Weekly REPORT Project: qweerwr

Location: Phnom Penh


Date: 30th-Sep-2022

Equipment
Work Description & Location
Description Quan. Unit Remark

1 Toolbox meeting Laser leveling machine 2 pcs


2 Marking centre line of bottom bracket L10 Satety belt 18 pcs
3 Drilling the hole top bracket at L23,L24,L25,L26,L27 Long measure tape 1 set
4 Drilling bottom hole at L18,L19 Marker 1 set
5 Install bracket L20, L21 Scaffolding 6 set
6 Marking bracket hole L28 Drilling motor 6 pcs
7 Ladder 6 pcs
8
Tomorrow Activities Manpower on Site

1 Toolbox meeting Description Quan. Unit Remark


2 Drilling the hole top bracket at L25,L26,L27 Manager 1 pax
3 Install bracket L20, L21 Site Manager 1 pax
4 Drilling bottom hole at L18,L19,L20 Team Leader 1 pax
5 Inspection the depth of hole L23-L26 Technician 8 pax
6 Drilling the hole top bracket at L25,L26,L27 Total worker 12 pax
7 Drilling the hole top bracket at L25,L26,L27 Morning No
Rainy
8 Afternoon No
Material Delivery
Name Quantity Unit Photo Remark

1
2
3
4

Prepared & Checked by: