker
Lighting
General Cleaning
Grout for construction joint

Pour List Sign-off


Date :
CURING

Remarks :

Checked By (Subcon's Rep) Verified by (PPCSB's Rep) Approved by (RE/COW)

Signature Signature Signature


Name : Name : Name :
Date: Date:

Project Quality Plan for MARC Service Residence Effective: 08 July 2004
Doc.Ref.: PPCSB/75/PQP/STR/FL/11
Putra Perdana Construction Sdn Bhd
Page 1 of 1
Column Inspection Checklist
Project : MARC Service Residence Date of Inspection :
Project Ref. No. : PPCSB/75 Level :
Block : Location/Gridline/Zone :
Drawing Ref. No. : LEGEND : Accept ( / ) , Reject ( X ) , Not applicable ( O )

Level : Gridline
Date
COLUMN 1st 2nd Sign off 1st 2nd Sign off 1st 2nd Sign off 1st 2nd Sign off 1st 2nd Sign off 1st 2nd Sign off 1st 2nd Sign off 1st 2nd Sign off
Construction joint surface
Size With
Alignment Attatch
Position Sketch
Planting of Bar's FORM ( sign off ) If any

REINFORCEMENT
No of Stater Bars
No of Main Bars
Lapping Length
Length over casting level
Provide Gap for postension Duct
Links Size
No of links
Spacing
Hight till casting level
Lapping area secure
Spacer
Embedded Item (if any)
Attach sign off M&E checking list
FORMWORK Date :
Size / Alignment
Verticality
Form ties secure properly
Sealing against grout loss
Secure main Bars in position
Proper working plat form
CONCRETING Date :
Method of casting / Trimie pipe
Concrete Mix / workability
No & length of Vibrator poker
Lighting
Grout for construction joint

Pour List Sign-off


Date :
CURING

Checked By (Subcon's Rep) Verified by (PPCSB's Rep) Approved by (RE/COW)

Signature Signature Signature


Name : Name : Name :
Date: Date: Date:

Project Quality Plan for MARC Service Residence Effective: 08 July 2004
Doc.Ref.: PPCSB/75/PQP/STR/FL/12
Putra Perdana Construction Sdn Bhd
Page 1 of 1

Grouting / Patching Inspection Checklist


Project : MARC Service Residence Date of Inspection :
Project Ref. No. : PPCSB/75 Level :
Block : Location/Gridline/Zone :
Drawing Ref. No. : Ren No. :

No & Element Location Sign -off by: Grouting / Patching Check By Verified By Approved By

Remarks Level Gridline Hacking Cleaning Aggregate Date Product Used Time Start-Finish Pressure(psi) No of Bags No of Cubes Sub-Con PPCSB RE/COW

Project Quality Plan for MARC Service Residence Effective: 08 July 2004
Doc.Ref.: PPCSB/75/PQP/STR/FL/13
Putra Perdana Construction Sdn Bhd
Page 1 of 1

Planting of Bars Inspection Checklist


Project : MARC Service Residence Date of Inspection :
Project Ref. No. : PPCSB/75 Level :
Block : Location/Gridline/Zone :
Drawing Ref. No. : Ren No. :

Location Hole Layer Product REBAR Check By Verified By Approved By


No Element Level Gridline Planted to Size Depth Cleanliness ( Top / Bottom / Used Size Embedded Number
Sub-Con PPCSB RE/COW
(mm) (mm) Internal or etc) (mm) (mm) Planted

Project Quality Plan for MARC Service Residence Effective: 08 July 2004
Doc.Ref.: PPCSB/75/PQP/STR/FL/14
Putra Perdana Construction Sdn Bhd
Page 1 of 1

Inspection Record
Project : MARC Service Residence Date of Inspection :
Project Ref. No. : PPCSB/75 Block :
Inspection Form No (RIF No.) : Level :
Drawing Ref. No. : Location/Gridline/Zone :
Element :

Date Date
Item Comments
Time Time

Commented by : Received by : Approved / Witness by :

Name : Name : Name :


Date : Time : Date : Time : Date : Time :

Project Quality Plan for MARC Service Residence Effective: 08 July 2004
Doc.Ref.: PPCSB/75/PQP/STR/FL/15
Putra Perdana Construction Sdn Bhd
Page 1 of 1

Pilecap Checklist
Project : MARCService Residence Inspection Date :
Project Ref. No : PPCSB/75 Pilecap Ref. No. :
Block : Location/Gridline/Zone :
Con. Grade : Concrete Supplier :
Drwg. Ref. No : Concrete Slump :
Theoretical Vol :

Item Description Acceptability


Legend: Acceptable: ( / ) Rejected: ( X Remarks
) Not Applicable: ( 0 ) Sub-Con/ R.E/C.O.W
PPCSB
1st. 2nd. 1st. 2nd.
1 Pre-Construction Inspection
a). Pile Eccentricity - Approved
b). Pile Cut-Off level
c). Pile Head Inspection - Approved
d). Pile Head Cleanliness
2 Formwork
a). Dimension
b). Depth of Pilecap
c). Rigidity/ Verticality/ Squareness
d). Mould Oil
e). Cleanliness
3 Reinforcement
a). No.& Diameter of Bottom/Top Bars
b). No.& Diameter of Loop Bars
c). Lapping
d). Cover Blocks
e). Reinforcement Cleanliness
4 Column Starter Bar
a). No.& Diameter of Main Bars
b). No. & Diameter & spacing of links
c). Alignment & Verticality
d). Length of Anchorage & Starters
5 Adequacy of base Concrete
6 RL of TOPC
7 Lean Concrete as Built Level
8 Temperature Control
9 Protection incase of Rain
10 Lighting

(1). Non-Conformance: (3). Re-Inspection:

(2). Disposition: (4). Comment:

Checked By (Sub-Con Rep) Verified By (PPCSB Rep) Approved By (RE/COW)

Signature: Signature: Signature:


Name: Name: Name:
Date: Date: Date:

Project Quality Plan for MARC Service Residence Effective: 08 July 2004
Doc.Ref.: PPCSB/75/PQP/STR/FL/16
Putra Perdana Construction Sdn Bhd Page 1 of 1

Verticality Checklist (for Lift Core Wall)


Project : MARC Service Residence Date of Inspection :
Project Ref. No. : PPCSB/75 Level :
Block : Location/Gridline/Zone :
Drawing Ref. No. :

1st Measurement 2nd Measurement


Wall No. Remarks
Top Middle Bottom Required Status Top Middle Bottom Required Status
Control Line - X
Control Line - Y
Point - A
Point - B
Point - C
Point - D
Point - E
Point - F
Point - G
Point - H
Corner - I
Corner - J
Corner - K
Corner - L
1st Measurement 2nd Measurement
Wall No. Remarks
Top Middle Bottom Required Status Top Middle Bottom Required Status
Control Line - X
Control Line - Y
Point - A
Point - B
Point - C
Point - D
Point - E
Point - F
Point - G
Point - H
Corner - I
Corner - J
Corner - K
Corner - L
1st Measurement 2nd Measurement
Wall No. Remarks
Top Middle Bottom Required Status Top Middle Bottom Required Status
Control Line - X
Control Line - Y
Point - A
Point - B
Point - C
Point - D
Point - E
Point - F
Point - G
Point - H
Corner - I
Corner - J
Corner - K
Corner - L
1st Measurement 2nd Measurement
Wall No. Remarks
Top Middle Bottom Required Status Top Middle Bottom Required Status
Control Line - X
Control Line - Y
Point - A
Point - B
Point - C
Point - D
Point - E
Point - F
Point - G
Point - H
Corner - I
Corner - J
Corner - K
Corner - L
Checked By (Subcon's Rep) Verified by (PPCSB's Rep) Approved by (RE/COW)

Signature Signature Signature


Name : Name : Name :
Date: Date: Date:

Project Quality Plan for MARC Service Residence Effective: 08 July 2004

You might also like